Sunteți pe pagina 1din 1

WELDER PERFORMANCE TECME/PUCP

QUALIFICATION RECORD SHEET: 1 of 1


(WPQR) ISSUE: 22/04/13
(See QW-301, Section IX, ASME Boiler and
Pressure Vessel Code) REVISION: 1

WELDER PERFORMANCE QUALIFICATION RECORD (WPQR)


Welder Name: Stamp No.: ID: WPQR No.:
WPS followed by the Welder: Evaluated in: Test Tube ( ) Production Welding ( )
Base Metal Specification: Backup Soldering Iron: --- ID: ---

Welding Variables (QW-350) Value Used in Rating Qualified Rank


Welding process:
Type Used (manual, semi-automatic) :
Backup (metal, welding, gas, electric arc) :
( )Iron ( )Pipe (enter diameter, if pipe):
Thickness:
Base Metal No. P or S to No. P or S:
Filler metal or electrode (SFA) specification:
Filler metal or electrode classification:
Filler Metal No. F:
Consumable Insert (GTAW or PAW) :
Filler Metal Type
(Solid/metal or Tubular flux/powder) :
Thickness deposited by each Process:
Process 1 --- 3 layers minimum Yes ( ) No ( )
Process 2 --- 3 layers minimum Yes ( ) No ( )
Sheet and Pipe ≤
Pipe 610mm and Fillet
Qualified Position: >610mm OD >73mm OD

Vertical Progression (ascending/descending) :


Type of fuel gas (OFW) :
Backup gas (GMAW,GTAW,PAW) :
GMAW transfer mode
(spray, globular, short circuit, pulsed) :
Current Type/Polarity (AC, DCEN, DCEP) :
RESULTS
Visual Inspection of Completed Welding: ACCORDING
Guided Bend Test Results: COMPLIANT
( ) Face and Transverse Root ( ) Face and Longitudinal Root ( ) Side
( ) Pipe, Corrosion resistant coatings ( ) Iron, Corrosion resistant coatings
( ) Pipe, Chemical attack test ( ) Iron, Chemical attack test
Guy Result Guy Result Guy Result

Alternative Radiographic Examination Result: ---


Fillet Weld: --- Fracture Test: --- Length and Percentage of Defects: ---
Macro attack: --- Fillet Size: --- Concavity/Convexity: ---
Other Tests: ---
Film or samples evaluated by: Company:
Mechanical tests conducted by: Laboratory Test No.:
Welding Supervised by:
We certify that the data recorded is correct and that the specimens were prepared, welded and tested in accordance with the
requirements of Section IX of the ASME Code – Boiler and Pressure Vessel – 2011a.

Organization:

DATE: By: