Documente Academic
Documente Profesional
Documente Cultură
Slide 1
Intake
Able to divert the design flow but discharge excess flows and reduce sediments and floating matter submerged orifice type intake with sill Sediments should not choke the intake: low weir height, sloped structure and flushing gate.
normal water level
Slide 2
(NB: A dam has a more important size than a weir. The objective of the dam is, therefore, to raise the water level significantly and to allow for water storage. Upstream of the dam is a reservoir.)
Consulting and Engineering 3
Slide 3
Slide 4
Slide 5
power house
Slide 6
Overall design considerations (contd.) Small weir with long canal followed by forebay: The water level in the forebay should be kept at its maximum level. The flow into the canal is controlled by a headgate at the weir. Dam with reservoir: Water levels in reservoir fluctuates because of storage operation. Maximize power generation following reservoir management plan.
Consulting and Engineering 7
Slide 7
Small weir with long canal followed by forebay Flow into canal can either be controlled by water level in forebay or by headgates at the intake into the canal If the flow is controlled by water level in forebay, that water level needs to be lowered to allow larger flows into the canal and increased in the case of small flows to maintain maximum head
forebay
Slide 8
Intake orifice Gravel trap Intake gate Sand trap Coarse rack Headrace
Slide 9
Weir
Intake Gate Intake Channel Sand trap Trash Rack Headrace Pipe
Consulting and Engineering 10
Slide 10
11
Slide 11
Weir Flow
free overfall nappe sharp crested
rounded
Consulting and Engineering
Slide 12
13
Slide 13
Qflood b H
2 Q= c b 3
14
Slide 14
Failure mechanisms Seepage flow always happens. Problem is progressive piping Downstream erosion supports progressive piping Leads eventually to failure
Seepage flow
Consulting and Engineering 15
Slide 15
Monitoring and Maintenance Watch seepage flows carefully, especially watch for increasing seepage flows, this is a signal for possible failure Watch for deflections and deformations of weir body Watch for new fractures, cracks or changes of existing fractures Watch for cavitation damage at spillways and stilling basin Watch for erosion downstream of weir or spillway or stilling basin, erosion behind wing walls, especially after floods ALL THESE OBSERVATIONS REQUIRE IMMEDIATE EVALUATION BY AN ENGINEER Maintain regular written protocols, such as monthly reports
16
Slide 16
Water Intakes
Sound design of the water intake is decisive for proper functionality of the whole hydropower plant and important to reduce cost for operation and maintenance of the plant.
17
Slide 17
Intake types
There are many different types of intakes, depending on specific situation: Free intake / bank intake without dam or weir Free intake / bank intake with temporary weir Side intake with solid dam or weir (Most common type of intake used for micro and mini hydropower development) Tyrolean weirs or Coanda type intake for steep mountain streams
18
Slide 18
19
Slide 19
20
Slide 20
21
Slide 21
22
Slide 22
23
Slide 23
24
Slide 24
25
Slide 25
26
Slide 26
27
Slide 27
Q= a b
2g z
28
Slide 28
Qdesign z a b
Slide 29
30
Slide 30
Design
Most importantly, design has to be good to allow diversion of required amounts of water into canal or penstock with minimum possible headloss. Trash and floating debris should be kept away and sediment should be kept from entering the headrace Submerged wall Floating bar Coarse trash rack Sluice gate
31
Slide 31
32
Slide 32
33
Slide 33
34
Slide 34
35
Slide 35
36
Slide 36
Slide 37
Operation The designer has to provide a weir regulation scheme that defines how the weir must be operated at different flows, especially during floods => Operation follows the design Transport of silt and sediment occurs mostly during high flows, often only a few days per year, depends on size of sediment No sediment should enter power canal When sediment transport occurs, open sluice gate at preset upstream water level to flush sediment downstream
Consulting and Engineering 38
Slide 38
Operation
Typical tasks for the operator include: Coarse trash rack at intake to be cleaned when necessary Remove floating debris from floating bar or submerged wall Close intake when sediment transport occurs during floods Watch for vortices that cause headloss, can depend on flow Watch for debris and sediment deposition, remove manually or by opening sluice gate during high flows or while turbine is shut down Check movable gates regularly Check structure similarly like dam and weir, especially after floods
Consulting and Engineering 39
Slide 39
40
Slide 40