Sunteți pe pagina 1din 58

CHAPTER-1 HIRE CHARGES OF PLANTS

Sr No 1 Description Unit Basic Cost Carriage Rate/Unit 960.000 19.20 Coaltar Boiler 900 to 1400 Per day litres Concrete Mixer 0.14 cubic Per day Diesel Road Roller-8 to 10 Per day Diesel Truck - 7 to 10 tonne Per day Spraying machine including Per day electric charges Coaltar sprayer Per day Remarks/ Input ref. 979.20 2% added forCarriage 816.00 2244.00 0.00 0.00

2 3 4 5

800.000 ### 0.000 0.000

16.00 44.00 0.00 0.00

6 7

0.000 ###

0.00

0.00

Barber green,drying,mixing Per day and Asphalt Plant,with accessories,capacity 30/45 tonne Derrick monkey Rope Per day

202.88 10346.88

8 9

0.000 0.000

0.00 0.00

0.00 0.00

Pumpset for Pumping water Per day @ 3636.8 litres/hour Vibrator (needle type 40 Per day Per day Per day Per day Per day grinder for mirror Per day Per day Per day spraying of Per day KM

10 11 12 13 14 15 16 17 18 19

0.000 0.000 0.000 ### 0.000 0.000 0.000 0.000 0.000 18.000

0.00 0.00 0.00 30.00 0.00 0.00 0.00 0.00 0.00 0.36

0.00 0.00 0.00 1530.00 0.00 0.00 0.00 0.00 0.00 18.36

Machine for rubbing of floors Mastic cooker Tipper Loader Hand

Pin Vibrator Surface vibrator Gusmer (for

CHAPTER-2 LABOUR CHARGES ( incusive Statutory obligations@12.5% + LA & LI( contractor) @3.5%)

Transporation cost of one Tipper 8Tonne capacity per Km

1of58

Sr No Sr No

Description Description

Remarks/ Unit Basic Cost Carriage Rate/Unit Input ref. Add for EPF/Emlo Remarks/ Unit Basic Cost Rate/Unit yees Input ref. welfare Per day 150.000 25.50 175.50 1 % for Welfare benefits for Labourers 140.40 292.50 234.00 0.00 292.50 234.00 128.70 146.25 140.40 292.50 234.00 351.00 292.50

Bandhani

2 3 4 5 6 7 8 9 10 11 12 13 14

Bhishti Blacksmith 1st class Blachsmith 2 nd class Bullockman with

Per day Per day Per day single Per day Per day Per day Per day Per day Per day Per day

120.000 250.000 200.000 0.000 250.000 200.000 110.000 125.000 120.000 250.000 200.000 300.000 250.000

Carpenter 1 st class Carpenter 2 st class Chowkidar Beldar Coolie Fitter

Assistant Fitter or 2nd Class Per day Glazier Per day

Mason( for palster of paris Per day work) 1st class Mason( for brick work) 1st Per day Mason( for brick work) 2st Per day Mason( for plain stone work) Per day Mason( for ornamental stone Per day work) 1st class Driver for Road Per day Roller,concrete Mixer,Truck etc. Mate Per day Mali Per day

0.00 20.40 0.00 42.50 0.00 34.00 0.00 0.00 0.00 42.50 0.00 34.00 0.00 18.70 0.00 21.25 0.00 20.40 0.00 42.50 0.00 34.00 0.00 51.00 0.00 42.50 0.00 38.25 0.00 34.00 0.00 34.00 0.00 42.50 0.00 38.25 0.00 25.50 0.00 17.00

15 16 17 18

225.000 200.000 200.000 250.000

263.25 234.00 234.00 292.50

19

225.000

263.25

20 21

150.000 100.000

175.50 117.00

2of58

Sr No 22 23 24 25 26 27 28 29 30 Mistry Painter

Description

Unit Basic Cost Carriage Rate/Unit 0.00 Per day Per day Per day Per day Per day Per day Per day 250.000 225.000 225.000 250.000 225.000 250.000 150.000 110.000 200.000 42.50 0.00 38.25 0.00 38.25 0.00 42.50 0.00 38.25 0.00 42.50 0.00 25.50 0.00 18.70 0.00 34.00 0.00 234.00 263.25 263.25 292.50 263.25 292.50 175.50 128.70 292.50

Remarks/ Input ref.

Rock Excavator Rock Breaker Rock Hole Driller Stone Chiseller Sewerman Sprayman(for etc.)

bitumen,tar Per day

Skilled Beldar(for flooring Per day rubbing etc.)/Grinder White washer Mason(average) Carpenter(average) Operator(Pile machines) Mechanic operator) (Pile / / Per day Per day Per day Special Per day Assistant Per day Per day Per day Per day

31 32 33 34 35 36

200.000 225.000 250.000 300.000 200.000 225.000 110.000 300.000

34.00 0.00 38.25 0.00 42.50 0.00 51.00 0.00 34.00 0.00 38.25 0.00 18.70 0.00 51.00

234.00 263.25 292.50 351.00 234.00 263.25 128.70 351.00

Skilled Torch operator waterman Foreman

CHAPTER-3 MATERIAL FOR BUILDING WORK AND ROAD WORK


Add for Carriege Remarks/ Unit Basic Cost Rate/Unit and Loss Input ref. @ 2%

Sr No

Description

3of58

Sr No 1 2 3 4

Description Adhesive(rubber base) Adhesive Solvent Cement Glue Aggregate Fine Aggregate(SAND) River Sand Fine sand Murrum Stone dust Surki Imported Earth Coarse Aggregate(JELLY) 75 mm nominal size 63 mm nominal size 50 mm nominal size 40 mm nominal size 25 mm nominal size 20 mm nominal size 12.5 mm nominal size 10.0 mm nominal size

Unit Basic Cost Carriage Rate/Unit Kilogram litre kilogram 95.000 130.000 35.000 1.90 2.60 0.70 96.90 132.60 35.70

Remarks/ Input ref.

UP cum cum cum cum cum cum cum cum cum cum cum cum cum cum tonne tonne tonne ### 0.000 910.000 840.000 800.000 650.000 250.000 225.000 960.000 960.000 960.000 ### ### ### 976.000 976.000 18.20 16.80 16.00 13.00 5.00 4.50 19.20 19.20 19.20 20.80 20.80 21.44 19.52 19.52 928.20 856.80 816.00 663.00 255.00 229.50 979.20 979.20 979.20 1060.80 1060.80 1093.44 995.52 995.52 Rs 60/100kg Rs 60/100kg Rs 60/100kg Rs 65/100kg Rs 65/100kg Rs 67/100kg Rs 61/100kg Rs 61/100kg Rs 65/100kg Rs 60/100kg

Cement Port Land cement White Cement Acid Proof cement

0.00 lead from stores 270.00 13770.00 0.00 0.00

Aluminium Aluminium Plain strip edging metre 38x12x3 strip 25 mm Aluminium kilogram 500.000 Aluminium strip 10 mm kilogram 500.000 Aluminium Plain strip edging metre 0.000 57x12x3 Strips-Aluminium fluted 3.15 metre 0.000 mm thick & 150mm wide Aluminium strip 40 mm wide kilogram 500.000 and 2 mm thick Aluminium strip 38 mm wide kilogram 500.000 and 1.6 mm thick Aluminium grip strip of size each 0.000 50x12x2 mm Stip-Aluminium fluted 3.15 metre 0.000 mm thick and 200mm wide Aluminium sheet 24 gauge sqm 0.000 0.00 10.00 10.00 0.00 0.00 10.00 10.00 0.00 0.00 0.00 0.00 510.00 510.00 0.00 0.00 510.00 510.00 0.00 0.00 0.00

4of58

Sr No

Description Aluminium Beading Aluminium U beading

Unit Basic Cost Carriage Rate/Unit metre kilogram 0.000 0.000 0.000 0.000 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.20 16.40 5.00 3.50 1.30 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 418.20 836.40 255.00 178.50 66.30 51.00

Remarks/ Input ref.

Aluminium Tee metre channel(heavy duty) with rollers and stop end Aluminium T and L sections kilogram

Aluminium single cleat of each 0.000 size 30x32x3washer 2 mm cent Aluminium 0.000 thick 15 mm dia Anodising 15 microns on kilogram 0.000 aluminium sections Glass 6mm thk sqm 410.000 Glass 10mm thk Anodised Aluminium Butt Hinges 100x58x1.9mm Anodised Aluminium Butt Hinges 50x37x1.5mm M.S. Screw 40mm M.S. Screw 30mm 7 Bitumen and Coal Tar Paving bitumen S-90 of approved quality Blown type petroleum bitumen of penetration 85/25 approved coal Tar quality Paving Asphalt Penetration Paving Asphalt PenetrationAsphalt Paving Penetration (Rapid RC - 3 30/40 80/100 60/70 tonne tonne litre tonne tonne tonne ### ### 0.000 0.000 ### ### 0.000 0.000 0.000 0.000 0.000 ### 30.000 50.000 70.000 sqm 10nos 10nos Cent Cent 820.000 250.000 175.000 65.000 50.000

440.00 22440.00 440.00 22440.00 0.00 0.00 0.00 0.00

440.00 22440.00 440.00 22440.00 0.00 0.00 0.00 0.00 0.00 24.00 0.60 1.00 1.40 0.00 0.00 0.00 0.00 0.00 1224.00 30.60 51.00 71.40

curing) tonne bitumen confirming to IS 217 Solvent Kilogram Modified Bitumen Refinery tonne produced CRMB - 55 Modified Bitumen Refinery tonne produced CRMB - 60 Bitumen Emulsion M.S. tonne (medium setting) conforming to IS:8887-1995 Steam Coal Quintal Anti corrosive bitumastic paintKilogram sqm APP polymeric polyethylene 1mm th GEO TEXTILE 8 Blasting Material Blasting powder Blasting Fuse (Fuse wire) Kilogram Each sqm

0.000 0.000

0.00 0.00

0.00 0.00

5of58

Sr No 9

Description Bricks Table mould bricks Machine moulded briks Bick bats

Unit Basic Cost Carriage Rate/Unit thousan d thousan d cum ### ### ### 50.00 60.00 20.00 2550.00 3060.00 1020.00

Remarks/ Input ref.

10

Distemper Dry Distemper kilogram 200.000 4.00 5.00 5.50 0.00 0.00 12.00 204.00 255.00 280.50 0.00 0.00 612.00 Oil bound washable kilogram 250.000 distemper water proofing cement paint kilogram 275.000 snowcem plus Plaster of Paris kilogram 0.000 whiting Indigo (Neel) quintal 0.000 kilogram 600.000

11

Stones Stone for Masonry work Stones for pitching Soling Stones cum cum cum ### 850.000 700.000 20.00 17.00 14.00 1020.00 867.00 714.00

12

Tiles 6 mm Ceramic Tiles 8 mm Ceramic Tiles Pressed cement tiles walkway tiles 10 mm thick Black Granite 20 mm thick Black Granite Vitrified ceramic Tiles Kota Stones for (35mmth) Rough sand stone Marble Dust Flooring sqm sqm sqm sqm sqm sqm sqm sqm sqm sqm cum 490.050 500.000 250.000 250.000 ### ### 0.000 350.000 150.000 350.000 ### 20.000 9.80 10.00 5.00 5.00 20.00 43.20 0.00 7.00 3.00 7.00 29.00 0.40 499.85 510.00 255.00 255.00 1020.00 2203.20 0.00 357.00 153.00 357.00 1479.00 20.40

Marble Stone 18mm th

Marble tile 8mm th 30cmX15cmEach

13

Roofing 0.6 mm thick (Corrugated) 0.6 mm thick AC Sheets sqm sqm sqm sqm sqm sqm 115.000 325.000 325.000 300.000 300.000 275.000 2.30 6.50 6.50 6.00 6.00 5.50 117.30 331.50 331.50 306.00 306.00 280.50 AC Sheets (Plain) (Plain 16 - gauge) GI Sheet GI Sheet (Plain 18 - gauge) MS Sheet - 16 Gauge MS Sheet - 18 Gauge

6of58

Sr No

Description Mangalore Tiles

Unit Basic Cost Carriage Rate/Unit sqm 0.000 0.00 0.00

Remarks/ Input ref.

14

Steel Reinforced Steel Structural steel Binding wire Nuts and bolts tonne tonne kgs kgs 48.000 54.000 0.96 1.08 0.00 lead from stores 0.00 48.96 55.08

15

Paints Aluminium paint Acid proof paint Enamel paint synthetic enamel paint plastic enamel paint road marking paint Acralyc exterior paint Primer Acrylic Emulsion Interior Grade Metal primer Special Primer C-W Epoxy paint Colouring Pigment litre litre litre litre litre litre litre litre litre Litre Litre Litre Kg 350.000 0.000 250.000 250.000 350.000 0.000 230.000 150.000 150.000 200.000 125.000 250.000 400.000 7.00 0.00 5.00 5.00 7.00 0.00 4.60 3.00 3.20 3.00 4.00 2.50 5.00 8.00 357.00 0.00 255.00 255.00 357.00 0.00 234.60 153.00 163.20 153.00 204.00 127.50 255.00 408.00

Paint kilogram 160.000

Multi surface paint "Uni-Gloss"

16

Fenceing Chain link Fencing Barbed wire GI wire interwoven in chain link sqm sqm 405.000 220.000 8.10 4.40 413.10 224.40

17

RCC Hume Pipe NP 3 150 mm 200 mm 300 mm 600 mm 900 mm 1200 mm NP 4 600 mm 900 mm 1200 mm rmt rmt rmt ### ### ### 33.00 58.00 88.00 1683.00 2958.00 4488.00 rmt rmt rmt rmt rmt rmt 220.000 300.000 375.000 ### ### ### 4.40 6.00 7.50 26.20 48.00 70.00 224.40 306.00 382.50 1336.20 2448.00 3570.00

7of58

Sr No 18

Description Paver Blocks 80 mm thick reflective type 80 mm thick non reflective type

Unit Basic Cost Carriage Rate/Unit sqm sqm 550.000 475.000 11.00 9.50 561.00 484.50

Remarks/ Input ref.

