Documente Academic
Documente Profesional
Documente Cultură
Max
Max
Intercon wind/(p
Wind wind/(mi
Country nection eak
Peak Min Power % peak n load Energy
capacity load
MW MW demand +interco Terms
+interc
nnectio
onnecti
n)
on)
West
3700 1400 2570 2350 63.51% 59.19% 37.48% 24%
Denmark
North
2000 750 5200 2275 113.75% 38.24% 31.60% 33%
Germany
Gotland
160 45 180 90 56.25% 40.00% 26.47% 19%
Sweden
Effect of Large Scale Wind
Generation on Grid Operation
Introduction
In power system reliability and quality is given
more emphasis as any disturbance is proved to
be costly to the economy
Wind generation has impacts in power system
reliability and efficiency
The impact is both positive as well as negative
and depends on the time scale
Different time scale means to different models
for studying impact on the grid
Generation
System-wide Primary Adequacy
over Reserve Secondary
1000MW Reserve
Hydro-Thermal
Efficiency Grid
Grid Transmission Adequacy
Stability Efficiency
Regional
100- Congestion
1000MW Management
Voltage Distribution
Local Management Efficiency
<50MW
Power
Quality
ms-sec Sec-min Min-hr Hr-days Years
Wind Generation
When wind power plants are introduced into the
power system, an additional source of variation
is added to the already variable nature of the
system.
Every change in wind output need not be
matched one-for-one by a change in another
generating unit moving in the opposite direction.
This is a direct consequence of the requirement
that the entire system must be balanced instead
of balancing each individual load or individual
wind generator.
Wind Generation
Available power from wind = 1/2 ρAvn (n = 2 to 2.3 for wind
turbines)
The power trace would follow the general trend of wind
speed closely but it would be smoother
This is because of the inertia of the machine
In general in a typical wind farm with large number of
wind turbines, the power flow is very smooth with a
standard deviation of 4.4MW in a 100MW wind farm
whose output has varied from 32.4MW to 47.9MW in an
hour
The co-efficient of variation would drop from 0.86 with
small capacity less than 2MW to 0.4 with capacity of 50 to
100MW and to 0.15 with capacity of over 1000MW
Variability of Wind Generation
Variability of wind has been widely studies across the
world
Most of the data available give insight into the variability
that is relevant for power system operation
Variability decreases with more turbines and wind power plants
distributed over the area
Larger areas decrease the number of hours of zero output
Variability decreases as the time scale decreases – second and
minute variability is generally small whereas variability for hours
can be large
Variability is high in off shore compared to on shore as
coherency is very strong in off shore
Wind output for single m/c., wind farm (72.7) and All
wind farms (15900MW)
Wind Generation in Tamilnadu July 2008
2000
1800
1600 7/1/2008
7/2/2008
1400
Gen eratio n in M W
7/3/2008
1200 7/4/2008
1000 7/5/2008
800 7/6/2008
7/7/2008
600
7/8/2008
400 7/9/2008
200
0
0:00
1:05
2:10
3:15
4:20
5:25
6:30
7:35
8:40
9:45
10:50
11:55
13:00
14:05
15:10
16:15
17:20
18:25
19:30
20:35
21:40
22:45
23:50
Time
Wind Gen. and TN Demand on 7th July 2008
10000 1800
9000 1600
8000 1400
7000
Demand in MW
Wind Gen. in MW
1200
6000
1000
5000
800
4000
600
3000
2000 400
Demand
1000 Wind Gen 200
0 0
0:00
1:17
2:34
3:51
5:08
6:25
7:42
8:59
10:16
11:33
12:50
14:07
15:24
16:41
17:58
19:15
20:32
21:49
23:06
Time
Worst Behaviour recorded
Denmark : 2000MW decrease in 6 hours
on 8th Jan 2005
North Germany: 4000MW decrease within
10 hours on 24th Dec. 2004
Portugal: 700MW decrease in 8 hours on
1st June 2006
Texas: Decrease of 1550MW in 2 and half
hours on 24th Feb 2007
Study results of NREL
1000
2000
3000
4000
5000
6000
0 :0 0 0
1 1 :2 9
1 2 :2 2
1 3 :1 5
1 4 :0 8
1 5 :0 1
1 5 :5 4
1 6 :4 7
1 7 :4 0
1 8 :3 3
1 9 :2 6
2 0 :1 9
FREQ
Demand
2 1 :1 2
2 2 :0 5
2 2 :5 8
2 3 :5 1
49
49.2
49.4
49.6
49.8
50
50.2
50.4
50.6
50.8
51
F re q u e n c y in H z
Load Following
Here is the generation schedules are adjusted ( or
paid for balancing market) following changes in the
loads
The time frame is of the order of 10 minutes
Load following requirement is highly correlated
Most load raise in the morning
Load decreases in the night
Total system load following requirement is less than
the sum of the load following requirements of the
individuals
With wind the requirement would depend on how
wind generation is concentrated or well distributed
along with the terrain,
Load Regulation
The random variation in the demand is adjusted
instantaneously by the generator– taken care of by
Primary response generators
The time frame is the real time
Load Regulation requirement are uncorrelated
Total system load regulation requirement is less than the
sum of the load regulation requirements of the
individuals
The wind variation would have to accounted and would
call for additional primary response generators in strict
frequency regime condition
Demand
Load following & Regulation Load Following
Base Load
Load Regulation
4500 100
4000 80
60
3500
40
Load Regulation
3000
Load in MW
20
2500
0
2000
-20
1500
-40
1000
-60
500 -80
0 -100
5:31
5:35
5:39
5:43
5:47
5:51
5:55
5:59
6:03
6:07
6:11
6:15
6:19
6:23
6:27
6:31
6:35
6:39
6:43
6:47
6:51
6:55
6:59
Time
Unit Commitment
Traditional unit commitment procedure need to
be modified by considering the wind power
variation with time scales of 1 hour to days
The main issue is on how the conventional
capacity is run and also on ramp rates, partial
operation, start/stops of conventional units
This calls for very good operational planning set-
up at the Load despatch center
System Adequacy
Transmission efficiency & operation is critical for
any generation if availability is less than 30%
Reactive power requirement of transmission
system depends on the loading of the lines
(above or below SIL)
Planning criteria for these generation be
modified from the conventional method (N-1 or
N-2)
Penetration of wind
The studies worldwide indicate that
What is “HIGH” penetration of wind power is
not straight forward
Metrics used are % of gross demand
(energy), % of peak load
Penetration level depend on the
interconnecting capacity of the grid as critical
moments of high wind and low load can be
relieved by the interconnector capacity
Conclusion
The large scale integration of wind energy has impacts
on the power system operation
The Impact has both positive and negative effects
Need to strengthen operational planning in the system
operation
Need for new operational tools for the system operator
for secure and reliable operation of the grid
Need for on-line monitoring of wind generation to take
effective steps during load regulation and load following
time scales
Acknowledgement
National Renewable Energy Lab
Wind Power Plant behaviors: Analysis of
Long-Term wind Power Data
A Method and case study for Estimating the
Ramping Capability of a Control Area or
Balancing Authority and Implications for
Moderate or High Wind Penetration
Acknowledgement
IEW wind
Design and operation of power system with large
amounts of wind power - VTT
GE Power Systems Energy Consultants
The Effects Of Integrating Wind Power On
Transmission System Planning, Reliability, and
Operations
Eltra
Specifications for Connecting Wind Farms to the
Transmission Network
Thank you