Sunteți pe pagina 1din 20

FORM OF AGREEMENT FOR THE SUPPLY OF E.H.T. ENERGY This agreement made on the .day of ..

between the Chief Engineer (Transmission- South ) for and on behalf of the Kerala State Electricity Board ( hereinafter referred to as the Board which expression shall , when the context so admits or implies, be deemed to include its successors or assignees as well) of the one part and the General Manager / Managing Director of M/s. The Kerala Minerals and Metals Ltd a company incorporated under the Indian Companies Act 1972 having its registered office at Sangaramangalam, Chavara ( hereinafter referred to as the Consumer) of the other part whereby it is agreed to as follows:1 (a) The Board shall furnish to the consumer and the consumer shall take from the Board all the energy required for operation and lighting the consumers . factory t Sangaramanglam , Chavara up to a total quantity of 12500 kVA ( hereinafter called the Contract Demand) The supply to the consumer shall be in the from of 3 phase alternating current at a frequency of approximately 50 cycles per second . Power up to a maximum of 125000 KVA will be supplied at a voltage of approximately 110000 volts (b) The frequency and pressure of electrical energy at the point of delivery of power to the consumers shall be subject of the fluctuations that are ordinary, usual and incidental to the generation and transmission of electrical energy, but such fluctuations shall not, except owing to extraordinary reasons beyond the control of the board, be more than plus or minus 3 per cent (3%) on the frequency and plus or minus twelve and half percent ( 12 % ) on the pressure. 2 (a) The point of delivery of power at 110000 volts shall be at the consumers side of the 110000 volts. Metering current transformers installed by the board at the cost of the consumer in the out door 110KV switchgear station at the consumers factory premises. (b) The consumer shall provide to the Board free of charges all land or space required for the purpose of erecting the necessary control switchgear and metering equipment and allow the Boards Engineer authorized in this behalf or his authorized representative access to such station at any time of the day or night. ( c) The consumer shall at his own cost provide, install and maintain suitable 110 KV Circuit Breakers complete with protective gear on the consumers side of the Boards outdoor metering current transformers or in his main feeders with settings of the protective relays properly co-ordinate with those of the 110 kv Circuit Breakers of the board. 3 The consumer shall furnish security either by cash or Demand Draft to the extent of two months current charge as fixed by the Chief Engineer ( Ele). This is fixed in the first instance as Rs. 558 lakhs . The consumer shall on demand in writing replenish or enhance within ten day such security in the event of the same being found by the Chief Engineer or his authorized representative to be insufficient exhausted and the decision of the Chief Engineer or his authorized representative in that regard shall be final and conclusive between the parties. A demand for the purpose of this clause shall be sufficient if a notice is sent by registered post giving ten days time to comply with it. The board is at liberty at any time to approximate and apply any security so furnished in or towards payment or satisfactory of all or any amount which shall become due from or owing by the consumers

to the board in respect of supply of energy or otherwise under the agreement. The security shall be in the form of cash or Demand d Draft for an amount equivalent to one months electricity charges ( inclusive of both demand and energy charges) and bank guarantee equivalent to one months electricity charges for the original contract demand. In the event of the consumer failing to replenish or enhance the security even after demand as stated above it shall be lawful for the board to disconnect the service even without any further notice and in that event the board shall not be liable for the loss if any sustained by the consumer on that account. 4. The quantity of electrical power and energy supplied by the Board to the consumer shall be ascertained by means of a meter or meter and current-potential transformers as per the specifications prescribed by the Board shall be provided at the cost of the consumer kept in repair by the calibrated by the Board. When. the meter or meters, current-potential transforms become defective or the meter or meter cease to measure the electrical quantity supplied by the Board , the consumers shall repair them or replace them by correct meter or meters or current potential transformers at the cost of the consumer within one month of the meter or meters becoming defective or ceasing to register the electrical quantity or the current potential transformers becoming defective. 5. The side meter or meters shall at all reasonable times be open to the inspection of the Boards Engineer authorized in this behalf, or his authorized representatives and shall be properly sealed on behalf of both parries and shall not be interfered with by either party except in the presence of the other party or his representative duly authorized in that behalf. 6. (a)The reading of the said meter or meters shall be taken by the accredited representative of both the parties hereto as near as soon as practicable on the last date of each calendar month and recorded. The reading so recorded shall be binding and conclusive between the parties hereto, as the quantity of electrical power and energy supplied under this agreement. The recording of the reading shall be in a card to be attached to such meters shall which shall be open to the inspection of the consumer also. Payment for power and energy supplied shall be made by the consumer according to the recorded reading of the meters and at the rates specified in the schedule attached hereto or other applicable rate. Payment shall be made within fifteen days from the date of receipt of the consumers of the invoice for the power supplied. In default of payment, the consumer is liable to pay interest at 24 %per annum or at such other percentage as fixed by the board from time to time also on this amount. Exact number of days delayed shall be reckoned as the number of days as such for the purpose of calculation if interest. 6 (b) If the consumer fails to remit the dues within the time stipulated in clause 6 (a) it shall be lawful for the Board to cut off the supply of power after giving the notice contemplated in Section 24 of the I.E. Act. In that event it shall also be lawful for the board to adjust the security deposit towards the dues . 7 If the consumer shall at any time consider that any meter is not in proper order for correctly registering the quantity of the supply, he may apply to the Boards Engineer authorized in this behalf for a special test, with a remittance of R. 1,000/-( Rupees one thousand only). On receipt of the application and testing fee, the Board in the presence of the consumer or an agent duly authorized by him, shall cause to test the meter and if during such test the error in the meter is found to exceed the limits of accuracy laid down in the Indian Electricity Rules, 1956, as amended form time to time, the consumers bill shall be adjusted in accordance with the result of the test for the provisos three months from the date of test or defect, unless there is satisfactory evidence to show that the meter was not registering

