In late 2001, the Steering Group to Monitor the Use of the Standard Method of Measurement for Civil Engineering Works set up a Working Group to review the Standard Method of Measurement for Civil Engineering Works, 1992 Edition (the SMM). Members of the Working Group comprised contract advisers of Works Departments under the Environment, Transport and Works Bureau of the Government of the Hong Kong Special Administrative Region (the Bureau) and representatives from the Legal Advisory Division of the Bureau. The Working Group produced a new measurement document entitled Handbook for Preparing Bills of Quantities for Civil Engineering Works (the Handbook), which is to replace the SMM. In the process of finalizing the Handbook, the Working Group took into consideration the findings and recommendations of a consultant appointed by the Bureau in October 2005 to review the draft Handbook. The Handbook sets out guidelines for preparing the Bills of Quantities for civil engineering works contracts. In identifying and describing the work required of an item of work, the Handbook takes a different approach from that of the SMM. While the SMM relies heavily on the concept of item coverage, the approach in the Handbook is to identify and describe the requirement by way of item description and item description extension. The Bills of Quantities remains to be intended in the first instance to give information upon which tenders can be obtained. When a contract has been entered into, the function of the priced Bills of Quantities is to provide for the valuation of the work executed. More emphasis, however, is now placed on the need to ensure that the price tendered represents the all inclusive value of the work required by the Conditions of Contract, Drawings and Specification. Provisions have also been made to do away with the time consuming and resources demanding Cost ascertainment exercise associated with excusable delay - by measuring and paying such Cost through items in the Bills of Quantities. Unlike the SMM, the Handbook will not form a part of the contract document. In using the Handbook, the contract drafter should devote sufficient time and resources to prepare the Bills of Quantities and take heed of any peculiarities of his project to ensure that the Bills of Quantities are compatible with other documents, including the Conditions of Contract, Drawings and Specification.

CONTENTS PAGE
Preface PART I PART II : : GUIDELINES FOR PREPARING BILLS OF QUANTITIES PREAMBLE ITEM DESCRIPTION, UNIT AND MEASUREMENT Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Section 8 Section 9 Section 10 Section 11 Section 12 Section 13 Section 14 Section 15 Section 16 Section 17 Section 18 Section 19 Section 20 Section 21 Section 22 Section 23 Preliminaries Ground Investigation Site Preparation Works Fencing and Gates Drainage and Ducts Pipework Earthworks Roads and Pavings Piling Works Formwork Steel Reinforcement Concrete Prestressing Steelwork Waterproofing Bearings and Movement Joints Marine Works Tunnelling Geotechnical Works Not Used Not Used Brickwork, Blockwork and Masonry Finishings 195 199 2 5 12 17 18 45 55 59 61 81 95 106 122 134 137 140 144 147 152 154 158 166 177

PART III :

Section 24 Section 25 Section 26 Section 27 Section 28 Section 29 Section 30

Landscape Works Testing Miscellaneous Daywork Site Safety and Environmental Management Prime Cost Sums Work and Services Not Separately Itemised

201 213 220 227 233 244 247

PART I GUIDELINES FOR PREPARING BILLS OF QUANTITIES


A. General A.1 These guidelines are to be used for the preparation of Bills of Quantities at the pre-contract stage. The Bills of Quantities shall comprise the following: Preamble Method of Measurement Bill No. 1 : Preliminaries Bill No. 2 : : - Bill No. : - Bill No. : Daywork -* Bill No. : Site Safety and Environmental Management -* Bill No. : Provisional Sums -* Bill No. : Prime Cost Sums - Bill No. : Work and Services Not Separately Itemised - Grand Summary * A.2 A.3 These bills should be included where applicable.

Part II of this Handbook shall be reproduced as the Preamble to the Bills of Quantities. The Method of Measurement shall be prepared to cover all items of work in the bills within the Bills of Quantities using Part III of this Handbook as the basis. The layout of the method of measurement for an item of work shall take the following form: (i) (ii) (iii) (iv) (v) Heading; Sub-heading; Item description and unit; Item description extension (if any); and Measurement (if any).

A.4

In Part III of the Handbook, notes, itemisation tables and any wording printed in italics and of a unique font of their own are for guidance of the contract drafter only and shall not be reproduced in the Method of Measurement. The itemisation tables are guidelines for preparing item descriptions. In determining the number of bills to be included in the Bills of Quantities, the contract drafter may take into account the nature and location of work, date of commencement, time for completion or any other pertinent circumstances. Thus, for example, separate bills may be provided for different areas of the Site or Sections of the Works. Each bill shall contain items of work grouped into appropriate sections, adopting the section headings/sub-headings, order and numbering in Part III of this Handbook. Where a section, a sub-heading or a paragraph in Part III of this Handbook is not required for incorporation into the Contract, the contract drafter shall state not used against such section, paragraph or chronological group of paragraphs in the Method of Measurement. This is necessary for maintaining the cross-referencing of paragraphs adopted in the Handbook. To maintain the

A.5 A.6

A.7

consecutive paragraph numbering in the Method of Measurement, when new paragraphs are inserted, the paragraphs should be suffixed with a capital alphabet. Thus, for example, if new measurement rules are provided in respect of manholes after paragraph 5.20 in Part III, they shall be designated as paragraphs 5.20A, 5.20B, etc. Additional paragraphs for items of work under a new sub-heading which are not provided in Part III of this Handbook should be added to the end of the appropriate sections of the Method of Measurement. A.8 Each item description is to be consistent with and be compounded from one or more of the descriptive features listed in the itemisation groups in the various sections in Part III of this Handbook. As many of these groups or features shall be used as may be necessary to identify the work required. However, no more than one feature from any one group may be represented in any one item description. If the descriptive features contained in the itemisation groups do not correctly identify the work required, the contract drafter shall amend and draft any additional item descriptions or item description extensions necessary to fully describe the work for inclusion in the Method of Measurement and the bills. The item descriptions shall be drafted using the wording and format of the itemisation tables in the Handbook. The contract drafter may add new sub-headings, but shall not delete, amend or revise existing sub-headings. The contract drafter shall also amend, revise or add anything to the unit, measurement, item description and item description extension where necessary to suit specific project needs. The purpose of the item description extension is to avoid lengthy item descriptions and to avoid uncertainty or ambiguity as to what is to be priced by identifying and listing those components that are intended to be included under that item of work as distinguished from any other separately measurable items of work. Work or services of an incidental nature need not be stated. Item descriptions shall be concise, comprising descriptions from the chosen groups and features of the itemisation tables, with reference to relevant Drawings where possible, although it is not necessary to refer to all Drawings on which the item being described appears. Information given in item descriptions should be sufficient to identify the work required without ambiguity. The Bills of Quantities are to contain all those items required to comprise the Works. Quantities may be rounded up or down where appropriate. Fractional quantities are not generally necessary but, where required, should not be given to more than one place of decimals.

A.9

A.10

A.11

A.12 A.13

B.

Materials supplied to the Contractor Where the Contractor is to be supplied with materials on Site or where he is to collect materials from a designated source, it should be so stated in the item description or item description extension in the Bills of Quantities.

C.

Work affected by non-tidal open water or tidal water and not covered in Marine Works section Work affected by non-tidal open water or tidal water shall not be measured separately unless the nature of the work is such that if separate measurement for such work is not provided for, this will cause undue difficulty to the tenderers in pricing their tenders.

D.

Plant used on daywork section 27 Separate items should be provided for Provisional Sums, and percentage adjustment thereto, for different categories of plant used on daywork in accordance with the relevant sections of the HKCA Schedules For Plant Used in Dayworks Carried Out Incidental to Contract Work.

E.

Prime Cost Sums section 29 E.1 Where Prime Cost Sums are included in the Bills of Quantities for work to be executed or services to be supplied by a Nominated Sub-contractor, separate items are to be provided for: (i) (ii) general attendance provided by the Contractor in connection therewith in the form of a lump sum; special attendance provided by the Contractor (if required) for any facility or specific requirements not covered under general attendance in the form of a lump sum. Such facility and specific requirements shall be stated clearly in the item description; the Contractors profit in relation to the Prime Cost Sum in the form of a percentage.

(iii) E.2

Where Prime Cost Sums are included in the Bills of Quantities for materials to be supplied by a Nominated Sub-contractor, a separate item shall be provided for the Contractors profit in relation to the Prime Cost Sum in the form of a percentage.

F.

Contingency Sum A Contingency Sum, if required, shall be provided in the Grand Summary following the total of the amounts brought forward from the summary of each bill.

G.

Adjustment Item An item described as the Adjustment Item shall be provided in the Grand Summary following the total of the amounts brought forward from the summary of each bill and the Contingency Sum.

H.

Drawings Measurement may be amplified by Drawings. The item descriptions, item description extensions and relevant measurement clauses pertaining thereto shall make reference to such Drawings where appropriate.

I.

Unit of measurement If it is intended that an item of work is to be paid as a lump sum, sum shall be used as the unit of measurement for such an item of work. The symbol - shall be inserted against the rate and quantity columns in the bills for items of work for which the unit of measurement is sum. For the avoidance of doubt, item shall not be used as a unit of measurement.

J.

Measurement of preliminaries J.1 The measurement of time based preliminaries is divided into two groups: (1) preliminaries other than the Contractors overheads as described in paragraph 1.6 in Part II of this Handbook

and (2) the Contractors overheads as described in paragraph 1.7 in Part II of this Handbook. J.2 Generally speaking and subject to other provisions to the contrary, time based preliminaries other than the Contractors overheads are measured during the original time for completion, the extended time for completion and the Maintenance Period of the Works when such work or services are required and executed. Measurement during the period of culpable delay by the Contractor (i.e. where Works have not been completed but the prescribed/extended time for completion has passed) will be excluded. This is provided for in paragraph 1.6 in Part II of this Handbook. In addition, paragraph 1.6 in Part II of this Handbook provides refinement of the general rule where the Works are divided into Sections. Generally speaking and subject to other provisions to the contrary, time based preliminaries which are the Contractors overheads (i.e. those provided for under the sub-heading Contractors overheads in section 1 in Part III of this Handbook) are measured during the original time for completion, part of the extended time for completion (where the extension of time is granted due to causes relating to direct actions of the Employer/Engineer; i.e. GCC Clauses 50(1)(b)(iii), (iv), (vi), (vii) and (viii)) and the Maintenance Period of the Works. Measurement during the period of culpable delay by the Contractor and the period of extension of time granted due to causes other than those described above will be excluded. This is provided for in paragraph 1.7 in Part II of this Handbook. In addition, paragraph 1.7 in Part II of this Handbook provides refinement of the general rule where the Works are divided into Sections. The expression excluding the Sections for Establishment Works and Aftercare to Old and Valuable Trees in paragraphs 1.6 and 1.7 in Part II of this Handbook assumes that Establishment Works and/or Aftercare to Old and Valuable Trees form a separate Section or separate Sections of the Works. If the Contract does not contain any Section of Works which comprises Establishment Works only or any Section of Works which comprises Aftercare to Old and Valuable Trees only, the expressions (excluding the Sections for Establishment Works and Sections for Aftercare to Old and Valuable Trees), /Works except Establishment Works and Aftercare to Old and Valuable Trees and other than the Maintenance Periods for Establishment Works and Aftercare to Old and Valuable Trees in paragraphs 1.6 and 1.7 in Part II of this Handbook shall be deleted as appropriate. If retained, the expressions shall not be italicised. The Handbook and the associated standard provisions are prepared on the assumption that all time based preliminaries are included into a single bill No. 1 (Preliminaries). Should a contract include Section(s) Subject to Excision and time based preliminaries related thereto are included in a separate bill, other than bill No. 1 (Preliminaries), the Method of Measurement, in particular paragraphs 1.6 and 1.7 in Part II of this Handbook, should be specifically drafted to suit.

J.3

J.4

J.5

K.

Measurement of work of a temporary nature It is recommended that work of a temporary nature shown on the Drawings and designed by the Engineer be measured irrespective of whether it is to be removed under the Contract.

L.

Measurement of items for photographs - section 1 Where separate measurements are provided for aerial photographs, record photographs etc., appropriate Particular Specification Clauses and Method of Measurement paragraphs should be included in the Contract.

M.

Temporary fencing section 4 Temporary fencing which is to be removed by the Contractor should be included as items under section 1 in Part III of this Handbook. Fencing which does not require removal by the Contractor should be included as items under section 4 in Part III of this Handbook.

N.

Excavation of soft spots, filling of soft spots and other voids sections 5, 6 and 7 No separate items are provided for excavation of soft spots and filling of soft spots and other voids under sections 5, 6 and 7 in Part III of this Handbook. Where soft spots are encountered below the formation level during excavation for works measured under the above sections, they should be dealt with as variations.

O.

General excavation lines - section 7 Lines and levels shall be shown on the Drawings or described in the Specification to indicate the extent of general excavation required to be carried out.

P.

Probing ahead - section 18 No separate items are provided for probing ahead under section 18 in Part III of this Handbook. Where probing ahead is specifically required by the Engineer during excavation for tunnel works, it should be dealt with as a variation.

Q.

Soil nails and erosion control - section 19 Where items for soil nails and erosion control under section 19 in Part III of this Handbook are included in the Contract, the corresponding Particular Specification Clauses should also be included.

R.

Items of work with small quantities The inclusion of items of work with very small quantities, especially items on earthwork and testing, may attract unreasonably high rates which would result in serious financial consequences if the quantities of such items increase substantially. If the only purpose for including these items is to obtain rate(s) from the Contractor, these items should not be included and the works should be dealt with as variations during construction.

S.

Bills for section 1 and section 30 Sections 1 and 30 in Part III of this Handbook are mandatory sections and the items contained therein should be included in each Contract under bill No. 1 (Preliminaries) and a separate last bill (Work and Services Not Separately Itemised) respectively.

T.

Sample bill page A sample showing the layout of a typical page from a bill within the Bills of Quantities is provided for reference at the end of this Part of the Handbook.

10

U.

Item description and item description extension Contract drafters should note that the item description and item description extension of an item of work are generally prepared using the relevant standard specification clauses at the time of preparation of the Handbook as the basis. If other specification clauses concerning any item of work are included in the Contract, the corresponding item description and item description extension should be reviewed and amended as appropriate.

V.

Application For the avoidance of doubt, the guidelines under this Part of the Handbook are to be used for the preparation of Bills of Quantities and are not to be included as part of the Bills of Quantities. Also, the guidelines shall not be deemed to form part of or be taken into consideration in the interpretation of the Bills of Quantities.

11

Sample bill page Bill No. 1 - Preliminaries


Item No. SECTION 1 PRELIMINARIES Description Quantity Unit Rate ($) Amount ($)

Temporary accommodation for the Engineer 1.1 1.2 1.3 Provision of temporary accommodation for the Engineer, principal office Servicing of temporary accommodation for the Engineer, principal office Dismantling and removal of temporary accommodation for the Engineer, principal office 36 sum mth sum
-

Temporary traffic arrangements 1.4 Planning and implementation of temporary traffic arrangements, on land sum
-

Sureties, security and insurances 1.5 Procurement of third party insurance sum
-

Total to Collection Sheet

12

PART II PREAMBLE
1. 1.1 General principles Items shown in the bills of the Bills of Quantities are items of work. In the Bills of Quantities, the headings, sub-headings, item descriptions and item description extensions describe and identify the work covered by the respective items of work. Such descriptions or identifications may not be exhaustive. The exact nature and extent of an item of work must be ascertained by reference to the Drawings, Specification, General Conditions of Contract and Special Conditions of Contract, as not all requirements may be stated in the item description or its item description extension. Furthermore, whilst the item description and item description extension may make specific reference to certain Drawings and/or Specification, the item of work described is deemed to include for all requirements shown on all Drawings and/or Specification pertaining to that item of work irrespective of whether or not the Drawing and/or Specification is stated in the item description or item description extension. The rate inserted against an item of work in the bills within the Bills of Quantities shall be deemed to be the full inclusive value of executing, completing, maintaining and/or supplying such item of work including any incidental work thereto, unless expressly stated otherwise elsewhere in the Bills of Quantities. The expression incidental work includes, but is not limited to, the carrying out of all work and services and complying with all obligations which are specified or reasonably implied in the Contract and which are related to, arise out of or are connected with the item of work as described in its headings, sub-headings, item description and item description extension. The rates inserted against the items of work in the bills within the Bills of Quantities shall include, but are not limited to, the following: labour; plant; materials and goods, including without limitation transportation and storage thereof; multiple handling of any kind; sampling and testing; preparation of surfaces and other preparatory work for follow-on activities; assembling, fixing, erecting, installing or placing of materials and goods in position; wastage, bulking, shrinkage and the disposal of any materials and goods; temporary protection and its subsequent removal; Temporary Works, including design; taking precautions and measures as far as is reasonable and practical to prevent interference with or damage to existing structures and utilities, roads, footpaths and paved areas, watercourses and drainage systems, public and private vehicular and pedestrian accesses, trees, graves and burial urns, including the provision of alternative access; (xii) keeping the Works where necessary, and as near as may be practical, free of water and protected from damage due to water and from weather conditions which may adversely affect the Works, and taking measures to prevent flotation of new or existing structures; (xiii) taking all measures required to execute the work as affected by non-tidal open water or tidal water; (xiv) dealing with water in watercourses, pipelines, drains and the like; (xv) working space; (xvi) overbreak and making good; (xvii) construction of longitudinal, expansion, contraction, movement, warping, construction, isolation joints and the like completed with sealants, fillers, cover plates and the like; (xviii) completion of formation and earthwork final surfaces; (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) (x) (xi)

1.2

13

(xix)

recording, taking readings, measurements and observations, and submitting to the Engineer all drawings, records, details of procedures and methods of construction to be used, technical literature, test certificates and any other documents or information required to be submitted under the Contract; (xx) carrying out trial mixes, trial runs and all other trials, demonstrations and mock-ups; (xxi) in the case of materials supplied by the Employer, return of the surplus; (xxii) taking all steps that are necessary to obtain and maintain all licences and permits necessary for the execution of the Works, and all costs in connection therewith including the costs of complying with the terms and conditions of the licences and permits; (xxiii) liabilities, obligations and risks involved in the execution of the Works set forth or reasonably implied in the Contract; (xxiv) establishment charges, overheads and profit. Provided that the Contractors overheads, including the overheads of any of his sub-contractors of any tier, shall be deemed to be included exclusively in the rates for the items under the sub-heading Contractors overheads in section 1 (Preliminaries) of the Method of Measurement. The rates inserted in other items of work in the bills within the Bills of Quantities shall not include the Contractors overheads. 1.3 The quantities shall be computed net from the Drawings, unless otherwise stated in the Contract, and no allowance shall be made for bulking, shrinkage or wastage. Where in the Contract a choice of alternative materials or designs is indicated, the item descriptions and rates inserted shall be deemed to cover any of the permitted alternative materials or designs which the Contractor may elect to use. Except for those tests provided for as separate items of work in the bills within the Bills of Quantities, the rates contained in the Contract shall be deemed to include for the cost of carrying out all tests on materials and workmanship specified in the Contract, including but not limited to, the cost of packing and transport required for delivering samples to and collecting from the place of testing. Without prejudice to provisions in other parts of the Bills of Quantities which expressly provide for certain items of work not to be measured, items of work under section 1 (Preliminaries) of the Method of Measurement the units of measurement of which are time based (but excepting items of work as described under the sub-heading Contractors overheads in section 1 (Preliminaries) of the Method of Measurement which shall be measured in accordance with paragraph 1.7 below)# shall not be measured: (i) where the Works are not divided into Sections, between (a) the end of the prescribed time or extended time for completion of the Works/Works except Establishment Works and Aftercare to Old and Valuable Trees**; and the date of completion of the Works/Works except Establishment Works and Aftercare to Old and Valuable Trees** certified by the Engineer in accordance with GCC Clause 53;

1.4

1.5

1.6

(b)

(ii)

where the Works are divided into Sections, between (a) the end of the prescribed time or extended time for completion of the Section of the Works (excluding the Sections for Establishment Works and Aftercare for Old and Valuable Trees)** which happens to be the latest in time; and the date of completion of whichever Section of the Works (excluding the Sections for

(b)

14

Establishment Works and Aftercare for Old and Valuable Trees)** certified by the Engineer in accordance with GCC Clause 53 which happens to be the latest in time; (iii) after the expiry of the Maintenance Period (or where there is more than one such Maintenance Period, after the expiry of the last Maintenance Period other than the Maintenance Periods for Establishment Works and Aftercare for Old and Valuable Trees**) where services are required as a consequence of the default of the Contractor.
(# Note: Please refer to Clauses J.1 and J.2 in Part I of this Handbook for guidance. note shall not be reproduced in the Method of Measurement.) (** Note: Please refer to Clause J.4 in Part I of this Handbook for guidance. not be reproduced in the Method of Measurement.) This

This note shall

1.7

Without prejudice to provisions in other parts of the Bills of Quantities which expressly provide for certain items of work not to be measured, items of work as described under the sub-heading Contractors overheads in section 1 (Preliminaries) of the Method of Measurement the units of measurement of which are time based shall not be measured##: (i) where the Works are not divided into Sections, between (a) the end of the prescribed time or extended time for completion of the Works/Works except Establishment Works and Aftercare to Old and Valuable Trees** due to extension of time which has been granted by the Engineer to the Contractor under sub-clauses (1)(b)(iii), (iv), (vi), (vii) and (viii) of GCC Clause 50; and the date of completion of the Works/Works except Establishment Works and Aftercare to Old and Valuable Trees** certified by the Engineer in accordance with GCC Clause 53.

(b)

For the purpose of calculating the extended time for completion of the Works due to extension of time granted by the Engineer under sub-clauses (1)(b)(iii), (iv), (vi), (vii) and (viii) of GCC Clause 50, the periods of extended time for completion granted under sub-clauses (1)(b)(iii), (iv), (vi), (vii) and (viii) of GCC Clause 50 shall be summed and added to the end of the prescribed time for completion of the Works; (ii) where the Works are divided into Sections, between (a) the end of the prescribed time or extended time for completion of the Section of the Works (excluding the Sections for Establishment Works and Aftercare for Old and Valuable Trees)** which happens to be the latest in time due to extension of time which has been granted by the Engineer to the Contractor under sub-clauses (1)(b)(iii), (iv), (vi), (vii) and (viii) of GCC Clause 50 (for the purpose of calculating the extended time for completion of each Section of the Works due to extension of time granted by the Engineer under sub-clauses (1)(b)(iii), (iv), (vi), (vii) and (viii) of GCC Clause 50, the periods of extended time for completion granted under sub-clauses (1)(b)(iii), (iv), (vi), (vii) and (viii) of GCC Clause 50 for that Section of the Works shall be summed and added to the end of the prescribed time for completion of that Section of the Works); and the date of completion of whichever Section of the Works (excluding the Sections for Establishment Works and Aftercare for Old and Valuable Trees)** certified by the Engineer in accordance with GCC Clause 53 which happens to be the latest in time.
This

(b)

(## Note: Please refer to Clauses J.1 and J.3 in Part I of this Handbook for guidance. note shall not be reproduced in the Method of Measurement.)

15

(** Note: Please refer to Clause J.4 in Part I of this Handbook for guidance. not be reproduced in the Method of Measurement.)

This note shall

1.8

The item description of an item of work shall be deemed to include an item description extension for the carrying out of all work and services necessary or desirable for the satisfactory completion of such item of work in accordance with the Contract.

2. 2.1

Definitions Unless otherwise defined in the Bills of Quantities, words and expressions defined in the Specification and Drawings and appearing in the Bills of Quantities shall bear the same defined meaning. The following words and expressions in the Bills of Quantities shall have the meanings hereby respectively assigned to them: (a) artificial hard material means brickwork, concrete, reinforced concrete, masonry, bituminous paving and any other artificial material of a similar nature and which necessitates the use of pneumatic tools or other similar methods for its removal; daywork means the work ordered under a variation order and to be paid in accordance with GCC Clause 62; existing ground surface means the surface of the ground before any work under the Contract has been carried out; Provisional Item means an item describing work, the requirement for which is uncertain at the time the tender documents are issued and which can only be carried out on instruction of the Engineer; For and only for the purposes of section 2 (Ground Investigation) of the Method of Measurement, rock means naturally occurring material of Grade I to III as classified in Tables 2 and 4 of Guide to Rock and Soil Descriptions Geoguide 3. For sections other than section 2 (Ground Investigation) of the Method of Measurement, rock means naturally occurring hard material whose geological classification is Grade I to III and which necessitates the use of blasting or pneumatic tools or other similar quarrying methods for its removal.

2.2

(b)

(c)

(d)

(e)

3. 3.1

Unit of measurement / Abbreviations The following unit and term abbreviations have been used: Unit/Term millimetre metre square millimetre square metre cubic metre kilogram tonne number hour Abbreviation mm m mm2 m2 m3 kg t nr h

16

week month number-day number-week number-month percentage British Standards Particular Specification Principal Datum General Conditions of Contract for Civil Engineering Works General Specification for Civil Engineering Works construction and demolition 3.2

wk mth nr-day nr-wk nr-mth % BS PS P.D. GCC GS C&D

The amount inserted by the tenderer in the bill for an item of work for which the unit of measurement is sum shall be deemed to be the rate inserted against such item of work in the bills within the Bills of Quantities.

4.

Discrepancy between the units of measurement given in the Method of Measurement and the bills Where there is discrepancy between the unit in the Method of Measurement and the unit for an item of work in the bills within the Bills of Quantities, the unit in the bill shall prevail, unless, by reference to the quantity in the bills and the nature of the item of work as identified by the Specification, Drawings, measurement rules, item description and item description extension in the Method of Measurement, the Engineer determines otherwise.

4.1

5. 5.1

Method of Measurement The Method of Measurement is set out in the following sections:

17

PART III ITEM DESCRIPTION, UNIT AND MEASUREMENT

18

SECTION 1
Heading

PRELIMINARIES
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. Where separate measurements are provided for aerial photographs, record photographs etc. under the sub-heading Photographs, appropriate Particular Specification Clauses and Method of Measurement paragraphs should be included in the Contract. Temporary fencing which is to be removed by the Contractor should be included as items under this section 1. Fencing which does not require removal by the Contractor should be included as items under section 4 (Fencing and Gates). This section 1 and section 30 are mandatory sections and the items contained therein should be included in the Contract under bill No. 1 (Preliminaries) and a separate last bill (Work and Services Not Separately Itemised) respectively.

Notes

ii

iii

iv

Measurement

1.01

Unless indicated otherwise and without prejudice to the adjustments in the Contract, for interim payment purpose the estimated value of a Preliminary Item with sum as the unit of measurement shall be calculated by multiplying the sum with the following factor: the period between B and C the period between A and C where A = anticipated date of completion of the Works or the last Section of the Works as determined by the Engineer B = end date of the monthly period as referred to in GCC Clause 78(1) = date when the relevant work, service or obligation mentioned in the said Preliminary Item has started

provided that the factor shall be taken as 1.0 if and when the factor is worked out to be more than 1.0.

Sub-heading

TEMPORARY ENGINEER
A.

ACCOMMODATION

FOR

THE

Notes

Separate items shall be provided for under the sub-heading Temporary accommodation for the Engineer in accordance with the following itemisation table:

19

Group

Feature

Unit

1. 2. 3.

4.

Provision of temporary accommodation for the Engineer Servicing of temporary accommodation for the Engineer Dismantling and removal of temporary accommodation for the Engineer Handing over temporary accommodation to the Employer

sum month sum

sum

II

1.

different types

B.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.02

Item description and unit shall be:

Item description Temporary accommodation for the Engineer 1.02.1 Provision of temporary accommodation for the Engineer, principal office Servicing of temporary accommodation for the Engineer, principal office Dismantling and removal of temporary accommodation for the Engineer, principal office Handing over temporary accommodation to the Employer, principal office

Unit

sum

1.02.2

month

1.02.3

sum

1.02.4

sum

Item description extension

1.03

The item description of the items for provision of temporary accommodation for the Engineer under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) foundations, bases and hardstandings; excavation in any material and disposal of any material; backfilling with materials from any source and compaction; provision and erection of fences, notice boards, direction boards, vehicle access, parking areas and footways; connection of utilities, including payment of all necessary fees; office and laboratory supplies, furniture and equipment, and surveying instruments.

1.04

The item description of the items for servicing of temporary accommodation for the Engineer under this sub-heading shall be

20

extended in accordance with Preamble paragraph 1.8 and as follows: (a) maintenance of the temporary accommodation for the Engineer, including fences, notice boards, direction boards, vehicle access, parking areas, hardstandings and footways; charges for utilities; maintenance of office and laboratory furniture and equipment, and surveying instruments, and equivalent replacement of furniture, equipment and surveying instruments when the original furniture, equipment and surveying instruments are unserviceable; moving and re-establishing temporary accommodation; provision of clerical assistants, watchmen, chainmen, office attendants and other assistants to the Engineer as specified in the Contract except for those as may be separately paid for elsewhere in the Contract; replenishment of consumables.

(b) (c)

(d) (e)

(f) 1.05

The item description of the items for dismantling and removal of temporary accommodation for the Engineer under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) receiving back supplies, furniture, equipment and surveying instruments not required by the Employer; disconnecting and removing utilities, and sealing disused utilities; reinstatement.

1.06

The item description of the items for handing over temporary accommodation to the Employer under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) receiving back supplies, furniture, equipment and surveying instruments not required by the Employer.

Measurement

1.07

For interim payment purpose, payment for the items for provision of temporary accommodation for the Engineer under this sub-heading shall be made in two parts. The estimated value of the first part shall be calculated up to the limit of expenditure incurred and paid for by the Contractor and substantiated to the satisfaction of the Engineer which shall not exceed the amount inserted by the Contractor in the bill in respect of these items. The estimated value of the second part shall be calculated by multiplying the balance of the amount, if any, with the factor referred to in paragraph 1.01 above. Subject to Preamble paragraph 1.6, the measurement of the items for servicing of temporary accommodation for the Engineer under this sub-heading shall commence from the date and for the period when the temporary accommodation for the Engineer is provided for occupation and use.

1.08

21

Sub-heading
Notes C.

TEMPORARY TRAFFIC ARRANGEMENTS


Separate items shall be provided for under the sub-heading Temporary traffic arrangements in accordance with the following itemisation table:

Group

Feature

Unit

1.

Planning and implementation temporary traffic arrangements

of

sum

II

1. 2.

on land marine

D.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.09

Item description and unit shall be

Item description Temporary traffic arrangements 1.09.1 Planning and implementation of temporary traffic arrangements, on land Planning and implementation of temporary traffic arrangements, marine

Unit

sum

1.09.2

sum

Item description extension

1.10

The item description of the items under the sub-heading Temporary traffic arrangements shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) liaising and coordinating; any amendments to the temporary traffic arrangements, including those required for whatsoever reasons during the implementation of the temporary traffic arrangements on Site; disposal of any material; reinstatement.

(c) (d)

Sub-heading
Notes E.

SURETIES, SECURITY AND INSURANCES


Separate items, if specifically required by the Contract, shall be provided for under the sub-heading Sureties, security and insurances in accordance with the following itemisation table:

22

Group

Feature

Unit

1. 2. 3. 4.

Procurement of sureties or provision of security Procurement of third party insurance Procurement of care of the Works insurance Procurement of professional indemnity insurance

sum sum sum sum

F.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.11

Item description and unit shall be:

Item description Sureties, security and insurances 1.11.1 1.11.2 1.11.3 1.11.4 Measurement 1.12 Procurement of sureties or provision of security Procurement of third party insurance Procurement of care of the Works insurance Procurement of professional indemnity insurance

Unit

sum sum sum sum

For interim payment purpose, payment for the items under the sub-heading Sureties, security and insurances shall be made in two parts. The estimated value of the first part shall be calculated up to the limit of expenditure incurred and paid for by the Contractor and substantiated to the satisfaction of the Engineer which shall not exceed the amount inserted by the Contractor in the bill in respect of these items. The estimated value of the second part shall be calculated by multiplying the balance of the amount, if any, with the factor referred to in paragraph 1.01 above.

Sub-heading
Notes G.

TRANSPORT FOR THE USE OF THE ENGINEER


Separate items shall be provided for under the sub-heading Transport for the use of the Engineer in accordance with the following itemisation table:

23

Group

Feature

Unit

1.

2.

Provision, operation and maintenance of land transport for the use of the Engineer Provision, operation and maintenance of marine transport for the use of the Engineer

number-week

number-week

II

1.

different types of transport

H.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.13

Item description and unit shall be:

Item description Transport for the use of the Engineer 1.13.1 Provision, operation and maintenance of land transport for the use of the Engineer, multi-purpose vehicle, with seating capacity not less than 8 seats, engine capacity not less than 2300 c.c. Provision, operation and maintenance of marine transport for the use of the Engineer, passenger launch, with seating capacity not less than 25 seats, speed not less than 23 knots

Unit

number-week

1.13.2

number-week

Item description extension

1.14

The item description of the items for provision, operation and maintenance of land transport for the use of the Engineer under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) serviceable mobile telephone for the use of the vehicle driver, including all charges and fees to mobile telephone; parking, ferry and toll charges; driver.

1.15

The item description of the items for provision, operation and maintenance of marine transport for the use of the Engineer under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) serviceable mobile telephone for the use of the coxswain and crew, including all charges and fees to mobile telephone; mooring fees; coxswain and crew.

24

Measurement

1.16

The measurement of the items under the sub-heading Transport for the use of the Engineer shall be the summed periods of service of the land or marine transport provided for use by the Engineer including the date of its delivery to the Engineer but excluding the date for its removal.

Sub-heading

CONTRACT ENGINEER
I.

COMPUTER

FACILITIES

FOR

THE

Notes

Separate items shall be provided for under the sub-heading Contract Computer Facilities for the Engineer in accordance with the following itemisation table:

Group

Feature

Unit

1.

Provision and maintenance of Contract Computer Facilities for the Engineer

sum

II

1. 2.

installed in the temporary accommodation for the Engineer installed in locations as detailed in the Specification

III

1.

to be handed over to the Employer

J.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

1.17

Item description and unit shall be:

Item description Contract Computer Facilities for the Engineer 1.17.1 Provision and maintenance of Contract Computer Facilities for the Engineer, installed in the temporary accommodation for the Engineer, to be handed over to the Employer

Unit

sum

Item description 1.18 extension

The item description of the items under the sub-heading Contract Computer Facilities for the Engineer shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) replenishment of consumables; telecommunication and internet connection services; provision of training;

25

(d)

(e)

where the computer equipment (including hardware and software) is to be handed over to the Employer, documentation of assignment of ownership, warranty agreements, maintenance agreements and the extension of software licences beyond the period as directed by the Engineer; where the computer equipment (including hardware and software) is not to be handed over to the Employer, disconnection, repacking and removal.

Sub-heading
Notes K.

PHOTOGRAPHS
Separate items shall be provided for under the sub-heading Photographs in accordance with the following itemisation table:

Group

Feature

Unit

1.

Provision of progress photographs

month

II

1.

underwater

L.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.19

Item description and unit shall be:

Item description Photographs 1.19.1 1.19.2 Item description extension 1.20 Provision of progress photographs Provision of progress photographs, underwater

Unit

month month

The item description of the items for provision of progress photographs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) all accessories for storage of photographs.

Measurement

1.21

The items for provision of progress photographs under this sub-heading shall be measured for the month when progress photographs are provided in accordance with the Contract.

Sub-heading

HOARDINGS, SIGNBOARDS
M.

