Sunteți pe pagina 1din 1

HELMARK STEEL 9/13/07 3:25 PM Page 200

HELMARK STEEL INC.

tion manager work very closely with us


via e-mail, phone and meetings to ensure
we are all on the same page with respect
to the dynamics of the project as things
move closer to the start of erection.
CT: Any unanticipated challenges you
have had to deal with?
EG: Soil contamination, buried utilities
and structures that were not anticipated
prior to the start of excavation have
delayed the start of our work.
Recently, the uncovering of a large
buried granite bulkhead that originally
was at the East River’s edge, a sheet pile
wall, and underground utilities were all
discovered by the excavator and will
push back the start of our work on site.
They must be dealt with prior to the
concrete pile caps with the column
anchor bolts, the pressure slab and
remaining concrete work that needs to
be completed before we mobilize on site.
CT: What were the the keys to winning
this job?
EG: We specialize in high-rise work, and
this is a fairly typical job that we are very
comfortable fabricating and erecting. The
key to us winning the contract was, of
course, the value that (prime) Turner (Con-
struction) knew they were getting when
they awarded us the job.
We worked closely with the Turner
team to ensure we had the scope of work
nailed down prior to putting in our best
number. We have worked on a number
of jobs with Turner New York in the past
and have a very good working relation-
ship with their firm.
above will not see any loading, and all of the cost of this work is significantly less CT: Helmark has an erection affiliate,
the load will be transferred directly to the than what it would have cost to do the Falcon Steel Co. What types of experi-
piles and down to the bedrock the piles splicing option. ences does Falcon bring to the company?
are driving to be in contact with. This CT: Did you experience any delays? EG: Falcon Steel Co. has vast experience
more complex floor system has a re- EG: Constant changes in the building in many types of steel structures, includ-
duced bearing capacity, which makes design have (also) brought on significant ing commercial building, industrial
running a mobile crane on it to set the steel detailing inefficiencies, and a delay- buildings, stadiums, rigging, millwright
girders that are outside the capacity of ed release for material procurement has work, metal siding, decking and structur-
the tower crane quite difficult. delayed the steel portion of the project. al renovations.
Getting this engineering done ahead of All schedule impacts for changes are Falcon’s specialty is high-rise steel
the concrete pour was imperative to our addressed with the construction manager buildings and our joint portfolio includes
plan for getting the steel set quickly and to ensure everyone is on the same page buildings up to 60 stories in height.
efficiently, rather than being forced to before we proceed with a change. Falcon owns seven self-climbing tower
fabricate the plate girders in sections and Steel shapes – especially larger mem- cranes – internal and external jacking –
splice the pieces together in the field. We bers – have a very long lead time, so it is with luffing booms, as well as numerous
have had to upsize piles and increase the important not to lengthen or add large other pieces of equipment.
rebar in the pressure slab to ensure the framing to a job when making design Falcon’s core personnel are very experi-
outrigger reactions will not damage the changes after materials (have) been pro- enced and more than capable to handle
slab when we are setting the girders. But, cured. The design team and the construc- the most difficult projects. ■

200 ■ CONSTRUCTION TODAY ■ OCTOBER 2007

S-ar putea să vă placă și