correctly for a definite period in which case the bills shall be adjusted for such definite period not exceeding six months and the test fee shall be retuned to the consumer. If, however during the test the error in the meter on dispute is found to be within the limits of accuracy laid down in the Indian electricity Rules, 1956, as amended from time to time previous bills shall be confirmed and the test fee shall be forfeited to the Board. Testing as stated above shall be done at the instance of the Board also in which case no testing fee shall be necessary. If upon such testing the meter or meters are found to be defective the Board shall be entitled to revise the invoice as sated above and it shall be binding on the consumer. 8 In the event of any meter ceasing to register the reading during the period of such cessation shall be based on the average consumption for the three normal pervious months immediately preceding the detection of the cessation of the meter.

9 (a) The consumer shall pay for all electrical energy supplied to him by the Board under this agreement and ascertained herein before provided which is inclusive of energy supplied under previous agreements, if any, as well an amount calculation at the EHT tariff for 110 kV consumers in force time to time in the Board. (b) The rate of supply shall be the EHT tariff for 110 KV consumer ( non power intensive) in force from time to time in the which case the revised rate/ rates shall be binding on the consumer and the levy of charges shall be at the revised rate or rates. (c) The ETH tariff notification in force in force in the Board form to time shall form part of this agreement. 10. For the purpose of this agreement ,the maximum kVA or KW demand shall be the average of the quantities of Kilowatt or KVA as the case may be, delivered at the point of supply of the consumer recorded during any consecutive 30 minutes period of maximum use in the month registered by the 110 KV metering equipment installed near the point of supply. This is also defined as twice the largest number of KWH or KVAH supplied and taken during any consecutive thirty minutes in the month. The Board however reserve the right to shorten the above time interval 30 minutes in special cases if necessary. The maximum demand based on which the consumer will be billed for demand charges and energy charges shall be the maximum demand for the month as given above. 11 All sums found due to the Board from the consumer under or by virtue of these presents or by reasons of the breach there of or other wise are recoverable under the provisions of the Revenue Recovery Act for the time being in force as if they are arrears of public revenue due on land or in such other manner the Board may deem fit. The above provisions shall not prejudice any other remedy to which the Board may be entitled for the recovery of such moneys. 12 The Board and the consumer hereby agree that it shall be competent for either party to terminates this agreement by issue of 3 months notice, sent by registered post. Provided always that the consumer may, at any time, with the previous consent of the Board, transfer this agreement to any other person and up on subscription by such transference of these presents, this agreement shall become binding on the transferee and shall take effect in all respects as if the transferee had originally been party here to in place of the consumer. But the consumer shall also liable to the Board for all sums due from

him till the date of such transfer and his liabilities till that will not cease by virtue of the transfer. 13 The consumer shall furnish to the Board, full particulars accompanied by drawing showing the arrangement of all electrical plant and equipments installed by the consumer as also full details of loads. The plant and equipment so installed shall be of suitable design and, in regard to manufacture, construction and performance, conform to the relevant Indian/ British standard specification or other equivalent standard specification applicable to such plans and equipments, and their operation shall not be calculation to interfere with or detrimentally effect the service of the Board or the supply to any other another consumers For that purpose the following regulation shall be observed. a)The power factor of the plant and apparatus owned and operated by the consumer at the individual point of supply shall not be less than 0.9 lag.. f it drops below 0.9 lag the consumer has to maintain power factor not below 0.9 lag by suitable power factor correction apparatus/ equipment. For Improving/ Deteriorating Power Factor. Power Factor Range For. P.f. between 0.90 to 1.00 For p.f below 0.90 Incentive / Penalty 0.15 of the energy charges foe each 0.01 unit increase in power factor from 0.90 p.f as incentive to the consumer by the licensee. 1% energy charge for every 0.01 fall from 0.90 p.f as penalty to be paid by the consumer to the licensee.

