Documente Academic
Documente Profesional
Documente Cultură
11 | P a g e
One side of the excavation required a retaining structure, so the area surrounded this side was not excavated until the retaining structure was installed.
Retaining structure
Bored piles were used to support the excavation side and prevent it from failure, the pile length was 10m, its diameter was 0.6m, and its reinforcement was 8 25 for the main reinforcement and the stirrups were 7 8 /m. The steps of forming these piles are as follows: 1. Site preparation and delivering equipments to site. 2. Marking out the position of piles, 10 cm was left between each pile and the adjacent pile. 3. Preparation and formation of the steel cage (the pile reinforcement). 4. A special machine was used in drilling, it pushed a casing down to a depth of 2m and it removed the soil within the casing, then it completed pushing the casing to the next 2m and removing the soil within the casing, this process continued until reaching the required depth. 5. Installation of the steel cage in the borehole. 6. Concrete was poured in the borehole to form the bored pile. 7. Casing was removed. 8. The next pile that was bored was not the adjacent pile to the finished pile but it was the one next to it, the piles were casted in a sequence as shown in figure 2 where the number written on each pile represents the order of casting this pile. 9. A 0.6m x 0.6m beam was casted on the top of the piles to connect them together, the reinforcement of this beam was 6 16 in the top and in the bottom. 10. The excavation process was then completed safely in this area. Figure 2
12 | P a g e
13 | P a g e