Sunteți pe pagina 1din 1

SKANSKA 9/17/07 11:53 AM Page 50

SKANSKA USA BUILDING INC. – BATTERY WHARF

required toe depths in several areas and cies expected by the end of the year and ing 50. On Building 20, Skanska is fram-
an expansive grouting operation was in early 2008, Ellis says his team is ing the exterior walls and placing the
required to prevent water from flooding “sprinting towards the finish line.” brick masonry.
the site and allow excavation and foun- As Ellis explains, subcontracts were “The exterior of the building is con-
dation operations to move forward. being procured during a time of rising structed with a combination of precast
Aside from working in the tight con- and uncertain material costs in the brick and metal panels,” Ellis describes.
fines of the site, an existing 807-foot-long industry. To control costs and tighten the “It fits in nicely with the surrounding
granite seawall needed to be incorporat- schedule, a design-assist effort was con- structures in the North End.”
ed into the developments design without ducted with several trades on the project
being altered. Originally constructed in including marine work, foundations, Executing A Vision
1646 of timber, the seawall was part of plumbing, electrical and HVAC. One of the project’s goals was to blend in
the former North Battery Wharf and was The Regent will occupy the first two the structures with the wharf and the
designed to protect the harbor and floors of the six-story Buildings 30 and North End community, says project con-

mouth of the Charles River. 40 situated over the wharf, and will sultant Francois Nivaud, also a principal
“We had to drive sheet piling within include, the hotel lobby, restaurant, at New England Management Services
the existing boundaries, that essentially lounge, bar and meeting space. The pri- and former director of The Boston Har-
preserved the seawall,” Ellis says. “Wharf vate residence marina will be adjacent to bor Hotel.
construction that support two of the Building 30 with water taxi service on “The North End is primarily a residen-
buildings was done from the water, while the opposite side, and the remaining four tial area – it’s not warehouse or commer-
excavation and foundation work was floors will be occupied by condos. cial – so it has a rich maritime heritage,”
formed on landside.” The five-story Buildings 20 and 50 are he says. “The North End is a very low-rise
Working from barges on the water, located along Commercial Street, and area built in brick. It’s a really beautiful
Skanska installed more than 400 con- will house condos on the top levels, a spa and peaceful area.
crete piles, Ellis notes. The pilings were and fitness center, a second restaurant “What we are trying to accomplish is a
driven up to 110 feet deep and connect- and a cafe. blending of the buildings. It’s really a for-
ed with precast troughs and planks that Skanska’s core group of experienced mation between the wharf and the char-
were tied together with reinforcing and management on the project – most of acteristics of the North End – it’s a liai-
cast-in-place concrete. The wharf ele- when have 25 years experience in com- son between the two.”
ments extended over the 12-foot-tall sea- mercial construction and some with According to Nivaud, a resurgence in
wall and connect to the foundation wall. experience on other wharf developments urban living makes the project ideal for
The buildings must also meet strict – has been a boon to construction, Ellis Boston. “In Boston, what you have is a
guidelines as defined by Chapter 91 of says. The interior finishes are now being huge influx in people migrating back
the Massachusetts laws, which defines placed in the upper condo levels of Build- into the city with a very high demand for
the standards for waterfront develop- ings 30 and 40. Interior framing and MPE high-end urban living, and we don’t see
ment. With the first residential occupan- rough operations are underway in Build- an end to that,” Nivaud explains. ■

50 ■ CONSTRUCTION TODAY ■ OCTOBER 2007

S-ar putea să vă placă și