GOVERNMENT OF ANDHRA PRADESH

PANCHAYATRAJ ENGINEERING DEPARTMENT HYDERABAD---INDIA

PMGSY PHASE IX

DETAILED ESTIMATE CONSTRUCTION OF BRIDGE @ 0/0 ON ROAD FROM BATHUPURAM TO CHINNAKOATA

CONSTITUENCY ESTIMATED COST DISTRICT CIRCLE DIVISION SUB DIVISION MANDAL

: ICHAPURAM & PALASA : 435.56 lakhs : SRIKAKULAM : SRIKAKULAM : SRIKAKULAM : SOMPETA : SOMPETA & MANDASA

SPECIFICATION REPORT
Name of the work:-Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta Est.Cost.Rs.435.56 lakhs Grant:-NABARD---INDIRAMMA Administrative Sanction:- The work "Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta"
was administratively sanctioned vide GO MS No: 330 PR&RD (Progs II) dated 17.09.10 under PMGSY Phase IX grant.

I.SCOPE: The proposed High level Bridge is connectiong the Bathupuram village to other 9 tribal villages in Mandasa mandal of total 2636 population benifited out of which 1342 are tribals.The objective of the original road ie., Providing BT to the R/F Bathupuram to chinnakosta proposed under PMGSY Phase II will be fulfilled and is very much useful for the transportation of Agricultural products like Paddy,Coconut and other Horticultural products like Cashew,Tribal produces like Termrind,Honey,Vegetables to the Market centres in Sompeta.The nearest railway station,Sompeta is situated at about 15 Kms from the Road.There is heavy pneumatic traffic such as trucks,tractors and iron wheel vehicles,Lorries on the road towards connecting Mandal head quarters and NH-5.

II.PROVISIONS IN THE ESTIMATE(STRENGTHENING OF ROAD UPTO B.T.STANDARDS) 1 Construction of high level T-beam bridge of 7 spans,each span being 16.50m with Pile foundations. Each Abutment has 9 piles of each 1.2mts dia and Pier has 4 piles of each 1.0mt dia.Super structure is consisting of RCC Simply supported T beam without footpaths type with 7.50mts carriage way(Drawings:BD/13-76,BD/14-76&BD/15-76A). 2 Providing Protection works on both sides opf the river and CC pavements to both sides of Bridge approaches to connect existing BT road. III.DESIGN CRITERIA 1 The Highlevel Bridge is designed to carry design speed of 50Kmph 2 The Bridge is of 7Vented 16.50mts effective span with Pile foundations as per MORT&H technical specifications. 3 The width of Bridge is 7.50m and Super structure is Tbeam and slab type as per MOST drawings. 4 The Bridge has 3.30mts approaches with CC pavements and has RCC hand railing as per MOST drawings. 5 The Current SSR of 2010-2011 is adopted. IV LIST OF BENIFITED VILLAGES Name of the village Bathupuram Chinnakosta Peddakosta Gowdaguranti Tallguranti Ambatikambaram Kulladi Tikkarapada Balarampuram Baliabada Kottabathupuram Population 479 619 170 385 242 71 110 139 151 55 215

2636

V.SOCIO-ECONOMIC CONDITIONS A) Market yards: B) Schools/Colleges: Ichapuram,Kanchili,Sompeta a)Ele.Schools b)U.P.Schools c)ZP High Schools 3 Nil Coir Industry,Cashew factories. Coconut,Cashew,Paddy and Forest Products like termarind etc 6 2 1

C) Hospitals: D) Growth Centres: E) Industries: F)Nature of crops grown:

VI.ESTIMATED AMOUNT The estimate for the construction of high level bridge and necessary protection works is prepared for an amount of Rs.435.56 lakhs.

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

INSPECTION REPORT OF THE SUPERINTENDING ENGINEER,PR,SRIKAKULAM Present: Sri.B.Appalanaidu,B.Tech.,(FAC)

Date of inspection Name of the work Estimated Cost Nature of grant Officers Present:

: 25.06.2010 : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road. : Rs.435.56 lakhs : PMGSY Phase IX : Sri.K.M.V.Prasada Rao,Dy.Exe.Engineer,PIU,Sompeta. : Sri.M.Srinivasa Rao,Asst.Exe.Engineer,PIU,Sompeta.

INSPECTION NOTE

The proposed bridge site at Bathupuram was inspected on 25.6.2010. The total width of the river Mahendratanaya is 115m at the proposed site at Bathupuram.During high flood,the width of the river will be even more as per the local enquiry.The river at this point is very deep.The river bed is composing of Coarse,fine sand and silt. The alignment of the existing road from Bathupuram to Chinnakosta has to be altered to the proposed alignment of the bridge as the Bridge alignment should be perpendecular to the stream. Hence,the Deputy Executive,PIU,Sompeta and the Asst.Exe.Engineer,PIU,Sompeta are hereby directed to prepare the Detailed Project Report with the following provisions:1 Depending upon the observation of the high river banks and the road way is above HFL, it is felt that High Level Bridge is necessary . 2 Depending upon the observation of the soil exploration obtained through trial bores and economical aspects,it is felt that Pile foundations may be necessary instead of open foundations as the hard strata(Rock) is available at deeper depth(ie., @ 10 to 11mts from LBL). 3 Depending upon the observation of the stream at HFL condition it is clearely evident that Linear waterway of the stream should not be less than 115mts. 4 As the Bridge is to be connected by an important inter mandal all weather road the carriage way width of 7.5mts is necessary. 5 As the stream is clean and has stright banks,no rifts or deep pools with fair surface the rugosity coefficient(n)may be taken as 0.03. 6 The protection work like revetment with the toe wall to both the banks of the River at Bridge site should be provided. 7 Approach road of 100mts to the Chinnakosta road side of the Bridge and 200mts to the Bathupuram road side of the Bridge should be provided with CC Pavement.

SUPERINTENDING ENGINEER PANCHAYAT RAJ,SRIKAKULAM

GENERAL ABSTRACT
Name of the work:-Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta

S.No

Description of item

Est.Cost:Rs.435.56 lakhs Quantity Amount in Rs As per Sub Estimate As per Sub Estimate -------LS--------------LS-------33644710 6977592 40000 100000

1 2 3 4 5

Construction of High level Bridge Approach Road and protection works Logo bards, Traffic sign boards and other road furniture Provision for Technical Personnels Provision for preparation of DPR,Sub soil exploration,drilling of conformatory bore well and testing etc Provision towards Seinarage charges Provision for VAT 4% Provision for unforseen items if any

-------LS--------------LS--------------LS--------------LS-------TOTAL

400000 767000 1626492 206

6 7 8

43556000

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

DETAILED AND ABSTRACT ESTIMATE (BRIDGE WORK)


Name of the work:-Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta S.No Description of item Nos L Measurements B D Quantity Rate/Per Amount

1 Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and Technical Specifications in Section 1100, 1600 & 1700 MORTH and removal of excavated earth with all lifts and lead upto 1000 m for Piles 1.0mt dia. For Piers 4X7 11.50

322.00 322.00 Rmt

7697.46 1 Rmt

2478581

2 Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and Technical Specifications in Section 1100 & 1700 MORTH and removal of excavated earth with all lifts and lead upto 1000 m for Piles 1.2mt dia. For abutments 9X2 11.70 210.60 210.60 Rmt

9991.81 1 Rmt

2104275

3 Providing MS steel Liner of 5mm thick for piles including fabricating and setting our as per detailed drawings and as per MORT&H speficiations 1200&1900 For Piers For abutments 4X7 9X2 1.00 1.00 28.00 18.00 46.00 Rmt

7587.24 1 Rmt

349013

4 Providing and laying of PCC M15 (Design Mix) leveling course 100mm thick below the pile cap. and 2700(Levelling course below approach slab) Levelling course below Pile cap(Under Piers) 1X7 Levelling course below Pile cap(Under Abutments) Deduct piles portion Levelling course below Approach slab 1X2 7X22/8X2 1X2 5.60 10.60 1.00 3.50 5.60 5.80 1.00 7.85 0.15 18.45 0.15 0.15 0.30 -1.65 16.49 66.22 Cum 32.93

3990.18 1Cum

264230

5 Cement Concrete for Reinforced Concrete in Pile Cap complete as per Drawing and Technical Specifications in Section 1100, 1500 & 1700 MORTH Pier Pile cap Deduct piles portion Abutment Pile cap Deduct piles portion 1X7 7X22/8X4 1X2 2X22/8X9 5.40 1.00 10.40 1.80 5.40 1.00 5.60 1.80 1.50 0.15 1.50 0.15 306.18 -3.30 174.72 -6.87 470.73 Cum

