Sunteți pe pagina 1din 3

SUBSEA TECHNOLOGY

Ormen Lange Subsea Production System

The Ormen Lange field, in the


Norwegian Sea, approximately 100 km
off Norway, is within the prehistoric
Storegga slide area with water depths
reaching 850 m in the main production
area. The gas will be produced from up
to 24 subsea wells. The well fluid will
be transported to the Nyhamna plant
through two 30‑in. multiphase lines.
After processing, the dry export gas
will be transported from the onshore
plant through a new 42‑in. pipeline
by way of the Sleipner riser platform
and further through a new 44‑in.
pipeline to the gas-receiving terminal
in Easington, England.

Introduction
Fig. 1 shows the development con-
cept selected for Ormen Lange, which Fig. 1—Ormen Lange initial subsea development.
comprises a subsea tieback to an
onshore processing plant at Nyhamna.
Conceptual engineering of the subsea A in December 2006. Completion of through a pipeline-end-termination
production system was initiated in the first subsea well on Template A was (PLET) system.
2002. The main contracts for subsea- scheduled for spring 2007, and subsea Two main control umbilicals link the
equipment supply, umbilical fabrica- production startup was scheduled for onshore plant to the subsea production
tion, and template installation were autumn of 2007. system; one is connected to Template
awarded between the autumn of 2003 A and the other to Template B. A cross-
and the summer of 2004. The main part Subsea-System Configuration over-control umbilical interconnects
of fabrication and testing took place With the large geographical extent of the two production templates, provid-
during 2004–05, with the subsea tem- the Ormen Lange reservoir and the risk ing redundant hydraulic supply to all
plates installed offshore in late summer of reservoir segmentation, the subsea- the subsea wells.
2005. Umbilical A and the remaining system design has a high degree of To prevent hydrate formation, all wells
subsea equipment were installed dur- flexibility, with four planned template are injected continuously with monoeth-
ing the summer of 2006, and the first locations. Therefore, a phased-develop- ylene glycol (MEG) through two 6-in.
subsea tree was installed on Template ment scheme was chosen. The phasing pipelines from the onshore plant. One
and location of the subsea wells will be line is connected to Template A and the
This article, written by Technology Editor timed to maintain plateau production other to Template B. A 6-in. crossover-
Dennis Denney, contains highlights as the field depletes. MEG line interconnects the two produc-
of paper OTC 18965, “Ormen Lange tion templates for added flexibility.
Subsea Production System,” by Thomas Initial Development. The initial sub-
Bernt, Hydro, and Endre Smedsrud, sea development consists of two eight- Future Development. Extension of the
FMC Technologies, prepared for the slot production templates (Templates field may require two additional produc-
2007 Offshore Technology Conference, A and B), approximately 4 km apart in tion templates (Templates C and D).
Houston, 30 April–3 May. the main production area. Each tem- Each template will produce gas through
plate is tied back into the two 30-in. dual infield flowlines tied back to the
Copyright 2007 Offshore Technology multiphase pipelines to shore. As Fig. 2 30-in. multiphase pipelines to shore. A
Conference. Reproduced by permission. shows, these lines are interconnected new infield 6-in. MEG line will be con-

The full-length paper is available for purchase from the OTC Library: www.otcnet.org. The paper has not been peer reviewed.

JPT • AUGUST 2007 59


nected to each of the future templates
as extensions from Templates A and B.
Similarly, a new infield-control umbili-
cal will be connected to each of the new
templates as extensions from Templates
A and B. The design has provisions for
tie-in to a future precompression plat-
form or a subsea compression unit.

