Documente Academic
Documente Profesional
Documente Cultură
Reinforcement for the suspended slab: assume #6@12" in the short span and #5@18" in the long direction for shrinkage
Calculating the quantities
1 Slab on Grade
Area
Volume
Edge forms
2 Suspended slab
Area / floor
Formwork / floor
Formwork all
Structural rebar
Shrinkage rebar
Total rebar
Volume
3 Footings
Volums / each
Volums all
Forms / each
Forms all
Rebar / each
Rebar Total
4 Short beams
Forms / each
Forms all
Volums / each
Volums all
Upper rebar / each
Lower reabr / each
Total No. 6 / each
Total No. 6
Stirrups / each
Stirrups / Beam
Stirrups all short beams
All rebar
5 Long beams
Forms / each
Forms all
Volums / each
Volums all
Upper rebar / each
Lower reabr / each
9,000.00 SF
166.67 CY
390.00 LF
8,500.00
8,760.00
26,280.00
44,358.67
20,111.00
87,602.49
43.80
629.63
1.19
33.19
32.00
896.00
36.67
1,026.67
2,741.20
1.37
SF
SF
SF
LF - No. 6
LF - No. 5
LB
Ton
CY
Added edges
The factor 0.94444 represents the the net concrete area out of the to
concrete area was written as 120' X 75' X 0.944444 rather than 8,50
CY
CY
SF
SF
LF
LF
LB
Ton
225.00
8,550.00
2.78
105.56
238.00
248.00
486.00
27,738.94
13.87
4.00
404.00
5,772.35
2.89
16.76
SF
SF
CY
CY
LF - No. 6
LF - No. 6
LF - No. 6
LB
Ton
LF - No. 3
LF - No. 3
LB
Ton
Ton
640.00
7,360.00
13.58
156.17
734.00
804.00
SF
SF
CY
CY
LF - No. 8
LF - No. 8
The duplication in volume as a result of the small and large beam int
Added 4' for splice laps and end hooks
Added 4' for splice laps and end hooks
The duplication in volume as a result of the small and large beam int
Added 8' for splice laps and end hooks
Added 8' for splice laps and end hooks
1,538.00
47,224.29
23.61
7.00
847
6,506.65
3.25
LF - No. 6
LB
Ton
LF - No. 4
LF - No. 4
LB
Ton
6 Columns
Forms / each
Forms all
Volume / each
Volume all
Rebar - No. 10
100.00 SF
8,400.00 SF
1.85 CY
155.56 CY
20,160.00 LF
Assumed total length is 15' per bar
86,748.48 LB
43.37 Ton
Stirrups / each
6.33 LF - No. 4
Stirrups all
6,916.00 LF - No. 4
4,619.89 LB
2.31 Ton
Note: For formwork and concrete, the length of the column was taken as 12'-6", which represents the length to the bottom
Note: The drawing at the top of page 70 shows continuation of the columns on the top of the roof slab. This is an error.
Columns stop at the roof slab. If the building design took in consideration the possibility of adding future floors, the rebar
would have stuck out of the roof slab to offer continuation with future columns. This assumption was NOT taken in consid
7 Parapets
perimeter length
perimeter area
390.00 LF
1,170.00 SF
1,316 Blocks
e the net concrete area out of the total area, i.e. 8,500 SF / 9,000 SF, so the total
0' X 75' X 0.944444 rather than 8,500 SF
Exercise 4: Columns
Qty
CSI Number
1 8,400.00
31113256650
2
2.31
32110600200
3
43.37
32110600250
4
155.56
33105350200
5
155.56
33105700800
Exercise 5: Footings
1
33.19
33105702450
2
33.19
33105350200
3
1.37
32110600550
4
896
31113455150
In the table above, we used the "under 1 CY" for concrete placement. If we use the average between "under 1 CY" and "over 5
Exercise 5: Footings (alternate solution)
33.19
33105702450
33.19
33105702650
1
33.19
33105702550
2
33.19
33105350200
3
1.37
32110600550
4
896
31113455150
Exercise 6: SOG
Qty
1
2
3
4
5
390
90
166.67
166.67
90
CSI Number
31113651100
32205500700
33105350200
33105704550
72610100900
Item 4 above is an interpolation between the 2 items below: one for 4" thick and one for over 6" thick
166.67
33105704350
166.67
33105704650
Exercise 7: CMU
1 1,170.00
42210240200
Cost per CY
CCI, Equip., Frankfort, KY
Qty
CSI Number
1 26,280.00
31113351150
2
43.8
32110600400
3
629.63
33105350200
4
629.63
33105701500
Rebar
Crew C2
1
4
1
Qty
CSI Number
1 26,280.00
31113351150
2
43.8
32110600400
3
629.63
33105350200
4
629.63
33105701500
629.63
33105701500
1
2
3
4
5
Qty
CSI Number
8,400.00
31113256650
2.31
32110600200
43.37
32110600250
155.56
33105350200
155.56
33105700800
Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals
Description
C.I.P. concrete forms, beams and girders, interior, plywood, 12" wide, 4 use, includes shoring, erecting, bracing, stripping and c
Reinforcing steel, in place, beams and girders, #3 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, beam, small, elevated, pumped, includes vibrating, excludes material
Totals
Description
C.I.P. concrete forms, beams and girders, interior, plywood, 24" wide, 4 use, includes shoring, erecting, bracing, stripping and c
Reinforcing steel, in place, beams and girders, #3 to #7, A615, grade 60, incl access. Labor
Reinforcing steel, in place, beams and girders, #8 to # 18, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, beam, large, elevated, pumped, includes vibrating, excludes material
Totals
Description
C.I.P. concrete forms, column, square, plywood, 24" x 24", 4 use, includes erecting, bracing, stripping and cleaning
Reinforcing steel, in place, columns, #3 to #7, A615, grade 60, incl access. Labor
Reinforcing steel, in place, columns, #8 to #18, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, column, square or round, pumped, 24" thick, includes vibrating, excludes material
Totals
Structural concrete, placing, spread footing, pumped, under 1 C.Y., includes vibrating, excludes material
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Reinforcing steel, in place, footings, #8 to #18, A615, grade 60, incl access. Labor
C.I.P. concrete forms, footing, spread, plywood, 4 use, includes erecting, bracing, stripping and cleaning
Totals
used the "under 1 CY" for concrete placement. If we use the average between "under 1 CY" and "over 5 CY", we get:
(alternate solution)
Structural concrete, placing, spread footing, pumped, under 1 C.Y., includes vibrating, excludes material
Structural concrete, placing, spread footing, pumped, over 5 C.Y., includes vibrating, excludes material
Structural concrete, placing, spread footing, pumped, avg. 1-5 C.Y., includes vibrating, excludes material
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Reinforcing steel, in place, footings, #8 to #18, A615, grade 60, incl access. Labor
C.I.P. concrete forms, footing, spread, plywood, 4 use, includes erecting, bracing, stripping and cleaning
Description
C.I.P. concrete forms, slab on grade, bulkhead with keyway, wood, 6" high, 4 uses, includes erecting, bracing, stripping and cle
Welded wire fabric, sheets, 4 x 4 - W4 x W4 (4 x 4) 85 lb. per C.S.F., A185
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, slab on grade, pumped, 4"-6" thick, includes vibrating, excludes material
Building Paper, polyethylene vapor barrier, standard, .006" thick, 9' x 400' roll
Totals
interpolation between the 2 items below: one for 4" thick and one for over 6" thick
Structural concrete, placing, slab on grade, pumped, 4" thick, includes vibrating, excludes material
Structural concrete, placing, slab on grade, pumped, over 6" thick, includes vibrating, excludes material
Concrete masonry unit (CMU), exterior, tooled joints both sides, normal weight, 2000 psi, 8" x 8" x 16", includes mortar and hor
quip., Frankfort, KY
Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals
Rodman
Carpenter foreman
Carpenter
Laborer
Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals
Description
C.I.P. concrete forms, elevated slab, flat plate, plywood, to 15' high, 4 use, includes shoring, erecting, bracing, stripping and cle
Reinforcing steel, in place, elevated slabs, #4 to #7, A615, grade 60, incl access. Labor
Structural concrete, ready mix, normal weight, 3500 psi, includes material only
Structural concrete, placing, elevated slab, pumped, 6" to 10" thick, includes vibrating, excludes material
Totals
Crew
C2
4 Rodm
C20
Crew
C2
4 Rodm
C20
Crew
C2
4 Rodm
4 Rodm
C20
Crew
C1
4 Rodm
4 Rodm
C20
C20
4 Rodm
C1
65
3.6
415
0.985 C.Y.
C.Y.
8.889 Ton
0.077 SFCA
$0.00
$2,738.18
$897.35
$501.76
$4,137.29
$637.25
$0.00
$349.35
$1,335.04
$2,321.64
$393.30
$0.00
$0.00
$0.00
$393.30
$1,030.55
$2,738.18
$1,246.70
$1,836.80
$6,852.23
0.985 C.Y.
0.427 C.Y.
0.706 C.Y.
C.Y.
8.889 Ton
0.077 SFCA
$0.00
$0.00
$0.00
$2,738.18
$897.35
$501.76
$4,137.29
$637.25
$277.14
$457.20
$0.00
$349.35
$1,335.04
$2,141.59
$393.30
$170.93
$282.12
$0.00
$0.00
$0.00
$282.12
$1,030.55
$448.07
$739.31
$2,738.18
$1,246.70
$1,836.80
$6,560.99
C20
C20
C20
4 Rodm
C1
65
150
107.5
3.6
415
Crew
C1
2 Rodm
C20
1 Carp
C20
C20
130
185
0.492 C.Y.
0.346 C.Y.
$0.00
$0.00
$1,608.37
$1,133.36
$983.35
$693.35
$2,591.72
$1,826.70
D8
360
0.111 S.F.
$3,077.10
$3,088.80
$0.00
$6,165.90
This is an additional
$549.79
$36.51
$586.30
$3.66
103.50%
Crew
C2
4 Rodm
C20
Crew
C2
4 Rodm
C7
Ea
$16.00
$14.00
$17.00
$19.00
Total / day
$20.00
$640.00
$640.00
$21.00
$18.00
$14.00
$168.00
$576.00
$112.00
$856.00
Total / day
Total / day
Crew
C2
4 Rodm
C20
Crew
C2
4 Rodm
Total / day
$128.00
$560.00
$136.00
$152.00
$976.00
C20
128
0.5 C.Y.
$0.00
$120,623
$6,217.60
$79,309
$3,785.65
$3,786
$10,003.25
$203,717
So, crews will work 60 hour. Effective hours = 60*0.925= 55.5. Pay hours = 40 + 20*1.5 = 70 hours
Crew
C2
4 Rodm
C20
Crew
C1
C1
$0.68
$2.54
Crew
C1
4 Rodm
4 Rodm
C20
Crew
C1
4 Rodm
4 Rodm
C20
Release Note
2006
2006
2006
2006
SKey
U22130
U22815
U23107
U23573
MFFlag
Release Note
2006
2006
2006
2006
SKey
U22019
U22794
U23107
U23556
MFFlag
Release Note
2006
2006
2006
2006
2006
SKey
U22027
U22794
U22798
U23107
U23559
MFFlag
Release Note
2006
2006
2006
2006
2006
SKey
U22102
U22800
U22805
U23107
U23565
MFFlag
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
$1,427.17
$3,020.29
$1,575.50
$2,625.28
$8,648.24
406
406
406
406
Union
Union
Union
Union
2006
2006
2006
2006
U23586
U23107
U22824
U22260
2
2
2
2
$1,427.17
$615.67
$1,021.42
$3,020.29
$1,575.50
$2,625.28
$8,242.49
406
406
406
406
406
406
Union
Union
Union
Union
Union
Union
2006
2006
2006
2006
2006
2006
U23586
U23590
2
2
2
2
2
2
U23107
U22824
U22260
Release Note
2006
2006
2006
SKey
U22303
U22937
U23107
MFFlag
2006
U33944
2
2
2
$3,583.41
$2,500.05
406 Union
406 Union
2006
2006
U23611
U23614
2
2
$8,073.00
406 Union
2006
U25717
$13,441
$469,446
Exercise 1 & 2
Quantity
10
20
20
Description
Columns, W 831
Columns, W 1287
Columns, W 12120
Ls 6 x 6 x 1/2
Ls 4 x 4 x 3/8
Base Plates, 1" thick
180
150
30
20
Length
15.5
17
17
Total weight of columns:
1.166667
1
2x2
2 x 2.5
Total weight of column details
22
Beams W 1026
18
28
Beams W 1049
22
36
Beams W 1650
24.25
24
Beams W 2193
29.5
Total weight of beams
Total weight of fabricated steel (lbs.):
Total weight of fabricated steel (ton):
CostWorks 2006
Qty
155
340
340
5,586.00
120
100
396
616
873
708
CSI Number
51223176850
51223177200
51223177250
51223400400
51223650500
51223652400
51223750720
51223750900
51223753120
51223754740
Description
Crew
Column, structural, 2-tier, W8x31, A992 steel, incl shopE2
primer, splice plates, bolts
Column, structural, 2-tier, W12x87, A992 steel, incl shopE2primer, splice plates, bolts
Column, structural, 2-tier, W12x120, A992 steel, incl shop
E2 primer, splice plates, bolts
Angle framing, structural steel, 4" and larger, field fabricated,
E3 incl cutting & welding
Steel plate, structural, for connections & stiffenners, 1" T, shop fabricated, incl shop primer
Steel plate, 5 to 50 tons, 48"-60" W, 10'-60' L, 2" T, mill price
Structural steel member, 100-ton project, 1 to 2 story building,
E2
W10x26, A992 steel, shop fabricated,
Structural steel member, 100-ton project, 1 to 2 story building,
E2
W10x49, A992 steel, shop fabricated,
Structural steel member, 100-ton project, 1 to 2 story building,
E2
W16x50, A992 steel, shop fabricated,
Structural steel member, 100-ton project, 1 to 2 story building,
E5
W21x93, A992 steel, shop fabricated,
Totals
Exercise 3
Qty
CSI Number
Description
Crew
121.898
51223770800 Structural steel project, offices, hospitals, etc, 100-ton project,
E6
3 to 6 stories, A992 steel, shop fabricat
Exercise 4
Qty
CSI Number
121.898 51223773400
Exercise 5
Crew E6
Description
Crew
Structural steel project, simple commercial building, 100-ton
E7 project, 1 to 2 stories, A992 steel, shop f
Quantity
3
9
1
1
1
1
Description
Struc Steel Foreman
Struc Steel Worker
Equip Oper (crane)
Welder
Equip Oper Oiler
Equip Oper (light)
$ / hr
$45.00
$43.00
$38.50
$40.00
$36.00
$38.50
Qty
Total
CSI Number
Description
Crew
121.898
51223770800 Structural steel project, offices, hospitals, etc, 100-ton project,
E6
3 to 6 stories, A992 steel, shop fabricat
Strange result: It exactly matches the result of Exercise 3!!!!
Exercise 6
Qty
CSI Number
Description
Crew
121.898
51223770800 Structural steel project, offices, hospitals, etc, 100-ton project,
E6
3 to 6 stories, A992 steel, shop fabricat
Exercise 7
inflation 1985-1995
Our est. inflation
Total bare cost
Total cost + OH&P
0.026793764
0.040190646
$387,259
$459,369
Exercise 8 & 9
No. of joists
Total length
Qty
1,000.00
25
1000 LF
CSI Number
Description
Crew
52119100560 Open web bar joist, 40-ton job lots, 22K9, 11.3 plf, 30' toE750' spans, K series, shop fabricated, incl sho
Exercise 10 & 11
Qty
CSI Number
90
51223773400
51223771100
90
51223773500
90
51223770800
90
Description
Crew
Structural steel project, simple commercial building, 100-ton
E7 project, 1 to 2 stories, A992 steel, shop f
Structural steel project, offices, hospitals, etc, 100-ton project, A992 steel, shop fabricated, incl shop p
Structural steel project, simple commercial building, 100-ton
E9 project, 7 to 15 stories, A992 steel, shop
Structural steel project, offices, hospitals, etc, 100-ton project,
E6
3 to 6 stories, A992 steel, shop fabricat
average of the two items above
Total
Exercise 12
Assume 4% annual inflation
Total bare cost
$274,508.20
18636
396
10296
616
30184
873
43650
708
65844
149974
243795
121.8975
Daily Output
Labor Hours
1,075
985
960
440
0.052
0.057
0.058
0.055
600
550
800
1,000
0.093
0.102
0.07
0.08
Daily Output
7.6
Total $ / day
$1,080.00
$3,096.00
$308.00
$320.00
$288.00
$308.00
Bare Mat.
Bare Labor
Bare Equip.
$5,192.50
$334.80
$238.70
$31,620.00
$802.40
$574.60
$43,520.00
$826.20
$591.60
$3,128.16
$13,238.82
$1,284.78
$4,800.00
$0.00
$0.00
$4,250.00
$0.00
$0.00
$10,890.00
$1,536.48
$1,096.92
$32,032.00
$2,605.68
$1,860.32
$47,142.00
$2,540.43
$1,807.11
$70,446.00
$2,385.96
$1,253.16
$ 253,021
$ 24,271
$ 8,707
Labor Hours
Unit
8.889 Ton
Bare Mat.
Bare Labor
Bare Equip.
$243,796.00
$45,711.75
$16,212.43
Labor Hours
Unit
10.526 Ton
Bare Mat.
Bare Labor
Bare Equip.
$243,796.00
$54,244.61
$29,986.91
14.4
Daily Output
Unit
L.F.
L.F.
L.F.
Lb.
S.F.
Cwt.
L.F.
L.F.
L.F.
L.F.
$5,400.00
Daily Output
Labor Hours
Unit
14.4
8.889 Ton
Daily Output
Labor Hours
14.4
Unit
8.889 Ton
Bare Mat.
Bare Labor
Bare Equip.
$243,796.00
$45,711.75
$16,212.43
Bare Mat.
Bare Labor
Bare Equip.
$243,796.00
$45,711.75
$12,248.89
Equip cost / day =
Daily Output
Labor Hours
Unit
0.04 L.F.
Labor Hours
7.6
Unit
10.526 Ton
8.3
14.4
11.35
15.422 Ton
8.889 Ton
12.1555
2,000
Daily Output
$1,446.98
Bare Mat.
Bare Labor
Bare Equip.
$7,200.00
$1,250.00
$750.00
Bare Mat.
Bare Labor
Bare Equip.
$164,250.00
$26,280.00
$18,810.00
$7,884.00
$189,000.00
$38,700.00
$20,160.00
$164,250.00
$22,140.00
$10,170.00
$176,625.00
$30,420.00
$15,165.00
$176,625.00
$38,304.00
$15,165.00
Bare Total
Total Incl. O&P
Zip Code Prefix
$5,766.00
$6,510.00
$32,997.00
$36,720.00
$44,937.80
$49,980.00
$17,651.76
$28,767.90
$4,800.00
$5,220.00
$4,250.00
$4,650.00
$13,523.40
$16,038.00
$36,498.00
$42,196.00
$51,489.54
$58,054.50
$74,085.12
$83,544.00
$ 285,999
$ 331,680
Type
Union
Union
Union
Union
Union
Union
Union
Union
Union
Union
Release
Note
2006
2006
2006
2006
2006
2006
2006
2006
2006
2006
Bare Total
Total Incl. O&P
Zip Code Prefix
Type
$305,720.18
$362,646.55
145 Union
Release
Note
2006
Bare Total
Total Incl. O&P
Zip Code Prefix
Type
$328,027.52
$393,121.05
145 Union
Release
Note
2006
145
145
145
145
145
145
145
145
145
145
Bare Total
Total Incl. O&P
$305,720.18
$358,736.67
Bare Total
Total Incl. O&P
$301,756.64
$354,376.77
Bare Total
Total Incl. O&P
Zip Code Prefix
Type
$9,200.00
$10,950.00
281 Union
Release
Note
2006
Bare Total
Total Incl. O&P
Zip Code Prefix
Type
$209,340.00
$247,500.00
850 Union
$7,884.00
$12,557.64
$247,860.00
$299,250.00
850 Union
$196,560.00
$229,500.00
850 Union
$222,210.00
$264,375.00
$230,094.00
$276,932.64
Release
Note
2006
2006
2006
SKey
U27239
U27246
U27247
U27259
U27362
U27373
U27421
U27423
U27455
U27479
MFFlag
SKey
U27586
MFFlag
SKey
U27626
MFFlag
2
2
2
2
2
2
2
2
2
2
SKey
U27923
MFFlag
SKey
U27626
MFFlag
U27627
U27586
2
2
2
Exercise 1
Total volume =
1600.000
1.600
0.384
0.182166667
3.052
0.96
0.36433334
1.04
15.43092
Use 16'
2.176
0.11
2040.9444
20.409444
20.409444
Rafters
Ridge board
Roof sheathing
Felt
Shingles
Qty
CSI Number
0.38
0.182
3.052
0.96
0.364
1.04
2.176
0.11
2,040.94
20.41
20.41
61110105060
61110324520
61110182740
61110060600
61110406020
61110406140
61110307060
61110307920
61636100700
75113401100
73113100500
Description
Triple 2" x 12", beams and girders
Wood framing, sills, 2" x 6"
2" x 12" wood joist, framing
18 gauge steel bridging, galvanized, for 2" x 14" joists at 16" O.C.
2" x 4" wood plates, walls
2" x 4" wood studs, 8' high wall
Wood framing, roofs, rafters, to 4 in 12 pitch, 2" x 8"
Wood framing, roofs, ridge boards, #2 or better, 2" x 10"
5/8" CDX plywood sheathing, on walls
Felt, asphalt, #30, 2 square per roll, no mopping
Asphalt Shingles, premium, laminated multi-layered shingles, clas
Totals
Exercise 11
Rafter's length
17.2078
Use 18'
2.448
0.11
2292.246
22.92246
22.92246
Rafters
Ridge board
Roof sheathing
Felt
Shingles
CSI Number
Qty
2.448
0.11
2,292.25
22.92
22.92
Exercise 12
Qty
CSI Number
3.052
61110307060
61110307920
61636100700
75113401100
73113100500
Description
Wood framing, roofs, rafters, to 4 in 12 pitch, 2" x 8"
Wood framing, roofs, ridge boards, #2 or better, 2" x 10"
5/8" CDX plywood sheathing, on walls
Felt, asphalt, #30, 2 square per roll, no mopping
Asphalt Shingles, premium, laminated multi-layered shingles, clas
Description
61110182740 2" x 12" wood joist, framing
Exercise 13
Qty
CSI Number
3.052
Description
61110182740 2" x 12" wood joist, framing
Exercise 14
Qty
CSI Number
3.052
Description
61110182740 2" x 12" wood joist, framing
Board-feet
MBF
MBF
MBF
MBF
CPR
MBF
MBF
feet
MBF
MBF
SF
SQ
SQ
Crew
2 Carp
2 Carp
2 Carp
1 Carp
2 Carp
2 Carp
2 Carp
2 Carp
2 Carp
1 Rofc
1 Rofc
Daily Output
Labor Hours
2.85
0.55
1.75
1.3
0.53
0.92
1.26
0.66
1,050
58
3
5.614
29.091
9.143
6.154
30.189
17.391
12.698
24.242
0.015
0.138
2.667
Unit
M.B.F.
M.B.F.
M.B.F.
C.Pr.
M.B.F.
M.B.F.
M.B.F.
M.B.F.
S.F.
Sq.
Sq.
Bare Mat.
Bare Labor
$209.00
$73.71
$1,678.60
$91.68
$140.14
$400.40
$957.44
$58.30
$918.42
$143.89
$1,561.37
$66.50
$163.80
$869.82
$184.32
$343.98
$566.80
$859.52
$83.05
$959.24
$65.11
$1,551.16
$6,232.95
$5,713.30
feet
MBF
MBF
SF
SQ
SQ
Crew
2 Carp
2 Carp
2 Carp
1 Rofc
1 Rofc
Crew
2 Carp
Daily Output
1.26
0.66
1,050
58
3
Daily Output
Labor Hours
12.698
24.242
0.015
0.138
2.667
Labor Hours
1.75
Unit
M.B.F.
M.B.F.
S.F.
Sq.
Sq.
Bare Mat.
Bare Labor
$1,077.12
$966.96
$58.30
$83.05
$1,031.51
$1,077.36
$161.59
$73.11
$1,753.38
$1,741.92
Unit
9.143 M.B.F.
Bare Mat.
Bare Labor
$1,678.60
$892.93
Crew
2 Carp
Daily Output
Crew
2 Carp
Daily Output
Labor Hours
Unit
9.143 M.B.F.
Bare Mat.
Bare Labor
$1,678.60
$1,087.28
Labor Hours
Unit
9.143 M.B.F.
Bare Mat.
Bare Labor
$1,678.60
$1,097.07
1.75
1.75
Bare Equip.
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Bare Equip.
Bare Total
Total Incl. O&P
Zip Code Prefix
$275.50
$332.50
166
$237.51
$336.70
166
$2,548.42
$3,204.60
166
$276.00
$384.00
166
$484.12
$691.60
166
$967.20
$1,326.00
166
$1,816.96
$2,393.60
166
$141.35
$192.50
166
$1,877.66
$2,530.77
166
$209.00
$268.39
166
$3,112.53
$4,347.33
166
$11,946.25
Release
2006
2006
2006
2006
2006
2006
2006
2006
2006
2006
2006
Type
Union
Union
Union
Union
Union
Release
2006
2006
2006
2006
2006
$16,007.99
$0.00
$0.00
$0.00
$0.00
$0.00
Bare Total
Total Incl. O&P
Zip Code Prefix
$2,044.08
$2,692.80
166
$141.35
$192.50
166
$2,108.87
$2,842.39
166
$234.70
$301.40
166
$3,495.30
$4,881.96
166
$0.00
Bare Total
$2,571.53
Bare Equip.
Type
Union
Union
Union
Union
Union
Union
Union
Union
Union
Union
Union
Bare Equip.
$0.00
Bare Equip.
Bare Total
$2,765.88
Bare Total
$0.00
$2,775.67
Note
Note
SKey
U29991
U30553
U30087
U29791
U30930
U30936
U30464
U30479
U31134
U35439
U34552
MFFlag
SKey
U30464
U30479
U31134
U35439
U34552
MFFlag
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
U30087
927
2147
5
276.84
SF
SF
FT
CY
Exercises 1 & 2
Qty
CSI Number
Description
Crew
Daily Output
277
312316420260 Excavating, bulk bank measure, 2 C.Y. capacity
B12C = 130 C.Y./hour,
1,050
backhoe, hydraulic, crawle
We have to make an assumption here: Since this excavation will take only 2.11 hours, we assume the backhoe and crew have
Otherwise, we may have to pay for the entire day plus mob & demob
Exercise 3
Total Incl. O&P
$393.35
Exercise 4
Use Means item
rent per month
Hourly oper cost
Daily cost
CCI
Bare cost
01 54 33 20 0300
$8,550
$43.70
$777.10
89.30%
$282.79
Exercise 5
Bare cost
$277.00
Exercise 6
The duration of the excavation is just 2.11 hours but we assume it is part of a larger job that will last 2 weeks
Bare cost
$336.95
Exercise 7
Daily labor crew cost
Bare cost
$384.00
$320.13
Exercise 8
Qty
CSI Number
Description
Crew
Daily Output
277
312316420200 Excavating, bulk bank measure, 1 C.Y. capacity
B12A = 75 C.Y./hour, backhoe,
600
hydraulic, crawler
Exercise 9 & 10
Qty
CSI Number
Description
Crew
Daily Output
2,986.67
321823530800 Tennis court, rubber-acrylic base, resilient
B37
pavement, includes base
600
Exercise 11
Total Incl. O&P
Exercise 12
Equip cost / day
CCI
$126,177.00
$161.20
102.30%
Bare cost
$112,582.07
Exercise 13
Bare cost
$113,440.77
Exercise 14
Duration
4.98 say 5 days. Assume one week
Bare cost
$113,481.27
Note in Exercises 13 & 14, the impact of productivity drop and overtime on the cost is very small. That's because most of the co
Exercise 15
Daily labor crew cost
Bare cost
$1,328.00
$113,204.76
Exercise 16
Qty
CSI Number
Description
Crew
Daily Output
688
323113260900 Tennis court fences, 11 ga. wire, 2-1/2" post
B80 10' O.C., 1-5/8" top rail,
19010' high, includes exca
8
323113261000 Chain link fence, tennis courts, 11 ga. wire,
B802-1/2" post 10' O.C., 1-5/8"
10 top rail, add for gate
Totals
Exercise 17 & 18
Qty
CSI Number
Description
Crew
Daily Output
10,000.00
312316501300 Excavation, bulk, bank measure, common
B33D
earth, 1500' haul, 14 C.Y.
800 bucket, self propelled s
10,000.00
312316501350 Excavation, bulk, bank measure, common
B33D
earth, 3000' haul, 14 C.Y.
700 bucket, self propelled s
The above 2 items are for 1,500' and 3,000' haul distance. We need to interpolate
Qty
CSI Number
Description
Crew
Daily Output
10,000.00
312316501320 Excavation, bulk, bank measure, common
B33D
earth, 3000' haul, 14 C.Y.
767 bucket, self propelled s
Exercise 19
Total Incl. O&P
Exercise 20
01 54 33 20 3550
01 54 33 20 4310
$37,927.13
Equipment
Elev scraper, 14 CY
Dozer, 300 HP
1
0.25
rent / mo
$13,500.00
$11,600.00
Bare cost
$26,573.87
Exercise 21
Bare cost
$40,125.00
Exercise 22
Duration
Bare cost
13.04347826 Days
$35,816.04
Exercise 23
say 2 weeks
$ / hr
1 Equip Oper
0.5 Laborer
0.25 Equip Oper
$30.00
$25.00
$30.00
total / day
$240.00
$100.00
$60.00
Total
Bare cost
$400.00
$31,150.72
Exercise 24
Qty
CSI Number
Description
Crew
Daily Output
10,000.00
312316501300 Excavation, bulk, bank measure, common
B33D
earth, 1500' haul, 14 C.Y.
800 bucket, self propelled s
10,000.00
312316501350 Excavation, bulk, bank measure, common
B33D
earth, 3000' haul, 14 C.Y.
700 bucket, self propelled s
The interpolated items is:
Qty
CSI Number
Description
Crew
Daily Output
10,000.00
312316501320 Excavation, bulk, bank measure, common
B33D
earth, 3000' haul, 14 C.Y.