TEMPORARY

FENCING

AND

Notes

Separate items shall be provided for under the sub-heading

26

Hoardings, temporary fencing and signboards in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Provision, maintenance removal of hoardings Provision, maintenance removal of temporary fencing Provision, maintenance removal of signboards

and and and

metre metre number

II

1.

different types and/or sizes

N.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.22

Item description and unit shall be:

Item description Hoardings, temporary fencing and signboards 1.22.1 1.22.2 Provision, maintenance and removal of hoardings, type I Provision, maintenance and removal of temporary fencing, type II Provision, maintenance and removal of signboards, as shown on Drawing No(s). _____ [Drawing No(s). to be
stated in the bill items]

Unit

metre metre

1.22.3

number

Item description extension

1.23

The item description of the items under the sub-heading Hoardings, temporary fencing and signboards shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) foundations, footings and anchorages; excavation in any material and disposal of any material; backfilling with materials from any source and compaction; lighting, including associated electricity supply; entrances, gates and the like; reinstatement.

Measurement

1.24

The measurement of the items for provision, maintenance and removal of hoardings and provision, maintenance and removal of temporary fencing under this sub-heading shall be the length along their centreline alignment on plan, inclusive of gates and entrances. No account shall be taken in the quantity of any corrugations in profile, or other integral features.

27

1.25

Items for provision, maintenance and removal of hoardings and provision, maintenance and removal of temporary fencing under this sub-heading shall only be measured where shown on Drawings.

Sub-heading
Notes O.

AIR POLLUTION ABATEMENT


Separate items shall be provided for under the sub-heading Air pollution abatement in accordance with the following itemisation table:

Group

Feature

Unit

1.

2.

3.

4.

Provision, maintenance and removal of covering for dusty materials or air pollution abatement measures for dusty activities Provision, maintenance and removal of screens or enclosures for smoky activities Provision, operation, maintenance and removal of wheel washing system# Provision and maintenance of mechanical covers for dump trucks

sum

sum

sum

sum

P.

It should be noted that some items may not be applicable to all contracts, in particular the optional items as marked # . The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Q.

Item description and unit

1.26

Item description and unit shall be:

Item description Air pollution abatement 1.26.1 Provision, maintenance and removal of covering for dusty materials or air pollution abatement measures for dusty activities Provision, maintenance and removal of screens or enclosures for smoky activities Provision, operation, maintenance and removal of wheel washing system Provision and maintenance of mechanical covers for dump trucks

Unit

sum

1.26.2

sum

1.26.3

sum

1.26.4

sum

28

Item description extension

1.27

The item description of the item for provision, maintenance and removal of covering for dusty materials or air pollution abatement measures for dusty activities under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) disposal of any material; reinstatement.

1.28

The item description of the item for provision, maintenance and removal of screens or enclosures for smoky activities under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) disposal of any material; reinstatement.

1.29

The item description of the item for provision, operation, maintenance and removal of wheel washing system under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) supply and installation of the system at all entrance/exit points on Site including all the necessary piping, equipment and facilities for reuse and recycling of water with the system performance; connection of utilities, including payment of all necessary fees, and charges for utilities; modification, relocation and improvement of the system to suit the Site conditions or Works programme; reinstatement.

(b) (c) (d) Measurement 1.30

The measurement of the item for provision, maintenance and removal of covering for dusty materials or air pollution abatement measures for dusty activities under this sub-heading shall be made when the Engineer is satisfied that all such covering or air pollution abatement measures are provided on Site, properly maintained during the course of the Contract and subsequently removed upon completion of the Works. The measurement of the item for provision, maintenance and removal of screens or enclosures for smoky activities under this sub-heading shall be made when the Engineer is satisfied that such screens or enclosures are provided for all smoky activities on Site, properly maintained during the course of the Contract and subsequently removed upon completion of the Works. The measurement of the item for provision, operation, maintenance and removal of wheel washing system under this sub-heading shall be made when the Engineer is satisfied that the wheel washing system is provided and installed at all entrance/exit points on Site, properly operated and maintained during the course of the Contract and subsequently removed upon completion of the Works. The measurement of the item for provision and maintenance of mechanical covers for dump trucks under this sub-heading shall be made if all dump trucks used for the transportation of C&D materials into and off the Site are installed with mechanical covers.

1.31

1.32

1.33

29

Sub-heading
Notes R.

NOISE POLLUTION ABATEMENT


Separate items shall be provided for under the sub-heading Noise pollution abatement in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Provision, maintenance and removal of acoustic screens or enclosures Provision, maintenance and removal of noise abatement practices other than acoustic screens or enclosures

sum sum

S.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.34

Item description and unit shall be:

Item description Noise pollution abatement 1.34.1 Provision, maintenance and removal of acoustic screens or enclosures Provision, maintenance and removal of noise abatement practices other than acoustic screens or enclosures

Unit

sum

1.34.2

sum

Item description extension

1.35

The item description of the item for provision, maintenance and removal of acoustic screens or enclosures under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) disposal of any material; reinstatement.

1.36

The item description of the item for provision, maintenance and removal of noise abatement practices other than acoustic screens or enclosures under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) disposal of any material; reinstatement.

30

Measurement

1.37

The measurement of the item for provision, maintenance and removal of acoustic screens or enclosures under this sub-heading shall be made when the Engineer is satisfied that such acoustic screens or enclosures are provided on Site, properly maintained during the course of the Contract and subsequently removed upon completion of the Works. The measurement of the item for provision, maintenance and removal of noise abatement practices other than acoustic screens or enclosures under this sub-heading shall be made when the Engineer is satisfied that such noise abatement practices are provided on Site, properly maintained during the course of the Contract and subsequently removed upon completion of the Works.

1.38

Sub-heading
Notes T.

WASTEWATER POLLUTION ABATEMENT


Separate items shall be provided for under the sub-heading Wastewater pollution abatement in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Provision, maintenance and removal of wastewater collection system Provision, operation, maintenance and removal of wastewater # treatment facilities

sum sum

U.

It should be noted that some items may not be applicable to all contracts, in particular the optional items as marked # . The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

V.

Item description and unit

1.39

Item description and unit shall be:

Item description Wastewater pollution abatement 1.39.1 Provision, maintenance and removal of wastewater collection system Provision, operation, maintenance and removal of wastewater treatment facilities

Unit

sum

1.39.2

sum

Item description extension

1.40

The item description of the item for provision, maintenance and removal of wastewater collection system under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provide all necessary dykes, ditches, pipes and fittings of

31

(b)

(c) (d) (e) 1.41

sufficient capacity and extent for collecting surface run-off and wastewater from all locations of the Site to appropriate treatment facilities, including any approved modification to the Works; modification or improvement of the wastewater collection system to suit any change in the Site conditions or progress of the Works, or if the Engineer is dissatisfied with its performance; make all necessary alterations to the Works to suit the system; disposal of any material; reinstatement.

The item description of the item for provision, operation, maintenance and removal of wastewater treatment facilities under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) make all necessary alterations to the Works to suit the construction of the facilities; periodic removal of sediments accumulated in the facilities with proper treatment and disposal of any material; provision of all necessary chemicals, power and other resources for the proper operation of the facilities; taking samples of treated effluent; modification or improvement of the wastewater treatment facilities to suit any change in the Site conditions or progress of the Works, or if the Engineer is dissatisfied with its performance; reinstatement; patent fees or royalties.

(f) (g) Measurement 1.42

The measurement of the item for provision, maintenance and removal of wastewater collection system under this sub-heading shall be made when the Engineer is satisfied that the wastewater collection system is provided and installed on Site, properly maintained during the course of the Contract and subsequently removed upon completion of the Works. The measurement of the item for provision, operation, maintenance and removal of wastewater treatment facilities under this sub-heading shall be made when the Engineer is satisfied that the wastewater treatment facilities are provided and installed on Site, properly maintained during the course of the Contract and subsequently removed upon completion of the Works.

1.43

Sub-heading
Notes W.

WASTE MANAGEMENT
A separate item shall be provided for under the sub-heading Waste management in accordance with the following itemisation table:

Group

Feature

Unit

1.

Arrange and conduct on-site sorting of C&D materials

sum

X.

The Method of Measurement shall contain the item descriptions and

32

units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

1.44

Item description and unit shall be:

Item description Waste management 1.44.1 Item description extension 1.45 Arrange and conduct on-site sorting of C&D materials

Unit

sum

The item description of the item for arrange and conduct on-site sorting of C&D materials under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) delivery of sorted materials to designated locations or proper recycling outlets; arrangement of recycling contractors to collect the sorted reusable or recyclable materials; handling, storage and disposal of chemical wastes ; disposal of any material.

Measurement

1.46

The measurement of the item for arrange and conduct on-site sorting of C&D materials under this sub-heading shall be made when the Engineer is satisfied with the Contractors performance in sorting C&D materials on Site.

Sub-heading

MONITORING THE USE OF ULTRA LOW SULPHUR DIESEL


Y. A separate item shall be provided for under the sub-heading Monitoring the use of ultra low sulphur diesel in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1.

Arrange and conduct testing of fuel samples by laboratory

number

Z.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

1.47

Item description and unit shall be:

33

Item description Monitoring the use of ultra low sulphur diesel 1.47.1 Arrange and conduct testing of fuel samples by laboratory

Unit

number

Item description extension

1.48

The item description of the item for arrange and conduct testing of fuel samples by laboratory under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) collection and delivery of fuel samples.

Measurement

1.49

The measurement of the item for arrange and conduct testing of fuel samples by laboratory under this sub-heading shall be made for every fuel sample collected from the Constructional Plant or storage facilities on the Site and sent to a HOKLAS accredited laboratory, which name is agreed by the Engineer, for confirming that only ultra low sulphur diesel is used pursuant to the Contract. If the result of the test on a fuel sample shows that it is not ultra low sulphur diesel, no measurement shall be made for the item for arrange and conduct testing of fuel samples by laboratory under this sub-heading for such a fuel sample.
For project specific requirements on environmental monitoring and mitigation measures specified either under the Environmental Permit (EP) (for designated projects) or by the Environmental Protection Department (EPD) for non-designated projects, such requirements should be incorporated under a new PS section 26 for ease of reference. The items under the sub-headings Environmental mitigation measures and Environmental monitoring measures are the balance of the items for the environmental measures that are not separately measured under the above sub-headings Air pollution abatement, Noise pollution abatement, Wastewater pollution abatement, Waste management and Monitoring the use of ultra low sulphur diesel.

Notes

AA.

Sub-heading
Notes BB.

ENVIRONMENTAL MITIGATION MEASURES


Separate items shall be provided for under the sub-heading Environmental mitigation measures in accordance with the following itemisation table:

Group

Feature

Unit

1.

Provision, maintenance and removal of environmental mitigation measures which are not separately measured under any other items of work

sum

II

1. 2. 3.

air related measures noise related measures water quality related measures

34

CC.

The item description extension, such as the Environmental Specialists and the details of the stated advices and services as highlighted by *, shall be deleted or amended as appropriate for compatibility with the PS of the Contract. The list in Group II may be expanded to include other measures as considered appropriate. The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

DD.

EE.

Item description and unit

1.50

Item description and unit shall be:

Item description Environmental mitigation measures 1.50.1 Provision, maintenance and removal of environmental mitigation measures which are not separately measured under any other items of work, air related measures Provision, maintenance and removal of environmental mitigation measures which are not separately measured under any other items of work, noise related measures Provision, maintenance and removal of environmental mitigation measures which are not separately measured under any other items of work, water quality related measures

Unit

sum

1.50.2

sum

1.50.3

sum

Item description extension

1.51

The item description of the items under the sub-heading Environmental mitigation measures shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) procuring the services of Environmental Specialists*; provision, setting up, maintenance and removal of all equipment, facilities, instruments and the like for environmental mitigation measures; attending relevant meetings, including District Council meetings, by the Contractor/Environmental Specialists* as and when requested by the Engineer or the Engineers Representative; modifications to environmental mitigation measures from time to time as recommended by the Environmental Specialists* and/or as identified in environmental monitoring; setting up, operate and removal of the waste management facilities; replenishment of consumables; reinstatement.

(c)

(d)

(e) (f) (g)

35

Sub-heading
Notes FF.

ENVIRONMENTAL MONITORING MEASURES


Separate items shall be provided for under the sub-heading Environmental monitoring measures in accordance with the following itemisation table:

Group

Feature

Unit

1.

Provision, maintenance and removal of environmental monitoring measures which are not separately measured under any other items of work

sum

II

1. 2. 3.

air related measures noise related measures water quality related measures

GG.

The item description extension, such as the Environmental Specialists and the details of the stated advices and services as highlighted by *, shall be deleted or amended as appropriate for compatibility with the PS of the Contract. The list in Group II may be expanded to include other measures as considered appropriate. The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

HH.

II.

Item description and unit

1.52

Item description and unit shall be:

Item description Environmental monitoring measures 1.52.1 Provision, maintenance and removal of environmental monitoring measures which are not separately measured under any other items of work, air related measures Provision, maintenance and removal of environmental monitoring measures which are not separately measured under any other items of work, noise related measures Provision, maintenance and removal of environmental monitoring measures which are not separately measured under any other items of work, water quality related measures

Unit

sum

1.52.2

sum

1.52.3

sum

36

Item description extension

1.53

The item description of the items under the sub-heading Environmental monitoring measures shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) procuring the services of Environmental Specialists*; provision, maintenance of access to monitoring and control stations; maintaining the services of Environmental Specialists*; provision, setting up maintenance and removal of all equipment, facilities, instruments and the like for environmental monitoring measures; setting out and marking sampling locations; provision of training to personnel for operation of the equipment; sampling and testing in approved laboratory; modifications to environmental monitoring measures from time to time as recommended by the Environmental Specialists* and/or as identified in environmental monitoring; identifying deficiencies in environmental mitigation measures and proposing rectification measures for approval by the Engineer; attending relevant meetings, including District Council meetings, by the Contractor/Environmental Specialists* as and when requested by the Engineer or the Engineers Representative; setting up, operate and removal of the waste monitoring and recording measures; replenishment of consumables; reinstatement.

(e) (f) (g) (h)

(i)

(j)

(k) (l) (m)

Sub-heading
Notes JJ.

MOBILE TELEPHONE FOR THE ENGINEER


Separate items shall be provided for under the sub-heading Mobile telephone for the Engineer in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Provision and maintenance of mobile telephone set for the Engineer Provision of local mobile telephone services for the Engineer

number number-week

KK.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.54

Item description and unit shall be:

37

Item description Mobile telephone for the Engineer 1.54.1 Provision and maintenance of mobile telephone set for the Engineer Provision of local mobile telephone services for the Engineer

Unit

number

1.54.2

number-week

Item description extension

1.55

The item description of the item for provision and maintenance of mobile telephone set for the Engineer under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) all accessories; replacement of mobile telephone sets and their accessories when the originals are unavailable or unserviceable.

Measurement

1.56

The measurement of the item for provision and maintenance of mobile telephone set for the Engineer under this sub-heading shall be the number of mobile telephone set provided for use by the Engineer. The measurement of the item for provision of local mobile telephone services for the Engineer under this sub-heading shall be the summed periods of local mobile telephone services of the mobile telephone including the date of its delivery to the Engineer but excluding the date for its removal instructed by the Engineer.

1.57

Sub-heading
Notes LL.

DAILY CLEANING AND WEEKLY TIDYING


Separate items shall be provided for under the sub-heading Daily Cleaning and Weekly Tidying in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Daily Cleaning Weekly Tidying

day day

MM.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.58

Item description and unit shall be:

Item description Daily Cleaning and Weekly Tidying 1.58.1 Daily Cleaning

Unit

day

38

1.58.2 Measurement 1.59

Weekly Tidying

day

The measurement of the item for Daily Cleaning under this sub-heading shall be made after cleaning and tidying up work of the Site for a Cleaning Day is carried out satisfactorily in accordance with the PS. The Contractor shall not be entitled to any payment for the item for Daily Cleaning under this sub-heading on a Cleaning Day if the performance of the Contractor on cleanliness and tidiness for any part of the Site for that Cleaning Day is not carried out to the satisfaction of the Engineer or the Engineers Representative. The Contractor shall not be entitled to any payment for the item for Daily Cleaning under this sub-heading for more than one day for the cleaning and tidying up work carried out by the Contractor for one Cleaning Day. The rate inserted by the Contractor against the item for Daily Cleaning under this sub-heading on a Cleaning Day shall not be adjusted for any difference in the actual size of the area to be cleaned from day to day during the progress of the Works as necessitated by the Contract on any Cleaning Day. The measurement of the item for Weekly Tidying under this sub-heading shall be made after the overall cleaning and tidying up work of the Site for a Cleaning Week Day is carried out satisfactorily in accordance with the PS. The Contractor shall not be entitled to any payment for the item for Weekly Tidying under this sub-heading on a Cleaning Week Day if the Contractor fails to rectify the identified defects pursuant to the Contract to the satisfaction of the Engineer or the Engineers Representative before the end of the day (which is not a General Holiday) following the Cleaning Week Day. The Contractor shall not be entitled to any payment for the item for Weekly Tidying under this sub-heading for more than one day for the cleaning and tidying up work and/or defects rectification carried out by the Contractor for one Cleaning Week Day. The rate inserted by the Contractor against the item for Weekly Tidying under this sub-heading on a Cleaning Week Day shall not be adjusted for any difference in the actual size of the area to be cleaned and tidied on any Cleaning Day or Cleaning Week Day.

1.60

1.61

1.62

1.63

1.64

1.65

1.66

Sub-heading
Notes NN.

CONTRACTORS OVERHEADS
Separate items shall be provided for under the sub-heading Contractors overheads in accordance with the following itemisation table:

39

Group

Feature

Unit

1.

2.

3.

4.

5. 6. 7. 8.

9.

Provision of Contractors personnel working on Site specified in the Contract which are not separately measured under any other items of work Provision of Contractors personnel working on Site not specified in the Contract Provision, operation, maintenance and removal of plant and equipment which are not covered or separately measured under any other items of work Procurement of insurances which are not covered or separately measured under any other items of work Provision of temporary accommodation for the Contractor Servicing of temporary accommodation for the Contractor Removal of temporary accommodation for the Contractor Allowance for all the Contractors overheads on Site not covered or separately measured under any other items of work Allowance for all the Contractors overheads off Site

month

month

month

month

sum month sum month

month

OO.

The number of months to be inserted under the Quantity column in the bill within the Bills of Quantities for the time based items under this sub-heading shall be the original time for completion of the Works plus a reasonable allowance of extension of time that may be granted due to causes relating to direct actions of the Employer/Engineer (see Clause J in Part I of this Handbook) and the Maintenance Period. The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

PP.

Item description and unit

1.67

Item description and unit shall be:

Item description Contractors overheads 1.67.1 Provision of Contractors personnel working on Site specified in the Contract which are not separately measured under any other items of work

Unit

month

40

1.67.2

Provision of Contractors personnel working on Site not specified in the Contract Provision, operation, maintenance and removal of plant and equipment which are not covered or separately measured under any other items of work Procurement of insurances which are not covered or separately measured under any other items of work Provision of temporary accommodation for the Contractor Servicing of temporary accommodation for the Contractor Removal of temporary accommodation for the Contractor Allowance for all the Contractors overheads on Site not covered or separately measured under any other items of work Allowance for all the Contractors overheads off Site

month

1.67.3

month

1.67.4

month

1.67.5

sum

1.67.6

month

1.67.7

sum

1.67.8

month

1.67.9 Item description extension 1.68

month

The item description of the item for provision, operation, maintenance and removal of plant and equipment which are not covered or separately measured under any other items of work under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provision, operation, maintenance and removal of all plant and equipment on the Site in connection with the execution of the Works, including without limitation surveying instruments, site vehicles, site boats, generators, small tools, machinery and equipment whether specified in the Contract or not.

1.69

The item description of the item for provision of temporary accommodation for the Contractor under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provision and erection of everything required by the Contractor including offices, sheds stores, mess rooms, canteens, pantries, latrines, workers accommodation and the like; provision of welfare facilities for workers employed on the Works, irrespective of whether they are in the employment of the Contractor or his sub-contractors.

(b)

1.70

The item description of the item for servicing of temporary accommodation for the Contractor under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) moving and re-establishing temporary accommodation; maintenance of welfare facilities for workers employed on the Works;

41

(c)

replenishing the insufficiency of provision of welfare facilities to meet the specified requirements as identified in the Site Safety and Environmental Management Committee meetings.

1.71

The item description of the item for removal of temporary accommodation for the Contractor under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) disconnecting and removing utilities, and sealing disused utilities; removal of welfare facilities for workers employed on the Works; reinstatement.

Measurement

1.72

Subject to Preamble paragraph 1.7, the measurement of the time based items under the sub-heading Contractors overheads, except the item for servicing of temporary accommodation for the Contractor, shall commence from the date for commencement of the Works until the last day of the Maintenance Period (or where there is more than one such Maintenance Period, until the last day of the last Maintenance Period other than the Maintenance Periods for Establishment Works and Aftercare to Old and Valuable Trees*).
* The expression other than the Maintenance Periods for Establishment Works and Aftercare to Old and Valuable Trees in paragraph 1.72 assumes that Establishment Works and/or Aftercare to Old and Valuable Trees form a separate Section or separate Sections of the Works. If the Contract does not contain any Section of Works which comprises Establishment Works only or any Section of Works which comprises Aftercare to Old and Valuable Trees only, such expression shall be deleted as appropriate.

Notes

QQ.

1.73

For interim payment purpose, payment for the item for provision of temporary accommodation for the Contractor under this sub-heading shall be made in two parts. The estimated value of the first part shall be calculated up to the limit of expenditure incurred and paid for by the Contractor and substantiated to the satisfaction of the Engineer which shall not exceed the amount inserted by the Contractor in the bill in respect of this item. The estimated value of the second part shall be calculated by multiplying the balance of the amount, if any, with the factor referred to in paragraph 1.01 above. Subject to Preamble paragraph 1.7, the measurement of the item for servicing of temporary accommodation for the Contractor under this sub-heading shall commence from the date when the temporary accommodation for the Contractor is provided for use on Site and the welfare facilities for workers employed on the Works as specified in the Contract are provided until the last day of the Maintenance Period (or where there is more than one such Maintenance Period, until the last day of the last Maintenance Period other than the Maintenance Periods for Establishment Works and Aftercare to Old and Valuable Trees**).
** The expression other than the Maintenance Periods for Establishment Works and Aftercare to Old and Valuable Trees in paragraph 1.74 assumes that Establishment Works and/or Aftercare to Old and Valuable Trees form a separate Section or separate Sections of the Works. If the Contract does not contain any Section

1.74

Notes

RR.

42

of Works which comprises Establishment Works only or any Section of Works which comprises Aftercare to Old and Valuable Trees only, such expression shall be deleted as appropriate.

Sub-heading
Notes SS.

GENERAL SITE CLEARANCE OF THE SITE


A separate item shall be provided for under the sub-heading General site clearance of the Site in accordance with the following itemisation table:

Group

Feature

Unit

1.

General site clearance of the Site

sum

TT.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

1.75

Item description and unit shall be:

Item description General site clearance of the Site 1.75.1 Item description extension 1.76 General site clearance of the Site

Unit

sum

The item description of the item for general site clearance of the Site under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) demolition, breaking up and removal of signs, lamp standards, fences, walls and disused ducts, pipes, sewers or drains above ground level and superficial obstructions affected by the Works; felling of trees, grubbing up stumps and roots, filling stump and root holes with fine fill material and compacting; removal of branches from trees which are not to be felled and treating cut surfaces with wound sealant; uprooting of bushes and hedges; disposal of any material; disconnecting and sealing utilities, and recording the position of sealed utilities; making good severed ends of existing fences, walls, utilities and other items, including fixing posts at ends of strained fences and restraining fences; making good damage to buildings and other surfaces caused by the removal of signs, fences, lamp standards and the like.

(b) (c) (d) (e) (f) (g)

(h)

43

Measurement

1.77

For interim payment purpose, payment for the item for general site clearance of the Site under this sub-heading shall be made in accordance with the proportion of site clearance carried out.

Sub-heading

SITE MANAGEMENT PLAN FOR TRIP TICKET SYSTEM


UU. Separate items shall be provided for under the sub-heading Site management plan for trip ticket system in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2.

Complete and distribute site management plan for trip ticket system Update and implement site management plan for trip ticket system

sum month

VV.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

1.78

Item description and unit shall be:

Item description Site management plan for trip ticket system 1.78.1 Complete and distribute site management plan for trip ticket system Update and implement site management plan for trip ticket system

Unit

sum

1.78.2

month

Item description extension

1.79

The item description of the item for update and implement site management plan for trip ticket system under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) implement measures to ensure that trucks carrying C&D materials from the Site proceed to the disposal grounds; devise and implement appropriate measures to ensure that the sorted recyclable materials, which are sorted on the Site for the purpose of recycling such materials, are delivered to a proper recycling outlet for processing; compile, submit and maintain disposal records; investigate and report on incidents of improper disposal and non-compliance with the trip ticket system; monitor performance of trip ticket system and implement improvement measures; implement additional measures to control disposal of C&D

(c) (d) (e) (f)

44

(g)

materials to alternative disposal ground which the Engineer has approved; distribute revisions of the site management plan for trip ticket system to all relevant parties including the truck drivers engaged in delivery of C&D materials for disposal.

Measurement

1.80

The item for complete and distribute site management plan for trip ticket system under this sub-heading shall be measured when the Engineer approves the site management plan for trip ticket system. The measurement of the item for update and implement site management plan for trip ticket system under this sub-heading shall be the period of time commencing from the date of approval by the Engineer of the site management plan for trip ticket system until all C&D materials have been removed from the Site, or an earlier or later date notified by the Engineer.

1.81

45

SECTION 2
Heading

GROUND INVESTIGATION
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. Reference should be made to paragraph 2.2(e) in Part II of this Handbook for the definition of rock for the purposes of this section 2.

Notes

ii

Sub-heading
Notes A.

DRILLING RIGS FOR GROUND INVESTIGATION


Separate items shall be provided for under the sub-heading Drilling rigs for ground investigation in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Provision and removal of drilling rigs Setting up drilling rigs Standing time for drilling rigs

sum number hour

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

2.01

Item description and unit shall be:

Item description Drilling rigs for ground investigation 2.01.1 2.01.2 2.01.3 Item description extension 2.02 Provision and removal of drilling rigs Setting up drilling rigs Standing time for drilling rigs

Unit

sum number hour

The item description of the items for provision and removal of drilling rigs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provision and removal of all ancillary drilling equipment including but not limited to pontoons, barges and the like.

46

2.03

The item description of the items for setting up drilling rigs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) moving drilling rigs and all ancillary drilling equipment set up between drillhole locations; relocation of drillhole locations as instructed by the Engineer; site clearance and reinstatement.

2.04

The item description of the items for standing time for drilling rigs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) idling of personnel, drilling rigs and all ancillary drilling equipment including but not limited to pontoons, barges and the like.

Measurement

2.05

The measurement of the items for provision and removal of drilling rigs under this sub-heading shall be for bringing drilling rigs and all ancillary drilling equipment to the Site and their subsequent removal off the Site. The measurement of the items for setting up drilling rigs under this sub-heading shall correspond to the number of drillholes as shown on Drawings or ordered by the Engineer. The measurement of the items for standing time for drilling rigs under this sub-heading shall be the hours for each drilling rig standing idle during normal working hours, as defined in section 27 (Daywork) of the Method of Measurement, from the time the Contractor notifies the Engineer that he is awaiting instructions and gives details of the circumstances until the time such instructions are issued. In the case of marine work, the time taken to move the marine plant to the nearest typhoon shelter when the tropical cyclone warning signal No. 3 or above is hoisted and the time taken to return to Site will be measured as standing time for drilling rigs.

2.06

2.07

2.08

Sub-heading
Notes C.

DRILLING FOR GROUND INVESTIGATION


Separate items shall be provided for under the sub-heading Drilling for ground investigation in accordance with the following itemisation table:

Group

Feature

Unit

1.

Drill holes

metre

II

1.

different diameters

47

Group

Feature

Unit

III

1. 2. 3. 4. 5.

vertically downwards downwards at an angle 0- 45 to the vertical horizontally or downwards at an angle less than 45 to the horizontal upwards at an angle 0 - 45 to the horizontal upwards at an angle less than 45 to the vertical

IV

1. 2. 3.

in materials other than rock or artificial hard materials in rock in artificial hard materials

1. 2.

depth not exceeding 25.00 m depth exceeding 25.00 m but not exceeding 50.00 m and so on in steps of 25.00 m

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

2.09

Item description and unit shall be:

Item description Drilling for ground investigation 2.09.1 Drill holes, 150 mm diameter vertically downwards in materials other than rock or artificial hard materials, depth not exceeding 25.00 m

Unit

metre

Item description extension

2.10

The item description of the items for drill holes under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) filling drillholes, reinstatement and marking position; disposal of any material; taking samples from drillholes; photographs.

48

Measurement

2.11

The measurement of the items for drill holes under this sub-heading shall be the drilled length of the drillholes within the depth range. The depth of drilling shall be measured from the start of the depth range to the end of the hole or the end of the depth range, whichever comes first. For example, for a drillhole of 40.00 m in length, it shall be measured under two depth ranges with the first 25.00 m and the remaining 15.00 m measured separately. If the measured drilled length of a drillhole exceeds the depth ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3). If drilling in rock is encountered and corresponding items for drill holes in rock are not provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3). If drilling in artificial hard materials is encountered and corresponding items for drill holes in artificial hard materials are not provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

2.12

2.13

2.14

Sub-heading

TRIAL PITS, TRIAL TRENCHES AND INSPECTION PITS


E. Separate items shall be provided for under the sub-heading Trial pits, trial trenches and inspection pits in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2. 3. 4. 5.

Excavation of trial pits Excavation of trial trenches Excavation of inspection pits Extra over for excavation in rock Extra over for excavation in artificial hard materials

cubic metre cubic metre cubic metre cubic metre cubic metre

II

1. 2.

maximum depth not exceeding 3.00 m maximum depth exceeding 3.00 m but not exceeding 6.00 m and so on in steps of 3.00 m

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

2.15

Item description and unit shall be:

49

Item description Trial pits, trial trenches and inspection pits 2.15.1 Excavation of trial pits, maximum depth not exceeding 3.00 m Excavation of trial trenches, maximum depth exceeding 3.00 m but not exceeding 6.00 m Excavation of inspection pits, maximum depth exceeding 6.00 m but not exceeding 9.00 m Extra over for excavation in rock Extra over for excavation in artificial hard materials

Unit

cubic metre

2.15.2

cubic metre

2.15.3

cubic metre

2.15.4 2.15.5 Item description extension 2.16

cubic metre cubic metre

The item description of the items for excavation of trial pits, excavation of trial trenches and excavation of inspection pits under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) disposal of any material; temporary fencing; backfilling with materials from any source and compaction; reinstatement; photographs.

Measurement

2.17

The total volume of any one trial pit, trial trench or inspection pit shall be assigned to the item with a depth range within which its maximum depth falls. Measurement of the items for excavation of trial pits, excavation of trial trenches and excavation of inspection pits under this sub-heading shall only be made for trial pits, trial trenches and inspection pits excavated on the specific instruction of the Engineer, and not for pits or trenches excavated in meeting the Contractor's obligations to establish the locations of existing utilities and underground features. If the measured depth of excavation of a trial pit, trial trench or inspection pit is outside the depth ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3). If rock is encountered during the excavation in trial pit, trial trench or inspection pit and items for extra over for excavation in rock under this sub-heading are not provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3). If artificial hard materials are encountered during the excavation in trial pit, trial trench or inspection pit and items for extra over for excavation in artificial hard materials under this sub-heading are not provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

2.18

2.19

2.20

50

Sub-heading
Notes G.

SAMPLING FOR GROUND INVESTIGATION


Separate items shall be provided for under the sub-heading Sampling for ground investigation in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Take samples Take rock cores

number metre

II

1. 2.

different types different sizes

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

2.21

Item description and unit shall be:

Item description Sampling for ground investigation 2.21.1 2.21.2 Item description extension 2.22 Take samples, soil sample from trial trenches Take rock cores, 100mm diameter from drillhole

Unit

number metre

The item description of the items under the sub-heading Sampling for ground investigation shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) containers for samples and core boxes; photographs; storage and delivery of samples and cores.

Measurement

2.23

The measurement of the items for take samples under this sub-heading shall be the number of samples ordered by the Engineer and of length or size not less than specified or ordered.

2.24

The measurement of the items for take rock cores under this sub-heading shall be the length of the specified core recovered and measured in the core box.

Sub-heading
Notes I.

IN-SITU TESTS
Separate items shall be provided for under the sub-heading In-situ

51

tests in accordance with the following itemisation table:

Group

Feature

Unit

1.

Arrange and conduct in-situ tests

number

II

1.

different types

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

2.25

Item description and unit shall be:

Item description In-situ tests 2.25.1 Arrange and conduct penetration test in-situ tests, standard

Unit

number

2.25.2 2.25.3 Item description extension 2.26

Arrange and conduct in-situ tests, vane shear test Arrange and conduct in-situ tests, in-situ density test

number number

The item description of the items under the sub-heading In-situ tests shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) testing equipment, moving between hole locations and removing on completion. shall

Measurement

2.27

The measurement of the items under the sub-heading In-situ tests be the number of in-situ tests carried out as ordered by the Engineer.

Sub-heading
Notes K.

GEOTECHNICAL INSTRUMENTATION
Separate items shall be provided for under the sub-heading Geotechnical instrumentation in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply, install and geotechnical instrument

maintain

number

52

Group

Feature

Unit

II

1.

different types

L.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

2.28

Item description and unit shall be:

Item description Geotechnical instrumentation 2.28.1 Supply, install and maintain geotechnical instrument, settlement plates

Unit

number

Item description extension

2.29

The item description of the items under the sub-heading Geotechnical instrumentation shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; protective caps, covers and the like; tubes and cables for instruments; grouting; monitoring and recording readings; reinstatement.

Measurement

2.30

The measurement of the items under the sub-heading Geotechnical instrumentation shall be the number of geotechnical instrumentation installed as ordered by the Engineer.

Sub-heading
Notes M.

LABORATORY TESTS
Separate items shall be provided for under the sub-heading Laboratory tests in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Arrange and conduct laboratory tests Extra over for testing time in carrying out laboratory tests

number hour

II

1.

different types

53

N.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

2.31

Item description and unit shall be:

Item description Laboratory tests 2.31.1 Arrange and conduct laboratory tests, particle size distribution test Extra over for testing time in carrying out laboratory tests

Unit

number

2.31.2

hour

Item description extension

2.32

The item description of the items for arrange and conduct laboratory tests under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) attendance and supervision of testing at approved laboratories; selecting, extruding and preparing specimens from the supplied samples, as directed by the Engineer; photographs; retaining samples until directed otherwise by the Engineer; disposal of samples or transport samples to the Employers store as directed by the Engineer.

Measurement

2.33

The measurement of the items for arrange and conduct laboratory tests under this sub-heading shall be the number of tests ordered by the Engineer. The measurement of the items for extra over for testing time in carrying out laboratory tests under this sub-heading shall be the testing time exceeding: (i) (ii) 60 hours for a single-stage triaxial compression test on soil; 144 hours for three stage (multi-stage) test on the same specimen.

2.34

The commencement time for a single-stage or multi-stage test shall be the time at which consolidation is commenced.

Sub-heading
Notes O.

REPORTS FOR GROUND INVESTIGATION


Separate items shall be provided for under the sub-heading Reports for ground investigation in accordance with the following itemisation table:

54

Group

Feature

Unit

1. 2.