The power factor shall be calculated up to two decimal point. The power factor shall be calculated and rounded to the second nearest decimal. Should the power factor drop below 0.75 and so remain for a period of two consecutive months it must be brought to 0.75 within a further period of six months by the consumer, failing which, without prejudice to right of the Board to collect the extra charge and without prejudice to such other rights as having accrued to the Board or any other rights of the Board, the supply to the consumer may be discontinued. (b)The consumer has to install suitable meter to record the power factor. If no such meter is installed the power factor shall be determined by the ratio of the readings of the KWH and KVAH energy taken monthly. If special meters for recording KVA are not available or can not be provided the power factor at the time of maximum KVA demand in any month shall be taken as the average of the hourly indicated power factor readings recorded for each day of the month in question during the time of maximum demand. ( c)The completed installation should be got satisfactorily tested and inspected by the Engineer of the Board authorized in this behalf and a certificate to that effect shall be produced before a power service is given.

14 (a) Should the consumer desire an increase in the supply of electrical energy in excess of what is provided for under this agreement at any time during the currency of this agreement, the consumer shall give six months previous notice in wiring to the board specifying the increased quantity required and the Board shall upon execution of a fresh agreement for the whole supply on terms and conditions mutually agreed upon, supply such additional requirement, provided sufficient surplus power is available the corresponding point of supply at the specified time. (b) The consumer shall not make an alternation in the machinery either by way of addition or substitution or transfer which may increase the obligation of the Board to supply electrical energy in excess of the agreed maximum demand and/ or which may effect the supply system of the Board to its determine. In any event the consumer shall notify the Board of the intended alternation, additions, substitutions or transfers and obtain the prior approval of the Board in writing before doing any such alternations, additions substitutions or transfers. (c ) When no such approval in writing is obtained the Board shall be entitled to cut off the supply if the Board is satisfied. i.. that the obligation to supply electrical power to the consumer is by any such alternation, addition, substitution or transfer becomes greater that the contract demand, or ii. that any part of the Boards electrical equipment including feeders and metering equipment is by any such alternation addition ,substitution or transfer over loaded, damaged or otherwise detrimentally affected or. iii. that supply of sufficient power to any other consumer is thereby jeopardized. (d) Where it is established to the satisfaction of the Boards Engineer/ Office that the consumer had dishonestly abstracted, used or wasted electrical energy, such Engineer/Officer shall estimate the value of the electrical energy to abstracted consumed, used or wasted and the same shall be demanded and collected by including it in the next bill or by a separate bill. Such amounts shall be deemed to be arrears of electricity charges when after demand they are not paid. Neither failure to launch a prosecution, nor the acquittal of the consumer in any criminal case launched against him on this account on a ground other than that the prosecution case is false, shall be a bar for claming such amount. The levy of these amount shall be without prejudice to the Boards right to disconnect the service of the consumer and/or take such other action as it is entitled to under law. The consumer if aggrieved against an order of assessment made by the Boards Engineer/ Officer, shall first pay the amount demanded and then appeal to the Chief Engineer ( Electricity) within a fortnight from the date of communication of the order. 15. The consumer also agreed that when the Actual Maximum demand of any month exceeds the contract demand as specified in the agreement entered into between the consumer and the Board , and Board and the consumer have not signed any new agreement as envisaged in clause 14 (a) above ,the excess demand will be charged at a percentage as shown in the tariff notification in force from time to time ( which is at present 150% of the normal tariff rate) of the demand charges shown in the schedule to this agreement.

16 (a) The supply of electrical power under this agreement shall be available continuously except in case of lockout, strike of the employees of the Boards, break down of machinery plant or flood, drought or other force majeure or any other case over which the Board has not control, in any of which cases the Board shall not be responsible for any discontinuance or diminution of the supply, but hall restore the supply as soon as reasonably can. (b) The consumer shall not be responsible for non- consumption of energy due to lock out, strike of employees of the consumer, major breakdown of machinery or plant which to the satisfaction of the Board is responsible for the non consumption of energy or other force majure over which the consumer has not control but shall resume consumption of energy as soon as he reasonably can. In such cases, where the consumer is unable consume energy shall promptly intimate the Board the reasons for such non consumption. In any event the consumer shall be bound to pay to the Board the minimum annual revenue guaranteed by the consumer and specified in the schedule to this agreement, irrespective of the question as to whether any energy has been consumed or not or as to what are the reasons for nonconsumption and also irrespective of the actual quantity consumed. However, the Board shall have the right to take periodical shut down as and when required for the purpose of routine maintenance after giving reasonable notice to the consumer and no claim for rebate or refund of charges on this account shall be entertained by the Board. 17 If at any time the consumer is prevented from receiving or using the electrical energy to be supplied under this agreement either in whole or in part owing to any strike, riots, insurrection, command of a civil or military authority, fire explosives, act of God or any other cause reasonably beyond control or if the Board is prevented form supply or unable to supply such electrical energy owing to all or any of the causes mentioned above, then the minimum charge or the minimum guarantee payable by the consumer for each month in which the consumer or the Board is so prevented shall be reduced for the time being in proportion to the ability of the consumer to take or the Board to supply such power, the ability being reckoned proportional to the energy consumed during the month in question in relation to the average consumption for six normal; months immediately proceeding the said period. This will be without prejudice to the provision contained in clause 16 above. Also periods of non- consumption of less than seven days, consecutive will not be considered for operation of this clause. 18. In this agreement , unless the context other wise require (a) the work Act Wherever it occurs shall mean the Indian Electricity Act, 1910 as amended from time to time or such other enactment governing the supply and use of electrical energy as may be in force for the time being and (b) the words Rules and Regulation Where ever they occur shall mean the rules and regulation for the time being force made by the Government or the Board. 19. The conditions of supply of Electrical Energy published by the Board as amended from time to time shall be deemed to be part of this agreement and the provisions there in which are not contradictory to the provisions made there in as also the statutory obligation under the act and /or Rules shall also be binding on the consumer. 20. Previous agreement, if any, between the consumer and the Board shall stand terminate with effect from the date Execution of this agreement. However the liability of the consumer under the previous agreements, if any, shall continue after the execution of this agreement. The arbitration clause, if any, in the prior agreement shall stand repealed by this agreement and the arbitration clause shall not be applicable to any dispute claims between the parties arising under the prior agreement or under the agreement.

