Sunteți pe pagina 1din 17

EXWord

Project structure Document


Version 1.0

Revision History
Date Version Description Author
9/20/2006 1.0 s06211005

10/18/2008 1
Table of Contents
Table of Contents.....................................................................................................................2
Project Approaches:.................................................................................................................1
Project Goals, Objectives, Assumptions, and Constraints.......................................................1
Project Scope...........................................................................................................................2
Project Trade-off Matrix......................................................................................................2
Project Trade-off Matrix......................................................................................................2
Master Project Approach.....................................................................................................3
Development Approach.......................................................................................................3
Test Approach......................................................................................................................4
Training Approach...............................................................................................................4
User Support Approach........................................................................................................4
Communication Approach...................................................................................................4
Deployment Approach.........................................................................................................4
Operations Approach...........................................................................................................4
Milestone Approach.............................................................................................................4
Project Estimates..................................................................................................................5
Schedule Summary..............................................................................................................7
Schedule Summary..............................................................................................................7
Roles and Responsibilities...................................................................................................9
Knowledge, Skills, and Abilities*........................................................................................9
Team Structure...................................................................................................................11
Project Protocols................................................................................................................11
Risk and Issue Management Approach..............................................................................11
Configuration Management Approach...............................................................................12
Change Management Approach.........................................................................................12
Release Management Approach.........................................................................................13
Project Quality Assurance Approach.................................................................................13
Project Communication Approach.....................................................................................13
Team Environment Approach............................................................................................14

10/18/2008 1
Project Approaches:

Project Goals, Objectives, Assumptions, and Constraints

Project Goals:
Our aim is to provide an application for XML coding which enables the XML coder to
create and manipulate XML documents.
Project Objectives:
The main features of this application are to provide user the ability to create, edit and save
XML document, some sort of way to validate the XML code that XML coder write as well
as application highlights the XML code by using colour codes and proper indentation

Project Assumptions:
1. Plate form(operations)
2. copy right
3.

Project Constraints:
1 time limitation
2 resources
3
4
Project Scope
[Description:
The Project Scope section defines the
1 tasks,
2 deliverables,
3 resources, and
4 schedule
Necessary to deliver the customer’s solution.

The tasks are expressed in the


1. Master Project Approach,
2. the Milestone Approach,
3. the Project Estimates, and
4. the Project Schedule.
These multiple views allow the customer and project team to look at the project from
different perspectives and to analyze how the work is organized.
The tasks, deliverables, resources, and schedule exist at a high level of detail.
These Project Scope statements provide the context for more detailed planning during
follow-on project phases.]
<<Begin text here>>

EXWord lies between the development environments.


XML coder will be the main user of EXWord
Using EXWord XML files could be created and manipulated using the graphical views by
XML coder
Data definition possible very easily and flexibly by using the EXWord with any invalid
xml code by redistricting the user to a non editable coding view
These xml file could be validated and test against a specific schema
The XML files contain data definition and not be executed and tested along with web
HTML files by using our software
The generated code by the EXWord could be saved as file print or could be used as data
source files are these are tested against a schema and validated easily embedded into any
system

Project Trade-off Matrix


[Description: The Project Trade-off Matrix is a table that represents the customer’s
preferences in setting priorities among schedule, resources and features.

Note: when using the graphic, move the check marks to the appropriate boxes and
fill in the _____(blanks) within the sentence.

The Trade-off Matrix sets the default standard of priorities and provides guidance for
making trade-offs throughout the project. These trade-offs should be established up front
and then reassessed throughout the project’s life.]

Project Trade-off Matrix

10/18/2008 2
es
Sc
urc

he
so

Fixed Chosen Adjusta


du
Re

Features
Features le ble

Resource
s

Schedul
e

Feature
Set

Given fixed Schedule, we will choose a resource, and adjust feature set as
necessary.

Master Project Approach


[Description: The Master Project Approach is the roll-up of all the project teams’
approaches. This includes an overall statement of strategy for the project and individual
strategy statements for each team. A strategy statement describes a general approach to
accomplish work without associated metrics.

The Master Project Approach also describes how the various project teams will
collaborate to build and deploy the customer solution. This creates an awareness of the
dependencies among the teams.

This section should also include a description of the high-level work tasks to be
undertaken by each team. The work can be described in part by identifying what its result
or deliverable will be. This description can also include things such as tools,
methodologies, best practices, sequences of events, etc.

