Documente Academic
Documente Profesional
Documente Cultură
Submitted By
ANIRUDDHA MEDHI
College of Engineering
University of Petroleum & Energy Studies
Dehradun
April, 2011.
1
CROSS COUNTRY GAS TRANSPORTATION LINES
Master of Technology
(Pipeline Engineering)
By
ANIRUDDHA MEDHI
Mr. ADARSH.K.ARYA
Assistant Professor
UPES (Dehradun)
Approved by
…………………………………
Dehradun
April, 2011
2
CERTIFICATE
This is to certify that the work contained in this thesis titled “Cross Country
Gas Transportation Lines” has been carried out by Aniruddha Medhi under
my supervision and has not been submitted elsewhere for a degree.
…………………
…
Mr. ADARSH.K.ARYA
Assistant Professor
UPES (Dehradun)
Date:-
3
ACKNOWLEDGEMENT
This is to acknowledge with thanks the help, gratitude and support that I have
received during the final report from the management of University of
Petroleum and Energy Studies.
I am very much thankful to Mr. B.C. Bora (Ex Chairman,ONGC) for his
extended help to me for this project.
ANIRUDDHA MEDHI
4
ABSTRACT
Cross-country pipeline transport for Natural Gas seems to be the most preferred convenient
economical & reliable method. The intrinsic properties of natural gas and its increasing
industrial /commercial importance have resulted in greater movement of natural gas through
the pipelines.
For the M.Tech final semester project titled “Cross-Country Gas Transportation Lines”, I
have joined as a Project Trainee in PUNJ LLOYD. I was in the Head Office in Gurgaon for
15 days for studying and understanding the scope and various activities regarding the project.
I have started my training from 20th of January 2011 in HO, Gurgaon and then shifted to one
of their Gas Pipeline Project site (Dahej-Vijaypur Pipeline-II) in Vadodara for further
training and getting the actual idea of Gas Pipeline Construction.
This project is on the construction activites involved with a 48-inch cross-country gas
pipeline (610 km) based on the estimated demand of 78 MMSCMD. The pipeline starts at
Dahej (Gujarat) to Vijaypur (Madhya Pradesh).
It also includes the study of the basics terms and equations used in the design of a Cross
Country Gas Pipeline.
5
CONTENTS
Topics Page no
2.2 Viscosity 02
6
Chapter 4 Project Details of a Cross Country Gas Pipeline 13-15
5.2.1.3 Trenching 21
5.2.1.4 Bending 23
5.2.1.5 Welding 24
5.2.1.6 Radiography 29
5.2.1.7 Joint-Coating 29
7
5.2.1.9 Lowering 33
5.2.1.10 Backfilling 35
5.2.2.1 Tie-Ins 35
5.2.2.2 Crossings 36
5.2.2.7 Documentation 41
Chapter 6 Observations 43
BIBLIOGRAPHY 45
8
LIST OF FIGURES
9
FIGURE 5.13 Lowering 34
LIST OF TABLES
10
CHAPTER 1
INTRODUCTION
Cross-Country Pipeline has been in use for transportation of water, petroleum liquids and
gases for the last 70-80 years in the developed countries. In India, cross-country pipelines
have been installed and operated for the past 25-30 years, especially water supply pipelines.
A cross-country pipeline (CCP) can be underground, submarine or aboveground.
The conventional mode of transportation of fluids before the advent of cross-country pipeline
was by sea, rail or road transport. These modes are still in use. However, wherever bulk
transportation on a continuous basis between two fixed locations is required, a cross-country
pipeline is the most economical mode.
The reason is that the transportation by cross-country pipeline is continuous and so it reduces
the quantity to be transported, to a manageable level. The cross-country pipeline
transportation reduces the risks since the quantity is small and are generally provided with
safety devices.
Cross-country pipeline transport for Natural Gas seems to be the most preferred convenient
economical & reliable method. The intrinsic properties of natural gas and its increasing
industrial /commercial importance have resulted in greater movement of natural gas through
the pipelines. These pipelines are often referred as highways of natural gas transmission.
Natural Gas is transported at high pressure in the pipeline at pressures anywhere between 30
~ 100 bar. This reduces the volume of natural gas being transported, as well as providing
propellant force to move the Natural Gas, through the pipeline.