4839.52 1Cum

2278106

6 M25 grade Reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH for Abutments & Piers For piers For abutments 7x22/8 1X2 1.80 9.40 1.80
(1.80+1.2)/2

5.214 1.714

92.83 48.34 141.17 Cum

5525.17 1Cum

779988

7 M25 grade Reinforced cement concrete in Substructure(Return walls upto 10mts height) complete as per drawing and MORT&H technical specifications 1500,1700&2200

For Return walls

1X4

7.60

(0.90+0.45)/2

3.40

69.77 69.77 Cum

5705.99 1Cum

398107

8 M30 grade Reinforced cement concrete in Substructure(Pier cap,Pier hammer head block&Abutment bed block upto 10mts height) complete as per drawing and MORT&H technical specifications 1500,1700&2200

S.No

Description of item

Nos L

Measurements B D
2.10 2.10 1.80 1.200 0.45 0.50 1.80 1.35 0.50 1.986

Quantity

Rate/Per

Amount

Pier Cap Pier Hammer Head Bedblock(middle stright portion) Pier Hammer Head Bedblock(Side Tapper portions) Abutment Bed block Backing wall or Guard wall

1X7 1X7 2X7 1X2 1X2

2.10 2.10 2.15 9.40 9.40

15.44 55.57 36.58 11.28 16.81 135.68 Cum

5709.23 1Cum

774629

9 Reinforced cement concrete M30 grade(upto 5mts) for Bearing Pedastals complete as per drawing and MORT&H technical specifications 1500,1700&2200 For Pier Bearing Pedastals For Abutments Bearing Pedastals 6X7 3X2 0.73 0.75 0.40 0.40 0.15 0.15 1.84 0.27 2.11 Cum

5552.75 Cum

11716

10 Providing and laying reinforced cement concrete M25 in superstructure( Slab & T Beams) as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5 MORD / Sections 1500, 1600 & 1700 MORTH(Height 5 to 10mts) As per MOST drawings 1X8 61.20 489.60 Cum 8135.48 Cum 3983131

11 Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications, in sections 1500, 1600, 1700 & 2703 MORTH. 1X2 140.58

281.16 Rmt

1463.27 1Rmt

411413

12 Providing and laying cement concrete wearing course M 30 grade including reinforcement complete as per drawing and technical specifications Clauses 800 and 1206.3 MORD and 2702 MORTH Wearing coat 1X1 140.58 7.50 0.075

79.08 Cum

5199.39 1Cum

411168

13 Reinforced cement concrete M30 approach slab including reinforcement and formwork complete as per drawing and Technical specification 1500, 1600, 1700 & 2704 MORTH

For Approach slab in between Returns

1X2

3.50

7.95

0.20

11.13 Cum

5355.68 Cum

59609

14 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 MORD & 1100, 1600 MORTH for Bars below 36 mm dia including over laps and wastage, where they are not welded. 90.00 MT 54008.64 MT 4860778

15 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 MORD / Sections 1600 & 2200 MORTH for Bars below 36 mm dia including over laps and wastage, where they are not welded. 70.00 MT 16 Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifications Clauses 1002, 1010 and 1202 MORD / 1600 MORTH, for Bars below 36 mm dia including over laps and wastage, where they are not welded. 130.00 MT 54930.44 MT 7140957 54116.48 MT 3788154

S.No

Description of item

Nos L

Measurements B D

Quantity

Rate/Per

Amount

17 Supplying, fitting and fixing in position true to line and level electrometric bearing conforming to IRC:83 (Part-II) Section IX(fully moulded type Neoprene Rubber Bearings of 500x400x96 mm. in 7 layers of 10 mm. each) complete, including all accessories as per drawings and technical specification Clause 1207.1 MORD For Pier Bearing Pedastals 6X7 63.00 22.00 6.10 For Abutments Bearing Pedastals 3X2 63.00 22.00 6.10

355093.20 50727.60 405820.80 Nos

0.95 1No

386896

18 Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7 MORD / 2706 & 2200 MORTH. In abutments(12X8=96nos per 1 Abutment) In Return walls(6X7=42nos per 1 Return wall) 2X96 4X42 192.00 168.00 360.00 Nos 19 Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8 MORD / 710.14 of IRC, 78 & 2200 MORTH Granular crushed aggregate: behind abutments 1X2 8.50 0.60 3.40 behind returns 1X4 3.50 0.60 3.40 173.01 1No 62283

34.68 28.56 63.24 Cum

1079.68 Cum

68279

20 Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 sqm as per Tech Specification 800 MORTH. For Pile caps sides(2*5.4+2*5.4=21.60) 1X7 21.60 1.50 For Abutment Pile caps 1X2 32.00 1.50 sides(2*10.4+2*5.60=32.0) For Piers(3.14*1.80=5.652) 1X7 5.652 5.21 For Abutments(9.40+2*1.5=12.40) 1X2 12.40 1.71 For Return walls out side 1X4 3.50 3.40 For Pier Caps(1.80*4=7.20) 1X7 7.20 0.50 For Hammer Head Bed 1X7 16.40 1.80 Blocks(1.8*2+6.4*2=16.2) For Abutment Bed 1X2 21.20 1.50 Blocks(9.40*2+1.2*2=21.20) For Super Structure(139.661/0.25=558.664)

226.80 96.00 206.29 42.51 47.60 25.20 206.64 63.60 558.66 1473.30 Sqm

299.92 Sqm

441878

21 Drainage spouts complete as per drawing and technical specifications Clause 1209 MORD & 2705 MORTH 2X45 90.00 No 4950.55 1No 445550

22 Providing and constructing one span service road to reach island location from one pier location to another pier location as per Tech. Specification 1203 MORTH. 1X150 23 Pile Load Test on single Vertical Pile in accordance with IS:2911(Part-IV) and as per Tech Specification 1113 MORTH (Assuming test conducted for 2 out of 52 piles for 150MT each) 1X2 150.00 300.00 MT 24 Painting 2 coats with Plastic Emulsion paint in all shades on new plastered concrete surfaces as per MOT&H technical specifiaction 803 For Piers(3.14*1.80=5.652) 1X7 5.65 5.21 For Abutments(9.40+2*1.5=12.40) 1X2 12.40 1.71 For Return walls out side 1X4 3.50 3.40 For Pier Caps(1.80*4=7.20) 1X7 7.20 0.50 2280.00 1MT 684000 150.00 Rmt 3840.85 1Rmt 576128

206.29 42.51 47.60 25.20

S.No

Description of item
For Hammer Head Bed Blocks(1.8*2+6.4*2=16.2) For Abutment Bed Blocks(9.40*2+1.2*2=21.20) For Super Structure(139.661/0.25=558.664) Hand Railing(B/S) Kerb(0.225+0.225=0.450)(B/S)

Nos L
1X7 1X2 16.40 21.20

Measurements B D
1.80 1.50

Quantity
206.64 63.60 558.66 421.74 189.79 1762.03 Sqm

Rate/Per

Amount

1X2 1X2

140.58 140.58

1.50 0.675

299.92 Sqm LS LS

528475

25 Provision for expansion joints 26 Provision for anti-corrosion treatement (Nitozic Primer) to HYSD steel to prevent corrosion. (1Ltr.per 5 sqm of steel surface and @ Rs. 700/- Ltr) 31 Provision for unforseen items if any

50000 300000

7369

33644710

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR, Srikakulam

DETAILED CUM ABSTRACT ESTIMATE


Name of the work:-Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta

Sub Work: Approach Road and Protection works


Sl No Description of the work 1 1 2 No 3 L 4 Measurements B 5 D 6

Estimate Cost: Rs. Qty 7 Rate 8

69.78
Per

Lakhs Amount 9

Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH For foundation of toe 2 150.00 1.65 1.80 891.00 walls 891.00 129.50 1 Cum Providing M10 concrete for plain/reinforced concrete in open foundations using 40 mm nominal size Graded hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH. For Base cocrete in foundation of toe walls 2 150.00 1.65 0.30 148.50 148.50

115383

3738.27

1 Cum

555134

Providing M15 Grade concrete for plain concrete in open foundations complete as per drawings and MORD technical specifications Clause 802,803,1202&1203 for sub structure items like Toe walls For toe walls 2 150.00 (1.50+0.4 2.50 731.25 5)/2 731.25 3964.29 1 Cum Construction of embankment with approved materials(Quarry Rubbish) from barrow pits with a lift upto 1.50mts ,transporting to site,spreading,grading to the required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000mts as per Technical Specification Clause 301.5 For Levelling of both the banks of the River at Bridge site before Revetment 1800.00

