Item Description of Work Unit B.O.Q Qty Rate Amount Ref. D.S.R- no. 2002 1 2 3 4 5 6 7 SUBHEAD NO 1: Earth work 1 Cum 19.97 93.55 1868.01 2.8.1 Earth work in excavation in formations trenches or drains (not exceeding 1.5m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5m, including getting out the excavated soil and disposal of surplus excavated soil as directed, with in a lead of 50m Sub Head No.2 Concrete Work 1 Providing and laying in position cement concrete of specified grade exculding the cost of centering and shuttering all work upto plinth level. 1.1 1:4:8 (1 Cement : 4 Coarse Sand : 8 Graded Stone Aggregate Cum 40 mm 2.4nominal size) 3371.28 4.5.8 1404.7 SUBHEAD NO 3 : REINFORCED CEMENT CONCRETE WORK 1 Providing and laying in position machine batched, machine mixed and machine vibrated design mix cement concrete of specified grade for reinforced cement concrete structural elements, excluding the cost of centering, shuttering, finishing and reinforcement including admixtures in recommended proportions (as per IS 9103) to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per the direction of Engineer-in-charge M-20 grade reinforced cement concrete. 1.1 All work from plinth level to floor V level 1.1.1 Walls, columns, pillars, posts and struts Cum 10.93 2411.4 26351.78 5.42.2.1 2 Centring and shuttering including strutting, propping etc. and removal of form for: 2.1 Walls (any thickness) including attached pilasters, Sqm 79.11 106.4 8417.52 5.14.2 butteresses, plinth and string courses etc. 3 Cum 10.93 84 917.95 5.44.1 Add or deduct for providing richer or leaner mixes for M-25 grade R.C.C instead of M-20 grade R.C.C Sub Head NO 4 :Brick Work 1 Half brick masonry with FPS bricks of class Sqm 19.47 196.85 3833.06 6.18.4+6.19 designation 75 in cement mortar 1:4 ( 1 Cement : 4 Coarse Sand) in super structure above plinth. 2 Steel work welded in built up sections/framed work including cutting hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc.as required. 2.1 In gratings, frames, guard bar, ladders, railings, Kg 2001.41 29.15 58341.04 10.32.2 brackets, gates & similar works. 3 Providing and fixing Ist quality ceramic glazed tiles Sqm 94.9 373.3 35424.68 11.73 conforming to IS : 13753 of minimum thickness 5 mm of approved make like NITCO, ORIENT, SOMANY KAJARIA, or equivalent make in all colours, shades except begundy, bottle green, black of any size as approved by Eningeer-in- Charge in skirting, risers of steps and dados over 12 mm thick bed of Cement Mortar 1:3 (1 Cement : 3 Coarse sand) and jointing with grey cement slurry @ 3.3kg per Sqm including pointing in white cement mixed with pigment of matching shade complete. 