A 48-inch cross-country gas pipeline (610 km) is being proposed based on the estimated
demand of 78 MMSCMD. The pipeline starts at Dahej (Gujarat) to Vijaypur (Madhya
Pradesh). Natural gas have customers on both ends of pipeline, the producers and processors
that input gas into the pipeline and the consumers and local distribution companies that take
gas out of the pipeline. Hence Supervisory Control & Data Acquisition (SCADA) system for
electronic monitoring of pipeline is done for the entire stretch of pipeline from the control
station.
11
CHAPTER 2
There are some very important terms associated with gas pipelines which we should be aware
of. These terms are very essential for designing a gas pipeline.
Specific gravity of gas, sometimes called gravity, is a measure of how heavy the gas is
compared to air at a particular temperature. It might also be called Relative Density, called as
the ratio of the gas to the density of the air. Because specific gravity is a ratio, it is a
dimensionless quantity.
𝑀𝑔
G =𝑀𝑎𝑖𝑟
Since natural gas consists of several gases (methane, ethane, etc.), the molecular weight Mg
referred to as the apparent molecular weight of the gas mixture. When the molecular weight
and the percentage or mole fractions of individual components of natural gas mixture are
know, we can calculate the molecular weight of the gas mixture by using a weighted average
method. Thus, a natural gas mixture consisting of 90% methane, 8% ethane, and 2% propane
will have a specific gravity of
Where M1, M2, and M3 are the molecular weights of methane, ethane, and propane,
respectively, and 29 represents the molecular weight of air.
2.2 Viscosity:-
The Viscosity of a fluid represents its resistance to flow. The higher the viscosity, the more
difficult it is to flow. Lower viscosity fluids flow easily in pipes and causes less pressure
drop. Even though gas viscosity is a smaller as compared to liquids, it has an important
function in determining the type of flow in pipelines.
12
2.3 Compressibility Factor:-
The compressibility factor is a measure of how close a real gas is to an ideal gas. The
compressibility factor is defined as the ratio of the gas volume at a given temperature and
pressure to the volume the gas would occupy if it were an ideal gas at the same temperature
and pressure. The compressibility factor is a dimensionless number close to 1.00 and is a
function of the gas gravity, gas temperature, gas pressure, and the critical properties of gas.
In a gas pipeline, the pressure varies along the length of the pipeline. The compressibility
factor Z also varies and must therefore be for an average pressure at any location on the
pipeline. If two points along the pipeline are at pressures P1, and P2, the following formula is
used for a more accurate value of the average pressure:
2
Pavg = [(P13-P23)/(P12-P22)]
3
Design factor can be determined by using class location table provided in ASME 31.8
2.4.1 Location Class 1: A location class 1 is any one mile section that has 10 or fewer
building intended for human occupancy. A location class 1 is intended to reflect areas such as
wastelands, deserts and mountains, grazing land, farmland, and sparsely populated areas.
2.4.2 Location Class 2: A location Class 2 is any one mile section that has more than 10 and
less than 46 buildings intended for human occupancy. A location class 2 is intended to reflect
areas where the degree of population is intermediate between Location class 1 and location
class 3 such as fringe areas around cities and towns, industrial areas, ranch or industrial
estates etc.
13
2.4.3 Location Class 3: A location class 3 is any one mile section that has 46 or more
building intended for human occupancy expect when a location class 4 prevails.
A location class 3 is intended for areas such as suburban housing development,
shopping centers, residential areas, industrial areas and other populated areas and
other populated areas not meeting location class 4 requirements.
2.4.4 Location Class 4: A location class 4 includes areas where multi-storey buildings
are prevalent and where traffic is heavy or dense and where there may be
numerous other utilities.
14
CHAPTER 3
FLOW EQUATIONS
Several equation are available that relate the gas flow rate with gas flow rate with gas
properties, pipe diameter and length, and upstream and downstream pressure. These
equations are listed as follows:
The most common form of this equation in U.S. Customary (USCS) of units is given in terms
of the pipe diameter, gas properties, pressure, temperatures, and flow rate as follows.
Where
15
D = Pipe inside diameter, inch,
The equivalent length Le and the term es take into account the elevation difference between
the upstream and downstream ends of the pipe segment. The parameter s depends upon the
gas gravity, gas compressibility factor, the flowing temperature, and the elevation difference.