21. The schedule appended here to shall from part of this agreement and shall be subject to revision from time to time as per rules and tariff in force. 22. This agreement is in force with effect from 16-04-2010 SCHEDULE Description of the premises at which the supply is to be given Purpose for which the supply is to be given Rates for supply

1 2 3

4 5

Maximum Electrical Power required by the consumer. Minimum revenue per year guaranteed by the Twelve times the demand charges consumer per month corresponding to 75% of the contract demand at the ruling rates.

Ti02 pigment plant, Sangaramangalam, Chavara. Power and lighting the factory EHT Tariff for 110 kV consumer non-power intensive) of the KSE Board in force from time will be applicable. 12500 kVA at 110000 volt.

In witness where of for and on behalf of Kerala State Electricity Board and .. for and behalf of the consumer have set their hands an seals on the . day of the month of two thousand and.. first above written.

Signature of the consumer Signature of the Chief Engineer ( Transmission- South) Witness 1. V. Ramachandran Achari Asst. General Manager (E) KMML, Chavara. Witness 1

Mani Swamy Secretary to Managing Director, KMML, Chavara.

( For the consumer)

( for the Chief Engineer ( Transmission-South)

FORM OF AGREEMENT FOR THE SUPPLY OF E.H.T. ENERGY This agreement made on the . .day of ..between the Chief Engineer (Transmission- South ) for and on behalf of the Kerala State Electricity Board ( hereinafter referred to as the Board which expression shall , when the context so admits or implies, be deemed to include its successors or assignees as well) of the one part and the General Manager / Managing Director of M/s. The Kerala Minerals and Metals Ltd a company incorporated under the Indian Companies Act 1972 having its registered office at Sangaramangalam, Chavara ( hereinafter referred to as the Consumer) of the other part whereby it is agreed to as follows:1(a) The Board shall furnish to the consumer and the consumer shall take from the Board all the energy required for operation and lighting the consumers . factory t Sangaramanglam , Chavara up to a total quantity of 12500 kVA ( hereinafter called the Contract Demand) The supply to the consumer shall be in the from of 3 phase alternating current at a frequency of approximately 50 cycles per second . Power up to a maximum of 125000 KVA will be supplied at a voltage of approximately 110000 volts (b) The frequency and pressure of electrical energy at the point of delivery of power to the consumers shall be subject of the fluctuations that are ordinary, usual and incidental to the generation and transmission of electrical energy, but such fluctuations shall not, except owing to extraordinary reasons beyond the control of the board, be more than plus or minus 3 per cent (3%) on the frequency and plus or minus twelve and half percent ( 12 % ) on the pressure. 2 (a) The point of delivery of power at 110000 volts shall be at the consumers side of the 110000 volts. Metering current transformers installed by the board at the cost of the consumer in the out door 110KV switchgear station at the consumers factory premises. (b) The consumer shall provide to the Board free of charges all land or space required for the purpose of erecting the necessary control switchgear and metering equipment and allow the Boards Engineer authorized in this behalf or his authorized representative access to such station at any time of the day or night. ( c) The consumer shall at his own cost provide, install and maintain suitable 110 KV Circuit Breakers complete with protective gear on the consumers side of the Boards outdoor metering current transformers or in his main feeders with settings of the protective relays properly co-ordinate with those of the 110 kv Circuit Breakers of the board. 3 The consumer shall furnish security either by cash or Demand Draft to the extent of two months current charge as fixed by the Chief Engineer ( Ele). This is fixed in the first instance as Rs. 558 lakhs . The consumer shall on demand in writing replenish or enhance within ten day such security in the event of the same being found by the Chief Engineer or his authorized representative to be insufficient exhausted and the decision of the Chief Engineer or his authorized representative in that regard shall be final and conclusive