740 bucket, self propelled s
Exercise 25
For the power, shovel, use Means item 31 23 16 42 3750
Crew B12M with daily production
680 CY / day
4.24 minutes
4.24
3.00
0.50
2.00
1.00
10.74
minutes
minutes
minutes
minutes
minutes
minutes
2.53
Case 1: 2 trucks
Shovel capacity
Crew
Truck crew, B34A
Shovel crew, B12M
Total cost
Cost per CY
536.55 CY / day
How many
cost / day ea
2
$553.40
1
$1,240.70
Shovel capacity
Crew
Truck crew, B34A
Shovel crew, B12M
Total cost
Cost per CY
680.00 CY / day
How many
cost / day ea
3
$553.40
1
$1,240.70
$4.38
Case 2: 3 trucks
a) Use 3 trucks
$4.27
b)
Bare cost
80.90%
$3,706.50 per day
$5.45 per CY
Exercise 26
For the power, shovel, use Means item 31 23 16 42 3750
Crew B12M with daily production
680 CY / day
4.24 minutes
4.24
4.50
0.50
3.00
1.00
13.24
minutes
minutes
minutes
minutes
minutes
minutes
3.13
Case 1: 3 trucks
Shovel capacity
Crew
Truck crew, B34A
Shovel crew, B12M
Total cost
Cost per CY
652.80 CY / day
How many
cost / day ea
3
$553.40
1
$1,240.70
Shovel capacity
Crew
Truck crew, B34A
Shovel crew, B12M
Total cost
Cost per CY
680.00 CY / day
How many
cost / day ea
4
$553.40
1
$1,240.70
$4.44
Case 2: 4 trucks
$5.08
a) Use 3 trucks
b)
Bare cost
80.90%
$3,706.50 per day
$5.45 per CY
$252.00
$711.68 CCI for equipment in Columbia, SC is
$963.68
$144.00
$324.31
$468.31
$2,368.62
680 CY
$3.48
$41,799.26
$2,887.64
$4.25
$50,958.30
Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P
$0.00
$174.51
$229.91
$404.42
$526.30
Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P Zip Code Prefix
$106,027
$5,734
$567
$112,329
$125,440
203
331
Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P Zip Code Prefix
$8,566
$3,000
$1,968
$13,533
$16,168
203
$936
$660
$436
$2,032
$2,520
203
$9,502
$3,660
$2,404
$15,565
$18,688
Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P Zip Code Prefix
$0.00 $5,900.00
$24,800.00 $30,700.00
$36,200.00
371
$0.00 $6,700.00
$28,200.00 $34,900.00
$41,400.00
371
Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P
$0.00 $6,166.67
$25,933.33 $32,100.00
$37,933.33
oper / hour
$84.60
$53.40
Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P Zip Code Prefix
$0.00 $5,900.00
$24,800.00 $30,700.00
$36,200.00
371
$0.00 $6,700.00
$28,200.00 $34,900.00
$41,400.00
371
Bare Mat. Bare Labor Bare Equip. Bare Total Total Incl. O&P
$0
$6,380
$26,840
$33,220
$39,320
or
85 CY / hr
or
85 CY / hr
Union
2006
U10258
Type
Union
Release Note
2006
SKey
U13133
MFFlag
2
Type
Union
Union
Release Note
2006
2006
SKey
U16531
U16533
MFFlag
Type
Union
Union
Release Note
2006
2006
SKey
U10464
U10465
MFFlag
2
2
2
2
Type
Union
Union
Release Note
2006
2006
SKey
U10464
U10465
MFFlag
2
2
Exercise 1
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
$225,000.00
$1,327.50
$13,500.00
$239,827.50
$0.00
$239,827.50
$0.00
$239,827.50
NA
225 HP - Diesel
55.00%
83.33%
5 Years
Hours
1,700
$3.30 Gallon
$12.00 Gallon
7 Gallon
4 Shop hour
$90.00 per shop hour
110 Hours
75% of annual depreciation cost
Average value P
$143,896.50
Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year
$47,965.50
$35,974.13
$14,389.65
$6,800.00
$105,129.28
$61.84
Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
$13.61
$4.04
$2.02
NA
NA
$19.67
$81.51
Exercise 2
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
$225,000.00
$1,327.50
$13,500.00
$239,827.50
$20,000.00
$219,827.50
$0.00
$219,827.50
NA
225 HP - Diesel
55.00%
83.33%
5 Years
Hours
1,700
$3.30 Gallon
$12.00 Gallon
7 Gallon
4 Shop hour
$90.00 per shop hour
110 Hours
90% of annual depreciation cost
Average value P
$151,896.50
Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year
$43,965.50
$39,568.95
$15,189.65
$6,800.00
$105,524.10
$62.07
Operating Cost
Fuel
Oil
Other lubricant
$13.61
$4.04
$2.02
Tire depreciation
Tire repair
Total operating cost / hour
Total cost per hour
Exercise 3
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
NA
NA
$19.67
$81.74
$225,000.00
$1,327.50
$13,500.00
$239,827.50
$0.00
$239,827.50
$10,000.00
$229,827.50
225
55.00%
83.33%
5
4,500
1,700
$3.30
$12.00
7
4
$90.00
110
75%
Average value P
$143,896.50
Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year
$45,965.50
$34,474.13
$14,389.65
$6,800.00
$101,629.28
$59.78
HP - Diesel
Years
Hours
Gallon
Gallon
Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
$13.61
$4.04
$2.02
$2.22
$0.44
$22.33
$82.12
Exercise 4
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
$225,000.00
$1,327.50
$13,500.00
$239,827.50
$20,000.00
$219,827.50
$10,000.00
$209,827.50
225
55.00%
83.33%
5
4,500
1,700
$3.30
$12.00
7
4
$90.00
110
90%
Average value P
$151,896.50
Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year
$41,965.50
$37,768.95
$15,189.65
$6,800.00
$101,724.10
HP - Diesel
Years
Hours
Gallon
Gallon
Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost
$59.84
Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
$13.61
$4.04
$2.02
$2.22
$0.44
$22.33
$82.17
Exercise 5
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
Average value P
Ownership Expenses
Depreciation
Maintenance
Investment
$225,000.00
$1,327.50
$13,500.00
$239,827.50
$0.00
$239,827.50
$0.00
$239,827.50
NA
225 HP - Diesel
55.00%
83.33%
5 Years
Hours
1,500
$3.30 Gallon
$12.00 Gallon
7 Gallon
4 Shop hour
$90.00 per shop hour
110 Hours
75% of annual depreciation cost
$143,896.50
$47,965.50
$35,974.13
$14,389.65
Insurance, etc.