Upon examining the General flow equation, we see that for a pipe segment of length L and
diameter D, the gas flow rate Q (at standard conditions) depends on several factors. Q
depends on gas properties represented by gravity G and the compressibility factor Z. If Gas
gravity is increased (heavier gas), then the flow rate will decrease. Similarly, as the
compressibility factor Z increases, the flow rate will decrease. Also, as the gas flowing
temperature Tf increases throughput will decrease. Thus, the hotter the gas, the lower the flow
rate will be. Therefore, to increase the flow rate, it helps to keeps the gas temperature low.
The impact of pipe length and inside diameter is also clear.
The velocity of gas flow in a pipeline represents the speed at which the gas molecules move
from one point to another. Unlike a liquid pipeline, due to compressibility, the gas velocity
depends upon the pressure and hence will vary along the pipeline even if the pipe diameter is
constant. The highest velocity will be at the downstream end, where the pressure is the least.
Correspondingly, the least velocity will be at the upstream end, where the pressure is higher.
u = 0.002122(Qb/D2)(Pb/Tb)(ZT/P)
16
Where
An important parameter in flow of fluids in a pipe is the non dimensional term Reynolds
number. The Reynolds number is used to characterize the type of flow in a pipe, such as
laminar, turbulent, or critical flow. It is also used to calculate the friction factor in pipe flow.
The Reynolds number is a function of the gas flow rate, pipe inside diameter, and the gas
density and viscosity and is calculated from the following equation:
Where
Laminar flow occurs in a pipeline when the Reynolds number is below a value of
approximately 2000. Turbulent flow occurs when the Reynolds number is greater than 4000.
For Reynolds numbers between 2000 and 4000, the flow is undefined and is referred to as
critical flow.
17
Most natural gas pipelines operate in the turbulent flow region. Therefore, the Reynolds
number is greater than 4000. Turbulent flow is further divided into three known as smooth
pipe flow, fully rough pipe flow, and transition flow.
In order to calculate the pressure drop in a pipeline at a given flow rate, the term friction
factor is used which is a dimensionless parameter that depends upon the Reynolds number of
flow.
1 𝑒 2.51
= - 2 log1o(3.7𝐷 + 𝑅𝑒 √𝑓 ) for Re >4000
√𝑓
Where
The transmission factor F is considered the opposite of the friction factor f, whereas the
friction factor indicates how difficult it is to move a certain quantity of gas through a
pipeline, the transmission factor is a direct measure of how much gas can be transported
through the pipeline. As the friction factor increases, the transmission factor decreases and
therefore the gas flow rate also decreases. Conversely the higher the transmission factor the
lower friction factor and therefore the higher the flow rate will be. The transmission factor F
is related to the friction f as follows:
2
F=
𝑓
In the flow of incompressible fluids such as water the pressure required to transport a
specified volume of fluid from point A to point B will consist of the following components:
1. Frictional component
2. Elevation component
3. Pipe delivery pressure
18
In addition in some cases where the pipeline elevation differences are drastic, we must also
take into account the minimum pressure in a pipeline such that vaporization of liquid does not
occur. The latter results in two phase flow in the pipeline which causes higher pressure drop
and therefore more pumping power requirement in addition to possible damage to pumping
equipment.
The hydraulic pressure gradient is a graphical representation of the gas pressure along the
pipeline. The horizontal axis shows the direction along the pipeline starting at the upstream
end. The vertical axis depicts the pipeline pressures.
Since pressure in a gas pipeline is nonlinear compared to liquid pipelines, the hydraulic
gradient for a gas pipeline appears to be a slightly curved line instead of a straight line. The
slope of the hydraulic pressure at any point represents the pressure loss due to friction per
unit length of pipe; this slope is more pronounced as we move toward the downstream end of
the pipeline, since the pressure drop is larger toward the end of the pipeline. If the flow rate
through the pipeline is a constant value and pipe size is uniform throughout, the hydraulic
gradient appears to be a slightly curved line. If there are intermediate deliveries or injections
along the pipeline, the hydraulic gradient will be a series of broken lines. A similar broken
hydraulic gradient can also be seen in the case of a pipeline with variable pipe diameters and
wall thickness, even if the flow rate is constant. Unlike liquid pipelines, the breaks in
hydraulic pressure gradient are not as conspicuous in gas pipelines.