The Master Project Approach ensures that each team member understands how it will
contribute to the project’s overall success. In addition, it communicates to the customer
that Microsoft and its partners are working from a well-developed strategy. The Master
Project Approach evolves into the Master Project Plan during the planning phase.]

The sections below describe the project team’s approach to building the project work
packages.

[Note: The sections identified below are suggested categories. Modify these
categories to fit your project. ]

Development Approach
<<Begin text here>>

10/18/2008 3
Test Approach
<<Begin text here>>

Training Approach
<<Begin text here>>

User Support Approach


<<Begin text here>>

Communication Approach
<<Begin text here>>

Deployment Approach
<<Begin text here>>

Operations Approach
<<Begin text here>>

Milestone Approach
[Description: The Milestone Approach identifies the significant events in the project’s
lifespan. During envisioning, these are usually expressed as External Milestones that
identify visible accomplishments of high-level deliverables and illustrate the project’s
schedule targets. At the highest level, External Milestones can be associated with the
completion of a specific project phase.

The Milestone Approach identifies the basis for establishing milestones. Depending on the
nature of the project, Milestones can be finance-based, progress-based, product-based,
and so on. The Milestone Approach defines this basis and identifies the milestone events
that will be tracked.

Describing Milestones early in the project establishes high-level time targets the customer
can confirm and the team must anticipate during its planning activities. It also identifies
the checkpoints where Milestone Reviews will occur to assess the project’s quality and its
results.]
At high level, the Milestones or goals in the lifespan of VUM Project are 7 which are:
1. Gathering & Analyzing Info
2. Envisioning the Solution
3. Planning the Solution
4. Development
5. Stabilizing
6. Deployment

10/18/2008 4
7. Viva Voice and presentation

Total 7 phases required to complete the Project of the EXWord. Project team will pass
through these above mentioned phases to successfully complete the whole development
process
The lifespan of each milestone vary by time allowed to achieve that milestone. In the
envisioning phase, the Project Team has to complete the 3 documents. This envisioning
phase has 7 days allotment in the Project Schedule. Project Team can take more than 7
days to complete this deliverable but in this case, they will get late for the next phase and
the Project Team has to work hard in the all remaining phases to complete the project
before the final allotted date.

Project Estimates
[Description: The Project Estimates section contains an estimate of the resources and
costs required for the project teams to accomplish their work. Resources include people,
equipment, facilities, and material. Costs are calculated by applying rates to each type of
resource requirement. This section should contain the following information, broken out by
each functional team:

A list of resource types

Following resources are available for our project.

Man Power:
Four out of four team members are available and are working on the whole
development process according to their responsibilities mentioned under the
heading “Roles and Responsibilities”

Equipments:

Hard ware Equipments:


Required hardware equipment for development are 2 (two) Desktop Computers.
These computers should base on Inter architecture with standard I/O devices.

Software Equipments:
Required software equipments for development are following:
Platform (Microsoft Windows XP (5.1, Build 2600) Service Pack 2 Professional
Edition)
Documentation
Text (Microsoft Word Processor)
Graphics (Microsoft Visio)
Integrated development environments (NetBean, Microsoft visual studio)

Facilities:
Uninterruptible Power Supply (UPS)
Proper installation of software
Hardware maintenance
Clean, healthy environment

10/18/2008 5
The amount of the resource required

Amount of Man Power


Amount
Available 4
Required 3-4
Deployed 4

Hardware Amount/ capability


Desktop PCs 2
Architecture Intel(R) Celeron(R) CPU 1.70GHz
Standard I/O Output devices Amount
devices Digital Colour 2
Monitors
supported with
Standard
Display Cards
Input Devices Amount
Standard PS2 2 each
Mouse,
Microsoft
Standard Key
board
CD ROM 2
Flash Drive 1
Power Device Amount
Equipments UPS 2

Software Type Name Amount/ Capability


Platform Microsoft Windows 2 installed copies on both
XP (5.1, Build 2600) desktop PCs
Service Pack 2
Professional Edition
Documentation software Microsoft Word 2 installed copies on both
Processor desktop PCs
Microsoft Visio 2 installed copies on both
desktop PCs
Integrated Development NetBean 2 installed copies on both
Environments desktop PCs
Microsoft visual 2 installed copies on both
studio desktop PCs

The rate applied to each resource

Resource Rate Applied


Man Power A+
Hardware resources A
Software resources A

10/18/2008 6
Facilities B
Material C

The cost of each resource

Total days 157


Total working days 135
Daily working hours 2
Total Working Hours for Unit man
Power 269

daily working hours = 1 unit 8


Units for one man power 34

Total Man Power Units 135

Total cost of resources for each functional team

Project Estimates provide information for calculating the budget estimate. They also
enable the project manager and team leads to identify the specific resources needed to
perform the work.]
<<Begin text here>>

Schedule Summary
[Description: The Schedule Summary section identifies and compiles the collective work
tasks and their calendar dates into a complete project schedule that identifies its
beginning and end dates. Each major Project Milestone is identified and assigned a
targeted completion date. The schedule is a consolidated schedule — it includes the work
and dates of all project teams.

