Sunteți pe pagina 1din 81

Chapter 4 - set B

Reinforcement for the suspended slab: assume #6@12" in the short span and #5@18" in the long direction for shrinkage
Calculating the quantities
1 Slab on Grade
Area
Volume
Edge forms
2 Suspended slab
Area / floor
Formwork / floor
Formwork all
Structural rebar
Shrinkage rebar
Total rebar
Volume
3 Footings
Volums / each
Volums all
Forms / each
Forms all
Rebar / each
Rebar Total

4 Short beams
Forms / each
Forms all
Volums / each
Volums all
Upper rebar / each
Lower reabr / each
Total No. 6 / each
Total No. 6
Stirrups / each
Stirrups / Beam
Stirrups all short beams
All rebar
5 Long beams
Forms / each
Forms all
Volums / each
Volums all
Upper rebar / each
Lower reabr / each

9,000.00 SF
166.67 CY
390.00 LF

8,500.00
8,760.00
26,280.00
44,358.67
20,111.00
87,602.49
43.80
629.63

1.19
33.19
32.00
896.00
36.67
1,026.67
2,741.20
1.37

SF
SF
SF
LF - No. 6
LF - No. 5
LB
Ton
CY

Added edges

The factor 0.94444 represents the the net concrete area out of the to
concrete area was written as 120' X 75' X 0.944444 rather than 8,50

CY
CY
SF
SF
LF
LF
LB
Ton

225.00
8,550.00
2.78
105.56
238.00
248.00
486.00
27,738.94
13.87
4.00
404.00
5,772.35
2.89
16.76

SF
SF
CY
CY
LF - No. 6
LF - No. 6
LF - No. 6
LB
Ton
LF - No. 3
LF - No. 3
LB
Ton
Ton

640.00
7,360.00
13.58
156.17
734.00
804.00

SF
SF
CY
CY
LF - No. 8
LF - No. 8

The duplication in volume as a result of the small and large beam int
Added 4' for splice laps and end hooks
Added 4' for splice laps and end hooks

The duplication in volume as a result of the small and large beam int
Added 8' for splice laps and end hooks
Added 8' for splice laps and end hooks

Total No. 8 / each


Total No. 8
Stirrups / each
Stirrups / Beam
Stirrups all long beams

1,538.00
47,224.29
23.61
7.00
847
6,506.65
3.25

LF - No. 6
LB
Ton
LF - No. 4
LF - No. 4
LB
Ton

6 Columns
Forms / each
Forms all
Volume / each
Volume all
Rebar - No. 10

100.00 SF
8,400.00 SF
1.85 CY
155.56 CY
20,160.00 LF
Assumed total length is 15' per bar
86,748.48 LB
43.37 Ton
Stirrups / each
6.33 LF - No. 4
Stirrups all
6,916.00 LF - No. 4
4,619.89 LB
2.31 Ton
Note: For formwork and concrete, the length of the column was taken as 12'-6", which represents the length to the bottom

Note: The drawing at the top of page 70 shows continuation of the columns on the top of the roof slab. This is an error.
Columns stop at the roof slab. If the building design took in consideration the possibility of adding future floors, the rebar
would have stuck out of the roof slab to offer continuation with future columns. This assumption was NOT taken in consid
7 Parapets
perimeter length
perimeter area

390.00 LF
1,170.00 SF
1,316 Blocks

8" in the long direction for shrinkage

e the net concrete area out of the total area, i.e. 8,500 SF / 9,000 SF, so the total
0' X 75' X 0.944444 rather than 8,500 SF

esult of the small and large beam intersection was neglected

esult of the small and large beam intersection was neglected

h represents the length to the bottom of the major beams

p of the roof slab. This is an error.


ty of adding future floors, the rebar of the top floor (or dowels)
ssumption was NOT taken in consideration in this example.

Exercise 1: Suspended slabs


Qty
CSI Number
1 26,280.00
31113351150
2
43.8
32110600400
3
629.63
33105350200
4
629.63
33105701500

Exercise 2: Small (short) beams


Qty
CSI Number
1 8,550.00
31113202150
2
16.76
32110600100
3
105.56
33105350200
4
105.56
33105700050

Exercise 3: Large (long) beams


Qty
CSI Number
1 7,360.00
31113202650
2
3.25
32110600100
3
23.61
32110600150
4
156.17
33105350200
5
156.17
33105700200

Exercise 4: Columns
Qty
CSI Number
1 8,400.00
31113256650
2
2.31
32110600200
3
43.37
32110600250
4
155.56
33105350200
5
155.56
33105700800

Exercise 5: Footings
1
33.19
33105702450
2
33.19
33105350200
3
1.37
32110600550
4
896
31113455150

In the table above, we used the "under 1 CY" for concrete placement. If we use the average between "under 1 CY" and "over 5
Exercise 5: Footings (alternate solution)
33.19
33105702450
33.19
33105702650
1
33.19
33105702550
2
33.19
33105350200
3
1.37
32110600550
4
896
31113455150

Exercise 6: SOG

Qty
1
2
3
4
5

390
90
166.67
166.67
90

CSI Number
31113651100
32205500700
33105350200
33105704550
72610100900

Item 4 above is an interpolation between the 2 items below: one for 4" thick and one for over 6" thick
166.67
33105704350
166.67
33105704650
Exercise 7: CMU
1 1,170.00

42210240200

Exercise 8: Total bare cost for all items above


Total =
Note that no waste factor was taken for the concrete or CMU. A 5% waste factor in the materials may be advisable. This is
This will bring the total bare cost to
Exercise 9: Total cost for Suspended Slabs including OH&P:
9.a.
Total cost
9.b.
Total cost
Exercise 10: Total cost for Small Beams including OH&P:
10.a.
Total cost
10.b.
Total cost
Exercise 11: Total cost for Large Beams including OH&P:
11.a.
Total cost
11.b.
Total cost
Exercise 12: Total cost for Columns including OH&P:
12.a.
Total cost
12.b.
Total cost
Exercise 13: Total cost for Footings including OH&P:
13.a.
Total cost
13.b.
Total cost
Exercise 14: Total cost for SOG including OH&P:
14.a.
Total cost
14.b.
Total cost
Exercise 15: Total cost for CMU Parapets including OH&P:
15.a.
Total cost
15.b.
Total cost
Exercise 16: Total cost for All Concrete/CMU members above including OH&P:
16.a.
Total cost
16.b.
Total cost

Exercise 17: Suspended slabs with pump rented for 21 days/mo


Using items 01 54 33 10 2120 and 01 54 33 10 3000
Daily cost

Cost per CY
CCI, Equip., Frankfort, KY
Qty
CSI Number
1 26,280.00
31113351150
2
43.8
32110600400
3
629.63
33105350200
4
629.63
33105701500

Exercise 18: Suspended slabs: Crane & Bucket


Qty
CSI Number
1 26,280.00
31113351150
2
43.8
32110600400
3
629.63
33105350200
4
629.63
33105701550

Exercise 19: Suspended slabs: Local Labor Rates


Labor only
Crew C20
1
5
1
1

Rebar

Crew C2

1
4
1

Qty
CSI Number
1 26,280.00
31113351150
2
43.8
32110600400
3
629.63
33105350200
4
629.63
33105701500

Exercise 20: Suspended slabs: Reduced Productivity


Qty
CSI Number
1 26,280.00
31113351150
2
43.8
32110600400
3
629.63
33105350200

629.63

33105701500

Exercise 21: Total bare cost for all items in 2012


Total in 2012
Exercise 22: Suspended slabs: Overtime
Use Note R012909-90
Pay factor =
Qty
CSI Number
1 26,280.00
31113351150
2
43.8
32110600400
3
629.63
33105350200
4
629.63
33105701500

Exercise 23: Columns: Use forms 5 times


Qty
CSI Number
1
100.00
31113256600
2
100.00
31113256650
Use interpolation:

1
2
3
4
5

Qty
CSI Number
8,400.00
31113256650
2.31
32110600200
43.37
32110600250
155.56
33105350200
155.56
33105700800

Exercise 24: Suspended slabs: Avg reinforcement


Use note R033105-10
Qty
CSI Number
1 26,280.00
31113351150
2 38.40743
32110600400
3
629.63
33105350200
4
629.63
33105701500

Exercise 25: Columns with Steel Forms


Qty
CSI Number
1 8,400.00
31113257750
2
2.31
32110600200
3
43.37
32110600250
4
155.56
33105350200
5
155.56
33105700800

Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals

Description
C.I.P. concrete forms, beams and girders, interior, plywood, 12" wide, 4 use, includes shoring, erecting, bracing, stripping and c
Reinforcing steel, in place, beams and girders, #3 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, beam, small, elevated, pumped, includes vibrating, excludes material
Totals

Description
C.I.P. concrete forms, beams and girders, interior, plywood, 24" wide, 4 use, includes shoring, erecting, bracing, stripping and c
Reinforcing steel, in place, beams and girders, #3 to #7, A615, grade 60, incl access. Labor
Reinforcing steel, in place, beams and girders, #8 to # 18, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, beam, large, elevated, pumped, includes vibrating, excludes material
Totals

Description
C.I.P. concrete forms, column, square, plywood, 24" x 24", 4 use, includes erecting, bracing, stripping and cleaning
Reinforcing steel, in place, columns, #3 to #7, A615, grade 60, incl access. Labor
Reinforcing steel, in place, columns, #8 to #18, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, column, square or round, pumped, 24" thick, includes vibrating, excludes material
Totals

Structural concrete, placing, spread footing, pumped, under 1 C.Y., includes vibrating, excludes material
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Reinforcing steel, in place, footings, #8 to #18, A615, grade 60, incl access. Labor
C.I.P. concrete forms, footing, spread, plywood, 4 use, includes erecting, bracing, stripping and cleaning
Totals
used the "under 1 CY" for concrete placement. If we use the average between "under 1 CY" and "over 5 CY", we get:
(alternate solution)
Structural concrete, placing, spread footing, pumped, under 1 C.Y., includes vibrating, excludes material
Structural concrete, placing, spread footing, pumped, over 5 C.Y., includes vibrating, excludes material
Structural concrete, placing, spread footing, pumped, avg. 1-5 C.Y., includes vibrating, excludes material
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Reinforcing steel, in place, footings, #8 to #18, A615, grade 60, incl access. Labor
C.I.P. concrete forms, footing, spread, plywood, 4 use, includes erecting, bracing, stripping and cleaning

Description
C.I.P. concrete forms, slab on grade, bulkhead with keyway, wood, 6" high, 4 uses, includes erecting, bracing, stripping and cle
Welded wire fabric, sheets, 4 x 4 - W4 x W4 (4 x 4) 85 lb. per C.S.F., A185
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, slab on grade, pumped, 4"-6" thick, includes vibrating, excludes material
Building Paper, polyethylene vapor barrier, standard, .006" thick, 9' x 400' roll
Totals
interpolation between the 2 items below: one for 4" thick and one for over 6" thick
Structural concrete, placing, slab on grade, pumped, 4" thick, includes vibrating, excludes material
Structural concrete, placing, slab on grade, pumped, over 6" thick, includes vibrating, excludes material

Concrete masonry unit (CMU), exterior, tooled joints both sides, normal weight, 2000 psi, 8" x 8" x 16", includes mortar and hor

e cost for all items above


$456,005
e factor was taken for the concrete or CMU. A 5% waste factor in the materials may be advisable. This is an additional
total bare cost to

t for Suspended Slabs including OH&P:


$236,488
$237,462

st for Small Beams including OH&P:


$89,107
$89,864

st for Large Beams including OH&P:


$91,721
$92,395

st for Columns including OH&P:


$126,917
$128,429

st for Footings including OH&P:


$8,648
$8,613

st for SOG including OH&P:


$26,381
$26,428

st for CMU Parapets including OH&P:


$8,073
$7,963

st for All Concrete/CMU members above including OH&P:


$587,335
$591,152

ded slabs with pump rented for 21 days/mo


33 10 2120 and 01 54 33 10 3000
Pump
2 Vibrators
Total

quip., Frankfort, KY

Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals

ded slabs: Crane & Bucket


Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, with crane and bucket, 6" to 10" thick, includes vibrating, excludes material
Totals

ded slabs: Local Labor Rates


Labor foreman
Laborer
Cement Finisher
Equip. Operator

Rodman

Carpenter foreman
Carpenter
Laborer

Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals

ded slabs: Reduced Productivity


Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only

Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals

re cost for all items in 2012


$576,992

ded slabs: Overtime


productivity = 92.5%
1.261261261

Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals

s: Use forms 5 times


Description
C.I.P. concrete forms, column, square, plywood, 24" x 24", 3 use, includes erecting, bracing, stripping and cleaning
C.I.P. concrete forms, column, square, plywood, 24" x 24", 4 use, includes erecting, bracing, stripping and cleaning

Unite price, materials, 5 times


Unite price, labor, 5 times
Description
C.I.P. concrete forms, column, square, plywood, 24" x 24", 4 use, includes erecting, bracing, stripping and cleaning
Reinforcing steel, in place, columns, #3 to #7, A615, grade 60, incl access. Labor
Reinforcing steel, in place, columns, #8 to #18, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, column, square or round, pumped, 24" thick, includes vibrating, excludes material
Totals

ded slabs: Avg reinforcement


Use "One Way Beam & Slab", Live Load = 100, Span = 15 (hours is only 10)
Total reinforcement
Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals

s with Steel Forms


Description
C.I.P. concrete forms, column, square, steel framed plywood, 24" x 24", rent, 4 uses per month, includes erecting, bracing, strip
Reinforcing steel, in place, columns, #3 to #7, A615, grade 60, incl access. Labor
Reinforcing steel, in place, columns, #8 to #18, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, column, square or round, pumped, 24" thick, includes vibrating, excludes material
Totals

Crew
C2
4 Rodm
C20

Crew
C2
4 Rodm
C20

Crew
C2
4 Rodm
4 Rodm
C20

Crew
C1
4 Rodm
4 Rodm
C20

C20
4 Rodm
C1

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
560
0.086 S.F.
$34,952.40
$44,676.00
$0.00
$79,628.40
2.9
11.034 Ton
$33,726.00
$13,797.00
$0.00
$47,523.00
C.Y. $51,944.48
$0.00
$0.00
$51,944.48
160
0.4 C.Y.
$0.00
$4,974.08
$3,028.52
$8,002.60
$120,622.88
$63,447.08
$3,028.52 $187,098.48

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
375
0.127 SFCA $10,773.00
$21,631.50
$0.00
$32,404.50
1.6
20 Ton
$12,234.80
$9,637.00
$0.00
$21,871.80
C.Y.
$8,708.70
$0.00
$0.00
$8,708.70
60
1.067 C.Y.
$0.00
$2,216.76
$1,356.45
$3,573.21
$31,716.50
$33,485.26
$1,356.45
$66,558.21

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
395
0.122 SFCA $6,771.20
$17,737.60
$0.00
$24,508.80
1.6
20 Ton
$2,372.50
$1,868.75
$0.00
$4,241.25
2.7
11.852 Ton
$17,235.30
$8,027.40
$0.00
$25,262.70
C.Y. $12,884.03
$0.00
$0.00
$12,884.03
90
0.711 C.Y.
$0.00
$2,170.76
$1,335.25
$3,506.02
$39,263.03
$29,804.51
$1,335.25
$70,402.80

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
238
0.134 SFCA $6,636.00
$21,756.00
$0.00
$28,392.00
1.5
21.333 Ton
$1,686.30
$1,420.65
$0.00
$3,106.95
2.3
13.913 Ton
$31,660.10
$17,348.00
$0.00
$49,008.10
C.Y. $12,833.70
$0.00
$0.00
$12,833.70
92
0.696 C.Y.
$0.00
$2,107.84
$1,306.70
$3,414.54
$52,816.10
$42,632.49
$1,306.70
$96,755.29

65
3.6
415

0.985 C.Y.
C.Y.
8.889 Ton
0.077 SFCA

$0.00
$2,738.18
$897.35
$501.76
$4,137.29

$637.25
$0.00
$349.35
$1,335.04
$2,321.64

$393.30
$0.00
$0.00
$0.00
$393.30

$1,030.55
$2,738.18
$1,246.70
$1,836.80
$6,852.23

0.985 C.Y.
0.427 C.Y.
0.706 C.Y.
C.Y.
8.889 Ton
0.077 SFCA

$0.00
$0.00
$0.00
$2,738.18
$897.35
$501.76
$4,137.29

$637.25
$277.14
$457.20
$0.00
$349.35
$1,335.04
$2,141.59

$393.30
$170.93
$282.12
$0.00
$0.00
$0.00
$282.12

$1,030.55
$448.07
$739.31
$2,738.18
$1,246.70
$1,836.80
$6,560.99

"over 5 CY", we get:

C20
C20
C20
4 Rodm
C1

65
150
107.5
3.6
415

Crew
C1
2 Rodm
C20
1 Carp

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
350
0.091 L.F.
$117.00
$686.40
$0.00
$803.40
25
0.64 C.S.F. $2,970.00
$1,669.50
$0.00
$4,639.50
C.Y. $13,750.28
$0.00
$0.00
$13,750.28
157.5
0.419 C.Y.
$0.00
$1,370.87
$838.35
$2,209.21
37
0.216 Sq.
$349.20
$420.30
$0.00
$769.50
$17,186.48
$4,147.07
$838.35
$22,171.89

C20
C20

130
185

0.492 C.Y.
0.346 C.Y.

$0.00
$0.00

$1,608.37
$1,133.36

$983.35
$693.35

$2,591.72
$1,826.70

D8

360

0.111 S.F.

$3,077.10

$3,088.80

$0.00

$6,165.90

This is an additional

All items below, 9-16, do not have a materials waste factor

$549.79
$36.51
$586.30
$3.66
103.50%
Crew
C2
4 Rodm

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
560
0.086 S.F.
$34,952.40
$44,676.00
$0.00
$79,628.40
2.9
11.034 Ton
$33,726.00
$13,797.00
$0.00
$47,523.00
C.Y. $51,944.48
$0.00
$0.00
$51,944.48
160
0.4 C.Y.
$0.00
$4,974.08
$2,387.97
$7,362.05
$120,623
$63,447
$2,388
$186,458

C20

Crew
C2
4 Rodm

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
560
0.086 S.F.
$34,952.40
$44,676.00
$0.00
$79,628.40
2.9
11.034 Ton
$33,726.00
$13,797.00
$0.00
$47,523.00
C.Y. $51,944.48
$0.00
$0.00
$51,944.48
110
0.655 C.Y.
$0.00
$8,185.19
$5,981.49
$14,166.68
$120,623
$66,658
$5,981
$193,263

C7

Ea
$16.00
$14.00
$17.00
$19.00
Total / day
$20.00

$640.00
$640.00

$21.00
$18.00
$14.00

$168.00
$576.00
$112.00
$856.00

Total / day

Total / day
Crew
C2
4 Rodm
C20

Crew
C2
4 Rodm

Total / day
$128.00
$560.00
$136.00
$152.00
$976.00

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
560
0.086 S.F.
$34,952.40
$40,170.86
$0.00
$75,123.26
2.9
11.034 Ton
$33,726.00
$9,666.21
$0.00
$43,392.21
C.Y. $51,944.48
$0.00
$0.00
$51,944.48
160
0.4 C.Y.
$0.00
$3,840.74
$3,028.52
$6,869.26
$120,623
$53,678
$3,029
$177,329

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
448
0.1075 S.F.
$34,952.40
$55,845.00
$0.00
$90,797.40
2.32 13.7925 Ton
$33,726.00
$17,246.25
$0.00
$50,972.25
C.Y. $51,944.48
$0.00
$0.00
$51,944.48

C20

128

0.5 C.Y.

$0.00
$120,623

$6,217.60
$79,309

$3,785.65
$3,786

$10,003.25
$203,717

So, crews will work 60 hour. Effective hours = 60*0.925= 55.5. Pay hours = 40 + 20*1.5 = 70 hours

Crew
C2
4 Rodm

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
560
0.086 S.F.
$34,952.40
$56,348.11
$0.00
$91,300.51
2.9
11.034 Ton
$33,726.00
$17,401.62
$0.00
$51,127.62
C.Y. $51,944.48
$0.00
$0.00
$51,944.48
160
0.4 C.Y.
$0.00
$6,273.61
$3,274.08
$9,547.69
$120,623
$80,023
$3,274
$203,920

C20

Crew
C1
C1

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
230
0.139 SFCA
$97.00
$267.00
$0.00
$364.00
238
0.134 SFCA
$79.00
$259.00
$0.00
$338.00

$0.68
$2.54
Crew
C1
4 Rodm
4 Rodm
C20

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
238
0.134 SFCA $5,728.80
$21,352.80
$0.00
$27,081.60
1.5
21.333 Ton
$1,686.30
$1,420.65
$0.00
$3,106.95
2.3
13.913 Ton
$31,660.10
$17,348.00
$0.00
$49,008.10
C.Y. $12,833.70
$0.00
$0.00
$12,833.70
92
0.696 C.Y.
$0.00
$2,107.84
$1,306.70
$3,414.54
$51,909
$42,229
$1,307
$95,445

Use 122 lb/CY


38.40743 Tons
Crew
Daily OutputLabor HoursUnit Bare Mat.
Bare Labor
Bare Equip. Bare Total
C2
560
0.086 S.F.
$34,952.40
$44,676.00
$0.00
$79,628.40
4 Rodm
2.9
11.034 Ton
$29,573.39
$12,098.21
$0.00
$41,671.60
C.Y. $51,944.48
$0.00
$0.00
$51,944.48
C20
160
0.4 C.Y.
$0.00
$4,974.08
$3,028.52
$8,002.60
$116,470
$61,748
$3,029
$181,247

Crew
C1
4 Rodm
4 Rodm
C20

Daily OutputLabor HoursUnit Bare Mat.


Bare Labor
Bare Equip. Bare Total
440
0.073 SFCA $12,264.00
$11,760.00
$0.00
$24,024.00
1.5
21.333 Ton
$1,686.30
$1,420.65
$0.00
$3,106.95
2.3
13.913 Ton
$31,660.10
$17,348.00
$0.00
$49,008.10
C.Y. $12,833.70
$0.00
$0.00
$12,833.70
92
0.696 C.Y.
$0.00
$2,107.84
$1,306.70
$3,414.54
$58,444
$32,636
$1,307
$92,387

Total Incl. O&P Zip Code Prefix


Type
$108,010.80
406 Union
$60,225.00
406 Union
$57,296.33
406 Union
$10,955.56
406 Union
$236,487.69

Release Note
2006
2006
2006
2006

SKey
U22130
U22815
U23107
U23573

MFFlag

Total Incl. O&P Zip Code Prefix


Type
$45,315.00
406 Union
$29,330.00
406 Union
$9,605.96
406 Union
$4,855.76
406 Union
$89,106.72

Release Note
2006
2006
2006
2006

SKey
U22019
U22794
U23107
U23556

MFFlag

Total Incl. O&P Zip Code Prefix


Type
$35,107.20
406 Union
$5,687.50
406 Union
$31,873.50
406 Union
$14,211.47
406 Union
$4,841.27
406 Union
$91,720.94

Release Note
2006
2006
2006
2006
2006

SKey
U22027
U22794
U22798
U23107
U23559

MFFlag

Total Incl. O&P Zip Code Prefix


Type
$40,992.00
406 Union
$4,215.75
406 Union
$62,886.50
406 Union
$14,155.96
406 Union
$4,666.80
406 Union
$126,917.01

Release Note
2006
2006
2006
2006
2006

SKey
U22102
U22800
U22805
U23107
U23565

MFFlag

2
2
2
2

2
2
2
2

2
2
2
2
2

2
2
2
2
2

$1,427.17
$3,020.29
$1,575.50
$2,625.28
$8,648.24

406
406
406
406

Union
Union
Union
Union

2006
2006
2006
2006

U23586
U23107
U22824
U22260

2
2
2
2

$1,427.17
$615.67
$1,021.42
$3,020.29
$1,575.50
$2,625.28
$8,242.49

406
406
406
406
406
406

Union
Union
Union
Union
Union
Union

2006
2006
2006
2006
2006
2006

U23586
U23590

2
2
2
2
2
2

U23107
U22824
U22260

Total Incl. O&P Zip Code Prefix


Type
$1,197.30
406 Union
$5,940.00
406 Union
$15,166.97
406 Union
$3,041.73
$1,035.00
406 Union
$26,381.00

Release Note
2006
2006
2006

SKey
U22303
U22937
U23107

MFFlag

2006

U33944

2
2
2

$3,583.41
$2,500.05

406 Union
406 Union

2006
2006

U23611
U23614

2
2

$8,073.00

406 Union

2006

U25717

$13,441
$469,446

Exercise 1 & 2
Quantity
10
20
20

Description
Columns, W 831
Columns, W 1287
Columns, W 12120
Ls 6 x 6 x 1/2
Ls 4 x 4 x 3/8
Base Plates, 1" thick

180
150
30
20

Base Plates, 2" thick

Length
15.5
17
17
Total weight of columns:
1.166667
1
2x2
2 x 2.5
Total weight of column details

22

Beams W 1026

18

28

Beams W 1049

22

36

Beams W 1650

24.25

24

Beams W 2193

29.5
Total weight of beams
Total weight of fabricated steel (lbs.):
Total weight of fabricated steel (ton):

CostWorks 2006
Qty
155
340
340
5,586.00
120
100
396
616
873
708

CSI Number
51223176850
51223177200
51223177250
51223400400
51223650500
51223652400
51223750720
51223750900
51223753120
51223754740

Description
Crew
Column, structural, 2-tier, W8x31, A992 steel, incl shopE2
primer, splice plates, bolts
Column, structural, 2-tier, W12x87, A992 steel, incl shopE2primer, splice plates, bolts
Column, structural, 2-tier, W12x120, A992 steel, incl shop
E2 primer, splice plates, bolts
Angle framing, structural steel, 4" and larger, field fabricated,
E3 incl cutting & welding
Steel plate, structural, for connections & stiffenners, 1" T, shop fabricated, incl shop primer
Steel plate, 5 to 50 tons, 48"-60" W, 10'-60' L, 2" T, mill price
Structural steel member, 100-ton project, 1 to 2 story building,
E2
W10x26, A992 steel, shop fabricated,
Structural steel member, 100-ton project, 1 to 2 story building,
E2
W10x49, A992 steel, shop fabricated,
Structural steel member, 100-ton project, 1 to 2 story building,
E2
W16x50, A992 steel, shop fabricated,
Structural steel member, 100-ton project, 1 to 2 story building,
E5
W21x93, A992 steel, shop fabricated,
Totals

Exercise 3
Qty
CSI Number
Description
Crew
121.898
51223770800 Structural steel project, offices, hospitals, etc, 100-ton project,
E6
3 to 6 stories, A992 steel, shop fabricat
Exercise 4
Qty
CSI Number
121.898 51223773400
Exercise 5
Crew E6

Description
Crew
Structural steel project, simple commercial building, 100-ton
E7 project, 1 to 2 stories, A992 steel, shop f

Quantity
3
9
1
1
1
1

Description
Struc Steel Foreman
Struc Steel Worker
Equip Oper (crane)
Welder
Equip Oper Oiler
Equip Oper (light)

$ / hr
$45.00
$43.00
$38.50
$40.00
$36.00
$38.50

Qty

Total
CSI Number
Description
Crew
121.898
51223770800 Structural steel project, offices, hospitals, etc, 100-ton project,
E6
3 to 6 stories, A992 steel, shop fabricat
Strange result: It exactly matches the result of Exercise 3!!!!

Exercise 6
Qty
CSI Number
Description
Crew
121.898
51223770800 Structural steel project, offices, hospitals, etc, 100-ton project,
E6
3 to 6 stories, A992 steel, shop fabricat

Exercise 7
inflation 1985-1995
Our est. inflation
Total bare cost
Total cost + OH&P

0.026793764
0.040190646
$387,259
$459,369

Exercise 8 & 9
No. of joists
Total length
Qty
1,000.00

25
1000 LF

CSI Number
Description
Crew
52119100560 Open web bar joist, 40-ton job lots, 22K9, 11.3 plf, 30' toE750' spans, K series, shop fabricated, incl sho

Exercise 10 & 11
Qty
CSI Number
90
51223773400
51223771100
90
51223773500
90
51223770800
90

Description
Crew
Structural steel project, simple commercial building, 100-ton
E7 project, 1 to 2 stories, A992 steel, shop f
Structural steel project, offices, hospitals, etc, 100-ton project, A992 steel, shop fabricated, incl shop p
Structural steel project, simple commercial building, 100-ton
E9 project, 7 to 15 stories, A992 steel, shop
Structural steel project, offices, hospitals, etc, 100-ton project,
E6
3 to 6 stories, A992 steel, shop fabricat
average of the two items above
Total

Exercise 12
Assume 4% annual inflation
Total bare cost

$274,508.20

Total Length (FT)


155
340
340
Total weight of columns:
210
150
NA
NA

Total Weight (LB)


4805
29580
40800
75185
4116
1470
4890
8160

Total weight of column details

18636

396

10296

616

30184

873

43650

708

65844

Total weight of beams

149974

otal weight of fabricated steel (lbs.):

243795

otal weight of fabricated steel (ton):

121.8975

Daily Output

Labor Hours
1,075
985
960
440

0.052
0.057
0.058
0.055

600
550
800
1,000

0.093
0.102
0.07
0.08

Daily Output

7.6

Total $ / day
$1,080.00
$3,096.00
$308.00
$320.00
$288.00
$308.00

Bare Mat.
Bare Labor
Bare Equip.
$5,192.50
$334.80
$238.70
$31,620.00
$802.40
$574.60
$43,520.00
$826.20
$591.60
$3,128.16
$13,238.82
$1,284.78
$4,800.00
$0.00
$0.00
$4,250.00
$0.00
$0.00
$10,890.00
$1,536.48
$1,096.92
$32,032.00
$2,605.68
$1,860.32
$47,142.00
$2,540.43
$1,807.11
$70,446.00
$2,385.96
$1,253.16
$ 253,021
$ 24,271
$ 8,707

Labor Hours

Unit
8.889 Ton

Bare Mat.
Bare Labor
Bare Equip.
$243,796.00
$45,711.75
$16,212.43

Labor Hours

Unit
10.526 Ton

Bare Mat.
Bare Labor
Bare Equip.
$243,796.00
$54,244.61
$29,986.91

14.4

Daily Output

Unit
L.F.
L.F.
L.F.
Lb.
S.F.
Cwt.
L.F.
L.F.
L.F.
L.F.

$5,400.00
Daily Output
Labor Hours
Unit
14.4
8.889 Ton

Daily Output

Labor Hours
14.4

Unit
8.889 Ton

Bare Mat.
Bare Labor
Bare Equip.
$243,796.00
$45,711.75
$16,212.43

Bare Mat.
Bare Labor
Bare Equip.
$243,796.00
$45,711.75
$12,248.89
Equip cost / day =

Daily Output

Labor Hours

Unit
0.04 L.F.

Labor Hours
7.6

Unit
10.526 Ton

8.3
14.4
11.35

15.422 Ton
8.889 Ton
12.1555

2,000

Daily Output

$1,446.98

Bare Mat.
Bare Labor
Bare Equip.
$7,200.00
$1,250.00
$750.00

Bare Mat.
Bare Labor
Bare Equip.
$164,250.00
$26,280.00
$18,810.00
$7,884.00
$189,000.00
$38,700.00
$20,160.00
$164,250.00
$22,140.00
$10,170.00
$176,625.00
$30,420.00
$15,165.00
$176,625.00
$38,304.00
$15,165.00

Bare Total
Total Incl. O&P
Zip Code Prefix
$5,766.00
$6,510.00
$32,997.00
$36,720.00
$44,937.80
$49,980.00
$17,651.76
$28,767.90
$4,800.00
$5,220.00
$4,250.00
$4,650.00
$13,523.40
$16,038.00
$36,498.00
$42,196.00
$51,489.54
$58,054.50
$74,085.12
$83,544.00
$ 285,999
$ 331,680

Type
Union
Union
Union
Union
Union
Union
Union
Union
Union
Union

Release
Note
2006
2006
2006
2006
2006
2006
2006
2006
2006
2006

Bare Total
Total Incl. O&P
Zip Code Prefix
Type
$305,720.18
$362,646.55
145 Union

Release
Note
2006

Bare Total
Total Incl. O&P
Zip Code Prefix
Type
$328,027.52
$393,121.05
145 Union

Release
Note
2006

145
145
145
145
145
145
145
145
145
145

Bare Total
Total Incl. O&P
$305,720.18
$358,736.67

Bare Total
Total Incl. O&P
$301,756.64
$354,376.77

Bare Total
Total Incl. O&P
Zip Code Prefix
Type
$9,200.00
$10,950.00
281 Union

Release
Note
2006

Bare Total
Total Incl. O&P
Zip Code Prefix
Type
$209,340.00
$247,500.00
850 Union
$7,884.00
$12,557.64
$247,860.00
$299,250.00
850 Union
$196,560.00
$229,500.00
850 Union
$222,210.00
$264,375.00
$230,094.00
$276,932.64

Release
Note
2006
2006
2006

SKey
U27239
U27246
U27247
U27259
U27362
U27373
U27421
U27423
U27455
U27479

MFFlag

SKey
U27586

MFFlag

SKey
U27626

MFFlag

2
2
2
2
2
2
2
2
2
2

SKey
U27923

MFFlag

SKey
U27626

MFFlag

U27627
U27586

2
2
2

Exercise 1
Total volume =

1600.000
1.600

Exercise 2-10 Quantities


Subfloor beam
Sills
Floor joists
Steel bridging: assume one pair per joist
Wall stud plates
Studs
Rafter's length

0.384
0.182166667
3.052
0.96
0.36433334
1.04
15.43092
Use 16'
2.176
0.11
2040.9444
20.409444
20.409444

Rafters
Ridge board
Roof sheathing
Felt
Shingles
Qty

CSI Number
0.38
0.182
3.052
0.96
0.364
1.04
2.176
0.11
2,040.94
20.41
20.41

61110105060
61110324520
61110182740
61110060600
61110406020
61110406140
61110307060
61110307920
61636100700
75113401100
73113100500

Description
Triple 2" x 12", beams and girders
Wood framing, sills, 2" x 6"
2" x 12" wood joist, framing
18 gauge steel bridging, galvanized, for 2" x 14" joists at 16" O.C.
2" x 4" wood plates, walls
2" x 4" wood studs, 8' high wall
Wood framing, roofs, rafters, to 4 in 12 pitch, 2" x 8"
Wood framing, roofs, ridge boards, #2 or better, 2" x 10"
5/8" CDX plywood sheathing, on walls
Felt, asphalt, #30, 2 square per roll, no mopping
Asphalt Shingles, premium, laminated multi-layered shingles, clas
Totals

Exercise 11
Rafter's length

17.2078
Use 18'
2.448
0.11
2292.246
22.92246
22.92246

Rafters
Ridge board
Roof sheathing
Felt
Shingles
CSI Number

Qty
2.448
0.11
2,292.25
22.92
22.92

Exercise 12
Qty
CSI Number
3.052

61110307060
61110307920
61636100700
75113401100
73113100500

Description
Wood framing, roofs, rafters, to 4 in 12 pitch, 2" x 8"
Wood framing, roofs, ridge boards, #2 or better, 2" x 10"
5/8" CDX plywood sheathing, on walls
Felt, asphalt, #30, 2 square per roll, no mopping
Asphalt Shingles, premium, laminated multi-layered shingles, clas

Description
61110182740 2" x 12" wood joist, framing

Exercise 13
Qty
CSI Number
3.052

Description
61110182740 2" x 12" wood joist, framing

Exercise 14
Qty
CSI Number
3.052

Description
61110182740 2" x 12" wood joist, framing

Board-feet
MBF
MBF
MBF
MBF
CPR
MBF
MBF
feet
MBF
MBF
SF
SQ
SQ
Crew
2 Carp
2 Carp
2 Carp
1 Carp
2 Carp
2 Carp
2 Carp
2 Carp
2 Carp
1 Rofc
1 Rofc

Daily Output

Labor Hours
2.85
0.55
1.75
1.3
0.53
0.92
1.26
0.66
1,050
58
3

5.614
29.091
9.143
6.154
30.189
17.391
12.698
24.242
0.015
0.138
2.667

Unit
M.B.F.
M.B.F.
M.B.F.
C.Pr.
M.B.F.
M.B.F.
M.B.F.
M.B.F.
S.F.
Sq.
Sq.

Bare Mat.

Bare Labor

$209.00
$73.71
$1,678.60
$91.68
$140.14
$400.40
$957.44
$58.30
$918.42
$143.89
$1,561.37

$66.50
$163.80
$869.82
$184.32
$343.98
$566.80
$859.52
$83.05
$959.24
$65.11
$1,551.16

$6,232.95

$5,713.30

feet
MBF
MBF
SF
SQ
SQ
Crew
2 Carp
2 Carp
2 Carp
1 Rofc
1 Rofc

Crew
2 Carp

Daily Output
1.26
0.66
1,050
58
3

Daily Output

Labor Hours
12.698
24.242
0.015
0.138
2.667

Labor Hours
1.75

Unit
M.B.F.
M.B.F.
S.F.
Sq.
Sq.

Bare Mat.
Bare Labor
$1,077.12
$966.96
$58.30
$83.05
$1,031.51
$1,077.36
$161.59
$73.11
$1,753.38
$1,741.92

Unit
9.143 M.B.F.

Bare Mat.
Bare Labor
$1,678.60
$892.93

Crew
2 Carp

Daily Output

Crew
2 Carp

Daily Output

Labor Hours

Unit
9.143 M.B.F.

Bare Mat.
Bare Labor
$1,678.60
$1,087.28

Labor Hours

Unit
9.143 M.B.F.

Bare Mat.
Bare Labor
$1,678.60
$1,097.07

1.75

1.75

Bare Equip.
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

Bare Equip.

Bare Total
Total Incl. O&P
Zip Code Prefix
$275.50
$332.50
166
$237.51
$336.70
166
$2,548.42
$3,204.60
166
$276.00
$384.00
166
$484.12
$691.60
166
$967.20
$1,326.00
166
$1,816.96
$2,393.60
166
$141.35
$192.50
166
$1,877.66
$2,530.77
166
$209.00
$268.39
166
$3,112.53
$4,347.33
166
$11,946.25

Release
2006
2006
2006
2006
2006
2006
2006
2006
2006
2006
2006

Type
Union
Union
Union
Union
Union

Release
2006
2006
2006
2006
2006

$16,007.99

$0.00
$0.00
$0.00
$0.00
$0.00

Bare Total
Total Incl. O&P
Zip Code Prefix
$2,044.08
$2,692.80
166
$141.35
$192.50
166
$2,108.87
$2,842.39
166
$234.70
$301.40
166
$3,495.30
$4,881.96
166

$0.00

Bare Total
$2,571.53

Bare Equip.

Type
Union
Union
Union
Union
Union
Union
Union
Union
Union
Union
Union

Bare Equip.
$0.00

Bare Equip.

Bare Total
$2,765.88

Bare Total
$0.00
$2,775.67

Note

Note

SKey
U29991
U30553
U30087
U29791
U30930
U30936
U30464
U30479
U31134
U35439
U34552

MFFlag

SKey
U30464
U30479
U31134
U35439
U34552

MFFlag

2
2
2
2
2
2
2
2
2
2
2

2
2
2
2
2

U30087

In the section for the wall on page 66, assume:


1. The slope of excavation is 1:1
2. The excavation extends from the ends also by 1'-6".
Quantities
Lower base, LB
Upper base, UB
Depth, h
Volume

927
2147
5
276.84

SF
SF
FT
CY

Exercises 1 & 2
Qty
CSI Number
Description
Crew
Daily Output
277
312316420260 Excavating, bulk bank measure, 2 C.Y. capacity
B12C = 130 C.Y./hour,
1,050
backhoe, hydraulic, crawle
We have to make an assumption here: Since this excavation will take only 2.11 hours, we assume the backhoe and crew have
Otherwise, we may have to pay for the entire day plus mob & demob
Exercise 3
Total Incl. O&P

$393.35

Exercise 4
Use Means item
rent per month
Hourly oper cost
Daily cost
CCI
Bare cost

01 54 33 20 0300
$8,550
$43.70
$777.10
89.30%
$282.79

Exercise 5
Bare cost

$277.00

Exercise 6
The duration of the excavation is just 2.11 hours but we assume it is part of a larger job that will last 2 weeks
Bare cost
$336.95
Exercise 7
Daily labor crew cost
Bare cost

$384.00
$320.13

Exercise 8
Qty
CSI Number
Description
Crew
Daily Output
277
312316420200 Excavating, bulk bank measure, 1 C.Y. capacity
B12A = 75 C.Y./hour, backhoe,
600
hydraulic, crawler
Exercise 9 & 10
Qty
CSI Number
Description
Crew
Daily Output
2,986.67
321823530800 Tennis court, rubber-acrylic base, resilient
B37
pavement, includes base
600
Exercise 11
Total Incl. O&P
Exercise 12
Equip cost / day
CCI

$126,177.00

$161.20
102.30%

Bare cost

$112,582.07

Exercise 13
Bare cost

$113,440.77

Exercise 14
Duration
4.98 say 5 days. Assume one week
Bare cost
$113,481.27
Note in Exercises 13 & 14, the impact of productivity drop and overtime on the cost is very small. That's because most of the co
Exercise 15
Daily labor crew cost
Bare cost

$1,328.00
$113,204.76

Exercise 16
Qty
CSI Number
Description
Crew
Daily Output
688
323113260900 Tennis court fences, 11 ga. wire, 2-1/2" post
B80 10' O.C., 1-5/8" top rail,
19010' high, includes exca
8
323113261000 Chain link fence, tennis courts, 11 ga. wire,
B802-1/2" post 10' O.C., 1-5/8"
10 top rail, add for gate
Totals