2898884

1800.00 5

247.91

1 Cum

446240

Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specifications Clause 1302 MORD / 2504 MORTH(Gravel Backing for Revetments as per APSS) For rivetment 2 150.00 9.00 0.20 540.00 540.00 430.28 1 Cum 232351

Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical specifications Clause 1302 MORD / 2504 MORTH(Stone boulder) 2 150.00 9.00 0.30 810.00 For rivetment 810.00 528.16 1 Cum Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain (not exceeding 0.6 m depth) and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 MORD / 305 MORTH Both sides to high level As per EW calculation sheet 6306.25 bridge 6306.25 103.75 1 Cum a) Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN static roller / Vibratory Roller 80-100 kN capacity to achieve the desired density, complete as per Technical Specification Clause 402 MORD Bathupuram side 1 200.00 4.00 0.20 160.00 approach road Tallaguranti side 1 150.00 4.00 0.20 120.00 approach road 280.00 540.04 1 Cum

427810

654281

151210

Sl No Description of the work 1 9

Measurements Qty Rate Per L B D 2 3 4 5 6 7 8 Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 MORD. Bathupuram side approach road Tallaguranti side approach road 1 1 200.00 150.00 3.75 3.75 0.20 0.20 150.00 112.50 262.50

No

Amount 9

5667.44

1 Cum

1487704 8596

10

Provision for soil testing and unforseen items if any Total:

6977592

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

DATA SHEET (Bridge work)


Name of the work:-Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta S.No 1
1

Quantity 2

Description 3
Specification 1200, 1500 & 1700 MORTH. PCC Grade M35 Design Mix(Vide 12C Bottom Plug) Case 1 : Using Concrete Mixer

Qty 4

Rate 5

Per

Amount 6

RBR-FNDN-4H Plain cement Concrete complete as per Drawing and Technical

Unit = 1 cum
Taking output = 15 cum

a)

Material
Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate Admixture

6.29 6.75 5.40 5.40 2.70 21.60

5500.00 665.00 894.70 1449.70 1094.70 54.00

MT cum cum cum cum Kg

34595.00 4488.75 4831.38 7828.38 2955.69 1166.40 54699.20 427.50 4493.50 4921.00 2070.00 3720.00 1680.00 2981.01 10451.01 70071.21

b)

Labour
Mason Mazdoor (Unskilled)

1.50 20.90

285.00 Day 215.00 Day

c)

Machinery
Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Light Crane of 3 tonnes capacity for handling tremie pipe
Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe.

6.00 6.00 6.00

345.00 Hour 620.00 Hour 280.00 Hour

cost of 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15

4671.41

RBR-FNDN-25 Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as
per Drawing and Technical Specifications in Section 1100, 1600 & 1700 MORTH and removal of excavated earth with all lifts and lead upto 1000 m.

Pile diameter-1000 mm Unit = meter Taking output = 10 m

a)

Material
PCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12 ( C ) (IV) Concrete to be cast with a tremie pipe 200mm dia.

7.85

4671.41 cum

36670.60

b)

Machinery (for boring and construction) Hire and running charges of hydrulic piling rig with power unit &Bentonite Pum and complete accessories including shifting from one bore location to another Hire and running charges of light crane for lowering reinforcement cage Loader 1 cum bucket capacity Tipper 5.5cum capacity for disposal of muck from pipe bore hole Bentonite Labour Mazdoor (unskilled) (a+b+c) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 10 m = a+b+c+d+d+e Rate per metre (a+b+c+d+e)/10

6.00

4485.00 Hour

26910.00

0.50 0.40 0.40 350.00

280.00 Hour 1320.00 Hour 696.40 Hour 6.00 Kgs

140.00 528.00 278.56 2100.00 29956.56 894.40 894.40 67521.56 9453.02 76974.58

c)

4.16

215.00 Day

d&e)

7697.46
Per Rmt

1
3

3
per Drawing and Technical Specifications in Section 1100 & 1700 MORTH and removal of excavated earth with all lifts and lead upto 1000 m.

RBR-FNDN-26 Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as

Pile diameter-1200 mm Unit = meter Taking output = 9 m

a)

Material
PCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12( C ) (IV) Concrete to be cast with a tremie pipe 200mm dia.

