Sunteți pe pagina 1din 40

ASEAN-German Mini Hydro Project (AGMHP)

Diversion Structure and Intake

Consulting and Engineering

Slide 1

ASEAN-German Mini Hydro Project (AGMHP)

Intake
Able to divert the design flow but discharge excess flows and reduce sediments and floating matter submerged orifice type intake with sill Sediments should not choke the intake: low weir height, sloped structure and flushing gate.
normal water level

Consulting and Engineering

Slide 2

ASEAN-German Mini Hydro Project (AGMHP)

Purpose of the diversion structure


The purpose of a dam or weir is to raise / control the water level in the stream so that sufficient quantities of water can be diverted into the intake of the hydropower plant. Upstream of the weir is no reservoir.

(NB: A dam has a more important size than a weir. The objective of the dam is, therefore, to raise the water level significantly and to allow for water storage. Upstream of the dam is a reservoir.)
Consulting and Engineering 3

Slide 3

ASEAN-German Mini Hydro Project (AGMHP)

Purpose of the water intake


The purpose of the water intake is to abstract water from a river or a pond and deliver it to a canal, penstock or storage basin. The main challenge is that intakes must operate under a full range of flows from low to flood, sometimes handle large quantities of silt, sand and gravel or floating debris ranging from full grown trees to leaves and weed. During normal operation, the water level at the weir should be kept at the highest possible level, without spilling water over the weir, to maintain the maximum head
Consulting and Engineering 4

Slide 4

ASEAN-German Mini Hydro Project (AGMHP)

Overall design considerations


Small weir with short canal: The water level at the weir is controlled by the flow through the turbine. The flow through the turbine must be equal to the flow in the river and the water level upstream of the weir should be at the weir crest. During high flows and floods, water spills over the weir or spillway.

Consulting and Engineering

Slide 5

ASEAN-German Mini Hydro Project (AGMHP)

Small weir with short canal


Maintain maximum water level at the weir but do not spill water over weir unless discharge is higher than turbine capacity

power house

Consulting and Engineering

Slide 6

ASEAN-German Mini Hydro Project (AGMHP)

Overall design considerations (contd.) Small weir with long canal followed by forebay: The water level in the forebay should be kept at its maximum level. The flow into the canal is controlled by a headgate at the weir. Dam with reservoir: Water levels in reservoir fluctuates because of storage operation. Maximize power generation following reservoir management plan.
Consulting and Engineering 7

Slide 7

ASEAN-German Mini Hydro Project (AGMHP)

Small weir with long canal followed by forebay Flow into canal can either be controlled by water level in forebay or by headgates at the intake into the canal If the flow is controlled by water level in forebay, that water level needs to be lowered to allow larger flows into the canal and increased in the case of small flows to maintain maximum head

forebay

Consulting and Engineering

Slide 8

ASEAN-German Mini Hydro Project (AGMHP)

Terminology of a typical intake with sand trap

Weir or diversion structure Sluice gate

Side spillway Flushing gate

Intake orifice Gravel trap Intake gate Sand trap Coarse rack Headrace

Consulting and Engineering

Slide 9

ASEAN-German Mini Hydro Project (AGMHP)

Terminology of a typical intake with sand trap (cont.)


Side Spillway Flushing Gate Sluice Gate Intake Orifice

Weir

Intake Gate Intake Channel Sand trap Trash Rack Headrace Pipe
Consulting and Engineering 10

Slide 10

ASEAN-German Mini Hydro Project (AGMHP)

The weir as diversion structure

Consulting and Engineering

11

Slide 11

ASEAN-German Mini Hydro Project (AGMHP)

Weir Flow
free overfall nappe sharp crested

submerged flow broad crested

rounded
Consulting and Engineering

adherent (if nappe is not sufficiently aeriated)


12

Slide 12

ASEAN-German Mini Hydro Project (AGMHP)

Flow over weirs

Consulting and Engineering

13

Slide 13

ASEAN-German Mini Hydro Project (AGMHP)

Example: Flow over weirs

Qflood b H
2 Q= c b 3

= 50 m3/s = 12 m c = 1.0 = 0.7 =?


