Sunteți pe pagina 1din 4

The Journal of the Society of Façade Engineering

December 2006

Safe Access
Case study: Swiss Re
CDM regulation update
Welcome to the second issue of Elevation. The construction industry has put the some notable accidents in the file for 2006 (the Battersea
crane collapse and the Witan Gate scaffold collapse). Gravity and facades have an interesting symbiotic relationship. The façade is so
fundamental in making a building safe, so it holds so much risk if things go wrong. Falls from height is number two on the HSE’s ‘High
Five’ risk list. Recent changes in fire legislation and the news that the UK CDM regulations have finally been approved by the Health and
Safety Commission have implications on designers of facades and our approach to safety. As façade designers and constructors, we have
had duties to prioritise the safety of individuals involved in the manufacturing, installation, cleaning, replacement and dismantling of the
façade… in other words, with each design should come a cradle to grave plan of safety.
Safe access and the designer’s duties
In this issue we focus on façade access, and the need to evolve clear maintenance access strategies for facades. The best solutions result in
effective integration of the access equipment into the building form… get it wrong, or plan it too late and the result can be unsightly, ineffi-
cient or even unsafe equipment that can blight an elegant and otherwise well designed façade.

Assessing
Access
early
consideration of a
maintenance
access strategy
As building designs become more complex
the need for effective internal and external
façade maintenance becomes more crucial
– writes Andy Jordan of Reef Associ-
ates.

Current legislation requires that all design-


ers consider the long-term maintenance of
the project during the early design stages.
A properly thought out and considered
maintenance strategy at an early stage will to consider in the provision of any mainte- quently considered much too late in a de-
provide the most economic and practical nance access strategy. sign, which can result in unsightly, obtru-
means of achieving this goal. sive, and in the long-term costly solutions
The safety of both operatives and those being employed.
Construction Design and Management affected by the maintenance operations
Regulations (CDM), The Working at must be considered in developing any Maintenance strategies for a project should
Height Regulations and the Lifting Opera- scheme, and significant emphasis is cur- be developed to include, but not be limited
tions and Lifting Equipment Regulations rently being placed by the HSE to reduce to:
(LOLER) are but a few of the regulations risks as low as reasonably practical.
• Identify the unique requirements of the
Firstly, risk and hierarchy of risk for each project
system must be assessed. Hazard assess- • Identify the layout, load paths and ma-
ment goes beyond routine cleaning to en- terials of the structure
compass the longer term requirements of • Identify all surfaces requiring access
façade maintenance and replacement of for cleaning or maintenance, including
elements of the façade. the requirements for replacement of
elements of the façade, such as security
As always there are a number of solutions cameras etc.
to achieving this goal, however an ill- • Identify the cleaning and maintenance
conceived solution can prove to be diffi- methodology and frequency of opera-
cult to use and increase the long-term tions for each of these surfaces, includ-
maintenance costs to any project. ing requirements for upkeep of warran-
ties
Considering the access requirements early • Identify the risks involved in perform-
in the design stage gives the opportunity to ing these operations. The eventual
incorporate systems that can be developed strategy should outline the equipment
to be in-keeping with and sympathetic to and methods employed in achieving
the architecture of a project. this required access
Access requirements of a project are fre-
Case Study:
The selection of any means of access solu-
tion is dependant on a large number of
factors: capital cost of equipment and costs
of incorporating systems into the design of
St Mary Axe
the structure and building fabric must also
be considered.

Not all projects will involve a permanent


means of access to maintain the façade.
The use of Mobile Elevated Working Plat-
forms (MEWPs) for example can have far
reaching and wider implications on selec-
tion of features on a façade and landscap-
ing, ground works around a project.

Andy Jordan is a project director with


REEF Associates Limited, façade access
consultants, who can be contacted on +44
(0)20 7407 1222
www.reefassociates.com

Useful Web Sites


A summary of HSE publications: The façade access consultants and the ar- the façade access consultants also devel-
(for the glass industry) chitects carried out careful and detailed oped the methodology for re-glazing of the
www.hse.gov.uk/pubns/glasindx.htm consideration of the access requirements building.
(falls from height) and the risks involved in this project at an
www.hse.gov.uk/pubns/fallindx.htm early stage in the design. A fourth piece of equipment (running on
(risk assessment) the same track system) is a dedicated res-
www.hse.gov.uk/pubns/raindex.htm Spatial and structural requirements to ac- cue unit. It can be driven out around the
(slips trips and falls) commodate the three machines employed track system under its own power to the
www.hse.gov.uk/pubns/slipindx.htm in accessing this building were considered other equipment providing access to assist
(Workplace health and safety—including at an early stage. in any rescue of operatives.
Regulation 14 implications for glazing)
www.hse.gov.uk/pubns/indg212.htm The cladding design was co-ordinated with
the requirements of the access equipment
Further Reading to incorporate storage in a garage area and
BS 1808 Safety Requirements on Sus- restraint points for use by the suspended
pended Access Equipment – Design Calcu- platform as it descends from the high level.
lations, Stability Criteria, Construction - The façade below the 36th level is accessed
Tests (1999) using two bespoke Building Maintenance
BS 6037 Code of Practice for the Plan- Units (BMU) each with a dedicated sus-
ning, Design, Installation and Use of Per- pended platform. The position of the plat-
manently Installed Access Equipment form on the façade is monitored and the
(2003) BMU automatically adjusts the outreach of
TN 42 Safety and fragility of glazed roof- the suspension jib to suit the curved shape
ing - CWCT of the façade.
TN 54 Self-Cleaning Glass - CWCT
TU 10 Use of glass overhead - CWCT The crown of the building is accessed us- When not in use, all of the external façade
Guide Design of Facades for Safety - ing a bespoke MEWP supported and run- access equipment is stored out of sight
CWCT ning on the same structural tracks around within the building garage area.
Design of facades for safe access for con- the building as the BMU’s.
struction, maintenance and repair, by In addition to providing access for general The internal surfaces of the high-level
Keiller, Ledbetter, Walker and Wolmuth. cleaning of the façade these systems are crown area is served by a purpose devel-
CIRIA also rated to carry the additional loads of oped MEWP. This was co-ordinated and
Lifting Operations and Lifting Equipment glazing and cladding panels during re- installed to be stored within a covered pit
Regulations (LOLER) 1998 placement. As part of the overall strategy in the floor slab, when not in use.
The Work at Height Regulations 2003

A Planning Supervisor by Any regulations combine Construction (Design emphasize the health, safety and broader
Other Name and Management) Regulations 1994 and business benefits of a well-managed and
the Construction (Health, Safety and Wel- coordinated approach to the management
The draft revised CDM regulations have fare) Regulations 1996 in a bid to unify the of health and safety in construction”
finally been approved by the Health and construction health and safety regime. A
line from the HSE website states: The Designer’s duty remains to eliminate
Safety Commission, making way for an
hazards and reduce remaining ones, so far
Approved Code of Practice (ACoP) that is
“The new CDM regulations offer an op- as is reasonably practicable. Newly re-
expected to be issued in the new year
portunity for a step change in health and quired is to ensure that any workplace they
ahead of introduction on 6 April.
safety performance and will be used to re- design complies with relevant sections of
Presented as a single package, the new
[continued]
Your Take
the Workplace (Health Safety and Wel- The laboratory has come a long way in 40
fare) Regulations 1992. years since the first windows were tested
in a humble garden shed. With some of
The principal contractor’s duties remain the finest facilities in Europe, the centre In the last edition of Elevation we posed
broadly similar; including requirements to now employs 105 staff in various branches the question of whether de-ionised water
allow for and notify about time for plan- of research and testing. adversely affects facades. Here we report
ning and preparation, providing training, on feedback.
monitoring compliance etc. Speakers addressed issues of European and
UK markets, sound and thermal insulation, Tucker Pole UK produce the systems that
All duty holders are required to check ventilation control, sealing, composite con- de-ionise water for cleaning facades. Their
competence before appointing other duty struction, tolerance, CE marking, legisla- fact sheet on the matter states that water is
holders. They must also seek and provide tion, quality assurance, electronics, future 99% pure after passing over polymer resin
co-operation with others. technologies, resource conservation and that adsorbs (rather than absorbing) impu-
sustainability. rities onto its surface. The resultant water
The Planning Supervisor will be replaced is slightly acidic… in fact acidity may ac-
by the CDM Coordinator, who is the em- Progress on developing technologies, such tually be lower than that of acid rain from
powered duty holder, to provide the client as semi transparent photo voltaic glazing industrial polluted areas. It is acidic be-
with suitable and sufficient advice, to help made using organic pigmenting dyes to cause carbon dioxide has been reduced
the client meet his duty to co-ordinate the collect energy was also summarised. along with the alkalinity it carries. The
planning and design, and to prepare the acidity helps in removing inorganic and
health and safety file. SFE Visits Test Lab organic dirt and reducing surface tension.
The Society of Façades Engineering visit Under long-term exposure it may remove
The key difference between the co- to Wintech’s Telford test centre in Septem- corrosion products from metals typically
ordinator and the planning supervisor is ber gave members an opportunity to meet used in the windows. Tucker also point
that the coordinator is also required to ad- others within the society and listen to talks out that heating DI water is inadvisable as
vise and assist the client in the discharge of about the work of the laboratory and asso- it may have adverse effects on susceptible
his duties, in particular to advise on the ciated topics. They then toured the depart- metals. But they emphasise that good
adequacy of other duty holders’ arrange- ments, learning about box window and full quality aluminium will suffer no reaction
ments for controlling risk arising from the size rig tests, building air leakage and vari- from the extremely transient contact in-
project. If the co-ordinator has concerns ous impact and loading tests. volved in cleaning.
about the arrangements for health and
safety made by any member of the project NCE Conference—Delivering Iconic Dow Corning importer, Geocel, advised us
team, they should advise the client of these Energy Efficient Exteriors that they are not aware of any issues from
concerns, and the client (as the person for Delegates gathered for a one day confer- deionised water having an adverse effect
whom the project is being carried out) will ence at the Oval in London to hear lectures on cured silicone or MS polymer sealants
have the power to make sure that these on topical subjects such as thermal effi- in the context of window cleaning.
concerns are addressed. ciency, procurement, refurbishment and
blast protection. Contacts
Changes in the client role are described as Tucker Pole Systems UK +44 12256
'enhanced' rather than new, reflecting the 844046

Coming soon
fact that the new rules make existing re- Dow Corning UK +44 1676 528 000
quirements more explicit. There will be a
primary duty to ensure that arrangements
made by other duty holders are in place
and sufficient, and clients must instruct
The Society of Façade Engineering will
shortly be announcing classes of member- Diary
any contractors they appoint how much ship to be adopted and minimum require-
time they have allowed for the planning ments for meeting each class. Existing 21 February 2007 SFE evening event:
and preparation of construction work. members will receive notifications and Facades in a Material World
further information in due course. Venue to be advised

28 - 30 March 2007 ICBEST


Events (International Conference for Building
Envelope Systems and Technology) at
University of Bath. www.icbest.org
IFT Rosenheim celebrates 40 years SFE annual general meeting will be con-
of research into facades. vened on 28 March 4.30pm. All members
This year’s annual gathering of are invited to attend and find out more
members of the European testing about future plans and offer feedback.
and research centre attracted a
record attendance of 880 dele- 19 June 2007 6.00pm SFE evening event:
gates. The City Towers. Lecture followed by
walking tour of new city facades.

For membership and other information


about the Society of Façade Engineering
visit www.cibse.org

Please help us by submitting comments,


Herr Sieberath, Director of IFT articles, letters and information for publica-
Rosenheim addresses the 40th tion to the editor, Mark Taylor, email:
anniversary assembly SFE@cibse.org

S-ar putea să vă placă și