19

Sanitary Items W.C pan (580x440)mm Orrisa pattern white 10 lit. PVC flushing cistern CI / M.S. Brackets G.I. 32mm telescopic flush pipe with fittings/specials 32mm M.S. holder bat clamp 20mm G.I pipe 'C' class Special for overflow pipe

Each Each Set Set Each Mt Each

700.000 350.000 50.000 120.000 20.000 105.000 50.000 100.000 150.000 300.000 1200.000

14.00 7.00 1.00 2.40 0.40 2.10 1.00 2.00 3.00 6.00 24.00 40.00

714.00 357.00 51.00 122.40 20.40 107.10 51.00 102.00 153.00 306.00 1224.00 2040.00

25mm Mosquito proof coupling Each 100mm sci 'P' or 'S' trap with vent horn Each Plastic seat & lid Black for EWC Each Europeanlevel vitreous 10lit.low type Water Closet flushing cistern with fittings & brackets, and 40mm flush bend China flat back or wall corner type Lipped front urinal basin of (430x260x350) mm or (340x410x265) mm sizes of White vitreous 5 lit. PVC automatic flushing cistern with fittings Standard size GI flush pipe and CP brass spreader, with brass union and clamps including fittings Wash basin of white vitreous China (630x450) mm size 15mm CP brass pillar tap (Continental) C.P. brass chain with plug 32mm C.P. brass waste of standard pattern C.P. Brass stop cock Lead connection Each

Each

2000.000 2400.000 48.00 16.00 2448.00 816.00

E.W.C.pan as specified pedestal Each type

Each Each

800.000 900.000 18.00 7.00 918.00 357.00

Each Each Each Each Each Each Each

350.000 1500.000 450.000 100.000 150.000 450.000 150.000 30.00 9.00 2.00 3.00 9.00 3.00 30.00 12.50 0.96 0.60 0.40 1530.00 459.00 102.00 153.00 459.00 153.00 1530.00 637.50 48.96 30.60 20.40

Stainless Steel Kitchen Sink 510x1040 1500.000 Each 1.8m long 100mm dia soil Each 625.000 pipe (SCI/SS) Pig lead for CI pipe Joints Spunclamps / stay for M.S. yarn 100mm dia pipe Kg Kg Each 48.000 30.000 20.000

8of58

Sr No

Description I5mm Dia G.I. pipes (CClass) dia G.I. pipes (C20mm class) dia G.I. pipes ( C25mm class) dia G.I. pipes ( C32mm class) dia G.I. pipes ( C40mm class) dia G.I. pipes ( C50mm class)

Unit Basic Cost Carriage Rate/Unit Mt Mt Mt Mt Mt Mt 79.000 101.000 147.000 191.000 221.000 300.000 1.58 2.02 2.94 3.82 4.42 6.00 80.58 103.02 149.94 194.82 225.42 306.00

Remarks/ Input ref.

20

Wooden Item 1st class Timber (Teak, Kail,Deodar etc) cum 2nd class Timber cum ### ### 1200.00 61200.00 980.00 49980.00

FAC TOR C ALC ULAT ION


SN 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 DESC RIPT ION DIREEC T SUPERVISION C OST OF C ONT RAC T OR INDIRECT SUPERVISION C OST OF C ONT RAC T OR PROFIT OF T C ONT HE RAC T OR Before printing, think P& E IDLING OF OPERAT ION about ENVIRONMENTAL T URNOVER BENEFIT FOR SUPPLY IT T C ONT EM O RAC T OR responsibility. BANK C HARGES FOR PBG / BG C ONT INGENC IES BUSINESS PROMOT ION WC T / T T BE PAID BY T C ONT DS O HE RAC T OR ESC ALAT ION EST ABLISHMENT OF REL OFFIC E, LAB ET C SC OPE REDUC T ION / INC REAMENT SENSIT Y IVIT T AL ST OT EEL (EXC EPT REINFORC EMENT ) AMT 3.0% 3.0% 12.0% 3.0% 4.0% 1.0% 1.0% 1.0% 2.5% 0.0% 1.0% 0.5% 32.0%

9of58

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

Rate analysis for civil iems (INDEX) Site Clearence Earth Work Carting Away Back Filling Dewatering of subsoil water from excavated pit by pumping or other suitable method Concrete - PCC & RCC MORTARS Masonry WATER PROOFING Flooring Aluminuim Work Plastering Flooring Road works/ pavement works Kerb stone Steel Works Fencing Works Paver Block Sanitary Items Damp Proof course DISMANTALLING & DEMOLISHING WORKS False ceiling Thermal insulation under deck.. WHITE WASHING, DISTEMPERING & PAINTING Bollard Fixing Provoding and injecting chemical pre constructional tntitermite treatment RAINWATER HARVESTING PVC PIPE LAYING Hume Pipe Culverts Providing plastering / pointing

S.No 1 1.1

Description Unit Site Clearence Clearing the site of all vegetation, shrubs, weeds, grass ,debris, refuse and all other obstructions/objectionable matter complete and disposing of the material to place upto 2 KM as directed by site engineer, including dressing up ground to a level surface as directed by the site engineer. Note:- Trees to be uprooted after getting approval from engineer-in-charge engineer-in-charge Details of cost of 100sqm Labour Beldar Coolie Add for Sundries and continges @3% SQM

Qty

Rate

Amount

each each

0.8 0.8

146.25 140.4 Subtotal Sub Total

Contractors profit and over heads @15% Cost of clearing jungle for 100 sqm Cost of 1 sqm 2 Earth Work Excavation in all kinds of soil /murrum for foundation, trenches and drains,columns, footings, landscaping and piping including disposal of surplus excavated earth to a location within site as directed by engineer-in charge & including shoring,shrutting etc. complete (Size of excavated pit for foundation, trenches& drains&footings to be considered for volumetric calculation for payment will be made on P.C.C.size basis as mentioned in the drawing) Including dressing . 2.1 Depth 0.0-1.50m All kinds of soils Out put =10 cum Labour Mate Beldar Coolies Add for Tools and plant tokaries etc.@2% CUM

Total

117.00 112.32 229.32 6.88 236.20 35.43 271.63 2.72

each each each

0.15 3 3.5

175.50 146.25 140.40 subtotal subtotal

Add for Sundries and contigencies @3% subtotal Add for contractors profit and overheads @15% Cost of excavation trench for 10 cum Cost of 1 cum 2.2 Depth 1.5-3.0m All kinds of soils Out put =10 cum Basic as 0.0-1.50m Extra for every additional lift of 1.5m Labour Colie/Beldar Add for Sundries and contigencies @3% subtotal Water and electricity charges @1.5% subtotal Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum 2.3 Depth 3.0-4.50m All kinds of soils Out put =10 cum Extra for every additional lift of 1.5m Labour Colie/Beldar Add for Sundries and contigencies @3% subtotal Water and electricity charges @1.5% subtotal Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum 2.4 Depth 4.50-6.0m All kinds of soils Out put =10 cum Basic cost of 3.0-4.50 Extra for every additional lift of 1.5m Labour Colie/Beldar Add for Sundries and contigencies @3% CUM CUM subtotal

26.33 438.75 491.40 956.48 19.13 975.60 29.27 1,004.87 150.73 1,155.60 115.56

956.48

each

1.15

140.4 subtotal

161.46 1,117.94 33.54 1,151.47 17.27 1,168.75 175.31 1,344.06 134.41

1,117.94

each

1.15

140.4 subtotal

161.46 1,279.40 38.38 1,317.78 19.77 1,337.54 200.63 1,538.18 153.82

1,279.40

each

1.15

146.25 subtotal

168.19 1,447.58 43.43

subtotal Water and electricity charges @1.5% subtotal Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum

1,491.01 22.37 1,513.38 227.01 1,740.38 174.04

Excavation Soft Rock Excavation in soft rock by chiseling etc. for foundation, trenches and drains,columns, footings, landscaping and piping work including disposal of surplus excavated shrutting, etc. complete (Size of excavated pit for foundation, trenches& drains& footings to be considered for volumetric calculation for payment will be made on P.C.C.size basis as mentioned in the drawing) including dressing 2.5 0 to 1.5 m depth in soft rock Output 10 cum A. Labour Excavators Breakers Beldar Mate Coolies Total cost of Labour Add for sharpning of tooles like crow bar, pickaxes etc, cost of chisels and sharpning the same @7.5% Add for Sundriesand contingencies @3% sub total Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum 2.6 1.5-3.0 m depth in soft rock Output 10 cum Basic Rate as per 0.0-1.50m (Labour + Tools) Extra for every additional lift of 1.5m Labour Colie/Beldar Add for Sundries and contigencies @3% sub total Water and electricity charges @1.5% sub total Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum 2.7 3.0-4.50 m depth in soft rock Output 10 cum Basic Rate as per 1.50-3.0m Extra for every additional lift of 1.5m Labour Colie/Beldar Add for Sundries and contigencies @3% sub total Water and electricity charges @1.5% sub total Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum 2.8 4.50-6.0 m depth in soft rock Output 10 cum Basic Rate as per 1.50-3.0m Extra for every additional lift of 1.5m Labour Colie/Beldar Add for Sundries and contigencies @3% sub total Water and electricity charges @1.5% sub total Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum CU. M 3,091.67 CU. M 2,930.21 CU. M 2,768.75 CU. M

each each each each each

1.8 3.5 3.00 0.35 3.5

263.25 292.5 146.25 175.5 175.5 sub total

473.85 1,023.75 438.75 61.43 614.25 2,612.03 156.72 2,768.75 83.06 2,851.81 427.77 3,279.58 327.96

sub total

each

1.15

140.4 sub total

161.46 2,930.21 87.91 3,018.11 45.27 3,063.38 459.51 3,522.89 352.29

each

1.15

140.4 sub total

161.46 3,091.67 92.75 3,184.42 47.77 3,232.18 484.83 3,717.01 371.70

each

1.15

140.4 sub total

161.46 3,253.13 97.59 3,350.72 50.26 3,400.98 510.15 3,911.13 391.11

Excavationin Hard Rock

2.9

Excavation in hard rock by chiseling, Rock drilling machine as per site soil condition for foundation, trenches and drains, columns, footings, landscaping and piping work including disposal of surplus excavated earth to a location within site as directed by engineer-incharge & including shoring, shrutting, etc. complete (Size of excavated pit for foundation, trenches& drains& footings to be considered for volumetric calculation for payment will be made on P.C.C. size basis as mentioned in the drawing) 0 to 1.5 m depth In Hard Rock Output 10cum A.Labour Mate Excavators Breakers Chisellers Beldar Coolies Total Labour Add for sharpning of tooles like crow bar, pickaxes etc, cost of chisels and sharpning the same @7.5% Add for Sundriesand contingencies @3%

CU. M

each each each each each each

0.5 5.00 8.00 3.00 3.25 6.00

175.50 263.25 292.50 292.50 146.25 140.40 sub total

87.75 1,316.25 2,340.00 877.50 475.31 842.40 5,939.21 445.44 6,384.65 191.54 6,576.19 986.43 7,562.62 756.26

sub total sub total Add for contractors profit and over heads @15% Cost of 10 cum Cost of 1 cum 2.10 1.5-3.0 m depth in Hard rock Output 10 cum Basic Rate as per 0.0-1.50m (Labour + Tools) Extra for every additional lift of 1.5m Labour Colie/Beldar Add for Sundries and contigencies @3% sub total Water and electricity charges @1.5% sub total Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum 2.11 3.0-4.50 m depth in Hard rock Output 10 cum Basic Rate as per 1.50-3.0m Extra for every additional lift of 1.5m Labour Colie/Beldar Add for Sundries and contigencies @3% sub total Water and electricity charges @1.5% sub total Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum 2.12 4.50-6.0 m depth in soft rock Output 10 cum Basic Rate as per 1.50-3.0m Extra for every additional lift of 1.5m Labour Colie/Beldar Add for Sundries and contigencies @3% sub total Water and electricity charges @1.5% sub total Add for contractors profit and over heads @15% Cost of 10 cum Rate per cum CU. M CU. M CU. M

6,384.65

each

140.4 sub total

280.80 6,665.45 199.96 6,865.42 102.98 6,968.40 1,045.26 8,013.66 801.37

6,665.45

each

140.4 sub total

280.80 6,946.25 208.39 7,154.64 107.32 7,261.96 1,089.29 8,351.25 835.13

6,946.25

each

140.4 sub total

280.80 7,227.05 216.81 7,443.87 111.66 7,555.52 1,133.33 8,688.85 868.89

Carting Away 2.13 Carting away elsewhere within/outside the premises surplus excavated material inclusive of earth cinder, rock, debris unfit for back filling as directed beyond site area,(by shortest route as assessed by site engineer ) including spreading and leveling all complete as directed by engineer-in charge Up to 1.50 km Unit Out put 100 cum Labour Mistri (Head) Mazderr(Beldars) Boys Total For Labopur Add Sundries and contingencies @ 3% Add water & E.C. charges 1.5% subtotal Add C.P. & O.H. @ 15% Cost for 100 Cum Cost per cum 2.14 1.5 km to 5 km radius Out put 123.77 cum No of trips required including loading & unloading in 3.50 cum lorry) Beldar sundries & contingencies 3% subtotal Add water & E.C. charges 1.5% subtotal Add C.P. & O.H. @ 15% subtotal Cost per cum CUM

Cum

Each Each Each

4.00 22.00 26.00

292.50 146.25 140.40

subtotal

1,170.00 3,217.50 3,650.40 8,037.90 241.14 8,279.04 124.19 8,403.22 1,260.48 9,663.71 96.64

trips each

35.36 28

200 146.25 subtotal

7,072.60 4,095.00 11,167.60 335.03 11,502.63 172.54 11,675.17 1,751.28 13,426.44 108.48

Back Filling Back filling in plinth, in embankments, around footings, pits, trenches, foundations etc.in layers not exceeding 200 mm thickness, including watering, compacting by ramming/rolling, levelling to specified slopes, dressing and consolidation etc. at optimum moisture content with mechanical Rollers/Rammers etc. ( compacted to 90 % modified proctor density) complete as per specification & as directed (payment shall be made based on certified excavation quantity less volume occupied by structures) &theoretical completed quantity as measured from drawings.