2g H1.5

free overflow ->

2 3Q H= ( )3 2 c b 2g 2 3 50 =( ) 3 = 1.60m 2 1.0 0.7 12 2 9.81

Consulting and Engineering

14

Slide 14

ASEAN-German Mini Hydro Project (AGMHP)

Failure mechanisms Seepage flow always happens. Problem is progressive piping Downstream erosion supports progressive piping Leads eventually to failure

Seepage flow
Consulting and Engineering 15

Slide 15

ASEAN-German Mini Hydro Project (AGMHP)

Monitoring and Maintenance Watch seepage flows carefully, especially watch for increasing seepage flows, this is a signal for possible failure Watch for deflections and deformations of weir body Watch for new fractures, cracks or changes of existing fractures Watch for cavitation damage at spillways and stilling basin Watch for erosion downstream of weir or spillway or stilling basin, erosion behind wing walls, especially after floods ALL THESE OBSERVATIONS REQUIRE IMMEDIATE EVALUATION BY AN ENGINEER Maintain regular written protocols, such as monthly reports

Consulting and Engineering

16

Slide 16

ASEAN-German Mini Hydro Project (AGMHP)

Water Intakes

Sound design of the water intake is decisive for proper functionality of the whole hydropower plant and important to reduce cost for operation and maintenance of the plant.

Consulting and Engineering

17

Slide 17

ASEAN-German Mini Hydro Project (AGMHP)

Intake types
There are many different types of intakes, depending on specific situation: Free intake / bank intake without dam or weir Free intake / bank intake with temporary weir Side intake with solid dam or weir (Most common type of intake used for micro and mini hydropower development) Tyrolean weirs or Coanda type intake for steep mountain streams

Consulting and Engineering

18

Slide 18

ASEAN-German Mini Hydro Project (AGMHP)

Location and design of the intake


As a basic principle, intakes should always be located on the outer side of a river bend to minimize sediment in headrace. Sluice gates in the intake are provided to allow flushing of deposited sediments from the intake

Consulting and Engineering

19

Slide 19

ASEAN-German Mini Hydro Project (AGMHP)

Bed load transport

Consulting and Engineering

20

Slide 20

ASEAN-German Mini Hydro Project (AGMHP)

Typical layout of a side intake with cross weir

Consulting and Engineering

21

Slide 21

ASEAN-German Mini Hydro Project (AGMHP)

Free intake / bank intake without dam or weir


The water level in the river is not dammed up for diversion (no cross weir or dam) Costs for the headworks can significantly be reduced Can only be applied, if a small proportion of the dependable river flow is to be abstracted and if there is always enough water depth and head available in the river for diversion. Ideal locations for free intakes are generally at natural control sections such as rock outcrops or big boulders.

Consulting and Engineering

22

Slide 22

ASEAN-German Mini Hydro Project (AGMHP)

Free intake / bank intake with temporary weir


A temporary weir is a low cost solution made of boulders, rocks and branches Operators are required to rebuild the weir after every major flood The reliability of such an intake structure is seriously reduced.

Consulting and Engineering

23

Slide 23

ASEAN-German Mini Hydro Project (AGMHP)

Side intake with solid weir or dam


Most common type of intake used for small hydropower development Design difficulties of side intakes with weirs are related to the foundation of the weir or dam. Unless there is solid rock available in the river bed, the dam structure requires large volumes of concrete or stone masonry in order to achieve sufficient resistance against sliding under flood conditions. Seepage through permeable ground underneath the dam or weir is a major cause of dam failure.

