Sunteți pe pagina 1din 4

NASSAU COUNTY

(as of 11/29/2011) Construction is Underway State Road A1A Adding two lanes from Griffin Road to Stratton Road including replacing the bridges over Mills Creek and Boggy Creek (6 miles). Superior Construction Company of Jacksonville and ARCADIS began the design on July 22, 2009; began construction on August 27, 2009 and should finish in 763 days (Spring 2012) at a cost of $26,205,000. This is a design/build project and is funded using federal economic stimulus funding. PB Americas, Inc., is CEI project manager. Shannon Mobley/FDOT project manager. (216873) State Road A1A Resurfacing from Interstate 95 to the Amelia River (10 miles). Hubbard Construction Company of Winter Park began January 24, 2011 and should finish in 276 days (Late 2011) at a cost of $12,599,739.35. Bill Downey of RS&H is CEI project manager (904256-2570). Jessica Tippett/FDOT project manager. (2107113) State Road A1A Landscaping from Amelia Island Parkway to Centre Street in Fernandina Beach (3.2 miles). Gainesville Landscape Contractors, Inc., of Gainesville began with the design phase on July 27, 2011 and should finish with the construction in 210 days (Spring 2012) at a cost of $437,500. This is a design-build project. R.J. White/FDOT project manager. (4287571) US 301 Adding lanes from the Duval County line to the four-lane just south of Callahan including replacing the Funks Creek Bridge (14 miles). Anderson Columbia Company of Lake City and Horizon/IDA began with the design August 18, 2011 and began with the construction November 14, 2011 and should finish in 1,200 days (Fall of 2014) at a cost of $59,559,000.00 (includes adding lanes in Duval County from a point where the future Baldwin bypass intersects to the Nassau County line for a total of 17 miles). Shannon Mobley/project manager. (4295511) Construction is Imminent State Road A1A Repaint the Amelia River bridges. Bids to open December 14, 2011 at estimated cost of $4 million. Jeff Bailey/project designer. (4282271) State Road A1A Install Intelligent Transportation System communications (installation and integration of closed circuit cameras) between Amelia Island Parkway and 15th Street (4 miles) in Fernandina. American Lighting and Signalization Inc., of Jacksonville should begin in early 2012 at a cost of $58,201.60. Pete Vega/project designer. (4300651) US 90 Resurface from the Baker County line to the Duval County line (2.2 miles). Hubbard Construction Company of Winter Park should begin in early 2012 at a cost of $911,000. Travis Humphries/project designer (4244711)

Projects in Five-Year Work Program Bay Road (County Road 115) Resurface from Conner Nelson Road to County Road 108 (3.2 miles) in 2012/13 at estimated cost of $963,000. (4282032) Chester Road Add lanes from State Road A1A to Green Pine Road (2.3 miles) in 2015/16 at estimated cost of $5.7 million. (4260312) Interstate 95 Resurface from the Duval County line to the Georgia state line (12.2 miles). Bids to open in July 2013 at estimated cost of $20 million. Amy Williams/project designer. (4288091) Sidewalks Build three sidewalks along Robin Hood Drive, Westchester Lane and Canterbury Lane between South 14th Street and Will Hardee Road around Emma Love Hardee Elementary School. This is a Safe Routes to School project. Bids to open in March 2012 at an estimated cost of $163,000. Jeff Daugharty/project designer (4288421) State Road A1A Build bike path/trail from the Nassau Sound Bridge to Peters Point Park. (6 miles). Bids to open in June 2012 at an estimated cost of $1.6 million. Amy Williams/project designer (4274301) State Road A1A Add lanes from west of Still Quarters Road to west of Rubin Lane (1.5 miles). Bids to open in June 2014 at an estimated cost of $16 million. Will Lyons/project designer (2107123) State Road A1A Add lanes from west of Rubin Road to east of Scott Road (County Road 107). Bids to open in October 2015 at estimated cost of $51 million. Will Lyons/project designer. (2107124) US 1 Add left turn lane 3.5 miles north of Callahan. Bids to open in January 2013 at an estimated cost of $303,403. Myrna Widmer/project designer (2106612) US 1 Resurface from Fifth Avenue in Callahan to Alligator Creek (.8 mile). Bids to open in December 2012 at an estimated cost of $1.1 million. Myrna Widmer/project designer (4269621) US 1 Resurface from the Duval County line to Fifth Avenue in Callahan (4.3 miles) in 2014/15 at estimated cost of $9.2 million. (4287111) US 17 Resurface from the Duval County line to Interstate 95 (11 miles) in 2013/14 at estimated cost of $7.3 million. (4287101) US 17 Repairs to pier five of the St. Marys River Bridge. Bids to open in September 2012 at an estimated cost of $1.6 million. Jeff Bailey/project designer (4244251) US 17 Rebuild the railroad crossing in Yulee near State Road A1A in 2013/14 at estimated cost of $375,000. (4272241)

Recently Completed Projects (within the past year) County Road 107 (Blackrock Road) Added sidewalk from Windsor Drive to Heron Isles Parkway (1.6 miles). Onas Corporation began April 2011 and finished May 5, 2011 at a cost of $288,550.00. (4283101) County Roads 115, 115A, Andrews Road and Thomas Creek Road Installed reflective pavement markers and striping at various locations. Ameriseal Highway Striping, Inc., of Jacksonville began June 6, 2011 and finished August 5, 2011 at a cost of $352,075.15. (4281861) County Roads 115, 115A, 119 and Henry Smith Road Installed guardrail at various locations. American Lighting and Signalization Inc., of Jacksonville began June 30, 2011 and finished September 23, 2011 at a cost of $341,580.80. (4281862) County Road 200 (Pages Dairy Road) Resurfaced from U.S. 17 to Felmore Road (1.2 miles). Duval Asphalt Products of Jacksonville began April 22, 2011 and finished August 19, 2011 at a cost of $831,478. (4288681) Lessie Road Replaced bridge over Little St. Marys River. Hal Jones Contractor Inc., of Jacksonville began June 1, 2010 and finished April 14, 2011 at a cost of $2,154,307.40. (2125941) State Road A1A Updated signal system from County Road 107 to Centre Street in Fernandina Beach. American Lighting and Signalization, Inc., of Jacksonville began August 6, 2010 and finished Feb. 18, 2011 at a cost of $1,181,124.44. (2107041) State Road A1A Resurfaced from the Nassau Sound Bridge to Atlantic Avenue and built a roundabout and added paved shoulders (10.7 miles). Hubbard Construction Company of Jacksonville began June 14, 2010 and finished May 13, 2011 at a cost of $4,636,499.05. (2105972) State Road A1A Installed traffic signal at Blackrock Road (County Road 107) and added right turn lane. Hubbard Construction Company of Winter Park began November 29, 2010 and finished May 13, 2011 at a cost of $812,245. (4283041) State Road A1A Repaired fender system at two Amelia River bridges. Misener Marine Construction, Inc., of Tampa began December 13, 2010 and finished November 15, 2011 at a cost of $1,583,772.37. (2106974) US 1 Added traffic signals at Fifth Avenue in Callahan. Callaway Contracting, Inc., of Jacksonville began March 31, 2011 and finished June 24, 2011 at a cost of $357,811.41. (2106697)

US 301 Resurfaced from the Duval County line to south of Pickett Road in Callahan (14.6 miles). Hubbard Construction Company of Winter Park began October 13, 2010 and finished March 4, 2011 at a cost of $2,111,350. (2106836) Projects Under Consideration Interstate 10 Study to determine improvements from Baker County line to Duval County line is underway. Leigh Ann Bennett/project designer. (2134702) State Road A1A Purchase right of way to add lanes from Interstate 95 to west of Still Quarters Road (2.1 miles) in 2012/13 and from west of Rubin Road to east of Scott Road (County Road 107) in 2012/13 and 2013/14. Will Lyons/project designer (2107112, 2107124) State Road A1A Design to add lanes from US 17 to County Road 107 (8 miles) begins in 2011/12. (2107121)

S-ar putea să vă placă și