Total per year
$6,800.00
$105,129.28
$70.09
Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
$13.61
$4.04
$2.02
NA
NA
Part b
$19.67
$89.75
$239,827.50
5 Years
$239,827.50
$95,931.00
$143,896.50
$57,558.60
$86,337.90
$34,535.16
$51,802.74
$20,721.10
$31,081.64
$12,432.66
$18,648.99
Sum-of-the-year-digit method
Value at beginning of 1st year
Depreciation of 1st year
Value at beginning of 2nd year
Depreciation of 2nd year
Value at beginning of 3rd year
Depreciation of 3rd year
Value at beginning of 4th year
Depreciation of 4th year
$239,827.50
$79,942.50
$159,885.00
$63,954.00
$95,931.00
$47,965.50
$47,965.50
$31,977.00
$15,988.50
$15,988.50
$0.00
$200,000.00
$1,430.00
$13,500.00
$214,930.00
$0.00
$214,930.00
$0.00
$214,930.00
NA
300 HP - Diesel
55.00%
83.33%
6 Years
Hours
1,500
$2.50 Gallon
$9.00 Gallon
8 Gallon
5 Shop hour
$70.00 per shop hour
120 Hours
75% of annual depreciation cost
Average value P
$125,375.83
Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year
$35,821.67
$26,866.25
$13,791.34
$6,500.00
$82,979.26
$55.32
Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
$13.75
$3.52
$1.76
NA
NA
$19.03
$74.34
Exercise 8
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
$200,000.00
$1,430.00
$13,500.00
$214,930.00
$30,000.00
$184,930.00
$0.00
$184,930.00
NA
300 HP - Diesel
55.00%
83.33%
6 Years
Hours
1,500
$2.50 Gallon
$9.00 Gallon
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
8
5
$70.00
120
90%
Average value P
Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost
$137,875.83
Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year
$30,821.67
$27,739.50
$15,166.34
$6,500.00
$80,227.51
$53.49
Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
Total cost per hour
Exercise 9
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
$13.75
$3.52
$1.76
NA
NA
$19.03
$72.51
$200,000.00
$1,430.00
$13,500.00
$214,930.00
$0.00
$214,930.00
$15,000.00
$199,930.00
300 HP - Diesel
55.00%
83.33%
6 Years
6,000 Hours
1,500
$2.50
$9.00
8
5
$70.00
120
75%
Gallon
Gallon
Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost
$125,375.83
$33,321.67
$24,991.25
$13,791.34
$6,500.00
$78,604.26
$52.40
Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
$13.75
$3.52
$1.76
$2.50
$0.38
$21.90
$74.30
Exercise 10
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
Engine Power
Operating factor
$200,000.00
$1,430.00
$13,500.00
$214,930.00
$25,000.00
$189,930.00
$15,000.00
$174,930.00
300 HP - Diesel
55.00%
83.33%
6
6,000
1,500
$2.50
$9.00
8
5
$70.00
120
90%
$135,792.50
$29,155.00
$26,239.50
$14,937.18
$6,500.00
$76,831.68
$51.22
Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
$13.75
$3.52
$1.76
$2.50
$0.38
$21.90
$73.12
Exercise 11
Cost F.O.B.
Shipping
Sales tax
Total
Salvage value
Total without salvage
Tires
Total without salvage and tires
$200,000.00
$1,430.00
$13,500.00
$214,930.00
$0.00
$214,930.00
$0.00
$214,930.00
Years
Hours
Gallon
Gallon
Gallon
Shop hour
per shop hour
Hours
of annual depreciation cost
Engine Power
Operating factor
Effective time factor
Expected Life
Life of tires
Operating hours / year
Cost of diesel fuel
Cost of lubricating oil
Capacity of crankcase
Time needed for oil change
Cost of labor for oil change
Time between oil changes
Maintenance cost
NA
Average value P
300 HP - Diesel
55.00%
83.33%
6 Years
Hours
1,200
$2.50 Gallon
$9.00 Gallon
8 Gallon
5 Shop hour
$70.00 per shop hour
120 Hours
75% of annual depreciation cost
$125,375.83
Ownership Expenses
Depreciation
Maintenance
Investment
Insurance, etc.