Figure 3.2
19
Figure 3.3
Where
20
3.9 Weymouth equation:-
The Weymouth equation is used for high pressure, high flow rate and large diameter gas
gathering systems. This formula directly calculates the flow rate through pipeline for given
values of gas gravity, compressibility, inlet and outlet pressures, pipe diameter and length. In
USCS units, the Weymouth equation is stated as follows:
Where
The Panhandle A Equation was developed for use in natural gas pipelines, incorporating an
efficiency factor for Reynolds numbers in the range of 5 to 11 million. In this equation, the
pipe roughness is not used. The general form of the Panhandle A equation is expressed in
USCS units as follows:
Where
21
By comparing the Panhandle A equation with the General Flow equation, we can calculate an
equivalent transmission factor in USCS units as follows:
The Panhandle B equation, also known as the revised Panhandle equation, is used large
diameter, high pressure transmission lines. In fully turbulent flow, it is found to be accurate for
values of Reynolds number in the range of 4 to 40 million. This equation in USCS units is as
follows:
Where
The equivalent transmission factor for the Panhandle B equation in USCS is given by:
22
CHAPTER 4
Capacity: 78 MMSCMD.
Dahej-Vijaypur Gas Pipeline Up-gradation Project is named as DVPL-II. The whole project
is divided into total of five spreads which is undertaken by three contractors i.e. Punj Lloyd
Ltd, Corrtech International Private Ltd, Fernas International Private Ltd.
Among all these Spread, this spread 1 is undertaken by Punj Lloyd Limited. It covers
approximately 145 Kms and it is from Dahej to Jhabua (near Bodeli). This spread consists of
six SV (Valve Stations), one Dispatch Terminal & one Intermediate Pigging Station. It has
two dump yards one is at 46 Km at Samili starting from Dahej i.e. 0 Km and another is at 135
Km at Waghodia of Vadodara District. In this spread it is found that there are 128 crossings
i.e. river, pond, highway & railway crossings.
The Project Office is located at village named Valan near Palej Ta. Karjan Dist, Vadodara.
Along with project office the camp is also located where the welder’s qualification test is
done.
The project duration is of 12 months including one month for commissioning of gas.
23
Figure 4.1- Route map of DVPL Up gradation.
Laying, Testing & Commisioning of approximately 145 Km long, 48” Pipeline and
associated facilities including the following:
24
Construction of gas stations (Scraper launching / Dispatch / Receiving / IP / SV’s)
and associated Mechanical, Civil, Electrical & Instrumentation works.
All consumables
Ball Valves (below 8”)
Globe and Check Valves
Fittings (below 16”)
Flanges (below 16”)
Assorted pipes (below 16”)
Induction bends
Coating material
Instrumentation Items
Electrical Equipments
OFC
HDPE
25
CHAPTER 5
Any large scale Cross-Country Gas Pipeline project involve multitude of activities, which
may be broadly classified into the following categories:
- Reconnaissance survey
- Detailed Engineering survey
- Permits & clearances from various statutory authorities.
- Acquisition of R.O.W in accordance with P&MP Act.
- Permanent acquisitions of land for pump stations, repeater stations, block valves.
- Opening of ROW
- Clearing and grading
- Hauling and stringing
- Trenching
- Bending
- Welding & Radiography
- Joint coating
- Lowering
- Back filling
26
5.2.2 Back End Activities:-
- Tie-ins
- Crossings
- Hydro testing
- Valves installation
- Final cleanup and restoration
- Installation of pipeline markers
- Documentation
- Caliper survey
- Line preservation
- Cathodic Protection
- Commissioning
27
5.1.1 Reconnaissance Survey:-
- Route Survey
- Ground Profile Survey
- Crossing Details
- Collection of hydrological data
- Collection of data on the type of terrain, soil and crop pattern
- Soil Resistivity Survey
28
5.2.1 Front end Construction Activities:-
- Stacking of ROW.
- Marking of ROW boundaries.
- Clearing of trees, bushes, farm crops, undergrowth and routes, electrical and
telephone poles falling within the 18 M width of ROW.
- Grading of ROW sufficient to be consistent with the maximum permitted pipe
bending radius.
- Providing ramps, diversion at road crossings, hume pipe culverts for maintaining
water flow across the ROW.
- Width of R.O.W is 25 M.
- Pipeline occupies a small area balance for movement of equipment and machinery.
