Sunteți pe pagina 1din 69

Short-Circuit Strength and Short Circuit Testing of Power and Distribution Transformers

Charlotte, North Carolina, March 17, 2008 Presented by: Marcel Fortin (Consultant), Pierre Riffon (HydroQubec), Juergen Gerth (ABB) and Richard P. McLaughlin (Kema Powertest)

Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Introduction
Charlotte, North Carolina, March 17, 2008 Presented by: Marcel Fortin Eng Test specialist Consultant

Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Contributors
Marcel Fortin: test specialist retired from Hydro-Qubec High Power Laboratory Juergen Gerth: Technical Manager of ABB Inc. Power Transformer Division at Varennes, Quebec, Canada. Pierre Riffon: test specialist for the Hydro-Qubec Quality Control Department Richard P. McLaughlin: Test Engineer Supervisor, KEMA Powertest.
Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Presentations
Standard Status M Fortin Designing Transformers to Withstand ShortCircuit Forces J Gerth Short-Circuit Withstand of Power Transformers, Utility Perspective P Riffon Short-Circuit Testing of Liquid Filled Transformers R McLaughlin Some Particular Cases M Fortin
Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Standard Requirements and Status


Charlotte, North Carolina, March 17, 2008 Presented by: Marcel Fortin Eng Test specialist Consultant

Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Continuous revision of C57.12.00 and C57.12.90


C57.12.00 sets requirements for short circuit withstand of oil filled transformers, clause 7 and table 21 C57.12.90 sets the short-circuit test procedure, including the pass criteria and diagnostic tools, clause 12. A TF chaired by myself is responsible for reviewing clause 12 of C57.12.90
Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Short Circuit withstand requirements


IEEE C57.12.00-2006, clause 7.1.1, states: "Liquid-filled transformers shall be designed and constructed to withstand the mechanical and thermal stresses produced by external short circuits under the conditions specified in 7.1.3, 7.1.4, and 7.1.5. The external short circuits shall include three-phase, single line-to-ground, double line-to-ground, and line-to-line faults on any one set of terminals at a time. IEC 60076-5 has the same design requirements
Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Short Circuit testing requirements


IEEE C57.12.00, clause 8.2 and table 21, states that short circuit test is:
A design test for transformers rated 500 kVA and below A test that may be specified by the purchaser (other) for transformers rated 501 kVA and higher (clause 8.2.3).

IEC 60076-5 requirements

has

also

the

same

design

Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Status of changes recommended by the Task Force


No changes to C57.12.00 Abandon of work on a short circuit test guide (PC57.133)
This guide project covered interpretation of LVI (low voltage impulse) diagnostic method The proposed change to C57.12.90 include removal of LVI as a diagnostic method
Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Status of changes recommended by the Task Force


Major changes proposed to C57.12.90 are:
Withdrawal of LVI Make dissolved gas analysis (DGA) a compulsory diagnostic tool Introduction of other diagnostic tools: FRA, FRSL, TOP Make the pre-set method the preferred one and keep the postset method as an alternative Introduce requirements and guidance for testing special transformers as axial split Add informative notes and figures to clarify the requirements Add an informative annex giving test circuit diagrams for single phase testing of 3 phase transformers
Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Jrgen Gerth Technical Manager ABB Inc. Varennes, Quebec Canada Designing Transformers to withstand Short-Circuit Forces

- 1/14 -

Designing Transformers to withstand Short-Circuit Forces

In case of external short-circuits the first peak of the fault current over the transformer will increase to a multiple of the rated current. The fault current is governed by: Open-circuit voltage Source and transformer impedance Instant of fault onset

- 2/14 -

Displacement of current

Designing Transformers to withstand Short-Circuit Forces 2D Plot of the magnetic stray field lines of a two winding transformer.

Radial direction

Axial direction

The stray flux has components in axial and radial direction. There are field compoments outside the windings.