The scheduling process is iterative. During the envisioning phase, the project’s Major
Milestones anchor the schedule. During the planning phase, the schedule will become
more granular as the work tasks are broken down.

The Schedule provides the basis for the customer to verify timelines and for the project
team to produce a constrained master plan from which it can validate proposed budgets,
resources, and timescales.]
<<Begin text here>>

Schedule Summary
Schedule/Work Plan Management consists of two perspectives: the high-level schedule
and dependencies, and the day-to-day tracking of work plan activities and task
completion.
The schedule management component consists of schedule timelines, dependencies and
resources, particularly where coordination with other external organizations is required.

The project schedule for EXWord was announced by the EXWord Project Instructor as a
framework. Constrained by the hard milestone dates specified in the Project Schedule
document, which is shown below:

10/18/2008 7
No. Phase Deliverables To Be Submitted Weight Allocated Submission
age(%age)
Days Date
0 Gathering & 1) Actors Catalog 10% 10 10/09/2006
Analyzing Info 2) Business Rules Catalog
3) Use cases & Usage
Scenarios
4) Glossary
1 Envisioning the 1) Vision Scope Document 05% 7 17/09/2006
Solution 2) The Risk Assessment
Document
3) The Project Structure
Document

2 Planning the 1) Functional Specification 30% 30 17/10/2006


Solution 2) Master Project Plan
3) Master Project Schedule
4) Risk Management Plan
3 Development 1) Development Plan 20% 30 16/11/2007
2) Source Code

4 Stabilizing 1) Test Plan 05% 7 23/11/2007


2) Test Cases

5 Deployment 1) Deployment Plan 05% 07 30/11/2007


2) Release Note
3) Installer
6 Final Evaluation 1) Presentation Document 25% 05 05/12/2007
& Viva Voice 2) Final Project Report

The graphical view of the Project Schedule is show below:

The development of these seven complete deliverables presents special


scheduling challenges for EXWord Project team. When project team completes
one deliverable then it will send it to VU Project Instructor for checking. Every
deliverable has its own dead date to submit, but it’s not necessary to send it before
on the dead date, Project team can send it after that individual deliverable dead
date, but the whole project (all deliverables) should be submitted before the dead
date of the project which is 5th of December.

10/18/2008 8
Roles and Responsibilities

Roles and Responsibilities


Khurram Sohail Butt Team Leader
bc020400183@vu.edu.pk
Key Roles & Responsibilities
i. Keeping the team on track
ii. Assigning units of work
iii. Leading meetings
iv. Scheduling team and client meetings

Mubashir Iqbal Lead Designer


bc020400362@vu.edu.pk
Key Roles & Responsibilities
i. Lead the team in all prospects of design
ii. Helping in code segment
iii. Structure design, interface design

Amjed Perviz Project Developer


bc020400295@vu.edu.pk
Key Roles & Responsibilities
i. Handling the developing process
ii. Coding the project
iii. Analyzing the information generated
iv. Finalizing the solution

Muhammad Yasir QA & Testing Manager


bc020401204@vu.edu.pk
Key Roles & Responsibilities
i. Overseeing the testing process
ii. keenly observing testing criterion
iii. Overseeing all module, integration, system and acceptance

Knowledge, Skills, and Abilities*


[Description: The Knowledge, Skills, and Abilities section specifies the requirements for
project participants. This is expressed by defining the knowledge, skills, and abilities
needed to conduct the project. These requirements should include technical, managerial,

10/18/2008 9
and support capabilities. This information is organized into functional teams and
responsibilities. At the highest level, the KSA can be based on the standard MSF roles.
Each functional team, or MSF role, is listed, and the team’s knowledge, skills, and abilities
requirements are defined alongside.

