TEESTA LOW DAM PROJECT, STAGE-IV RATE ANALYSIS FOR CONCRETE POURING INCLUDING VIBRATING (By other than Tower Crane) Sl No 1 a b c d
Annexure-3 Page-10 of 22
Description
Factors
Unit
Quantity
Rate
Amount
Remarks
Manpower Charges for 143 cum pouring of concrete per shift (considering 12.96 cum per hour) Mason 1.00 No Skilled helper 1.00 No Unskilled labour 1.00 No Vibrator man 1.00 No Cost of manpower for 143 cum of concrete pouring Rs Add contractors profit & overhead 10.00% Rs Total Cost For 143 cum of concrete pouring Rs Total Cost per cum of contrete pouring Rs/cum Time cycle considered Total concrete pouring per shift 12.96 cum/hr 142.56 cum/shift