Documente Academic
Documente Profesional
Documente Cultură
Abstract: Good reactive power management is essential for the secure operation of power systems.
In a deregulated power market environment, apart from technical complexities, economic
considerations of compensating reactive power suppliers and charging transmission users add new
challenges to the problem. The problem of pricing reactive ancillary services is addressed. It is
formulated as a joint cost allocation problem. The total reactive support costs are determined to be
the increase in real generation costs from the reactive unconstrained case (base case) to the case in
which voltage security constraints are considered. The incurred costs are allocated to consumers
with the application of the Aumann-Shapley method. The results of the simulation of the proposed
methodology are demonstrated on an eight-bus system.
IEE Proc.-Gener. Transm. Distrib., Vol. 152, No. 5, September 2005 617
Generators’ profits from real power selling are affected
consequently. It is assumed in this paper that the uniform
bidding curve
market clearing price obtained in the base case is used for
real power settlement, even after generation rescheduling.
Bpg , $/MW
The profit change of generator i can be written as:
h i h i
Drgi ¼ lPgUi Cpgi PgUi lPgCi Cpgi PgCi ð3Þ market clearing price
i
The effects of rescheduling on a generator’s profits in real
power market are discussed in the following according to its
base case schedule.
PU
g =0
PC
g
Pg , max
i
0oPgUi oPgi ;max :
i i
2.3.1 In this case, the generator’s bid Pg , MW
price (its marginal cost) at PgUi is equal to the market i
clearing price, l ¼ bgi þ 2cgi PgUi . When the generator is Fig. 2 Lost profit illustration when PgUi ¼ 0
requested by the ISO to decrease its scheduled real power
output (PgCi oPgUi , a constrained-off generator), its income
decrease, lðPgUi PgCi Þ, will be larger than its real power
production cost decrease, bgi ðPgUi PgCi Þ þ cgi ðPgUi PgCi Þ market clearing price
ðPgUi þ PgCi Þ. Conversely, when the unused capacity of a
Bpg , $/MW
generator is called on by the ISO to balance the system real
bidding curve
power insufficiency (PgCi 4PgUi , a constrained-on generator),
i
the increase in real power production cost will be larger
than that in income. Hence the generator’s profit decreases
no matter if the generator is constrained on or off. This is
illustrated in Fig. 1. Shaded areas 1 and 2 represent the
0 PC PU
profit losses in the cases of constrained-off and constrained- g i g i = Pg i , max
on, respectively. Pg , MW
i
a price vector of the same dimension (ZPd ¼ ½ZPd are the Lagrange multipliers associated with the reactive
1 power balance equations at bus i of problem (2) in normal
ZPdi ZPd , ZQd ¼ ½ZQd ZQdi ZQd ). and contingent sets at demand level t, respectively. It should
N 1 N
The well-known Aumann-Shapley (A-S) pricing method be noted that as reactive power demands have no effects on
falling in the category of axiomatic approaches is adopted in the base case dispatch (qF U =qQdi ¼ 0), the reactive
this paper to calculate the price vector Z. The A-S method marginal costs in (9) only use information of problem (2).
has been applied to many areas such as transportation cost Hence, a numerical approach can be used to solve (6) and
allocation [18], risk management [19] and transmission (7). Numerical approximations of ZPdi and ZQdi are given by:
loss cost allocation [20]. It has become a powerful tool for K
joint cost allocation problem due to the properties of 1X 0 k k k
ZPdi ¼ p D þ pP d i D l D
economic efficiency, fairness and robustness. Billera, Heath K k¼1 Pdi K K K
and Raanan [12] first applied the value concept of
nonatomic games studied by Aumann and Shapley to solve ð10Þ
an internal telephone-billing problem. It has been shown in K
[13, 14] that A-S prices are uniquely determined by a set of 1X k k
ZQdi ¼ p0Qd D þ pQdi D ð11Þ
neutral, and in a sense equitable, axioms imposed on pricing K k¼1 i K K
methods. The axioms and relevant economic interpretations
are given by: where K is the number of numerical integration steps.