- 3/14 -

Designing Transformers to withstand Short-Circuit Forces

The direction of forces is always directed perpendicular to the magnetic field lines Forces usually are split into the two components Radial forces Axial forces

Electromagnetic forces tend to increase the main insulation duct and to increase existing un-symmetries.
- 4/14 -

Designing Transformers to withstand Short-Circuit Forces Radial forces failure modes:


Buckling of the inner winding Diameter increase of the outer winding, rupture of cable Spiralling of end turns in helical winding

Buckling: Characteristic failure mode for inner winding

Spiralling: Characteristic failure mode for inner and outer winding

- 5/14 -

Designing Transformers to withstand Short-Circuit Forces Axial forces failure modes:


Telescoping of windings Damage of conductor insulation

Collapse of end support

Conductor tilting

Bending of cables

- 6/14 -

Designing Transformers to withstand Short-Circuit Forces Steps to design transformers to survive short-circuits Step 1: Run fault current calculations, covering all external fault modes:

Three phase fault on HV, LV and Tertiary side Line to line fault on HV, LV and Tertiary side Line to ground fault on HV and LV side

Consider the network impedance in line with the Standard or the spec. Consider different tap changer positions Consider that impedances are subject of tolerances Consider that current limiting reactors may show saturation effects
- 7/14 -

Designing Transformers to withstand Short-Circuit Forces Step 2: Calculate the forces and the stresses

Radial forces and copper stresses in all windings Spiralling forces on the exits Axial compression forces and:

Bending stresses in the cables Stresses on the paper of the winding conductors Critical tilting stresses of the winding conductors

Axial forces on the end supports and stresses in the mechanical support structure

The highest fault current will not always lead to the highest forces in a winding. Superimposed fields of other windings may create higher stresses
- 8/14 -

Designing Transformers to withstand Short-Circuit Forces

Step 3: Take the right design measures


Design the windings radially self supporting Select the cable dimensions, copper yield strength and epoxy bonding to meet the stresses Focus on axial ampere-turn balancing optimization of all windings, Require close manufacturing tolerances, Provide solid clamping of the windings, Provide safe fastening of the winding exits and connection leads.

- 9/14 -

Designing Transformers to withstand Short-Circuit Forces Which simplifications are applied during design?

The forces alternate with the square of the current. During design only the peak force is calculated and considered as a static force. A dynamic factor may be used to consider the dynamic effects. Core and coils are a 3 D arrangement. The routine field calculations are ran with 2 D programs, Layer and helical windings have a pitch creating variable displacements. It depends on the manufacturers rules which displacement is considered, The calculation of the forces on the winding exits is based on a simplified model. The mechanical withstand limits of helical windings against spiralling forces are based on limited number of experiments.

- 10/14 -

Designing Transformers to withstand Short-Circuit Forces Which improvements have been achieved over the last 20 years?

Computer programs run fault current and force calculations for all fault conditions and all winding connections automatically, 3 D magnetic tools have been applied for R&D work, Epoxy bonding of winding conductors has become available and the application became a standard practice, Hard and very hard drawn copper is applied more frequently, Pre-compressed pressboard is exclusively used, There is more focus on the short circuit strength during the design stage, More experience has been gained in the field and by testing.

- 11/14 -

Designing Transformers to withstand Short-Circuit Forces

Why do transformers fail testing?

Due to design weakness because:


The rules did not fully cover the case, There are effects which have not been considered,

Due to shortcomings during manufacturing, Due to transportation issues or poor test preparations,

- 12/14 -

Designing Transformers to withstand Short-Circuit Forces Benefit and risk of testing

Test results are an important feedback and a valuable source for improvements. Due to the high cost and the limited number of test facilities the number of tests will remain limited. Submitting a transformer to a short-circuit test is always connected to high expenses for the purchaser. In case of a failure the expenses become very high for purchaser and manufacturer. A short-circuit test therefore involves a risk for both parties.

- 13/14 -

Designing Transformers to withstand Short-Circuit Forces Personal observations after 40 years in business

Designing for short-circuit strength was not high on the list 40 and 30 years ago, Radial buckling, axial winding collapse and broken press rings were a non-rare experience, In the meantime the design philosophy has changed, More experience has been gained, mainly after performing tests, There are better design rules, the calculation tools were improved, and there are better materials to strengthen windings and winding supports, I did not see a winding with buckling, collapsing, tilting indication for more than 10 years in a transformer designed during that period.

- 14/14 -

Short Circuit Withstand of Power Transformers, Utility Perspective


Charlotte, North Carolina, March 17, 2008 Presented by: Pierre Riffon Eng.
Test Specialist Hydro-Quebec

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Type of faults to be considered


All type of external faults such as: Line faults, 1, 2, 3 (not so severe if far from transformer). Substation faults 1, 2, 3, Severe cases, highest fault current, not frequent. Worst case: 3 phases short-circuit caused by forgotten safety grounding devices after maintenance
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Fault occurrence utility experience


Line faults statistics (IEC 62271-310), more frequent than substation faults, approximately 4 to 6 faults per year per line, typically due to lightning strokes.