between the parties. A demand for the purpose of this clause shall be sufficient if a notice is sent by registered post giving ten days time to comply with it. The board is at liberty at any time to approximate and apply any security so furnished in or towards payment or satisfactory of all or any amount which shall become due from or owing by the consumers to the board in respect of supply of energy or otherwise under the agreement. The security shall be in the form of cash or Demand d Draft for an amount equivalent to one months electricity charges ( inclusive of both demand and energy charges) and bank guarantee equivalent to one months electricity charges for the original contract demand. In the event of the consumer failing to replenish or enhance the security even after demand as stated above it shall be lawful for the board to disconnect the service even without any further notice and in that event the board shall not be liable for the loss if any sustained by the consumer on that account. 4.The quantity of electrical power and energy supplied by the Board to the consumer shall be ascertained by means of a meter or meter and current-potential transformers as per the specifications prescribed by the Board shall be provided at the cost of the consumer kept in repair by the calibrated by the Board. When. the meter or meters, current-potential transforms become defective or the meter or meter cease to measure the electrical quantity supplied by the Board , the consumers shall repair them or replace them by correct meter or meters or current potential transformers at the cost of the consumer within one month of the meter or meters becoming defective or ceasing to register the electrical quantity or the current potential transformers becoming defective. 5. The side meter or meters shall at all reasonable times be open to the inspection of the Boards Engineer authorized in this behalf, or his authorized representatives and shall be properly sealed on behalf of both parries and shall not be interfered with by either party except in the presence of the other party or his representative duly authorized in that behalf. 6. (a)The reading of the said meter or meters shall be taken by the accredited representative of both the parties hereto as near as soon as practicable on the last date of each calendar month and recorded. The reading so recorded shall be binding and conclusive between the parties hereto, as the quantity of electrical power and energy supplied under this agreement. The recording of the reading shall be in a card to be attached to such meters shall which shall be open to the inspection of the consumer also. Payment for power and energy supplied shall be made by the consumer according to the recorded reading of the meters and at the rates specified in the schedule attached hereto or other applicable rate. Payment shall be made within fifteen days from the date of receipt of the consumers of the invoice for the power supplied. In default of payment, the consumer is liable to pay interest at 24 %per annum or at such other percentage as fixed by the board from time to time also on this amount. Exact number of days delayed shall be reckoned as the number of days as such for the purpose of calculation if interest. 6(b) If the consumer fails to remit the dues within the time stipulated in clause 6 (a) it shall be lawful for the Board to cut off the supply of power after giving the notice contemplated in Section 24 of the I.E. Act. In that event it shall also be lawful for the board to adjust the security deposit towards the dues. 7 If the consumer shall at any time consider that any meter is not in proper order for correctly registering the quantity of the supply, he may apply to the Boards Engineer authorized in this behalf for a special test, with a remittance of R. 1,000/-( Rupees one thousand only). On receipt of the application and testing fee, the Board in the presence of the consumer or an agent duly authorized by him, shall cause to test the meter and if during such test the error in the meter is found to exceed the limits of accuracy laid down in the

Indian Electricity Rules, 1956, as amended form time to time, the consumers bill shall be adjusted in accordance with the result of the test for the provisos three months from the date of test or defect, unless there is satisfactory evidence to show that the meter was not registering correctly for a definite period in which case the bills shall be adjusted for such definite period not exceeding six months and the test fee shall be retuned to the consumer. If, however during the test the error in the meter on dispute is found to be within the limits of accuracy laid down in the Indian electricity Rules, 1956, as amended from time to time previous bills shall be confirmed and the test fee shall be forfeited to the Board. Testing as stated above shall be done at the instance of the Board also in which case no testing fee shall be necessary. If upon such testing the meter or meters are found to be defective the Board shall be entitled to revise the invoice as sated above and it shall be binding on the consumer. 8 In the event of any meter ceasing to register the reading during the period of such cessation shall be based on the average consumption for the three normal pervious months immediately preceding the detection of the cessation of the meter. 9 (a) The consumer shall pay for all electrical energy supplied to him by the Board under this agreement and ascertained herein before provided which is inclusive of energy supplied under previous agreements, if any, as well an amount calculation at the EHT tariff for 110 kV consumers in force time to time in the Board. (b) The rate of supply shall be the EHT tariff for 110 KV consumer ( non power intensive) in force from time to time in the which case the revised rate/ rates shall be binding on the consumer and the levy of charges shall be at the revised rate or rates. (c) The ETH tariff notification in force in force in the Board form to time shall form part of this agreement. 10. For the purpose of this agreement ,the maximum kVA or KW demand shall be the average of the quantities of Kilowatt or KVA as the case may be, delivered at the point of supply of the consumer recorded during any consecutive 30 minutes period of maximum use in the month registered by the 110 KV metering equipment installed near the point of supply. This is also defined as twice the largest number of KWH or KVAH supplied and taken during any consecutive thirty minutes in the month. The Board however reserve the right to shorten the above time interval 30 minutes in special cases if necessary. The maximum demand based on which the consumer will be billed for demand charges and energy charges shall be the maximum demand for the month as given above. 11 All sums found due to the Board from the consumer under or by virtue of these presents or by reasons of the breach there of or other wise are recoverable under the provisions of the Revenue Recovery Act for the time being in force as if they are arrears of public revenue due on land or in such other manner the Board may deem fit. The above provisions shall not prejudice any other remedy to which the Board may be entitled for the recovery of such moneys. 12 The Board and the consumer hereby agree that it shall be competent for either party to terminates this agreement by issue of 3 months notice, sent by registered post. Provided always that the consumer may, at any time, with the previous consent of the Board, transfer this agreement to any other person and up on subscription by such transference of these presents, this agreement shall become binding on the transferee and