2.15

(a). Using Available earth Out put 10 cum (I). Using 10 Tonne Roller Charges for road roller (10 T) Cap Diesel Carriage of diesel A.Total Machinery Labour for watering & placing etc. Beldar coolies Water man B.Total Labour Total A+B Add Sundries and contingencies @ 3% Add water & E.C. charges 1.5% subtotal Add for C.P. & O.H @ 15% Cost for 10Cum Cost per Cum

Per day lit q

0.01 0.15 0.0015

2244.00 34.94 3500.00

20.20 5.24 5.25 30.69 197.44 189.54 14.04 401.02 431.70 12.95 444.65 6.67 451.32 67.70 519.02 51.90

Nos @ Rs. Nos @ Rs. Nos @ Rs.

1.35 1.35 0.10

146.25 140.40 140.40

subtotal

2.16

Using earth Brought outside. With 5 km lead Using 10T Roller cost of Imported good earth incl loading and unloading Placing and rolling as item 2.15 Cost per Cum Cum Cum 1.00 1.00 229.50 51.90 229.50 51.90 281.40

2.17

Using earth Brought outside. With 25 km lead Using 10T Roller

Extra Transportation cost for 5 cum Cost per cum Hire Cost of Tipper Assume Tipper usage per is 8hrs, and travelling at 30KM per hour and 25% of time spent on loadin and unloading 180.00 Assume tipper consumes a litre of diesel for every 5 KM Diesel Driver Helper Other consumables for 240Km Per KM

Km

1.00 5.00

18.36

18.36 3.67

Per day

1.00

1500.00

1,500.00

Litres Each Each Ls

36.00 1.00 1.00 1.00

38.00 225.00 150.00 50.00

1,368.00 225.00 150.00 50.00 3,293.00 18.29

2.18

Supply and filling with approved quality sand brought from other areas Cost of 10 CUM Cost of River sand A.Cost of Material Beldar/coolie Waterman B. Cost of Labour Total ( A+B) Add ofr sundries and contingencies@3% Add for wate and electricity charges@1.5%

CUM

cum

10

928.20

9,282.00 9,282.00 252.72 25.74 278.46 9,560.46 286.81 9,847.27 147.71 9,994.98 1,499.25 11,494.23 1,149.42

each each

1.8 0.2

140.40 128.70

Subtotal Subtotal Add for contractors profit and overheads @15% Cost of 10 cum Cost of 1 cum

Dewatering of pits and trenches

2.19

Dewatering of subsoil water from excavated pit by pumping or other suitable method for keeping the pit dry. MATERIAL

HP/HR

Pump set for pumping water up to 1 HP. Hiring charges Rs.400/- Per day. Cost per Hr. /for 8 hrs LABOUR Beldar(M) Day 1.00 400.00 400.00

Each

1.00

146.25 sub total

146.25 546.25 16.39 562.64 8.44 571.08 85.66 656.74 82.09

Add for sundries & Contingencies @ 3% sub total Add for electricity & W.C. @ 1.5% sub total Add for C.P. & O.H @ 15% Cost per 8 hours Cost per HR

3.0

Concrete - PCC & RCC Providing & laying blinding layer using plain cement concrete with coarse aggregates as leveling course at all levels in foundations, basement & under flooring including the cost of formwork and curing.

3.1

Mix 1:4:8(PCC) using 40 mm and down size coarse aggregates. Details of cost for 1 Cum Materials Stone aggregate 40 mm Stone aggregate 20 mm Coarse sand Cement (0.1175 Cum) Total Material (A) Labour Mason Beldar Foreman Waterman coolie Total Labour(B) A+B Add for Hire and running charges of mixer @1.9%

CUM

Cum Cum Cum Tonne

0.69 0.28 0.5 0.17

1060.80 1093.44 928.20 0.00

730.15 300.70 464.10 1,494.94

each each each each each

0.125 0.65 0.05 0.13 0.65

263.25 146.25 351.00 128.70 140.40 sub total sub total

Add for sundries and contingencies@3% sub total Add for water & electricity @1.5% sub total Add for Contractor's profit and Overheads @15% Cost of 1 Cum 3.2 Mix 1:3:6(P.C.C) using 20 mm and down size coarse aggregate Details of cost for 1 Cum Materials Stone aggregate 20 mm (one size) Stone aggrigate 12mm Coarse sand Cement (0.15674 Cum) Total Material(A) Labour Mason Beldar Foreman Waterman coolie Total Labour(B) Total (A+B) Add for Hire and running charges of mixer @1.70% Add for sundries and contingencies @3% sub total Add for Water and elctricity @1.5% sub total Add for Contractor's profit and overheads @ 15% Cost per CUM sub total Cum cum Cum Tonne 0.73 0.24 0.49 0.22 1093.44 995.52 928.20 0.00 794.93 240.92 450.18 1,486.02 CUM

32.91 95.06 17.55 16.09 91.26 252.87 1,747.81 33.21 1,781.02 53.43 1,834.45 27.52 1,861.97 279.29 2,141.26

each each each each each

0.13 0.8 0.08 0.13 0.8

263.25 146.25 351 128.7 140.4 sub total sub total

32.91 117.00 28.08 16.09 112.32 306.39 1,792.42 30.47 1,822.89 54.69 1,877.58 28.16 1,905.74 285.86 2,191.60

3.3

Mix M15(PCC) with 20mm down size coarse aggregate Details of cost for 1 Cum Materials Stone aggregate 20 mm Stone aggregate 12 mm Coarse sand Cement Total Material (A) Labour Mason Beldar Foreman Waterman coolie Total Labour(B) Total(A+B) Add for Hire and running charges of mixer,vibrator water pump etc @1.75% Add for sundries and contingencies @3%

CUM

Cum Cum Cum Tonne

0.71 0.24 0.47 0.32

1093.44 995.52 928.20 0.00

770.88 233.95 436.25 1,441.08

each each each each each

0.13 0.7 0.05 0.13 0.7

292.50 146.25 351 128.7 140.4 subtotal

36.56 102.38 17.55 16.09 98.28 270.86 1,711.93 29.96 1,741.89 52.26 1,794.15 26.91 1,821.06 273.16 2,094.22

subtotal subtotal Add for Water and electricity charges@1.5% subtotal Add for Contractor's profit and overheads @ 15% Cost of 1 Cum 3.3.A Mix 1:5:10(PCC) using 40 mm and down size coarse aggregates. Details of cost for 1 Cum Materials Stone aggregate 40 mm Stone aggregate 20 mm Coarse sand Cement (0.1175 Cum) Total Material (A) Labour Mason Beldar Foreman Waterman coolie Total Labour(B) A+B Add for Hire and running charges of mixer @1.9% sub total Add for sundries and contingencies@3% sub total Add for water & electricity @1.5% sub total Add for Contractor's profit and Overheads @15% Cost of 1 Cum Cum Cum Cum Tonne 0.66 0.26 0.48 0.13 1060.80 1093.44 928.20 0.00

CUM

702.57 282.44 440.90 1,425.90

each each each each each

0.125 0.65 0.05 0.13 0.65

292.50 146.25 351.00 128.70 140.40 sub total

36.56 95.06 17.55 16.09 91.26 256.52 1,682.42 31.97 1,714.39 51.43 1,765.82 26.49 1,792.31 268.85 2,061.15

Reinforced Cement Comcrete Providing, mixing and placing in position R.C.C.. conforming to grade M 20 of IS 456-2000 using ordinary Portland cement with 20 mm and down graded coarse aggregates for concreting in columns, foundation, pedestal, slab, beam etc, including Vibrating ,curing etc. complete as per drawings, specifications and as directed by owner/consultant (Reinforcement and shuttering to be paid separately). 3.4 For depth not exceeding 5m below ground In foundations plinth flooring,walls,beams column,driveways etc. - upto Plinth level Details of cost for 1 Cum Materials Stone aggregate 20 mm Stone aggrigate 12mm Coarse sand Cement Total Material(A) Labour

Cum Cum Cum Tonne

0.66 0.22 0.44 0.4

1093.44 995.52 928.20 0.00

723.31 219.51 409.34 1,352.16

Mason Beldar Foreman Waterman coolie Total Labour(B) Total ( A+B) Add for Hire and running charges of mixer,vibrator water pump etc @1.55% Add for Sundries and contingencies@3%

each each each each each

0.2 0.8 0.05 0.15 0.8

293 146 351 129 140 subtotal

58.50 117.00 17.55 19.31 112.32 324.68 1,676.83 25.99 1,702.82 51.08 1,753.91 7.89 1,761.80 26.31 1,788.11 268.22 2,056.33

subtotal subtotal testing of materials@0.45% subtotal Add for Water and electricity @1.5% subtotal Add for Contractor's profit and OH @15% Cost of 1 Cum 3.5 RCC M25 For depth not exceeding 5m below ground In foundations plinth flooring,walls,beams column,driveways etc. - upto Plinth level Details of cost for 1 Cum Materials Stone aggregate 20 mm Stone aggrigate 12mm Coarse sand Cement Total Material(A) Labour Mason Beldar Foreman Waterman coolie Total Labour(B) Total ( A+B) Add for Hire and running charges of mixer,vibrator water pump etc @1.15% Add for Sundries and contingencies@3% subtotal testing of materials@0.35% subtotal Add for Water and electricity @1.5% subtotal Add for Contractor's profit and OH @15% Cost of 1 Cum

Cum Cum Cum Tonne

0.68 0.23 0.45 0.61

1093.44 995.52 928.20 0.00

738.07 223.99 417.69 1,379.75

each each each each each

0.15 0.7 0.05 0.13 0.7

293 146 351 129 140 subtotal

43.88 102.38 17.55 16.09 98.28 278.17 1,657.92 19.07 1,676.99 50.31 1,727.30 6.05 1,733.34 25.91 1,759.25 263.89 2,023.14

subtotal

3.6

RCC M20 For Height not exceeding 15m( Five floors) above ground,beams column,driveways etc. - above Plinth level including scaffolding Details of cost for 1 Cum Materials Stone aggregate 20 mm Stone aggrigate 12mm Coarse sand Cement Total Material(A) Labour

Cum Cum Cum Tonne

0.66 0.22 0.44 0.4

1093.44 995.52 928.20 0.00

723.31 219.51 409.34 1,352.16

Mason Beldar Foreman Waterman coolie Total Labour(B) Total ( A+B) Add for Hire and running charges of mixer,vibrator water pump etc @3.5%

each each each each each

0.15 0.7 0.05 0.13 0.7

293 146 351 129 140 subtotal

43.88 102.38 17.55 16.09 98.28 278.17 1,630.33 57.06 1,687.39

subtotal For scaffolding,testing cement, stone aggrigate, sand, water& and casting of concrete cubes for testing including curing, cost of cement slurry, hacking exposed surfaces for finishing etc., @3.5% subtotal Add for Sundries and contingencies@3% subtotal Add for Water and electricity @1.5% subtotal Add for Contractor's profit and OH @15% Cost of 1 Cum 3.7 RCC M25 For Height not exceeding 15m( Five floors) above ground,beams column,driveways etc. - above Plinth level including scaffolding Details of cost for 1 Cum Materials Stone aggregate 20 mm Stone aggrigate 12mm Coarse sand Cement Total Material(A) Labour XXXX Mason Beldar Foreman Waterman coolie Total Labour(B) Total ( A+B) Add for Hire and running charges of mixer,vibrator water pump etc @2.75%

59.06 1,746.45 50.62 1,797.07 26.96 1,824.02 273.60 2,097.63

Cum Cum Cum Tonne

0.68 0.23 0.45 0.61

1093.44 995.52 928.20 0.00

738.07 223.99 417.69 1,379.75

each each each each each

0.15 0.7 0.05 0.13 0.7 0.7

156 293 146 351 129 140 subtotal

23.40 204.75 7.31 43.88 90.09 98.28 444.31 1,824.06 50.16 1,874.22

subtotal For scaffolding,testing cement, stone aggrigate, sand, water& and casting of concrete cubes for testing including curing, cost of cement slurry, hacking exposed surfaces for finishing etc., @1.75% subtotal Add for Sundries and contingencies@3% subtotal Add for Water and electricity @1.5% subtotal Add for Contractor's profit and OH @15% Cost of 1 Cum

32.80 1,907.02 56.23 1,963.25 29.45 1,992.70 298.90 2,291.60

3.8

Providing precast concrete units in M20 grade using necessary reinforcement and casting it at contractors casting yard, including curing, fixing erecting hooks etc., as per specification drawings and as directed by engineer-in-charge. (Reinforcement will be paid under separate item) Precast slab-At all levels( Reinforcement to be paid seperately) Basic cost of Cement concrete 1:1.5:3 as above Materail for fixing Cement(0.6*0.06) Sand Labour for fixing Foreman Beldar Coolie Mason Water man H&M of mixer vibrotor and pump for water @ 2% sub total Construction and casting of platform, curing tank, building paper cost of moulds and cost of oil etc @3% sub total Hoisting arrangement including scaffolding ., pullies ropes etc @3% sub total Add for sundries and contingencies @3% sub total Water charges and electricity @1.5% sub total Add for OH&CP Cost of 1 Cum cum q Cum Each Each Each Each Each 1 0.6 0.13 0.08 1.5 1.5 0.6 0.04 2056.33 0.00 928.20 351.00 146.25 140.40 292.50 128.70 sub total 2,056.33 117.60 28.08 219.38 210.60 175.50 5.15 638.70 12.77 651.48 19.54 671.02 20.13 691.15 20.73 711.89 10.68 722.56 108.38 3,004.88

3.9

Providing and fixing to correct level, line plumb, vertical, plain formwork in all shapes made of plywood/ MS plates for RCC works including necessary shuttering,scaffolding, removal using approved mould releasing agents, bracing etc. leaving necessary recesses opening etc. keeping the same in position during concreting and removing after the specified curing period, all complete as per specification and as directed by engineer-in charge. For depth not exceeding 5m below ground Centering and shuttering including strutting,propping etc. and removal of formwork for Foundation, footing bases of columns etc.for mass concrete below ffl Details of cost for footing size 2.7m x 2.7m x 1m Contact area =10.8 sqm Materials MS sheet 14g for main and small forms Main Small Add for wastage@10% Weight @15.7kg/sqm Angle iron for backing Verticals Horizontals