Exercise 17 & 18
Qty
CSI Number
Description
Crew
Daily Output
10,000.00
312316501300 Excavation, bulk, bank measure, common
B33D
earth, 1500' haul, 14 C.Y.
800 bucket, self propelled s
10,000.00
312316501350 Excavation, bulk, bank measure, common
B33D
earth, 3000' haul, 14 C.Y.
700 bucket, self propelled s
The above 2 items are for 1,500' and 3,000' haul distance. We need to interpolate

Qty
CSI Number
Description
Crew
Daily Output
10,000.00
312316501320 Excavation, bulk, bank measure, common
B33D
earth, 3000' haul, 14 C.Y.
767 bucket, self propelled s
Exercise 19
Total Incl. O&P
Exercise 20
01 54 33 20 3550
01 54 33 20 4310

$37,927.13
Equipment
Elev scraper, 14 CY
Dozer, 300 HP

Equip. crew cost

1
0.25

rent / mo
$13,500.00
$11,600.00

$1,564.55 per day

Bare cost

$26,573.87

Exercise 21
Bare cost

$40,125.00

Exercise 22
Duration
Bare cost

13.04347826 Days
$35,816.04

Exercise 23

say 2 weeks

$ / hr
1 Equip Oper
0.5 Laborer
0.25 Equip Oper

$30.00
$25.00
$30.00

total / day
$240.00
$100.00
$60.00

Total
Bare cost

$400.00

$31,150.72

Exercise 24
Qty
CSI Number
Description
Crew
Daily Output
10,000.00
312316501300 Excavation, bulk, bank measure, common
B33D
earth, 1500' haul, 14 C.Y.
800 bucket, self propelled s
10,000.00
312316501350 Excavation, bulk, bank measure, common
B33D
earth, 3000' haul, 14 C.Y.
700 bucket, self propelled s
The interpolated items is:

Qty
CSI Number
Description
Crew
Daily Output
10,000.00
312316501320 Excavation, bulk, bank measure, common
B33D
earth, 3000' haul, 14 C.Y.
740 bucket, self propelled s
Exercise 25
For the power, shovel, use Means item 31 23 16 42 3750
Crew B12M with daily production

680 CY / day

For the dump truck, use Means item 31 23 23 18 0100


Crew B34A
Shovel cycle time:
Loading

4.24 minutes

Truck cycle time:


Loading
Hauling
Dumping
Returning
Positioning (assume)
Total

4.24
3.00
0.50
2.00
1.00
10.74

Number of trucks needed


Use 2 or 3 trucks

minutes
minutes
minutes
minutes
minutes
minutes

2.53

Case 1: 2 trucks
Shovel capacity
Crew
Truck crew, B34A
Shovel crew, B12M
Total cost
Cost per CY

536.55 CY / day
How many
cost / day ea
2
$553.40
1
$1,240.70

Shovel capacity
Crew
Truck crew, B34A
Shovel crew, B12M
Total cost
Cost per CY

680.00 CY / day
How many
cost / day ea
3
$553.40
1
$1,240.70

$4.38

Case 2: 3 trucks

a) Use 3 trucks

$4.27

b)
Bare cost

Cost incl OH&P:

CCI, earthwork, Columbia, SC, instal


$41,414.61
the cost of the crews incl OH&P:
or
$52,915.74

80.90%
$3,706.50 per day
$5.45 per CY

Exercise 26
For the power, shovel, use Means item 31 23 16 42 3750
Crew B12M with daily production

680 CY / day

For the dump truck, use Means item 31 23 23 18 0100


Crew B34A
Shovel cycle time:
Loading

4.24 minutes

Truck cycle time:


Loading
Hauling
Dumping
Returning
Positioning (assume)
Total

4.24
4.50
0.50
3.00
1.00
13.24

Number of trucks needed


Use 3 or 4 trucks

minutes
minutes
minutes
minutes
minutes
minutes

3.13

Case 1: 3 trucks
Shovel capacity
Crew
Truck crew, B34A
Shovel crew, B12M
Total cost
Cost per CY

652.80 CY / day
How many
cost / day ea
3
$553.40
1
$1,240.70

Shovel capacity
Crew
Truck crew, B34A
Shovel crew, B12M
Total cost
Cost per CY

680.00 CY / day
How many
cost / day ea
4
$553.40
1
$1,240.70

$4.44

Case 2: 4 trucks

$5.08

a) Use 3 trucks
b)
Bare cost

Cost incl OH&P:


Exercise 27

CCI, earthwork, Columbia, SC, instal


$49,315.21
the cost of the crews incl OH&P:
or
$52,915.74

80.90%
$3,706.50 per day
$5.45 per CY

Assume a truck driver is paid same as equipment operator

For shovel crew, labor cost / day


For shovel crew, equip cost / day
Total shovel crew cost / day

$252.00
$711.68 CCI for equipment in Columbia, SC is
$963.68

For truck crew, labor cost / day


For truck crew, equip cost / day
Total truck crew cost / day

$144.00
$324.31
$468.31

Bare cost per day


Production per day
Bare Cost per CY
Total bare cost
Cost per day incl OH&P
Bare Cost per CY
Total bare cost

$2,368.62
680 CY
$3.48
$41,799.26
$2,887.64
$4.25
$50,958.30

Labor Hours Unit


Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P
0.015 B.C.Y.
$0.00
$99.72
$218.83
$318.55
$396.11
ssume the backhoe and crew have other work to do in the project.

rger job that will last 2 weeks

Labor Hours Unit


0.027 B.C.Y.

Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P
$0.00
$174.51
$229.91
$404.42
$526.30

Labor Hours Unit


0.08 S.Y.

Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P Zip Code Prefix
$106,027
$5,734
$567
$112,329
$125,440
203

331

ume one week

small. That's because most of the cost is in materials

Labor Hours Unit


0.168 L.F.
3.2 Ea.

Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P Zip Code Prefix
$8,566
$3,000
$1,968
$13,533
$16,168
203
$936
$660
$436
$2,032
$2,520
203
$9,502
$3,660
$2,404
$15,565
$18,688

Labor Hours Unit


0.018 B.C.Y.
0.02 B.C.Y.

Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P Zip Code Prefix
$0.00 $5,900.00
$24,800.00 $30,700.00
$36,200.00
371
$0.00 $6,700.00
$28,200.00 $34,900.00
$41,400.00
371

Labor Hours Unit


0.02

Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P
$0.00 $6,166.67
$25,933.33 $32,100.00
$37,933.33

oper / hour
$84.60
$53.40

Labor Hours Unit


0.018 B.C.Y.
0.02 B.C.Y.

Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P Zip Code Prefix
$0.00 $5,900.00
$24,800.00 $30,700.00
$36,200.00
371
$0.00 $6,700.00
$28,200.00 $34,900.00
$41,400.00
371

Labor Hours Unit


0.019

Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P
$0
$6,380
$26,840
$33,220
$39,320

or

Total cost / day


$1,106.80
$1,240.70
$2,347.50

Total cost / day


$1,660.20
$1,240.70
$2,900.90

85 CY / hr

This cost is not yet adjusted for City

This cost is not yet adjusted for City

or

Total cost / day


$1,660.20
$1,240.70
$2,900.90

Total cost / day


$2,213.60
$1,240.70
$3,454.30

85 CY / hr

This cost is not yet adjusted for City

This cost is not yet adjusted for City

CI for equipment in Columbia, SC is 99.3%

Union

2006

U10258

Type
Union

Release Note
2006

SKey
U13133

MFFlag
2

Type
Union
Union

Release Note
2006
2006

SKey
U16531
U16533

MFFlag

Type
Union
Union

Release Note
2006
2006

SKey
U10464
U10465

MFFlag

2
2

2
2

Type
Union
Union

Release Note
2006
2006

SKey
U10464
U10465

MFFlag
2
2

Exercise 1
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost

$225,000.00
$1,327.50
$13,500.00
$239,827.50
$0.00
$239,827.50
$0.00
$239,827.50

NA

225 HP - Diesel
55.00%
83.33%
5 Years
Hours
1,700
$3.30 Gallon
$12.00 Gallon
7 Gallon
4 Shop hour
$90.00 per shop hour
110 Hours
75% of annual depreciation cost

Average value P

$143,896.50

Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year

$47,965.50
$35,974.13
$14,389.65
$6,800.00
$105,129.28

Fixed Cost / hour

$61.84

Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour

$13.61
$4.04
$2.02
NA
NA
$19.67

Total cost per hour

$81.51

Exercise 2
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost

$225,000.00
$1,327.50
$13,500.00
$239,827.50
$20,000.00
$219,827.50
$0.00
$219,827.50