Submission of draft final reports Submission of final reports

sum sum

P.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

2.35

Item description and unit shall be:

Item description Reports for ground investigation 2.35.1 2.35.2 Item description extension 2.36 Submission of draft final reports Submission of final reports

Unit

sum sum

The item description of the items under the sub-heading Reports for ground investigation shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) report boxes and folders.

55

SECTION 3
Heading

SITE PREPARATION WORKS


i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Measurement

3.01

The taking up of existing carriageways, pavings and kerbs, other than those required to be set aside for re-laying or removing to store, and the demolition of underground structures or foundations (including in the case of demolition of buildings or structures, work below and including ground slabs), if any, shall be measured in accordance with the Preamble and section 7 (Earthworks) of the Method of Measurement and shall not be measured under this section 3.

Sub-heading
Notes A.

DEMOLITION AND REMOVAL WORKS


Separate items shall be provided for under the sub-heading Demolition and removal works in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Demolition of buildings or structures Removal of disused sewers, drains or ducts

sum metre

II

1. 2.

individual or groups of buildings or structures different diameters of sewer, drain or duct

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

3.02

Item description and unit shall be:

Item description Demolition and removal works 3.02.1 Demolition of buildings, pumping station No. 1 as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

Unit

sum

56

3.02.2

Demolition of structures, wing wall and head wall of the drainage structure of the existing 2550 mm diameter drain pipe as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

sum

3.02.3

Removal of disused sewers, 150 mm diameter from MH1 to MH3 as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

metre

3.02.4

Removal of disused ducts, 2 x 100 mm diameter from MH7 to MH8 as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

metre

Item description extension

3.03

The item description of the items for demolition of buildings or structures under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) carrying out surveys of buildings or structures prior to demolition; disconnecting and sealing utilities, and marking and recording the position of sealed utilities, including liaising with relevant authorities; excavation in any material and disposal of any material; protecting areas adjacent to demolition works from damage resulting from such demolition; making good damage to buildings, structures and pavements caused by the removal of adjoining buildings or structures; reinstatement.

3.04

The item description of the items for removal of disused sewers, drains or ducts under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) excavation in any material and disposal of any material; removal of any bedding, haunch or surround of the sewers, drains or ducts and associated manholes, catchpits, gullies, drawpits and the like; backfilling with materials from any source and compaction; reinstatement; sealing the ends of sewers, drains or ducts.

Measurement

3.05 3.06

The items for demolition of buildings or structures under this sub-heading shall exclude the removal of any ground slab and foundation. The items for removal of disused sewers, drains or ducts under this sub-heading shall be measured only where the disused sewers, drains or ducts are required to be removed as shown on Drawings.

Sub-heading

TAKE UP AND STORE EXISTING PAVINGS OR OTHER STATED ITEMS


C. Separate items shall be provided for under the sub-heading Take up and store existing pavings or other stated items in accordance with the following itemisation table:

Notes

57

Group

Feature

Unit

1. 2. 3. 4. 5.

Take up and store paved areas Take up and store fencing Take up and store pipes Take up and store lamp standards Take up and store stated materials, street furniture or fittings

square metre metre metre number number

II

1. 2.

different types different types and diameters of pipe

III

1. 2.

deliver to different locations re-erect with foundations or base

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

3.07

Item description and unit shall be: Item description Take up and store existing pavings or other stated items Unit

3.07.1

Take up and store paved areas, precast concrete paving blocks, deliver to the Employers store as instructed by the Engineer Take up and store fencing, chain link fencing, re-erect with foundations or base Take up and store pipes, 150 mm diameter DI pipe Take up and store lamp standards, re-erect with foundations or base Take up and store traffic sign posts with attached sign faces, re-erect with foundations or base

square metre

3.07.2 3.07.3 3.07.4 3.07.5 Item description extension 3.08

metre metre number number

The item description of the items under the sub-heading Take up and store existing pavings or other stated items shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) excavation in any material and disposal of any material; making good any damage and replacing losses and breakages; reinstatement; disconnecting and sealing utilities, and recording the position of sealed utilities; making good damage to buildings and other surfaces caused by

58

the removal of signs, fences, lamp standards and the like. Measurement 3.09 The items under the sub-heading Take up and store existing pavings or other stated items shall be measured only where such pavings or items are required to be taken up and stored as shown on Drawings.

59

SECTION 4
Heading

FENCING AND GATES


i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. Temporary fencing which is to be removed by the Contractor should be included as items under section 1 (Preliminaries). Fencing which does not require removal by the Contractor should be included as items under this section 4.

Notes

ii

Sub-heading

FENCING, HANDRAILING, PEDESTRIAN PARAPETS AND GATES


A. Separate items shall be provided for under the sub-heading Fencing, handrailing, pedestrian parapets and gates in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2. 3. 4.

Supply and install fencing Supply and install handrailing Supply and install pedestrian parapets Supply and install gates

metre metre metre number

II

1.

different types, sizes and/or materials

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

4.01

Item description and unit shall be:

Item description Fencing, handrailing, pedestrian parapets and gates 4.01.1 Supply and install fencing, chain link fence, 1500 mm high as shown on Drawing No(s). _____ [Drawing
No(s). to be stated in the bill items]

Unit

metre

60

4.01.2

Supply and install handrailing, tubular with mesh infilling, 900 mm high as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

metre

4.01.3

Supply and install pedestrian parapets, type 1 as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], not exceeding 500 mm high Supply and install pedestrian parapets, type 1 as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], not exceeding 1300 mm high Supply and install gates, emergency crash gate, 1100 mm high, as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

metre

4.01.4

metre

4.01.5

number

Item description extension

4.02

The item description of the items under the sub-heading Fencing, handrailing, pedestrian parapets and gates shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) foundations, footings and anchorages, including concrete, reinforcement, formwork and granular materials; excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas; jointing to existing fences, handrailing, pedestrian parapets, gates and the like; protective treatment and painting; trimming or filling ground to maintain uniform clearance between bottom of fence or gate at entrances and ground.

Measurement

4.03

The measurement of the items for supply and install fencing, supply and install handrailing and supply and install pedestrian parapets under this sub-heading shall be the length along their centreline alignment on plan. No account shall be taken in the quantity of any corrugations in profile, or other integral features. Spacing between individual units comprising a length of railing or barrier shall be included within the overall length measured.

4.04

61

SECTION 5
Heading

DRAINAGE AND DUCTS


i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. No separate items are provided for excavation of soft spots and filling of soft spots and other voids under this section 5. Where soft spots are encountered below the formation level during excavation for works measured under this section 5, they should be dealt with as variations.

Notes

ii

Measurement

5.01

The items of work under this section 5 shall be deemed to include concrete, reinforcement, formwork and steelwork. Headwall, outfall works and box culverts, if any, shall be measured in accordance with the Preamble and other relevant sections of the Method of Measurement and shall not be measured under this section 5. Sewers, drains, piped culverts, ducts and trench drains designed for use under pressure, if any, shall be measured in accordance with the Preamble and section 6 (Pipework) of the Method of Measurement and shall not be measured under this section 5.

5.02

5.03

Sub-heading

SEWERS, DRAINS, PIPED CULVERTS, DUCTS AND TRENCH DRAINS OTHER THAN BY TRENCHLESS METHOD
A. Separate items shall be provided for under the sub-heading Sewers, drains, piped culverts, ducts and trench drains other than by trenchless method in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2. 3. 4.

Supply and lay sewers, drains or piped culverts Supply and lay sewers or drains, in group of pipes Supply and lay ducts, different numbers of ways Supply and lay trench drains

metre metre metre metre

II

1.

different types of material

III

1.

different diameters

62

Group

Feature

Unit

IV

1.

different types of bedding, surround, haunch or filling

1. 2.

3.

in trench, depth not exceeding 1.50 m in trench, depth exceeding 1.50 m but not exceeding 2.50 m and so on in steps of 1.00 m suspended on different types of support

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.04

Item description and unit shall be:

Item description Sewers, drains, piped culverts, ducts and trench drains other than by trenchless method 5.04.1 Supply and lay sewers, vitrified clay pipe, 225 mm diameter, type F bedding, in trench, depth not exceeding 1.50 m Supply and lay drains, precast concrete pipe, 225 mm diameter, concrete surround type I as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], in trench, depth exceeding 1.50 m but not exceeding 2.50 m Supply and lay drains, precast concrete pipe, in group of 2 pipes, 225 mm diameter each, concrete surround as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], in trench, depth exceeding 2.50 m but not exceeding 3.50 m Supply and lay ducts, UPVC grade ___, 3 x 100 mm diameter, with general fill material backfill, in trench, depth not exceeding 1.50 m

Unit

metre

5.04.2

metre

5.04.3

metre

5.04.4

metre

Item description extension

5.05

The item description of the items under the sub-heading Sewers, drains, piped culverts, ducts and trench drains other than by trenchless method shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) excavation in any material except for rock and artificial hard

63

(b) (c) (d)

materials and disposal of any material; backfilling with materials from any source and compaction; filter materials; reinstatement of existing ground except for reinstatement of carriageways, footways and paved areas.

Measurement

5.06

The measurement of the items under the sub-heading Sewers, drains, piped culverts, ducts and trench drains other than by trenchless method shall be the summed lengths of the categories described within each depth range. Group of pipes or ducts of different number of ways shall be measured once only along the centreline of the pipe group or ducts. Such centreline shall be the line along the mid-point of the two outer most edges of the pipe groups or ducts on plan. Lengths shall be measured along the centreline between the adjacent terminations as defined below: (i) (ii) (iii) (iv) the external face of manhole or other chamber, gully or headwall; the intersection of the centreline of the pipes or pipe groups at pipe junctions; the position of the termination as shown on Drawings; the point at which the depth range changes.

5.07

Depths of the items under the sub-heading Sewers, drains, piped culverts and ducts and trench drains other than by trenchless method shall be the vertical measurement between the invert of the pipe or duct (the invert of group of pipes or ducts of different number of ways shall be the invert of the lowest pipe or duct) and the following: (i) where the invert level is below the existing ground surface - the existing ground surface, except that where the earthworks final surface is below the existing ground surface the measurement shall be taken to the earthworks final surface; where the invert is at or above the existing ground surface - the earthworks final surface; where a length of pipeline in or beneath areas of fill is not permitted to be constructed until a specified minimum level of cover is obtained then notwithstanding sub-paragraphs (i) and (ii) above - to the specified minimum level of cover or the earthworks final surface whichever is the lower.

(ii) (iii)

5.08

If the measured depth of a sewer, pipe culvert, duct or trench drain laid is outside the depth ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

Sub-heading

CONNECTIONS TO EXISTING SEWERS, DRAINS, DUCTS, TRENCH DRAINS, CULVERTS, WATERCOURSES, MANHOLES, STATED CHAMBERS AND DRAWPITS
C. Separate items shall be provided for under the sub-heading Connections to existing sewers, drains, ducts, trench drains, culverts, watercourses, manholes, stated chambers and drawpits in accordance with the following itemisation table:

Notes

64

Group

Feature

Unit

1.

Connections to existing sewers, drains, ducts, trench drains, culverts, watercourses, manholes, stated chambers and drawpits

number

II

1.

different types

III

1.

different diameters

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.09

Item description and unit shall be: Item description Connections to existing sewers, drains, ducts, trench drains, culverts, watercourses, manholes, stated chambers and drawpits Unit

5.09.1

Connections to existing sewers, precast concrete pipe, 225 mm diameter Connections to existing ducts, vitrified clay pipe, 150 mm diameter

number

5.09.2

number

Item description extension

5.10

The item description of the items under the sub-heading Connections to existing sewers, drains, ducts, trench drains, culverts, watercourses, manholes, stated chambers and drawpits shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) excavation in any material except for rock and artificial hard materials and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground except for reinstatement of carriageways, footways and paved areas.

Sub-heading
Notes E.

SEWERS AND DRAINS BY TRENCHLESS METHOD


Separate items shall be provided for under the sub-heading Sewers and drains by trenchless method in accordance with the following itemisation table:

65

Group

Feature

Unit

1. 2.

Establishment for trenchless construction Supply and lay sewers or drains by trenchless method

sum metre

II

1.

different types of material

III

1.

different diameters

IV

1.

different reference manhole or chamber

numbers

of

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.11

Item description and unit shall be:

Item description Sewers and drains by trenchless method 5.11.1 Establishment for trenchless construction, precast concrete pipe, 300 mm diameter, between manholes reference ___ and ___ Supply and lay sewers by trenchless method, precast concrete pipe, 300 mm diameter, complying with BS ___ and PS Clause ___, between manholes reference ___ and ___

Unit

sum

5.11.2

metre

Item description extension

5.12

The item description of the items for establishment for trenchless construction under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) setting up, moving and removal of all plant and equipment set up for trenchless construction; construction of access tunnels, access shafts, working pits, thrust pits, reception pits and thrust blocks; excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas; measures to control ground movements and settlement of adjacent structures and utilities, including but not limited to

66

grouting. 5.13 The item description of the items for supply and lay sewers or drains by trenchless method under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; filter materials; reinstatement of existing ground including carriageways, footways and paved areas; grouting of over-break and cavities, sealing gaps between pipe shafts or lining and the pipelines; measures to control ground movements and settlement of adjacent structures and utilities, including but not limited to grouting; CCTV confirmatory inspections of pipelines and reports.

(g) Measurement 5.14

The items for supply and lay sewers or drains by trenchless method under this sub-heading shall be measured along the centreline of the sewers or drains between the external face of manholes or other chambers.

Sub-heading
Notes G.

PENSTOCKS AND VALVES


Separate items shall be provided for under the sub-heading Penstocks and valves in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Supply and install penstocks Supply and install valves

number number

II

1.

different types

III

1.

different diameters

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.15

Item description and unit shall be:

Item description Penstocks and valves 5.15.1 Supply and install penstocks, with spindle, pillar and actuator, 1400 mm diameter

Unit

number

67

5.15.2

Supply and install penstocks, wall mounted weir, with actuator, 1500 x 1800 mm Supply and install valves, gate valve, DI, handwheel operation, DN 200 Supply and install valves, flap valve, DI, DN 150

number

5.15.3

number

5.15.4

number

Sub-heading

MANHOLES, GULLIES, CATCHPITS, DRAWPITS AND STATED CHAMBERS


I. Separate items shall be provided for under the sub-heading Manholes, gullies, catchpits, drawpits and stated chambers in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2. 3. 4. 5.

Construction of manholes Construction of gullies Construction of catchpits Construction of drawpits Construction of stated chambers

number number number number number

II

1.

different types and sizes

III

1.

different types of cover, grating and overflow weir

frame,

IV

1. 2.

depth not exceeding 1.50 m depth exceeding 1.50 m but not exceeding 2.50 m and so on in steps of 1.00 m

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.16

Item description and unit shall be:

68

Item description Manholes, gullies, catchpits, drawpits and stated chambers 5.16.1 Construction of manholes, in-situ concrete, type C as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 550 x 550 mm chamber, with heavy duty cover and frame, depth not exceeding 1.50 m Construction of manholes, precast concrete, type A with medium cover and frame, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 750 x 750 mm chamber, depth exceeding 1.50 m but not exceeding 2.50 m Construction of gullies, untrapped in-situ gully, type GA2-325 grating in rigid pavement, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], with kerb overflow weir type 1-325, depth not exceeding 1.50 m Construction of catchpits, in-situ concrete, with trap as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 1000 x 1000 mm chamber, with precast concrete cover, depth not exceeding 1.50 m Construction of drawpits, in-situ concrete, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], depth not exceeding 1.50m Construction of sand traps, in-situ concrete, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 900 x 900 mm, depth not exceeding 1.50 m Construction of septic tanks, in-situ concrete, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 1200 x 1200 mm, depth exceeding 2.50 m but not exceeding 3.50 m

Unit

number

5.16.2

number

5.16.3

number

5.16.4

number

5.16.5

number

5.16.6

number

5.16.7

number

Item description extension

5.17

The item description of the items under the sub-heading Manholes, gullies, catchpits, drawpits and stated chambers shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (d) excavation in any material except for rock and artificial hard materials and disposal of any material; backfilling with materials from any source and compaction; building in pipe connections, including fittings and pipes; step irons, access ladders and the like; reinstatement of existing ground except for reinstatement of carriageways, footways and paved areas.

69

Measurement

5.18

The measurement of the items under the sub-heading Manholes, gullies, catchpits, drawpits and stated chambers shall be the complete manhole, gully, catchpit, drawpit and stated chamber. Penstocks and valves shall be measured separately. Depths of manholes shall be the vertical distance between the top surface of the cover and the invert of the main channel. Depths of catchpits, drawpits and stated chambers shall be the vertical distance between the top surface of the cover or grating and the uppermost surface of the base slab. If the measured depth of a manhole, gully, catchpit, drawpit or stated chamber constructed is outside the depth ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

5.19

5.20

Sub-heading
Notes K.

DRAINAGE CHANNELS
Separate items shall be provided for under the sub-heading Drainage channels in accordance with the following itemisation table:

Group

Feature

Unit

1.

Construction of channels

metre

II

1.

different types and sizes

III

1.

different types of cover

L.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.21

Item description and unit shall be:

Item description Drainage channels 5.21.1 Construction of channels, half round channels, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 150 mm diameter, with cast iron grating Construction of channels, U channels, type A as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 200 mm diameter, without cover

Unit

metre

5.21.2

metre

70

5.21.3

Construction of channels, stepped channels, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 150 mm diameter, without cover

metre

Item description extension

5.22

The item description of the items under the sub-heading Drainage channels shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) excavation in any material except for rock and artificial hard materials and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground except for reinstatement of carriageways, footways and paved areas. building in pipes; waterbars and waterstops; connection to existing drainage channels; concrete apron.

Measurement

5.23

The measurement of the items under the sub-heading Drainage channels shall be the length of the drainage channel along its centreline.

Sub-heading

EXCAVATION MATERIALS
M.

IN

ROCK

OR

ARTIFICIAL HARD

Notes

Paragraphs 5.24 to 5.30, with amendments as may be necessary, shall be included for all contracts using section 5 regardless whether items under this sub-heading are provided in the bills. Separate items shall be provided for under the sub-heading Excavation in rock or artificial hard materials in accordance with the following itemisation table:

N.

Group

Feature

Unit

1.

Excavation in rock or artificial hard materials by whatsoever means

cubic metre

O.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

5.24

Item description and unit shall be:

Item description Excavation in rock or artificial hard materials 5.24.1 Excavation in rock or artificial hard materials by whatsoever means

Unit

cubic metre

71

Item description extension

5.25

The item description of the items under the sub-heading Excavation in rock or artificial hard materials shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) disposal of any material.

Measurement

5.26

The measurement of the items under the sub-heading Excavation in rock or artificial hard materials shall be the in-situ volume of the rock or artificial hard materials removed within the widths, lengths and depths required in the Contract for sewers, drains, piped culverts, ducts, trench drains, manholes, gullies, catchpits, drawpits, stated chambers, drainage channels and the like. For excavation in artificial hard materials, any empty space within such materials shall not be measured. For measurement purpose, the trench width required in the Contract shall be taken as the effective trench widths specified in Table 5.9 of the GS. The centreline of the trench shall be taken as the centreline of the pipe in the trench. For group of pipes or ducts of different number of ways, the trench width required in the Contract shall be taken as the distance between the two outer most edges of the pipe barrels or ducts plus 300 mm on either side of the group of pipes or ducts of different number of ways. No measurement shall be made for excavation in rock or artificial hard materials encountered by sewers and drains constructed by trenchless method. For work under this section 5, if rock or artificial hard materials are encountered, excavation for such materials shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3) unless such excavation is measured under other paragraphs of this section 5.

5.27

5.28

5.29

5.30

Sub-heading

REINSTATEMENT OF EXISTING CARRIAGEWAYS, FOOTWAYS AND PAVED AREAS


P. Separate items shall be provided for under the sub-heading Reinstatement of existing carriageways, footways and paved areas in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2. 3.

Reinstatement of existing carriageways Reinstatement of existing footways Reinstatement of stated existing paved areas

square metre square metre square metre

II

1.

different types of construction

72

Group

Feature

Unit

III

1. 2. 3.

within limit of excavation outside limit of excavation, thickness not exceeding 50 mm outside limit of excavation, thickness exceeding 50 mm but not exceeding 150 mm

Q.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.31

Item description and unit shall be:

Item description Reinstatement of existing carriageways, footways and paved areas 5.31.1 Reinstatement of existing carriageways, bituminous, within limit of excavation Reinstatement of existing carriageways, concrete, within limit of excavation Reinstatement of existing carriageways, bituminous, outside limit of excavation, thickness exceeding 50 mm but not exceeding 150 mm Reinstatement of existing footways, concrete, within limit of excavation Reinstatement of existing paved areas, outside limit of excavation, thickness not exceeding 50 mm

Unit

square metre

5.31.2

square metre

5.31.3

square metre

5.31.4

square metre

5.31.5

square metre

Item description extension

5.32

The item description of the items under the sub-heading Reinstatement of existing carriageways, footways and paved areas shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) excavation in any material and disposal of any material for reinstatement outside limit of excavation; backfilling with materials from any source and compaction; replacing street furniture, road studs, road markings, kerbs, edgings, channels, barriers, fences and the like.

73

Measurement

5.33

The measurement of the items under the sub-heading Reinstatement of existing carriageways, footways and paved areas within limit of excavation shall be the area within the trench width as stated in paragraphs 5.27 or 5.28 as the case may be, or for other cases, within limits of excavation as required by the Contract. The measurement of the items under the sub-heading Reinstatement of existing carriageways, footways and paved areas outside limit of excavation shall be the area reinstated outside the said limit of excavation as shown on Drawings or ordered by the Engineer.

Sub-heading

ADJUSTMENT OF LEVEL OF COVERS TO EXISTING MANHOLES AND STATED CHAMBERS


R. Separate items shall be provided for under the sub-heading Adjustment of level of covers to existing manholes and stated chambers in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2.

Raise level of cover Lower level of cover

number number

II

1.

different types of manhole or stated chamber

III

1. 2.

height not exceeding 250 mm height exceeding 250 mm but not exceeding 500 mm and so on in steps of 250 mm

S.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.34

Item description and unit shall be:

Item description Adjustment of level of covers to existing manholes and stated chambers

Unit

5.34.1

Raise level of cover, in-situ concrete manholes, height not exceeding 250 mm Lower level of cover, precast concrete manholes, height exceeding 250 mm but not exceeding 500 mm

number

5.34.2

number

74

Item description extension

5.35

The item description of the items under the sub-heading Adjustment of level of covers to existing manholes and stated chambers shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) excavation in any material and disposal of any material; taking up, storing and reinstallation of covers, frames and the like; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas.

Measurement

5.36

If the level of cover raised or lowered in accordance with the contract requirement is outside the height ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

Sub-heading
Notes T.

DRAINAGE AND DUCTS IN STRUCTURES


Separate items shall be provided for under the sub-heading Drainage and ducts in structures in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Supply and install drainage Supply and install ducts

sum sum

II

1.

in different structures or parts of structure

U.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.37

Item description and unit shall be:

Item description Drainage and ducts in structures

Unit

5.37.1 5.37.2 Item description extension 5.38

Supply and install drainage, in Pumping Station A Supply and install ducts, in wet well

sum sum

The item description of the items under the sub-heading Drainage and ducts in structures shall be extended in accordance with Preamble paragraph 1.8 and as follows:

75

(a)

(b)

(c) (d) (e)

building into, fixing to or forming in the structures the following: manholes, gullies, chambers, drawpits, junction boxes and the like, including covers; building into or fixing to the structures the following: pipework, gutters, ducts and the like, including fittings, brackets and hangers, and removing protective coating from pipes to be built in; flexible joints in drainage pipes or ducts, including those adjacent to outside face of structure; protective treatments and painting; temporary sealing to ends of drainage pipes or ducts built into structures and subsequent removal.

Sub-heading
Notes V.

DRAINAGE LAYERS
Separate items shall be provided for under the sub-heading Drainage layers in accordance with the following itemisation table:

Group

Feature

Unit

1.

Construction of drainage layers

cubic metre

II

1.

different types and thicknesses

W.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.39

Item description and unit shall be:

Item description Drainage layers 5.39.1 Construction of drainage layers, type B fill material, with 75 mm thick cement mortar bedding as shown on Drawing No(s). _____ [Drawing No(s). to be stated
in the bill items]

Unit

cubic metre

5.39.2

Construction of drainage layers, 10 mm nominal diameter hard granular material and 100 mm thick.

cubic metre

Item description extension

5.40

The item description of the items under the sub-heading Drainage layers shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways,

76

footways and paved areas.

Sub-heading
Notes X.

GRANULAR FILTERS
Separate items shall be provided for under the sub-heading Granular filters in accordance with the following itemisation table:

Group

Feature

Unit

1.

Construction of granular filters

cubic metre

II

1.

different types

Y.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

5.41

Item description and unit shall be:

Item description Granular filters 5.41.1 Construction of granular filters, granular hard material, size 20 25 mm, wrapped by non-woven geotextile membrane, 300 mm thick

Unit

cubic metre

Item description extension

5.42

The item description of the items under the sub-heading Granular filters shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas.

Sub-heading
Notes Z.

GEOTEXTILE FILTER
Separate items shall be provided for under the sub-heading Geotextile filter in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and lay geotextile filter

square metre

77

Group

Feature

Unit

II

1.

different types

AA.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

5.43

Item description and unit shall be:

Item description Geotextile filter 5.43.1 Measurement 5.44 Supply and lay geotextile filter, type A

Unit

square metre

The measurement of the items under the sub-heading Geotextile filter shall be the area of the surface to which the geotextile filter is applied. No measurement shall be made for laps and joints.

Sub-heading

FILLING AND SEALING DISUSED MANHOLES AND STATED CHAMBERS


BB. Separate items shall be provided for under the sub-heading Filling and sealing disused manholes and stated chambers in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2.

Filling and sealing of disused manholes Filling and sealing of stated chambers

number number

II

1.

different dimensions

III

1.

with different types of material for filling and/or sealing

CC.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.45

Item description and unit shall be:

78

Item description Filling and sealing disused manholes and stated chambers 5.45.1 Filling and sealing of disused manholes, internal size 600 mm x 600 mm, with foam concrete Filling and sealing of disused petrol interceptor A, with materials as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

Unit

number

5.45.2

number

Item description extension

5.46

The item description of the items under the sub-heading Filling and sealing disused manholes and stated chambers shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; removing covers and frames; sealing ends of pipes connecting to manhole or chamber; reinstatement of existing ground including carriageways, footways and paved areas.

Measurement

5.47

The measurement of the items under the sub-heading Filling and sealing disused manholes and stated chambers shall be the number of disused manholes and other chambers filled and sealed.

Sub-heading
Notes DD.

FILLING AND SEALING DISUSED PIPES


Separate items shall be provided for under the sub-heading Filling and sealing disused pipes in accordance with the following itemisation table:

Group

Feature

Unit

1.

Filling and sealing of disused pipes

metre

II

1.

different diameters

III

1.

with different types of material for filling and/or sealing

EE.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

5.48

Item description and unit shall be:

79

Item description Filling and sealing disused pipes 5.48.1 Filling and sealing of disused pipes, 150 mm diameter, with foam concrete Filling and sealing of disused pipes, 200 mm diameter, with grout

Unit

metre

5.48.2

metre

Item description extension

5.49

The item description of the items under the sub-heading Filling and sealing disused pipes shall be extended in accordance with Preamble paragraph 1.8 and as follows: excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas. The measurement of the items under the sub-heading Filling and sealing disused pipes shall be the summed length of the categories described. Length shall be measured along the centreline between the following terminations: (i) (ii) (iii) the internal face of manhole or other chamber, gully or headwall; the intersection of the centrelines of the pipes at pipe junctions; the position of the terminations as shown on Drawings. (a) (b) (c)

Measurement

5.50

Sub-heading

CLOSED CIRCUIT TELEVISION INSPECTION OF PIPELINES


FF. Separate items shall be provided for under the sub-heading Closed circuit television inspection of pipelines in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1.

Arrange and conduct closed circuit television inspection of pipelines

metre

II

1.

different diameters

GG.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

5.51

Item description and unit shall be:

80

Item description Closed circuit television inspection of pipelines 5.51.1 Arrange and conduct closed circuit television inspection of pipelines, 150 mm diameter

Unit

metre

Item description extension

5.52

The item description of the items under the sub-heading Closed circuit television inspection of pipelines shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) setting up, assembling, maintaining, moving and removal of all equipment; photographs; preparation and submission of video, records and reports.

Measurement

5.53

The measurement of the items under the sub-heading Closed circuit television inspection of pipelines shall be the length of the pipelines inspected but excluding the length of pipelines by trenchless method. Length shall be measured along the centreline of the pipelines between the internal face of manholes or stated chambers.

81

SECTION 6
Heading

PIPEWORK
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. No separate items are provided for excavation of soft spots and filling of soft spots and other voids under this section 6. Where soft spots are encountered below the formation level during excavation for works measured under this section 6, they should be dealt with as variations.

Notes

ii

Measurement

6.01

All works associated with pipes designed for use under pressure, except testing for such pipes and works mentioned in paragraph 6.02 below, if any, shall be measured under this section 6. The items of work under this section 6 shall be deemed to include concrete, reinforcement, formwork and steelwork. Headwall, outfall works, piling and plumbing, if any, shall be measured in accordance with the Preamble and other relevant sections of the Method of Measurement and shall not be measured under this section 6.

6.02

Sub-heading
Notes A.

PIPES OTHER THAN BY TRENCHLESS METHOD


Separate items shall be provided for under the sub-heading Pipes other than by trenchless method in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Supply and lay pipes Supply and lay pipes, supplied by the Employer

pipes

metre metre

II

1.

different types of materials

III

1.

different diameters

IV

1.

different types of joint

1.

different types of bedding, surround, haunch, leakage collection or filling (for pipes in trench)

82

Group

Feature

Unit

VI

1. 2.

3.

in trench, depth not exceeding nominal trench depth* in trench, depth exceeding nominal trench depth* but not exceeding nominal trench depth * plus 1.00 m and so on in steps of 1.00 m suspended on pier supports

Nominal trench depth for water mains shall be determined by reference to the following table: 450 to below 600 2.0 600 to below 800 2.1 800 to below 1000 2.3 1000 to below 1200 2.5

nominal 300 or diameter of pipe less (mm) nominal trench 1.8 depth (m)

1200 2.7

The actual depth should be used in the item description. For pipes of size greater than 1200 mm, the nominal trench depth shall be pipe size plus 1.50 m. B. The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

6.03

Item description and unit shall be:

Item description Pipes other than by trenchless method 6.03.1 Supply and lay pipes, DI, DN 600, spigot and socket joints, on 100 mm granular bedding in trench, depth not exceeding 2.10 m Supply and lay pipes, MS, DN 300, flange joints, suspended on pier supports type A Supply and lay pipes, pipes supplied by the Employer, MS, DN 800, spigot and socket welded joints, in common ground, in trench, depth exceeding 2.30 m but not exceeding 3.30 m

Unit

metre

6.03.2

metre

6.03.3

metre

Item description extension

6.04

The item description of the items under the sub-heading Pipes other than by trenchless method shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) excavation in any material except for rock and artificial hard materials and disposal of any material; backfilling with materials from any source and compaction;

83

(c) (d) (e) (f)

protective treatment and painting; gusseted bend 6 or less; reinstatement of existing ground except for reinstatement of carriageways, footways and paved areas; taking delivery of materials supplied by the Employer and transporting to Site and/or point of use.

Measurement

6.05

The measurement of the items under the sub-heading Pipes other than by trenchless method shall be the summed lengths of the categories described within each depth range. Pipes in common trench shall be measured separately. Unless otherwise stated, lengths shall be measured along the centreline through pipe fittings, valves and joints, with tapers included under the diameter of the larger pipe, between the adjacent terminations as defined below: (i) (ii) (iii) (iv) (v) the external face of manhole or other chamber or headwall; the intersection of the centreline of the pipes at pipe junctions; the position of the termination indicated on the Drawings; the point at which the depth range changes; the point at which the pipes in pier supports enter the ground or the mid-point between two adjacent different pier supports.

6.06

No measurement of the items under the sub-heading Pipes other than by trenchless method shall be made within chambers or along tee branch sections of single air valves, double air valves and inspection tees installation. Depths shall be the vertical measurement between the invert level of the pipe and the following: (i) where the invert level is below the existing ground surface the existing ground surface, except that where the earthworks final surface is below the existing ground surface the measurement shall be taken to the earthworks final surface; where the invert level is at or above the existing ground surface the earthworks final surface; where a length of pipeline in or beneath areas of fill is not permitted to be constructed until a specified minimum level of cover is obtained, then notwithstanding sub-paragraphs (i) and (ii) above - to the specified minimum level of cover or the earthworks final surface, whichever is the lower.

6.07

(ii) (iii)

6.08

If the measured depth of a pipe laid is outside the depth ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

Sub-heading
Notes C.

PIPES BY TRENCHLESS METHOD


Separate items shall be provided for under the sub-heading Pipes by trenchless method in accordance with the following itemisation table:

84

Group

Feature

Unit

1. 2.

Establishment for trenchless construction Supply and lay pipes by trenchless method

sum metre

II

1.

different types of material

III

1.

different diameters

IV

1.

different locations

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

6.09

Item description and unit shall be:

Item description Pipes by trenchless method 6.09.1 Establishment for trenchless construction, steel pipes, DN 1200 at Road A Supply and lay pipes by trenchless method, steel pipes, DN 1200 at Road A

Unit

sum

6.09.2

metre

Item description extension

6.10

The item description of the items for establishment for trenchless construction under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) setting up, moving and removal of all plant and equipment set up for trenchless construction; construction of access tunnels, access shafts, working pits, thrust pits, reception pits and thrust blocks; excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas; measures to control ground movements and settlement of adjacent structures and utilities, including but not limited to grouting.

6.11

The item description of the items for supply and lay pipes by trenchless method under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows:

85

(a) (b) (c) (d) (e)

(f) Measurement 6.12

excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas; grouting of over-break and cavities, sealing gaps between pipe shafts or lining and the pipelines; measures to control ground movements and settlement of adjacent structures and utilities, including but not limited to grouting; CCTV confirmatory inspections of pipelines and reports.

The items under the sub-heading Pipes by trenchless method shall be measured along the centreline of the pipes between the external faces of thrust pit and reception pit. Pipes inside the pits shall be measured as items under the sub-heading Pipes other than by trenchless method.

Sub-heading

VALVES WITHOUT A HOUSING CHAMBER AND PIPE FITTINGS FOR PIPES OTHER THAN BY TRENCHLESS METHOD
E. Separate items shall be provided for under the sub-heading Valves without a housing chamber and pipe fittings for pipes other than by trenchless method in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2. 3.

4.

Extra over for supply and install valves without a housing chamber* Extra over for supply and install pipe fittings Extra over for install valves without a housing chamber*, valves supplied by the Employer Extra over for install pipe fittings, pipe fittings supplied by the Employer

number number number

number

II

1. 2. 3. 4. 5. 6.

bends (other than gussetted bends) gussetted bends junctions tees tapers stated fittings

III

1.

different types

IV *

1.

different diameters valves housed in chambers shall not be included

86

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

6.13

Item description and unit shall be:

Item description Valves without a housing chamber and pipe fittings for pipes other than by trenchless method 6.13.1 Extra over for supply and install valves without a housing chamber, gate valves, DN 300 Extra over for supply and install pipe fittings, bends (other than gussetted bends), DI, 45, DN 600 Extra over for supply and install pipe fittings, tees, DI, DN 600 x dn 150 Extra over for supply and install pipe fittings, tapers, DI, DN 600 x dn 450 Extra over for supply and install pipe fittings, gussetted bends, 30, steel pipes, DN 800 Extra over for install valves without a housing chamber, valves supplied by the Employer, gate valves, DN 600

Unit

number

6.13.2

number

6.13.3

number

6.13.4

number

6.13.5

number

6.13.6

number

Item description extension

6.14

The item description of the items under the sub-heading Valves without a housing chamber and pipe fittings for pipes other than by trenchless method shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) protective treatment and painting; in case of valves or pipe fittings supplied by the Employer, taking delivery of materials supplied by the Employer and transporting to Site and/or point of use.