Total per year
$35,821.67
$26,866.25
$13,791.34
$6,500.00
$82,979.26
$69.15
Operating Cost
Fuel
Oil
Other lubricant
Tire depreciation
Tire repair
Total operating cost / hour
$13.75
$3.52
$1.76
NA
NA
$19.03
$88.17
$214,930.00
$30,000.00
6 Years
Part c
Sum-of-the-year-digit method
Value at beginning of 1st year
Depreciation of 1st year
Value at beginning of 2nd year
Depreciation of 2nd year
Value at beginning of 3rd year
Depreciation of 3rd year
Value at beginning of 4th year
Depreciation of 4th year
Value at beginning of 5th year
Depreciation of 5th year
Value at the end of 5th year
Depreciation of 6th year
Value at the end of 6th year
$214,930.00
$85,972.00
$128,958.00
$51,583.20
$77,374.80
$30,949.92
$46,424.88
$18,569.95 Since this depreciation puts the value of the equipm
$27,854.93 Then use 4th year depreciation of $16,424.88 so th
$0.00 end of the 4th year / beginning of the 5th year will
is allowed
$0.00
$214,930.00
$61,408.57
$153,521.43
$51,173.81
$102,347.62
$40,939.05
$61,408.57
$30,704.29
$30,704.29
$20,469.52
$10,234.76
$10,234.76
$0.00
Exercise 13
Hourly oper cost Rent / day
Rent / week
$38.75
$895.00
$2,690.00
$14,275.00
Cost / hour
Part a
Part b
Total cost
$4,240.00
Cost / hour
Part c
Total cost
$1,205.00
Cost / hour
Part d
Total cost
$3,930.00
Cost / hour
Part e
Total cost
$13,035.00
Cost / hour
Exercise 14
Use Means item 01 54 33 20 5200
Part a Total cost - one month rental
Total cost - three week rental
Part b
Total cost
$6,384.00
Cost / hour
Part c
Total cost
$2,133.00
Cost / hour
Part d
Total cost
$7,300.00
Cost / hour
Part e
Total cost
$9,145.00
Cost / hour
preciation. Convert to SL
iation puts the value of the equipment under the $30,000 salvage value
r depreciation of $16,424.88 so the value of the equipment at the
ar / beginning of the 5th year will be $30,000. No more depreciation
Rent / month
$8,075.00
$89.22
$106.00
$150.63
$122.81
$101.84
Rent / month
$15,000.00
$191.18 Use one month rental
$199.63
$266.00 This would be slightly cheaper than renting 3 days
$266.63
$182.50
$152.42
Exercise 1
Qty
CSI Number
40,000 1719700010
CSI Number
1719703100
CSI Number
277,200
1719100020
13,200
1719100010
The answers were listed both for SF and CF units. Probably, it is more reliable to use the CF answer
Total cost
$2,536,380
Exercise 5
Use median
13,200
13,200
13,200
Exercise 6
Total cost
Exercise 7
Qty
1719102720
1719102770
1719102900
$3,209,330
CSI Number
17,500
1713400010
Total cost
$542,500
Exercise 8
Total cost
$805,000
Exercise 9
17,500
1713400100
We can use a number between $61,425 and 112,000, perhaps closer to the $112,000 number
Exercise 10
Qty
CSI Number
17,500
1713400010
The point here is to demonstrate the huge difference merely because of location
Exercise 11
Qty
200
CSI Number
1718009000
Total cost
Total cost
$5,980,000
$7,820,641
Exercise 12
The cost per SF is $113
Then assume the total area
Using the number above, we estimate:
Qty
CSI Number
52,920.00
1718000500
52,920.00
1718001800
Use the median
Exercise 13
Qty
CSI Number
200
1718009000
assume 5% annual inflation
Total cost
$6,740,000
Total cost
$8,814,568
Exercise 14
Total area
165000
Qty
CSI Number
165,000.00
1710300010
assume 5% annual inflation
Total cost
$22,275,000
Total cost
$27,075,402
Exercise 15
Method 1 calculated the cost per SF. Method 2 calculates the cost per apartment
Qty
CSI Number
165,000.00
1710303100
150
1710309500
Take an answer in between the two numbers, say $4,500,000
Adjustment for inflation
$5,469,778
Exercise 16
Qty
CSI Number
165,000.00
1710300010
assume 5% annual inflation
Total cost
$15,757,500
Total cost
$19,153,340
Description
Warehouses & Storage Buildings
Unit
S.F.
r of construction to 2010
ercentile cost, then total cost
n cost, then total cost
Description
Warehouses & Storage Buildings Total M & E
1/4
$1,520,000
2006 cost
$1,520,000
$2,180,000
Unit
S.F.
r of construction to 2010
1/4
$238,000
2006 cost
$366,000
Description
Theaters Total Project Costs
Theaters
re listed both for SF and CF units. Probably, it is more reliable to use the CF answer
Theaters Plumbing
Theaters HVAC
Theaters Electrical
Unit
C.F.
S.F.
1/4
$1,164,240
$1,201,200
Unit
S.F.
S.F.
S.F.
1/4
Unit
S.F.
1/4
$39,996
$116,160
$104,940
Description
Factories
$542,500
Keep in mind this is only for the structure. Equipment is not included
S.F.
$61,425
Description
Factories
s to demonstrate the huge difference merely because of location
Unit
S.F.
1/4
Description
Schools Vocational Per Pupil Total Cost
Unit
Ea.
1/4
$2,220,000
52,920 SF
er above, we estimate:
Description
Schools Vocational Masonry
Schools Vocational Equipment
Description
Schools Vocational Per Pupil Total Cost
$988,750
Unit
S.F.
S.F.
1/4
Unit
Ea.
1/4
$2,500,000
Unit
S.F.
1/4
$18,315,000
Unit
S.F.
Apt.
1/4
$3,795,000
$3,765,000
Unit
S.F.
1/4
$13,035,000
$248,724
$127,008
SF
Description
Apartments High Rise (8-24 Story)
Using 2006 cost
Using 2010 cost
ated the cost per SF. Method 2 calculates the cost per apartment
Description
Apartments High Rise (8-24 Story) Total Project M & E
Per Apartment Unit Apartments High Rise (8-24 Story) Total Cost M & E
in between the two numbers, say $4,500,000
say $5.5m
Description
Apartments High Rise (8-24 Story)
Using 2006 cost
Using 2010 cost
Median
3/4
$2,180,000
$3,080,000
2010 cost
$1,847,570
$2,649,804
Median
3/4
$366,000
$798,000
2010 cost
$444,875
Median
3/4
$1,732,500
$2,536,380
$1,491,600
$2,270,400
Median
3/4
$43,428
$176,880
$141,240
$174,900
$141,240
$290,400
Median
3/4
Zip Code Prefix
Type
$805,000
$1,233,750
324 Union
$112,000
$177,625
324 Union
Release
2006
2006
Median
3/4
Zip Code Prefix
Type
$1,478,750
$2,275,000
101 Union
Release
2006
Median
3/4
Zip Code Prefix
Type
$5,980,000
$8,920,000 C31
Union
Release
2006
his number can be approaximately calculated by dividing the cost per pupil by the cost per SF
Median
3/4
Zip Code Prefix
Type
$613,872
$939,330 C31
Union
$179,928
$457,758 C31
Union
Release
2006
2006
Median
3/4
Zip Code Prefix
Type
$6,740,000 $10,100,000
941 Union
Release
2006
Median
3/4
Zip Code Prefix
Type
$22,275,000 $25,410,000
101 Union
Release
2006
Median
3/4
Zip Code Prefix
Type
$4,785,000
$5,775,000
101 Union
$4,290,000
$4,545,000
101 Union
Release
2006
2006
Median
3/4
Zip Code Prefix
Type
$15,757,500 $18,150,000
461 Union
Release
2006