Documente Academic
Documente Profesional
Documente Cultură
Attendance:
Moses Abraham PennDOT Bureau of Aviation (717) 705-1249
Robert Kriner FAA Local Technician (570) 368-1426
Michael Sweet Williamsport ATCT (570) 368-2838
Michael Nedorostek FAA Coordinator (570) 457-5051
Bob Fries Williamsport Regional Airport (570) 368-2444
Jill Byrne L. Robert Kimball and Associates (814) 867-4566
Rick Holes L. Robert Kimball and Associates (814) 472-7700
Background:
On the 5-Year ACIP for Williamsport for FY 2007, there were 2 projects that were
proposed. They were:
However, during a planning session with the FAA in February, Wayne Heibeck
mentioned that Wilmington, DE Airport was to receive a large amount of FAA
Discretionary Funding in FY 2007 for their Runway Safety Area Improvement Projects,
but that they had informed the FAA that they would not be able to use the funding. As a
result, Wayne asked if Williamsport could have their entire Runway and Taxiway
Extension Project designed and bid in time to use this Discretionary Funding. After some
discussion, it was determined that Williamsport would proceed forward with the design in
order to receive bids to utilize this available funding.
The Site Preparation package will consist primarily of placing fill material in the
area where the taxiway extension will be constructed. This will require
approximately 100,000 cubic yards of fill material. The first source for the fill
material will be to remove deposited sediments from Loyalsock Creek between
the Broad Street Bridge and the existing railroad bridge. This is expected to
produce 10,000 to 20,000 cubic yards. The remainder of the fill material will be
obtained from the old Runway 33 borrow area that is currently being used for the
Improve Runway 27 Safety Area Project. Additional work as a part of this
package will include the installation of drainage piping and construction of a
small stormwater detention basin.
The Paving & Lighting package will include paving the new taxiway and
installing medium-intensity taxiway lighting. Additional work will include
construction of a connector taxiway in the current location of Taxiway B.
Concrete pavement from existing Taxiway B will be removed and stockpiled for
later reuse by the Borough of Montoursville for streambank protection along
Loyalsock Creek.
Meeting Discussion:
1. Per FAA requirements, the Runway 27 localizer antenna can be no closer than
600’ from the Runway 9 end. Based on preliminary estimates, it appears that,
with the 350’ extension, the distance between the new end of the runway and the
localizer antenna will be less than 600’. For this reason, it will be necessary to
relocate the localizer antenna. It was suggested that Kimball start discussions
regarding this work with the FAA Harrisburg ADO and then move up the line
from there. Kimball will contact John Carter from the FAA in Harrisburg.
2. Initially, there were plans to not replace the existing VASI for the Runway 9 end
since the entire runway will be worked on in the coming years. However, the
Williamsport ATCT suggested that the VASI be replaced or relocated since it
provides the only visual guidance to Runway 9. As a result, Kimball will include
a new PAPI or GVGI for Runway 9 as a part of the project. It was noted that the
current VASI is offset 10 degrees.
3. Kimball is providing for new REILs for Runway 9 as a part of the project.
Everyone in attendance agreed that this should be done.
4. Currently, the FAA owns and maintains the VASI and REILs. After the project is
completed, ownership of the new PAPI and REILs will be retained by the Airport.
5. The ATCT asked that Kimball keep the VASI in operation as long as possible
during the construction so there will be visual guidance for aircraft using Runway
9.
6. The construction within the localizer critical area was also discussed. The ATCT
indicated that the localizer would be needed during IFR conditions. Kimball
suggested that the construction be allowed during daytime VFR conditions, but, if
IFR conditions were present, that construction would have to occur at night. It
was discussed that the Contractor could be given additional contract time for each
IFR daytime construction period.
7. The addition of a bypass taxiway at the Runway 9 end was discussed. It was
agreed that this would be a good thing to have since, many times, small aircraft
are doing runups on the taxiway prior to takeoff. Having a bypass taxiway would
allow other aircraft to go around the small aircraft, better utilizing the runway.
8. Kimball asked the ATCT if the existing wig-wag lights would be necessary with
the new parallel taxiway. It was decided that the wig-wag lights would not be
necessary because there would be a standard holdline after the parallel taxiway
project was completed.
9. Bob Fries marked the location of many utilities that are within the Runway and
Parallel Taxiway Extension work area. Kimball will show those approximate
locations on the drawings. In addition, the existing Montoursville Borough water
mains were discussed. Bob Fries will meet with Frank Thalman from the
Borough to discuss what work the Borough will want completed as a part of this
project in order to protect the water mains.
10. FAA suggested that multiple spare conduits be installed under the new pavement
to allow for both Airport and FAA electrical cables to be installed.
11. Drawings will need to be sent to PPL for review. There is a PPL main electric
line located near the base of the northern existing fill slope for Runway 9. This
electric line feeds the VASI and the VASI transformer. It was suggested that the
VASI transformer could be put into an electrical vault and extended to the ground
level.
This will allow for the greatest amount of funding flexibility for the FAA.
- FAA Pavement (75-blow Marshall) will be used for the Runway and Taxiway
Paving.
- It is assumed that the Runway 9-27 lighting circuit has available capacity to
handle the additional lighting.
- It is assumed that the Taxiway B lighting circuit has available capacity to handle
the additional lighting.
- At this time, it is not certain as to whether the Runway Distance Remaining signs
on Runway 9-27 will need to be relocated as a part of the Runway 9 Extension
project. This will be coordinated with John Greene and Dennis O’Donnell from
the FAA.
- The existing VASI for Runway 9 will be removed as a part of the Extend Parallel
T/W B to R/W 9 End project and will not be replaced at this time. An ILS System
for R/W 9 is proposed in the future.
Project Schedules: