Project urban mass transportation

INTRODUCTION Pakistan have large road network of 259, 758km of which 8,318km are National Highway And 2,027km are Motorways. The National Highway pass through major cities are backbone of our economy.. In developing country like Pakistan, the poor are disproportionately affected, with most of the victims being pedestrian, bicyclist, motorcyclists and passenger of public transport riders and with more than half of them between ages of 15 to 44 years. Young road users are particularly more vulnerable. Karachi is one of the metropolitan city of Pakistan. It has the vast transportation network between several town and zones.

PROJECT OBJECTIVE 1. 2. 3. 4. To calculate the delay at important intersection in the city. To identify the delay problem Number of buses approaches to the (case study) intersection Calculation of Delay in term of Money

Intersection Name Johar chworangi Hill park intersection Tariq road signal Itehad commercial signal (D.H.A) PHAS 2 EXTANTION Defense morr intersection Metric board office intersection

UMT Project.

Page 1

Project urban mass transportation

Johar chworangi No. of Location Total Observation of signal cycle time 01 J.C 45sec 01 03 04 05 06 07 Average delay= 0.85 Average delay cost= 1.47 Name of Buses: W-30, G-25, G-27, G-15, etc Total red 30sec No. of buses 2 1 3 2 0 2 1 Kind of buses Mini bus Mini bus Mini bus Bus and M.B M.B M.B Delay due to red 2 mint 1mint 1.15 mint 35sec Timing of reading 3pm Delay cost (Rs) 3.5 1.75 2.04 1.03

1 mint 15 sec

1.78 0.445

Hill park intersection No. of Location Total Observation of signal cycle time 01 Hill 60 Park Sec 02 03 04 05 Average delay= 1.27mint Average delay cost= Rs 2.44 Total red 40sec No. of buses 4 3 5 2 3 Kind of buses M.B M.B M.B M.B M.B Delay due to red 1.50 mint 40 sec 2 mint 45sec 1.45mint Timing of reading 6pm Delay cost (Rs) 2.85 1.18 3.75 1.335 3.115

UMT Project.

Page 2

Project urban mass transportation


Name of Buses: U-10, S-2, Biala Couch, F-21, X-23, M-1 etc Tariq road signal No. of Location Total Total Observation of signal cycle red time 01 Tariq 50 sec 30 sec Road 02 03 04 05 Average delay= 0.71mint Average delay cost= Rs 1.225 No. of buses 4 2 3 4 1 Kind of buses M.B M.B M.B M.B M.B Delay due to red 1.35 mint 40sec 27sec 55sec 10sec Timing of reading 7pm Delay cost (Rs) 2.81 1.18 0.801 1.63 0.29

Name of Buses: U-10, S-2, Biala Couch, F-21, X-23, M-1 etc

Itehad commercial signal (D.H.A) PHAS 2 EXTANTION No. of Location Total Total Observation of signal cycle red time 01 DHA 1.15min 50sec 02 03 04 05 Average delay= 1.04mint Average delay cost= Rs 1.86 No. of buses 2 4 2 3 1 Kind of buses M.B M.B M.B M.B M.B Delay due to red 40sec 1.5mint 1.20mint 1.20mint 40sec Timing of reading 1:00pm Delay cost (Rs) 1.18 2.67 2.136 2.136 1.18

Name of Buses: W-21, W-30, Y, N-4, Shama couch. Afridi couch, Data couch, N, etc

UMT Project.

Page 3

Project urban mass transportation

Defense morr intersection No. of Location Total Total Observation of signal cycle red time 01 DHA 1.20min 40 sec 02 03 04 05 Average delay= 1.04mint Average delay cost= Rs 1.86 No. of buses 2 3 2 4 2 Kind of buses M.B&B M.B&B M.B M.B&B M.B Delay due to red 40sec 1.5mint 1.20mint 1.20mint 40sec Timing of reading 2:00pm Delay cost (Rs) 1.18 2.67 2.136 2.136 1.18

Name of Buses: W-21, W-30, Y, N-4, , N, 17-J, N-5, N-17, Shma couch, etc

Metric board office intersection No. of Location Total Observation of signal cycle time 01 M.B.O 1mint 02 03 04 05 Average delay= 1.01mint Average delay cost= Rs 1.80 Total red 40sec No. of buses 4 2 4 3 2 Kind of buses MB&B1 MB&B1 MB&B1 MB&B1 MB&B1 Delay due to red 1.25mint 1mint 1.20mint 40sec 57sec Timing of reading 4:00pm Delay cost (Rs) 2.225 1.78 2.136 1.18 1.68

Name of Buses: W-30, 4-K, 5-C, W-22, U-8, Khan couch, W-55, 4-J etc
UMT Project. Page 4

Project urban mass transportation

Method of calculation of delay cost in term of Rupee Assumption Fuel cost Rs 89 per liter If a vehicle travel in following conditions then. 1 mint (travelling) = 1 Km 1 Liter travelling = 50 Km The cost of 1 Km = Rs 1.78/=

Formula Delay in term of cost= Time (mint) x 1.78

Delay Problem at the intersection. The most important delay cause at the intersection that are under observation is congestion and signal timing. The signal timing that is currently operating the traffic of roads is not design for the current scenario. Due to growth in traffic congestion and number of vehicles in Karachi city the current signal timing cause delay problem at the intersection. Some important parameter is: Increasingly traffic Number of users Un-revise Signal timing Road condition Buses issue

UMT Project.

Page 5

Project urban mass transportation

RECOMMENDATIONS

Maintain the road network Maintain the operational process of buses Revise the signal cycle timing Proper control on traffic laws Introducing the Mass transit system

References

http://www.google.com.pk/#hl=en&q=traffic+delays+study&oq=traffic+delays+studY www.easts.info/on-line/proceedings_05/945.pdf http://onlinemanuals.txdot.gov/txdotmanuals/tff/intersection_delay_study.htm http://www.denverpost.com/breakingnews/ci_18127577

UMT Project.

Page 6

Project urban mass transportation

Topic

Delay Analysis at different intersection in Karachi city.

Name Of Group Member:


Mohammed Azeem U:E 46 Syed Umair Karim U:E 14

B.E Urban

Submitted to Prof. Dr Muhammad Adnan Department of Urban and infrastructure NED University

UMT Project.

Page 7