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Transformers failures caused by short circuit events Hydro-Qubec


Hydro-Quebec transformer short-circuit failures have been compiled for the period of 1970 to 1998. The results are:
System voltage Number of transformer - years Number of faults 1970 1998 Number of faults 1993 1997 Failure rate 1970 1998 % Failure rate 1993 1997 % Comparison HQ/CIGRE 1970 1998 Comparison HQ/CIGRE 1993 - 1997

145 -170 765

6912 3255

10 6

1 3

0,145 0,184

0,015 0,092

11,15 9,20

1,15 4,60

A CIGRE TF with WG 12.19 made survey in 1997 (18 utilities in 11 countries). Time frame of the results: 1993 1997 (5 years)

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Transformers failures caused by short circuit events Hydro-Qubec


Well spread among 7 different manufacturers (no specific manufacturer nor design). Hydro-Quebec short-circuit related failure rates significantly higher than the figures reported by CIGRE. Short-circuit failure rates improved in the last 5 years (1993- 1998). Average age of transformers when failing: 19 years (CIGR), 17 years (HQ).
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Transformer failure during shortcircuit tests - CIGR


CIGRE SC12 has conducted in 1998 a worldwide survey among high-power laboratories (12 labs). The results are:
Transformer power rating (MVA) 2,5 > 2,5 and 40 > 40 and 100 > 100 Average failure rate during tests % 22,9 22,3 12,1 41,9

Transformer impedances for units rated 25 to 200 MVA were in the range of 14,3% to 19,5%.
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Demonstration of transformer ability to withstand short-circuit currents


Manufacturer: Calculations at the design stage. Calculation methods should be based on experience gained on similar transformer testing (not always the case). IEC 60076-5 does accept calculations and does give calculations guidance and criteria. User: Shall review the manufacturer short-circuit calculation results and transformer design and decide if a test is needed.
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Is a short-circuit test to be considered?


Technical aspects to consider: Mandatory for distribution transformers ( 500 kVA) Is the test possible? Not possible for large units ( >400 MVA). Only few laboratories (outside North America) are able to test units rated over 100 MVA. What is the application (normal substation, GSU, interconnections between two systems (phaseshifter or HVDC), etc..)
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Is a short-circuit test to be considered?


Technical aspects to consider: Is a spare available? Is that a single and unique order or this is an order that can be related to several identical units (e.g. distribution transformers or standardisation of a specific design); Can the power be fed through a parallel path (generally possible in power substations but not in generating plants).
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Is a short-circuit test to be considered?


Technical aspects to consider: Short-circuit occurrence and amplitude; Utility service experience; Manufacturer performance in service; Manufacturer experience of short-circuit tests; Risky design, small safety margins, new design, etc
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Is a short-circuit test to be considered?


Economical aspects to consider: Testing costs (including transport costs) and associated risks (project delays in case of a failure); Evaluation of revenue losses, mainly for bulk power applications like interconnections, generating power stations, large industrial plants, etc.; Large number of units to be ordered e.g. distribution transformers

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Is a short-circuit test to be considered?


Economical aspects to consider: Duration of an outage; For GSU applications, is it possible to store the energy e.g. in a water reservoir for hydro power; Time needed to replace the failed transformer; Costs for transformer replacement; Costs of energy replacement; Costs of power replacement.
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Is a short-circuit test to be considered? A composite evaluation of all aspects (technical and economical) shall be done. Costs of performing a short-circuit test series shall then be compared with the costs, inconveniences and risk of having a failure in service.