4 Providing and fixing C.P. brass bib cock of Each 32 163.75 5240 20.9 approved quality conforming to IS:8931 a) 15 mm nominal bore 5 Providing and fixing G.I. pipes complete with G.I. fittings and clamps,including cutting and making good the walls etc. (internal work) 5.1 15mm dia. nominal bore Rm 20.8 62.65 1303.12 20.2.1.1 TOTAL FOR SCHEDULE -A 145068.44 SCHEDULE- 'B' ( REINFORCEMENT STEEL - NON SCHEDULE ITEMS) 1 Providing, cutting, straightening, hooking, bending, Kg 728.13 40.6 29562.00 Package placing, and binding in position reinforcement of SB-2 ( R ) Thermo mechanically treated steel bars for RCC works or as per approved drawings including binding wires and all lead & lift as acomplete job as per specifications and as per instructions of Engineer-in-charge. NOTE- Payment for above shall be made only for quantity of reinforcement steel actually used as per approved drawing excluding all wastages. TOTAL FOR SCHEDULE -B 29562 GRAND TOTAL FOR SCHEDULE- A & SCHEDULE- B 174630.43 21,828.80 QUANTITY ESTIMATE 1. Earth work in Excavation in one Water booth Description Length in mts Beradth in m Depth in mts Qty in Cum In Foundation 2.6 1.6 0.6 2.5
2. P.C.C (1:4:8) in one Water booth
Description Length in mts Beradth in m Depth in mts Qty in Cum In Foundation 2.5 1.6 0.08 0.3
3. Concrete M-20 (1:4:8) in one Water booth
Description Nos Length in mts Beradth in m Depth in mts Qty in Cum In Raft 1 2.5 1.6 0.23 0.9 In wall 1 0.94 0.15 1.58 0.22 1 0.45 0.15 0.2 0.01 2x1/2 0.25 0.15 0.2 0.01 Side wall 2 0.75 0.08 0.59 0.07 2X2X1/2 2 0.15 0.08 0.18 0 2 0.15 0.08 0.18 0 Side wall 2 0.94 0.12 0.08 0.02 Top Slab 2 1.1 0.3 0.08 0.05 Bottom slab 2 0.75 0.38 0.08 0.05 Deduction for offset in bottom slab -1 0.18 0.23 0.08 0 Wall on 2 0.4 0.12 0.08 0.01 bottom slab 2 0.5 0.12 0.08 0.01 4 0.2 0.21 0.08 0.01 Total qty of M-20 conc 1.366
4. Half Brick Masonry in one Water booth
Description Nos Length in mts Height in m Qty in Sqm In Foundation 2 2.5 0.22 1.08 2 1.53 0.22 0.66 2 1.25 0.22 0.54 2 0.38 0.22 0.16 Total qty of Half brick masonry 2.434
5. Structural steel in single section in one Water booth
Description No of frame Nos Length in mts Wt / mt Qty in Kgs In Frame ISA 1 2 2.4 4.5 21.6 50x50x6 1 2 1.4 4.5 12.6 Flat 50x6mm 8 10 0.59 2.23 104.5 in one frame 8 12 0.52 2.23 111.47 Total qty of structural steel 250.176
6. Tiles. in wall of one Water booth
Description Nos Length in mts Height in m Qty in Sqm Wall upto 2 1.15 0.55 1.27 900mm high 2 0.9 0.4 0.72 4 0.3 0.47 0.56 2 0.55 0.2 0.22 Top water 2 1.15 0.33 0.76 booth outlet/counter Top water booth 4 0.12 0.38 0.18 outlet/counter 1 1.06 0.2 0.21 2 0.9 0.33 0.59 2 0.46 0.2 0.18 2 0.9 0.3 0.54 4 0.18 0.23 0.17 2 0.8 0.22 0.35 2 0.4 0.18 0.14 Bottom water 2 0.1 0.36 0.07 booth counter 2 0.41 0.25 0.2 2 0.8 0.35 0.56 2 0.65 0.15 0.2 2 0.2 0.15 0.06 2 0.56 0.15 0.17 2 0.43 0.13 0.11 2 0.56 0.3 0.34 Floorings 1 2.27 1.3 2.95 1 7.14 0.15 1.07 1 2.8 0.15 0.42 Deduction in flooring 1 -1.25 0.15 -0.19 Total qty of Tiles in one water booth 11.862
7. shuttering in wall/slab/Raft of one Water booth
Description Nos Length in mts Height in m Qty in Sqm Wall upto 2 1.15 0.9 2.07 900mm high 2 0.9 0.15 0.27 Slab Lower 2 0.46 0.75 0.69 2 0.4 0.2 0.16 Sides of slab 4 0.25 0.2 0.2 4 0.29 0.2 0.23 2 0.4 0.13 0.1 4 0.25 0.13 0.13 4 0.2 0.22 0.17 Slab Upper 4 0.3 0.3 0.36 Wall above 2 0.3 1.1 0.66 900mm high 2 1.1 0.27 0.59 2 0.75 0.25 0.38 4 0.3 0.3 0.36 2 0.94 0.5 0.94 2 0.45 0.2 0.18 2 0.17 0.2 0.07 Deduction -2 0.15 0.3 -0.09 Raft 2 2.5 0.3 1.5 2 1.53 0.3 0.92 Total qty of Shuttering in one water booth 9.89