Key Technical Challenges


The seabed in the development area is
highly irregular, with soil conditions
varying from very stiff clay with boul-
ders to soft clay. Also, the environmental
conditions are extremely challenging
and the installation season is very short.
Fig. 2—Installation layout of Template B and PLET system.
Currently, there is no fishing activity
in the area where the subsea templates
are installed. In the future, howev- be as high as 107 std m3/d. A major less techniques. The tree is configured
er, trawling activity may commence; challenge for the project has been to with hydraulics to enable a safe opera-
therefore, the large subsea installations ensure that all equipment is designed to tion and testing of tree/running-tool
are equipped with overtrawlable pro- accommodate this very high flow rate. system by use of the workover system.
tection structures. Erosion and vibration are two impor-
tant areas of focus in this respect. MEG Distribution. The MEG-distribu-
Hydrate Prevention. Hydrate preven- tion system is designed to minimize the
tion is a main technical challenge for the Systems risk of hydrate formation. Each well
system. With the low seabed tempera- The design allows simultaneous produc- is equipped with a distribution system
ture (-1°C), both hydrates and ice may tion and drilling/completions/workover ensuring that sufficient MEG is injected
form, unless the well fluid is sufficiently operations. During deployment of heavy into each well. The subsea tree sys-
inhibited. The overall hydrate-preven- equipment in open water from the tem is equipped with two MEG-injec-
tion strategy is to minimize the risk of drilling/completion rig, the rig is posi- tion points. During normal production,
operating within the hydrate region by tioned at a safe horizontal distance from MEG is injected between the production
continuous MEG injection at individual any subsea installation, even though wing valve and the production choke to
subsea trees. For accurate injection con- dropped-object protection is part of the ensure good mixing. During well startup
trol, each well is equipped with an MEG template design. The template system and for barrier testing, MEG is injected
flowmeter and dosage valve. comprises a foundation bottom struc- between the production master valve
ture with skirt foundations and a mani- and the production wing valve.
Long-Offset Control. Control of the fold module. The production manifolds
subsea production system will be from have dual production headers. For each Completion and Workover. The com-
the onshore terminal at Nyhamna, a well, two hydraulically actuated valves pletion and workover system comprises
distance of 120 km. Availability of the direct gas flow to either of the manifold all equipment and associated control
subsea control system on Ormen Lange headers. Umbilicals and pipelines/spools systems required to install, retrieve,
is strongly emphasized because the were tied in by use of horizontal-con- and commission a horizontal tubing-
production rate from each well is very nection systems. hanger system and to perform well
high and interventions will be both interventions and workovers during
costly and challenging with the water Subsea Tree. The subsea-tree system the operational phase over the life of
depth and weather conditions. A fiber- is a 7‑in. horizontal production tree the field. The workover-control system
optic/electrohydraulic multiplexed con­ equipped with an annulus bore. The provides the necessary functionality to
trol system was designed, built, and tree is configured with a separately control all functions on the comple-
tested. Components include high-volt- retrievable subsea-control module tion/workover equipment and subsea
age power transformers, low-pressure (SCM) and a choke module, the latter tree. It includes facilities to perform
hydraulic power, and backup commu- containing instrumentation, flow-con- normal and emergency shutdown and
nication on high-voltage power. trol, and measurement equipment. The disconnection of specified functions in
production flow loop and the MEG, automatic sequences upon activation
High Flow Rates. The initial eight annulus-test, and control lines on the from the surface unit.
development wells will be 95/8-in. subsea tree are connected to the choke
hybrid well completions with dual module through a multibore-horizon- Production Control. The produc-
downhole safety valves (deep-set) and tal hub. A remotely operated vehicle tion-control system uses a redundant
horizontal subsea trees. The remaining (ROV) panel is attached to the sub- fiber-optic bidirectional point-to-point
well completions for Templates A and sea-tree frame structure, and all valves communication link between land and
B are planned as 7-in. completions. The operated by ROV are on this panel. each SCM. The control system has
average flow rate from each well may Subsea-tree installation used guideline- fully redundant hydraulic, electrical,

JPT • AUGUST 2007


and communication systems and is, PLET modules, and the pig loop. The in terms of planning cost estimates,
as much as possible, based on proven PLET system allows for thermal expan- specification of installation vessels, and
subsea-control-system components. sion of the 30‑in. pipeline. It provides other such details.
The subsea-control unit is installed at for tie-in of 16‑in. rigid spools from 2. Active risk management has been
the onshore plant at Nyhamna and is a Template B and 12-in. rigid spools performed throughout the project,
node on the main-control-system net- from Template C (future). whereby key risks have been systemati-
work. The subsea- and onshore-control cally and proactively identified, evalu-
systems are, therefore, fully integrated Achievements ated, and acted upon to minimize nega-
with no requirement for a subsea mas- As of February 2007, the design, fab- tive effects and maximize benefit.
ter-control station. rication, testing, and installation of the 3. The project team has executed
Ormen Lange subsea-production system effective change management, whereby
PLET. The 30-in. PLET system is were nearly completed. Templates A all change proposals have been care-
installed close to Template B. The and B, the in-line tees, the PLET system, fully reviewed and evaluated before
PLET-system design comprises a PLET and spools were successfully installed implementation or rejection.
bottom structure, which was installed subsea and all tie-ins completed. 4. The project team has performed
before pipeline lay down. The pro- close and active monitoring of interface
tection structure protects equipment Key Success Factors work between contractors.
from dropped objects and fishing 1. The level of detail and the qual- 5. Qualification and verification tests of
activities. The PLET bottom structure ity of the conceptual engineering per- all new components and thorough test-
was designed to function as a landing formed before contract award provided ing onshore have contributed to smooth
base for the pipeline terminations, the a very good basis for project execution and effective offshore operations. JPT

JPT • AUGUST 2007 61

S-ar putea să vă placă și