NA

225 HP - Diesel
55.00%
83.33%
5 Years
Hours
1,700
$3.30 Gallon
$12.00 Gallon
7 Gallon
4 Shop hour
$90.00 per shop hour
110 Hours
90% of annual depreciation cost

Average value P

$151,896.50

Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year

$43,965.50
$39,568.95
$15,189.65
$6,800.00
$105,524.10

Fixed Cost / hour

$62.07

Operating Cost
Fuel
Oil
Other lubricant

$13.61
$4.04
$2.02

Tire depreciation
Tire repair
Total operating cost / hour
Total cost per hour
Exercise 3
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost

NA
NA
$19.67
$81.74

$225,000.00
$1,327.50
$13,500.00
$239,827.50
$0.00
$239,827.50
$10,000.00
$229,827.50
225
55.00%
83.33%
5
4,500
1,700
$3.30
$12.00
7
4
$90.00
110
75%

Average value P

$143,896.50

Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year

$45,965.50
$34,474.13
$14,389.65
$6,800.00
$101,629.28

Fixed Cost / hour


Operating Cost

$59.78

HP - Diesel

Years
Hours
Gallon
Gallon
Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost

Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour

$13.61
$4.04
$2.02
$2.22
$0.44
$22.33

Total cost per hour

$82.12

Exercise 4
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost

$225,000.00
$1,327.50
$13,500.00
$239,827.50
$20,000.00
$219,827.50
$10,000.00
$209,827.50
225
55.00%
83.33%
5
4,500
1,700
$3.30
$12.00
7
4
$90.00
110
90%

Average value P

$151,896.50

Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year

$41,965.50
$37,768.95
$15,189.65
$6,800.00
$101,724.10

HP - Diesel

Years
Hours
Gallon
Gallon
Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost

Fixed Cost / hour

$59.84

Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour

$13.61
$4.04
$2.02
$2.22
$0.44
$22.33

Total cost per hour

$82.17

Exercise 5
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
Average value P
Ownership Expenses
Depreciation
Maintenance
Investment

$225,000.00
$1,327.50
$13,500.00
$239,827.50
$0.00
$239,827.50
$0.00
$239,827.50

NA

225 HP - Diesel
55.00%
83.33%
5 Years
Hours
1,500
$3.30 Gallon
$12.00 Gallon
7 Gallon
4 Shop hour
$90.00 per shop hour
110 Hours
75% of annual depreciation cost
$143,896.50

$47,965.50
$35,974.13
$14,389.65

Insurance, etc.
Total per year

$6,800.00
$105,129.28

Fixed Cost / hour

$70.09

Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour

$13.61
$4.04
$2.02
NA
NA

Total cost per hour


Exercise 6
Total purchase cost of the equipment
Part a

Part b

Use Double-Declining Balance Method


Expected life

$19.67
$89.75

$239,827.50

5 Years

Value at beginning of 1st year


Depreciation of 1st year
Value at beginning of 2nd year
Depreciation of 2nd year
Value at beginning of 3rd year
Depreciation of 3rd year
Value at beginning of 4th year
Depreciation of 4th year
Value at beginning of 5th year
Depreciation of 5th year
Value at the end of 5th year

$239,827.50
$95,931.00
$143,896.50
$57,558.60
$86,337.90
$34,535.16
$51,802.74
$20,721.10
$31,081.64
$12,432.66
$18,648.99

Sum-of-the-year-digit method
Value at beginning of 1st year
Depreciation of 1st year
Value at beginning of 2nd year
Depreciation of 2nd year
Value at beginning of 3rd year
Depreciation of 3rd year
Value at beginning of 4th year
Depreciation of 4th year

$239,827.50
$79,942.50
$159,885.00
$63,954.00
$95,931.00
$47,965.50
$47,965.50
$31,977.00

Value at beginning of 5th year


Depreciation of 5th year
Value at the end of 5th year
Part c

$15,988.50
$15,988.50
$0.00

Double Declining Balance with Conversion to Straight-Line Depreciation


Straight-Line Depreciation per year
$47,965.50
Value at beginning of 1st year
$239,827.50
Depreciation of 1st year
$95,931.00
Value at beginning of 2nd year
$143,896.50
Depreciation of 2nd year
$57,558.60
Value at beginning of 3rd year
$86,337.90
Depreciation of 3rd year
$34,535.16 Don't use this depreciation. Convert to SL
Depreciation of 3rd year - SL
$28,779.30
Value at beginning of 4th year
$57,558.60
Depreciation of 4th year
$28,779.30
Value at beginning of 5th year
$28,779.30
Depreciation of 5th year
$28,779.30
Value at the end of 5th year
$0.00

Part (d Not available. Drop


Exercise 7
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change

$200,000.00
$1,430.00
$13,500.00
$214,930.00
$0.00
$214,930.00
$0.00
$214,930.00

NA

300 HP - Diesel
55.00%
83.33%
6 Years
Hours
1,500
$2.50 Gallon
$9.00 Gallon
8 Gallon
5 Shop hour
$70.00 per shop hour

Time between oil changes


Maintenance cost

120 Hours
75% of annual depreciation cost

Average value P

$125,375.83

Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year

$35,821.67
$26,866.25
$13,791.34
$6,500.00
$82,979.26

Fixed Cost / hour

$55.32

Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour

$13.75
$3.52
$1.76
NA
NA
$19.03

Total cost per hour

$74.34

Exercise 8
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil

$200,000.00
$1,430.00
$13,500.00
$214,930.00
$30,000.00
$184,930.00
$0.00
$184,930.00

NA

300 HP - Diesel
55.00%
83.33%
6 Years
Hours
1,500
$2.50 Gallon
$9.00 Gallon

Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost

8
5
$70.00
120
90%

Average value P

Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost

$137,875.83

Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year

$30,821.67
$27,739.50
$15,166.34
$6,500.00
$80,227.51

Fixed Cost / hour

$53.49

Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
Total cost per hour
Exercise 9
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires

$13.75
$3.52
$1.76
NA
NA
$19.03
$72.51

$200,000.00
$1,430.00
$13,500.00
$214,930.00
$0.00
$214,930.00
$15,000.00
$199,930.00
300 HP - Diesel
55.00%
83.33%
6 Years
6,000 Hours

Operating hours / year


Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
Average value P
Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year
Fixed Cost / hour

1,500
$2.50
$9.00
8
5
$70.00
120
75%

Gallon
Gallon
Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost

$125,375.83

$33,321.67
$24,991.25
$13,791.34
$6,500.00
$78,604.26
$52.40

Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour

$13.75
$3.52
$1.76
$2.50
$0.38
$21.90

Total cost per hour

$74.30

Exercise 10
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor

$200,000.00
$1,430.00
$13,500.00
$214,930.00
$25,000.00
$189,930.00
$15,000.00
$174,930.00
300 HP - Diesel
55.00%

Effective time factor


Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
Average value P
Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year
Fixed Cost / hour

83.33%
6
6,000
1,500
$2.50
$9.00
8
5
$70.00
120
90%
$135,792.50

$29,155.00
$26,239.50
$14,937.18
$6,500.00
$76,831.68
$51.22

Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour

$13.75
$3.52
$1.76
$2.50
$0.38
$21.90

Total cost per hour

$73.12

Exercise 11
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires

$200,000.00
$1,430.00
$13,500.00
$214,930.00
$0.00
$214,930.00
$0.00
$214,930.00

Years
Hours
Gallon
Gallon
Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost

Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost

NA

Average value P

300 HP - Diesel
55.00%
83.33%
6 Years
Hours
1,200
$2.50 Gallon
$9.00 Gallon
8 Gallon
5 Shop hour
$70.00 per shop hour
120 Hours
75% of annual depreciation cost
$125,375.83

Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year

$35,821.67
$26,866.25
$13,791.34
$6,500.00
$82,979.26

Fixed Cost / hour

$69.15

Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour

$13.75
$3.52
$1.76
NA
NA

Total cost per hour


Exercise 12
Total purchase cost of the equipment
Salvage value
Part a

Use Double-Declining Balance Method


Expected life

$19.03
$88.17

$214,930.00
$30,000.00

6 Years

Value at beginning of 1st year


Depreciation of 1st year
Value at beginning of 2nd year
Depreciation of 2nd year
Value at beginning of 3rd year
Depreciation of 3rd year
Value at beginning of 4th year
Depreciation of 4th year
Value at beginning of 5th year
Depreciation of 5th year
Value at the end of 5th year
Depreciation of 6th year
Value at the end of 6th year
Part b

