Documente Academic
Documente Profesional
Documente Cultură
I.P.C.L-
Vadodara
GUJARAT,
INDIA
TRANSITION ZONE,
COLLECTOR, DUCT AND
STACK,
CONTENTS
1. SCOPE
2. REFERENCE DOCUMENTS
3. TYPE OF LINING
SCOPE:
2. REFERENCE DOCUMENTS:
3. TYPE OF LINING:
B) Procedure
The lining of both the Radiant and Transition zone arch are to be
carried out after erection of the same and in position. Walls lining
are to be lined after erection of burner block as insitu.
As described above, the stud welding has to be completed as per
the layout shown in the drawing and painting as per CIRIA
Specification furnished, prior to commencing the lining installation.
Stud welding and painting can be done in at ground or insitu.
5.4
5.5
5.6
5.6.1
5.6.2
5.6.3
5.6.4
5.3.3
CONTENTS
Introduction
Ceramic fiber products are extensively used in the lining of
furnaces. And products are used basically due to its light weight,
low thermal conductivities and thermal shock resistance etc.
A General
• Design Considerations
• Installation Sequence
B Installation
A GENERAL
Design Considerations
Ceramic fiber Module lining of side walls shall be done first after
that end walls lining. Top most one or two row of walls ceramic fiber
Modules shall be installed after completing the arch lining and then
the left out one or two row of walls lining shall be completed.
B INSTALLATION
Equipment Check List
The following list details the basic equipment required to carry out
a typical Z-Blok 3 Module installation.
Step 2
At the points where the chalk lines cross it is good practice to spot
grind an area approximately 10mm diameter to ensure that the weld
is made onto clean steel. This is especially important on old steel
casings.
Step 3
At the points where the chalk lines cross, weld a T Bar anchor
onto the steel casing
Step 4
If coating / painting is being used it is a good idea to protect
the threads of the anchors by installing plastic covers over the
anchors. If a coating is not being used, plastic covers for the
anchors are not needed. At this point, back-up layers of
blanket and Aluminium or Stainless Steel foil vapour barriers
should be installed if being incorporated into the lining of the
furnace.
Step 5
When the necessary backing coatings and or linings have been
installed the Z-Blok 3 Modules can be installed. The modules
are installed in rows therefore at the start of a row remove the
arms from one side of a T Bar yoke. Locate the T Bar yoke onto
the anchor, which has been welded to the wall previously, fixing
it into position with a locking nut.
Step 6
The tubes in the module are then located onto the arms of the
T Bar yoke, another T Bar yoke is located into the tubes in the
opposite end of the module. The module is then compressed
into position.
Step 7
The sequence is completed by fitting the T Bar yoke onto the
anchor and securing with the locking nut.
Step 8
The procedure mentioned above is repeated until the row is
completed. Before commencing the installation of another row
of modules a packing strip of Ceramic Fibre blanket should be
installed (folded & compressed as per lining arrangement &
detail drawing). This blanket packer should be jointed using a
staggered joint and not exceed 2 metres in length.
Step 9
When the packing strip is in place the next row of modules can
be installed. The anchor positions will ensure that the modules
are compressed during installation. The use of thin steel or
plastic plates allows the modules to be slid into position
making the task of obtaining the necessary compression
easier.
Step 10
The lining is carried out as described above till the end of the row is
reached. For the last but one module a half split yoke is used to complete
the Z-Blok 3 lining with one module space at the end left vacant. Because
of this the split yoke can be easily fixed. For the last module a center
fixing module Pyrofold M Module is used which can be easily installed
and fixed to the prewelded shell as described below under stop end
fixing.
Step 11
B) Procedure:
B) Procedure:
Work Planning
Formwork
Formwork should be constructed from strong materials.
Generally 3/4 inch plywood or steel forms are favored for this
job because of their inherent strength and non-absorbent
nature. The surface of the formwork must be cleaned, lightly
and thoroughly oiled or greased to facilitate easy removal
from the face of the casting after completion of lining activity.
PH : 6.5 to 8.35
Ca2+ : < 300 PPM
Mg2+ : < 300 PPM
K++Na+ : < 150 PPM
Cl- : < 200 PPM
Fe3+ : < 300 PPM
SO42- : < 200 PPM
Residue after
Evaporation at 180 Dg C : 1500 PPM
Mixing –
Mixing combines the dry materials and water into a
homogenous mass. Mixing must be done in paddle type
mixer of sufficient capacity to ensure through mixing of the
Castable.
Placement:
The Castable shall be installed immediately after mixing.
The aim should be to position and consolidate freshly mixed
material within 15 minutes of it leaving the mixer. The
location of mixer machine and manpower required to shift
the mixed Castable and for placing should be adequate for
fast placement. This has to be taken care of while planning
the Castable lining. Also the time between pouring of
consecutive batches must be such that the setting of the first
batch should not begin before the second batch is poured.
The Castable must be installed in a manner, which minimizes
material segregation. It should be poured slowly into
position, taking care that every undercut or profile is
completely filled up and the lining is devoid of any air
pockets. For insulating Castables rodding or tamping is
sufficient to remove voids and to consolidate the material
without excess compaction. Excessive rodding is also not
advisable for lightweight Castables as it will crush the
materials and increase the density. Striking the formwork
from outside with hammer will also help to avoid formation of
air pockets.