shall take effect in all respects as if the transferee had originally been party here to in place of the consumer. But the consumer shall also liable to the Board for all sums due from him till the date of such transfer and his liabilities till that will not cease by virtue of the transfer. 13 The consumer shall furnish to the Board, full particulars accompanied by drawing showing the arrangement of all electrical plant and equipments installed by the consumer as also full details of loads. The plant and equipment so installed shall be of suitable design and, in regard to manufacture, construction and performance, conform to the relevant Indian/ British standard specification or other equivalent standard specification applicable to such plans and equipments, and their operation shall not be calculation to interfere with or detrimentally effect the service of the Board or the supply to any other another consumers For that purpose the following regulation shall be observed. a. The power factor of the plant and apparatus owned and operated by the consumer at the individual point of supply shall not be less than 0.9 lag.. f it drops below 0.9 lag the consumer has to maintain power factor not below 0.9 lag by suitable power factor correction apparatus/ equipment. For Improving/ Deteriorating Power Factor. Power Factor Range For. P.f. between 0.90 to 1.00 Incentive / Penalty 0.15 of the energy charges foe each 0.01 unit increase in power factor from 0.90 p.f as incentive to the consumer by the licensee. 1% energy charge for every 0.01 fall from 0.90 p.f as penalty to be paid by the consumer to the licensee.

For p.f below 0.90

The power factor shall be calculated up to two decimal point. The power factor shall be calculated and rounded to the second nearest decimal. Should the power factor drop below 0.75 and so remain for a period of two consecutive months it must be brought to 0.75 within a further period of six months by the consumer, failing which, without prejudice to right of the Board to collect the extra charge and without prejudice to such other rights as having accrued to the Board or any other rights of the Board , the supply to the consumer may be discontinued. (b)The consumer has to install suitable meter to record the power factor. If no such meter is installed the power factor shall be determined by the ratio of the readings of the KWH and KVAH energy taken monthly. If special meters for recording KVA are not available or can not be provided the power factor at the time of maximum KVA demand in any month shall be taken as the average of the hourly indicated power factor readings recorded for each day of the month in question during the time of maximum demand.

( C) The completed installation should be got satisfactorily tested and inspected by the Engineer of the Board authorized in this behalf and a certificate to that effect shall be produced before a power service is given. 14 (a) Should the consumer desire an increase in the supply of electrical energy in excess of what is provided for under this agreement at any time during the currency of this agreement, the consumer shall give six months previous notice in wiring to the board specifying the increased quantity required and the Board shall upon execution of a fresh agreement for the whole supply on terms and conditions mutually agreed upon, supply such additional requirement, provided sufficient surplus power is available the corresponding point of supply at the specified time. (b) The consumer shall not make an alternation in the machinery either by way of addition or substitution or transfer which may increase the obligation of the Board to supply electrical energy in excess of the agreed maximum demand and/ or which may effect the supply system of the Board to its determine. In any event the consumer shall notify the Board of the intended alternation, additions, substitutions or transfers and obtain the prior approval of the Board in writing before doing any such alternations, additions substitutions or transfers. (C ) When no such approval in writing is obtained the Board shall be entitled to cut off the supply if the Board is satisfied. i.. that the obligation to supply electrical power to the consumer is by any such alternation, addition, substitution or transfer becomes greater that the contract demand, or ii. that any part of the Boards electrical equipment including feeders and metering equipment is by any such alternation addition ,substitution or transfer over loaded, damaged or otherwise detrimentally affected or. iii. that supply of sufficient power to any other consumer is thereby jeopardized. (d) Where it is established to the satisfaction of the Boards Engineer/ Office that the consumer had dishonestly abstracted, used or wasted electrical energy, such Engineer/Officer shall estimate the value of the electrical energy to abstracted consumed, used or wasted and the same shall be demanded and collected by including it in the next bill or by a separate bill. Such amounts shall be deemed to be arrears of electricity charges when after demand they are not paid. Neither failure to launch a prosecution, nor the acquittal of the consumer in any criminal case launched against him on this account on a ground other than that the prosecution case is false, shall be a bar for claming such amount. The levy of these amount shall be without prejudice to the Boards right to disconnect the service of the consumer and/or take such other action as it is entitled to under law. The consumer if aggrieved against an order of assessment made by the Boards Engineer/ Officer, shall first pay the amount demanded and then appeal to the Chief Engineer ( Electricity) within a fortnight from the date of communication of the order. 15. The consumer also agreed that when the Actual Maximum demand of any month exceeds the contract demand as specified in the agreement entered into between the consumer and the Board , and Board and the consumer have not signed any new agreement as envisaged in clause 14 (a) above ,the excess demand will be charged at a percentage as shown in the tariff notification in force from time to time ( which is at present 150% of the normal tariff rate) of the demand charges shown in the schedule to this agreement. 16 (a) The supply of electrical power under this agreement shall be available continuously except in case of lockout, strike of the employees of the Boards, break down of machinery plant or flood, drought or other force majeure or any other case over which the Board has not control, in any of which cases the Board shall not be responsible for any discontinuance or diminution of the supply, but hall restore the supply as soon as reasonably can.

