Documente Academic
Documente Profesional
Documente Cultură
cl
I. FOREWORD
For a better understanding of this report it is necessary to set a few
definitions and enunciate the fundamental legal regulations on the subject of
the execution of the obligations of a contract along with the application of those
norms at the judiciary and academic level.
Chilean Civil Code (CCC) is the key regulatory body on this matter, namely
from Articles 1554 to Article 1559 which regulates the consequences of the
failure to perform any term of a contract. The provisions of the legal action to
claim the fulfillment of the obligations of the counterpart are referred on Article
1489 of CCC that regulates the tacit resolution condition1 according to which the
part towards whom the undertaking has not been fulfilled has the choice either
to compel the other to fulfil the agreement when it is possible, or to request its
avoidance with damages.
a. The contracting party did not perform his/her obligations in the manner
(Article 1569) or to the extent agreed (partial performance does not imply
fulfillment of the other party’s obligations. Article 1569 CCC) .
b. Delayed execution.
1
Equivalent to Article 1184 of the French Civil Code.
1
G. Echeñique 446, Las Condes, Santiago, Chile | (+562) 8979756 | www.lexnet.cl | abogados@lexnet.cl
In conclusion, our legal system is diverse from the Common Law and also
from the Continental European Law. In fact, in Comparative Law it is noticeable
a growing evolution towards the protection of the creditor, and consequently to
an establishment of solutions or remedies aimed at the protection of such
interest. This trend inspire the Vienna Convention on Contracts for the
International Sale of Goods, the BGB (German Civil Code) and Directive
99/44/CE of the European Parliament.
2
Raúl Lecaros, Civil Law Professor Universidad Católica de Chile, Former member of Chilean Supreme Court
of Justice.
2
G. Echeñique 446, Las Condes, Santiago, Chile | (+562) 8979756 | www.lexnet.cl | abogados@lexnet.cl
In relation to the first element, jurist Fernando Fueyo asserts that even
though art 45 of the CCC does not mention this element, it is deduced from
other norms of the same Code, such as art 1547. He also mentions that in
various articles of the same code the expression deed or negligence are related
to a personal act and, in opposition, in the case of the force majeure no
personal and direct intervention exist. And at the same time, the action should
not have been caused by the creditor, which in this case there is negligence
from his part and also a liberation of the non-performing debtor, but in no way
this could be deem as force majeure4.
3
Professor Rene Abeliuk M. en su tratado “De las Obligaciones”, pagina 687, supra 839 declares: “Our CCC,
in the line of the classic authors has only established the “termination” of the obligations for force majeure. In
no case this code establishes the “modification” of the obligations for this reason”. He also mentions that “the
definition of force majeure is strict, because in order to exist it needs two correlative elements: irresistibility
and unexpectedness. In other words, it is implied that the obligation performance turns out to be impossible in
absolute terms no matter how serious the previsions of the debtor could possible have foreseen.
4
René Abeliuk M. en su tratado “De las Obligaciones”, pagina 688, supra 841.
3
G. Echeñique 446, Las Condes, Santiago, Chile | (+562) 8979756 | www.lexnet.cl | abogados@lexnet.cl
Professor Fueyo states that Law takes care of normal situations according
to a probabilistic estimation over the specific event. The result of this estimation
is derived from the assessment of the way in which the event occurs, its
circumstances and also a diligence to the agent in order to avoid occurrence of
events by previously assess the likelihood of an event7.
Another aspect of the unpredictability is given by the fact that the behavior
of the debtor is also relevant in terms that he is obliged to collaborate in order
to avoid risks and to take the necessary precautions. Any event beyond this
provisions will be considered force majeure from the obliged party. According to
Fueyo the calculation of odds of the occurrence of the event is ultimately based
on a certain degree of diligence or precaution measures, and it is unpredictable
what occurs beyond these provisions.
Finally, the third element, the irresistibility which is referred to a case when
the consequences are unavoidable in terms that no rational person under the
same circumstances could have behaved in a different manner.