SQM

4*4*0.6*1.2 4*1*0.3*1 Total q 4*4*2*1.2 4*1*2*1 4*4*4*0.6 4*1*4*0.3

11.52 1.2 1.28 14 2.2 38.4 8 38.4 4.8 89.6 313.6 17.9 3.32 5 0.18 5.3 0.56

sqm sqm sqm 3500.00

7,700.00

Weight @3.5kg/rm Add for wastage Total corner angle including wastage Weight Fabrication charges of panels, angles Cariage of steel assuming 80 times usage Total Rate per usage Salvage@25% Total cost per usage MS pipes 40mm dia (4*3*3.25) Double couplers Single couplers Bolts and nuts Cost per usage (200 uses) Labour

q 4*1.2 q q MT

RM kg kg 3500.00 m 3500.00 1500.00 2500.00

11,602.50 612.50 7,950.00 1,402.50 29,267.50 365.84 (91.46) 274.38 11,700.00 1,080.00 1,800.00 800.00 76.90

m Nos Nos LS

39 12 24

300.00 90.00 75.00

Carpenter Helper Total cost per 10.8sqm shuttering Add for shuttering oil @0.5%

Nos Nos

1.4 2.4

292.50 175.50

Sub total Contingencies@6% Sub total Contractors profit and OH@15% Total per sqm

409.50 421.20 830.70 1,181.98 5.91 1,187.89 71.27 1,259.17 188.87 134.08

4 4.1

MORTARS Cement mortar (1:1) cum Output - 1 cum Materials cement Tonne Sand cum Cost of Material(A) Labour For Measuring and mixing Mate Each Beldar Each Water man Each Total Labour(B) Total(A+B) Hire charges, mainatence of mixer sundries and contingencies @0.85% Cost of 1 cum of Mortar Cement mortar (1:2) cum Output - 1 cum Materials cement Tonne Sand cum Cost of Material(A) Labour For Measuring and mixing Mate Each Beldar Each Water man Each Total Labour(B) Total(A+B) Hire charges, mainatence of mixer sundries and contingencies @1.0% Cost of 1 cum of Mortar Cement mortar (1:3) cum Output - 1 cum Materials cement Tonne Sand cum Cost of Material(A) Labour For Measuring and mixing Mate Each Beldar Each Water man Each Total Labour(B) Total(A+B) Hire charges, mainatence of mixer sundries and contingencies @1.25% Cost of 1 cum of Mortar Cement mortar (1:4) cum Output - 1 cum Materials cement Tonne Sand cum Cost of Material(A) Labour For Measuring and mixing Mate Each Beldar Each Water man Each Total Labour(B) Total(A+B) Hire charges, mainatence of mixer sundries and contingencies @1.5% Cost of 1 cum of Mortar

1.03 0.71

0.00 928.20

661.34 661.34

0.25 0.5 0.2

175.5 146.25 128.7

43.88 73.13 25.74 142.74 804.08 6.83 810.92

4.2

0.68 0.95

0.00 928.20

881.79 881.79

0.25 0.5 0.2

175.5 146.25 128.7

43.88 73.13 25.74 142.74 1,024.53 10.25 1,034.78

4.3

0.51 1.07

0.00 928.20

993.17 993.17

0.25 0.5 0.2

175.5 146.25 128.7

43.88 73.13 25.74 142.74 1,135.91 14.20 1,150.11

4.4

0.38 1.07

0.00 928.20

993.17 993.17

0.25 0.5 0.2

175.5 146.25 128.7

43.88 73.13 25.74 142.74 1,135.91 17.04 1,152.95

4.5

Cement mortar (1:5) cum Output - 1 cum Materials cement Tonne Sand cum Cost of Material(A) Labour For Measuring and mixing Mate Each Beldar Each Water man Each Total Labour(B) Total(A+B) Hire charges, mainatence of mixer sundries and contingencies @1.75% Cost of 1 cum of Mortar Cement mortar (1:6) cum Output - 1 cum Materials cement Tonne Sand cum Cost of Material(A) Labour For Measuring and mixing Mate Each Beldar Each Water man Each Total Labour(B) Total(A+B) Hire charges, mainatence of mixer sundries and contingencies @1.9% Cost of 1 cum of Mortar

0.31 1.07

0.00 928.20

993.17 993.17

0.25 0.5 0.2

175.5 146.25 128.7

43.88 73.13 25.74 142.74 1,135.91 19.88 1,155.79

4.6

0.25 1.07

0.00 928.20

993.17 993.17

0.25 0.5 0.2

175.5 146.25 128.7

43.88 73.13 25.74 142.74 1,135.91 21.58 1,157.50

Masonry Providing & laying thk brick masonry work in C.M. 1:5 including all necessary scaffolding, raking out joints, curing etc. complete as per specification and as directed by engineer-in charge.(Bricks shall be of 1 st class quality & conforming to S 1077 with minimum crushing strength of 35 kg/sq. cm) Below FGL up to 5 m depth. cum Details of cost for 1 cum Materials Bricks of class designation 35 Cement Mortar 1:5 Material Cost(A) Labour Mason Beldar Coolie Waterman Labour cost(B) Add for pumps and wate@0.5% sub total Sundries@3% sub total Add for water charges & electricity@1.5% sub total Add for Contractor's profit and overheads @ 15% Cost of 1 Cum 1000 Nos Cum 0.5 0.25 2550.00 1155.79 1,275.00 288.95 1,563.95

5.1

each each each each

0.4 0.5 0.5 0.20

292.50 146.25 140.40 128.70 sub total

117.00 73.13 70.20 25.74 286.07 1,850.01 9.25 1,859.26 55.78 1,915.04 28.73 1,943.77 291.57 2,235.33

5.2

Brickwork in super structure above plinth level up to 5th floor Materials Bricks of class designation 35 Cement Mortar 1:5 Material Cost(A) Labour Foreman Mason Beldar Coolie Waterman Labour cost(B) Add for H&M of mixer, lift,pumps fr water etc., @3% sub total Scaffolding, Challies ropes etc.,@3% sub total Sundries and contingencies@3% sub total Add for water charges & electricity@1.5% sub total Add for Contractor's profit and overheads @ 15% Cost of 1 Cum 1000 Nos Cum 0.5 0.25 2550.00 1155.79 1,275.00 288.95 1,563.95 58.50 87.75 91.26 83.66 45.05 366.21 1,930.16 57.90 1,988.06 59.64 2,047.70 61.43 2,109.14 31.64 2,140.77 321.12 2,461.89

each each each each each

0.2 0.6 0.65 0.65 0.35

292.50 146.25 140.40 128.70 128.70 sub total

5.3

Half brick masonry (115mm thk) in CM 1:3 Below FGL up to 5 m depth. Details of cost for 10 sqm Materials Bricks of class designation 35 Cement Mortar 1:5 Material Cost(A) Labour Mason Beldar Coolie Waterman Labour cost(B) Add for pumps and wate@0.5%

sqm

1000 Nos Cum

0.57 0.28

2550.00 1150.11

1,440.75 322.03 1,762.78

each each each each

0.9 0.6 0.4 0.20

292.50 146.25 140.40 128.70 sub total sub total

Sundries@3% sub total Add for water charges & electricity@1.5% sub total Add for Contractor's profit and overheads @ 15% 10 sqm Rate per sqm

263.25 87.75 56.16 25.74 432.90 2,195.68 10.98 2,206.66 66.20 2,272.86 34.09 2,306.95 346.04 2,653.00 265.30

5.3

Half brick masonry (115mm thk) in CM 1:3 In supersructure up to 5th floor Out put - 10 sqm Materials Bricks of class designation 35 Cement Mortar 1:5 Material Cost(A) Labour Foreman Mason Beldar Coolie Waterman Labour cost(B) Add for H&M of mixer, lift,pumps fr water etc., @3% sub total Scaffolding, Challies ropes etc.,@3% sub total Sundries and contingencies@3% sub total Add for water charges & electricity@1.5% sub total Add for Contractor's profit and overheads @ 15% Cost of 10 sqm rate per SQM 1000 Nos Cum 0.57 0.28 2550.00 1150.11 1,453.50 322.03 1,775.53 70.20 351.00 102.38 84.24 32.18 639.99 2,415.52 72.47 2,487.99 74.64 2,562.63 76.88 2,639.51 39.59 2,679.10 401.86 3,080.96 308.10

each each each each each

0.2 1.2 0.7 0.6 0.25

351.00 292.50 146.25 140.40 128.70 sub total

5.4

RR masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12, at plinth level with cement mortar 1:6 Unit Output - 3 cum Material Hard stone at quarry Bond stones(Headers) Quoins(Corner stones0 Cement mortar 1:6 Cement for concrete 20mm stone aggrigate including carting Total Material(A) Labour Foreman Mason Beldar Coolie Water man Total Labour (B) Total (A+B) Sundries and contingencies @3% Add for water charges & electricity@1.5% subtotal Add for Contractor's profit and overheads @ 15% subtotal Rate of RR masonry per CUM 7,212.63 2,404.21 cum

cum 100 Nos 100 Nos cum kg cum

2.58 0.14 0.2 1 5 0.02

1020 1020 1020 1,157.50 0 1093.44

2,631.60 142.80 204.00 1,157.50 24.06 4,159.95

Each Each Each Each Each

0.6 3 2.4 2.4 0.45

351 292.5 146.25 140.4 140.4

subtotal

210.60 877.50 351.00 336.96 63.18 1,839.24 5,999.19 179.98 6,179.17 92.69 6,271.86 940.78

5.5

CRS masonry with hard stone in foundation and plinth with cement mortar 1:6 Unit cum Output - 4 cum Material Size stone Bond stones Quoins(Corner stones) Cement mortar 1:6 Hard stone Total Material (A) Labour Foreman Mason Beldar Coolie Water man Total Labour (B) Total (A+B) Sundries and contingencies @3% Add for water charges & electricity@1.5% subtotal Add for Contractor's profit and overheads @ 15% subtotal Rate of RR masonry per CUM 6,802.44 1,700.61

each 100 Nos 100 Nos cum cum

84 0.12 0.12 1.2 0.73

18 1500 2000 1157.50 282

1,512.00 180.00 240.00 1,389.00 205.86 3,526.86

Each Each Each Each Each

0.15 3.5 3.5 3.5 0.4

351 292.5 146.25 140.4 128.7

subtotal

52.65 1,023.75 511.88 491.40 51.48 2,131.16 5,658.01 169.74 5,827.75 87.42 5,915.17 887.28

6 6.1

WATER PROOFING Providing laying brickbat coba for water proofing treatment Unit Output - 16.2 sqm Materials Cement Brick bats Course sand Water proofing compund Total Material (A) Labour for applying slury twice including cleaning surface Beldar For bottom 20mm rendering Foreman Mason Beldar Coolie Water man Total Labour for 20m rendering (B) For brick bat concrete Foreman Mason Beldar Coolie Water man Total labour For brick bat concrete ( C) For two Days Curing Water man Total labour For curing (D) For final finishing Foreman Mason Beldar Coolie Water man Total labour For Final finishing ( E) For flooding the terrace for 15 days Foreman Water man Total labour For Flooding( F) For Dewatering and cleaning surface Beldar Total labour For Dewatering( G) Total A+B+C+D+E+F+G Add for lift to convey materils, pumps for water@1% Subtotal Add for wire brushes , brooms etc.,@0.75% Subtotal Add for rounding corners grooves and cheques @3% Subtotal sundries and contingencies@3% Subtotal Add for water and electricity @1.5% Subtotal Add for contractors profit and over head charges@15% Cost of 16.2 sqm Rate per sqm Subtotal

SQM

q cum cum q

5.2 0.9 1.25 0.11

0 1020 928.2 100

918.00 1,160.25 10.50 2,088.75

each each each each each each

1.25 0.25 1 1 1 0.2

146.25 351 292.5 146.25 140.4 128.7

182.81 87.75 292.50 146.25 140.40 25.74 875.45

each each each each each

0.25 0.25 0.95 0.95 0.35

351 292.5 146.25 140.4 128.7

87.75 73.13 138.94 133.38 45.05 478.24

each

0.5

128.7

64.35 64.35

each each each each each

0.25 1.5 1.5 1.5 0.35

351 292.5 146.25 140.4 128.7

87.75 438.75 219.38 210.60 45.05 1,001.52

each each

0.5 4

351 128.7

175.50 514.80 690.30

1.5

146.25

219.38 219.38 4,939.75 49.40 4,989.14 37.42 5,026.56 150.80 5,177.36 155.32 5,332.68 79.99 5,412.67 811.90 6,224.57 384.23

7 7.1

Flooring Coloured glazed tile, grade 1 of approved make 8 mm thick Ceramic tiles 1Sq.mt + 5% wastage 12 mm th CM 1:3 Cement for slurry @3.3 kg /smt foreman mason beldar waterman Add for mortar for pointing@7% subtotal Add for sundries @3% subtotal Add for water charges @ 1% subtotal Add for OH and CP @15% cost per sqmt Sq.mt Cum q Each Each Each Each 1.05 0.14 0.03 0.10 0.50 0.50 0.05 510.00 1150.11 0.00 351.00 263.25 146.25 128.70 subtotal 535.50 165.62 35.10 131.63 73.13 6.44 947.40 66.32 1,013.72 30.41 1,044.13 10.44 1,054.57 158.19 1,212.76

7.2

White glazed tile, grade 1 of approved make 6 mm thick Ceramic tiles 1Sq.mt + 5% wastage 12 mm th CM 1:3 Cement for slurry @3.3 kg /smt foreman mason beldar waterman Add for mortar for pointing@7% subtotal Add for sundries @3% subtotal Add for water charges @ 1% subtotal Add for OH and CP @15% cost per sqmt Sq.mt Cum q Each Each Each Each 1.05 0.14 0.03 0.10 0.50 0.50 0.05 510.00 1150.11 0.00 351.00 263.25 146.25 128.70 subtotal 535.50 161.02 35.10 131.63 73.13 6.44 942.80 66.00 1,008.80 30.26 1,039.06 10.39 1,049.45 157.42 1,206.87

7.3

KOTA STONE FLOORING (25mmto 40mm) for 10 sqmt Kota Stone inclusive of Wastage 10Sq.mt + 5% wastage 20 mm th CM 1:4 Cement +slurry CEMENT pigment foreman mason beldar waterman Special Beldar for Polishing Add for polihing@4%

