OBSERVATIONS IN PIPING TO BE ATTENDED Drawing No. Sheet No. Rev. Line Description No. Observations
M/S Greenesol Power Services Pvt. Ltd. M/s Karpara Project Engineering Pvt. Ltd.
Sl. No.
Remarks
1104-02-241F
10 of 12
Page 1 of 3
Date: 26-10-2011
OBSERVATIONS IN PIPING TO BE ATTENDED Drawing No. Sheet No. Rev. Line Description No. Observations
M/S Greenesol Power Services Pvt. Ltd. M/s Karpara Project Engineering Pvt. Ltd.
Sl. No.
Remarks
Joints welding balance from NRV to the deaerator connection PS-F6/04,05,06,07 & 08 supports base plate anchoring balance PS-F6/01 welding Balance for trunion & ISMC Box PS-F6/02 welding Balance for trunion & ISMC Box PS-F6/03 welding Balance for trunion & ISMC Box All the above supports trunion support with MS rods provided below the base plate of trunion. Supports Drawing not available. Joints welding balance from NRV to the deaerator connection PS-F8/01 support was not provided. PS-F8/05 support was not provided. PS-F8/02 welding Balance for trunion & ISMC Box Extra support provided at 2.7 mtrs elevation. Temporary clits on line at 2.7 mtrs elevation to be removed. PS-F8/03,04,06,07 & 08 supports base plate anchoring balance All the above supports trunion support with MS rods provided below the base plate of trunion. Supports Drawing not available.
1104-02-241F
08 of 12
1104-02-241S
14 of 33
1104-02-241S
17 of 33
Page 2 of 3
Date: 26-10-2011
OBSERVATIONS IN PIPING TO BE ATTENDED Drawing No. Sheet No. Rev. Line Description No. Observations
CRH 201-1 support was observed in inclined condition
M/S Greenesol Power Services Pvt. Ltd. M/s Karpara Project Engineering Pvt. Ltd.
Sl. No.
Remarks
At steam taping connection 1" half coupling connection welding not completed at 5.5 mtrs elevation. 1" Drain connection orientation changed Flange connection of LS 917/919 is not properly aligned. No gap for LS 919 (motorised fouling) No gap between floor & drain lines at 5.5 mtrs elevation. CRH 110-1 base plate anchoring balance at 16.4 mtrs elevation CRH 226 - 1hanger support was in inclined position. Temporary cleats on pipe to be removed. CRH 245 -1 ISMC box welding incomplete. CRH 1005 -1 not resting on MS rods. CRH 130-1balls for spring support was not provided & SMC box welding incomplete. 8" stub in connection observed at 5.5 mtrs elevation on header. CRH 195-1balls for spring support was not provided & Base plate anchoring not done. Drain lines at 16.4 mtrs elevation was not completed. CRH 205-1 trunion support not resting & guide support was not provided & extra MS rods provided. LHS to be submitted for RT & welding CRH 215-1 supports bolts not tightened CRH 70-1 spring support was not provided. 3 No. of joints welding was not completed at NRV 16.4mts CRH 355-1 support was not provided. 1" drain at 16.4mts was not completed.
1104-02-241S
07 of 33
Cold Reheat
1104-02-241S
08 of 33
Cold Reheat
CRH 345-1 trunion support not resting on MS rods & ISMC box welding not completed. CRH 1070 -1 location changed & observed in loose condition CRH 385-1 ISMC box welding not completed. LHS to be submitted for RT & welding. CRH 365-1 & CRH 355 -1 ISMC box welding not completed. Temporary cleats on pipe to be removed.
1104-02-241S
10 of 33
HP bypass -I outlet 1" screwed coupling was not provided. (Dump steam) LHS to be submitted for RT & SR. 1" screwed coupling was not provided. HP bypass -II outlet LHS to be submitted for RT & SR. (Dump steam) 1" half coupling & 1/2" half coupling orientation changed.
1104-02-241S
12 of 33
Page 3 of 3