5
Fernando Fueyo, “Tratado Cumplimiento e Incumplimiento de las Obligaciones”, pages 399 and 400
6
Fallo de la Corte Suprema de fecha 09 del septiembre de 1992
7
Fernando Fuello, “Tratado Cumplimiento e Incumplimiento de las Obligaciones”, página 401. This author
quotes an remarkable sentence of april 14th 1941 according to which abundant precipitations are no cause for
application of force majeur in very rainy areas.
4
G. Echeñique 446, Las Condes, Santiago, Chile | (+562) 8979756 | www.lexnet.cl | abogados@lexnet.cl
Chilean jurist René Abeliuk suggests that the above mentioned applies not
only to the obligations of transfer but also to the obligations of do and not do.
1. Outright execution.
2. Successive payments (tracto sucesivo).
3. Permanent effects.
Professor Lecaros maintains that this division has not only theoric purposes
but practical as well. Indeed, it is key at the time of the application of the force
majeure as a fundamental for the liberation of contractual responsibility
because in each case it is applied distinctly.
5
G. Echeñique 446, Las Condes, Santiago, Chile | (+562) 8979756 | www.lexnet.cl | abogados@lexnet.cl
according to professor López Santa María in this case “the obligations are
fulfilled at the time of the signature. The contract is created and extinguished at
the same time and thus the parties are liberated instantly”. This is the case of a
cash contract of sale. The latter type is also called of differed execution being
an example a contract of sale when the price is established in specific regular
intervals.
Lecaros adds that in this kind of contracts the force majeure that affects
the party at the same time liberates the other for logical reasons of
commutative justice: if one party gets nothing, then why the other party should
be bounded to perform anything. The unilateral performance of this party will
be considered without a cause and thus there will be an illegal profit. This
principle is regulated in the Chilean legislation in the CCC norms about the
contract of lease. Article 1590 of the CCC mandates that the contract of lease
ends when the leased object perishes. If the rented thing is not available for the
lessee, why should he/se be bounded to pay the rent to the leaser?
6
G. Echeñique 446, Las Condes, Santiago, Chile | (+562) 8979756 | www.lexnet.cl | abogados@lexnet.cl
“not doing” a given deed the force majeure in the obligation of one party,
extinguishes the obligations of the other contractor.
Chilean Supreme Court have sustained the same doctrine for over a
century: “Lease contract is subjected to the regulation of article 1550 so when a
rented house is destroyed by fire, the contract ends and the leaser are not
entitled to claim the full payments of the rents from the day of the destruction
on. In consequence the petition of the defendant in order a request from this
Court the dismissal of the allegations of the plaintiff should be sustained”.
Nevertheless, it is relevant to mention the fact that in successive payment
contracts with a limited duration when the force majeure does not destroy the
object but only prevents its use for a limited period of time. The contract, and
consequently the obligations to perform for both parties persist beyond the
temporary limitations.
7
G. Echeñique 446, Las Condes, Santiago, Chile | (+562) 8979756 | www.lexnet.cl | abogados@lexnet.cl
impossibility of performance for one party is absolute and permanent until the
end of contract. On the contrary, if the irresistible event ends before the
expiration time, the obligations persist for the remaining periods of the
contract.
8
G. Echeñique 446, Las Condes, Santiago, Chile | (+562) 8979756 | www.lexnet.cl | abogados@lexnet.cl
bilateral agreement is involved, this is, a contract in which both parties are
benefited, they must respond for ordinary fault (levis clupa), and ultimately, no
further obligations exist.
Drought must not be considered force majeure per se considering the fact
that its occurrence it is likely to occur at some intervals in our country. Thus, it
is not possible to purge the obligations of the contractor in case a drought
occurs, specially considering that normal levels of energy production are
feasible in cases of low levels of precipitation periods and that in extreme cases
it is still possible the generation via thermoelectricity. On the contrary, it is
indeed a case of force majeure when an event of drought lingers for periods
beyond which in which the government is forced to decree the rationing of the
supply of water.