Measurement

6.15

Gussetted bends in steel pipes shall be measured as follows: 6 or less over 6 up to 30 over 30 up to 60 over 60 up to 90 - no measurement shall be made - measured as 30 bend - measured as 60 bend - measured as 90 bend

Sub-heading

CONNECTIONS TO PIPES, VALVES OR EQUIPMENT NOT CONSTRUCTED UNDER THE CONTRACT


G. Separate items shall be provided for under the sub-heading

Notes

87

Connections to pipes, valves or equipment not constructed under the Contract in accordance with the following itemisation table:

Group

Feature

Unit

1.

Connections to pipes, valves or equipment not constructed under the Contract

number

II

1.

different types

III

1.

different diameters

IV

1.

materials supplied by the Employer

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

6.16

Item description and unit shall be:

Item description Connections to pipes, valves or equipment not constructed under the Contract 6.16.1 Connections to pipes not constructed under the Contract, DI, DN 600 Connections to valves not constructed under the Contract, gate valves, DN 450

Unit

number

6.16.2

number

Item description extension

6.17

The item description of the items under the sub-heading Connections to pipes, valves or equipment not constructed under the Contract shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) taking delivery of materials supplied by the Employer and transporting to Site and/or point of use; excavation in any material except for rock and artificial hard materials and disposal of any material; backfilling with materials from any source and compaction; protective treatment and painting; reinstatement of existing ground except for reinstatement of carriageways, footways and paved areas.

88

Sub-heading

VALVE CHAMBERS, CHAMBERS


I.

PUMP

PITS

AND

STATED

Notes

Separate items shall be provided for under the sub-heading Valve chambers, pump pits and stated chambers in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Construction of valve chambers Construction of pump pits Construction of stated chambers

number number number

II

1.

different types

III

1.

different sizes

IV

1.

different depth ranges (only requires for same types of chamber with same sizes of valve but having a difference in depth exceeding 1.00 m) or different types

1.

materials supplied by the Employer

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

6.18

Item description and unit shall be:

Item description Valve chambers, pump pits and stated chambers 6.18.1 Construction of valve chambers, vertical gate valve chambers, valve size DN 450 Construction of valve chambers, gate valve chambers, valve size DN 300 Construction of valve chambers, horizontal gate valve chambers, valve size DN 600 Construction of valve chambers, double air valve chambers, valve size DN 150, depth not exceeding 2.00 m

Unit

number

6.18.2

number

6.18.3

number

6.18.4

number

89

6.18.5

Construction of valve chambers, double air valve chambers, valve size DN 150, depth exceeding 2.00 m but not exceeding 3.00 m Construction of valve chambers, single air valve chambers, valve size DN 100, depth not exceeding 2.00 m Construction of pump pits, washout pump pit, type A, depth not exceeding 6.00 m Construction of flow meter chambers, flow meter size DN 800 Construction of inspection tee chambers, pipe size DN 800

number

6.18.6

number

6.18.7

number

6.18.8

number

6.18.9

number

Item description extension

6.19

The item description of the items under the sub-heading Valve chambers, pump pits and stated chambers shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) supply and installation of pipes, valves, fittings and associated fixtures; excavation in any material except for rock and artificial hard materials and disposal of any material; backfilling with materials from any source and compaction; protective treatment and painting; reinstatement of existing ground except for reinstatement of carriageways, footways and paved areas; taking delivery of materials supplied by the Employer and transporting to Site and/or point of use.

Measurement

6.20

The measurement of the items under the sub-heading Valve chambers, pump pits and stated chambers shall be for the complete chamber or pit. Depths of valve chambers, pump pits and stated chambers, if described in the item of works, shall be the distance between the top surface of the cover and the uppermost surface of the base slab. If the measured depth of a valve chamber, pump pit or stated chamber constructed is outside the depth ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

6.21

6.22

Sub-heading

EXCAVATION IN ROCK OR ARTIFICIAL HARD MATERIALS


K. Paragraphs 6.23 to 6.31, with amendments as may be necessary, shall be included for all contracts using section 6 regardless whether items under this sub-heading are provided in the bills. Separate items shall be provided for under the sub-heading Excavation in rock or artificial hard materials in accordance with the

Notes

L.

90

following itemisation table:

Group

Feature

Unit

1.

Excavation in rock or artificial hard materials by whatsoever means

cubic metre

M.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

6.23

Item description and unit shall be:

Item description Excavation in rock or artificial hard materials 6.23.1 Excavation in rock or artificial hard materials by whatsoever means

Unit

cubic metre

Item description extension

6.24

The item description of the items under the sub-heading Excavation in rock or artificial hard materials shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) disposal of any material.

Measurement

6.25

For excavation in artificial hard materials, any empty space within such materials shall not be measured. For pipes in trench, the measurement of the items under the sub-heading Excavation in rock or artificial hard materials shall be the in-situ volume of rock or artificial hard materials removed within the space bounded by the vertical sides of the trench width and the horizontal plane at the invert level of the pipe or, if there is a bedding as shown on Drawings, at the bottom of the bedding. The centreline of the trench width shall coincide with the centreline of the pipes on plan. For measurement purposes, the trench width shall be determined as below:
Trench width (m) for different pipe size DN 100 DN 125 DN 175 DN 275 DN 375 above above or under to to to to DN 450 DN 500 DN 150 DN 250 DN 350 DN 450 to DN 500 nominal 0.45 0.60 0.70 0.80 0.95 1.00 diameter plus 0.50 nominal 0.70 0.75 0.85 0.95 1.05 1.11 diameter plus 0.60

6.26

Depth to invert

not exceeding 1.50 m

exceeding 1.50 m

91

6.27

For thrust block, the measurement of the items under the sub-heading Excavation in rock or artificial hard materials shall be the in-situ volume of rock or artificial hard materials removed within the space occupied by the thrust block plus the space vertically above any part of the thrust block up to existing ground surface or earthwork final surface, whichever is the lower. Provided that the quantity measured under paragraph 6.26 above shall not be measured again under this paragraph. For rock and artificial hard materials encountered in the pipes laid by trenchless method, measurement for excavation in rock or artificial hard materials shall not be made. For chambers and pits, the measurement of the items under the sub-heading Excavation in rock or artificial hard materials shall be the in-situ volume of rock or artificial hard materials removed within the space occupied by the chamber or pit, and the space vertically above any part of the chamber or pit up to existing ground surface or earthwork final surface, whichever is the lower. For pipes suspended on pier supports, the measurement of the items under the sub-heading Excavation in rock or artificial hard materials shall be the in-situ volume of rock or artificial hard materials removed within the space occupied by the pier support or the pipe, and the space vertically above any part of the pier support or the pipe up to existing ground surface or earthwork final surface, whichever is the lower. For work under this section 6, if rock or artificial hard materials are encountered, excavation for such materials shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3) unless such excavation is measured under other paragraphs of this section 6.

6.28

6.29

6.30

6.31

Sub-heading
Notes N.

THRUST BLOCK
Separate items shall be provided for under the sub-heading Thrust block in accordance with the following itemisation table:

Group

Feature

Unit

1.

Construction of thrust block

number

II

1. 2. 3. 4. 5.

horizontal bends bottom vertical bends top vertical bends tees end caps

III

1. 2.

bends not exceeding 30 bends exceeding 30 but not exceeding 45 and so on in steps of 15

92

Group

Feature

Unit

IV

1.

different sizes

1.

different types of anchoring method

O.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

6.32

Item description and unit shall be:

Item description Thrust block 6.32.1 Construction of thrust block, horizontal bends not exceeding 30, DN 300 Construction of thrust block, horizontal bends exceeding 30 but not exceeding 45, DN 450 Construction of thrust block, top vertical bends not exceeding 30, DN 300 Construction of thrust block, bottom vertical bends not exceeding 30, DN 150 Construction of thrust block, tees, DN 450 x dn 150 Construction of thrust block, end caps, DN 800

Unit

number

6.32.2

number

6.32.3

number

6.32.4

number

6.32.5 6.32.6 Item description extension 6.33

number number

The item description of the items under the sub-heading Thrust block shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) excavation in any material except for rock and artificial hard materials and disposal of any material; backfilling and compaction with materials from any source; reinstatement of existing ground except for reinstatement of carriageways, footways and paved areas.

Sub-heading

REINSTATEMENT OF EXISTING CARRIAGEWAYS, FOOTWAYS AND PAVED AREAS


P. Separate items shall be provided for under the sub-heading Reinstatement of existing carriageways, footways and paved areas in accordance with the following itemisation table:

Notes

93

Group

Feature

Unit

1. 2. 3.

Reinstatement of existing carriageways Reinstatement of existing footways Reinstatement of stated existing paved areas

square metre square metre square metre

II

1.

different types of construction

III

1. 2. 3.

within limit of excavation outside limit of excavation, thickness not exceeding 50 mm outside limit of excavation, thickness exceeding 50 mm but not exceeding 150 mm

Q.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

6.34

Item description and unit shall be:

Item description Reinstatement of existing carriageways, footways and paved areas 6.34.1 Reinstatement of existing carriageways, bituminous, outside limit of excavation, thickness not exceeding 50 mm Reinstatement of existing carriageways, concrete, outside limit of excavation, thickness exceeding 50 mm but not exceeding 150 mm Reinstatement of existing footways, concrete, within limit of excavation Reinstatement of existing paved areas, concrete, within limit of excavation

Unit

square metre

6.34.2

square metre

6.34.3

square metre

6.34.4

square metre

Item description extension

6.35

The item description of the items under the sub-heading Reinstatement of existing carriageways, footways and paved areas shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) excavation in any material and disposal of any material for reinstatement outside limit of excavation; backfilling with materials from any source and compaction;

94

(c)

replacing street furniture, road studs, road markings, kerbs, edgings, channels, barriers, fences and the like.

Measurement

6.36

The measurement of the items under the sub-heading Reinstatement of existing carriageways, footways and paved areas within limit of excavation shall be, for pipe in trench, the area within the trench width as defined in paragraph 6.26, or for other cases, within the limits of excavation as required by the Contract. The measurement of the items under the sub-heading Reinstatement of existing carriageways, footways and paved areas outside limit of excavation shall be the area reinstated outside the said limit of excavation as shown on Drawings or ordered by the Engineer.

95

SECTION 7
Heading

EARTHWORKS
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. No separate items are provided for excavation of soft spots and filling of soft spots and other voids under this section 7. Where soft spots are encountered below the formation level during excavation for works measured under this section 7, they should be dealt with as variations.

Notes

ii

Measurement

7.01

For the purpose of this section 7, it shall be assumed that one cubic metre of material to be excavated forms one cubic metre of compacted fill material, and no allowance shall be made in the measurement for bulking and shrinkage. Excavated materials and dredged materials, if any, arising from the Works measured under sections other than this section 7 of the Method of Measurement shall not be taken into account in the measurement of the items under the sub-heading Excavation under this section 7. Any additional fill material, deposition and compaction required due to settlement of an area of fill shall be measured as from the date of completion of the Works or the relevant Section thereof certified in accordance with the Contract. All fill materials shall be measured as general fill materials unless otherwise shown on Drawings. There shall only be one bill item for disposal of any material under the sub-heading Disposal of any material for the whole Contract which shall be measured in accordance with paragraph 7.20 and which has been included in bill No.___ *.
* The bill No. to be stated shall be the first bill with earthworks items under this section 7.

7.02

7.03

7.04

7.05

Notes

A.

Sub-heading
Notes B.

EXCAVATION
Separate items shall be provided for under the sub-heading Excavation in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

General excavation Excavation for structures

cubic metre cubic metre

96

Group

Feature

Unit

II

1.

different types of structure

III

1. 2. 3. 4. 5.

in materials other than rock or artificial hard materials in rock by whatsoever means in artificial hard materials by whatsoever means in rock, blasting not permitted under the Contract in artificial hard materials, blasting not permitted under the Contract

IV

1. 2.

structure maximum depth not exceeding 3.00 m structure maximum depth exceeding 3.00 m but not exceeding 6.00 m and so on in steps of 3.00 m

C.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

7.06

Item description and unit shall be:

Item description Excavation 7.06.1 7.06.2 General excavation, in materials other than rock or artificial hard materials Excavation for structures, Box Culvert No. 1, in materials other than rock or artificial hard materials, structure maximum depth not exceeding 3.00 m Excavation for structures, Footbridge No. 1, in rock by whatsoever means, structure maximum depth exceeding 3.00 m but not exceeding 6.00 m

Unit

cubic metre cubic metre

7.06.3

cubic metre

Item description extension

7.07

The item description of the items under the sub-heading Excavation shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) additional excavation the Contractor may require for working space, timbering, formwork or other Temporary Works and its subsequent backfilling, compaction and reinstatement; forming and trimming side slopes, benching and berms, or in the case of structures, trimming the bottom and sides of excavation and clearing away loose rock.

(b)

97

Measurement

7.08

The measurement of the items for general excavation under this sub-heading shall be the volume of the void formed by the excavation to the lines and levels as shown on Drawings or described in the Contract.
Lines and levels shall be shown on Drawings or described in Specification to indicate the extent of general excavation required to be carried out.

Notes

D.

7.09

The measurement of the items for excavation for structures under this sub-heading shall be the volume below the existing ground surface or the lines and levels as referred to in paragraph 7.08, whichever is the lower, which is to be occupied by the structure, plus any additional volume vertically above any part of the structure measured up to existing ground surface or the lines and levels as referred to in paragraph 7.08, whichever is the lower. In the case of structures constructed in fill materials, no measurement will be made. The total volume of excavation for any one structure shall be assigned to the item with a depth range within which its maximum depth falls. Each bay of structure between consecutive movement joints shall be taken as a structure for measuring the volume of excavation. If the measured depth of excavation for structures is outside the depth ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3). If excavation in rock is encountered and corresponding items for excavation in rock are not provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3). If excavation in artificial hard materials is encountered and corresponding items for excavation in artificial hard materials are not provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

7.10

7.11

7.12

7.13

Sub-heading
Notes E.

DEPOSITION OF FILL MATERIALS


Separate items shall be provided for under the sub-heading Deposition of fill materials in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5. 6.

Deposition of general fill materials Deposition of fine fill materials Deposition of granular fill materials Deposition of special fill materials Deposition of rock fill materials Deposition of stated types of fill material

cubic metre cubic metre cubic metre cubic metre cubic metre cubic metre

98

Group

Feature

Unit

II

1. 2. 3. 4. 5. 6. 7.

in embankments in platforms in slopes in intermediate areas of fill above structures adjacent to structures in stated locations

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

7.14

Item description and unit shall be:

Item description Deposition of fill materials 7.14.1 7.14.2 Item description extension 7.15 Deposition of general fill materials, in embankments Deposition of general fill materials, in slopes

Unit

cubic metre cubic metre

The item description of the items under the sub-heading Deposition of fill materials shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) haulage; making good or replacing materials which have become unsuitable for use in the permanent works; breaking down materials necessary to comply with the requirements of fill; selecting, processing and mixing materials to make them suitable for use as fill materials; replacing excavated materials required for use in the permanent works as fill materials which have been removed from Site or used for other purposes; mechanical or chemical treatment of materials; forming of benches; deposition of additional fill materials to replace fill materials lost by settlement of or penetration into the underlying materials.

(f) (g) (h)

99

Measurement

7.16

The measurement of the items under the sub-heading Deposition of fill materials for each type of fill material shall be calculated in accordance with the following formula: D=CS where D = volume of the items under the sub-heading Deposition of fill materials for each type of fill material generated from excavation measured under this section 7 volume of the items under the sub-heading Compaction of fill materials for each type of fill material calculated in accordance with paragraphs 7.28 to 7.31 inclusive volume of the items under the sub-heading Deposition of fill materials provided by the Contractor or others for each type of fill material calculated in accordance with paragraph 7.23 (if any) which in any case shall not have a negative value

7.17

The items under the sub-heading Deposition of fill materials other than the items for deposition of general fill materials shall only be separately measured where such fill materials are specifically shown on Drawings.

Sub-heading
Notes G.

DISPOSAL OF ANY MATERIAL


A separate item shall be provided for under the sub-heading Disposal of any material in accordance with the following itemisation table:

Group

Feature

Unit

1.

Disposal of any material

cubic metre

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

7.18

Item description and unit shall be:

Item description Disposal of any material 7.18.1 Disposal of any material

Unit

cubic metre

100

Item description extension

7.19

The item description of the item for disposal of any material under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) haulage and deposition in tips off Site; sorting, processing and treatment of materials to facilitate disposal.

Measurement

7.20

The measurement of the item for disposal of any material under this sub-heading shall be calculated in accordance with the following formula: Di = [E (C S) M] where Di = volume of the item for disposal of any material under this sub-heading volume of the items under the sub-heading Excavation for each type of material excavated from within the Site measured in this section 7 volume of the items under the sub-heading Compaction of fill materials for each type of fill material calculated in accordance with paragraphs 7.28 to 7.31 inclusive volume of each type of fill material calculated in accordance with paragraph 17.08 (if any) volume of the items under the sub-heading Deposition of fill materials provided by the Contractor or others for each type of fill material calculated in accordance with paragraph 7.23 (if any) which in any case shall not have a negative value summation of

If the volume of each type of material for disposal calculated in accordance with the formula within the above square brackets is a negative value, it shall be taken as zero.

Sub-heading

DEPOSITION OF FILL MATERIALS PROVIDED BY THE CONTRACTOR OR OTHERS


I. Separate items shall be provided for under the sub-heading Deposition of fill materials provided by the Contractor or others in accordance with the following itemisation table:

Notes

101

Group

Feature

Unit

1. 2. 3. 4. 5. 6.

Deposition of general fill materials Deposition of fine fill materials Deposition of granular fill materials Deposition of special fill materials Deposition of rock fill materials Deposition of stated types of fill material

cubic metre cubic metre cubic metre cubic metre cubic metre cubic metre

II

1. 2. 3. 4. 5. 6. 7.

in embankments in platforms in slopes in intermediate areas of fill above structures adjacent to structures in stated locations

III

1. 2. 3.

materials provided by the Contractor materials provided and delivered by others materials provided by others, collected by the Contractor from stated locations

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

7.21

Item description and unit shall be:

Item description Deposition of fill materials provided by the Contractor or others 7.21.1 7.21.2 Item description extension 7.22 Deposition of general fill materials, in embankments, materials provided by the Contractor Deposition of general fill materials, adjacent to structures, materials provided and delivered by others

Unit

cubic metre cubic metre

The item description of the items under the sub-heading Deposition of fill materials provided by the Contractor or others shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) haulage; making good or replacing materials which have become unsuitable for use in the permanent works; breaking down materials necessary to comply with the

102

(d) (e) (f) Measurement 7.23

requirements of fill; selecting, processing and mixing materials to make them suitable for use as fill materials; forming of benches; deposition of additional fill materials to replace fill materials lost by settlement of or penetration into the underlying materials.

The measurement of the items under the sub-heading Deposition of fill materials provided by the Contractor or others for each type of fill material shall be calculated in accordance with the following formula: S=CE where S = volume of the items under the sub-heading Deposition of fill materials provided by the Contractor or others for each type of fill material which in any case shall not have a negative value volume of the items under the sub-heading Compaction of fill materials for each type of fill material calculated in accordance with paragraphs 7.28 to 7.31 inclusive volume of the items under the sub-heading Excavation for each type of fill material excavated from within the Site measured in this section 7

7.24

The items under the sub-heading Deposition of fill materials provided by the Contractor or others other than the items for deposition of general fill materials shall only be separately measured where such fill materials are specifically shown on Drawings. Fill materials provided by the Contractor shall include those surplus materials generated from work under sections other than this section 7 of the Method of Measurement unless otherwise stated in the Contract.

7.25

Sub-heading
Notes K.

COMPACTION OF FILL MATERIALS


Separate items shall be provided for under the sub-heading Compaction of fill materials in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5. 6.

Compaction of general fill materials Compaction of fine fill materials Compaction of granular fill materials Compaction of special fill materials Compaction of rock fill materials Compaction of stated types of fill material

cubic metre cubic metre cubic metre cubic metre cubic metre cubic metre

103

Group

Feature

Unit

II

1. 2. 3. 4. 5. 6. 7.

in embankments in platforms in slopes in intermediate areas of fill above structures adjacent to structures in stated locations

L.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

7.26

Item description and unit shall be:

Item description Compaction of fill materials 7.26.1 7.26.2 Item description extension 7.27 Compaction of general fill materials, in embankments Compaction of rock fill materials, in slopes

Unit

cubic metre cubic metre

The item description of the items under the sub-heading Compaction of fill materials shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) forming and trimming of side slopes, benchings and berms; providing and maintaining telltales for the measurement of settlement; compaction of additional fill materials to replace fill materials lost by settlement of, or penetration into, the underlying materials; protection of formations; blinding the final surface with suitable fine fill materials.

Measurement

7.28

The measurement of the items for compaction of fill materials in embankments, platforms, slopes and intermediate areas of fill shall be the volume formed or void filled up to lines and levels as shown on Drawings or described in the Contract from existing ground surface together with the filling of any void the excavation of which has been measured in accordance with paragraph 7.08. The measurement of the items for compaction of fill materials above structures shall be the volume of the void excavated measured in accordance with paragraph 7.09 less the volume of the structures within that void.

7.29

104

7.30

The measurement of the items for compaction of fill materials adjacent to structures shall be the volume filled to the lines and levels as shown on Drawings or described in the Contract, or if no such indication is made on the Drawings or described in the Contract, within 3.00 metres of any structure, but not below any structure and excluding that defined as being above structures. It shall also exclude that required for backfilling necessitated by excavation for working space and overbreak. The items under the sub-heading Compaction of fill materials other than the items for compaction of general fill materials shall only be separately measured where such fill materials are specifically shown on Drawings.

7.31

Sub-heading
Notes M.

PRESPLITTING
Separate items shall be provided for under the sub-heading Presplitting in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Presplitting by whatsoever means Presplitting, blasting not permitted under the Contract

square metre square metre

N.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

7.32

Item description and unit shall be:

Item description Presplitting 7.32.1 7.32.2 Item description extension 7.33 Presplitting by whatsoever means Presplitting, blasting not permitted under the Contract

Unit

square metre square metre

The item description of the items under the sub-heading Presplitting shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) screens and other protective covers, and subsequent removal; measuring and recording vibrations, and supplying records to the Engineer; drilling shot holes at the appropriate position and inclination; trimming.

105

Measurement

7.34

The items under the sub-heading Presplitting shall only be measured where specified. The measurement of the items under the sub-heading Presplitting shall be the surface area of the face formed by presplitting. No allowance shall be made for irregularities, depressions or other local peculiarities.

106

SECTION 8
Heading

ROADS AND PAVINGS


i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Measurement

8.01

The items of work under this section 8 shall be deemed to include concrete, reinforcement, formwork and steelwork. Pedestrian railing, if any, shall be measured in accordance with the Preamble and section 4 (Fencing and Gates) of the Method of Measurement and shall not be measured under this section 8.

8.02

Sub-heading
Notes A.

SUB-BASE, ROADBASE AND REGULATING COURSE


Separate items shall be provided for under the sub-heading Sub-base, roadbase and regulating course in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply and lay sub-base Supply and lay roadbase Supply and lay regulating course

cubic metre square metre tonne

II

1.

different types of material

III

1.

different thicknesses of roadbase

B.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.03

Item description and unit shall be:

Item description Sub-base, roadbase and regulating course 8.03.1 Supply and lay sub-base, type I granular sub-base

Unit

cubic metre

107

8.03.2

Supply and lay roadbase, bituminous material roadbase, 37.5 mm nominal size aggregate, 250 mm thick Supply and lay regulating course, bituminous material regulating course, 28 mm nominal size aggregate

square metre

8.03.3

tonne

Item description extension

8.04

The item description of the items under the sub-heading Sub-base, roadbase and regulating course shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) compaction of deposited materials in layers.

Measurement

8.05

The measurement of the items for supply and lay sub-base under this sub-heading shall be the volume measured as shown on Drawings. No deduction shall be made for voids each not exceeding 0.3 cubic metres. The measurement of the items for supply and lay roadbase under this sub-heading shall be the area at the top surface. No deduction shall be made for openings each not exceeding one square metre. The measurement of the items for supply and lay regulating course under this sub-heading shall be the weight of regulating course as instructed by the Engineer or otherwise derived from the Drawings.

8.06

8.07

Sub-heading
Notes C.

FLEXIBLE SURFACING
Separate items shall be provided for under the sub-heading Flexible surfacing in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4.

Supply and lay base course Supply and lay wearing course Supply and lay friction course Supply and lay surface dressing

square metre square metre square metre square metre

II

1.

different types of material

III

1.

different thicknesses

D.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.08

Item description and unit shall be:

108

Item description Flexible surfacing 8.08.1 Supply and lay base course, 37.5 mm nominal size aggregate, 60 mm thick Supply and lay wearing course, 20 mm nominal size aggregate, 40 mm thick Supply and lay friction course, 10 mm nominal size bituminous material, 30 mm thick Supply and lay surface dressing, anti-skid surface dressing

Unit

square metre

8.08.2

square metre

8.08.3

square metre

8.08.4

square metre

Item description extension

8.09

The item description of the items under the sub-heading Flexible surfacing shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) compaction of deposited materials in layers.

Measurement

8.10

The measurement of the items under the sub-heading Flexible surfacing shall be the area at the top surface. No deduction shall be made for openings each not exceeding one square metre.

Sub-heading
Notes E.

MILLING OF FLEXIBLE PAVEMENT


Separate items shall be provided for under the sub-heading Milling of flexible pavement in accordance with the following itemisation table:

Group

Feature

Unit

1.

Milling

square metre

II

1. 2.

to depth not exceeding 50 mm to depth exceeding 50 mm but not exceeding 100 mm and so on in steps of 50 mm

III

1. 2.

materials to become the Contractors property materials to be disposed of at designated locations

F.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.11

Item description and unit shall be:

109

Item description Milling of flexible pavement 8.11.1 Milling, to depth not exceeding 50 mm, materials to become the Contractors property Milling, to depth exceeding 50 mm but not exceeding 100 mm, materials to be disposed of at designated locations

Unit

square metre

8.11.2

square metre

Item description extension

8.12

The item description of the items under the sub-heading Milling of flexible pavement shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) excavation in any material and disposal of any material; removal of existing road studs.

Measurement

8.13

The measurement of the items under the sub-heading Milling of flexible pavement shall be the summed area of milled flexible pavement within each depth range. The area of milled flexible pavement shall be measured once only at the top surface of the flexible pavement assigned to the item with a depth range within which the maximum milled depth falls. When there are multiple milling operations on a particular surface, the milled depth refers to the total depth of the milling on that surface. No deduction shall be made for openings each not exceeding one square metre.

Sub-heading
Notes G.

CONCRETE PAVEMENT
Separate items shall be provided for under the sub-heading Concrete pavement in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Construction of concrete carriageways Construction of stated paved concrete areas

square metre square metre

II

1. 2.

reinforced unreinforced

III

1.

different grades of concrete

IV

1.

different thicknesses

H.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item

110

descriptions and units under this sub-heading:

Item description and unit

8.14

Item description and unit shall be:

Item description Concrete pavement 8.14.1 Construction of concrete carriageways, unreinforced, grade 40 concrete, 230 mm thick Construction of run-in, reinforced with one layer of C283 fabric reinforcement, grade 30 concrete, 150 mm thick

Unit

square metre

8.14.2

square metre

Item description extension

8.15

The item description of the items under the sub-heading Concrete pavement shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) waterproof membrane underlay; jointing to existing pavement including dowels.

Measurement

8.16

The measurement of the items under the sub-heading Concrete pavement shall be at the top surface. No deduction shall be made for openings each not exceeding one square metre.

Sub-heading
Notes I.

PAVING SLABS AND INTERLOCKING BLOCKS


Separate items shall be provided for under the sub-heading Paving slabs and interlocking blocks in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Supply and lay paving slabs Supply and lay interlocking blocks

square metre square metre

II

1.

different types of material

III

1.

different types of construction

J.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.17

Item description and unit shall be:

111

Item description Paving slabs and interlocking blocks 8.17.1 Supply and lay paving slabs, 50 mm thick, clay paver with 30 mm thick sand bed Supply and lay interlocking blocks, 60 mm thick, grade 30 concrete, paving block with 30 mm thick sand bed

Unit

square metre

8.17.2

square metre

Item description extension

8.18

The item description of the items under the sub-heading Paving slabs and interlocking blocks shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) compacting sand bed; jointing to existing paved areas; in case of paving slabs or interlocking blocks procured from Correctional Services Department (CSD), price charged by CSD and taking delivery, transporting to Site and storage.

Measurement

8.19

The measurement of the items under the sub-heading Paving slabs and interlocking blocks shall be the area at the top surface. No deduction shall be made for openings each not exceeding one square metre.

Sub-heading
Notes K.

FOOTWAYS, CYCLETRACKS AND PAVED AREAS


Separate items shall be provided for under the sub-heading Footways, cycletracks and paved areas in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Construction of footways Construction of cycletracks Construction of paved areas

square metre square metre square metre

II

1.

different thicknesses

III

1.

different types of construction

IV

1.

different thicknesses of sub-base of stated types

L.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.20

Item description and unit shall be:

112

Item description Footways, cycletracks and paved areas 8.20.1 Construction of footways, 75 mm thick, grade 30 concrete with 100 mm thick type I granular sub-base Construction of cycletracks, 25 mm thick, wearing course with nominal maximum aggregate size 10 mm and 100 mm thick type I granular sub-base Construction of paved areas, 225 mm thick, grade 20 concrete

Unit

square metre

8.20.2

square metre

8.20.3

square metre

Item description extension

8.21

The item description of the items under the sub-heading Footways, cycletracks and paved areas shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) waterproof membrane underlay; compaction of deposited materials in layers; jointing to existing pavement.

Measurement

8.22

The measurement of the items under the sub-heading Footways, cycletracks and paved areas shall be the area at the top surface. No deduction shall be made for openings each not exceeding one square metre.

Sub-heading
Notes M.

KERBS, EDGINGS AND QUADRANTS


Separate items shall be provided for under the sub-heading Kerbs, edgings and quadrants in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4.

Supply and lay kerbs Supply and lay edgings Supply and lay quadrants Supply and lay special sections

kerb

metre metre number number

II

1.

different types

III

1.

different sizes

IV

1. 2.

straight or curved not less than 10.00 m radius curved less than 10.00 m radius

N.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills

113

of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.23

Item description and unit shall be:

Item description Kerbs, edgings and quadrants 8.23.1 Supply and lay kerbs, precast concrete kerbs type K1, straight or curved not less than 10.00 m radius Supply and lay edgings, precast concrete edgings type E2, curved less than 10.00 m radius Supply and lay quadrants, precast concrete quadrants, 300 mm radius Supply and lay special kerb sections, as shown on Drawing No(s). _____ [Drawing No(s). to be stated
in the bill items]

Unit

metre

8.23.2

metre

8.23.3

number

8.23.4

number

Item description extension

8.24

The item description of the items under the sub-heading Kerbs, edgings and quadrants shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas; foundation and backing; building in gully grating and frames and overflow weirs; in case of kerbs, edgings and quadrants procured from Correctional Services Department (CSD), price charged by CSD and taking delivery, transporting to Site and storage.

Measurement

8.25

The measurement of the items for supply and lay kerbs, supply and lay quadrants and supply and lay special kerb sections under this sub-heading shall be the length along their vertical faces abutting carriageways. The measurement of the items for supply and lay edgings under this sub-heading shall be the length along their vertical faces abutting footpath.

8.26

Sub-heading
Notes O.

VEHICULAR PARAPETS - BEAM BARRIERS


Separate items shall be provided for under the sub-heading Vehicular parapets beam barriers in accordance with the following itemisation table:

114

Group

Feature

Unit

1. 2. 3. 4. 5. 6.

Supply and install beam barriers Supply and install steel parapets Extra over for anchor blocks Extra over for end beams Extra over for end specials Extra over for transition pieces

metre metre number number number number

II

1.

different types and/or sizes

P.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.27

Item description and unit shall be:

Item description Vehicular parapets beam barriers 8.27.1 Supply and install beam barriers, untensioned beam barriers, direct mounting, circular hollow section posts at 4000 mm centres, concrete footings as shown on Drawing No(s). _____ [Drawing No(s). to be
stated in the bill items]

Unit

metre

8.27.2

Supply and install steel parapets, vehicular parapet as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

metre

8.27.3

Extra over for anchor blocks, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

number

8.27.4

Extra over for end beams, as shown on Drawing No(s). ______ [Drawing No(s). to be stated in the
bill items]

number

8.27.5

Extra over for end specials, as shown on Drawing No(s). ______ [Drawing No(s). to be stated in the
bill items]

number

8.27.6

Extra over for transition pieces, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

number

Item description extension

8.28

The item description of the items under this sub-heading Vehicular parapets - beam barriers shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) foundations, footings and anchorages;

115

(b) (c) (d) (e) (f) (g)

excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas; jointing to existing fences or parapets; protective treatment and painting; trimming or filling ground to maintain uniform clearance between bottom of barrier and ground.

Measurement

8.29

The measurement of the items for supply and install beam barriers and supply and install steel parapets under this sub-heading shall be the length along the centreline alignment inclusive of anchor blocks, end beams, end specials and transition pieces. The measurement of the items for extra over for anchor blocks, extra over for end beams, extra over for end specials and extra over for transition pieces under this sub-heading shall be of the complete installation.

8.30

Sub-heading

VEHICULAR BARRIERS
Q.

PARAPETS

CONCRETE

PROFILE

Note

Separate items shall be provided for under the sub-heading Vehicular parapets - concrete profile barriers in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Construction of concrete profile barriers Construction of end sections to concrete profile barriers Construction of special sections to concrete profile barriers

metre number number

II

1.

different types and/or sizes

R.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.31

Item description and unit shall be:

Item description Vehicular parapets - concrete profile barriers 8.31.1 Construction of concrete profile barriers, type 1, as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

Unit

metre

116

8.31.2

Construction of end sections to concrete profile barriers, type 2, as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

number

8.31.3

Construction of special sections to concrete profile barriers, type 3, as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

number

Item description extension

8.32

The item description of the items under the sub-heading Vehicular parapets - concrete profile barriers shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) (h) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas; foundation and backing; drain pipes, service ducts and the like; concrete topping; lamp standard sockets; cover plates.

Measurement

8.33

The measurement of the items for construction of concrete profile barriers under this sub-heading shall be the length along their centreline alignment excluding end sections and special sections. In the case of double face concrete profile barriers, the centreline shall be that between the exposed far faces of concrete profile barriers.

Sub-heading
Notes S.