(b) The consumer shall not be responsible for non- consumption of energy due to lock out, strike of employees of the consumer, major breakdown of machinery or plant which to the satisfaction of the Board is responsible for the non consumption of energy or other force majure over which the consumer has not control but shall resume consumption of energy as soon as he reasonably can. In such cases, where the consumer is unable consume energy shall promptly intimate the Board the reasons for such non consumption. In any event the consumer shall be bound to pay to the Board the minimum annual revenue guaranteed by the consumer and specified in the schedule to this agreement, irrespective of the question as to whether any energy has been consumed or not or as to what are the reasons for nonconsumption and also irrespective of the actual quantity consumed. However, the Board shall have the right to take periodical shut down as and when required for the purpose of routine maintenance after giving reasonable notice to the consumer and no claim for rebate or refund of charges on this account shall be entertained by the Board. 17) If at any time the consumer is prevented from receiving or using the electrical energy to be supplied under this agreement either in whole or in part owing to any strike, riots, insurrection, command of a civil or military authority, fire explosives, act of God or any other cause reasonably beyond control or if the Board is prevented form supply or unable to supply such electrical energy owing to all or any of the causes mentioned above, then the minimum charge or the minimum guarantee payable by the consumer for each month in which the consumer or the Board is so prevented shall be reduced for the time being in proportion to the ability of the consumer to take or the Board to supply such power, the ability being reckoned proportional to the energy consumed during the month in question in relation to the average consumption for six normal; months immediately proceeding the said period. This will be without prejudice to the provision contained in clause 16 above. Also periods of non- consumption of less than seven days, consecutive will not be considered for operation of this clause. 18) In this agreement , unless the context other wise require (a) the work Act Wherever it occurs shall mean the Indian Electricity Act, 1910 as amended from time to time or such other enactment governing the supply and use of electrical energy as may be in force for the time being and (b) the words Rules and Regulation Where ever they occur shall mean the rules and regulation for the time being force made by the Government or the Board. 19) The conditions of supply of Electrical Energy published by the Board as amended from time to time shall be deemed to be part of this agreement and the provisions there in which are not contradictory to the provisions made there in as also the statutory obligation under the act and /or Rules shall also be binding on the consumer. 20) Previous agreement, if any, between the consumer and the Board shall stand terminate with effect from the date Execution of this agreement. However the liability of the consumer under the previous agreements, if any, shall continue after the execution of this agreement. The arbitration clause, if any, in the prior agreement shall stand repealed by this agreement and the arbitration clause shall not be applicable to any dispute claims between the parties arising under the prior agreement or under the agreement. 21. The schedule appended here to shall from part of this agreement and shall be subject to revision from time to time as per rules and tariff in force. 22. This agreement is in force with effect from 16-04-2010

1 2 3

SCHEDULE Description of the premises at which the supply is to be given Purpose for which the supply is to be given Rates for supply

4 5

Maximum Electrical Power required by the consumer. Minimum revenue per year guaranteed by the Twelve times the demand charges consumer per month corresponding to 75% of the contract demand at the ruling rates.

Ti02 pigment plant, Sangaramangalam, Chavara. Power and lighting the factory EHT Tariff for 110 kV consumer non-power intensive) of the KSE Board in force from time will be applicable. 12500 kVA at 110000 volt.

In witness where of for and on behalf of Kerala State Electricity Board and .. for and behalf of the consumer have set their hands an seals on the . day of the month of two thousand and.. first above written.

Signature of the consumer Signature of the Chief Engineer ( Transmission- South) Witness 1. V. Ramachandran Achari Asst. General Manager (E) KMML, Chavara. Witness 1

Mani Swamy Secretary to Managing Director, KMML, Chavara.

( For the consumer)

( for the Chief Engineer ( Transmission-South)

To The Security Inspector ( thro Duty Officer ) KMML Tio2 Sir, Kindly permit the following employees of M/s. Santhima to transport a motor from. to .. .. on .time Thanking you Date. ERS Following Members

Yours faithfully APE (E) T.No.