Problems (1) and (2) have to be solved K times sequentially
(A1) (Cost sharing): The generated revenue exactly recovers to calculate A-S prices. Indeed, A-S prices are average
the total cost. marginal costs concerning all level of the demand vector,
(A2) (Additivity): The price based on the total cost function but a constant mix of each component (real loads and
is equal to the sum of the prices computed with respect reactive loads increasing at the same speed) is needed.
to the (additive) components of the cost function. Normally, reactive support cost FQ has a positive relation
(A3) (Positivity): The demand of a consumer that actually with the level of demand. FQ is zero when there is no
contributes to total costs should have non-negative voltage congestion under light loading condition. There
price. exists a critical demand level satisfying FQ ðtDÞ ¼ 0; t t0
(A4) (Rescaling): A (linear) change in the units of and FQ ðtDÞ40; t4t0 . This is illustrated in Fig. 4 using the
measurement of the demand results in a concomitant test system described in Section 4.
change in the price. Demand changes under t0 have no effect on the reactive
support costs. The interval [t0, 1] is the effective integration
(A5) (Consistency): Two consumers that have the same region. A preliminary identification of t0 would improve the
effect on the cost function should be charged the same computation efficiency in practice. The bisection method,
price. which is commonly adopted in polynomial root finding [21],
is used for this purpose. Given this new start point t0 of
Rather than using game theoretic notions, these axioms are numerical integration, (10) and (11) can be rewritten as:
K h
stated in purely economic terms, hence providing an 1 t0 X
economic justification for using A-S prices. According to ZP d i ¼ p0 ðt0 þ khD Þ
K k¼1 Pdi
[13], A-S prices related to the real and reactive loads of the i
consumer at bus i can be expressed as: þ pPdi ðt0 þ khD Þ lðt0 þ khD
Þ ð12Þ
Z 1
qFQ ðtDÞ
ZPdi ¼ ð6Þ K h i
qPdi
dt 1 t0 X
0 ZQdi ¼ p0Qd t0 þ khD þ pQdi t0 þ khD ð13Þ
K k¼1 i
Z 1
qFQ ðtDÞ
ZQdi ¼ dt ð7Þ where h ¼ ð1 t0 Þ=K is the step size. Obviously, the
0 qQdi approximation accuracy of these two equations is higher
IEE Proc.-Gener. Transm. Distrib., Vol. 152, No. 5, September 2005 619
1.6 Table 1: Generator data
1.4 Generator G1 G2 G3
0.4
Table 2: Consumer data
0.2
L1 3 0.50 0.31
−0.2
0 0.80 t 0 0.90 1.00 L2 4 3.00 1.85
t L3 5 1.50 0.93
Fig. 4 Reactive support cost against demand level L4 7 2.00 1.24
A simple eight-bus system (Fig. 5) is used for computer 1 3 0.00 0.037 0.06
simulation studies. The system has eight buses and nine tie 1 8 0.00 0.03 0.06
lines. There are three generators and four consumers in 2 4 0.00 0.031 0.06
the system. Their data is summarised in Tables 1 and 2,
2 7 0.00 0.03 0.06
respectively. Table 3 gives transmission line data. The
system base capacity is 100 MVA. The voltage limits are 3 5 0.00 0.037 0.06
all within the range 0:95 Vi 1:05 (p.u.) 4 5 0.00 0.05 0.06
(i ¼ 1; 2; . . . ; 8). Bus 8 is selected as the angle reference 4 8 0.00 0.03 0.06
bus. The base (unconstrained) case real power dispatch is 6 7 0.00 0.03 0.06
given in Table 4. 6 8 0.00 0.015 0.06
When reactive/voltage constraints are taken into account,
the generators’ real power outputs will need to be adjusted
owing to system voltage control requirements both in Tables 5 and 6, respectively. The voltage profile shows that
normal and contingent states. The preventive control no bus voltage is constrained in the normal state. But in the
concept is adopted in this paper and only one potential contingency case, the voltage set point of G3 at bus 8 has to
contingency is considered. In this example, only the outage be adjusted to its upper limit and the voltage at bus 5 hits its
of the line 4–8 will force the base case real power dispatch to lower limit.
be rescheduled owing to the voltage constraints. The voltage Adjusted real power generations are shown in column 2 of
profile and generation rescheduling results are given in Table 6. This column shows that G1 and G2 have to
decrease their real power output for the provision of reactive
power support. Owing to the no-load curtailment assump-
L1 tion, the most expensive generator G3 has to generate more
G3 G1
than its base case schedule. All three generators are subject to
losses of profit as listed in the last column. The total real
8 1 3 power production costs (Fc) rises up to 11.871 103($/h).
