Documente Academic
Documente Profesional
Documente Cultură
in EPC Contracts
Mr Christopher Chuah
Partner
Infrastructure, Projects & Construction
Engineering, Procurements & Construction
contracts
The EPC Contract – General Overview
– In its most extreme form, may be referred to as a Turnkey contract
• Places all design and construction responsibility on the contractor
• Reduced involvement and intervention by the Employer
• No need to identify party to attribute liability for defect as responsibility for
scope of works very broad and will fall on the contractor
• Attractive to Employers as it preserves contractor liability
• May be additional benefit of efficiency in the design and construction process
to achieve faster completion time and reduction in the price of the project
– Contractor would require broad range of experience across different
industries
• For e.g., where the scope of works encompasses civil and structural works,
specialized M&E works etc.
2
Engineering, Procurements & Construction
contracts
The EPC Contract – Importance of Tender Process
– The Request for Tender takes on greater importance than in
traditional construction contract
• Minimal/ no opportunity for the Employer or its Consultant to amplify or
develop the design after call for and submission of tender
• Employer to state in precision and detail its requirements in terms of
capacities and performance required of the works
• Employer to invest greater resources at tender review to ensure that
the Contractor’s proposed design meets the Employer’s requirements
and are of the requisite quality
• Contractor also to invest greater resources in tender preparation as it is
responsible for buildability of the Project
• May be necessary to carry out pre-qualification due diligence to
ascertain that the contractors are competent and capable of
performance the contract
3
Engineering, Procurements & Construction
contracts
The EPC Contract – Pre-tender considerations
– Determination of extent of role of the Employer/Consultant
(A) Minimal involvement: Employer only to turn the key after completion to
commence operation of the constructed facility.
(B) Moderate involvement: Employer/ Consultant to supervise Contractor’s
works and issue instructions or request for proposals
(C) Most involved/ Semi-Turnkey: Combination of turnkey contract in respect
of one area of works, with a traditional building contract in respect of
another area of works in the same project.
Disadvantage is risk of potential cost/ time claims where a contractor alleged poor
co-ordination between packages
4
Engineering, Procurements & Construction contracts
Cost Management
Pre-tender considerations
– Employer to rationalize price of the contract
• Determine design source: Employer’s inhouse staff/ independent
Consultant/ the Contractor
– Oversight function
• Allocation of co-ordination responsibility as between:
– individual elements of the design
– management of incoming and on-site material
– inspection and testing crews belong to the Employer/ Contractor/
local regulatory authorities
• Determine party undertaking co-ordination responsibility
– Employer’s inhouse staff/ independent Consultant/ Contractor/
Management Contractor
– Determine Project duration and define milestones
5
Engineering, Procurements & Construction contracts
Cost Management
The EPC Contract – Key considerations
– Risk transfer: greater amount of risk placed on the Contractor, to
the benefit of the Employer
• However, the Contractor is likely to price for the risk especially in a
low-competition environment.
• The benefit of risk transfer is likely to manifest in extra cost to the
Employer
• Ultimately, the balance of risk assumption by either party is determined
by the balance of power between the contracting parties.
– In an employer/ developer’s market, the Contractor may have to assume
greater risk without being commensurately compensated by an increase in
contract price.
– During a construction boom such as in Singapore at present, employers can
expect more resistance from Contractors in assuming additional risk.
Alternatively, the Contractors will price for such additional risks during
tender.
6
Engineering, Procurements & Construction contracts
Cost Management
The EPC Contract – Lump Sum Pricing
– Lump Sum pricing is generally used due to difficulties in verification
by the Employer or its consultants of valuation of interim payment
claims submitted by the contractor.
Benefits of lump sum pricing:
• Provides greater certainty in overall cost
• Provides greater certainty in timing of payments
• Minimize front loading by the Contractor
• Encourages rapid or early completion
• Facilitates financing (Lenders will have greater certainty of financial
exposure and timing of draw downs)
However, lump sum pricing does not preclude the contractor, under
certain circumstances, from claiming an increase in the contract price.
7
Engineering, Procurements & Construction contracts
Cost Management
8
Engineering, Procurements & Construction contracts
Cost Management
9
Engineering, Procurements & Construction contracts
Cost Management
10
Engineering, Procurements & Construction contracts
Cost Management
11
Engineering, Procurements & Construction contracts
Cost Management
Provisional Sums
– There may be expenditures whose cost cannot be determined
at the time of tender and contracting, such as subcontracted
works or purchase/supply agreements that are only entered
into after the signing of the EPC contract.
– Where the actual cost exceeds the sum allowed as a
‘provisional sum’, the contract price is increased.
– Such provision may be useful insofar as it gives the Employer
some influence over the Project
– However, it is not entirely in place in an EPC contract as it
carves out areas from the absolute responsibility of the
Contract.
12
Engineering, Procurements & Construction contracts
Cost Management
Key contractual terms that impact cost
– Risk
• “the Contractor shall take full responsibility for the care of the Works and
materials and Plant from the Commencement Date until the [date of TOP].”
• In negotiating the lump sum price, the Contractor will incorporate a premium to
reflect the assumed risks – the quantum of such premium will be influenced by
market forces.
– Variations
• EPC contracts generally attempt to limit any opportunity by the contract to claim
for additional cost. However, the acceptance of variations may achieve a lower
contract price and impart flexibility to the contract in dealing with risks and
contingencies
16
Engineering, Procurements & Construction contracts
Cost Management
17
Engineering, Procurements & Construction contracts
Cost Management
18
Engineering, Procurements & Construction contracts
Cost Management
– Material fluctuation
• “The contract price shall not take into account any unforeseen
difficulties or costs, except as otherwise stated in the contract.”
20
Engineering, Procurements & Construction contracts
Cost Management
Key contractual terms that impact cost ‘ctd
Value Engineering
– FIDIC Silver Book: Cl 13.2(1)
The Contractor may submit to the Employer a written proposal at
any time, which will, if adopted:
• Accelerate completion
• Reduce maintenance and operating costs to the Employer
• Improve the efficiency or value of the completed works
– Orgalime Turn Key: Cl 8.2
The Contractor may inform the Purchaser of possible variations
which the Contractor considers to be in the interest of the
Purchaser
– Under both standard conditions, the Contractor holds control of
value engineering since it is restricted to his opinion on the matter.21
Engineering, Procurements & Construction contracts
Variation Management
Variation/ Change Orders generally
“The Contractor may request and the Owner may order changes in the Work
within the scope of the Contract Documents …. “
22
Engineering, Procurements & Construction contracts
Variation Management
Minor Changes not constituting Variation
“The Contractor may make minor changes in the design and construction of
the Project consistent with the intent of the Contract Documents which do not
involve an adjustment in the Contract Price …and do not materially and
adversely affect the design of the Project… “
23
Engineering, Procurements & Construction contracts
Variation Management
Limit / Prohibit drastic Variations
24
Engineering, Procurements & Construction contracts
Variation Management
Costs due to preparation of variations
– FIDIC Silver Book: Cl 13.2(2)
• The party initiating the proposal for variation prepares it at his own cost,
i.e.
– Contractor bears cost of Contractor-initiated proposal.
– The Employer prepares any variation instruction at his own cost
– the Contractor is not entitled to any payment for responding to a request
– Orgalime Turn Key: Cl 8.6
• Where a variation is requested by the Purchaser, the Purchaser shall
reimburse the Contractor any costs incurred in examining the
consequences of the variation
• Silent on which party is to bear the cost of preparation of variations in the
event of Contractor-initiated proposals
– Recommendation:
• The costs in this respect should be expressly agreed upon and stated in
the EPC contract, especially when detailed and expensive design is
involved.
25
Engineering, Procurements & Construction contracts
Variation Management
Determination of costs arising from variations
The various standard form contracts set out the method(s) for the
determination of costs of variations. The provisions describing the
methods of valuation range from the broadly-worded to very
specific, regimented approaches.
26
Engineering, Procurements & Construction contracts
Variation Management
Determination of costs arising from variations ‘ctd
27
Engineering, Procurements & Construction contracts
Variation Management
Determination of costs arising from variations ‘ctd
3) FIDIC Silver Book: Cl 13.3(4), 3.5
• If no agreement reached following the Contractor’s proposal, the
Employer shall proceed to determine adjustments to the Contract
Price and the Schedule of Payments
– Adjustments shall include reasonable profit, and take into
account the Contractor’s submissions regarding value
engineering
• Silent on compensation on delay arising from variation
4) Engineering Advancement Association of Japan Model
Form: Cl 39.5, 39.8
• Cl 39.5: Adjustment of Contract Price shall as far as practicable be
calculated in accordance with the unit rates. If the unit rates are
unavailable or inequitable, the parties to agree specific rates for the
valuation of the Change
• Cl 39.8: If parties cannot agree within 60 days of the variation
instruction, either party may refer the dispute to an expert
28
Engineering, Procurements & Construction contracts
Variation Management
Determination of costs arising from variations ‘ctd
In order for the latter provision to work, crucial that the Contract provides
that the Contractor shall maintain a documented, itemized accounting
evidence the expenses and savings.
29
Engineering, Procurements & Construction contracts
Variation Management
Determination of costs arising from variations ‘ctd
In order for the latter provision to work, crucial that the Contract provides
that the Contractor shall maintain a documented, itemized accounting
evidence the expenses and savings.
30
Engineering, Procurements & Construction contracts
Variation Management
Determination of costs arising from variations ‘ctd
– Recommendation:
• If any variation order/ work change directive issued by the
Employer cannot be agreed upon, and the Contract does not
provide a specific guideline, there is a risk of the Contractor
proceeding with the instruction to carry out the works and
commence claim in quantum meruit thereafter.
• The Employer should be cautioned against imposing expensive
variations on the contractor without affording sufficient
compensation even if the EPC contract allows the same. The
Employer’s interest in the long-term performance and efficiency
in operating/ maintenance costs of the facility may be
adversely impacted by poor design decisions.
31
Thank You
32