TRAFFIC SIGNS, BOLLARDS AND MARKER POSTS


Separate items shall be provided for under the sub-heading Traffic signs, bollards and marker posts in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply and install traffic signs Supply and install bollards Supply and install marker posts

number number number

II

1. 2. 3. 4. 5.

internally illuminated externally illuminated non-illuminated retroreflective non-retroreflective

III

1. 2.

different types and/or sizes different materials

IV

1.

with different supports

117

T.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.34

Item description and unit shall be:

Item description Traffic signs, bollards and marker posts 8.34.1 Supply and install traffic signs, retroreflective, triangular, 600 mm high Supply and install traffic signs, with supports as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

Unit

number

8.34.2

number

8.34.3

Supply and install bollards, internal illuminated, as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

number

8.34.4

Supply and install marker posts, single post chainage marker sign supports, 2200 mm high

number

Item description extension

8.35

The item description of the items under the sub-heading Traffic signs, bollards and marker posts shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) foundations, footings and anchorages; excavation in any material and disposal of any material ; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas; in case of materials procured from Correctional Services Department (CSD), price charged by CSD and taking delivery, transporting to Site and storage; temporary screening of signs; protective treatment and painting.

(f) (g)

Sub-heading
Notes U.

SIGN GANTRIES
Separate items shall be provided for under the sub-heading Sign gantries in accordance with the following itemisation table:

Group

Feature

Unit

1.

Construction of sign gantries

number

II

1.

different types

118

V.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.36

Item description and unit shall be:

Item description Sign gantries 8.36.1 Construction of sign gantries, type ADS1 as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items]. Construction of sign gantries, type ADS2 with 19.4 m span

Unit

number

8.36.2

number

Item description extension

8.37

The item description of the items under the sub-heading Sign gantries shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) (h) foundations, footings and anchorages ; excavation in any material and disposal of any material; backfilling with materials from any source and compaction; reinstatement of existing ground including carriageways, footways and paved areas; lightning protection, electrical installation, testing and commissioning; temporary screening of signs; protective treatment and painting; signs.

Sub-heading
Notes W.

ROAD STUDS
Separate items shall be provided for under the sub-heading Road studs in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and install road studs

number

II

1.

different types and/or sizes

X.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

119

Item description and unit

8.38

Item description and unit shall be:

Item description Road studs 8.38.1 Supply and install road studs, non-reflective, stainless steel, non-depressive stud RM1075

Unit

number

Item description extension

8.39

The item description of the items under the sub-heading Road studs shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) excavation in any material and disposal of any material; reinstatement.

Sub-heading
Notes Y.

ROAD MARKINGS
Separate items shall be provided for under the sub-heading Road markings in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5.

Supply and lay continuous lines Supply and lay intermittent lines Supply and lay ancillary lines Supply and lay letters, characters, figures and symbols Supply and lay arrows

metre metre metre number number

II

1.

different materials and colours

III

1.

different lengths of mark and gap for intermittent lines

IV

1. 2. 3.

different widths of line different heights of letter, character, figure and symbol different types and/or lengths of arrow

Z.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.40

Item description and unit shall be:

120

Item description Road markings 8.40.1 Supply and lay continuous lines, white, hot applied thermoplastic material, 150 mm wide Supply and lay intermittent lines, white, hot applied thermoplastic material, 100 mm wide, 300 mm mark, 150 mm gap Supply and lay ancillary lines, white, hot applied thermoplastic material, 150 mm wide Supply and lay letters, characters, figures and symbols, white, hot applied thermoplastic material, 2800 mm high Supply and lay arrows, white, hot applied thermoplastic material, straight ahead arrow, 600 mm long

Unit

metre

8.40.2

metre

8.40.3

metre

8.40.4

number

8.40.5

number

Measurement

8.41

The measurement of the items for supply and lay intermittent lines under this sub-heading shall include unmarked intervals. Double lines shall be measured as two single lines. Ancillary lines shall include lines forming hatched areas, chevrons, zig-zag lines and boxed areas including their enclosing lines.

Sub-heading
Notes AA.

REMOVAL OF EXISTING ROAD MARKINGS


Separate items shall be provided for under the sub-heading Removal of existing road markings in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5.

Removal of continuous lines Removal of intermittent lines Removal of ancillary lines Removal of letters, characters, figures and symbols Removal of arrows

metre metre metre number number

II

1.

different lengths of mark and gap for intermittent lines

III

1. 2. 3.

different widths of line different heights of letter, character, figure and symbol different types and/or lengths of arrow

121

BB.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

8.42

Item description and unit shall be:

Item description Removal of existing road markings 8.42.1 8.42.2 Removal of continuous lines, 150 mm wide Removal of intermittent lines, 100 mm wide, 300 mm mark, 150 mm gap Removal of ancillary lines, continuous lines, 100 mm wide Removal of letters, characters, figures and symbols Removal of arrows, directional arrows

Unit

metre metre

8.42.3

metre

8.42.4 8.42.5 Item description extension 8.43

number number

The item description of the items under the sub-heading Removal of existing road markings shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) providing temporary traffic signs; protecting and making good any damage to existing pavements and surfaces.

Measurement

8.44

The measurement of the items for removal of intermittent lines under this sub-heading shall include unmarked intervals. Double lines shall be measured as two single lines. Ancillary lines shall include lines forming hatched areas, chevrons, zig-zag lines and boxed areas including their enclosing lines.

122

SECTION 9
Heading

PILING WORKS
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Measurement

9.01

Ground investigation works including pre-drilling associated with piling, if any, shall be measured in accordance with the Preamble and section 2 (Ground Investigation) of the Method of Measurement and shall not be measured under this section 9. Proof-drilling, if any, shall be measured in accordance with the Preamble and section 25 (Testing) of the Method of Measurement and shall not be measured under this section 9. Steel struts, steel waling and steel ties for supporting steel sheet piling, if any, shall be measured in accordance with the Preamble and section 14 (Steelwork) of the Method of Measurement and shall not be measured under this section 9.

9.02

9.03

Sub-heading
Notes A.

PILING PLANT
Separate items shall be provided for under the sub-heading Piling plant in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Provision and removal of piling plant Setting up piling plant

sum number

II

1.

piling plant for different types of pile

III

1. 2.

preliminary piling main piling

B.

Separate items for provision and removal of piling plant under this sub-heading shall be provided in each bill with items for piling works. The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

C.

123

Item description and unit

9.04

Item description and unit shall be:

Item description Piling plant 9.04.1 Provision and removal of piling plant, for bored piles, main piling Provision and removal of piling plant, for driven piles, preliminary piling Setting up piling plant, for bored piles, main piling

Unit

sum

9.04.2

sum

9.04.3 Item description extension 9.05

number

The item description of the items for provision and removal of piling plant under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provision and removal of all associated plant and equipment including but not limited to piling stagings, pile frames, drilling rigs and special plant.

9.06

The item description of the items for setting up piling plant under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) moving of piling plant and all associated plant and equipment set up.

Measurement

9.07

The measurement of the items for provision and removal of piling plant under this sub-heading shall be for bringing piling plant and all associated plant and equipment for the execution and completion of the piling work and their subsequent removal off the Site. The measurement of the items for setting up piling plant under this sub-heading shall be the number of piles as shown on Drawings or ordered by the Engineer. Any additional setting up of piling plant to suit the Contractors method of working shall not be measured. The items for setting up piling plant under this sub-heading shall not be measured for steel sheet piles.

9.08

9.09

Sub-heading
Notes D.

CAST-IN-SITU CONCRETE PILES


Separate items shall be provided for under the sub-heading Cast-in-situ concrete piles in accordance with the following itemisation table:

124

Group

Feature

Unit

1. 2. 3. 4. 5. 6.

Construction of pile shafts Construction of empty bores Extra over for breaking out obstructions Extra over for enlarged bases Extra over for toeing-in to bedrock Extra over for permanent linings

metre metre cubic metre number metre metre

II

1. 2.

vertical raking

III

1.

different types

IV

1.

different materials

1.

different cross sections

VI

1.

different thicknesses of permanent lining

VII

1. 2.

length not exceeding 5.00 m length exceeding 5.00 m but not exceeding 10.00 m and so on in steps of 5.00 m

VIII

1. 2.

preliminary piling main piling

E.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

9.10

Item description and unit shall be: Item description Cast-in-situ concrete piles Unit

9.10.1

Construction of pile shafts, vertical bored piles, 900 mm diameter, length exceeding 30.00 m but not exceeding 35.00 m, preliminary piling Construction of empty bores, vertical, 900 mm diameter, length exceeding 5.00 m but not exceeding 10.00 m, main piling

metre

9.10.2

metre

125

9.10.3 9.10.4 9.10.5 9.10.6

Extra over for breaking out obstructions, raking bored piles, 2000 mm diameter, main piling Extra over for enlarged bases, vertical bored piles, 900 mm diameter, main piling Extra over for toeing-in to bedrock, vertical bored piles, 900 mm diameter, main piling Extra over for permanent linings, 5mm thick, vertical bored piles, 900 mm diameter, details as shown on Drawing No(s). [Drawing No(s). to be stated in the bill items], main piling

cubic metre number metre metre

Item description extension

9.11

The item description of the items for construction of pile shafts under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) pre-boring and jetting; temporary casings or linings; excavation in any material except for rock and artificial hard materials and disposal of any material; measures to minimize settlement of ground, adjacent structures and utilities; monitoring the noise levels, vibration, ground movement and groundwater levels, taking records and supplying such records to the Engineer; forming the pile including grout and concrete; casting in tubes for sonic testing, tubes for coring and tubes for proof drilling and the like; cutting back concrete to form bond and/or trimming to required finished level; taking undisturbed soil or rock samples from the bore at any level; pressure grouting; provision of apparatus for the inspection of pile excavation or inside of pile casing.

(f) (g) (h) (i) (j) (k)

9.12

The item description of the items for construction of empty bores under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) pre-boring and jetting; temporary casings or linings; excavation in any material except for rock and artificial hard materials and disposal of any material; measures to minimize settlement of ground, adjacent structures and utilities; monitoring the noise levels, vibration, ground movement and groundwater levels, taking records and supplying such records to the Engineer; taking undisturbed soil or rock samples from the bore at any level; provision of apparatus for the inspection of pile excavation or inside of pile casing.

(f) (g)

126

9.13

The item description of the items for extra over for breaking out obstructions under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) excavation in rock and artificial hard materials and disposal of any material.

9.14

The item description of the items for extra over for enlarged bases under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) additional concrete or other materials required to fill or form the enlarged base; excavation in any material and disposal of any material.

9.15

The item description of the items for extra over for toeing-in to bedrock under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) excavation in rock and artificial hard materials and disposal of any material.

9.16

The item description of the items for extra over for permanent linings under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) protective treatment and painting; filling voids between linings and excavated faces.

Measurement

9.17

The measurement of the items for construction of pile shafts under this sub-heading shall be the length of the pile measured along the axis from the specified cut-off level to the toe of the pile shoe or the bottom of excavation including any enlarged base as required by the Engineer, whichever is appropriate. Where an empty bore is specified above a pile shaft, the length classification of the pile shaft shall be based on the overall excavated depth including the empty bore. The items for construction of empty bores under this sub-heading shall only be measured when commencement levels are specified and shall be the length of the empty bore from the specified cut-off level to the specified commencement level. The measurement of the items for extra over for breaking out obstructions under this sub-heading shall be the volume of the voids formed by the removal of rock (except bedrock), boulders, artificial hard material and the like, which can only be removed by special plant and which is within the specified cross section of the pile or enlarged base. The measurement of the items for extra over for toeing-in to bedrock under this sub-heading shall be the length of the toeing-in measured along the axis of the pile from the commencement level of bedrock at the axis to the toe of the pile shoe or the bottom of excavation including any enlarged base as required by the Engineer, whichever is appropriate.

9.18

9.19

9.20

127

9.21

The measurement of the items for extra over for permanent linings under this sub-heading shall be the length of the permanent lining shown on Drawings or ordered by the Engineer. If the measured length of a pile shaft or empty bore constructed is outside the length ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

9.22

Sub-heading

REINFORCEMENT FOR CAST-IN-SITU CONCRETE PILES


F. Separate items shall be provided for reinforcement for under the sub-heading Reinforcement for cast-in-situ concrete piles in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2.

Supply and fix bar reinforcement Supply and fix helical reinforcement

tonne tonne

II

1. 2. 3.

mild steel high yield steel stainless steel

III

1. 2. 3.

bar diameter not exceeding 16 mm bar diameter exceeding 16 mm different diameters of helical reinforcement

IV

1. 2.

bar length not exceeding 12.00 m bar length exceeding 12.00 m but not exceeding 15.00 m and so on in steps of 3.00 m

G.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

9.23

Item description and unit shall be:

Item description Reinforcement for cast-in-situ concrete piles 9.23.1 Supply and fix bar reinforcement, high yield steel, bar diameter exceeding 16 mm, bar length not exceeding 12.00 m

Unit

tonne

128

9.23.2 Item description extension 9.24

Supply and fix helical reinforcement, mild steel, 16 mm diameter

tonne

The item description of the items under the sub-heading Reinforcement for cast-in-situ concrete piles shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) protective treatment and painting; reinforcement connectors; preparing bending schedules.

Measurement

9.25

The measurement of the items under the sub-heading Reinforcement for cast-in-situ concrete piles shall include the reinforcement specified to be cast into the pile and required to bond into the substructure. The weight of plain bar reinforcement shall be calculated on the basis that steel weighs 0.00785 kilogram per square millimetre of cross sectional area per linear metre. The weight of deformed bar reinforcement shall be calculated from the nominal rolling mass of the reinforcement. Steel bar supports to reinforcement where shown on Drawings shall be measured as reinforcement.

9.26

Sub-heading
Notes H.

PRECAST CONCRETE PILES


Separate items shall be provided for under the sub-heading Precast concrete piles in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply precast concrete piles Drive precast concrete piles Strip pile heads

metre metre number

II

1. 2.

vertical raking

III

1.

different types

IV

1.

different materials

1.

different cross sections

VI

1. 2.

length not exceeding 5.00 m length exceeding 5.00 m but not exceeding 10.00 m and so on in steps of 5.00 m

VII

1. 2.

preliminary piling main piling

129

I.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

9.27

Item description and unit shall be:

Item description Precast concrete piles 9.27.1 Supply precast concrete piles, vertical, 600 mm diameter, length exceeding 20.00 m but not exceeding 30.00 m, preliminary piling Drive precast concrete piles, raking, 800 mm diameter, length exceeding 35.00 m but not exceeding 40.00 m, main piling Strip pile heads, vertical, 900 mm diameter, main piling

Unit

metre

9.27.2

metre

9.27.3 Item description extension 9.28

number

The item description of the items for supply precast concrete piles under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) reinforcement; formwork.

9.29

The item description of the items for drive precast concrete piles under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) measures to minimize settlement of ground, adjacent structures and utilities; monitoring the noise levels, vibration, ground movement and groundwater levels, taking records and supplying such records to the Engineer; re-setting up and moving plant and equipment and to redrive risen piles; re-setting up and moving plant and equipment to correct displaced piles; extracting preliminary pile; overcoming or breaking out obstructions including extraction of piles.

(c) (d) (e) (f)

9.30

The item description of the items for strip pile heads under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) disposal of any material; stripping concrete from the head to the required level and exposing the reinforcement required for bonding into the substructure; bending the projecting reinforcement as necessary to bond into

(c)

130

(d) (e) Measurement 9.31

the substructure; protective treatment and painting; capping plates, reinforcement, infill concrete and the like.

The measurement of the items for supply precast concrete piles under this sub-heading shall be the length of the pile from the toe or tapered point to the specified cut-off level. The measurement of the items for drive precast concrete piles under this sub-heading shall be the length of the pile measured from the toe or tapered point to the existing ground surface or the level of the underside of the pile cap (excluding any blinding layer), whichever is the lower. Provided that where a particular level is specified from which driving shall commence, then the measurement shall be to that specified level. If the measured length of a precast concrete pile supplied or driven is outside the length range of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

9.32

9.33

Sub-heading
Notes J.

STEEL BEARING PILES


Separate items shall be provided for under the sub-heading Steel bearing piles in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply steel bearing piles Drive steel bearing piles Prepare pile heads

metre metre number

II

1. 2.

vertical raking

III

1.

different types

IV

1. 2.

preliminary piling main piling

K.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

9.34

Item description and unit shall be:

131

Item description Steel bearing piles 9.34.1 9.34.2 9.34.3 Item description extension 9.35 Supply steel bearing piles, vertical, 600 mm diameter steel tubular bearing piles, main piling Drive steel bearing piles, raking, 305 x 305 x 223 kg/m steel H-piles, main piling Prepare pile heads, vertical, 600 mm diameter steel tubular bearing piles, main piling

Unit

metre metre number

The item description of the items for supply steel bearing piles under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) protective treatment and painting.

9.36

The item description of the items for drive steel bearing piles under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) measures to minimize settlement of ground, adjacent structures and utilities; monitoring the noise levels, vibration, ground movement and groundwater levels, taking records and supplying such records to the Engineer; re-setting up and moving plant and equipment to redrive risen piles; re-setting up and moving plant and equipment to correct displaced piles; extracting preliminary pile; overcoming or breaking out obstructions including extraction of piles.

(c) (d) (e) (f)

9.37

The item description of the items for prepare pile heads under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) capping plates; protective treatment and painting; in the case of the heads of piles being encased in concrete, removal of protective coating and other surface treatment.

Measurement

9.38

The measurement of the items for supply steel bearing piles under this sub-heading shall be the length of the pile from the toe or tapered point to the specified cut-off level. The measurement of the items for drive steel bearing piles under this sub-heading shall be the length of the pile measured from the toe or tapered point to the existing ground surface or the level of the underside of the pile cap (excluding any blinding layer), whichever is the lower. Provided that where a particular level is specified from which driving shall commence, then the measurement shall be to that specified level.

9.39

132

Sub-heading
Notes L.

STEEL SHEET PILES


Separate items shall be provided for under the sub-heading Steel sheet piles in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Supply steel sheet piles Drive steel sheet piles Feature

square metre square metre Unit

Group

II

1.

different types

III

1. 2.

vertical length not exceeding 5.00 m vertical length exceeding 5.00 m but not exceeding 10.00 m and so on in steps of 5.00 m

M.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

9.40

Item description and unit shall be:

Item description Steel sheet piles 9.40.1 Supply steel sheet piles, FSP-IIA steel sheet piles, vertical length exceeding 5.00 m but not exceeding 10.00 m Drive steel sheet piles, FSP-IIA steel sheet piles, vertical length exceeding 5.00 m but not exceeding 10.00 m

Unit

square metre

9.40.2

square metre

Item description extension

9.41

The item description of the items for supply steel sheet piles under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) weepholes; forming openings; protective treatment and painting.

133

9.42

The item description of the items for drive steel sheet piles under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) measures to minimize settlement of ground, adjacent structures and utilities; monitoring the noise levels, vibration, ground movement and groundwater levels, taking records and supplying such records to the Engineer; setting up and moving plant and equipment at each pile position including site preparation or levelling; re-setting up and moving plant and equipment to redrive risen piles; re-setting up and moving plant and equipment to correct displaced piles; overcoming or breaking out obstructions including extraction of piles.

(c) (d) (e) (f)

Measurement

9.43

The measurement of the items for supply steel sheet piles under this sub-heading shall be the plane (not developed) horizontal length along the centreline of the piling multiplied by the vertical length as shown on Drawings or ordered by the Engineer. The measurement of the items for drive steel sheet piles under this sub-heading shall be the plane (not developed) horizontal length along the centreline of the piling multiplied by the depth from the toe to the existing ground surface or the specified cut off level of the pile, whichever is the lower. Provided that where a particular level is specified from which driving shall commence, then the measurement shall be to that specified level. If the measured vertical length of steel sheet piles supplied or driven is outside the length ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

9.44

9.45

134

SECTION 10
Heading

FORMWORK
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading

FORMWORK, PROFILED PERMANENT FORMWORK


A.

FORMWORK

AND

Notes

Separate items shall be provided for under the sub-heading Formwork, profiled formwork and permanent formwork in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply, install and remove formwork Supply, install and remove profiled formwork Supply and install permanent formwork

square metre square metre square metre

II

1.

2.

3.

4. 5. 6. 7.

width exceeding 300 mm, horizontal or at any inclination up to and including 5 to the horizontal width exceeding 300 mm, at any inclination more than 5 up to and including 85 to the horizontal width exceeding 300 mm, at any inclination more than 85 up to and including 90 to the horizontal width not exceeding 300 mm, at any inclination curved, girth and width exceeding 300 mm, at any inclination curved, girth or width not exceeding 300 mm, at any inclination domed

III

1. 2.

different classes of finish different types of permanent formwork

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

135

Item description and unit

10.01

Item description and unit shall be:

Item description Formwork, formwork 10.01.1 profiled formwork and permanent

Unit

Supply, install and remove formwork, width exceeding 300 mm, horizontal or at any inclination up to and including 5 to the horizontal, Class F3 Supply, install and remove profiled formwork, width exceeding 300 mm, at any inclination more than 5 up to and including 85 to the horizontal, Class F6 Supply and install permanent formwork, width exceeding 300 mm, at any inclination more than 85 up to and including 90 to the horizontal, type 1 as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

square metre

10.01.2

square metre

10.01.3

square metre

Measurement

10.02

The measurement of the items for supply, install and remove formwork and supply and install permanent formwork under this sub-heading shall, subject to the qualifications stated in paragraph 10.07, be the area of formwork which is in contact with the finished concrete together with the area of the openings in such finished concrete provided that the size of the openings does not exceed one square metre each. Where concrete other than blinding concrete is placed in structural foundations, the items for supply, install and remove formwork under this sub-heading shall be measured to the sides of such concrete foundations regardless of whether any formwork is used, except where it is expressly stated on the Drawings that the concrete is to be cast against the soil face. The measurement of the items for supply, install and remove profiled formwork under this sub-heading shall, subject to the qualifications stated in paragraph 10.07, be the plane (not developed) area of the profiled concrete as shown on Drawings. Where such formwork is bounded by strips of plain finish not exceeding 300 millimetres wide, these strips shall be measured under the items for supply, install and remove profiled formwork under this sub-heading. The items for supply, install and remove formwork under this sub-heading shall be measured to one face only at movement joints. Curved formwork shall be measured separately only where the face of the formwork in contact with the concrete is curved to a radius of 12.00 metres or less. The items under the sub-heading Formwork, profiled formwork and permanent formwork shall not be measured: (a) (b) to construction joints; to holes, ducts, pockets, sockets, mortices and the like not

10.03

10.04

10.05

10.06

10.07

136

(c)

(d) (e)

exceeding 0.15 cubic metres each in volume; to individual fillets, chamfers, splays, drips, rebates, recesses, grooves and the like not exceeding 100 millimetres total girth measured on the faces in contact with the concrete; to edges of concrete in blinding layers; to upper surfaces of concrete inclined at an angle of 15 or less to the horizontal.

Sub-heading
Notes C.

VOID FORMERS
Separate items shall be provided for under the sub-heading Void formers in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Supply and install void formers Supply, install and remove void formers

metre metre

II

1.

different types

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

10.08

Item description and unit shall be:

Item description Void formers 10.08.1 Supply, install and remove void formers, type I as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

Unit

metre

137

SECTION 11
Heading

STEEL REINFORCEMENT
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading
Notes A.

REINFORCEMENT
Separate items shall be provided for under the sub-heading Reinforcement in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply and fix bar reinforcement Supply and fix fabric reinforcement Supply and fix helical reinforcement

tonne square metre tonne

II

1. 2. 3. 4. 5.

mild steel high yield steel stainless steel galvanised steel epoxy coated steel

III

1. 2. 3. 4.

bar diameter not exceeding 16 mm bar diameter exceeding 16 mm different BS references of fabric reinforcement different diameters of helical reinforcement

IV

1. 2.

bar length not exceeding 12.00 m bar length exceeding 12.00 m but not exceeding 15.00 m and so on in steps of 3.00 m

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

11.01

Item description and unit shall be:

138

Item description Reinforcement 11.01.1 Supply and fix bar reinforcement, high yield steel, bar diameter exceeding 16 mm, bar length not exceeding 12.00 m Supply and fix fabric reinforcement, high yield steel, A393 to BS 4483 Supply and fix helical reinforcement, high yield steel, 10 mm diameter

Unit

tonne

11.01.2 11.01.3 Item description extension 11.02

square metre tonne

The item description of the items under the sub-heading Reinforcement shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) protective treatment and painting; reinforcement connectors; cover spacers, chairs, supports and spacers; preparing bending schedules.

Measurement

11.03

The mass of plain bar reinforcement shall be calculated on the basis that steel weighs 0.00785 kilogram per square millimetre of cross sectional area per linear metre. The mass of deformed bar reinforcement shall be calculated from the nominal rolling mass of the reinforcement. Steel bar supports to reinforcement where shown on Drawings shall be measured as reinforcement. The items for supply and fix fabric reinforcement under this sub-heading shall be measured as the area of fabric excluding laps. No deduction shall be made for openings each not exceeding one square metre.

11.04

Sub-heading
Notes C.

DOWELS
Separate items shall be provided for under the sub-heading Dowels in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and install dowels

number

II

1.

different types of material

III

1.

different diameters and lengths of dowel

IV

1.

different accessories

139

D.

The Method of Measurement shall contain item descriptions and units for the items of work that are measured in the bills of the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

11.05

Item description and unit shall be:

Item description Dowels 11.05.1 Item description extension 11.06 Supply and install dowels, high yield steel, 25 mm diameter, 1000 mm long

Unit

number

The item description of the items under the sub-heading Dowels shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) drilling in any material and grouting; protective treatment and painting.

140

SECTION 12
Heading

CONCRETE
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading
Notes A.

IN-SITU CONCRETE
Separate items shall be provided for under the sub-heading In-situ concrete in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply and cast concrete Supply and cast blinding concrete Supply and cast no-fines concrete

cubic metre cubic metre cubic metre

II

1.

different grades of concrete and different sizes of aggregate

III

1. 2.

different types of cement with pulverised fuel ash

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

12.01

Item description and unit shall be:

Item description In-situ concrete 12.01.1 Supply and cast concrete, grade 40/20D, with pulverised fuel ash Supply and cast concrete, grade 30/20S Supply and cast blinding concrete, grade 10D Supply and cast no-fines concrete

Unit

cubic metre

12.01.2 12.01.3 12.01.4

cubic metre cubic metre cubic metre

141

Item description extension

12.02

The item description of the items under the sub-heading In-situ concrete shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) finishes to unformed surfaces; formwork to upper surfaces inclined at an angle of 15 or less to the horizontal; weep pipes, pipe sleeves and the like; casting built-in items, forming holes, ducts, pockets, sockets, mortices and the like, including formwork; formwork to blinding concrete; underlay and sliding layers of any type.

Measurement

12.03

No deduction shall be made for: (a) (b) (c) built-in items, holes, ducts, pockets, sockets, mortices and the like each not exceeding 0.15 cubic metres in volume; reinforcement; individual fillets, chamfers, splays, drips, rebates, recesses, grooves and the like not exceeding 100 millimetres in girth measured on the faces in contact with the formwork; in the case of concrete with profiled face, any indentations of 100 millimetres total girth or less when measured in contact with the profiled formwork.

(d)

Sub-heading Measurement
Notes

PRECAST CONCRETE
12.04 The term precast applies to any concrete unit cast on Site but not in its final position and to concrete units manufactured off the Site.
Separate items shall be provided for under the sub-heading Precast concrete in accordance with the following itemisation table:

C.

Group

Feature

Unit

1.

2.

3.

Supply and install precast copings and the like of uniform cross section Supply and install precast members, slabs, units and specially moulded blocks Supply and install precast prestressed members and units

metre

number

number

II

1.

different types

III

1.

different sizes

IV

1.

curved

142

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

12.05

Item description and unit shall be:

Item description Precast concrete 12.05.1 Supply and install precast copings, type I as shown on Drawing No(s). _____ [Drawing No(s). to be stated in
the bill items]

Unit

metre

12.05.2 12.05.3

Supply and install precast slabs, type A Supply and install precast prestressed members, segmental beam, 5.0m long, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

number number

Item description extension

12.06

The item description of the items under the sub-heading Precast concrete shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) formwork, reinforcement and surface finishes; casting built-in items, forming holes, ducts, pockets, sockets, mortices and the like; caulking and sealing between and under units and members; in case of precast prestressed members and units, ducts, tendons and stressing (including partially stressing) and grouting internal tendons; in case of precast members and precast prestressed members and the like for incorporation in in-situ post tensioned prestressed construction, forming and installing tendon ducts to profile and sealing, forming recesses in the concrete for anchorages and jack seatings, bearing plates, reinforcing helices, grout inlets, vents and other components, including casting in.

(e)

Sub-heading
Notes E.

TREATMENT TO FACES OF IN-SITU CONCRETE


Separate items shall be provided for under the sub-heading Treatment to faces of in-situ concrete in accordance with the following itemisation table:

143

Group

Feature

Unit

1. 2. 3. 4. 5. 6. 7.

Provision of exposed aggregate treatment Provision of point tooled treatment Provision of bush hammered treatment Provision of broken rib treatment Provision of light blasting treatment Provision of heavy blasting treatment Provision of stated treatments

square metre square metre square metre square metre square metre square metre square metre

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

12.07

Item description and unit shall be:

Item description Treatment to faces of in-situ concrete 12.07.1 Measurement 12.08 Provision of exposed aggregate treatment

Unit

square metre

The measurement of the items under the sub-heading Treatment to faces of in-situ concrete shall be the area of the treated face shown on Drawings, except for concrete faces formed with profiled formwork in which case the measurement shall be the same area as that for the profiled formwork.

144

SECTION 13
Heading

PRESTRESSING
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Measurement

13.01

For the purpose of this section 13, a tendon is defined as all the permanent components of a system which imparts a compressive load to a concrete member through a common anchorage or bearing plate.

Sub-heading
Notes A.

IN-SITU POST TENSIONED PRESTRESSING


Separate items shall be provided for under the sub-heading In-situ post tensioned prestressing in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply, install, stress and grouting internal tendons Supply, install and stress external tendons Final stressing and grouting tendons of members supplied partially prestressed

number number number

II

1. 2.

tendons for in-situ concrete construction tendons for segmental construction

III

1.

different types of tendon

IV

1. 2. 3.

longitudinal tendons transverse tendons tendons in any other direction

1.

different stated lengths in range of tendon

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

145

Item description and unit

13.02

Item description and unit shall be:

Item description In-situ post tensioned prestressing 13.02.1 Supply, install, stress and grouting internal tendons, longitudinal prestressing tendons for segmental construction, 37 number of 15.7 mm diameter strand, 70 - 75 m long Supply, install, stress and grouting internal tendons, transverse tendons for in-situ concrete construction, 9 number of 12.9 mm diameter strand, 10 - 15 m long Supply, install and stress external tendons, longitudinal prestressing tendons for segmental construction, 37 number of 12.9 mm diameter strand, 60 65 m long Final stressing and grouting tendons of members supplied partially prestressed, 19 number of 15.7 mm diameter strand, 50 55 m long

Unit

number

13.02.2

number

13.02.3

number

13.02.4

number

Item description extension

13.03

The item description of the items under the sub-heading In-situ post tensioned prestressing shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) steel bars, cables, wires or strands with couplers, binders, spacers and the like; prestressing components, anchorages, sheaths, deviators, bearing plates, reinforcing helices, grout inlets, grout vents and taps, tendon ducts and the like; protective treatment and painting; forming recesses in the concrete for anchorages and jack seating; applying prestress in one or more stages; releasing tension and re-tensioning.

(c) (d) (e) (f) Measurement 13.04

Lengths of tendons shall be measured along the line of the tendon between the outside faces of those parts of the anchorage units cast into the concrete. Tendons shall be grouped so that no member of the group differs in length from the stated length in range by more than 5 %.

Sub-heading
Notes C.

PROTECTIVE COVERING TO EXTERNAL TENDONS


Separate items shall be provided for under the sub-heading Protective covering to external tendons in accordance with the following itemisation table:

146

Group

Feature

Unit

1.

Provision of protective covering to external tendons

number

II

1.

different types or sizes of external protective covering

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

13.05

Item description and unit shall be:

Item description Protective covering to external tendons 13.05.1 Provision of protective covering to external tendons, 37 number of 15.7 mm diameter strand, 140 - 145 m long as shown on Drawing No(s). _____ [Drawing
No(s). to be stated in the bill items]

Unit

number

13.05.2

Provision of protective covering to external tendons, 37 number of 15.7 mm diameter low relaxation supper strand for segmental construction, lengths of tendons exceeding 255 m but not exceeding 260 m as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

number

Item description extension

13.06

The item description of the items under the sub-heading Protective covering to external tendons shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) tying or bonding to main structure.

147

SECTION 14
Heading

STEELWORK
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading
Notes A.

STEELWORK
Separate items shall be provided for under the sub-heading Steelwork in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Fabrication of steelwork Erection of steelwork

tonne tonne

II

1. 2. 3.

rolled steel cast steel cast iron

III

1. 2. 3. 4. 5.

I, H, U, L, C or Z sections plates hollow sections composite sections stated sections

IV

1.

different sizes and weights

1.

different grades of steel

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

14.01

Item description and unit shall be:

Item description Steelwork 14.01.1 Fabrication of steelwork, rolled steel, H sections, 305 x 305 x 223 kg/m, steel grade 50C

Unit

tonne

148

14.01.2

Erection of steelwork, rolled steel, H sections, 305 x 305 x 223 kg/m, steel grade 50C

tonne

Item description extension

14.02

The item description of the items for fabrication of steelwork under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) workshop drawings; examining and checking steel for defects and carrying out any remedial measures in respect thereof; welding, shear connectors, rivets, bolts, nuts, washers, drifts, cleats and the like required to fabricate, erect and install the steelwork; spare parts.

(d) 14.03

The item description of the items for erection of steelwork under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) welding; erection and fixing in position, complete with any concrete cast on and grouting.

Measurement

14.04

The measurement of the items under the sub-heading Steelwork shall be the total weight of the finished member comprising plates, rolled sections, shear connectors, stiffeners, cleats, packs, splice plates and all fittings, with no allowance for tolerances for rolling margins and other permissible deviations from standard weights, and excluding the weights of weld fillets, bolts, nuts and washers, rivet heads, and protective coatings. No deduction shall be made for splays, notches, holes and the like each not exceeding 0.03 square metres. The weight of rolled steel standard sections shall be computed in accordance with the mass per unit length stated in the relevant standards specified in the Contract and the dimensions shown on Drawings, with no allowance for addition for fillets and overruns for castings. The weight of rolled steel, cast steel and cast iron sections where mass per unit length is not given in the relevant standard specified in the Contract shall be computed from the dimensions shown on Drawings, with no allowance for addition for fillets and overruns for castings, on the following basis: (a) (b) rolled steel or cast steel, 7850 kilogram per cubic metre; cast iron, 7210 kilogram per cubic metre.

14.05

14.06

Sub-heading
Notes C.

TRIAL ERECTION AT THE PLACE OF FABRICATION


Separate items shall be provided for under the sub-heading Trial erection at the place of fabrication in accordance with the following itemisation table:

149

Group

Feature

Unit

1.

Trial erection fabrication

at

the

place

of

sum

II

1. 2. 3.

rolled steel cast steel cast iron

III

1. 2. 3. 4. 5.

I, H, U, L, C or Z sections plates hollow sections composite sections stated sections or structures

IV

1.

different sizes and weights

1.

different grades of steel

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

14.07

Item description and unit shall be:

Item description Trial erection at the place of fabrication 14.07.1 Trial erection at the place of fabrication, Footbridge No. 1, main span as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], total weight of steel 500 tonnes, steel grade 50C

Unit

sum

Item description extension

14.08

The item description of the items under the sub-heading Trial erection at the place of fabrication shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) erection and fixing in position in any specified sequence; dismantling; modifications and refitting of members as a result of the trial erection.

