VARIABLE AIR VOLUME WITHOUT REHEAT TERMINAL UNITS FUNCTIONAL PERFORMANCE TESTS
A) OBJECTIVES 1) To verify that the terminal units supply air at the proper rates and maintain space temperature via modulation of the supply air damper. 2) Specifically this test will check that: a) The minimum and maximum air flows are programmed and controlled correctly and match the TAB report values. b) The space temperature is maintained within 2F of setpoint. c) The damper does not over or under modulate. B) EQUIPMENT TESTED 1) Variable Air Volume Terminal Units without Reheat listed below. C) BASIS OF TEST 1) Project drawings 2) Test and Balance Report 3) Sequences of Operation as shown below: D) VAV TERMINAL SEQUENCE OF OPERATION 1. NOT AVAILABLE
Floor No
S.No A
Description VAV Boxes suitable for Cooling application foe following air deliveries
Unit
Total
Page 1 of 11
E) PREREQUISITES 1) The following items must be completed prior to performing the testing procedures: a) Final installation of this system component, installation verification forms accepted. b) Equipment to be controlled is operational. F) MINIMUM PARTICIPANTS 1) The following personnel should be present for the testing: a) Owners witnesses b) Contractors representative: commissioning coordinator c) Test technician: BMS system contractor d) Commissioning Authority
G) TEST EQUIPMENT 1) The following test equipment is required to complete this procedure: a) Handheld anemometer Page 2 of 11
1) Participants sign in on the log below. 2) Record the equipment data on the next table. 3) Verify the prerequisites as shown. If any prerequisite fails, remedy the failure and verify the remedy before continuing. 4) Follow the step by step instructions in each step following. 5) To facilitate photocopying, do not write on the backs of forms. I) PARTICIPANT SIGN-IN Role Owners Witness Name Initials Company Email Phone
Contractors Cx Coordinator
Tech: EMS system contractor
Commissioning Authority
J) TEST EQUIPMENT RECORD 1) Record the make, model, serial number and last calibration date for each piece of equipment used Page 3 of 11
Model
K) PREREQUISITES 1) Verify the following prerequisites. Initial the pass or fail line and record the date and time. a) Final installation of system components, installation verification forms accepted b) Equipment is operational. Pass: ______ Fail: ______ Pass: ______ Fail: ______ c) Air Handlers serving the terminal units are operating normally. Pass: ______ Fail: ______ Date: _____ Time: _____ Date: _____ Time: _____ Date: _____ Time: _____
2) Provide a report with the K-factor programmed for each terminal unit being tested. 3) Provide a copy of the most current Test and Balance Report END OF PREREQUISITES PROCEDURE
Page 4 of 11
1) The majority of the testing will be accomplished via manual test for the terminal units. Please keep that in mind and follow the requested waiting times between certain steps to allow the participants time to respond to the changes being made. 2) In addition to waiting the appropriate times, recording the time of test steps is critical in allowing the tester to locate the events in the logs. 3) This test is designed to test the terminal units one at time. 4) Identify the VAV units which will be tested. These should be readily accessible. A suggested sample size is 10% which is 35 units.
Page 5 of 11
5) Logic Control Test a) Identify VAV units being tested (up to 4) _________ VAV Tag Current Space Set point (C) Max CFM (TAB) Min CFM (TAB) k-factor Observed Damper position (%) Set space cooling set point to a very warm value (30C) Time Observed Damper position (%) (should be 100%) Measured DP (inch w.c.)
Page 6 of 11
Set space cooling set point to a very cool value (15C) Time Observed Damper position (%) (should be min %) Measured DP (inch w.c.) Measured airflow (CFM) Does minimum
Page 7 of 11
Page 8 of 11
a) Identify VAV units being tested _______ (up to unit 4) VAV Tag Current Space Set point (C) Actual measured space temp (C) Result PASS is within (+ 2C) Notes
Page 9 of 11
Page 10 of 11
Page 11 of 11