Sq.mt Cum kg kg Each Each Each Each Each

11.50 0.22 64.00 4.48 0.15 3.35 3.35 1.00 1.25

357.00 1152.95 0.00 0.00 351.00 263.25 146.25 128.70 146.25 subtotal subtotal

4,105.50 258.26 52.65 881.89 489.94 128.70 182.81 6,099.75 243.99 6,343.74 126.87 6,470.61 194.12 6,664.73 99.97 6,764.70 1,014.71 7,779.41 777.94

add for carborunum stones @2% subtotal Add for sundries @3% subtotal Add for water charges @ 1.5% subtotal Add for OH and CP @15% subtotal cost per sqmt

7.4

P/F GRANITE STONE, 12 mm thick Detail cost for 10 Sqm Sq.mt 11.50 Cum kg kg Each Each Each Each Each 0.22 64.00 4.48 0.15 3.35 3.35 1.00 1.25

Granite Stone inclusive of Wastage 10Sq.mt + 5% wastage 20 mm th CM 1:4 Cement +slurry CEMENT pigment foreman mason beldar waterman Special Beldar for Polishing Add for polihing@4%

1020.00 1152.95 0.00 0.00 351.00 263.25 146.25 0.00 146.25 subtotal subtotal

11,730.00 258.26 52.65 881.89 489.94 182.81 13,595.55 543.82 14,139.37 282.79 14,422.16 432.66 14,854.82 222.82 15,077.65 2,261.65 17,339.29 1,733.93

add for carborunum stones @2% subtotal Add for sundries @3% subtotal Add for water charges @ 1.5% subtotal Add for OH and CP @15% subtotal cost per sqmt 7.4 P/F GRANITE STONE, 20 mm thick Detail cost for 10 Sqm Sq.mt 11.50 Cum kg kg Each Each Each Each Each 0.22 64.00 4.48 0.15 3.35 3.35 1.00 1.25

Granite Stone inclusive of Wastage 10Sq.mt + 5% wastage 20 mm th CM 1:4 Cement +slurry CEMENT pigment foreman mason beldar waterman Special Beldar for Polishing Add for polihing@4%

2203.20 0.00 0.00 0.00 0.00 0.00 351.00 128.70 146.25 subtotal subtotal

25,336.80 1,175.85 128.70 182.81 26,824.16 1,072.97 27,897.13 536.48 28,433.61 804.72 29,238.34 402.36 29,640.70 4,023.62 33,664.32 3,366.43

add for carborunum stones @2% subtotal Add for sundries @3% subtotal Add for water charges @ 1.5% subtotal Add for OH and CP @15% subtotal cost per sqmt

7.6

50 mm th Cement concrete flooring 1:2: 4 Mix using 20mm metal For 10 Sqm Details of cost for 10 sqmt Materials Stone aggregate 20 mm Stone aggregate 12 mm Coarse sand Cement Cost of material Labour Mason Beldar Foreman Waterman coolie Total Add for Hire and running charges of mixer,vibrator water pump etc @2% Add for form work @2% Add for Sundriesand contingencies @3% Add for W.C. & Electricity @ 1.5% Add for Contractor's profit and overheads @ 15% overheads @ 15% Cost per 10 sqm Cost of 1 Sqm

Cum Cum Cum Tonne

0.35 0.12 0.24 2.02

1093.44 995.52 928.2 0

385.44 116.97 218.13 720.54 263.25 146.25 35.10 19.31 140.40 604.31 1,324.84 26.50 1,351.34 27.03 1,378.37 41.35 1,419.72 21.30 1,441.01 216.15 1,657.17 165.72

each each each each each

1 1 0.1 0.15 1

263.25 146.25 351 128.7 140.4

7.7

40 mm th Cement concrete flooring using 20mm metal For 10 Sqm Details of cost for 10 sqmt Materials Stone aggregate 20 mm Stone aggregate 12 mm Coarse sand Cement Total material Labour Mason Beldar Foreman Waterman coolie Total Labour Total Add for Hire and running charges of mixer,vibrator water pump etc @2% Add for form work @2% Add for Sundriesand contingencies @3% Add for W.C. & Electricity @ 1.5% Add for Contractor's profit and overheads @ 15% Cost for 10 sqm Cost of 1 Sqm

Cum Cum Cum Tonne

0.28 0.09 0.19 0.17

1093.44 995.52 928.2 0

308.35 93.58 174.50 576.43 250.09 138.94 35.10 19.31 133.38 576.81 1,153.24 23.06 1,176.31 23.53 1,199.83 35.99 1,235.83 18.54 1,254.36 188.15 1,442.52 144.25

each each each each each

0.95 0.95 0.1 0.15 0.95

263.25 146.25 351 128.7 140.4

Aluminuim Work

Providing and fixing in position glazed anodised aluminum windows of 15 micron anodised aluminum sections of approved quality and make, including all anodised aluminum fixtures, like hinges, handles, fastenings etc. including making recesses in brick/concrete surfaces and making good the same after fixing windows, all as per manufacturer's specifications etc. complete as per spec. and directions. 8.1 For Frame(39.13Kg output) Aluminium Cp Brass/stainless steel screws 20mm for cleat angle Dash hold fastners Labour charges for manufacturing the required the required section by a reputed work shop Labour fitter helper Add for anodizing the sections@.19.35 sub total Add for carriage of other materials@0.75% sub total Add for rawl plug andscrews @0.85% sub total For PVC/neoprinefelt for filling gaps @0.5% sub total Hire charges of dril @0.5% sub total Sundries and contingencies @3% sub total Water charges @1% sub total Cp&OH @15% TOTAL Cost per KG 8.2 For shutter(39.13Kg output) Aluminium Cp Brass/stainless steel screws 20mm for cleat angle Dash hold fastm\ners Labour charges for manufacturing the required the required section by a reputed work shop Labour fitter helper Add for anodizing the sections@.22% sub total Add for carriage of other materials@1.25% sub total Add for rawl plug andscrews @1.00% sub total For PVC/neoprinefelt for filling gaps @0.65% sub total Hire charges of dril @0.75% sub total Sundries and contingencies @3% sub total Water charges @1% sub total Cp&OH @15% TOTAL Cost per KG

kg 100 Nos Each kg

41.89 0.72 12 39.13

200 50 20 35

8,378.00 36.00 240.00 1,369.55

0.25 0.25

292.5 140.4 sub total

73.13 35.10 10,131.78 1,960.50 12,092.27 90.69 12,182.97 103.56 12,286.52 61.43 12,347.95 61.74 12,409.69 372.29 12,781.98 127.82 12,909.80 1,936.47 14,846.27 379.41

kg 100 Nos Each kg

41.89 0.72 12 39.13

180 50 20 35

7,540.20 36.00 240.00 1,369.55

Each Each

0.4 0.4

292.5 140.4 sub total

117.00 56.16 9,358.91 2,058.96 11,417.87 142.72 11,560.59 115.61 11,676.20 75.90 11,752.09 88.14 11,840.24 355.21 12,195.44 121.95 12,317.40 1,847.61 14,165.01 362.00

8.3

Providing glazing Unit 1 sqm - 6mm thk glass Glass Noeprine/PVC gasket Glacier Helper Carrige of al material @1..5%

sqm m each each

1.1 6 0.2 0.2

418.2 15 351 140.4 sub total sub total

460.02 90.00 70.20 28.08 648.30 9.72 658.02 19.74 677.77 20.33 698.10

Sundries and contigencies @3% sub total CP&OH @15% Cost per SQM 8.4 Unit 1 sqm - 10mm thk glass Glass Noeprine/PVC gasket Glacier Helper Carrige of al material @1..5% sub total Sundries and contigencies @3% sub total CP&OH @15% Cost per SQM Plastering 1 Providing and laying 20mm thick cement plaster in two layers on RCC or masonry to all heights, including scaffolding, raking out of joints, mouldings complete as per the specifications, drawings & as directed by owner/consultant. a Cement Mortar plastering of 1:5 per 10 sqm Cement Sand( fine aggregate) water Total cost of material labour Component Skilled Labour Semi Skilled Unskilled labour Total cost for Labour Scaffolding, pumps for water contingencies and sundries Water and electricity charges @1.5% Add overhead and CP 15% Total cost other items Total for 10Sqm Rate per Sqm b Cement Mortor plastering of 1:4 per 10 sqm Cement Sand( fine aggregate) water Total cost of material labour Component Skilled Labour Semi Skilled Unskilled labour Total cost for Labour Scaffolding, pumps for water contingencies and sundries Water and electricity charges @1.5% Add overhead and CP 15% Total cost other items Total for 10Sqm Rate per Sqm TOTAL TOTAL

sqm m each each

1.1 6 0.2 0.2

836.4 15 351 140.4 sub total

920.04 90.00 70.20 28.08 1,108.32 16.62 1,124.94 33.75 1,158.69 34.76 1,193.45

tonnes cum litres

0.07 0.24

0 928.2

222.47 222.47

Nos Nos Nos

1.2 2.5 0.15

292.5 234 175.5

351.00 585.00 26.33 962.33 20.19 0.79 17.77 177.72 216.47 1,401.26 140.13

2.50% 3.00% 1.50% 15%

10

tonnes cum litres

0.09 0.24

0 928.2 0.3

222.47 222.47

Nos Nos Nos

1.2 2.5 0.15

292.5 234 175.5

351.00 585.00 26.33 962.33 20.19 0.79 17.77 177.72 216.47 1,401.26 140.13

2.50% 3.00% 1.50% 15%

10

Cement Mortor plastering of 1:3 per 10 sqm Cement Sand( fine aggregate) water Total cost of material labour Component Skilled Labour Semi Skilled Unskilled labour Total cost for Labour Scaffolding, pumps for water contingencies and sundries Water and electricity charges Add overhead and CP Total cost other items Total for 10Sqm Rate per Sqm Providing and laying 12mm thick cement plaster in one layers on RCC or masonry to all heights, including scaffolding, raking out of joints, mouldings complete as per the specifications, drawings & as directed by owner/consultant.

tonnes cum litres

0.11 0.24

0 928.2 0.3

222.47 222.47

Nos Nos Nos

1.2 2.5 0.15

292.5 234 175.5

351.00 585.00 26.33 962.33 0.66 35.54 36.20 1,221.00 122.10

2.50% 3.00% 1.50% 15%

10

Cement Mortor plastering of 1:5 per 10 sqm Cement Sand( fine aggregate) water Total cost of material labour Component Skilled Labour Semi Skilled Unskilled labour Total cost for Labour Scaffolding, pumps for water contingencies and sundries Water and electricity charges Add overhead and CP Total cost other items Total for 10Sqm Rate per Sqm

tonnes cum litres

0.04 0.16

0 928.2 0.3

143.87 143.87

Nos Nos Nos

0.75 1.5 0.15

292.5 234 175.5

219.38 351.00 26.33 596.70 0.66 22.22 22.88 763.45 76.34

2.50% 3.00% 1.50% 15%

10

Cement Mortor plastering of 1:4 per 10 sqm Cement Sand( fine aggregate) water Total cost of material labour Component Skilled Labour Semi Skilled Unskilled labour Total cost for Labour Scaffolding, pumps for water contingencies and sundries Water and electricity charges Add overhead and CP Total cost other items Total for 10Sqm Rate per Sqm

tonnes cum litres

0.05 0.16

0 928.2 0.3

143.87 143.87

Nos Nos Nos

1.2 2.5 0.15

292.5 234 175.5

351.00 585.00 26.33 962.33 0.66 33.19 33.84 1,140.04 114.00

2.50% 3.00% 1.50% 15%

10

Cement Mortor plastering of 1:3 per 10 sqm Cement Sand( fine aggregate) water Total cost of material labour Component Skilled Labour Semi Skilled Unskilled labour Total cost for Labour Scaffolding, pumps for water contingencies and sundries Water and electricity charges Add overhead and CP Total cost other items Total for 10Sqm Rate per Sqm

tonnes cum litres

0.07 0.16

0 928.2 0.3

143.87 143.87

Nos Nos Nos

1.2 2.5 0.15

292.5 234 175.5

351.00 585.00 26.33 962.33 0.66 33.19 33.84 1,140.04 114.00

2.50% 3.00% 1.50% 15%

10

Flooring Providing & laying minimum 25 mm thk. cement chequered tiles of approved make & colour laid in approved pattern and to the required slope in cement/sand C M 1:3 (cement mortor of 20mm thk) bedding on floor, including filling joints with cement compacting & rolling etc.,complete as per specifications, drawings & as directed by owner/consultant.(contractor shall state the basic rate & type of tile assumed at time of quoting) Carriage : Chequered tiles delivered at site Material cost of cement mortor of 1:4 , 20mm thk Total cost of material labour component for laying the cement concrete Skilled labour Semi skilled Unskilled Coolie water man Beldar for polishing Total cost for labour contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items Total for 10 Sqm Total for 1 sqm Walkway Tiles around tank farm area and sales building Carriage : Walk way tiles delivered at site Material cost of cement mortor of 1:4 , 20mm thk Total cost of material labour component for laying the cement concrete Skilled labour Semi skilled Unskilled Coolie water man Beldar for polishing Total cost for labour contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items Total for 10 Sqm Total for 1 sqm 4 Filling with available good Excavated earth for 10 cum Labour component Semi skilled unskilled Total for labour component contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items Total cost for 10 cum Cost for 1 cum

sqm sqm

11 12

255 122.10

2,805.00 1,465.20 4,270.20

Each Each Each Each Each Each

0.15 3 2.5 2.5 1 2

292.5 234 175.5 117 140.4 146.25

43.88 702.00 438.75 292.50 140.40 292.50 1,910.03 185.41 92.70 927.03 1,205.14 7,385.37 738.54

3.00% 1.50% 15%

10

sqm sqm

11 12

255 122.10

2,805.00 1,465.20 4,270.20

Each Each Each Each Each Each

0.15 3 2.5 2.5 1 2

292.5 234 175.5 117 140.4 146.25

43.88 702.00 438.75 292.50 140.40 292.50 1,910.03 185.41 92.70 927.03 1,205.14 7,385.37 738.54

3.00% 1.50% 15%

10

Nos Nos

1.35 1.45

234 175.5

315.90 254.48 570.38 17.11 8.56 85.56 111.22 681.60 68.16

3.00% 1.50% 15%

10

Supply and filling in plinth/ Around tank walls/ canopy foundation.. Etc Cost imported CNS Earth transported from 5 km radius Cum 10 229.5 2,295.00