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Hydro-Quebec policy regarding the need of performing short-circuit tests


Short-circuit tests on critical power transformers since 1997. Short-circuit tests on small power transformers and distribution transformers are still performed. Can be easily tested in North American Laboratories without excessive transport costs. Nowadays, short-circuit tests on large power transformers can be hardly justified because of the extreme transport costs for sending transformers to laboratories outside North America.
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Tests performed on Hydro-Quebec's power transformers since 1997


Description Manufacturer Succeed at the first trial No Modifications made on the initial design Yes Failure has been observed by 2,5 MVA, Special application A 1st test series: Impedance variation: Yes Visual inspection: Yes, axial failure 2nd test series: Impedance variation: No, less than 2% Dissolved gas-in-oil analysis: Yes, presence of acetylene. Visual inspection: Yes, axial failure 47 MVA, 170 kV / 25 kV B Yes No N/A

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Tests performed on Hydro-Quebec's power transformers since 1997


Description Manufacturer Succeed at the first trial No Modifications made on the initial design Yes Failure has been observed by 102 MVA, GSU Axial-split 230 kV /11 kV / 13,8 kV 775 MVA, 230 kV / 24 kV GSU C Arcing fault to the tank Impedance variation: Yes Dissolved gas-in-oil analysis: Yes, presence of acetylene. Visual inspection: Yes, axial failure Impedance variation: No less than 2% but more than 1% Dissolved gas-in-oil analysis: Yes, presence of acetylene. Visual inspection: Yes, spiralling failure of the LV winding

No

Yes

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Benefits of performing shortcircuit tests


Feedback for improving calculations, design evaluation and manufacturing methods; Changes and improvements made on a design which has initially failed a short-circuit test are normally implemented as a common manufacturing practice. Increase manufacturer and utility knowledge. Long-term improved reliability for all similar transformers.
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Does a short-circuit test damage the transformer?


Hydro-Quebec have not seen any service problems on the units which have been shortcircuit tested. EDF (France) and ENEL (Italy) who did perform extensive short-circuit test campaigns did not report any particular problems with these units.

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

How to be sure that a transformer subjected to a short-circuit test has no internal damages
By doing additional diagnostic tests such as FRA or FRSL; By adding a dissolved gas-in-oil analysis after tests; By doing a mandatory and detailed out-of-tank active part inspection;

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

How to be sure that a transformer subjected to a short-circuit test has no internal damages
By requesting a temperature rise test at maximum rating after the active part inspection; By requesting dielectric type tests to be performed after the active part inspection at 100% of the rated test levels; By requesting all other type and routine test at 100% of the various ratings.

Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Conclusions
Short-circuit failures represent only a few percentage of total transformer failures but do generally result in catastrophic failures. Test is the only method to guaranty the ability of a transformer to withstand a short-circuit. Tests are providing valuable inputs to designers and utilities for improving actual and future designs and service continuity.
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

Conclusions
Short-circuit tests are expensive and an extensive technical, economical and risk evaluation should be conducted before requiring a test. Adequate diagnostic methods, active part inspection and final type and routine tests at 100% of the rated levels are needed to insure that a short-circuit test did not damage the transformer.
Pierre Riffon, Eng., Charlotte, SC, March 17, 2008

SHORT-CIRCUIT TESTING OF LIQUID-FILLED TRANSFORMERS


Charlotte, North Carolina, March 17, 2008
Presented by: Richard P. McLaughlin Supervising Test Engineer Kema Powertest, LLC

Richard P. McLaughlin, Charlotte, SC, March 17, 2008

CONSIDERATIONS BEFORE TESTING


SPECIFY WHICH TESTS TO PERFORM
Dictated by the client as to which tests are to be witnessed and/or performed by the test lab.

Richard P. McLaughlin, Charlotte, SC, March 17, 2008

CONSIDERATIONS BEFORE TESTING


SCHEDULING OF SUFFICIENT TEST TIME
Depending on the above specified tests to be performed the test lab will submit an estimated time quotation to perform all tests for approval.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

INFORMATION NECESSARY FOR SHORT-CIRCUIT TEST


TRANSFORMER NAMEPLATE INFORMATION
Require the MVA, voltage ratings, and total percent impedance to calculate the necessary short-circuit test levels. Each test transformer is calculated on an individual basis.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

INFORMATION NECESSARY FOR SHORT-CIRCUIT TEST


POST-SET VS. PRE-SET
Typically perform most short-circuit tests with the pre-set method due to a generator fed source (2250MVA short-circuit generator). Post-set testing can be performed on a strict individual basis depending on the test transformer voltage, short-circuit current ratings, and no-load losses.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

PERFORMANCE OF SHORTCIRCUIT TESTING


SET-UP Depending on the calculated impedance and short-circuit test levels will dictate how extensive the set-up needs to be. Typically is a minimum of a to of a work-shift.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

PERFORMANCE OF SHORTCIRCUIT TESTING INITIAL IMPEDANCE MEASUREMENTS Measure on all necessary taps that the short-circuit tests are to be apllied to. Typically only takes a several minutes for each tap position.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

