RVD HYDRAULIC POWER PACK Equipment no. Hours of Maintenance (hrs/miles/km) Suggested interval: 60 days Base Location and number Date (ddMMyyyy)

MO#

v = OK F = Failure (create the RPM order) N/A = not applicable

SAFETY
1 2 3

****Lock out tag out unit per HMS procedures**** Hold a safety huddle before work to identify safety risks Wear appropriate PPE before beginning work HYDRAULIC SYSTEM CH

4 5 6 7 8 9 10 11 12 13 14 15

Check oil level in the tank. Fill up to the right level if is necessary Check for leaks in the tank. Check tank for secure mounting and overall condition. Check condition of the dirty alarm gauge in the tank. Change the filter if it necessary Check condition of the dirty alarm gauge in the manifold. Change the filter if it necessary Check for leaks and condition of the quick connections in the manifold. Change the connector if it necessary Check condition of the pressure gauge in the manifold. Check condition and operation of the pressure adjustment valve. Check hydraulic hoses and fittings for leaks and verify they are in good condition. replace if required Check the piping and fittings for leaks and verify they are in good condition. replace if required Check hydraulic pumps for leaks. Check condition of the coupling for the hydraulic pumps to the motor. COOLING SYSTEM CH

16 17 18 19

Check all hoses, lines and connections for leaks Check radiator for obstruction and condition Clean the radiator Check adjustment of connections, unions and terminals of the hydraulic system, adjust if necessary

20 Check radiator, mounts, supports and guards 21 Check the free rotation of the fan and the condition of the fan assembly

ELECTRICAL SYSTEM
22 Check fasteners of the electric panel that it is complete. 23 Check gland connector of the connection box of the main motor 34 Check gland connector of the electrical panel 25 Review cabling and power supply plug.

GROUNDING SYSTEM
26 Check the connection of the grounding system

CH

Page 1/3

Inspection sheet of Preventive maintenance B29A_E

Revision date: 10/27/2008

HALLIBURTON
RVD HYDRAULIC POWER PACK FUNCTIONAL TEST
27 Power pack should be hooked up to a RVD that will allow full function of all hydraulic systems. 28 Assure Electric motor starts properly and oil pressure gauge functions. 29 Check hydraulic system for leaks while pumps have pressure on them. Repair all hydraulic leaks. 30 Verify and document the temperature (max. Temp. 150 F). _____________ F

Suggested interval: 60 days

31 Hydraulic oil Pressure at the gauge (For 7.5 HP unit, Max. Pressure 1000 psi) . _____________ PSI, adjust if necessary 32 Hydraulic oil Pressure at the gauge (For 25 HP unit, Max. Pressure 1500 psi) . _____________ PSI, adjust if necessary ENVIRONMENT
33

Properly dispose of all waste. Make sure any spill has been cleaned up and has been placed in an appropriate container. REQUIRED DOCUMENTATION

34 Check regulatory documents and decals (required by State and/or Country, DOT, CVIP,

manufacturing specifications: MMS, of environmental protection, etc.)


35 Check that the decals and logos of the appropriate company have been installed per the Branding

initiative. Check that the number of the SAP equipment is clearly marked on the unit (see the Internet page of ESG Branding for instructions) 36 Check that the DOT/CVIP and the annual state inspection decals are up-todate (if applicable). Replace decal if the 90-day period of validity has expired

Date

Page 2/3

Inspection sheet of Preventive maintenance B29A_E

Revision date: 10/27/2008

HALLIBURTON
RVD HYDRAULIC POWER PACK Suggested interval: 60 days MAKE A LIST of ALL REPAIRS THAT WILL BE MADE DURING THE INSPECTION. THIS LIST WILL BE USED AS A TOOL TO CHANGE THE SCHEDULING OF ANY REPAIR THAT WAS FOUND DURING THE INSPECTION OF PREVENTIVE MAINTENANCE (PM):
1 Mechanics name: Repair Date: 2 Mechanics name: Repair Date: 3 Mechanics name: Repair Date: 4 Mechanics name: Repair Date: 5 Mechanics name: Repair Date: 6 Mechanics name: Repair Date: 7 Mechanics name: Repair Date: 8 Mechanics name: Repair Date:

9
Mechanics name: Repair Date:

Done by: Report any errors found on check sheet to the supervisor Page 3/3

Employee no.:

Inspection sheet of Preventive maintenance B29A_E