Justification: Knowledge, Skills, and Abilities information will facilitate the careful
selection of specific project participants and provide the basis for creating the core team
structure.]
<<Begin text here>>
Knowledge
i. Khurram
Base knowledge of Management such as
Finical management
Operations Research
HRM
Business Communication and Report writing
ii. Mubashir
Algorithms
Mathematical analysis
Software Engineering
Database
iii. Amjed
Modern Programming languages
Java, Visual C++
Databaseconstruction
iv. Yasir
HCI
Software Engineering
Theory of Automata
Skills
i. Khurram
Having skills to use the best use of the managerial skills in
right direction at right time and right directions
ii. Mubashir
Best logic building and Design structure skills for the
support of project and module designing
iii. Amjed
Development skills like to do programming in different
languages over different plate form and having the skill
adopt the new technologies required to manage the tools and
techniques and discuss documentations
iv. Yasir
Good skills of communication, software project management
and QA skills.

Abilities

10/18/2008 10
Team Structure
[Description: The Team Structure section defines the project’s organizational entities
(project manager, sponsor(s), steering committee, team leads, etc.), illustrates their
relationships to one another, and defines levels of responsibility and reporting structure.
When complete, the team structure assigns names to each organizational entity and
explicitly calls out the individual team (or team members) tasked with executing,
reviewing, and approving the project’s work. This assignment is spread across all entities
participating in the project: Microsoft, Partners, and Customer.
Hierarchy
Justification: The documentation of the project’s organizational structure ensures that all
project participants understand their roles in making the project a success, clarifies lines
of reporting and decision-making, and provides key stakeholders an opportunity to ensure
that the project’s organizational structure (project form) will facilitate the work (project
function).]
<<Begin text here>>
The EXWord teaming arrangements were initially developed based on the interests,
experience and expertise. From that starting point and with the understanding that Team
Leader’s home institution, would serve as the EXWord lead institution, arrangements were
made there for doing project work.
The Team of EXWord Project consists of 4 members. All members are playing a
significant role in the EXWord Project.

The following team structure is defined over the skills and abilities

Project supervisor

Mr. Khurram Sohail Main Client


Team Leader Contact

Mr. Mubashir Iqbal Mr. Amjed Perviz Mr. Muhammad Yasir


Lead Designer Project Developer QA & Testing Manager

Project Protocols
[Description: Project Protocols are the set of project processes that must be
standardized to ensure all project participants are performing the processes in the same
manner. This standardization creates performance efficiencies and facilitates a common
language among the project stakeholders.]

Risk and Issue Management Approach


[Description: The Risk and Issue Management Approach section describes the
processes, methods, and tools to be used to manage the project’s risks and issues. It

10/18/2008 11
must be sufficiently detailed to facilitate the risk and issue management process during
the envisioning and planning phases. It must also make it possible to categorize issues as
product issues or project issues. This section will include the following:

Description of risk and issue management processes, methods, and tools


Schedule/frequency of risk and issue management activities
Roles and responsibilities within the risk and issue management process
Specifications of the risk/issue assessment form and the issues resolution form

Justification: The Risk and Issue Management documentation ensures that all project
participants understand their responsibilities in identifying and managing risks and issues,
and that all project personnel are using the same risk and issue management processes.]
<<Begin text here>>
Risk and issue management approach:
Risk management is a continuous process beginning in Phase I and continuing through
launch and orbital operations. Activities include planning for risk, assessing (identifying
and analyzing) risk areas, developing risk mitigation plans, and monitoring risks to
determine how they have changed over time, and implementing risk mitigation plans in a
timely manner. Risks can enter the project as technical or programmatic risks. Although the
Team Leader, QA & testing Manager and the Lead Designer will identify most risks,
risks can be identified by anyone in the project team at any time. The Team Leader is the
owner of the risk management process. Team Leader will continuously monitor the risk
management process to ensure that risks are being reported, tracked, and dealt with in a
proactive manner.

Configuration Management Approach


[Description: The Configuration Management Approach section defines how all the
project’s deliverables (hardware, software, management and technical documents, and
work in progress) will be tracked, accounted for, and maintained. Configuration
Management includes project documents, the development and test environments, and
any impact on the production environment. This section will include the following:

Description of configuration management processes, methods, and tools


Processes to request configuration changes (steps, approval levels)
Roles and responsibilities for configuration management
Version-control standards for documents

Justification: Configuration Management documentation ensures that the project can


maintain object and document integrity so that a single version is used at all times.]
<<Begin text here>>

Change Management Approach


[Description: The Change Management Approach section describes how the project’s
scope will be maintained through structured procedures for submitting, approving,
implementing, and reviewing change requests. The change management process is
charged with providing prompt and efficient handling of any request for change. This
section should include the following:

Change management processes, methods, and tools


Composition of the Change Advisory Board

10/18/2008 12
Change request form
Roles and responsibilities of change management activities
Reference to the contractual change order from the Customer Contracting
Approach section

Justification: Documenting the Change Management Approach helps the project


maintain a timely single perspective of the project’s scope (both project activities and
products produced) and ensure that only contracted work is undertaken.]
<<Begin text here>>

Release Management Approach


[Description: The Release Management Approach section describes the processes,
methods, and tools that coordinate and manage releases of the solution to the different
test and production environments. It describes the processes of coordinating and
managing the activities by which all releases to the production IT environment are
planned, tested, and implemented.

This section includes the transition plan (release to production) and plans for back-out
processes. The approach should be compliant with the Microsoft Operations Framework
(MOF) Release Management Process.

Justification: This information ensures that the project plans for and follows an orderly
process of solution test and implementation, thus limiting the impact on the customer’s
operational environment and ensuring that environment is operationally ready to receive
the release.]
<<Begin text here>>

Project Quality Assurance Approach


[Description: The Project Quality Assurance Approach section defines how the project
intends to deliver products that meet the customer’s quality expectations and
Microsoft/Partner quality standards. It addresses both the project’s management and the
development of the project’s product. This section should include the following:

Quality expectations
Process for assurance (audit, reviews, contractor controls)
Process for control (peer reviews, inspections, tests)
Quality organization (entities, roles, and responsibilities)
Templates for the Product Review, Project Milestone Review, and Customer
Approval reports
Training requirements

Justification: A well-developed Product Quality Assurance Approach is key to managing


customer confidence and ensuring the development and deployment of a golden solution.]
<<Begin text here>>

Project Communication Approach


[Description: The Project Communication Approach section defines how and what the
project will communicate with its stakeholders. This communication occurs within the team
and between the team and external entities. The Project Communication Approach

10/18/2008 13
identifies the processes, methods, and tools required to ensure timely and appropriate
collection, distribution, and management of project information for all project stakeholders.
It also describes the team’s strategy for communicating internally among team members
and company personnel, as well as externally with vendors and contractors.

This section includes the following:

Project Stakeholders and their communication requirements


Types of communications (progress reports, change management requests,
configuration management documentation, release management documentation,
risks and issues, financial reports, project plans, technical specifications, etc.) and
their standard configurations and media
Communication type owners
Project organization/distribution lists
Communication infrastructure requirements (tools, internal and external tracking
systems, etc.)

The progress report is an important document that should be detailed in this section. It
describes how to collect and distribute the non-financial metrics and qualitative
information that pertain to project progress, team performance, schedule slippage, risks,
and issues that impact the project. The progress report should summarize completed
work, report on milestones, and highlight new risks.

The Project Communication Approach should be organized into two sections:


communication within the project and user communication.

The user communication section should include the processes, methods, and tools that
will explain the solution to the customer and user communities to ensure rapid and
trouble-free adoption of the solution. This should identify the key points along the project
cycle where the solution will be presented to the users and provide a description of what is
presented (user requirements, functional specifications, prototypes, etc.). This section
should identify responsibilities for creating and delivering the user communication and
identify a process for collecting user feedback for incorporation into technical documents
and the solution.

Justification: A well-developed Project Communication Approach ensures that


information is available to its users in a timely manner to facilitate decision-making. It sets
the expectations with the customer and the project teams that information will be
distributed in a standardized fashion and on a regular basis.]
<<Begin text here>>

Team Environment Approach


[Description: The Team Environment Approach section defines the approach for creating
the project team environment. It defines the physical environment requirements needed to
conduct the project and the plan to establish that environment. Environmental elements
include at least floor space (offices, meeting rooms, etc.) and equipment (computers,
desks, chairs, telephones, etc.). The requirements should also define the location of the
environmental elements and their proximity to each other. It also describes tools, systems,
and infrastructure needed by the team, such as version-control software, developer tools
and kit, test tools and kit, etc.

10/18/2008 14
In addition to requirements, this section should determine infrastructure staging and the
roles and responsibilities for environment setup. If necessary, the requirements can be
identified by team role (development, logistics, testing, user education, etc.).

Justification: The Team Environment Approach ensures that the working environment is
readily available in the timeframes set by the project schedule.]
<<Begin text here>>

10/18/2008 15

S-ar putea să vă placă și