Part c

Sum-of-the-year-digit method
Value at beginning of 1st year
Depreciation of 1st year
Value at beginning of 2nd year
Depreciation of 2nd year
Value at beginning of 3rd year
Depreciation of 3rd year
Value at beginning of 4th year
Depreciation of 4th year
Value at beginning of 5th year
Depreciation of 5th year
Value at the end of 5th year
Depreciation of 6th year
Value at the end of 6th year

$214,930.00
$85,972.00
$128,958.00
$51,583.20
$77,374.80
$30,949.92
$46,424.88
$18,569.95 Since this depreciation puts the value of the equipm
$27,854.93 Then use 4th year depreciation of $16,424.88 so th
$0.00 end of the 4th year / beginning of the 5th year will
is allowed
$0.00

$214,930.00
$61,408.57
$153,521.43
$51,173.81
$102,347.62
$40,939.05
$61,408.57
$30,704.29
$30,704.29
$20,469.52
$10,234.76
$10,234.76
$0.00

Not available. Drop

Exercise 13
Hourly oper cost Rent / day
Rent / week
$38.75
$895.00
$2,690.00
$14,275.00
Cost / hour

Part a

Use Means item 01 54 33 20 3300


Total cost

Part b

Total cost

$4,240.00

Cost / hour

Part c

Total cost

$1,205.00

Cost / hour

Part d

Total cost

$3,930.00

Cost / hour

Part e

Total cost

$13,035.00

Cost / hour

Exercise 14
Use Means item 01 54 33 20 5200
Part a Total cost - one month rental
Total cost - three week rental

Hourly oper cost Rent / day


Rent / week
$57.25
$1,675.00
$5,010.00
$21,412.00
Cost / hour
$22,358.00
Cost / hour

Part b

Total cost

$6,384.00

Cost / hour

Part c

Total cost

$2,133.00

Cost / hour

Part d

Total cost

$7,300.00

Cost / hour

Part e

Total cost

$9,145.00

Cost / hour

preciation. Convert to SL

iation puts the value of the equipment under the $30,000 salvage value
r depreciation of $16,424.88 so the value of the equipment at the
ar / beginning of the 5th year will be $30,000. No more depreciation

Rent / month
$8,075.00
$89.22
$106.00
$150.63

$122.81
$101.84
Rent / month
$15,000.00
$191.18 Use one month rental
$199.63
$266.00 This would be slightly cheaper than renting 3 days
$266.63
$182.50
$152.42

Exercise 1
Qty

CSI Number
40,000 1719700010

Assume 5% annual inflation


Change the year of construction to 2010
If we use 25th percentile cost, then total cost
If we use median cost, then total cost
Exercise 2
Qty
40,000

CSI Number
1719703100

Assume 5% annual inflation


Change the year of construction to 2010
Use median cost
Exercise 3
Use 75th percentile cost
Adjustment for inflation
Exercise 4
Qty

CSI Number
277,200
1719100020
13,200
1719100010
The answers were listed both for SF and CF units. Probably, it is more reliable to use the CF answer
Total cost
$2,536,380

Exercise 5
Use median
13,200
13,200
13,200
Exercise 6
Total cost
Exercise 7
Qty

1719102720
1719102770
1719102900

$3,209,330

CSI Number
17,500
1713400010

Total cost

$542,500

Exercise 8
Total cost

$805,000

Exercise 9
17,500
1713400100
We can use a number between $61,425 and 112,000, perhaps closer to the $112,000 number

Exercise 10
Qty

CSI Number
17,500
1713400010
The point here is to demonstrate the huge difference merely because of location

Exercise 11
Qty
200

CSI Number
1718009000

Total cost
Total cost

$5,980,000
$7,820,641

Exercise 12
The cost per SF is $113
Then assume the total area
Using the number above, we estimate:
Qty
CSI Number
52,920.00
1718000500
52,920.00
1718001800
Use the median
Exercise 13
Qty

CSI Number
200
1718009000
assume 5% annual inflation
Total cost
$6,740,000
Total cost
$8,814,568

Exercise 14
Total area
165000
Qty
CSI Number
165,000.00
1710300010
assume 5% annual inflation
Total cost
$22,275,000
Total cost
$27,075,402
Exercise 15
Method 1 calculated the cost per SF. Method 2 calculates the cost per apartment
Qty
CSI Number
165,000.00
1710303100
150
1710309500
Take an answer in between the two numbers, say $4,500,000
Adjustment for inflation
$5,469,778
Exercise 16
Qty
CSI Number
165,000.00
1710300010
assume 5% annual inflation
Total cost
$15,757,500
Total cost
$19,153,340

Description
Warehouses & Storage Buildings

Unit
S.F.

r of construction to 2010
ercentile cost, then total cost
n cost, then total cost

Description
Warehouses & Storage Buildings Total M & E

1/4
$1,520,000

2006 cost
$1,520,000
$2,180,000

Unit
S.F.

r of construction to 2010

1/4
$238,000

2006 cost
$366,000

$3,080,000 2006 cost


$3,743,759 2010 cost

Description
Theaters Total Project Costs
Theaters
re listed both for SF and CF units. Probably, it is more reliable to use the CF answer

Theaters Plumbing
Theaters HVAC
Theaters Electrical

Unit
C.F.
S.F.

1/4
$1,164,240
$1,201,200

Unit
S.F.
S.F.
S.F.

1/4

Unit
S.F.

1/4

$39,996
$116,160
$104,940

For 2012 construction, assuming 4% annual inflation

Description
Factories

$542,500

Keep in mind this is only for the structure. Equipment is not included

Factories Site Work


umber between $61,425 and 112,000, perhaps closer to the $112,000 number

S.F.

$61,425

Description
Factories
s to demonstrate the huge difference merely because of location

Unit
S.F.

1/4

Description
Schools Vocational Per Pupil Total Cost

Unit
Ea.

1/4
$2,220,000

Using 2006 cost


Using early 2012 cost

Keep in mind these are US, not Canadian, dollars

52,920 SF

er above, we estimate:
Description
Schools Vocational Masonry
Schools Vocational Equipment

Description
Schools Vocational Per Pupil Total Cost

$988,750

This number can be approaximately

Unit
S.F.
S.F.

1/4

Unit
Ea.

1/4
$2,500,000

Unit
S.F.

1/4
$18,315,000

Unit
S.F.
Apt.

1/4
$3,795,000
$3,765,000

Unit
S.F.

1/4
$13,035,000

$248,724
$127,008

Using 2006 cost


Using early 2012 cost

SF
Description
Apartments High Rise (8-24 Story)
Using 2006 cost
Using 2010 cost

ated the cost per SF. Method 2 calculates the cost per apartment
Description
Apartments High Rise (8-24 Story) Total Project M & E
Per Apartment Unit Apartments High Rise (8-24 Story) Total Cost M & E
in between the two numbers, say $4,500,000
say $5.5m

Description
Apartments High Rise (8-24 Story)
Using 2006 cost
Using 2010 cost

Median
3/4
$2,180,000
$3,080,000

2010 cost
$1,847,570
$2,649,804

Median
3/4
$366,000
$798,000

2010 cost
$444,875

Median
3/4
$1,732,500
$2,536,380
$1,491,600
$2,270,400

Median
3/4
$43,428
$176,880
$141,240
$174,900
$141,240
$290,400

Median
3/4
Zip Code Prefix
Type
$805,000
$1,233,750
324 Union

$112,000

$177,625

324 Union

Release
2006

2006

Median
3/4
Zip Code Prefix
Type
$1,478,750
$2,275,000
101 Union

Release
2006

Median
3/4
Zip Code Prefix
Type
$5,980,000
$8,920,000 C31
Union

Release
2006

hese are US, not Canadian, dollars

his number can be approaximately calculated by dividing the cost per pupil by the cost per SF
Median
3/4
Zip Code Prefix
Type
$613,872
$939,330 C31
Union
$179,928
$457,758 C31
Union

Release
2006
2006

Median
3/4
Zip Code Prefix
Type
$6,740,000 $10,100,000
941 Union

Release
2006

Median
3/4
Zip Code Prefix
Type
$22,275,000 $25,410,000
101 Union

Release
2006

Median
3/4
Zip Code Prefix
Type
$4,785,000
$5,775,000
101 Union
$4,290,000
$4,545,000
101 Union

Release
2006
2006

Median
3/4
Zip Code Prefix
Type
$15,757,500 $18,150,000
461 Union

Release
2006

S-ar putea să vă placă și