To The Security Inspector ( thro Duty Officer ) KMML Tio2 Sir, Kindly permit the following employees of M/s. Santhima to transport a motor from. to .. .. on .time Thanking you Date. ERS Following Members

Yours faithfully APE (E) T.No.

To The Security Inspector ( thro Duty Officer ) KMML Tio2 Sir, Kindly permit the following employees of M/s. Santhima to transport a motor from. to .. .. on .time Thanking you

Date. ERS Following Members

Yours faithfully APE (E) T.No.

PART B-CIVIL WORK Augmentation of MSDS- Scope of work for civil part The scope of work of tenderer shall include design, engineering and all civil works for construction of Main- Step down station ( MSDS) of size 27x 7.25 m and height 6m. It also includes construction of all types of foundation for equipment, pipe supports, cable tray supports and miscellaneous structures, all channels and tunnels etc. A typical soil bearing capacity test of a proximate area shows a value of 5 tons/m2 for a depth of 1.25 m. The value is indicative only; actual may be verified before tendering. Soil testing to be conducted by the tender and any variation required in design shall be in the scope of tenderer. The scope of work also includes: 1.0 GENERAL 1.1 These specifications shall apply to engineering works to be exulted for the project. The quality of materials and work shall comply with the stipulation made in the various sections of these specifications. Should it be necessary in the opinion of the Purchaser, he will issue additional specifications to supplement these. 1.2 Unless mentioned otherwise, current versions of all relevant specifications, codes, standards and method of tests, including National Building Code, issued by Indian Standards Institution shall be deemed to be fully applicable to the civil engineering works. Similarly, latest editions, codes specifications and standards etc. Issued by Indian Roads Congress shall beheld to be equally relevant. In the absence of appropriate publication on any subject by Indian standard Institution and Indian Congress adaptable specifications etc. of International Standards Organization shall be referred to. The specifications set forth are further elaboration, amplification, modification of, and addition to the standards, codes, specification etc. of Indian Standards Institution and Indian Roads Congress In case of any disagreement between these specifications and publications of Indian Standards Institution and Indian Road congress, the previsions made in these specifications shall prevail. 1.3 A few codes, specification & standards etc which will need reference to, more frequently, are listed below ; However Tenderer should follow the latest IS specifications for each.

IS: IS : IS:

1200 Method of measurement of building and Civil engineering works (all the part) 1256 Code of practice for building bye laws. 1642 Code of practice for materials and details of construction, fire safety of building (General)

Earthwork IS : IS : IS : 1498 3764 7293 Classification and identification of soils for general engineering purpose. Safety code for excavation work. Safety code for working with construction machinery.

Concrete IS : IS : IS : IS : IS IS IS IS IS IS IS IS IS : : : : : : : : : 226 269 383 432 455 456 460 516 1199 1566 1786 1834 2502 3414 6452 7861 Structural steel Ordinary, rapid hardening and low heat port-land cement. Aggregates, coarse and fine, form natural sources for concrete. Mild steel and medium tensile steel bars and drawn steel wire for concrete reinforcement. Port land blast furnace slag cement. Code for practice for plain and reinforced concrete. Test sieves Strength of concrete Sampling and analysis of concrete Hard drawn steel wire bars fabric for concrete reinforcement. Cold visited steel bars for concrete reinforcement. Sealing compounds, hot applied, for joints in concrete. Code of practice for bending and fixing of bars for concrete reinforcement. Code of practice for design and installation of joints in buildings High alumina cement for structural use. Code of practice for extreme weather concerting

IS : IS : IS :

Masonry . IS : 712 IS : 1077 IS : 1127 IS : IS IS IS IS : : : : 1528 1597 2112 2116 2185

Building Common burnt clay bulding bricks Recommendations for dimensions and workmanship of natural building stones from masonry work Methods of sampling and physical tests for refractory materials. Code of practice for constricting of stone masonry ( all parts) Code of practice for brickwork Sand for masonry mortars Hollow cement concrete blocks

IS : IS : IS : IS : IS :

2250 3414 2572 3102 3495

Code of practice for preparation and use of masonry mortars. Code of practice for design and installation of joints in buildings. Code of practice for construction of hollow concrete block masonry Classification of burnt clay solid bricks. Method of test of clay building bricks.

Doors, Windows & Ventilators. IS : IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS IS : : : : : : : : : : : : : : : : : : 399 883 1038 1081 1361 1761 2191 2202 3614 809 1195 1196 1197 1198 1237 Classification of commercial timbers and their zonal distribution Code of practice for design of structural timber in building

22/07/2010 GM (F) thro AGM (E)/DGM (M) Sub:- Approval for excess room rent. I have been in Banglore for the workshop as power system protection from 28-05-2010 to 29-07-2010. I got accommodation @ Rs. 525/- per day and request to kindly approve excess amount incurred towards room rent. The bill is enclosed herewith. Jahangir. M 050645 M (E)

S-ar putea să vă placă și