Labour component Semi skilled unskilled Total for labour component contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items Total cost for 10 cum Cost for 1 cum 6 Supply and filling with graded course aggregate metal around Fuel Tank - 10mm down size Cost of 10mm downgraded coarse aggregate

Nos Nos

1.35 1.45

234 175.5

315.90 254.48 570.38 17.11 8.56 85.56 111.22 2,976.60 297.66

3.00% 1.50% 15%

10

cum

10

995.52

9,955.20

Labour component Semi skilled unskilled Total for labour component contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items Total cost for 10 cum Cost for 1 cum 7 a Road works/ pavement works Subgrade preparation Preparation of subgrade by excavating earth to average of 225mm depth. Dressing to camber and consolidating with road roller. Incl making good the undulations etc. and disposal of surplus earth lead upto 50 m say for 100sqm Earth works in excavation Labour component Skilled semi skilled unskilled total Labour component

Nos Nos

1.35 1.45

234 175.5

315.90 254.48 570.38 17.11 8.56 85.56 111.22 10,636.80 1,063.68

3.00% 1.50% 15%

10

cum

22.5

No Nos nos

1 9.25 9.25

225 110 110

225.00 1,017.50 1,017.50 2,260.00

Equipment - Hire cost of Road roller incl operator and lubes Diesel for Road roller Total for Equipment cost contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items Total cost for 100sqm Cost for 1 sqm

Each/per day Litres

0.05 0.97

2244 34.94

121.18 33.96 155.13 4.65 2.33 23.27 30.25 2,445.38 24.45

3.00% 1.50% 15%

100

Granular Sub base- preparation for 100 sqm

Refering to Z0-Z00-C3-1775-03 Granular sub base considering 5% soaked CBR Sub-base to be prepared by filling supersaturated river sand/stone grit/murrum/granular soil or mixture of all in case of murrum & soil the liquid limit & plasticity index shall be less than 20 & 6 respectively, complete as per drawing. The compaction shall be in layers to get 98 % relative density after sprinkling required quantity of water. The consolidation shall be done using 8-10 ton roller as per the camber required. Suitable thickness of Sub-base shall be selected as per SOAK CBR VALUE available at site & as per drawing. The gradation and CBR value of the material to be used for sub-base shall be as per Table 1A /1B (Thk OF GSB of 250mm) cum Labour component Skilled semi skilled unskilled total Labour component

25

816

20,400.00

No Nos nos

1.25 7.75 12.75

225 110 110

281.25 852.50 1,402.50 2,536.25

Equipment - Hire cost of Road roller incl operator and lubes Diesel for Road roller Total for Equipment cost Add for carriage of diesel,templates,screens and hand brooms contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items Total cost for 100sqm Cost for 1 sqm Cost per Cum

Each/per day Litres

0.1 1.95

5000 35

500.00 68.25 568.25 310.45 93.14 31.05 465.68 589.86 24,094.36 240.94 963.77

10% 3.00% 1.00% 15%

100 1

Providing & laying waterbound macadam for paving portion 225 mm compacted thickness in three layers of 75 mm thick each (using 40 to 65 mm size crushed stone aggregate of approved quality). spreading metal of specified zone, dry rolling with 10 M.T roller. NOTE:- a) After final compaction of each layer the paving shall be allowed to cure overnight. any unevenness noticed on the surface shall be filled with screenings or binding material, lightly sprinkled with water & rolled . No traffic shall be allowed b) quoted rates shall be inclusive of taking levels before & after laying various layers & carrying out following lab test on aggregates & test results to be submitted to engineer in charge before use. LAB TEST- i) LA abrasion value- 40 % max.

Material cost for 1 cum Coarse aggreagate 40 mm to 65 mm Stone screenings /binding material Total cost of material Labour component Skilled Semi skilled Unskilled Total cost for Labour component Cum Cum 0.96 0.7 979.2 663 940.03 464.10 1,404.13

Nos Nos Nos Nos

0.1 0.25 0.5

225 150 110

22.50 37.50 55.00 115.00

Equipment - Hire cost of Road roller incl operator and lubes Diesel for Road roller Total for Equipment cost Add for carriage of diesel,templates,screens and hand brooms contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items Total cost of material for 1cum

Each/per day Litres

0.03 0.59

2244 34.94

74.05 20.61 94.66 10.48 6.29 2.10 31.45 50.32 1,664.11

5% 3.00% 1.00% 15% 1

10

Providing and laying 50mm thick Bituminous macadam course above the W.B.M layer of road/paving portion.Firstly application of Prime coat of 0.9kg/m & tack coat of 0.3kg/m over WBM layer. Bituminous macadam shall consist of aggregates 19 mm & downsize . Material cost Considering 66.81 cum output mixer plant Bitument 80/100 Stone aggregate 19.5mm Stone aggregate 13.2mm fine aggregate Total material cost Hirecharges for Equipment BG(Barber green hot Mix) plant Tipper Loader Roadroller Total Diesel qty for hotmix plant,premixing and heating material,steam burner,road roller and tipper Total for Equipment hire and operation Labour component Skilled labour Semi skilled waterman Total cost for labour Add for carriage of diesel,templates,screens and hand brooms contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items total cost for 66.81 cum Cost per cum Cost per Sqm

Ton Cum Cum Cum

5.88 21.75 74.17 2.97

22440 1093.44 995.52 928.2

131,947.20 23,782.32 73,837.72 2,756.75 232,323.99

perday perday perday perday litres

1 5 1 4 1016

10346.88 1530 0 2244 34.94

10,346.88 7,650.00 8,976.00 35,493.96 62,466.84

nos nos nos

1 12 7

292.5 234 128.7

2% 3.00% 1.00% 15%

Sqm

66.81 20

292.50 2,808.00 900.90 4,001.40 298,792.23 5,228.86 8,963.77 2,987.92 44,818.83 61,999.39 360,791.62 5,400.26 270.01

11

Providing and laying 20mm thick Premix carpet above the Bituminious course of road/paving portion.Firstly application of Tack coat of 0.3 kg/mbitumen over bituminous macadam course. Premix carpet shall consist of aggregates of nominal stone size 13.2 mm Material component Bitument Aggregate 11.2 mm Diesel for road roller total for material hire charge for Equipement Road roller Mixer Total cost for Equipment Hires Labour component Skilled Semi skilled unskilled Waterman total labour Add for carriage of diesel,templates,screens and hand brooms contingencies and sundries Water and electricity charges Add overhead and CP Total cost of other items Total for 100 sqm Cost per sqm

tons cum litres

0.23 2.4 1.8

22440 995.52 34.94

5,161.20 2,389.25 62.88 7,613.33

Per day Per day

0.1 0.05

2244 816

224.40 40.80 265.20

each each each each

0.3 5.25 2.35 0.4

292.5 234 175.5 175.5

4% 3.00% 1.00% 15% sqm 100

87.75 1,228.50 412.43 70.20 1,798.88 9,677.41 387.10 290.32 96.77 1,451.61 2,225.80 11,903.21 119.03

12

Seal Coat. Providing and laying seal coat of premixed fine aggregate Analysis for 100 Sqm Material component Bitumen Coarse sand Steam coal Diesel for roller Total cost of material Hire charges for equipment Road roller Boiler Mixer Total cost of Equipment Labour component Skilled semi skilled Unskilled Cost of labour component Subtotal other cost Add for screening/wire brushes ..etc Add for carriage and steel. Etc Add for sundies and contigencies Add for water charges Add for OH and CP Total other cost Rate per sqm Kerb stone ( Includes Precast of Kerb Stones and Fixing and Excludes excavation and PCC base concrete) Supply and Laying of kerb stone( 10.156m) Transport cost Labour cost Skilled Semi Skilled Unskilled Waterman Total for Labour cost Other cost Marking Drainage opening,cement nmortor and fixing cost Add for sundies and contigencies Add for water charges Add for OH and CP Total other cost Cost for laying per RM Rm

Tonne cum Quintal Lit

0.08 0.6 0.15 2.7

22440 928.2 1224 34.94

1,723.39 556.92 188.01 94.32 2,562.64

per day per day per day

0.15 0.25 0.04

2244 979.2 816

336.60 244.80 32.64 614.04

Each Each Each

0.3 4.35 2.4

351 234 117

105.30 1,017.90 280.80 1,404.00 4,580.68 114.52 91.61 137.42 45.81 687.10 1,076.46 5,657.14 56.57

2.50% 2.00% 3% 1% 15%

100

Rm Tones

10.15 1.48

1200 150

12,180.00 222.00

Each Each Each Each

1.25 0.3 0.2 0.1

351 234 117 128.7

438.75 70.20 23.40 12.87 545.22 12,947.22 776.83 388.42 129.47 1,942.08 3,236.81 4,004.03 364.00

6% 3% 1% 15%

11

Steel Works Reinforcement works Providing and laying high yield strength deformed steel bars Fe 415 (ribbed Tor--steel or approved equivalent) in all reinforced concrete work including cutting, bending, laying in position binding with 18 gauge annealed steel wire Fe 415 steel, All diametres Quintal Carriageof steel bar tonr Binding wires 1% kg Total cost of material Labour Component Skilled Semiskiled Cost of labour Other cost Tools and tackles Scafollds and cocver block Sundries and cont Add for OH and CP Total other cost Total cost Cost per Kg Structural steel Supply & fabrication of structural steel at shop using steel conforming to IS :2062, including transporting, erecting prefabricated structure (using lifting equipments like cranes, tools & tackles), framed arched structure, fabricated built-up steel sect Note-site welding will not be permitted. Cleaning the surface of dust and loose particles, surface preparation, by sandblasting process to achieve surface roughness not exceeding 20 microns, two primer coats of catalysed epoxy resin/zinc phosphate cured with polyamide 30 microns DFT per coat & t Cost of material Cost of priming coat Carriageof steel bar Cost of material Labour Skiled Unskiled Cost of Labour Other Cost Add for Gas cutting/ scafolding Sundries and cont Water and Electircty Add for OH and CP Total other cost Cost per Quintal Cost per Kg Quintal Sq ton 2.78 7 0.28 0 15.3 107.10 107.10

1 0.11 5

0 48.96

244.80 244.80

Eac Eac

0.54 0.5

292.5 234

157.95 117.00 274.95 519.75 7.80 7.80 15.59 77.96 109.15 628.90 6.29

1.50% 1.50% 3.00% 15%

100

Each Each

2 4

292.5 234

585.00 936.00 1,521.00 1,628.10 65.12 48.84 8.14 244.22 366.32 1,994.42 7.53

4% 3.00% 0.50% 15% 265

Concrete pavement M 20concrete 1:1.5:3 for 54 m x 54 m Concrete delivered at site Cost of plastic sheet 250micron thk Material cost Labour component Skilled Semi skilled Unskilled cum sqm 291.6 1603.8 2,056.33 1.5 599,625.09 2,405.70 602,030.79

Each Each Each

45 95 113

225 150 110

10,125.00 14,250.00 12,430.00 36,805.00 638,835.79 1,597.09 1,916.51 3,833.01 19,165.07 9,582.54 95,825.37 131,919.59 770,755.37 2,643.19

Total other cost Add for Farm work/diesel, sheets .brooming..etc Planks for mason to work Add for casting and cube testing Sundries and cont Water and Electircty Add for OH and CP Total other cost Total cost Per cum

0.25% 0.30% 0.60% 3.00% 1.50% 15%

291.6

Fencing Works Barbed wire fencing Providing & fixing barbed wire fencing 1.5 m height including supply and fixing of support angles L 50x50 x 6 ( with bend part angle with 3 stand) at 3m c/c including embedding the angles in PCC 1:2:4 tying the barbed wire to the support angles with 18 gauge wire and applying 1 coat of red oxide primer and 2 coats of synthetic enamel paint of approved make and shade etc complete as per drawing for 30m length Material cost Earth work in excavation cum CC 1:5:10 cum Angle post q Barbed wire Runner flat Labour Skilled Unskilled Rm Quint

1.75 1.75 1.06 210 0.26

115.56 2,061.15 0 10 0

202.23 3,607.02 2,100.00 5,909.25 73.13 877.50 950.63 6,859.87 137.20 205.80 1,028.98 1,371.97 8,231.85 274.39

Each Each

0.25 3.75

292.5 234

other cost Add for Bidind wires, bolts Sundries Add OH and CP other cost Total Cost Cost per Rm Chain link fencing Providing, supplying, fabricating and fixing GI chain link fencing of 50mm x50mm mesh of 10g thick with MS angles and of approved manufacturer and fixing to 65 x 65 x 6angle posts at approximately 3m c/c and at corners, including excavation & backfilling of required width & depth for post foundations , PCC 1:3:6 for foundations and supply & application of one coat of primer & 2 coats of finish paint of approved shade and quality etc. complete as per spec. and as directed by engineer - in - charge. Material cost Earth work in excavation CC 1:5:10 Angle post Chain link fencing Runner flat Labour Skilled Unskilled

2% 3% 15%

30

cum cum q kg Quint

1.75 1.75 1.06 126 0.26

115.56 2,061.15 0 38 0

202.23 3,607.02 4,788.00 8,597.25 73.13 877.50 950.63 9,547.87 190.96 286.44 1,432.18 1,909.57 11,457.45 381.91

Each Each

0.25 3.75

292.5 234

other cost Add for Bidind wires, bolts Sundries Add OH and CP other cost Total Cost Cost per Rm

2% 3% 15%

30

Paver Block Interlocking pavement Supply and laying of M 40 grade (Comp. Strength of 400 kg/sq. cm) interlocking concrete paving blocks of approved make.The concrete block should be machine made, pattern of laying is as specified type with brick size minimum 200mm x 100mm The rate should include providing 70 to 100 mm thk coarse silt free river sand bedding. The block to be laid to the required slope and profile for better water management as at site and compacted with appropriate mechanical compactors. The edges to be neatly trimmed by providing kerbs along the periphery of the paved area in PCC 1:2:4 of150mm x200 mm in cross section all complete as per standards. The ingrace and out grace needs to be reinforced with cement concrete for smooth entry and exit of vehicles. MATERIAL Paver block Fine sand Coarse sand LABOUR Mason Beldar Water man Beldar for cleaning cost of vibrator

sqm cum cum

10.00 0.15 0.50

561 928.2 928.2

5,610.00 139.23 464.10 6,213.33 131.63 146.25 146.25 75.00 499.13 6,712.46 201.37 100.69 1,006.87 1,308.93 8,021.38 802.14

each each each each each

0.50 1.00 0.00 1.00 0.15

263.25 146.25 128.7 146.25 500

Other cost Add for contingencies & sundries @ 3% Add for W.C. & Electricity @ 1.5% Add for CP & O.H.@ 15% Total of other cost cost for 10 Sqm Cost per Sqm Sanitary Items Stoneware pipe Providing and laying , jointing the glazed stoneware pipe of grade A with Stiff Mixture of Cement mortor 1;1. Detail of cost of working for 30 M Material S W pipe 150mm dia, each 600mm in length Cement Sand Spun Yarn Total material Labour Skilled semi skilled Unskilled Water man Total Labour Other cost Add testing of pipe,cement slurry etc Sundries Add OH and CP Water charges Total of other cost Cost for 30 m Per RM