- Rail tracks, highways, roads, canals, and embankment of canals not to be disturbed
during clearing and grading.
29
5.2.1.2 Hauling and Stringing of pipes
Definition: Once the construction rights-of-way have been cleared sufficiently to
allow construction equipment to gain access, sections of pipe are laid out along the
rights-of-way. This process is called 'stringing' the pipe.
- Transportation of pipe from stockpile/storage yard and arranging them along R.O.W
is done.
- Extreme care is exercised during loading and unloading.
- Rough handling is avoided as it may gouge or dent a pipe.
- Coated pipes require extra-ordinary precautions.
- Stringing to be done in such a manner that the pipes are readily accessible but do not
obstruct the movement of equipment and personnel.
- In rocky areas, pipe stringing shall be done after rock trenching.
- Stringing shall not be done for more than 10 km ahead of trenching.
- Pipes of special grades or wall thickness shall be strung at the required specific
locations.
30
Figure 5.3- Stringing.
5.2.1.3 Trenching
Definition: After stringing the pipe sections in place, a trench is dug along the rights-
of-way alongside the pipe sections. Topsoil is often removed from the work area and
stockpiled separately to be used in site restoration.
- The pipeline shall be laid at a distance of 5 mtr. from one edge of the ROW.
- Stacking of trench line.
- The width of the trench shall be equal to the pipe diameter plus 400 mm.
- The depth of the trench shall be equal to diameter of the pipe plus 1 mtr.
- Extra width and depth shall be provided in rocky terrain.
- Stripping of the top soil upto 30 cm of the trench and storing separately.
- Suitable crossing for passage of men, equipment, cattle etc. shall be provided.
31
- Sometimes rocks may come in the trench route. The thickness of rock to be removed
is less than 500 mm then it is done by rock breaker (attached to the excavator).
32
5.2.1.4 Bending
Definition: A bending machine is used in the field to make slight bends in individual
sections of the pipe to account for changes in the pipeline route and to conform to the
topography.
33
- Check for ovality, thinning, wrinkles and buckles.
34
- Welding procedure specification has to be prepared for approval of the procedure and
qualification of the welders as per API 1104.
- Internal line up clamp shall be used for proper alignment of joint.
1. Bevel cleaning:
It is done with help of wire grinding and its purpose is to remove any foreign material
or rust from the bevel.
2. Alignment of Pipes:
This is the operation of bringing two pipes together. With the help of internal clamp a
second pipe is brought into alignment with the first one. This is a manual clamp
whose operation is controlled with a handle coming out of the free end of the second
pipe.
The seams of the adjacent pipes are kept in such a way that they are at least 30° away
from the vertical plane (at least 60° away from each other). This is done so as to
facilitate weld joints. The seams shall not be kept at the lower side because the
possibility of corrosion and erosion are maximum throughout the seam.
35
3. Preheating:
This is an important operation that plays a vital role in determining the weld quality.
Since the pipe comes from a distant place and comes across different temperature
conditions it becomes necessary to preheat the pipe that removes some of the possible
residual stresses and avoids sudden rise in temperature while welding.
4. Root-Gap:
After the preheating the root gap is provided. It facilitates the proper penetration of
the root pass.
5. Hammering:
Hammering is done with help of a brass hammer to detect ovality in the pipes.
Purpose of using brass hammer is to avoid making dents on the pipe surface (since
brass is softer than steel).
6. Root-Pass:
The whole quality of the weld jont depends upon root pass so this is done by the
specialist welders. This is a downhill operation. Current used is 90-130 Amps.
Electrode used for this operation is E6010 type (3.2 mm).
7. Root- Grinding:
After the root pass root grinding is done to remove slag as well as to give bevel for the
hot pass. This must be done within 3 minutes of the root pass.
8. Hot-Pass:
This is done at a current around 110-140 Amps. The electrode used is E8010 (4 mm).
Hot pass must be completed within 5 minutes from the root pass.
9. Slag-Removal:
After the hot pass the slags are removed by wire brushing. A shining face would
indicate proper slag removal.
36
10. Filler Pass and Capping:
Filler and capping are multiple pass operation. Filler has three steps F1, F2 & F3.
Electrode used is E8010 (4.8 mm).
Capping is again wire brushed and left with shining face; start point of the capping
pass is grounded to an even surface.