Sub-heading
Notes E.

CORRUGATED STEEL STRUCTURES


Separate items shall be provided for under the sub-heading Corrugated steel structures in accordance with the following itemisation table:

150

Group

Feature

Unit

1.

Fabrication and erection corrugated steel structures

of

number

II

1.

different types

III

1.

different sizes

IV

1.

different thicknesses

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

14.09

Item description and unit shall be:

Item description Corrugated steel structures 14.09.1 Fabrication and erection of corrugated steel structures, as shown on Drawing No(s). _____ [Drawing No(s).
to be stated in the bill items]

Unit

number

Item description extension

14.10

The item description of the items under the sub-heading Corrugated steel structures shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) workshop drawings; channels, laps, rivets, bolts, nuts, washers, service bolts, drifts, cleats and the like required to assemble, fix and install the corrugated steel structures; spare parts; protective treatment and painting.

(c) (d)

Sub-heading
Notes G.

PROTECTION OF STEELWORK
Separate items shall be provided for under the sub-heading Protection of steelwork in accordance with the following itemisation table:

151

Group

Feature

Unit

1.

Provision of protective systems

square metre

II

1.

different types

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

14.11

Item description and unit shall be:

Item description Protection of steelwork 14.11.1 Provision of protective systems, galvanised coatings at a rate of 335 kg/m Provision of protective systems, painting system E

Unit

square metre

14.11.2 Measurement 14.12

square metre

The measurement of the items under the sub-heading Protection of steelwork shall be the external surface area of the steelwork required to be protected.

152

SECTION 15
Heading

WATERPROOFING
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading
Notes A.

WATERPROOFING SYSTEMS
Separate items shall be provided for under the sub-heading Waterproofing in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Provision of waterproofing systems Protection to waterproofing systems

square metre square metre

II

1.

different types

III

1.

2.

3.

horizontal surfaces and inclined surfaces sloping at 45 or less to the horizontal vertical surfaces and surfaces sloping at more than 45 to the horizontal domed surfaces

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

15.01

Item description and unit shall be:

Item description Waterproofing systems 15.01.1 Provision of waterproofing systems, prefabricated sheeting, horizontal surfaces and inclined surfaces sloping at 45 or less to the horizontal Provision of waterproofing systems, bituminous paint, vertical surfaces and surfaces sloping at more than 45 to the horizontal

Unit

square metre

15.01.2

square metre

153

15.01.3

Protection to waterproofing systems, bentonite panels, vertical surfaces and surfaces sloping at more than 45 to the horizontal

square metre

Measurement

15.02

The measurement of the items under the sub-heading Waterproofing systems shall be the area of the surface covered. No deduction shall be made for openings each not exceeding one square metre.

154

SECTION 16
Heading

BEARINGS AND MOVEMENT JOINTS


i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading
Notes A.

BEARINGS
Separate items shall be provided for under the sub-heading Bearings in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and install bearings

number

II

1.

different types

III

1.

different sizes

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

16.01

Item description and unit shall be:

Item description Bearings 16.01.1 16.01.2 Item description extension 16.02 Supply and install bearings, guided pot bearing reference BNB31b Supply and install bearings, free pot bearing reference BNB32p

Unit

number number

The item description of the items under the sub-heading Bearings shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) accessories, fixings and fittings; construction of plinths, bedding and grouting, including concrete, reinforcement and formwork; protective coatings, marking and painting.

155

Sub-heading
Notes C.

FABRICATED MOVEMENT JOINTS


Separate items shall be provided for under the sub-heading Fabricated movement joints in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and install movement joints

fabricated

number

II

1.

different types

III

1.

different lengths

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

16.03

Item description and unit shall be:

Item description Fabricated movement joints 16.03.1 Supply and install fabricated movement joints, as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

Unit

number

16.03.2

Supply and install fabricated movement joints, type 1, 14.00 m long as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

number

Item description extension

16.04

The item description of the items under the sub-heading Fabricated movement joints shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) accessories, fixings and fittings; cover plates to concrete profile barriers and parapets; forming grooves in pavements, walls above joints, facework and other surfaces, including sealing; making good road surface adjoining fabricated movement joints; protective treatment.

Sub-heading
Notes E.

MOVEMENT JOINTS FORMED IN PLACE


Separate items shall be provided for under the sub-heading

156

Movement joints formed in place in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5. 6. 7.

Supply and install joint filler Supply and install joint sealant Supply and install compression seal Supply and install bearing strip Supply and install waterbar Supply and install waterstop Supply and install dowels

square metre metre metre metre metre metre number

II

1.

different types of material

III

1. 2.

different sizes different thicknesses

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

16.05

Item description and unit shall be:

Item description Movement joints formed in place 16.05.1 16.05.2 16.05.3 Supply and install joint filler, compressive type, 25 mm thick non-absorbent

Unit

square metre metre metre

Supply and install joint sealant, hot applied rubber bitumen type, 20 mm x 30 mm Supply and install compression seal, as shown on Drawing No(s). _____ [Drawing No(s). to be stated
in the bill items]

16.05.4

Supply and install bearing strip, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

metre

16.05.5

Supply and install waterbar, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

metre

16.05.6

Supply and install waterstop, PVC center bulb type, 250 mm wide

metre

157

16.05.7

Supply and install dowels, galvanised mild steel dowel, 25 mm diameter, 800 mm long

number

Item description extension

16.06

The item description of the items for supply and install joint filler and supply and install joint sealant under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) bond breaker tape or PVC capping strip; forming, cutting or sealing grooves.

16.07

The item description of the items for supply and install dowels under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) drilling in any material and grouting; protective treatment and painting.

Measurement

16.08

The measurement of the items for supply and install compression seal, supply and install bearing strip, supply and install waterbar and supply and install waterstop under this sub-heading shall be the length along its axis.

158

SECTION 17
Heading

MARINE WORKS
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Measurement

17.01

Marine structures and submarine outfalls, if any, shall be measured in accordance with the Preamble and the relevant sections for Earthworks, Drainage and Ducts, Pipework, Formwork, Steel Reinforcement and Concrete of the Method of Measurement and shall not be measured under this section 17.

Sub-heading
Notes A.

DREDGING
Separate items shall be provided for under the sub-heading Dredging in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Dredging by whatsoever means Dredging, blasting not permitted under the Contract Redredging of surcharge material

cubic metre cubic metre cubic metre

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

17.02

Item description and unit shall be:

Item description Dredging 17.02.1 17.02.2 17.02.3 Item description extension 17.03 Dredging by whatsoever means Dredging, blasting not permitted under the Contract Redredging of surcharge material

Unit

cubic metre cubic metre cubic metre

The item description of the items under the sub-heading Dredging shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) initial and final surveys;

159

(b) (c) (d)

(e) (f) (g) Measurement 17.04

marking the Site with flags, marker buoys and lights; provision, maintenance and removal of temporary tide gauges; dredging in all types of material and disposal of the dredged materials, including in the case of rock or artificial hard materials, breaking up and getting out; trimming to dredging profiles; removing any siltage deposited prior to filling; dredging outside the dredging profile.

The measurement of the items under the sub-heading Dredging shall be the volume of the void formed by the removal of materials to the dredging profile as defined in the Contract.

Sub-heading

DEPOSITION OF FILL MATERIALS FOR MARINE STRUCTURES AND RECLAMATION


C. Separate items shall be provided for under the sub-heading Deposition of fill materials for marine structures and reclamation in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2. 3.

Deposition of underwater fill materials Deposition of rock fill materials Deposition of stated types of fill material

cubic metre cubic metre cubic metre

II

1. 2. 3. 4.

in seawall foundations in breakwaters in stated marine structures in reclamation

III

1. 2.

different types of material different grades of material

IV

1. 2. 3. 4.

materials from excavation on Site materials provided by the Contractor materials provided and delivered by others materials provided by others and collected by the Contractor

1.

different sources collection

or

points

of

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of

160

Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

17.05

Item description and unit shall be:

Item description Deposition of fill materials for marine structures and reclamation 17.05.1 Deposition of rock fill materials, in seawall foundations, Grade 200, materials provided by the Contractor Deposition of sand, in reclamation, materials provided by others and collected by the Contractor from Area A

Unit

cubic metre

17.05.2

cubic metre

Item description extension

17.06

The item description of the items under the sub-heading Deposition of fill materials for marine structures and reclamation shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) initial and final surveys; marking the Site with flags, marker buoys and lights; provision, maintenance and removal of temporary tide gauges; compaction of fill materials; selection, separation and processing of materials; additional fill materials to replace fill materials lost by settlement of or penetration into the underlying materials; consolidation of fill materials; trimming to specified profiles; removal and disposal of any unsuitable overburden materials or materials deposited by siltage prior to filling subsequent layers; filling of any void caused by overdredging or any other fill outside the fill profile.

Measurement

17.07

The measurement of the items for deposition of fill materials in reclamation under this sub-heading shall be the fill materials deposited below +2.50 metres P.D. Deposition of fill materials above +2.50 metres P.D. shall be measured under section 7 (Earthworks) of the Method of Measurement. The measurement of the items under the sub-heading Deposition of fill materials for marine structures and reclamation shall be the volume of the fill materials formed within the fill profiles as defined in the Contract.

17.08

Sub-heading
Notes E.

ROCK ARMOUR
Separate items shall be provided for under the sub-heading Rock armour in accordance with the following itemisation table:

161

Group

Feature

Unit

1.

Deposition of rock armour

cubic metre

II

1.

different types

III

1. 2. 3.

for breakwaters for revetments for stated marine structures

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

17.09

Item description and unit shall be:

Item description Rock armour 17.09.1 Item description extension 17.10 Deposition of rock armour, type 1, for breakwaters

Unit

cubic metre

The item description of the items under the sub-heading Rock armour shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) initial and final surveys; marking the Site with flags, marker buoys and lights; provision, maintenance and removal of temporary tide gauges; selection, separation and processing of materials; allowance for settlement and displacement of the underlying materials.

Sub-heading
Notes G.

LEVELLING COURSE
Separate items shall be provided for under the sub-heading Levelling course in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and lay levelling course

square metre

II

1.

different thicknesses

162

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

17.11

Item description and unit shall be:

Item description Levelling course 17.11.1 Item description extension 17.12 Supply and lay levelling course, 150 mm thick

Unit

square metre

The item description of the items under the sub-heading Levelling course shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) compaction of materials; trimming.

Measurement

17.13

The measurement of the items under the sub-heading Levelling course shall be the plan area of the levelling course as shown on Drawings.

Sub-heading
Notes I.

BERMSTONES
Separate items shall be provided for under the sub-heading Bermstones in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and lay bermstones

square metre

II

1.

different sizes

III

1.

different thicknesses

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

17.14

Item description and unit shall be:

163

Item description Bermstones 17.14.1 Supply and lay bermstones, one tonne in size, 600 mm thick

Unit

square metre

Item description extension

17.15

The item description of the items under the sub-heading Bermstones shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) initial and final surveys; marking the Site with flags, marker buoys and lights; provision, maintenance and removal of temporary tide gauges; selection, separation and processing of materials; trimming; allowance for settlement and displacement of the underlying materials; filling the cavities beneath and between bermstones.

Measurement

17.16

The measurement of the items under the sub-heading Bermstones shall be the plan area of the bermstones as shown on Drawings.

Sub-heading
Notes K.

FENDERING
Separate items shall be provided for under the sub-heading Fendering in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply and install timber fendering Supply and install rubber fendering Supply and install stated types of fendering

cubic metre number number

II

1.

different types

L.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

17.17

Item description and unit shall be:

Item description Fendering 17.17.1 Supply and install timber fendering, type 1

Unit

cubic metre

164

17.17.2 17.17.3 Item description extension 17.18

Supply and install rubber fendering, type 2 Supply and install type 3 fendering

number number

The item description of the items under the sub-heading Fendering shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) accessories, fixings and fittings; protective treatment and painting.

Measurement

17.19

The measurement of the items for supply and install timber fendering under this sub-heading shall be the total volume of timber as shown on Drawings with no deduction made for bolt holes, notches and the like. The measurement of the items for supply and install rubber fendering and supply and install stated types of fendering under this sub-heading shall be of the complete fender as shown on Drawings.

17.20

Sub-heading
Notes M.

MARINE FITTINGS
Separate items shall be provided for under the sub-heading Marine fittings in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4.

Supply and install mooring eyes Supply and install bollards Supply and install tide gauges Supply and install stated marine fittings

number number number number

II

1.

different types

III

1.

different sizes

N.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

17.21

Item description and unit shall be:

Item description Marine fittings 17.21.1 Supply and install mooring eyes, as shown on Drawing No(s). _____ [Drawing No(s). to be stated
in the bill items]

Unit

number

165

17.21.2

Supply and install bollards, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

number

17.21.3

Supply and install tide gauges, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

number

Item description extension

17.22

The item description of the items under the sub-heading Marine fittings shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) casting or fixing into structures; protective treatment and painting; reinstatement; in the case of bollards, reinforcement, concrete plinth, filling metal collar with concrete.

Measurement

17.23

The measurement of the items under the sub-heading Marine fittings shall be for the complete fitting as shown on Drawings.

166

SECTION 18
Heading

TUNNELLING
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. No separate items are provided for probing ahead under this section 18. Where probing ahead is specifically required by the Engineer during excavation for tunnel works, it should be dealt with as a variation.

Notes

ii

Measurement

18.01

Tunnels constructed by cut and cover methods, if any, shall be measured in accordance with the Preamble and other relevant sections of the Method of Measurement and shall not be measured under this section 18.

Sub-heading

TEMPORARY EQUIPMENT
A.

TUNNELLING

FACILITIES

AND

Notes

Separate items shall be provided for under the sub-heading Temporary tunnelling facilities and equipment in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

4. 5.

Provision, maintenance and removal of temporary ventilation Provision, maintenance and removal of temporary lighting Provision, maintenance and removal of temporary fire protection measures Provision, maintenance and removal of temporary communication system Provision, setting up and removal of tunnel excavation equipment

sum sum sum

sum sum

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

18.02

Item description and unit shall be:

167

Item description Temporary tunnelling facilities and equipment 18.02.1 Provision, maintenance and removal of temporary ventilation Provision, maintenance and removal of temporary lighting Provision, maintenance and removal of temporary fire protection measures Provision, maintenance and removal of temporary communication system Provision, setting up excavation equipment and removal of tunnel

Unit

sum

18.02.2

sum

18.02.3

sum

18.02.4

sum

18.02.5

sum

Sub-heading
Notes C.

EXCAVATION
Separate items shall be provided for under the sub-heading Excavation in accordance with the following itemisation table:

Group

Feature

Unit

1 2. 3.

Excavation in tunnel by whatsoever means Excavation in shaft by whatsoever means Excavation for stated chamber by whatsoever means

metre metre cubic metre

II

1.

for different types of lining

III

1. 2.

straight curved

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

18.03

Item description and unit shall be:

168

Item description Excavation 18.03.1 Excavation in tunnel by whatsoever means, for in-situ concrete lining type A, curved Excavation in shaft by whatsoever means, for preformed segmental lining type B Excavation for chamber No. 1 by whatsoever means, for in-situ concrete lining type C

Unit

metre

18.03.2

metre

18.03.3

cubic metre

Item description extension

18.04

The item description of the items under the sub-heading Excavation shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) excavation in any material and disposal of any material; temporary drainage, protection and support; probing ahead or radially; formation, maintenance and reinstatement of temporary access tunnels and shafts; preparation and submission of records to the Engineer.

Measurement

18.05

The measurement of the items for excavation in tunnel by whatsoever means and excavation in shaft by whatsoever means under this sub-heading shall be the length of the lining of a particular type as shown on Drawings or ordered by the Engineer.

Sub-heading
Notes E.

IN-SITU CONCRETE LINING


Separate items shall be provided for under the sub-heading In-situ concrete lining in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Construction of in-situ lining in tunnel Construction of in-situ lining in shaft Construction of in-situ lining in stated chamber

concrete concrete concrete

metre metre cubic metre

II

1.

different types

III

1.

different grades of concrete

IV

1. 2.

straight curved

169

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

18.06

Item description and unit shall be:

Item description In-situ concrete lining 18.06.1 Construction of in-situ concrete lining in tunnel, type A, grade 40/20, straight Construction of in-situ concrete lining in shaft, type B, grade 40/20 Construction of in-situ concrete lining in chamber No. 1, type C, grade 40/20

Unit

metre

18.06.2

metre

18.06.3

cubic metre

Item description extension

18.07

The item description of the items under the sub-heading In-situ concrete lining shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) (h) (i) weep pipes, grout pipes, pipe sleeves and the like; waterbars and waterstops; forming holes, ducts, pockets, sockets, mortices and the like; waterproofing; formwork; reinforcement; drainage pipes and filter layers; grouting; chainage and level marks.

Measurement

18.08

The measurement of the items for construction of in-situ concrete lining in tunnel and construction of in-situ concrete lining in shaft under this sub-heading shall be the length along its axis. At junctions, measurement shall terminate at the external face of the lining to the adjoining tunnel or shaft. The measurement of the items for construction of in-situ concrete lining in stated chamber under this sub-heading shall be the difference between the volume of the concrete lining at the stated chamber indicated on Drawings and the volume of the regular in-situ concrete lining as shown on Drawings.

18.09

Sub-heading
Notes G.

PREFORMED SEGMENTAL LINING


Separate items shall be provided for under the sub-heading Preformed segmental lining in accordance with the following itemisation table:

170

Group

Feature

Unit

1. 2. 3. 4.

Supply and install precast reinforced concrete segmental lining Supply and install steel segmental lining Supply and install cast iron segmental lining Supply and install ductile iron segmental lining

metre metre metre metre

II

1.

different types or sizes

III

1. 2.

in tunnel in shaft

IV

1. 2.

straight curved

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

18.10

Item description and unit shall be:

Item description Preformed segmental lining 18.10.1 Supply and install precast reinforced concrete segmental lining, type A, in tunnel, straight Supply and install steel segmental lining, size B, in tunnel, curved Supply and install cast iron segmental lining, type C, in shaft Supply and install ductile iron segmental lining, size D, in shaft

Unit

metre

18.10.2

metre

18.10.3

metre

18.10.4

metre

Item description extension

18.11

The item description of the items under the sub-heading Preformed segmental lining shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) formwork; waterproofing; forming holes, ducts, pockets, sockets, mortices and the like; erection and fixing in position; steelwork;

171

(f) (g) (h) (i) Measurement 18.12

drainage pipes and filter layers; grouting; protective treatment and painting; chainage and level marks.

The measurement of the items under the sub-heading Preformed segmental lining shall be the length along its axis. At junctions, measurement shall terminate at the external face of the lining to the adjoining tunnel or shaft.

Sub-heading
Notes I.

STEEL LINING
Separate items shall be provided for under the sub-heading Steel lining in accordance with the following itemisation table:

Group

Feature

Unit

1.

Construction of steel lining

metre

II

1.

different thicknesses

III

1.

different diameters

IV

1.

different grades of steel

1. 2.

in tunnel in shaft

VI

1. 2.

straight curved

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

18.13

Item description and unit shall be:

Item description Steel lining 18.13.1 Construction of steel lining, __ mm thick, __ mm diameter, steel grade A, in tunnel, curved Construction of steel lining, __ mm thick, __ mm diameter, steel grade B, in shaft

Unit

metre

18.13.2

metre

172

Item description extension

18.14

The item description of the items under the sub-heading Steel lining shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) protective treatment and painting; chainage and level marks; internal lining to steel.

Measurement

18.15

The measurement of the items under the sub-heading Steel lining shall be the length measured along its axis. At junctions, measurement shall terminate at the external face of the lining to the adjoining tunnel or shaft.

Sub-heading
Notes K.

CONCRETE SURROUND TO STEEL LINING


Separate items shall be provided for under the sub-heading Concrete surround to steel lining in accordance with the following itemisation table:

Group

Feature

Unit

1.

Construction of concrete surround

metre

II

1.

different grades

III

1.

to different diameters of steel lining

IV

1. 2.

in tunnel in shaft

1. 2.

straight curved

L.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

18.16

Item description and unit shall be:

Item description Concrete surround to steel lining 18.16.1 Construction of concrete surround, grade 30/20, to __ mm diameter steel lining, in tunnel, curved

Unit

metre

173

18.16.2

Construction of concrete surround, grade 30/20, to __ mm diameter steel lining, in shaft

metre

Item description extension

18.17

The item description of the items under the sub-heading Concrete surround to steel lining shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) (h) (i) weep pipes, grout pipes, pipe sleeves and the like; waterbars and waterstops;; forming holes, ducts, pockets, sockets, mortices and the like; waterproofing; formwork; reinforcement; drainage pipes and filter layers; grouting; chainage and level marks.

Measurement

18.18

The measurement of the items under the sub-heading Concrete surround to steel lining shall be the length of steel lining surround measured along the axis of the steel lining. At junctions, measurement shall terminate at the external face of the adjoining tunnel or shaft lining.

Sub-heading
Notes M.

SPRAYED CONCRETE
Separate items shall be provided for under the sub-heading Sprayed concrete in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and cast sprayed concrete

square metre

II

1.

different grades

III

1.

different thicknesses of layer

IV

1. 2.

with steel fibres of different dosages with fabric reinforcement of different types

1. 2. 3.

to tunnel to shaft to stated chamber

N.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

174

Item description and unit

18.19

Item description and unit shall be:

Item description Sprayed concrete 18.19.1 Supply and cast sprayed concrete, grade 25D, in 25 mm thick layers, reinforced with steel fibres at __kg per cubic metre, to tunnel Supply and cast sprayed concrete, grade 25D, in 25 mm thick layers, reinforced with fabric reinforcement type A, to shaft

Unit

square metre

18.19.2

square metre

Item description extension

18.20

The item description of the items under the sub-heading Sprayed concrete shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) anchor bars; formwork; weepholes and filter materials.

Measurement

18.21

The items under the sub-heading Sprayed concrete shall only be measured if ordered by the Engineer and if they do not form part of a tunnel lining or junction measured under another item. The measurement of the items under the sub-heading Sprayed concrete shall be the surface area of the face to be covered. No allowance shall be made for surface irregularities or other local peculiarities.

18.22

Sub-heading
Notes O.

STEEL ARCH RIBS AND INVERT STRUTS


Separate items shall be provided for under the sub-heading Steel arch ribs and invert struts in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Supply and install steel arch ribs Supply and install steel invert struts

tonne tonne

II

1.

different types

III

1.

different grades of steel

P.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the

175

Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

18.23

Item description and unit shall be:

Item description Steel arch ribs and invert struts 18.23.1 Supply and install steel arch ribs, type D, steel grade 43 Supply and install steel invert struts, type E, steel grade 43

Unit

tonne

18.23.2

tonne

Item description extension

18.24

The item description of the items under the sub-heading Steel arch ribs and invert struts shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) detailed working drawings; excavation in any material and disposal of any material; backfilling with materials from any source and compaction; protective treatment and painting.

Measurement

18.25

The items under the sub-heading Steel arch ribs and invert struts shall only be measured if ordered by the Engineer and if they do not form part of a tunnel lining measured under another item. The measurement of the items under the sub-heading Steel arch ribs and invert struts shall be the total weight of the ribs or struts excluding the weights of base plates, bolts, nuts, washers, spacer bars and the like. No deduction shall be made for bolt holes.

18.26

Sub-heading
Notes Q.

JUNCTIONS
Separate items shall be provided for under the sub-heading Junctions in accordance with the following itemisation table:

Group

Feature

Unit

1.

Construction of junctions

number

II

1. 2.

3.

between tunnels with stated types of lining between tunnel with stated type of lining and shaft with stated type of lining between different stated types of lining

R.

The Method of Measurement shall contain item descriptions and

176

units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

18.27

Item description and unit shall be:

Item description Junctions 18.27.1 Construction of junctions, between tunnels with in-situ concrete lining and pre-cast reinforced concrete segmental lining Construction of junctions, between tunnel with steel segmental lining and shaft with cast iron segmental lining Construction of junctions, between in-situ concrete lining and pre-cast reinforced concrete segmental lining

Unit

number

18.27.2

number

18.27.3

number

Item description extension

18.28

The item description of the items under the sub-heading Junctions shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) excavation in any material and disposal of any material; supply, install and construct all types of lining including concrete surround to steel lining; sprayed concrete.

177

SECTION 19
Heading

GEOTECHNICAL WORKS
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. Where items for soil nails and erosion control under this section 19 are included in the Contract, the corresponding Particular Specification Clauses should also be included.

Notes

ii

Measurement

19.01

Buttresses, if any, shall be measured in accordance with the Preamble and the relevant sections for Earthworks, Formwork, Steel Reinforcement and Concrete of the Method of Measurement and shall not be measured under this section 19.

Sub-heading
Notes A.

SLOPE INSPECTION FACILITIES


Separate items shall be provided for under the sub-heading Slope inspection facilities in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Provision, maintenance and removal of inspection scaffolding Stripping of slope surfaces

square metre square metre

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

19.02

Item description and unit shall be:

Item description Slope inspection facilities 19.02.1 Provision, maintenance and removal of inspection scaffolding Stripping of slope surfaces

Unit

square metre

19.02.2 Item description extension 19.03

square metre

The item description of the items for provision, maintenance and removal of inspection scaffolding under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows:

178

(a) (b) 19.04

safety ropes and harnesses; platforms, ramps, protection fences and barriers.

The item description of the items for stripping of slope surfaces under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) excavation in any material and disposal of any material, including but not limited to topsoil and existing impermeable surfaces of any kind; temporary protection of stripped areas; reinstatement.

(b) (c) Measurement 19.05

The measurement of the items for provision, maintenance and removal of inspection scaffolding under this sub-heading shall be the surface area of the face to be covered by the scaffolding. No allowance shall be made for surface irregularities or other local peculiarities. The items for provision, maintenance and removal of inspection scaffolding under this sub-heading shall only be measured if ordered by the Engineer. The measurement of the items for stripping of slope surfaces under this sub-heading shall be the surface area of the area or face ordered to be stripped. No allowance shall be made for surface irregularities or other local peculiarities. The items for stripping of slope surfaces under this sub-heading shall only be measured if it is required to be carried out in a separate operation prior to excavation or slope treatment works for slope inspection purpose where no further excavation works is required, or if ordered by the Engineer.

19.06

19.07

19.08

Sub-heading
Notes C.

ROCK SLOPE TREATMENT WORKS


Separate items shall be provided for under the sub-heading Rock slope treatment works in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5.

Scaling and trimming of rock slopes Splitting of rock Removal of boulders Sealing and infilling of rock joints Supply and fix protective mesh for slopes

square metre square metre cubic metre cubic metre square metre

II

1.

different types of mesh

179

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

19.09

Item description and unit shall be: Item description Rock slope treatment works Unit

19.09.1 19.09.2 19.09.3 19.09.4

Scaling and trimming of rock slopes Splitting of rock Removal of boulders Sealing and infilling of rock joints, as shown on Drawing No(s). _____ [Drawing No(s). to be stated
in the bill items]

square metre square metre cubic metre cubic metre

19.09.5

Supply and fix protective with mesh for slopes, as shown on Drawing No(s). _____ [Drawing No(s). to
be stated in the bill items]

square metre

Item description extension

19.10

The item description of the items for scaling and trimming of rock slopes, splitting of rock and removal of boulders under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) excavation in any material and disposal of any material.

19.11

The item description of the items for sealing and infilling of rock joints under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) excavation in any material and disposal of any material, including but not limited to materials in the joints and existing unsuitable infill; weepholes and filter materials; infilling or sealing materials including but not limited to concrete, cement mortar and masonry.

(b) (c) Measurement 19.12

The measurement of the items for scaling and trimming of rock slopes and splitting of rock under this sub-heading shall be the surface area of the face to be treated as ordered by the Engineer. No allowance shall be made for surface irregularities or other local peculiarities. The measurement of the items for removal of boulders under this sub-heading shall be the portion of rocks or boulders, other than those required to be cut back in the Contract, which are ordered to be removed by the Engineer. Only rocks or boulders on slope surface that cannot be removed without the use of powered mechanical equipment and exceeding 0.2 cubic metres before removal shall be measured. No measurement shall be made for overbreak.

19.13

180

19.14

The measurement of the items for sealing and infilling of rock joints under this sub-heading shall be the volume of materials used for filling and sealing the rock joints and shall only be made if ordered by the Engineer. The measurement of the items for supply and fix protective mesh for slopes under this sub-heading shall be the surface area of the face to be protected. No allowance shall be made for surface irregularities or other local peculiarities. No deduction shall be made for openings each not exceeding one square metre.

19.15

Sub-heading
Notes E.

RELIEF DRAINS
Separate items shall be provided for under the sub-heading Relief drains in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and fix relief drains

metre

II

1.

different sizes

III

1.

different locations

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

19.16

Item description and unit shall be:

Item description Relief drains 19.16.1 Item description extension 19.17 Supply and fix relief drains, 200 mm wide

Unit

metre

The item description of the items under the sub-heading Relief drains shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) excavation in any material and disposal of any material, including but not limited to materials from joints, faults and discontinuities; trial length of relief drains; weepholes and filter materials; connecting to weepholes and outlets.

(b) (c) (d)

181

Measurement

19.18

The measurement of the items under the sub-heading Relief drains shall be along the centreline of the relief drain installed.

Sub-heading
Notes G.

RAKING DRAINS
Separate items shall be provided for under the sub-heading Raking drains in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4.

Provision and removal of rigs Setting up rigs Drilling for raking drains Supply and install raking drains

sum number metre metre

II

1. 2. 3. 4. 5.

vertically downwards downwards at an angle 0 - 45 to the vertical horizontally or downwards at an angle less than 45 to the horizontal upwards at an angle 0 - 45 to the horizontal upwards at an angle less than 45 to the vertical

III

1.

different diameters

IV

1.

different types of raking drain

1. 2.

length not exceeding 25.00 m length exceeding 25.00 m but not exceeding 40.00 m and so on in steps of 15.00 m

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

19.19

Item description and unit shall be:

Item description Raking drains 19.19.1 Provision and removal of rigs

Unit

sum

182

19.19.2 19.19.3

Setting up rigs Drilling for raking drains, upwards at an angle 0 - 45 to the horizontal, 55 mm diameter, length not exceeding 25.00 m Supply and install raking drains, upwards at an angle 0 - 45 to the horizontal, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], Type 2, length exceeding 25.00 m but not exceeding 40.00 m

number metre

19.19.4

metre

Item description extension

19.20

The item description of the items for provision and removal of rigs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provision and removal of all ancillary equipment.

19.21

The item description of the items for setting up rigs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) moving rigs and all ancillary equipment set up between hole locations; relocation of drain hole locations as instructed by the Engineer; site clearance and reinstatement.

19.22

The item description of the items for drilling for raking drains under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) sampling for undistributed soil samples and rock cores; disposal of any material.

Measurement

19.23

The measurement of the items for provision and removal of rigs under this sub-heading shall be for bringing rigs and all ancillary equipment to the Site and their subsequent removal off the Site. The measurement of the items for setting up rigs under this sub-heading shall correspond to the number of drain holes as shown on Drawings or ordered by the Engineer. The measurement of the items for drilling for raking drains under this sub-heading shall be the drilled length of the drain holes. The measurement of the items for supply and install raking drains under this sub-heading shall be the length of the raking drains installed. If the length of a raking drain installed in accordance with the contract requirement is outside the length ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

19.24

19.25

19.26

19.27

183

Sub-heading
Notes I.

PREFABRICATED BAND DRAINS


Separate items shall be provided for under the sub-heading Prefabricated band drains in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Provision and removal of rigs Setting up rigs Supply and install prefabricated band drains

sum number metre

II

1. 2.

length not exceeding 10.00 m length exceeding 10.00 m but not exceeding 20.00 m and so on in steps of 10.00 m

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

19.28

Item description and unit shall be:

Item description Prefabricated band drains 19.28.1 19.28.2 19.28.3 Provision and removal of rigs Setting up rigs Supply and install prefabricated band drains, length not exceeding 10.00 m

Unit

sum number metre

Item description extension

19.29

The item description of the items for provision and removal of rigs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provision and removal of all ancillary equipment.

19.30

The item description of the items for setting up rigs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) moving rigs and all ancillary equipment set up between drain locations; site clearance and reinstatement.

184

Measurement

19.31

The measurement of the items for provision and removal of rigs under this sub-heading shall be for bringing rigs and all ancillary equipment to the Site and their subsequent removal off the Site. The measurement of the items for setting up rigs under this sub-heading shall correspond to the number of prefabricated band drains as shown on Drawings or ordered by the Engineer. If the length of a prefabricated band drain installed in accordance with the contract requirement is outside the length ranges of the corresponding items provided in the bills, such work shall be deemed to be an item omitted from the Bills of Quantities stated under GCC Clause 59(3).

19.32

19.33

Sub-heading
Notes K.

GROUTING FOR GEOTECHNICAL WORKS


Separate items shall be provided for under the sub-heading Grouting for geotechnical works in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5.

Provision, setting up and removal of drilling and grouting plants Drilling for geotechnical works Grouting with cement Grouting with silicate based chemicals Grouting with stated chemicals

sum metre tonne tonne tonne

II

1. 2. 3. 4. 5.

vertically downwards downwards at an angle 0 - 45 to the vertical horizontally or downwards at an angle less than 45 to the horizontal upwards at an angle 0 - 45 to the horizontal upwards at an angle less than 45 to the vertical

III

1. 2.

in rock or artificial hard materials in materials other than rock or artificial hard materials

IV

1. 2.

from the surfaces from the tunnels

L.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

185

Item description and unit

19.34

Item description and unit shall be:

Item description Grouting for geotechnical works 19.34.1 Provision, setting up and removal of drilling and grouting plants Drilling for geotechnical works, vertically downwards, in rock or artificial hard materials, from the surfaces Grouting with cement Grouting with silicate based chemicals

Unit

sum

19.34.2

metre

19.34.3 19.34.4 Item description extension 19.35

tonne tonne

The item description of the items for provision, setting up and removal of drilling and grouting plants under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) provision and removal of all ancillary equipment including but not limited to pumps, mixers and the like; moving drilling and grouting plants and all ancillary equipment set up between hole locations; relocation of grout hole locations as instructed by the Engineer; site clearance and reinstatement.

19.36

The item description of the items for drilling for geotechnical works under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) modifying the drilling pattern to take into account locations of underground utilities and obstructions and redrilling; standpipes and capping pipes; disposal of any material; reinstatement.

19.37

The item description of the items for grouting with cement, grouting with silicate based chemicals and grouting with stated chemicals under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) making good grout holes after grouting; dealing with loss or leakage of grout; monitoring of grouting operations.

Measurement

19.38

The items under the sub-heading Grouting for geotechnical works shall only be measured if ordered by the Engineer. The measurement of the items for drilling for geotechnical works under this sub-heading shall be the drilled length of the grout holes.

19.39

186

19.40

The measurement of the items for grouting with cement, grouting with silicate based chemicals and grouting with stated chemicals under this sub-heading shall be the dry weight of the cement or chemicals in the grout solution.

Sub-heading
Notes M.

ROCK DOWELS
Separate items shall be provided for under the sub-heading Rock dowels in accordance with the following itemisation table:

Group

Feature

Unit

1.