Using (4), the system reactive support cost is 1509.88 $/h,
which will be recovered from consumers. Column 3 shows
6 5 the corresponding reactive capabilities given the real power
L3
620 IEE Proc.-Gener. Transm. Distrib., Vol. 152, No. 5, September 2005
Table 5: Voltage profile
Bus number 1 2 3 4 5 6 7 8
Normal voltage (p.u.) 1.0165 1.0000 0.9780 0.9633 0.9516 1.0025 0.9692 1.0188
Contingent voltage (p.u.) 1.0402 1.0133 0.9868 0.9507 0.9500 1.0338 1.0042 1.0500
Generator Real power output (p.u.) Reactive power capability (p.u.) Reactive power output (p.u.) Loss of profit ($/h)
normal contingency
IEE Proc.-Gener. Transm. Distrib., Vol. 152, No. 5, September 2005 621
6 Acknowledgment systems without loopflow’, IEEE Trans. Power Syst., 2000, 15, (3),
pp. 923–929
11 Chu, W.C., Chen, B.W., and Liao, C.H.: ‘Allocating the costs
Supports from the Research Committee of the Hong Kong of reactive power purchased in an ancillary service market by modified
Polytechnic University and Research Grants Council of Y-Bus matrix method’, IEEE Trans. Power Syst., 2004, 19, (1),
Hong Kong (5215/03E) are gratefully acknowledged. pp. 174–179
12 Billera, L.J., Heath, D.C., and Raanan, J.: ‘Internal telephone billing
rates-a novel application of non-atomic game theory’, Oper. Res.,
7 References 1978, 26, (6), pp. 956–965
13 Billera, L.J., and Heath, D.C.: ‘Allocation of shared costs: a set of
1 Caramanis, M.C., Bohn, R.E., and Schweppe, F.C.: ‘Spot pricing of axioms yielding a unique procedure’, Math. Oper. Res., 1982, 7, (1),
electricity: practice and theory’, IEEE Trans. Power Appar. Syst., pp. 32–39
1982, 101, (9), pp. 3234–3245 14 Mirman, L.J., and Taumam, Y.: ‘Demand compatible equitable cost
2 Baughman, M.L., and Siddiqi, S.N.: ‘Real time pricing of reactive sharing prices’, Math. Oper. Res., 1982, 7, (1), pp. 40–56
power: theory and case study results’, IEEE Trans. Power Syst., 1991, 15 Rosehart, W.D., Canizares, C.A., and Quintana, V.H.: ‘Effect of
6, (1), pp. 23–29 detailed power system models in traditional and voltage-stability-
3 Ei-Keib, A.A., and Ma, X.: ‘Calculating short-run marginal costs of constrained optimal power-flow problems’, IEEE Trans. Power Syst.,
active and reactive power production’, IEEE Trans. Power Syst., 1997, 2003, 18, (1), pp. 27–35
12, (2), pp. 559–565 16 Rider, M.J., and Paucar, V.L.: ‘Application of a nonlinear reactive
4 Baughman, M.L., Siqqiqi, S.N., and Zanikau, J.W.: ‘Advanced power pricing model for competitive electric markets’, IEE Proc.,
pricing in electrical systems Part II: implications’, IEEE Trans. Power Gener. Transm. Distrib., 2004, 151, (3), pp. 407–414
Syst., 1997, 12, (1), pp. 496–502 17 Gill, P.E., Murray, W., and Wright, M.H.: ‘Numerical linear
5 Lamont, J.W., and Fu, J.: ‘Cost analysis of reactive power support’, algebra and optimization’ (Addison Wesley, Old Tappan, 1991),
IEEE Trans. Power Syst., 1999, 14, (3), pp. 890–896 Vol. 1
6 Dai, Y., Ni, Y.X., Wen, F.S., Han, Z.X., and Wu, F.F.: ‘A study of 18 Samet, D., Tauman, Y., and Zang, I.: ‘An application of the Aumann-
reactive power marginal price in electricity market’, Electr. Power Syst. Shapley prices for cost allocation in transportation problems’, Math.
Res., 2001, 57, (1), pp. 41–48 Oper. Res., 1984, 9, (1), pp. 25–42
7 Hao, S., and Papalexopoulos, A.: ‘Reactive pricing and management’, 19 Denault, M.: ‘Coherent allocation of risk capital’, J. Risk., 2001, 4, (1),
IEEE Trans. Power Syst., 1997, 12, (1), pp. 95–104 pp. 7–21
8 Hao, S.: ‘A reactive power management proposal for transmission 20 Tan, X.H., and Lie, T.T.: ‘Allocation of transmission loss cost using
operators’, IEEE Trans. Power Syst., 2003, 18, (4), pp. 1374–1380 cooperative game theory in the context of open transmission access’.
9 Bialek, J.J.: ‘Topological generation and load distribution factors for Proc. IEEE Power Engineering Society Meeting, Columbus, OH,
supplement charge allocation in transmission open access’, IEEE USA, 2001, Vol. 3, pp. 1215–1219
Trans. Power Syst., 1997, 12, (3), pp. 1185–1193 21 Bachanan, J.L.: ‘Numerical methods and analysis’ (McGraw-Hill,
10 Wu, F.F., Ni, Y.X., and Wei, P.P.: ‘Power transfer allocation for open New York, USA, 1992), pp. 49–54
access using graph theory F fundamentals and applications in
622 IEE Proc.-Gener. Transm. Distrib., Vol. 152, No. 5, September 2005