Documente Academic
Documente Profesional
Documente Cultură
1
BDM, 2007/s2
Commence after
Activity Duration completion of
A1 Excavation 2
A2 Foundations 4 A1
A3 Rough Wall 10 A2
A4 Exterior plumbing 4 A3
A5 Rough electricals 7 A3
A6 Roof 6 A3
A7 Interior plumbing 5 A4
A8 Gyprock 8 A5, A7
A9 Flooring 4 A8
A10 Interior painting 5 A8
A11 Interior fixtures 6 A9, A10
A12 Exterior siding 7 A6
A13 Exterior painting 9 A4, A12
A14 Exterior fixtures 2 A13
2
BDM, 2007/s2
Goals:
3
BDM, 2007/s2
Project Network
Start
A1
A2
A3
A5 A4 A6
A7 A12
A8 A13
A9 A10 A14
A11
Finish
4
BDM, 2007/s2
Networks
1
2
1 4 2 3
3
4
5
BDM, 2007/s2
• Example.
– Nodes: {1, 2, 3, 4, 5}.
– Links:
{(1, 2), (2, 3), (2, 4), (3, 2)(3, 5), (5, 2)}
– Graphical representation:
4
1 2 3 5
6
BDM, 2007/s2
7
BDM, 2007/s2
AON representation
8
BDM, 2007/s2
Project Timetable
9
Gantt Chart
Essentially the AON network representation with node size proportional to activity duration, and nodes placed along time line.
A very useful graphical presentation of project schedule.
BDM, 2007/s2
A5 A8 A11
A1 A7 A9
A2 A4 A10
A3
A6 A13
A12 A14
0 4 8 12 16 20 24 28 32 36 40 44
10
BDM, 2007/s2
Start
A1
A2
A3
A5 A4 A6
A7 A12
A8 A13
A9 A10 A14
A11
Finish
11
BDM, 2007/s2
Typical Uses
12
BDM, 2007/s2
Typical Questions
13
BDM, 2007/s2
14