3% 1.50% 15%

10

each Kg Cum Kg

55 75 0.05 9

45.9 0 928.2 5.1

2,524.50 48.73 45.90 2,619.13

Each Each Each Each

0.45 3 4 0.3

292.5 234 140.4 128.7

131.63 702.00 561.60 38.61 1,433.84 4,052.97 111.46 121.59 607.94 40.53 881.52 4,934.49 164.48

2.75% 3% 15% 1%

30

Pile Works Details for Under reamed Pile, providing and installaton of csat in situ single inder reamed pile of Specified Dia sauy 300mm 10m long Material Cement Aggregates Sand rebars @2% steel Bentonite slury Cost of material Labour for Boring Skilled Semi skilled Unskilled helper Labour for concreting Skilled Semi skilled Unskilled helper Total for Labour Other costs Add for Lab, consultantss Add for conducting test, design accuracy..etc Add for Concrete Mixer , batcheer, vibrators Add for Hire of Piling rigs, steel casing cariageof material Repair and replace cost of parts, concrete for casinf pile cap Sundries Add OH and CP

Kg Cum Cum Kg t

265 0.73 0.37 200 0.08

1,060.80 928.20 6.29 8,000.00

774.38 343.43 1,257.80 624.00 2,999.61

each each each each each each each each

0.5 0.5 0.5 2 0.2 0.37 2.5 1.45

292.50 234.00 175.50 175.50 292.50 234.00 175.50 175.50

146.25 117.00 87.75 351.00 58.50 86.58 438.75 254.48 1,540.31 4,539.92 227.00 90.80 90.80 726.39 136.20 68.10 680.99 2,020.26 6,560.18 656.02

5% 2% 2% 16% 3% 1.50% 15%

Rate per Rm Bored Piles for 300mm for 20m length Details for bored Pile, providing and installaton of Cast insitu Pile

Rm

10

Material Cement Aggregates Sand rebars @2% steel Bentonite slury Cost of material Labour for Boring Skilled Semi skilled Unskilled helper Labour for concreting Skilled Semi skilled Unskilled helper Total for Labour Other costs Add for Lab, consultantss Add for conducting test, design accuracy..etc Add for Concrete Mixer , batcheer, vibrators Add for Hire of Piling rigs, steel casing cariageof material Repair and replace cost of parts, concrete for casinf pile cap Sundries Add OH and CP Total of other cost Rate per Rm

Kg Cum Cum Kg t

479 1.32 0.66 200 0.14

1,060.80 928.20 6.29 8,000.00

1,400.26 612.61 1,257.80 1,128.00 4,398.66

each each each each each each each each

0.75 0.75 0.75 3 0.15 0.3 2 1.15

292.50 234.00 175.50 175.50 292.50 234.00 175.50 175.50

219.38 175.50 131.63 526.50 43.88 70.20 351.00 201.83 1,719.90 6,118.56 305.93 122.37 122.37 1,330.79 152.96 91.78 917.78 3,043.99 9,162.55 458.13

5% 2% 2% 22% 3% 1.50% 15%

Rm

20

Water supply Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and making good the walls etc. (Internal Work) Exposed wall 15 mm dia G.I. pipe for 10 m length Materials Components Pipe cost + Add 20% extra for fittings Carriage cost Total cost for Materials labour Component Foreman (Skilled Labour) Plumber (Semi Skilled) Helper (unskilled labour) Total cost for Labour Other Component Add for Clamps, white lead, hemp, cement, sand grit, oil, wooden plugs, screws ect contingencies and sundries add for water Charges Total cost other items Add overhead and CP 15% Amount for 10 M Length Total Cost for 1 RM RM RM RM

RM Ton

12.00 0.0152

80 1000

960.00 15.24 975.24

Nos Nos Nos

0.15 1.20 1.20

225 150 110

33.75 180.00 132.00 345.75

2.00% 3.00% 1.00%

26.42 39.63 13.21 79.26 198.15 1598.40 159.84

15.00% 10.00

20 mm dia G.I. pipe for 10 m length Materials Components Pipe cost + Add 20% extra for fittings Carriage cost Total cost for Materials labour Component Foreman (Skilled Labour) Plumber (Semi Skilled) Helper (unskilled labour) Total cost for Labour Other Component Add for Clamps, white lead, hemp, cement, sand grit, oil, wooden plugs, screws ect contingencies and sundries add for water Charges Total cost other items Add overhead and CP 15% Amount for 10 M Length Total Cost for 1 RM 25 mm dia G.I. pipe for 10 m length Materials Components Pipe cost + Add 20% extra for fittings Carriage cost Total cost for Materials labour Component Foreman (Skilled Labour) Plumber (Semi Skilled) Helper (unskilled labour) Total cost for Labour Other Component Add for Clamps, white lead, hemp, cement, sand grit, oil, wooden plugs, screws ect contingencies and sundries add for water Charges Total cost other items Add overhead and CP 15% Amount for 10 M Length Total Cost for 1 RM

RM

RM Ton

12.00 0.0198

80 1000

960.00 19.80 979.80

Nos Nos Nos

0.15 1.40 1.40

225 150 110

33.75 210.00 154.00 397.75

2.00% 3.00% 1.00%

27.55 41.33 13.78 82.65 206.63 1666.84 166.68

15.00% RM RM RM 10.00

RM Ton

12.00 0.0301

80 1000

960.00 30.12 990.12

Nos Nos Nos

0.15 1.50 1.50

225 150 110

33.75 225.00 165.00 423.75

1.75% 3.00% 1.00%

24.74 42.42 14.14 81.30 212.08 1707.25 170.72

15.00% RM RM 10.00

32 mm dia G.I. pipe for 10 m length Materials Components Pipe cost + Add 20% extra for fittings Carriage cost Total cost for Materials labour Component Foreman (Skilled Labour) Plumber (Semi Skilled) Helper (unskilled labour) Total cost for Labour Other Component Add for Clamps, white lead, hemp, cement, sand grit, oil, wooden plugs, screws ect contingencies and sundries add for water Charges Total cost other items Add overhead and CP 15% Amount for 10 M Length Total Cost for 1 RM 40 mm dia G.I. pipe for 10 m length Materials Components Pipe cost + Add 20% extra for fittings Carriage cost Total cost for Materials labour Component Foreman (Skilled Labour) Plumber (Semi Skilled) Helper (unskilled labour) Total cost for Labour Other Component Add for Clamps, white lead, hemp, cement, sand grit, oil, wooden plugs, screws ect contingencies and sundries add for water Charges Total cost other items Add overhead and CP 15% Amount for 10 M Length Total Cost for 1 RM 50 mm dia G.I. pipe for 10 m length Materials Components Pipe cost + Add 20% extra for fittings Carriage cost Total cost for Materials labour Component Foreman (Skilled Labour) Plumber (Semi Skilled) Helper (unskilled labour) Total cost for Labour Other Component Add for Clamps, white lead, hemp, cement, sand grit, oil, wooden plugs, screws ect contingencies and sundries add for water Charges Total cost other items Add overhead and CP 15% Amount for 10 M Length Total Cost for 1 RM Concealed pipe inculding painting with anti corrosive bitumastic paint, cutting chases and making good the walls etc.

RM

RM Ton

12.00 0.0388

80 1000

960.00 38.76 998.76

Nos Nos Nos

0.15 1.60 1.60

225 150 110

33.75 240.00 176.00 449.75

2.00% 3.00% 1.00%

28.97 43.46 14.49 86.91 217.28 1752.70 175.27

15.00% RM RM RM 10.00

RM Ton

12.00 0.0446

80 1000

960.00 44.64 1004.64

Nos Nos Nos

0.20 1.70 1.70

225 150 110

45.00 255.00 187.00 487.00

2.00% 3.00% 1.00%

29.83 44.75 14.92 89.50 223.75 1804.88 180.49

15.00% RM RM RM 10.00

RM Ton

12.00 0.0629

80 1000

960.00 62.88 1022.88

Nos Nos Nos

0.25 1.80 1.80

225 150 110

56.25 270.00 198.00 524.25

2.25% 3.00% 1.00%

34.81 46.41 15.47 96.70 232.07 1875.90 187.59

15.00% RM RM 10.00

15 mm dia G.I. pipe (Concealed) for 10 m length Materials Components Pipe cost + Add 20% extra for fittings Carriage cost Painting for pipe Cement plaster 1:4 Cement Sand Total cost for Materials labour Component For cutting Belder(Semi Skilled) For fixing Foreman (Skilled Labour) Plumber (Semi Skilled) Helper (unskilled labour) For Painting Painter (Semi Skilled)) For Plastring Mason (Skilled Labour) Belder(Semi Skilled) Total cost for Labour Other Component Add for Chisels for cutting chases, carriage of paint, cost of brushes, sand paper etc. Add for white lead, hemp, ballies and planks Scaffolding/ladders for concreting & plaster wherever required contingencies and sundries add for water Charges Total cost other items Add overhead and CP 15% Amount for 10 M Length Total Cost for 1 RM 20 mm dia G.I. pipe (Concealed) for 10 m length Materials Components Pipe cost + Add 20% extra for fittings Carriage cost Painting for pipe Cement plaster 1:4 Cement Sand Total cost for Materials labour Component For cutting Belder(Semi Skilled) For fixing Foreman (Skilled Labour) Plumber (Semi Skilled) Helper (unskilled labour) For Painting Painter (Semi Skilled)) For Plastring Mason (Skilled Labour) Belder(Semi Skilled) Total cost for Labour Other Component Add for Chisels for cutting chases, carriage of paint, cost of brushes, sand paper etc. Add for white lead, hemp, ballies and planks Scaffolding/ladders for concreting & plaster wherever required contingencies and sundries add for water Charges Total cost other items Add overhead and CP 15% Amount for 10 M Length Total Cost for 1 RM

RM

RM Ton Litre Q Cum

12.00 0.0152 0.0750 0.0410 0.0115

80 1000

960.00 15.24 0.00 0.00 0.00 975.24

Nos

0.95

225

213.75

Nos Nos Nos Nos Nos Nos

0.15 1.20 1.20 0.50 0.20 0.20

225 150 110 150 225 150

33.75 180.00 132.00 75.00 45.00 30.00 709.50

4.00% 4.00% 2.00% 3.00% 1.00%

67.39 67.39 33.69 50.54 16.85 235.86 252.71 2173.31 217.33

15.00% RM RM RM 10.00

RM Ton Litre Q Cum

12.00 0.0198 0.0900 0.0410 0.0115

100 1000

1200.00 19.80 0.00 0.00 0.00 1219.80

Nos

0.95

225

213.75

Nos Nos Nos Nos Nos Nos

0.15 1.40 1.40 0.50 0.20 0.20

225 150 110 150 225 150

33.75 210.00 154.00 75.00 45.00 30.00 761.50

4.00% 4.00% 2.00% 3.00% 1.00%

79.25 79.25 39.63 59.44 19.81 277.38 297.20 2555.88 255.59

15.00% RM RM 10.00

Damp Proof course Providing and laying damp proof course 40 mm thick with cement concrete 1:2:4(1 cement:2course sand:4graded stone aggregate) 12.5 mm nomonal size Details of cost of 12 SQM Materials Stone aggregate 12.5 mm graded Coarse sand Cement Labour Mason Beldar Foreman Waterman coolie Total Add for Hire and running charges of mixer,vibrator water pump etc @6% Add for Sundriesand contingencies @3% Add for Contractor's profit and overheads @ 15% Add for water and Electricity charges @1.5% Cost of 12 SQ.Mt. Cost of 1 Sq. mt

Cum Cum Tonne

0.45 0.23 0.15

600 700 3200

270.60 157.50 491.20

each each each each each

0.6 0.55 0.1 0.05 0.55

150 80 120 80 80

90.00 44.00 12.00 4.00 44.00 1,113.30 66.80 1,180.10 35.40 1,215.50 182.33 1,397.83 20.97 1,418.79 118.23

DISMANTALLING & DEMOLISHING WORKS Dismantalling ,breaking and demolition of all existing building structures at all levels along with foundation,including dismantalling of doors,windows,plumbing,sanitary and electrical fittings,fixtures etc.stacking the usable materials within the site. Brick masonary Detail cost for 1 cum

CUM

Foreman Mazdoor (M) Mazdoor (F) Watchman Total Add for hammer & chisselles etc @ 2% Add for contingencies & sundries @ 3% Add for CP & O.H.@ 15% cost for 1 cum

Nos. @ Rs. Nos. @ Rs. Nos. @ Rs. Nos. @ Rs.

0.10 351 0.95 117 0.85 117 0.10 117

35.10 111.15 99.45 11.70 257.40 5.15 262.55 7.88 270.42 40.56 310.99 248.00

PCC Detail cost for 1 cum

Say Rs. CUM

Foreman Beldar Coolie TOTAL Add for hammer & chisselles etc @ 5% Add for contingencies & sundries @ 3% Add for CP & O.H.@ 15% cost for 1 cum

Nos. @ Rs. Nos. @ Rs. Nos. @ Rs.

0.05 1.50 0.80

351 117 117

17.55 175.50 93.60 286.65 14.33 300.98 9.03 310.01 46.50 356.51 304.00

Say

RCC Works Detail cost for 1 cum

CUM

Foreman Beldar Watchman Coolie TOTAL Add for hammer & chisselles etc @ 2% Add for contingencies & sundries @ 3% Add for CP & O.H.@ 15% cost for 1 cum Stone masonary Detail cost for 1 cum

Nos. @ Rs. Nos. @ Rs. Nos. @ Rs. Nos. @ Rs.