Bevel cleaning
Alignment of pipes
Root-Gap
Preheating
37
Hammering
Root-Pass
Slag Removal
38
Weld joint Numbering
Two welding machines are connected in series so that two welders can perform the welding
operation simultaneously.
All main-line weldings are done by the contractors as per the API 1104 specification. Any
doubtful joints are then made to undergo radiographic testing; the NDT has been caried out
by the NDT team.
5.2.1.6 Radiography:
- Radiographic inspection is carried out by using X-rays.
- Visual inspection of all welds shall be carried out by qualified welding engineer
having minimum qualification of Level - II certification.
- All joints at the following locations shall be radiographed.
Initial 1 km.
At cased road / rail, submerged crossings,
Tie-ins (including golden tie-ins)
Marshy areas.
Valves and insulating couplings
20% of balance mainline joints(100% here)
5.2.1.7 Joint-coating:
The main pipe coating is 3LPE (Three Layer Polyethylene) coating. Field-coating is applied
to the welded areas at the ends of the pipe sections to prevent corrosion.
39
- 250 mm on either side of the pipe is left un-coated in the coating yard to facilitate
welding.
- The width of the sleeve shall depend upon the cut back length provided in the yard
coated pipe.
- Heat shrinkable sleeves are used for coating welded joints.
- Pipe surface is sand blasted to SA-21/2 specification.
- Sand blasted area is heated upto 600C and epoxy primary is applied on the surface.
- The sleeve is wrapped around and then shrunk on the joint using a propane/ LPG
torch.
- Air bubbles trapped are removed using hand rollers.
- The integrity of the joint coating is tested by conducting peel test.
1. Sand Blasting:
The flawless joints are sand blasted to shining face (SA 2.5). Sand is directed to the
joint surface with the help of a hose pipe and compressed air. 100 mm on the both
sides of the joint of the factory coating adjacent to surfaces shall be thoroughly
cleaned.
40
2. Heating:
The sand blasted surface is heated with gas flames by two operators. It must go up to
70-80° C. the line coating edge is prepared with a 30° chamfer to provide a smooth
transition between the pipeline coating and the bare steel.
3. Apply Polymer: Then Primer A and B is mixed in the ratio of 70%:30% respectively.
Then the mix is applied on the heated surface with the help of brushes.
6. Rolling:
Freshly applied coating is rolled properly to eject any air entrapped in between the
metal and the coat.
41
Heating and Chamfering Applying Primer
Rolling
Finishing
42
5.2.1.8 Holiday Testing:
This is done with the help of holiday machine. This is done to detect any damage in the
coating before lowering. Before the lowering operation the whole pipe section has to be
checked for any irregularities or disbondment in the coating. This operation is known as
holiday detection. The instrument with which it is done is called “Jeep” or “Holiday
Detector”. A “beep” in the Jeep gives indication of irregularity at that point/position.The flaw
must be removed (coating repaired) again checked for holiday and then only the lowering is
allowed.
5.2.1.9 Lowering:
- Ditch to be free from rock, hard clods, welding rods or objects that may damage
the pipe
- Pipe to be handled using non-abrasive lowering belts to avoid coating damage.
- Sufficient number of side booms to be deployed for lifting the pipe to ensure safe
operation without overstressing the pipe.
- Trench to be rectified so that bends fit the ditch in a satisfactory manner.
- Padding (min 4”) to be done in rocky areas.
- Usually the section of 1.2 km can be lowered in a day.
43
Figure 5.13- Lowering.
44
5.2.1.10 Backfilling:
Definition: Once the pipeline is lowered into the ground, the trench is carefully
backfilled, to ensure that the pipe and its coating are not damaged. Materials like
Sand, silt, clay is used in backfilling.
- In areas where the ground is rocky and coarse, the backfill material is screened to
remove rocks or the pipe is covered with a material to protect it from sharp rocks
and abrasion.
- Clean fill may be brought in to cover the pipe. Once the pipe is sufficiently
covered, the coarser soil and rock can then be used to complete the backfill.
- As the backfill operations begin, the excavated material is returned to the trench in
reverse order, with the subsoil put back first, followed by the topsoil. This ensures
the topsoil is returned to its original position.
- After backfilling 300 mm above the pipe top surface a warning tape (Red Colour)
is laid throughout the length. Purpose of this warning tape is to warn any future
excavation activity about the pipeline’s existence.