Consulting and Engineering

24

Slide 24

ASEAN-German Mini Hydro Project (AGMHP)

Typical layout of a side intake

Consulting and Engineering

25

Slide 25

ASEAN-German Mini Hydro Project (AGMHP)

Section of a typical side intake

Consulting and Engineering

26

Slide 26

ASEAN-German Mini Hydro Project (AGMHP)

Sections of side intake with cross weir

Consulting and Engineering

27

Slide 27

ASEAN-German Mini Hydro Project (AGMHP)

Flow through submerged orifice

Q= a b

2g z

Consulting and Engineering

28

Slide 28

ASEAN-German Mini Hydro Project (AGMHP)

Example: Flow through submerged orifice

Qdesign z a b

= 0.5x1.2=0.6 m3/s = 0.10 m = 0.40 m =?

Q = a b 2g z Q b = a 2g z 0.6 = = 1.34m 0.8 0.4 2 9.81 0.10


Consulting and Engineering 29

Slide 29

ASEAN-German Mini Hydro Project (AGMHP)

Submerged intake orifice

Consulting and Engineering

30

Slide 30

ASEAN-German Mini Hydro Project (AGMHP)

Design
Most importantly, design has to be good to allow diversion of required amounts of water into canal or penstock with minimum possible headloss. Trash and floating debris should be kept away and sediment should be kept from entering the headrace Submerged wall Floating bar Coarse trash rack Sluice gate

Consulting and Engineering

31

Slide 31

ASEAN-German Mini Hydro Project (AGMHP)

Typical layout of a Tyrolean Weir


Has specifically been designed for mountain torrents (river gradients from 1 % to over 10 %) with coarse bed load during floods Comprises a collecting channel across the river covered by a screen or a perforated plate. The intake screen is designed to work as a self-cleaning screen, however, this may not always be the case in reality

Consulting and Engineering

32

Slide 32

ASEAN-German Mini Hydro Project (AGMHP)

Typical layout of a Tyrolean Weir

Consulting and Engineering

33

Slide 33

ASEAN-German Mini Hydro Project (AGMHP)

Typical arrangement of a lateral / Tyrolean Intake

Consulting and Engineering

34

Slide 34

ASEAN-German Mini Hydro Project (AGMHP)

Typical sections and details of a Tyrolean Intake

Consulting and Engineering

35

Slide 35

ASEAN-German Mini Hydro Project (AGMHP)

Intake with submerged perforated plate


Alternative Design

Consulting and Engineering

36

Slide 36

ASEAN-German Mini Hydro Project (AGMHP)

Summary: parameters and requirements


For stream gradients above 2.5% a Tyrolean intake should be used, for other cases or a lateral diversion is recommended. The water intake must divert the required stream flow at all times and all water levels in the river. The Intake location and design should reject bed load and prevent excessive flood water from entering the system. An intake orifice (always submerged) should be provided to reduce the abstracted flow when the river / stream is in flood. Stop logs shall be provided in order to completely close off the system when required. Provision shall be made to exclude large floating debris, and gravel from the diverted water.
Consulting and Engineering 37

Slide 37

ASEAN-German Mini Hydro Project (AGMHP)

Operation The designer has to provide a weir regulation scheme that defines how the weir must be operated at different flows, especially during floods => Operation follows the design Transport of silt and sediment occurs mostly during high flows, often only a few days per year, depends on size of sediment No sediment should enter power canal When sediment transport occurs, open sluice gate at preset upstream water level to flush sediment downstream
Consulting and Engineering 38

Slide 38

ASEAN-German Mini Hydro Project (AGMHP)

Operation
Typical tasks for the operator include: Coarse trash rack at intake to be cleaned when necessary Remove floating debris from floating bar or submerged wall Close intake when sediment transport occurs during floods Watch for vortices that cause headloss, can depend on flow Watch for debris and sediment deposition, remove manually or by opening sluice gate during high flows or while turbine is shut down Check movable gates regularly Check structure similarly like dam and weir, especially after floods
Consulting and Engineering 39

Slide 39

ASEAN-German Mini Hydro Project (AGMHP)

Operation during floods


Watch for bank erosion behind wing walls, respond immediately if this happens Open sluice gates to lower water level and allow flushing of sediment from behind weir After flood, watch for downstream erosion and damage in stilling basin

Consulting and Engineering

40

Slide 40

S-ar putea să vă placă și