0.05 351 2.40 117 0.05 117 0.80 117

17.55 280.80 5.85 93.60 397.80 7.96 405.76 12.17 417.93 62.69 480.62

SQM

Foreman Beldar Coolie Watchman Add for hammer & chisselles etc @ 3% Add for contingencies & sundries @ 3% Add for CP & O.H.@ 15% cost for 1 cum

Nos. @ Rs. Nos. @ Rs. Nos. @ Rs. Nos. @ Rs.

0.10 351 1.23 117 0.92 117 0.10 117

35.10 143.91 107.64 11.70 298.35 8.95 307.30 9.22 316.52 47.48 364.00

False ceiling Provide and fix 12.5 mm Gypsum board false ceiling confirming to IS 2095. For 103.79 Sqm Providing and fixing false ceiling of Gypsum ceiling board 12 mm thick conforming to IS 2095 of India gypsum company which includes fixing G.I.perimeter chanel of size 20 mm flange x 27 mm web x 30 mm flange x 0.55 mm thk along the perimeter of ceiling wall, M.S. coach screws at 610 mm c/c .; suspending G .I. Intermediate channel of size 15 mm flange x 45 mm web x 15 mm flange x 0.9 mm thk. suspended from the soffit @ 610 x 1220 mm c/c with G.I. ceiling angle of 25 mm width x10 mm x 0.55 mm thick @ 610 x 1220 mm c/c fixed to soffit with G.I.soffit Cleat with M.S. coach screw & T.W. plug ; Ceiling section of 0.55 mm.thickness having knurled web of 51.5 mm & two flanges of 26 mm each with lips of 10.5 mm connected with the help of connecting clips 2.64 mm thk. and in direction perpendicular to the intermediate channel at 457 mm c/c. gypsum board fixed to intermediate ceiling section by means of 25 mm long M.S. self tapping screws at 230 mm c/c. Screw fixing is done mechanically either with screw driver or drilling machine with suitable attachment.Finally the boards are to be jointed and finished so as to have a flush look which in edges of the boards with jointing compound &' paper tape.The false ceiling shall be painted with one coat of primer & two coats of oil bound distemper white coloured paint Material component 12.5 mm thk Gypsum board Sqm Ceiling Section - G.I. ceiling angle of 25 mm width x10 mm x 0.55 RM mm thick Perimeter channels RM Intermediate channel RM Strap hangers Each Connecting Clips Each 6mm dia nuts and bolts 10 nos Soffit cleats Each 25mm long driveall screws 10 Nos Joint filler Kg Joint Finisher Kg Joint Tape Roll 12mm dia 40mm long with 6mm dia bolt-fastners Each Total Material Cost Labour Component Assembly the structure and fixing tiles Fore man Carpenter Helper Total Labour component other cost Carriage of material and scaffolding add for Rawl plugs.. Etc Add for cutting channels , angle iron..etc Sundries and conti.. OH and C.P Total other cost Cost per Sqm

109 240 42 91.5 11 190 2.2 75 100 24 35 1.5 75

200 25 20 20 10 2 150 5 10 5 5 35 5

21,800.00 6,000.00 840.00 1,830.00 110.00 380.00 330.00 375.00 1,000.00 120.00 175.00 52.50 375.00 33,387.50

Each Each Each

5 35 70

225 150 110

1,125.00 5,250.00 7,700.00 14,075.00 47,462.50 949.25 1,423.88 2,373.13 1,423.88 7,119.38 13,289.50 128.04

2% 3% 5% 3% 15% 103.79

Thermal insulation under deck.. 10Sqm Material 50Mm thk expanded polystyrene Labour Foreman Beldhar

Sq

10.5

50

525.00

Each Each

0.5 2

225 150

112.50 300.00 412.50 937.50 93.75 28.13 140.63 262.50 1,200.00 120.00

Others Carriage of material and scaffolding Sundries and conti.. OH and C.P Total other cost Total cost Cost per SQm

10% 3% 15%

10

WHITE WASHING, DISTEMPERING & PAINTING WHITE WASHING ON NEW WORK (3 COATS) Material White Lime Carriage White Lime Indigo labour White washer Helper other cost Add for Gum,Putty @ 7% Add for Sundries & Contingencies @ 3% Add for Scaffolding @ 1.5% Add for W.C. & Electricity @ 1.5% OH and CP Total cost for White washing Cost per sqm TWO COAT EXISTING WORK Material White Lime Carriage White Lime Indigo labour White washer Helper other cost Add for Gum,Putty @ 7% Add for Sundries & Contingencies @ 3% Add for Scaffolding @ 1.5% Add for W.C. & Electricity @ 1.5% OH and CP Total cost for White washing Cost per sqm

Quintal Quintal Gramms

0.03 0.03 9.00

400.00 12.00 50.00 1.50 1.00 9.00 22.50 40.50 27.00 67.50 90.00 6.30 2.70 1.35 1.35 13.50 25.20 115.20 11.52

Each Each

0.18 225 0.18 150

7% 3% 1.50% 1.50% 15.00% 10

Quintal Quintal Gramms

0.02 0.02 6.00

400.00 8.00 50.00 1.00 1.00 6.00 15.00 27.00 18.00 45.00 60.00 6.30 2.70 1.35 1.35 13.50 25.20 85.20 8.52

Each Each

0.12 225 0.12 150

7% 3% 1.50% 1.50% 15.00% 10

Painting with Acrylic Emolsion Material Paint Primer

Ltrs @ Rs. Ltrs @ Rs.

1.25 150 1.00 110

187.50 110.00 297.50 225.00 150.00 375.00 672.50 67.25 6.73 20.18 1,008.75 100.88 1,203.78 120.38

Painter Belder

Nos. @ Rs. Nos. @ Rs.

1.00 225 1.00 150

Add for carriage of mateial, brushes sand paper, putty etc @ 10% Add for Scaffolding @ 1% Add for Contingencies 3% Add for W.C. & Electricity @ 1.5% Add for CP & O.H.@ 15% Cost per 10sqm Cost per sqm

10% 1% 3% 1.5 15% 10

WATER PROOFING CEMENT PAINT MATERIALS Water proofing cement paint LABOUR Painter Helper Waterman Material + labour other cost Add for sand paper putties etc @ 6% Add for Scaffolding @ 1% Add for Contingencies 3% Add for W.C. & Electricity @ 1.5% Add for CP & O.H.@ 15% Cost per 10sqm Cost per sqm P&L APEX EXTERIOR PAINT Material Paint Primer Labour Painter Belder Waterman

kg @ Rs.

5.00 280.5

1,402.50

Nos. @ Rs. Nos. @ Rs. Nos. @ Rs.

0.60 263.25 0.60 117 0.10 128.7

157.95 70.20 12.87 241.02 1,643.52 98.61 16.44 49.31 24.65 246.53 435.53 2,079.05 207.91

6% 1% 3% 1.50% 15% 10

Ltrs @ Rs. Ltrs @ Rs.

1.25 234.6 1.00 153

293.25 153.00 446.25 263.25 87.75 12.87 363.87 810.12 67.25 6.73 20.18 1,008.75 100.88 1,203.78 120.38

Nos. @ Rs. Nos. @ Rs.

1.00 263.25 0.60 146.25 0.10 128.7

Add for carriage of mateial, brushes sand paper, putty etc @ 10% Add for Scaffolding @ 1% Add for Contingencies 3% Add for W.C. & Electricity @ 1.5% Add for CP & O.H.@ 15% Cost per 10sqm Cost per sqm

10% 1% 3% 1.5 15% 10

Bollard Fixing Assumed the Bollard is delevered at site in ready to fix fashion. Bollard pedestals and anchor bolt is ready to take on the Bollard. Only fixing of bollard is incl in this scope. 12 Nos Labour: Assumed One fitter and helper will be in aposition to fix 12 Nos of Bollard per day. Fitter Each Beldar Each other cost Add for Sundries & Contingencies @ 3% Add for tools and tackles OH and CP

1 1

292.5 146.25

292.50 146.25 438.75 13.16 6.58 65.81 85.56 524.31 43.69

3% 1.50% 15%

Cost per each

Nos

12

Provoding and injecting chemical pre constructional tntitermite treatment emulsion pre constructional anti

Material Chloropyriphos 20% EC required Labour Drilling and injecting chemical emulsion Total Add for water charges @1% Add for Contractor's profit and overheads @ 15% Cost per sqm SQM 1 1% 15% Ltr 0.2 -

RAINWATER HARVESTING PVC PIPE LAYING Providing and fixing of PVC/CI Pipe encased in Concrete for 30 Rm Material Earthwork excavation in all kinds of soil \ murrum for foundations Cum & trenches etc. Back filling with graded metal 75mm and sandand down sizes as Cum per specfication Providing & laying M20 grade concrete Cum mt Providing and laying high yield strength deformed steel bars Fe 415 Providing and fixing to correct level, line plumb, vertical, plain formwork in all shapes made of plywood/ MS plates for RCC worksin charge. Providig & Laying of pvc pipe 150 dia with 20mm thick R.C.C coping. Labour for Pipe laying Masons Mate Total for labour Material and labour cost Other cost Add for Sundries & Contingencies @ 3% Add for tools and tackles OH and CP Total other Cost Total cost Cost per RM sqm

8.5 13.5 6.25 0.51 28

115.56 963.90 2,056.33 6.29 134.08

982.26 13,012.65 12,852.05 3.21 3,754.18

Rm

33

165.00

5,445.00 36,049.35

Each Each

1.75 2

234 175.5

409.50 351.00 760.50 36,809.85 1,104.30 552.15 5,521.48 7,177.92 43,987.77 1,466.26

3% 1.50% 15%

30

Hume Pipe Culverts Laying Reinforced Cement Concrete Pipe NP3 / Prestressed Concrete Pipe on First Class Bedding in Single Row . Laying Reinforced cement concrete pipe NP3/prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and Unit = metre Taking output = 12.5 metres ( 5 pipes of 2.5 m 1000 mm dia a) Labour Mate Mason Mazdoor b) Material Sand at site Cement at site RCC pipe NP-3 /prestressed concrete pipe including Granular material passing 5.6 mm sieve for bedding

day day day

0.180 292.5 0.500 292.5 4.000 175.5

52.65 146.25 702.00 900.90 64.97 30,600.00 4,479.84 35,144.81 36,045.71 1,081.37 16.22 2.43 37,145.74 73,191.45 5,855.32

cum tonne metre cum

0.070 0.050 12.500 4.500

928.2 0 2448 995.52

Add for Sundries & Contingencies @ 3% Add for tools and tackles OH and CP Total other Cost Cost per Rm

0.030 0.015 0.150

12.5

Providing plastering / pointing over brick / stone masonry / RCC / CC surface in plinth superstructure & roof etc. including all leads / lifts. Pointing with cement mortar 1:3 FLUSH Pointing 12 mm thick Details of cost for 10 sqm. Materials Cement mortar 1:3 Labour Mason II class Coolie beldar water man Total Add 6% for scaffoldings,& pumping Add for Sundries and Contingencies @3% Add for Water charges and Electricity @ 1.5% Add 15% for Contractor's profit and overheads Cost of 10 Sqm Cost of 1 sqm each each each each 1.2 1.2 0.20 0.15 292.50 140.40 146.25 128.70 351.00 168.48 29.25 19.31 594.49 35.67 630.16 18.90 649.06 9.74 658.80 98.82 Cum 0.02 1150.11 26.45

757.62 75.76

Pointing with cement mortar 1:3 Raised and Cutting pointing 12 mm thick Details of cost for 10 sqm. Materials Cement mortar 1:3 Labour Mason II class Coolie beldar water man Total Add 3.5% for scaffoldings,& pumping Add for Sundries and Contingencies @3% Add for Water charges and Electricity @ 1.5% Add 15% for Contractor's profit and overheads Cost of 10 Sqm Cost of 1 sqm Pointing with cement mortar 1:3 Strunk pointing for RR/Brick masonry 12 mm thick Details of cost for 10 sqm. Materials Cement mortar 1:3 Labour Mason II class Coolie beldar water man Total Add 8% for scaffoldings,& pumping Add for Sundries and Contingencies @3% Add for Water charges and Electricity @ 1.5% Add 15% for Contractor's profit and overheads Cost of 10 Sqm Cost of 1 sqm each each each each 0.9 0.9 0.25 0.15 292.50 140.40 146.25 128.70 263.25 126.36 36.56 19.31 479.98 38.40 518.38 15.55 533.93 8.01 541.94 81.29 Cum 0.03 1150.11 34.50 each each each each 2 2 0.20 0.15 292.50 140.40 146.25 128.70 585.00 280.80 29.25 19.31 966.11 33.81 999.92 30.00 1,029.92 15.45 1,045.37 156.81 Cum 0.05 1150.11 51.76

1,202.18 120.22

623.23 62.32

New Code Providing and fixing false ceiling of Gypsum ceiling board 12 mm thick conforming to IS 2095 of India gypsum company which includes fixing G.I.perimeter chanel of size 20 mm flange x 27 mm web x 30 mm flange x 0.55 mm thk along the perimeter of ceiling wall, M.S. coach screws at 610 mm c/c .; suspending G .I. Intermediate channel of size 15 mm flange x 45 mm web x 15 mm flange x 0.9 mm thk. suspended from the soffit @ 610 x 1220 mm c/c with G.I. ceiling angle of 25 mm width x10 mm x 0.55 mm thick @ 610 x 1220 mm c/c fixed to soffit with G.I.soffit Cleat with M.S. coach screw & T.W. plug ; Ceiling section of 0.55 mm.thickness having knurled web of 51.5 mm & two flanges of 26 mm each with lips of 10.5 mm connected with the help of connecting clips 2.64 mm thk. and in direction perpendicular to the intermediate channel at 457 mm c/c. gypsum board fixed to intermediate ceiling section by means of 25 mm long M.S. self tapping screws at 230 mm c/c. Screw fixing is done mechanically either with screw driver or drilling machine with suitable attachment.Finally the boards are to be jointed and finished so as to have a flush look which in SQ.M. 20 20 90 83 213 edges of the boards with jointing compound &' paper tape.The false ceiling shall be painted with one coat of primer & two coats of oil bound distemper white coloured paint

S-ar putea să vă placă și