COMMISSIONING PROCEDURES
EWRNo E024
All Drawings, Bill Of Materials and EWP shall be returned to the originator (Design
Engineer) after commissioning is completed and shall be the marked up ' As Built '
documents. All changes to the original issue shall be marked, Red = Additions, Blue =
Deletions.
The Construction Supervisor shall sign all returned drawings complete.
CONTENTS
1. GENERAL
1. General
This Document intended to guide testing process during simulation of
Black start from Generator CAT Diesel B15-G01. The commissioning
must be performing carefully to prevent unwanted condition of the
control system and accident.
2.3 Paralleling
[ ] Check the loads at G01 are around 1 MW
[ ] Synchronize CAT Diesel no#2 with bus bar and set the load set
point to 300 KW
[ ] Synchronize CAT Diesel no#3 with bus bar and set the load set
point to 300 KW
[ ] Add load by close the TPL#2 – B10S05
Page 3 of 3
PT. INTERNATIONAL NICKEL INDONESIA
Utilities Department
Page 4 of 3