Once the installation has started, it should proceed without
interruption until the lining of the part or section concerned is
completed. In case of any unavoidable interruption in lining
activity, the wet edge of the lining shall be cut back at right
angle to the surface of lining and all material ahead of the
cut shall be removed and discarded.
Each batch from the mixer shall be installed so that the full
thickness of the lining is produced, rather than building up
the thickness in layers. When doing vertical casting as in
walls, the Castable shall be spread evenly along the length of
the shuttering and tamped in order to obtain a homogeneous
lining.
Joints
Construction joints are designed the break the job up into
conveniently sized panels. Adjoining panels are cast against
each other without leaving any gaps using the set face of
previously cast section as the formwork edge. Typical joint
details are as shown in relevant drawings. At expansion
joints, Ceramic fiber blanket strips covered with thin
polythene sheet (to prevent absorption of water) are used.
Finishing
When finishing the exposed surface of the refractory
Castable lining, it is important to avoid smooth / excessive
trowelling of the surface. Excessive working draws water to
the surface along with the fines and cement binder and
produces a fine finish rich in cement which is easily dislodged
by peeling on curing and certainly on exposure to elevated
temperature / alternate heating and cooling. Thus the lined
Castable surface only needs to be leveled with a screed or
wood float and not to be trowelled to a smooth finish.
Curing
Curing prevents the loss of moisture from freshly cast
refractory concrete. Loss of water from the surface of the
cast before the bond is fully hydrated results in a weaker
lining. To prevent this, various methods of moist curing can
be used. Formwork should be left in place for a minimum of
24 hours and exposed refractory concrete either sprayed
with water, covered with plastic sheeting or with wet gunny
bags. This is called moist curing. Moist curing can start
immediately after the initial setting when the lining surface is
hard enough to prevent impinging water from washing out
the surface cement and shall proceed for a minimum of 24
hours. During the curing process the refractory lining and
casing temperature shall be maintained between 10 to 32°C,
if the lining is done in open air, the surface of lining should be
protected from direct sunlight by shading until the wet curing
process is complete.
Welding
• Measurement Tape
• Long Bladed Knife
• Hack Saw for cutting SS Tubes in Modules
• Lubricators / Slip Plates
• Socket with extension arm for tightening nuts to fix
modules
• Hand Tools like Screw Driver, Pliers etc.
• Tamping Tool (small flat piece of ply wood / wood or
expanded metal Approx.300 x 250mm with a handle for
tamping modules after installation.
Castable Lining:
• Paddle Mixer
• Water Tank
• Wooden tray with GI or Aluminium facing
• Rubber / GI Buckets for transporting mixed castable.
• Formwork, Supports and hand tools for fixing formwork /
supports.
• Pans
• Tamping Rods
• Electric or Diesel Vibrator
• Thermometer
• Trowel
• Gunny Bags for curing
• Wooden Hammer
• Binding wire.
• Spirit Level / water level.
• Measuring Jar
• Moulds for sample preparation.
• Measurement Tape
• Drill Machine with 6mm & 12mm drill bits for bricks and
blocks
• Hand Saw for cutting
• Pans for mortar / block mix
• Heavy Duty Drill Machine with spatula for mixing mortar
• Wooden / Robber Hammer
• Plumb Bob
• Trowel
• Straight Edge
• Angle
• Water Level
5.5 Drying Out
Castable Lining:
The main objective of physical testing of samples made at
site is to assess and judge the quality of installed lining to
some extent without disturbing the lining. Thus the essence
of sampling is to ensure that the sample represent the
installed lining in all aspects, including the material batch,
method of installation etc and is marked properly to correlate
the sample to the installed portion of the unit.
Sampling for application by casting:
One sample per section of the lining for each quality and
batch of castable being installed is made during the actual
installation.
Each sample consists of 3 nos. 50mm ± 4mm cubes, which
are cast in metal moulds. The metal moulds are cleaned,
slightly oiled and kept ready for sampling. When the
installation work / castable lining is ongoing the cubes are
cast with the same material. The cubes are then cured,
carefully coded and marked. The codes are then mentioned
on the lining drawing to indicate the location where the
parent material, from which sample was cast, is lined. The
batch number of the castable is also noted while sampling to
enable correlation of the sample with the batch of the
material.
The cubes per batch of Castable are then kept together and
randomly 3 cubes are selected for testing. 3 cubes per lot
(supplied batches of each type of Castable material) of
Castable material are then sent for testing (Bulk Density and
Cold Crushing Strength). The cubes after wet curing of 24
hours are allowed to air dry for 24 hours before being sent to
testing to an approved laboratory or the laboratory specified
by the customer/client. The cubes are tested for bulk density
and cold compressive strength after oven drying at 105°C,
B.D. as per ASTM C 134 & CCS as per ASTM C 133 standards.
The results are then compared with the acceptance criteria
with an additional tolerance of 10% of the material. Ie for
Cold Compressive strength, the permissible value shall be the
minimum value as per acceptance criteria less 10% and no
limit for the maximum value. Similarly for Bulk Density, the
permissible value shall be the maximum value as per
acceptance criteria + 10% and no limit for the minimum
value. Thus permissible values are
Bulk Density : Max of (Acceptance Criteria
Value + 10%)
Cold Crushing Strength : Minimum (Acceptance Criteria
Value – 10%)