PERFORMANCE OF SHORTCIRCUIT TESTING SHORT-CIRCUIT CURRENT CALCULATIONS Calculate the required shortcircuit current values based on the limitations and equations in IEEE C57.12.00 and C57.12.90.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

PERFORMANCE OF SHORTCIRCUIT TESTING


SHORT-CIRCUIT TEST PROCEDURE
Typical procedure for each winding of a three-phase unit: Impedance - 2 full-level shortcircuit current tests - Impedance.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

PERFORMANCE OF SHORTCIRCUIT TESTING


SHORT-CIRCUIT TEST PROCEDURE
Alternate procedure for each winding of a three-phase unit: Impedance - 6 full-level shortcircuit current tests - Impedance.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

PERFORMANCE OF SHORTCIRCUIT TESTING


SHORT-CIRCUIT TEST PROCEDURE
Typically it takes a minimum of 1 work-shift to perform the typical short-circuit test procedure. This is depending on the performance of the test transformer and the test station.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

PERFORMANCE OF SHORTCIRCUIT TESTING


POST IMPEDANCE MEASUREMENTS Measure on all necessary taps that the short-circuit tests were apllied to. Typically only takes a several minutes for each tap position.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

CONCLUSIONS
The impedance variation larger than that specified in the test standard is the most common after the short-circuit tests.

Richard P. McLaughlin, Charlotte, SC, March 17, 2008

CONCLUSIONS
KEMA (Arnhem) shows that in 11 years of testing (of 77) large transformers (25 - 440 MVA, 20 500 kV), 31% fails initially to pass the short-circuit test, mostly because an unacceptable increase in reactance. 1
1

KEMA'S TEST EXPERIENCES WITH SHORT-CIRCUI T WI THSTAND CAPABILI TY OF LARGE POWER TRANSFORMERS : R. P. P. Smeets, L. H. te Paske, P.P. Leufkens - KEMA T&D Testing Services, Arnhem, the Netherlands

Richard P. McLaughlin, Charlotte, SC, March 17, 2008

CONCLUSIONS
Every tested transformer provides many levels of concern, all must be accounted for with every short-circuit test.

Richard P. McLaughlin, Charlotte, SC, March 17, 2008

CONCLUSIONS
Each test facility shall make accommodations for the areas covered, and not covered, in this tutorial depending on their circumstances presented to them at the time of the test.
Richard P. McLaughlin, Charlotte, SC, March 17, 2008

Some Particular Cases


Charlotte, North Carolina, March 17, 2008 Presented by: Marcel Fortin Eng Test specialist Consultant

Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Content
Low X/R transformers Multi winding autotransformers Non-circular coils Axial split transformers

Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Axial split
Axial-split transformers comprise transformers having 3 or more windings with 2 or more windings physically superimposed axially one the same magnetic leg. Each of the axial-split windings can be connected to different sources and/or loads by different sets of bushings.
H1 load 1 source

load 2

Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Axial split
Fault shall be applied to only 1 axial split winding To lower the magnetizing inrush the post-set method is preferred
Clause 12.2.3.1 of the draft and CIGRE paper 12-104

H1 load 1 source

load 2

Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Non circular coils


Many lower size and distribution transformers are built using non-circular coils (square or rectangular) On the first asymmetry, somethime on the calibration, these windings will bulge radially and show a high impedance variation Usually, after the first maximum peak test the windings have bulged to their limit and most of the time no impedance variation, or very light, is observed on following tests Heat run test and visual inspection is of prime importance to ascertain that the transformer have passed the test.
Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Other multiwinding transformers


Single phase 120/240 V transformers Single phase multiple connection transformers/ autotransformers
HV: 14400 V LV: 3 x 2400 V windings

Transformer connection: 14400/2400 or 7200 V Autotransformer connection: 14400/7200 V


Marcel Fortin Eng, Charlotte, SC, March 17, 2008

Other multiwinding transformers


During testing, each winding shall be subjected to its maximum calculated fault current on at least one test. In general, a given fault type and location will not produce the maximum fault current in more than one winding, so it will be necessary to make tests with several different connections to fully evaluate the capability of all windings. (clause 12.2.2.1 of C57.12.90 2006)

Marcel Fortin Eng, Charlotte, SC, March 17, 2008

S-ar putea să vă placă și