Supply and install rock dowels

number

II

1.

different types of material

III

1.

different diameters and lengths of dowel

N.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

19.41

Item description and unit shall be:

Item description Rock dowels 19.41.1 Supply and install rock dowels, high yield steel, 16 mm diameter, 2000 mm long

Unit

number

Item description extension

19.42

The item description of the items under the sub-heading Rock dowels shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) drilling in any material and grouting; protective treatment and painting.

Sub-heading
Notes O.

ROCK BOLTS
Separate items shall be provided for under the sub-heading Rock bolts in accordance with the following itemisation table:

187

Group

Feature

Unit

1 2. 3.

Provision and removal of rigs Setting up rigs Supply and install rock bolts

sum number number

II

1.

different types

III

1.

different free lengths

IV

1.

different working loads

P.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

19.43

Item description and unit shall be:

Item description Rock bolts 19.43.1 19.43.2 19.43.3 Provision and removal of rigs Setting up rigs Supply and install rock bolts, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 1000 mm free length, 100 kN working load

Unit

sum number number

Item description extension

19.44

The item description of the items for provision and removal of rigs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provision and removal of all ancillary equipment.

19.45

The item description of the items for setting up rigs under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) moving rigs and all ancillary equipment set up; relocation of rock bolt locations as instructed by the Engineer; site clearance and reinstatement.

19.46

The item description of the items for supply and install rock bolts under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) drilling in any material and grouting;

188

(b) (c) (d) (e) (f)

reinforcement, formwork and concrete; excavation in any material and disposal of any material; protective treatment and painting; stressing, proving and re-stressing of rock bolts; construction of rock bolts for pull-out trials and subsequent removal and reinstatement as instructed by the Engineer.

Measurement

19.47

The measurement of the items for provision and removal of rigs under this sub-heading shall be for bringing rigs and all ancillary equipment to the Site and their subsequent removal off the Site. The measurement of the items for setting up rigs under this sub-heading shall correspond to the number of rock bolts as shown on Drawings or ordered by the Engineer.

19.48

Sub-heading
Notes Q.

SURFACE PROTECTION
Separate items shall be provided for under the sub-heading Surface protection in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Provision of chunam for surface protection Provision of sprayed concrete for surface protection

square metre square metre

II

1.

different thicknesses of layer

III

1.

different grades of concrete

IV

1.

with steel fabric reinforcement of different BS references

1.

different colouring methods

R.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

19.49

Item description and unit shall be:

189

Item description Surface protection 19.49.1 Provision of chunam for surface protection, 50 mm thick Provision of sprayed concrete for surface protection, 150mm thick, Grade 20 concrete, with 1 layer of A252 mesh, with painting as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

Unit

square metre

19.49.2

square metre

Item description extension

19.50

The item description of the items under the sub-heading Surface protection shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) weepholes and filter materials; dowels; formwork.

Measurement

19.51

The items under the sub-heading Surface protection shall only be measured if ordered by the Engineer or shown on Drawings and shall be measured as the surface area of the face to be covered. No allowance shall be made for surface irregularities or other local peculiarities. No deduction shall be made for holes and the like each not exceeding 0.1 square metres.

Sub-heading
Notes S.

GROUNDWATER CONTROL AND DRAWDOWN


Separate items shall be provided for under the sub-heading Groundwater control and drawdown in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Dewatering Arrange and conduct groundwater recharge

sum sum

II

1.

different locations

T.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

19.52

Item description and unit shall be:

190

Item description Groundwater control and drawdown 19.52.1 19.52.2 Dewatering, at location A Arrange and conduct groundwater recharge, at location B

Unit

sum sum

Item description extension

19.53

The item description of the items for dewatering under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) discharging of water; silt-traps; monitoring of groundwater levels and ground movement.

19.54

The item description of the items for arrange and conduct groundwater recharge under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) supply of water; monitoring of groundwater levels and ground movement.

Measurement

19.55

The measurement of the items under the sub-heading Groundwater control and drawdown shall be for the complete installation and operation and shall only be measured if ordered by the Engineer.

Sub-heading
Notes U.

SOIL NAILS
Separate items shall be provided for under the sub-heading Soil nails in accordance with the following itemisation table:

Group

Feature

Unit

1.

2. 3. 4. 5. 6. 7.

Provision and removal of rigs for soil nails construction and pull-out tests Setting up rigs for soil nails construction and pull-out tests Construction of soil nails Arrange and conduct pull-out tests Extra over for permanent steel casing Extra over for grouting of soil nails with excessive grout loss Extra over for enlarged soil nail heads

sum

number number number metre cubic metre number

II

1.

different types

191

Group

Feature

Unit

III

1. 2.

different thicknesses of permanent steel casing different size of enlarged soil nail heads

IV

1.

different diameters of bar

1.

different lengths

VI

1.

different diameters of hole

VII

1. 2.

vertically downwards horizontally or downwards at an angle less than 45 to the horizontal

V.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

19.56

Item description and unit shall be:

Item description Soil nails 19.56.1 Provision and removal of rigs for soil nails construction and pull-out tests Setting up rigs for soil nails construction and pull-out tests Construction of soil nails, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 25 mm diameter bar, 10.00 m in length in hole of 100 mm diameter, horizontally at an angle less than 45 to the horizontal Arrange and conduct pull-out tests Extra over for permanent steel casing, minimum 6 mm thick Extra over for grouting of soil nails with excessive grout loss

Unit

sum

19.56.2

number

19.56.3

number

19.56.4 19.56.5

number metre

19.56.6

cubic metre

Item description extension

19.57

The item description of the items for provision and removal of rigs for soil nails construction and pull-out tests under this sub-heading shall be

192

extended in accordance with Preamble paragraph 1.8 and as follows: (a) 19.58 provision and removal of all ancillary equipment.

The item description of the items for setting up rigs for soil nails construction and pull-out tests under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) moving rigs and all ancillary equipment set up between hole locations; relocation of hole locations as instructed by the Engineer; site clearance and reinstatement.

19.59

The item description of the items for construction of soil nails under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) drilling in any material and grouting; reinforcement, formwork and concrete; excavation in any material and disposal of any material; protective treatment and painting; uncover soil nail heads for examination /re-examination by the Engineer as specified, re-construct soil nail heads after examination /re-examination; reinstatement.

(f) 19.60

The item description of the items for arrange and conduct pull-out tests under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) construction of soil nails for testing; re-testing; grouting; reinstatement.

19.61

The item description of the items for extra over for permanent steel casing under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) excavation in any material and disposal of any material.

19.62

The item description of the items for extra over for grouting of soil nails with excessive grout loss under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) monitoring of grouting operations.

Measurement

19.63

The measurement of the items for provision and removal of rigs for soil nails construction and pull-out tests under this sub-heading shall be for bringing the rigs and all ancillary equipment to the Site and their subsequent removal off the Site.

193

19.64

The measurement of the items for setting up rigs for soil nails construction and pull-out tests under this sub-heading shall correspond to the number of soil nails constructed and the number of soil nails for pull-out tests as shown on Drawings or ordered by the Engineer. The measurement of the items for arrange and conduct pull-out tests under this sub-heading shall be the number of pull-out tests ordered by the Engineer. The measurement of the items for extra over for permanent steel casing under this sub-heading shall be the length of the casing permanently embedded in the ground as shown on Drawings or ordered by the Engineer. The items for extra over for grouting of soil nails with excessive grout loss under this sub-heading shall only be measured if ordered by the Engineer. The measurement shall be the volume of grout used for filling the drilled hole after a volume of grout exceeding the threshold volume of grout injected as specified in the Contract or ordered by the Engineer.

19.65

19.66

19.67

Sub-heading
Notes W.

EROSION CONTROL
Separate items shall be provided for under the sub-heading Erosion control in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Supply and install wire meshes Supply and install mats

square metre square metre

II

1.

different types

X.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

19.68

Item description and unit shall be:

Item description Erosion control 19.68.1 Supply and install wire meshes, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

Unit

square metre

19.68.2

Supply and install mats, polyethylene type

square metre

194

Item description extension

19.69

The item description of the items for supply and install mats under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) infilling voids within mats with filling materials.

Measurement

19.70

The measurement of the items under the sub-heading Erosion control shall be the surface area to be covered. No allowance shall be made for surface irregularities or other local peculiarities.

195

SECTION 22
Heading

BRICKWORK, BLOCKWORK AND MASONRY


i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading
Notes A.

BRICKWORK AND BLOCKWORK


Separate items shall be provided for under the sub-heading Brickwork and blockwork in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Construction of brickwork Construction of blockwork

square metre square metre

II

1.

different types

III

1.

different thicknesses

IV

1.

different bonds

1.

curved on plan

VI

1.

with a battered face

VII

1. 2. 3. 4.

in walls in facework in columns and piers in arches

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

196

Item description and unit

22.01

Item description and unit shall be:

Item description Brickwork and blockwork 22.01.1 Construction of brickwork, 200 x 100 x 75 mm clay brick in cement mortar, 100 mm thick, stretcher bond, in walls Construction of brickwork, 200 x 100 x 75 mm clay brick in cement mortar, 200 mm thick, English bond, in walls Construction of blockwork, 190 x 190 x 390 concrete blocks in cement mortar, 190 mm thick, stretcher bond, in walls

Unit

square metre

22.01.2

square metre

22.01.3

square metre

Item description extension

22.02

The item description of the items under the sub-heading Brickwork and blockwork shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) brick copings, bands, plinths, corbels, sills, bull-noses and the like; wall ties, dowels, mortar and the like or other fixing devices; bonding into existing work; reinforcement; filling the cavity between the brickwork, blockwork and the backing and finishing of joints; building in doors, windows, louvres and the like, and forming openings; damp proof courses.

Measurement

22.03

The measurement of the items under the sub-heading Brickwork and blockwork shall be the length or girth along the centreline multiplied by the vertical height stating the thickness, or in the case of walls with battered faces, stating the average thickness. No deduction shall be made for openings each not exceeding 0.10 square metres.

Sub-heading Measurement
Notes

MASONRY
22.04 The term masonry shall be taken for the purpose of this section 22 to include cast stonework.
Separate items shall be provided for under the sub-heading Masonry in accordance with the following itemisation table:

C.

197

Group

Feature

Unit

1. 2. 3. 4. 5.

6. 7.

Construction of mass masonry Construction of masonry facings Construction of masonry walls Construction of masonry copings Construction of specially shaped and dressed string courses of masonry Construction of masonry arches Construction of individual masonry blocks, features or stones

cubic metre square metre square metre metre metre

metre number

II

1.

different types

III

1.

different thicknesses

IV

1.

different coursing

1.

curved on plan

VI

1.

with a battered face

VII

1. 2. 3.

in lining to watercourses in pitching to slopes in facing to seawalls

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

22.05

Item description and unit shall be:

Item description Masonry 22.05.1 22.05.2 Construction of mass masonry, random rubble in cement mortar Construction of masonry facings, granite stone facing 100 mm thick to sloping planter wall as shown on Drawing No(s). _____ [Drawing No(s). to be stated in
the bill items]

Unit

cubic metre square metre

22.05.3

Construction of masonry walls, granite stone, 300 mm thick, with a battered face

square metre

198

22.05.4

Construction of masonry copings, granite stone curved on plan, 400 x 200 x 75 mm thick as shown on Drawing No(s). _____ [Drawing No(s). to be stated
in the bill items]

metre

22.05.5

Construction of specially shaped and dressed string courses of masonry, granite stone, as shown on Drawing No(s). _____ [Drawing No(s). to be stated
in the bill items]

metre

22.05.6

Construction of masonry arches, granite, as shown on Drawing No(s). _____ [Drawing No(s). to be stated
in the bill items]

metre

22.05.7

Construction of individual masonry features, granite stone planter, as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items], 1500 mm long

number

Item description extension

22.06

The item description of the items under the sub-heading Masonry shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) wall ties, dowels, mortar and the like or other fixing devices; bonding into or tying to existing work, concrete or other types of structures and finishing of joints; reinforcement; filling the cavity between the masonry and the backing; building in doors, windows, louvres and the like, and forming openings; damp proof courses; protection of masonry.

Measurement

22.07

For the items for construction of mass masonry under this sub-heading, no deduction shall be made from the measurement for voids each not exceeding 0.15 cubic metres. The measurement of the items for construction of masonry facings and construction of masonry walls under this sub-heading shall be the length or girth along the centreline multiplied by the vertical height stating the thickness, or in the case of walls with battered faces, stating the average thickness. No deduction shall be made for openings each not exceeding 0.10 square metres.

22.08

199

SECTION 23
Heading

FINISHINGS
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. The variety of different finishings available is too extensive to list in detail under the itemisation table hereunder. Different types of finishings shall be measured in an appropriately logical order with in-situ finishings measured before tile, slab and sheet finishings and followed by painting. Associated skirtings, nosings and the like shall follow the same order as the respective finishings to which they relate.

Notes

ii

Sub-heading
Notes A.

FINISHINGS
Separate items shall be provided for under the sub-heading Finishings in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply and lay/fix finishings Supply and apply painting Supply and lay/fix skirtings, nosings and the like

square metre square metre metre

II

1.

different types or compositions

III

1.

different sizes and/or thicknesses

IV

1. 2. 3. 4. 5.

to ceilings including sides and soffits of beams to walls and columns to floors to roofs to kerbs, treads, risers and the like

1.

curved

VI

1. 2.

internally externally

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of

200

Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

23.01

Item description and unit shall be:

Item description Finishings 23.01.1 Supply and lay finishings, ceramic tiles, size 150 x 150 x 8 mm, to walls and columns, internally Supply and lay finishings, wash granolithic, 25 mm thick, to floors, externally Supply and lay finishings, concrete tiles, size 300 x 300 x 30 mm, to roofs, externally Supply and apply painting, cement paint to walls and columns, externally Supply and lay nosings, vitreous clay tiles, size 75 x 150 x 10 mm, to treads, externally

Unit

square metre

23.01.2

square metre

23.01.3

square metre

23.01.4

square metre

23.01.5

metre

Item description extension

23.02

The item description of the items under the sub-heading Finishings shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) bedding, backing, bitumen, reinforcement and the like; edges, angles, corners, joints and the like including special tiles.

Measurement

23.03

The measurement of the items under the sub-heading Finishings shall be the area of the exposed face. No deduction shall be made for openings each not exceeding one square metre.

201

SECTION 24
Heading

LANDSCAPE WORKS
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading
Notes A.

PRE-PLANTING WORKS
Separate items shall be provided for under the sub-heading Pre-planting works in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5.

Cleaning ground Scarifying Ripping Cultivation Soiling

square metre square metre square metre square metre square metre

II

1.

different depths

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

24.01

Item description and unit shall be:

Item description Pre-planting works 24.01.1 24.01.2 24.01.3 24.01.4 24.01.5 Cleaning ground Scarifying, 10 to 20 mm deep Ripping, 300 mm deep Cultivation, 150 mm deep Soiling, 150 mm deep

Unit

square metre square metre square metre square metre square metre

202

Item description extension

24.02

The item description of the items for cleaning ground under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) excavation in any material and disposal of any material; filling the voids left by excavation and removal of contaminated materials.

24.03

The item description of the items for scarifying, ripping and cultivation under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) removal of stones and all debris produced by scarifying, ripping and cultivation, and disposal of any material; spreading of pre-planting fertilizer and soil conditioner before cultivation; protection of prepared ground against compaction, erosion and siltation.

24.04

The item description of the items for soiling under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) mixing, depositing, spreading, levelling and consolidation; protection of prepared ground against compaction, erosion and siltation; soil mix from any source.

Measurement

24.05

The measurement of the items under the sub-heading Pre-planting works shall be the surface area of the face to be prepared as shown on Drawings or ordered by the Engineer.

Sub-heading
Notes C.

PLANTING WORKS
Separate items shall be provided for under the sub-heading Planting works in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply and plant trees Supply and plant shrubs Supply and plant stated plants

number number number

II

1.

different species

III

1.

different sizes

IV

1. 2.

rootballed containerised

203

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

24.06

Item description and unit shall be:

Item description Planting works 24.06.1 Supply and plant trees, Acacia auriculaeformis, standard tree, containerised Supply and plant shrubs, Acalypha godseffiana, small shrub, containerised Supply and plant aquatic plants, Nelumbra nucifera, spread of plant 300 to 450 mm, containerised

Unit

number

24.06.2

number

24.06.3

number

Item description extension

24.07

The item description of the items under the sub-heading Planting works shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; fertilising, soil conditioning, mulching and top dressing; watering, weeding and pruning; stakes, ties, guys, sleeves and adjusters; reinstatement.

Sub-heading
Notes E.

GRASSING
Separate items shall be provided for under the sub-heading Grassing in accordance with the following itemisation table:

Group

Feature

Unit

1.

Grassing

square metre

II

1. 2. 3. 4.

by broadcast seeding by hydroseeding by turfing by sprigging

III

1.

different species

F.

The Method of Measurement shall contain item descriptions and units

204

for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

24.08

Item description and unit shall be:

Item description Grassing 24.08.1 Item description extension 24.09 Grassing, by hydroseeding, with grass seed mix

Unit

square metre

The item description of the items under the sub-heading Grassing shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) surface preparation, including removal of stones, disposal of any material, fine tilth cultivation and final grading; pegging, netting, sheeting and biodegradable fabric; fertilising, soil conditioning, mulching and top dressing; watering, weeding and cutting.

Measurement

24.10

The measurement of the items under the sub-heading Grassing shall be the surface area of the face to be grassed as shown on Drawings or ordered by the Engineer.

Sub-heading
Notes G.

POST-PLANTING MULCHING
Separate items shall be provided for under the sub-heading Post-planting mulching in accordance with the following itemisation table:

Group

Feature

Unit

1.

Post-planting mulching

square metre

II

1.

different thicknesses

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

24.11

Item description and unit shall be:

Item description Post-planting mulching 24.11.1 Post-planting mulching, 75 mm thick

Unit

square metre

205

Item description extension

24.12

The item description of the items under the sub-heading Post-planting mulching shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) storage; spreading and levelling.

Measurement

24.13

The measurement of the items under the sub-heading Post-planting mulching shall be the surface area of the face to be mulched after the planting work as shown on Drawings or ordered by the Engineer.

Sub-heading
Notes I.

ESTABLISHMENT WORKS
Separate items shall be provided for under the sub-heading Establishment Works in accordance with the following itemisation table:

Group

Feature

Unit

1.

Carry out Establishment Works

sum

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

24.14

Item description and unit shall be:

Item description Establishment Works 24.14.1 Item description extension 24.15 Carry out Establishment Works

Unit

sum

The item description of the items under the sub-heading Establishment Works shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) watering; control of pests and disease; protecting, including netting and sheeting; removal of all rubbish, stones and other debris, and disposal of any material; firming up plants; regrassing where the grass fails to become established; securing and adjusting stakes, ties and guys; plant replacements and replanting; fencing, signboards and notices; weeding, cutting grass, forking-over and pruning; application of post-planting fertilisers.

206

Notes

K.

Items under the sub-headings Preservation and protection of existing trees and Tree survey records are used for contracts where the existing trees requiring preservation and protection do not include Old and Valuable Trees. Items under the sub-headings Preservation and protection of existing trees including Old and Valuable Trees, Tree survey records of existing trees other than Old and Valuable Trees, Independent tree specialist and Aftercare to Old and Valuable Trees are used for contracts where the existing trees requiring preservation and protection include Old and Valuable Trees.

L.

Sub-heading

PRESERVATION AND PROTECTION OF EXISTING TREES


M. Separate items shall be provided for under the sub-heading Preservation and protection of existing trees in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1.

Preservation and protection of all existing trees

month

II

1.

in different Portions of the Site

N.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

24.16

Item description and unit shall be:

Item description Preservation and protection of existing trees 24.16.1 Preservation and protection of all existing trees, in Portion A of the Site

Unit

month

Item description extension

24.17

The item description of the items under the sub-heading Preservation and protection of existing trees shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) identification labelling or marking systems; temporary protective fencing/armouring/mulching; physical support measures to protect the trees from instability; measures to protect the trees from reduction in ground level, including construction of retaining wall, precautionary measures

207

(e) (f)

(g)

(h) (i)

(j) Measurement 24.18

during excavation and root cutting, and measures to maintain balanced moisture content after change in ground level; measures to protect the trees from rise in ground level, including construction of dry wall and soil aeration system; measures to protect the trees from excavation, including submission of photographic records, precautionary measures during excavation, tunnelling of services and root cutting, and measures to maintain balanced moisture content after excavation; measures to protect the trees from drilling, including precautionary measures during drilling and root cutting, and measures to maintain balanced moisture content after drilling; control of pests and disease; pruning of the trees, including pre-pruning preparation, pruning operation, post-pruning treatment, and reinstatement of affected areas; precautionary measures.

The measurement of the items for preservation and protection of all existing trees under this sub-heading shall be the duration in which preservation and protection measures for preserved trees are provided in accordance with the Contract.

Sub-heading
Notes O.

TREE SURVEY RECORDS


Separate items shall be provided for under the sub-heading Tree survey records in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Arrange and conduct tree survey of all existing trees submission of reports on updated photographic record of all preserved trees

sum number

P.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

24.19

Item description and unit shall be:

Item description Tree survey records 24.19.1 24.19.2 Arrange and conduct tree survey of all existing trees Submission of reports on updated photographic record of all preserved trees

Unit

sum number

208

Item description extension

24.20

The item description of the items for arrange and conduct tree survey of all existing trees under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) identification labelling or marking systems for trees to be felled.

24.21

The item description of the items for submission of reports on updated photographic record of all preserved trees under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) amending reports on the updated photographic record of the preserved trees.

Measurement

24.22

The measurement of the items for arrange and conduct tree survey of all existing trees under this sub-heading shall be made when the Engineer is satisfied that the survey record meets all requirements of the Contract. The measurement of the items for submission of reports on updated photographic record of all preserved trees under this sub-heading shall be the number of reports on updated photographic record of all preserved trees that are required to be submitted to the Engineer in accordance with the requirements stated in the Contract.

24.23

Sub-heading

PRESERVATION AND PROTECTION OF EXISTING TREES INCLUDING OLD AND VALUABLE TREES
Q. Separate items shall be provided for under the sub-heading Preservation and protection of existing trees including Old and Valuable Trees in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1.

2.

Preservation and protection of all existing trees other than Old and Valuable Trees Preservation and protection of Old and Valuable Trees

month

month

II

1. 2.

different Portions of the Site different Old and Valuable Trees [one item for each Old and Valuable Tree]

R.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

24.24

Item description and unit shall be:

209

Item description Preservation and protection of existing trees including Old and Valuable Trees 24.24.1 Preservation and protection of all existing trees other than Old and Valuable Trees, in Portion A of the Site Preservation and protection of Old and Valuable Trees, Old and Valuable Tree No. OVT 1

Unit

month

24.24.2

month

Item description extension

24.25

The item description of the items under the sub-heading Preservation and protection of existing trees including Old and Valuable Trees shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) identification labelling or marking systems; temporary protective fencing/armouring/mulching; physical support measures to protect the trees from instability; measures to protect the trees from reduction in ground level, including construction of retaining wall, precautionary measures during excavation and root cutting, and measures to maintain balanced moisture content after change in ground level; measures to protect the trees from rise in ground level, including construction of dry wall and soil aeration system; measures to protect the trees from excavation, including submission of photographic records, precautionary measures during excavation, tunnelling of services and root cutting, and measures to maintain balanced moisture content after excavation; measures to protect the trees from drilling, including precautionary measures during drilling and root cutting, and measures to maintain balanced moisture content after drilling; measures to control pest and disease for the trees, including precautionary measures to prevent pest and disease attack and control measures to eradicate pest and disease from the infected trees; pruning of the trees, including pre-pruning preparation, pruning operation, post-pruning treatment, and reinstatement of affected areas; precautionary measures.

(e) (f)

(g)

(h)

(i)

(j) Measurement 24.26

The measurement of the items for preservation and protection of all existing trees other than Old and Valuable Trees under this sub-heading shall be the duration in which preservation and protection measures for preserved trees other than Old and Valuable Trees are provided in accordance with the Contract. The measurement of the items for preservation and protection of Old and Valuable Trees under this sub-heading shall be the duration in which preservation and protection measures for Old and Valuable Trees are provided in accordance with the Contract.

24.27

210

Sub-heading

TREE SURVEY RECORDS OF EXISTING TREES OTHER THAN OLD AND VALUABLE TREES
S. Separate items shall be provided for under the sub-heading Tree survey records of existing trees other than Old and Valuable Trees in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1.

2.

Arrange and conduct tree survey of all existing trees other than Old and Valuable Trees Submission of reports on updated photographic record of all preserved trees other than Old and Valuable Trees

sum

number

T.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

24.28

Item description and unit shall be:

Item description Tree survey records of existing trees other than Old and Valuable Trees 24.28.1 Arrange and conduct tree survey of all existing trees other than Old and Valuable Trees Submission of reports on updated photographic record of all preserved trees other than Old and Valuable Trees

Unit

sum

24.28.2

number

Item description extension

24.29

The item description of the items for arrange and conduct tree survey of all existing trees other than Old and Valuable Trees under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) identification labelling or marking systems for trees to be felled.

24.30

The item description of the items for submission of reports on updated photographic record of all preserved trees other than Old and Valuable Trees under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) amending reports on the updated photographic record of the preserved trees.

211

Measurement

24.31

The measurement of the items for arrange and conduct tree survey of all existing trees other than Old and Valuable Trees under this sub-heading shall be made when the Engineer is satisfied that the survey record meets all requirements of the Contract. The measurement of the items for submission of reports on updated photographic record of all preserved trees other than Old and Valuable Trees under this sub-heading shall be the number of reports on updated photographic record of all preserved trees other than Old and Valuable Trees that are required to be submitted to the Engineer in accordance with the requirements stated in the Contract.

24.32

Sub-heading
Notes U.

INDEPENDENT TREE SPECIALIST


Separate items shall be provided for under the sub-heading Independent tree specialist in accordance with the following itemisation table:

Group

Feature

Unit

1.

Provision specialist

of

independent

tree

month

V.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

24.33

Item description and unit shall be:

Item description Independent tree specialist 24.33.1 Item description extension 24.34 Provision of independent tree specialist

Unit

month

The item description of the items under the sub-heading Independent tree specialist shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provision of facilities and attendance on the independent tree specialist.

Measurement

24.35

The measurement of the items under the sub-heading Independent tree specialist shall be the duration in which the services of an independent tree specialist is provided in accordance with the Contract.

Sub-heading
Notes W.

AFTERCARE TO OLD AND VALUABLE TREES


Separate items shall be provided for under the sub-heading Aftercare

212

to Old and Valuable Trees in accordance with the following itemisation table:

Group

Feature

Unit

1.

Provision of Aftercare to Old and Valuable Trees

month

II

1.

different Old and Valuable Trees [one item for each Old and Valuable Tree]

X.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

24.36

Item description and unit shall be:

Item description Aftercare to Old and Valuable Trees 24.36.1 Provision of Aftercare to Old and Valuable Trees, Old and Valuable Tree No. OVT 1

Unit

month

Item description extension

24.37

The item description of the items under the sub-heading Aftercare to Old and Valuable Trees shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) tree maintenance work, work of repair to damage or health deterioration, or precautionary or mitigation measures against damage; removal of all debris and disposal of any material; reinstatement.

(b) (c) Measurement 24.38

The measurement of the items under the sub-heading Aftercare to Old and Valuable Trees shall be the duration in which all requirements for providing Aftercare to Old and Valuable Trees as stated in the Contract are complied with.

213

SECTION 25
Heading

TESTING
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading
Notes A.

PILE TESTING
Separate items shall be provided for under the sub-heading Pile testing in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5. 6.

Provision, setting up and removal of all types of pile testing equipment Arrange and conduct load tests Arrange and conduct sonic tests Arrange and conduct core tests Arrange and conduct integrity tests Arrange and conduct proof drilling

sum number metre metre number number

II

1.

different types of test

III

1.

on different types of pile

IV

1. 2.

preliminary piling main piling

1.

load tests of different specified loads and/or different angles of application of load

VI

1.

different diameters of core

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

25.01

Item description and unit shall be:

214

Item description Piling testing 25.01.1 Provision, setting up and removal of all types of pile testing equipment Arrange and conduct load tests, compression load tests, on bored piles, main piling Arrange and conduct sonic tests, on 2.00 m diameter bored piles, preliminary piling Arrange and conduct core tests, on 2.00 m diameter bored piles, main piling, 150 mm (minimum) diameter cores Arrange and conduct integrity tests, on 2.00 m diameter bored piles, main piling Arrange and conduct proof drilling, on 2.00 m diameter bored piles, main piling

Unit

sum

25.01.2

number

25.01.3

metre

25.01.4

metre

25.01.5

number

25.01.6

number

Item description extension

25.02

The item description of the item for provision, setting up and removal of all types of pile testing equipment under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) provision, setting up and removal of all ancillary pile testing equipment including but not limited to test rigs, plant, instruments, kentledge and the like; moving pile testing equipment and all ancillary equipment set up between test sites; site clearance and reinstatement.

(b) (c) 25.03

The item description of the items for arrange and conduct load tests, arrange and conduct sonic tests, arrange and conduct core tests, arrange and conduct integrity tests and arrange and conduct proof drilling under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) drilling in any material, recovery and storage of cores; cutting and test of cores; construction of temporary pile caps and their subsequent removal; reinstatement; re-testing and additional testing.

Measurement

25.04

The measurement of the item for provision, setting up and removal of all types of pile testing equipment under this sub-heading shall be for bringing and setting up of all types of pile testing equipment and ancillary equipment to the Site for the execution and completion of the pile testing work at the required locations and their subsequent removal off the Site. The measurement of the items for arrange and conduct load tests, arrange and conduct integrity tests and arrange and conduct proof

25.05

215

drilling under this sub-heading shall be the number of tests ordered by the Engineer. 25.06 The measurement of the items for arrange and conduct sonic tests under this sub-heading shall be the total length of tested pile as ordered by the Engineer. The measurement of the items for arrange and conduct core tests under this sub-heading shall be the total length of pile drilled as ordered by the Engineer. Re-testing or additional testing where the original test has identified defective materials or workmanship shall not be measured.

25.07

25.08

Sub-heading
Notes C.

TESTING PRECAST CONCRETE MEMBERS


Separate items shall be provided for under the sub-heading Testing precast concrete members in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Arrange and conduct non-destructive tests Arrange and conduct destructive tests

number number

II

1.

different types of test

III

1.

different types of precast concrete member

IV

1.

different sizes of member

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

25.09

Item description and unit shall be:

216

Item description Testing precast concrete members 25.09.1 Arrange and conduct non-destructive tests, load testing of type A precast concrete units as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill items] Arrange and conduct destructive tests, load testing of type B precast concrete units as shown on Drawing No(s). _____ [Drawing No(s). to be stated in the bill
items]

Unit

number

25.09.2

number

Item description extension

25.10

The item description of the items under the sub-heading Testing precast concrete members shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) transportation of members to and erection at the place of test, and subsequent removal; in case of destructive tests, supply of the members.

Measurement

25.11

The measurement of the items under the sub-heading Testing precast concrete members shall be the number of tests ordered and accepted by the Engineer as giving satisfactory results. If a member is found to be unsatisfactory on testing, the testing of all other members in the same batch of members at the Contractors option shall not be measured.

Sub-heading
Notes E.

TESTING BEARINGS
Separate items shall be provided for under the sub-heading Testing bearings in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5. 6. 7. 8.

Arrange and conduct compression tests Arrange and conduct shear tests Arrange and conduct bond tests Arrange and conduct tests for physical properties Arrange and conduct weathering tests Arrange and conduct friction tests Arrange and conduct vertical load tests Arrange and conduct horizontal load tests

number number number number number number number number

II

1.

on different types of bearing

III

1.

different sizes of bearing

217

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

25.12

Item description and unit shall be:

Item description Testing bearings 25.12.1 Arrange and conduct compression tests, on bridge bearing ref. B1 Arrange and conduct shear tests, on bridge bearing ref. B2 Arrange and conduct bond tests, on bridge bearing ref. B3 Arrange and conduct tests for physical properties, quick production tests, on bridge bearing ref. B4 Arrange and conduct weathering tests, on bridge bearing ref. B5 Arrange and conduct friction tests, on bridge bearing ref. B6 Arrange and conduct vertical load tests, on bridge bearing ref. B7 Arrange and conduct horizontal load tests, on bearing to roof joint

Unit

number

25.12.2

number

25.12.3

number

25.12.4

number

25.12.5

number

25.12.6

number

25.12.7

number

25.12.8

number

Item description extension

25.13

The item description of the items under the sub-heading Testing bearings shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) in case of destructive tests, supply of the samples; re-testing.

Measurement

25.14

The measurement of the items under the sub-heading Testing bearings shall be the number of tests ordered and accepted by the Engineer as giving satisfactory results.

Sub-heading
Notes G.

PRESSURE TESTING PIPELINES


Separate items shall be provided for under the sub-heading Pressure testing pipelines in accordance with the following itemisation table:

218

Group

Feature

Unit

1.

Arrange and conduct pressure tests on pipelines

sum

II

1.

different types

III

1.

different locations

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

25.15

Item description and unit shall be:

Item description Pressure testing pipelines 25.15.1 Arrange and conduct pressure tests on pipelines, hydraulic pressure test, from Chainage A to Chainage B

Unit

sum

Item description extension

25.16

The item description of the items under the sub-heading Pressure testing pipelines shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) construction of temporary anchor or thrust blocks, and their subsequent removal; excavation in any material and disposal of any material; backfilling with materials from any source and compaction; water, taking delivery of water if supplied by the Employer, transporting to Site and/or point of use and draining on completion; re-testing; cleaning and sterilising.

(e) (f) Measurement 25.17

The measurement of the items under the sub-heading Pressure testing pipelines shall only be made upon the testing giving satisfactory results.

Sub-heading
Notes I.

TESTING WATER RETAINING STRUCTURES


Separate items shall be provided for under the sub-heading Testing water retaining structures in accordance with the following itemisation table:

219

Group

Feature

Unit

1.

Arrange and conduct tests on water retaining structures

sum

II

1.

different types structure

or

sections

of

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

25.18

Item description and unit shall be:

Item description Testing water retaining structures 25.18.1 Arrange and conduct tests on water retaining structures, aeration tank No. 1

Unit

sum

Item description extension

25.19

The item description of the items under the sub-heading Testing water retaining structures shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) taking delivery of water and sterilising chemicals supplied by the Employer, transporting to Site and/or point of use and draining on completion; taking delivery of testing equipment supplied by the Employer, transporting to Site and/or point of use and removal on completion of test; re-testing; cleaning and sterilising.

(b)

(c) (d)

220

SECTION 26
Heading

MISCELLANEOUS
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement.

Notes

Sub-heading

DOORS, WINDOWS, SHUTTERS


A.

LOUVRES

AND

ROLLER

Notes

Separate items shall be provided for under the sub-heading Doors, windows, louvres and roller shutters in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4.

Supply and fix doors Supply and fix windows Supply and fix louvres Supply and fix roller shutters

number number number number

II

1.

different types and/or materials

III

1.

different sizes

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

26.01

Item description and unit shall be:

Item description Doors, windows, louvres and roller shutters 26.01.1 Supply and fix doors, solid core hardwood door, size 1050 x 2100 mm as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

Unit

number

26.01.2

Supply and fix windows, galvanized mild steel, size 400 x 600 mm as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

number

221

26.01.3

Supply and fix louvres, aluminum, size 1000 x 1000 mm as shown on Drawing No(s). _____ [Drawing
No(s). to be stated in the bill items]

number

26.01.4

Supply and fix roller shutters, stainless steel, size 3000 x 2100 mm as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

number

Item description extension

26.02

The item description of the items under the sub-heading Doors, windows, louvres and roller shutters shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) steelwork, frames, guide rails, hoods, casings and the like; fixings, fittings, accessories, bedding, dowels, sealants and the like; glazing; fittings and furniture protective treatment and painting; weather bars, waterbars, waterstops and the like; ironmongery.