5.2.2.1 Tie-ins:
Situations in mainline such as rail/ road/ river crossings etc. may cause a break in the
continuity of mainline laying operation and are normally by-passed by the mainline
laying crew.
45
The process of connecting the un-connected sections of the pipeline is defined us tie-
in operation.
5.2.2.2 Crossings:
Type of Crossings
1. Open Cut : Roads, and minor water courses.
2. Cased : Railways, National & State Highways.
3. Submerged crossings : Major Rivers.
4. Horizontal Directional Drilling : Perennial Rivers & Canals.
46
Working Steps involved in H.D.D are:
- PILOT DRILLING:
- PRE-REAMING:
- PULLBACK:
47
REAMER AND DRILL PIPE:
48
Figure 5.17- HDD Machine.
49
5.2.2.4 Hydrotesting:
Definition: The purpose of a hydrostatic pressure test is to eliminate any defect that
might threaten the pipeline's ability to sustain its maximum operating pressure, or to
determine that no defects exist.
- Hydrostatic pressure testing consists of filling the pipeline with water and raising the
internal pressure to a specified level above the intended operating pressure. Critical
defects that cannot withstand the pressure will fail.
- Upon detection of failures, the defects are repaired or the affected section of the
pipeline is replaced and the test resumed until the pipeline "passes".
- Inline Inspection (ILI) technologies are also used that permit the identification of
specific types of defects, such as corrosion. But because not all lines can be inspected
with ILI tools and because of the need to find types of defects that are not currently
detected by ILI technology, hydrostatic testing is an accepted method for
demonstrating the fitness of a pipeline segment for service.
Hydrotesting may be done either section wise before lowering in or between two
successive valve stations just before commissioning. Difficulties with the sectional
Hydrotesting is that after testing the section has to be filled with standard fluids along
with corrosion inhibitor which may raise the cost.
- Availability of water
- Suitable place for disposal
- Ground profile
- Logistics
Test procedure
50
- Evaluation and acceptance
5.2.2.7 Documentation:
- Daily log book
- Separate register for each activity
- Pipe Book
- Welding inspection report
- Radiographic inspection report
- Tie-in charts
- Pipe damage register
- Equipment & manpower mobilization report
- Hydrostatic testing register
- Claims register
Due to deviations
Due to change in work plan
Damage to pipes etc.
51
5.2.2.8 Site Restoration:
52
CHAPTER 6
OBSERVATIONS
- Construction schedule :10 months for Mechanical completion and 1 months for gas In
- Controlled Rock blasting.
- Pipeline is laid at a clearance of 6 m from existing pipeline ( except at river and
Special crossings.)
- Most of the pipeline crossings is by Open cut, except one HDD (Narmada Canal)
- Line pipe Material grade is API 5L X 70 or X 80 or combination.
- The station construction would be in X70 grade pipes with X 70 grade fittings.
- Number of Hot bends is significantly higher than conventional pipeline as the
Pipeline is being laid in common ROU.
- Additional ROU width to be acquired by GAIL is
Dahej To Vemar : 10 Meters
Vemar to Vijaipur : 18meters
- Lack of experienced of X 80 welding (manual and semi-automatic)
- Availability of Automatic welders for X-80 grade Line pipes
- Availability of AUT and UT Operators for X-80 grade line pipes.
- Necessity to conduct Field cold bending test to determine max. angle achievable.
- Line pipe hot bend manufacturer to assess their capacity to fabricate
Induction bends with X80 material (LSAW/HSAW).
- Farmers creating problem related to land acquisition.
- As a result problem faced by GAIL in acquiring the land and submitting the ROU to
Punj Lloyd to further proceed.
- Imperfect mobilization of funds.
- Improper planning.
- Delay in the project by a larger time period.
53
CHAPTER 7
Suggestions:
54
BIBLIOGRAPHY
1. Menon E. Shashi. Gas Pipeline Hydraulics. Published in 2005 by CRC Press, Taylor
& Francis Group, LLC.
2. ASME B31.8- 1995 Edition, New York. Gas Transmission and Distribution Piping
Systems.
3. Mr. S.R. Bhaskar. (2009, August 12th) Indian Oil Corporation Limited.
Pipeline Construction- An Overview – Presentation.
4. Scope of Work (SOW) provided by Punj Lloyd.
5. Construction Manual and Documents provided by Punj Lloyd.
55