Sub-heading
Notes C.

PLUMBING
Separate items shall be provided for under the sub-heading Plumbing in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3.

Supply and fix pipes Extra over for valves or stopcocks Supply and fix sanitary appliances

metre number number

II

1.

different types and/or materials

III

1.

different sizes and/or diameters

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

26.03

Item description and unit shall be:

Item description Plumbing 26.03.1 Supply and fix pipes, copper pipe, 40 mm diameter

Unit

metre

222

26.03.2 26.03.3

Extra over for valves, 40mm diameter gate valves Supply and fix sanitary appliances, vitreous china wash basins, size 650 x 450 mm

number number

Item description extension

26.04

The item description of the items under the sub-heading Plumbing shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) fixings, fittings, accessories, bedding, pipe brackets and the like; connections to pipes; protective treatment and painting; in case of water supply pipes, cleansing and sterilisation, including taking delivery of water and chemicals supplied by the Employer, transportation to Site and/or point of use and draining on completion.

Sub-heading
Notes E.

SUNDRY METALWORK
Separate items shall be provided for under the sub-heading Sundry metalwork in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4.

Supply and fix flooring Supply and fix covers Supply and fix ladders Supply and fix step irons

square metre number number number

II

1.

different types and/or materials

III

1.

different sizes

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

26.05

Item description and unit shall be:

Item description Sundry metalwork 26.05.1 Supply and fix flooring, chequer plates, 8 mm thick as shown on Drawing No(s). _____ [Drawing No(s).
to be stated in the bill items]

Unit

square metre

26.05.2

Supply and fix covers, stainless steel, size 1000 x 1000 mm as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

number

223

26.05.3

Supply and fix ladders, galvanized mild steel cat ladders, 350 mm wide and 3000 mm high as shown on Drawing No(s). _____ [Drawing No(s). to be
stated in the bill items]

number

26.05.4

Supply and fix step irons, galvanized mild steel, 350 x 450 mm as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

number

Item description extension

26.06

The item description of the items under the sub-heading Sundry metalwork shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) building in, including fixings, grouting and bedding, fillers, sealing materials and the like; protective treatment and painting; insulation; frames; ironmongery.

Sub-heading
Notes G.

ASPHALT ROOFING
Separate items shall be provided for under the sub-heading Asphalt roofing in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Supply and lay asphalt roofing Supply and lay skirtings

square metre metre

II

1.

different thicknesses and/or sizes

III

1.

2.

3. 4.

horizontal surfaces and inclined o surfaces sloping at 30 or less to the horizontal vertical surfaces and inclined o surfaces sloping at more than 30 to the horizontal curved surfaces domed surfaces

H.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

26.07

Item description and unit shall be:

224

Item description Asphalt roofing 26.07.1 Supply and lay asphalt roofing, 20 mm thick, horizontal surfaces and inclined surfaces sloping at 30o or less to the horizontal Supply and lay skirtings, 150 mm high and 15 mm thick

Unit

square metre

26.07.2

metre

Item description extension

26.08

The item description of the items under the sub-heading Asphalt roofing shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) isolating membranes; forming angles and the like; dressing to rainwater outlets; in case of laying asphalt roofing, forming drainage channels; reinforcement; finishing roof surfaces; solar protection and painting.

Measurement

26.09

The measurement of the items for supply and lay asphalt roofing under this sub-heading shall be the plan area covered. No deduction shall be made for opening each not exceeding one square metre.

Sub-heading

WORK FOR ELECTRICAL INSTALLATIONS


I.

AND

MECHANICAL

Notes

Separate items shall be provided for under the sub-heading Work for electrical and mechanical installations in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4. 5. 6.

Supply and fix electrical conduit systems Supply and fix cable duct systems Supply and fix light fittings Construction of earthing pits Construction of earthing trenches Grouting with stated chemicals

metre metre number number metre square metre

II

1.

different types and/or materials

III

1. 2. 3.

different diameters different sizes different thicknesses

225

Group

Feature

Unit

IV

1.

different types surround or filling

of

bedding,

1. 2.

3. 4. 5. 6. 7. 8.

in trench, depth to invert not exceeding 1.50 m in trench, depth to invert exceeding 1.50 m but not exceeding 2.50 m and so on in steps of 1.00 m fixed to concrete fixed to brickwork or blockwork fixed to steelwork fixed to reinforcement fixed in chases fixed to stated supports or surfaces

J.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

26.10

Item description and unit shall be:

Item description Work for electrical and mechanical installations 26.10.1 Supply and fix electrical conduit systems, galvanized mild steel, 25 mm diameter, fixed to brickwork Supply and fix cable duct systems, UPVC, 50 mm diameter, on granular bed, in trench, depth to invert not exceeding 1.50 m Supply and fix light fittings, surface mounted type A, fixed to concrete Construction of earthing pits, size 1000 x 1000 x 750 mm deep as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

Unit

metre

26.10.2

metre

26.10.3

number

26.10.4

number

26.10.5

Construction of earthing trenches, 750 mm wide x 500 mm deep as shown on Drawing No(s). _____
[Drawing No(s). to be stated in the bill items]

metre

26.10.6

Grouting with cement and sand, 15 mm thick

square metre

226

Item description extension

26.11

The item description of the items for supply and fix electrical conduit systems and supply and fix cable duct systems under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) (h) (i) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; fixings, boxes, fittings, bedding, accessories, holes, recesses and the like; protective treatment and painting; fire barriers; in case of electrical conduit systems, terminations of the systems; cleaning of the systems; completion and protection of the work for electrical and mechanical installations; reinstatement.

26.12

The item description of the items for supply and fix light fittings under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) holes, bases, recesses and the like; internal wiring and connections; internal fuses, switches, cut-outs and the like.

26.13

The item description of the items for construction of earthing pits and construction of earthing trenches under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) (f) (g) excavation in any material and disposal of any material; backfilling with materials from any source and compaction; building in duct connections, including ducts and fittings; covers, frames and lifting keys; formwork; reinforcement and steelwork; fill materials in pits or trenches.

26.14

The item description of the items for grouting with stated chemicals under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) formwork.

227

SECTION 27
Heading

DAYWORK
i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. Separate items should be provided for Provisional Sums, and percentage adjustment thereto, for different categories of plant used on daywork in accordance with the relevant sections of the HKCA Schedules For Plant Used in Dayworks Carried Out Incidental to Contract Work.

Notes

ii

Sub-heading
Notes A.

LABOUR
Separate items shall be provided for under the sub-heading Labour in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

3.

Provision of labour working during normal working hours Provisional Sum for provision of labour working overtime, to be paid at rates for normal working hours (Note : the Provisional Sum shall be inserted in the Amount column of this item in the bill) Percentage adjustment to the Provisional Sum in item ___ for provision of labour working overtime (to be stated and extended by the tenderer) (Note : the Provisional Sum shall be inserted in the Quantity column of this item in the bill)

hour sum

percentage

II

1. 2.

different types of labour different periods of overtime

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

27.01

Item description and unit shall be:

228

Item description Labour 27.01.1 Provision of labour working during normal working hours, labourer (unskilled) male Provisional Sum for provision of labour working overtime, to be paid at rates for normal working hours, from 1800 hours to 2300 hours on all days excluding General Holidays and from 0800 hours to 2300 hours on General Holidays excluding Lunar New Year Holiday Percentage adjustment to the Provisional Sum in item
[item number as described in 27.01.2 to be stated]

Unit

hour

27.01.2

sum

27.01.3

percentage

for provision of labour working overtime (to be stated and extended by the tenderer) 27.01.4 Provisional Sum for provision of labour working overtime, to be paid at rates for normal working hours, from 2300 hours to 0800 hours next days excluding Lunar New Year Holidays Percentage adjustment to the Provisional Sum in item
[item number as described in 27.01.4 to be stated]

sum

27.01.5

percentage

for provision of labour working overtime (to be stated and extended by the tenderer) 27.01.6 Provisional Sum for provision of labour working overtime, to be paid at rates for normal working hours, from 0800 hours to 0800 hours next day on all days excluding Lunar New Year Holiday Percentage adjustment to the Provisional Sum in item
[item number as described in 27.01.6 to be stated]

sum

27.01.7

percentage

for provision of labour working overtime (to be stated and extended by the tenderer) 27.01.8 Provisional Sum for provision of labour working overtime, to be paid at rates for normal working hours, from 2300 hours to 0800 hours on Lunar New Year holidays Percentage adjustment to the Provisional Sum in item
[item number as described in 27.01.8 to be stated]

sum

27.01.9

percentage

for provision of labour working overtime (to be stated and extended by the tenderer) 27.01.10 Provisional Sum for provision of labour working overtime, to be paid at rates for normal working hours, from 0800 hours to 0800 hours next day on Lunar New Year Holiday sum

229

27.01.11

Percentage adjustment to the Provisional Sum in item


[item number as described in 27.01.10 to be stated]

percentage

for provision of labour working overtime (to be stated and extended by the tenderer) Item description extension 27.02 The item description of the items under the sub-heading Labour shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) (d) (e) Measurement 27.03 hand tools, ladders, trestles and the like; protective clothing and safety equipment; supervision; use of existing services and Temporary Works; travelling time to and from the Site.

The measurement of the items for provision of labour working during normal working hours under this sub-heading shall be the aggregate time employed on daywork to the nearest hour. Meal breaks and rest periods shall not be measured. Travelling time by the labour from their normal place of employment on the Site to and from the location where daywork is to be carried out shall be measured. Normal working hours shall be 0800 hours to 1800 hours or such other periods as stated in the Contract on all days excluding General Holidays. Daywork ordered by the Engineer to be executed outside the normal working hours shall be measured as overtime. Overtime shall be paid at the rates for normal working hours plus a percentage to be inserted by the tenderer. Voluntary overtime on all days including General Holidays will be measured as normal working hours. Voluntary overtime is when the Contractor elects to execute daywork outside the normal working hours. If, in the opinion of the Engineer, daywork is ordered to be carried out under dangerous or exceptionally foul conditions, then the labour shall be measured as 1.5 times the time spent working under such conditions.

Sub-heading
Notes C.

PLANT
Separate items shall be provided for under the sub-heading Plant in accordance with the following itemisation table:

Group

Feature

Unit

1.

2.

Provisional Sum for provision of plant (Note : the Provisional Sum shall be inserted in the Amount column of this item in the bill) Percentage adjustment to the Provisional Sum in item ___ for provision of plant (to be stated and extended by the tenderer) (Note : the Provisional Sum shall be inserted in the Quantity column of this item in the bill)

sum

percentage

230

Group

Feature

Unit

II

1.

different categories of plant

III

1.

different items for Provisional Sum

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

27.04

Item description and unit shall be:

Item description Plant 27.04.1 Provisional Sum for provision of plant, at rates contained in Section ___ of the HKCA Schedules For Plant Used in Dayworks Carried Out Incidental to Contract Work Percentage adjustment to the Provisional Sum in item
[item number as described in 27.04.1 to be stated]

Unit

sum

27.04.2

percentage

for provision of plant (to be stated and extended by tenderer) Item description extension 27.05 The item description of the items under the sub-heading Plant shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) Measurement 27.06 fuel, consumable stores, insurance, repairs and maintenance.

The rates contained in the HKCA Schedules For Plant Used in Dayworks Carried Out Incidental to Contract Work current at the date for return of Tender (the Schedules) shall be used for provision of plant on daywork. The Notes and Conditions contained therein do not form part of the Method of Measurement. The rates shall be exclusive of drivers and attendants. Minimum measurement shall be for the basic hire period quoted in the Schedules under each item. An additional 3 hours is to be measured for each item of land-based plant, and an additional 6 hours for each item of marine plant, specially brought on Site on the instructions of the Engineer to carry out daywork, and a further 3 hours or 6 hours for each such respective item of plant that is removed from Site on completion of the daywork. 6 hours is to be measured for any transport used to carry or tow land-based plant, and 12 hours for any transport used to carry or tow marine plant, to Site for use on daywork, or used for their respective removal from Site on completion of the daywork.

231

For land-based plant mounted on marine craft, the percentage adjustment appropriate to marine plant shall apply to the rates quoted for the land-based plant in the Schedules. On-site transportation of labour, materials or plant used on daywork to or from the daywork location is to be measured. Standing time shall be included in the measurement of the items for provision of plant under this sub-heading where the nature of the daywork requires intermittent working. Where standing time for any item for provision of plant is ordered by the Engineer, such plant shall be measured as two thirds of the time standing during normal working hours. Sub-heading
Notes E.

MATERIALS
Separate items shall be provided for under the sub-heading Materials in accordance with the following itemisation table:

Group

Feature

Unit

1.

2.

Provisional Sum for provision of materials (Note : the Provisional Sum shall be inserted in the Amount column of this item in the bill) Percentage adjustment to the Provisional Sum for provision of materials (to be stated and extended by the tenderer) (Note : the Provisional Sum shall be inserted in the Quantity column of this item in the bill)

sum

percentage

F.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

27.07

Item description and unit shall be:

Item description Materials 27.07.1 27.07.2 Provisional Sum for provision of materials Percentage adjustment to the Provisional Sum for provision of materials (to be stated and extended by the tenderer)

Unit

sum percentage

232

Item description extension

27.08

The item description of the items for percentage adjustment to the Provisional Sum for provision of materials under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) taking delivery, unloading, unpacking, storing and protecting.

Measurement

27.09

The measurement of the items for provision of materials under this sub-heading shall be the actual quantity of materials incorporated in the Works measured on a daywork basis except if the materials are only obtainable in minimum quantities, then any surplus materials arising therefrom and which cannot otherwise be used in the Works shall also be measured. Such surplus materials may be retained for use by the Employer or disposed of, as directed by the Engineer. Payment shall be made at invoiced cost after the deduction of all discounts obtained by the Contractor but inclusive of any suppliers delivery charges to the Site. Collection and distribution of materials by the Contractor shall be measured under the sub-headings Labour and/or Plant as appropriate.

233

SECTION 28
Heading

SITE SAFETY MANAGEMENT


i

AND

ENVIRONMENTAL

Notes

These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. For lump sum works contracts, the items under this section 28 shall be marked as ALL PROVISIONAL. For works contracts where Safety Plans are not required and therefore not included in the Pay for Safety and Environment Scheme, this section 28 shall not be used.

ii

iii

Measurement

28.01

Rates appearing in the items under this section 28, whether pre-fixed or inserted by the Contractor, shall be deemed to allow for the value of work in connection with meeting all statutory and contractual obligations in the upkeeping of safety and health and environmental management in the execution of the Works and any other related obligations, liabilities, risks and profit. In the event that the rates have been insufficient or where there are any aspects where the methods provided hereunder do not measure any item of work or exclude the measurement of any item of work or part thereof, the difference in value shall be deemed to have been included in the rates inserted elsewhere in the bills within the Bills of Quantities.

Sub-heading

SAFETY PLAN AND MANAGEMENT PLAN


A.

ENVIRONMENTAL

Notes

Separate items shall be provided for under the sub-heading Safety Plan and Environmental Management Plan in accordance with the following itemisation table:

Group

Feature

Unit

1. 2. 3. 4.

Complete and distribute Safety Plan Complete and distribute Environmental Management Plan Update Safety Plan Update Environmental Management Plan

sum sum month month

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

234

Item description and unit

28.02

Item description and unit shall be:

Item description Safety Plan and Environmental Management Plan 28.02.1 28.02.2 Complete and distribute Safety Plan Complete and distribute Environmental Management Plan Update Safety Plan Update Environmental Management Plan

Unit

sum sum

28.02.3 28.02.4 Measurement 28.03

month month

The item for complete and distribute Safety Plan under this sub-heading shall be measured when the Engineer is satisfied that the Safety Plan has been completed and it meets all the requirements of the Contract at the time of its completion and copies distributed. The item for complete and distribute Environmental Management Plan under this sub-heading shall be measured when the Engineer is satisfied that the Environmental Management Plan has been completed and it meets all the requirements of the Contract at the time of its completion and copies distributed. The measurement of the item for update Safety Plan under this sub-heading shall be the period of time commencing from the date of distribution of the completed Safety Plan until the date of substantial completion of the Works, or where the Works are divided into Sections, the date of substantial completion of the last Section of the Works, or an earlier or later date notified by the Engineer. No measurement shall be made for the item for update Safety Plan under this sub-heading for any period of time in which the Contractor fails to discharge any of its contractual obligations in respect of reviewing, revising, updating or distribution of the Safety Plan. The measurement of the item for update Environmental Management Plan under this sub-heading shall be the period of time commencing from the date of distribution of the completed Environmental Management Plan until the date of substantial completion of the Works, or where the Works are divided into Sections, the date of substantial completion of the last Section of the Works, or an earlier or later date notified by the Engineer. No measurement shall be made for the item for update Environmental Management Plan under this sub-heading for any period of time in which the Contractor fails to discharge any of its contractual obligations in respect of reviewing, revising, updating or distribution of the Environmental Management Plan.

28.04

28.05

28.06

28.07

28.08

235

Sub-heading
Notes C.

SAFETY OFFICER AND ENVIRONMENTAL OFFICER


Contract drafter should amend the sub-heading to Safety Officer and delete/amend the paragraphs and phrases relating to Environmental Officer as appropriate if the Contract does not require an Environmental Officer or if the Contract only requires an Assigned Person to oversee the environmental matters. Separate items shall be provided for under the sub-heading Safety Officer and Environmental Officer in accordance with the following itemisation table:

D.

Group

Feature

Unit

1. 2.

Provision of Safety Officer Provision of Environmental Officer

number-month number-month

E.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

28.09

Item description and unit shall be:

Item description Safety Officer and Environmental Officer 28.09.1 28.09.2 Measurement 28.10 Provision of Safety Officer Provision of Environmental Officer

Unit

number-month number-month

The measurement of the item for provision of Safety Officer under this sub-heading shall commence from the date of appointment of the Safety Officer as approved by the Engineer or the date on which the Safety Officer commences his duty on the Site whichever is the later. No measurement shall be made for any Safety Officer employed by the Contractor over and above the number of Safety Officers required under the Contract. The measurement of the item for provision of Environmental Officer under this sub-heading shall commence from the date of appointment of the Environmental Officer as approved by the Engineer or the date on which the Environmental Officer commences his duty on the Site, whichever is the later. No measurement shall be made for the items under the sub-heading Safety Officer and Environmental Officer after the date of substantial completion of the Works, or where the Works are divided into Sections, the date of substantial completion of the last Section of the Works, or an earlier or later date notified by the Engineer. No measurement shall be made for any period of time in which the Safety

28.11

28.12

28.13

236

Officer and/or the Environmental Officer fails to discharge any of his duties.

Sub-heading

SITE SAFETY AND ENVIRONMENTAL COMMITTEE, SITE SAFETY AND ENVIRONMENTAL MANAGEMENT COMMITTEE
F. Separate items shall be provided for under the sub-heading Site Safety and Environmental Committee, Site Safety and Environmental Management Committee in accordance with the following itemisation table:

Notes

Group

Feature

Unit

1. 2.

Arrange and attend Site Safety and Environmental Committee Arrange and attend Site Safety and Environmental Management Committee

month month

G.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

28.14

Item description and unit shall be:

Item description Site Safety and Environmental Committee, Site Safety and Environmental Management Committee 28.14.1 Arrange and attend Site Safety and Environmental Committee Arrange and attend Site Safety and Environmental Management Committee

Unit

month

28.14.2

month

Measurement

28.15

The measurement of the items under the sub-heading Site Safety and Environmental Committee, Site Safety and Environmental Management Committee shall commence from the date of the first meeting of the relevant Committee until the date of substantial completion of the Works, or where the Works are divided into Sections, the date of substantial completion of the last Section of the Works, or an earlier or later date notified by the Engineer. The item for arrange and attend Site Safety and Environmental Management Committee under this sub-heading shall be measured as a whole if separate meetings are held for discussion on site safety and environmental issues individually. No measurement shall be made for any month in which the Contractor fails to hold or attend any such Committee meetings in accordance with the Contract or fails to deal with any of the matters associated with such Committees in a satisfactory manner.

28.16

28.17

237

Sub-heading
Notes H.

SAFETY WALKS AND ENVIRONMENTAL WALKS


Separate items shall be provided for under the sub-heading Safety walks and environmental walks in accordance with the following itemisation table:

Group

Feature

Unit

1. 2.

Arrange and attend weekly safety walks Arrange and attend weekly environmental walks

number number

I.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

28.18

Item description and unit shall be:

Item description Safety walks and environmental walks 28.18.1 28.18.2 Item description extension 28.19 Arrange and attend weekly safety walks Arrange and attend weekly environmental walks

Unit

number number

The item description of the items under the sub-heading Safety walks and environmental walks shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) implementation and upkeeping of all measures stipulated in Contract on site safety, the Safety Plan, environmental management, the Environmental Management Plan and maintaining the effectiveness of all such provisions for the duration of the Contract; conducting safety and environmental inspections; implementation of the decisions and recommendations made by the Site Safety and Environmental Management Committee on matters of safety, health, environmental nuisance and waste management.

(b) (c)

Measurement

28.20

Only those safety walks or environmental walks conducted during the period from the date for commencement of the Works until the date of substantial completion of the Works, or where the Works are divided into Sections, the date of substantial completion of the last Section of the Works, or an earlier or later date notified by the Engineer, are qualified for measurement.

238

28.21

No payment shall be made for the item for arrange and attend weekly safety walks under this sub-heading for any week when any one of the following events occurs during that week: (i) the Contractor has received Improvement Notice or Suspension Notice issued by the Labour Department under the Occupational Safety and Health Ordinance in respect of any activities on the Site; the Engineer has suspended the progress of the Works or any part thereof due to any reason caused by any default on the part of the Contractor in failing to ensure safety and health; the Engineer has given written notification to the Contractor requiring the Contractor to rectify any deficiency in the proper and full implementation of the Safety Plan, and the Contractor has failed to rectify the deficiency within a reasonable time; the Contractor has failed to rectify the defects and deficiencies identified in the weekly safety walk within the agreed time; or any impending prosecution comes to the knowledge of the Engineer under Section 27 of the Public Health and Municipal Services Ordinance.

(ii)

(iii)

(iv) (v)

28.22

No payment shall be made for the item for arrange and attend weekly environmental walks under this sub-heading for any week when any one of the following events occurs during that week: (i) (ii) any Air Pollution or Noise Abatement Notice has been issued by the Environmental Protection Department; any impending prosecution comes to the knowledge of the Engineer under any of the following Ordinances: (1) Air Pollution Control Ordinance; (2) Noise Control Ordinance; (3) Water Pollution Control Ordinance; (4) Waste Disposal Ordinance; (5) Environmental Impact Assessment Ordinance; (6) Dumping at Sea Ordinance; and (7) Ozone Layer Protection Ordinance; test results confirming that diesel-operated Constructional Plant replenished with other than ultra low sulphur diesel; any illegal or unauthorized disposal of C&D materials in connection with the Works notified by the Environmental Protection Department or other relevant departments; the public filling reception facilities have refused to receive the C&D materials from the Site because the materials contain an unacceptably high proportion of non-inert C&D materials or other waste; the Engineer has given written notification to warn the Contractor for any failure in the proper and full implementation of the Environmental Management Plan, but the Contractor has failed to rectify such failure within a reasonable time; or the Contractor has failed to rectify the defects and deficiencies identified in the weekly environmental walk within the agreed time.

(iii) (iv)

(v)

(vi)

(vii)

239

28.23

The weekly safety walks and weekly environmental walks carried out simultaneously and by the same inspection team shall be measured separately.

Sub-heading
Notes J.

SAFETY AND ENVIRONMENTAL TRAINING


Separate items shall be provided for under the sub-heading Safety and environmental training in accordance with the following itemisation table:

Group

Feature

Unit

1.

Provision of safety environmental training

and

number

II

1. 2. 3.

in the form of safety training for specified trade workers in the form of site specific induction training in the form of tool box talks

K.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

28.24

Item description and unit shall be:

Item description Safety and environmental training 28.24.1 Provision of safety and environmental training, in the form of safety training for specified trade workers

Unit

number

Item description extension

28.25

The item description of the items under the sub-heading Safety and environmental training shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) payment of the token allowance to workers.

240

Measurement

28.26

The measurement of the item for provision of safety and environmental training, in the form of safety training for specified trade workers under this sub-heading shall be on a per worker basis subject to the production of a Specified Trade Safety Training Certificate (Silver Card) and submission of the original attendance certificate issued by the Construction Industry Training Authority as evidence of completing the Safety Training Course for Construction Workers of Specified Trade or its revalidation course, in accordance with the Contract. The Engineer or his representative will stamp on the attendance certificate and return it to the Contractor after the measurement for this item has been made. No measurement will be made if: (i) (ii) (iii) the specified trade worker has attended the course before he starts works on the Site or after he has left the Site; or the specified trade worker has attended the same course for the same trade more than once during the Contract period; or measurement for this item has been made under another public works contract for the same trade worker to attend the same course for the same trade, or a valid or clean attendance certificate without prior payment record cannot be produced.

28.27

The measurement of the item for provision of safety and environmental training, in the form of site specific induction training under this sub-heading shall be paid on a per worker per training basis. The measurement of the item for provision of safety and environmental training, in the form of tool box talks under this sub-heading shall be paid on a per worker per talk basis based on a frequency of one talk per worker every two weeks in accordance with the Contract. No measurement of the items for provision of safety and environmental training, in the form of site specific induction training or provision of safety and environmental training, in the form of tool box talks under this sub-heading shall be made if the Engineer or the Engineers Representative is dissatisfied with the frequency, arrangements, numbers certified, relevance or quality of such training and the Contractor cannot provide any justification acceptable to the Engineer.

28.28

28.29

Sub-heading
Notes L.

SITE SAFETY CYCLE


A separate item shall be provided for under the sub-heading Site Safety Cycle in accordance with the following itemisation table:

Group

Feature

Unit

1.

Arrange and hold Pre-work Activities of Site Safety Cycle

number

M.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

241

Item description and unit

28.30

Item description and unit shall be:

Item description Site Safety Cycle 28.30.1 Arrange and hold Pre-work Activities of Site Safety Cycle

Unit

number

Measurement

28.31

Subject to paragraphs 28.32 to 28.36 below, the measurement of the item for arrange and hold Pre-work Activities of Site Safety Cycle under this sub-heading shall be the number of persons attending a complete set of the following Pre-work Activities on one day: (i) (ii) (iii) Pre-work Exercise and Safety (PES) meetings; Hazard Identification Activity (HIA) meetings; and Pre-work Safety Checks.

28.32

Measurement shall only be made for persons employed on the Works (excluding clerical and administrative staff in the Site office), irrespective of whether they are in the employment of the Contractor or his sub-contractors. For the avoidance of doubt, persons employed on the Works are those persons whose number of man-hours worked on the Site are to be included in the number of man-hours worked for the Contract. Measurement shall only be made for a person who has completed the set of Pre-work Activities on one day prior to his/her work on that day. No extra measurement shall be made for a person who has attended more than one set of Pre-work Activities in a day. A maximum of two numbers for the item for arrange and hold Pre-work Activities of Site Safety Cycle under this sub-heading shall be measured for the same person in any one calendar week (commencing on Monday) unless prior approval has been obtained from the Engineer. No measurement shall be made for the number of persons who have attended the Pre-work Activities in a group but the Engineer or the Engineers Representative is dissatisfied with the content and/or the arrangement of the Pre-work Activities for that group. If the Engineer or the Engineers Representative is only dissatisfied with the content and/or the arrangement of the HIA meeting for a particular group only, then the non-measurement shall be limited to the number of persons for that group which the Engineer or the Engineers Representative considers unsatisfactory. No measurement shall be made for the total number of attendees of Pre-work Activities in a week (commencing on Monday) if the number of individual persons who have attended the Pre-work Activities to the satisfaction of the Engineer or the Engineers Representative within that week is less than 70% of the average number of persons working at the Site in that week. For the avoidance of doubt, the average number of persons working at the Site in a week (commencing on Monday) shall be the quotient of the total number of man-days worked for the Contract in that week divided by the number of working days within that week.

28.33

28.34

28.35

28.36

242

Sub-heading
Notes N.

SAFETY BULLETIN BOARD


A separate item shall be provided for under the sub-heading Safety bulletin board in accordance with the following itemisation table:

Group

Feature

Unit

1.

Provision, maintenance and removal of safety bulletin board

sum

O.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

28.37

Item description and unit shall be:

Item description Safety bulletin board 28.37.1 Provision, maintenance and removal of safety bulletin board

Unit

sum

Item description extension

28.38

The item description of the item under the sub-heading Safety bulletin board shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) (b) (c) disposal of any material; relocating safety bulletin board if required from one place to another within the Site during the various stages of the Contract; reinstatement.

Sub-heading
Notes P.

QUALITY POWERED MECHANICAL EQUIPMENT


The method of measurement for the sub-heading Quality powered mechanical equipment shall only be included for works contracts with an estimated contract sum of $200M or above. A separate item shall be provided for under the sub-heading Quality powered mechanical equipment in accordance with the following itemisation table:

Q.

Group

Feature

Unit

1.

Use of quality powered mechanical equipment

month

243

R.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

28.39

Item description and unit shall be:

Item description Quality powered mechanical equipment 28.39.1 Measurement 28.40 Use of quality powered mechanical equipment

Unit

month

The item for use of quality powered mechanical equipment under this sub-heading shall be measured once only for each month when during the whole month, all Constructional Plant used on the Site, insofar as they fall under a category of the Quality Powered Mechanical Equipment (QPME) as listed in the relevant PS Clauses, have at all times been registered with the Environmental Protection Department (EPD) as a QPME and affixed with a relevant label issued by the EPD. No measurement shall be made for this item if there is no site activity requiring the use of QPME for the month, or if there is site activity requiring the use of QPME for the month but the Contractor has not used QPME for such site activity or any part thereof during the month.

244

SECTION 29
Heading

PRIME COST SUMS


i These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. Where Prime Cost Sums are included in the Bills of Quantities for work to be executed or services to be supplied by a Nominated Sub-contractor, separate items are to be provided for: (i) general attendance provided by the Contractor in connection therewith in the form of a lump sum; (ii) special attendance provided by the Contractor (if required) for any facility or specific requirements not covered under general attendance in the form of a lump sum. Such facility and specific requirements shall be stated clearly in the item description; (iii) the Contractors profit in relation to the Prime Cost Sum in the form of a percentage. iii Where Prime Cost Sums are included in the Bills of Quantities for materials to be supplied by a Nominated Sub-contractor, a separate item shall be provided for the Contractors profit in relation to the Prime Cost Sum in the form of a percentage.

Notes

ii

Sub-heading
Notes A.

PRIME COST SUMS FOR WORK OR SERVICES


Separate items shall be provided for under the sub-heading Prime Cost Sums for work or services in accordance with the following itemisation table:

Group

Feature

Unit

1.

2.

3. 4.

Prime Cost Sum for work to be executed or services to be supplied by a Nominated Sub-contractor (Note : the Prime Cost Sum shall be inserted in the Amount column of this item in the bill) Profit percentage in relation to the Prime Cost Sum for work or services (Note : the Prime Cost Sum shall be inserted in the Quantity column of this item in the bill) Provision of general attendance Provision of special attendance

sum

percentage

sum sum

245

B.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

29.01

Item description and unit shall be:

Item description Prime Cost Sums for work or services 29.01.1 Prime Cost Sum for work to be executed or services to be supplied by a Nominated Sub-contractor Profit percentage in relation to the Prime Cost Sum for work or services Provision of general attendance Provision of special attendance

Unit

sum

29.01.2

percentage

29.01.3 29.01.4 Item description extension 29.02

sum sum

The item description of the item for provision of general attendance under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) affording the use of existing work space, access, temporary roads, erected scaffolding, working shelters, staging, ladders, hoists, storage, latrines, messing, welfare and other facilities existing on Site and the provision of protection, water, telephone, electricity for lighting, and clearing away rubbish and debris arising from the work.

29.03

The item description of the item for provision of special attendance under this sub-heading shall be extended in accordance with Preamble paragraph 1.8 and as follows: (a) facilities not covered under the item for provision of general attendance but have been specified in the Contract.

Sub-heading
Notes C.

PRIME COST SUMS FOR MATERIALS


Separate items shall be provided for under the sub-heading Prime Cost Sums for materials in accordance with the following itemisation table:

246

Group

Feature

Unit

1.

2.

Prime Cost Sum for materials to be supplied by a Nominated Sub-contractor (Note : the Prime Cost Sum shall be inserted in the Amount column of this item in the bill) Profit percentage in relation to the Prime Cost Sum for materials (Note : the Prime Cost Sum shall be inserted in the Quantity column of this item in the bill)

sum

percentage

D.

The Method of Measurement shall contain item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following are typical examples of such item descriptions and units under this sub-heading:

Item description and unit

29.04

Item description and unit shall be:

Item description Prime Cost Sums for materials 29.04.1 Prime Cost Sum for materials to be supplied by a Nominated Sub-contractor Profit percentage in relation to the Prime Cost Sum for materials

Unit

sum

29.04.2

percentage

247

SECTION 30
Heading

WORK AND ITEMISED


i

SERVICES

NOT

SEPARATELY

Notes

These notes, itemisation tables and any wording appearing below in italics and of a unique font of their own are for information only and are not to be reproduced in the Method of Measurement. Section 1 and this section 30 are mandatory sections and the items contained therein should be included in the Contract under bill No. 1 (Preliminaries) and a separate last bill (Work and Services Not Separately Itemised) respectively.

ii

Sub-heading
Notes A.

WORK AND SERVICES NOT SEPARATELY ITEMISED


A separate item shall be provided for under the sub-heading Work and services not separately itemised in accordance with the following itemisation table:

Group

Feature

Unit

1.

Execute, complete, maintain and/or supply all work and services described or identified in the Specification, General Conditions of Contract or Special Conditions of Contract and which are not shown on Drawings and not covered or separately measured under any other items of work

sum

B.

The Method of Measurement shall contain the item descriptions and units for all items of work that are measured in the bills within the Bills of Quantities. The following is a typical example of such item descriptions and units under this sub-heading:

Item description and unit

30.01

Item description and unit shall be:

Item description Work and services not separately itemised 30.01.1 Execute, complete, maintain and/or supply all work and services described or identified in the Specification, General Conditions of Contract or Special Conditions of Contract and which are not shown on Drawings and not covered or separately measured under any other items of work

Unit

sum

248

Measurement

30.02

For interim payment purpose, the estimated value of the item under the sub-heading Work and services not separately itemised shall be calculated by multiplying the amount inserted by the Contractor in the bill in respect of such item with the following factor: X Y where X = estimated value of the Works other than the item under the sub-heading Work and services not separately itemised and the Adjustment Item Y = the Contract Sum less the amount inserted by the Contractor in the bill in respect of the item under the sub-heading Work and services not separately itemised and the Adjustment Item provided that the factor X/Y shall be taken as 1.0 if and when the factor is worked out to be more than 1.0.

30.03

Subject to paragraph 30.02 above, any balance of the amount inserted by the Contractor in the bill in respect of the item under the sub-heading Work and services not separately itemised shall be paid following the issue of the certificate of completion of the Works or the last Section of the Works.