10.17

4671.41 cum

47508.28

b)

Machinery (for boring and construction) Hire and running charges of hydrulic piling rig with power unit &Bentonite Pum and complete accessories including shifting from one bore location to another
Hire and running charges of light crane for lowering reinforcement cage Loader I cum bucket capacity. Tipper 5.5 cum capacity for disposal of muck from pile bore hole Bentonite

6.00

4485.00 Hour

26910.00

0.50 0.50 0.50 385.00

280.00 1320.00 696.40 6.00

Hour Hour Hour Kgs

140.00 660.00 348.20 2310.00 30368.20 1006.20 1006.20 78882.68 11043.58 89926.26

c)

Labour Mazdoor (unskilled) (a+b+c) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 9 m = a+b+c+d+d+e Rate per metre (a+b+c+d+e)/9

4.68

215.00 Day

d&e)

9991.81
Per Rmt

RBR-FNDN-23 Providing MS steel Liner of 5mm thick for piles including fabricating and setting our as per detailed drawings and as per MORT&H speficiations 1200&1900 Unit = 1 MT Material a) Structural steel including 5% wastage Electrodes cutting gas and other consumables @ 5% on cost (a) above b) Labour Fitter Blacksmith Welder Mazdoor (Unskilled) Total (a+b) Over head charges & contractor's profit @ 14% Excluding VAT Rate per 1 MT Rate per Rmt (123.92kg per meter)

1.05

42500.00 MT

44625.00 2231.25 46856.25 1710.00 1300.00 1425.00 2416.60 6851.60 53707.85 7519.10

6.00 5.00 5.00 11.24

285.00 260.00 285.00 215.00

Day Day Day Day

d&e)

61226.95 7587.24
Per Rmt

RBR-FNDN-40 Providing and laying of PCC M15 (Design Mix) leveling course 100mm
thick below the pile cap.

Unit : 1 Cum Taking our put = 15Cum a) Material Cement Coarse Sand 40mm HBG metal 20mm HBG metal 10mm HBG metal Labour Mason Mazdoor (Unskilled) Machinery Consrete Mixer (cap 0.40/0.28 cum)

4.13 6.75 8.10 4.05 1.35

5500.00 665.00 894.70 1449.70 1094.70

MT cum cum cum cum

22715.00 4488.75 7247.07 5871.29 1477.85 41799.95 427.50 4484.90 4912.40 2070.00

b)

1.50 20.86

285.00 Day 215.00 Day

c)

6.00

345.00 Hour

2
Generator 33KVa

3
Total a+b+c Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15

4
6.00

5
620.00 Hour

6
3720.00 5790.00 52502.35 7350.33 59852.68

d&e)

3990.18
Per 1Cum

RBR-FNDN-39 Cement Concrete for Reinforced Concrete in Pile Cap complete as per
Drawing and Technical Specifications in Section 1100, 1500 & 1700 MORTH A. RCC Grade M20 (Design Mix) Unit = cum Taking output = 15 cum

a)

Material Cement Coarse Sand 20mm HBG metal 10mm HBG metal Labour Mason Mazdoor for concreting Mazdoor for breaking pile head,bending bars,cleaning etc., Machinery Consrete Mixer (cap 0.40/0.28 cum) Generator 33KVa

5.12 6.75 8.10 5.40

5500.00 665.00 1449.70 1094.70

MT cum cum cum

28160.00 4488.75 11742.57 5911.38 50302.70 427.50 4493.50 215.00 5136.00 2070.00 3720.00 5790.00 61228.70 2449.15 63677.85 8914.90 72592.75

b)

1.50 20.90 1.00

285.00 Day 215.00 Day 215.00 Day

c)

6.00 6.00

345.00 Hour 620.00 Hour

d) e&f)

Total a+b+c Formwork @ 4% Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15

4839.52
Per 1Cum

RBR-SBST-5

Reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH for Abutments & Piers

VI (i)

R.C.C. grade M 25 (Design Mix)

Unit = Cum
Height upto 5m Case I : Using concrete Mixer

a)

Taking out put = 1cum Material Cement Coarse Sand 20mm HBG metal 10mm HBG metal Labour
Mason (1st Class) Mazdoor (Unskilled)

0.403 0.450 0.540 0.360

5500.00 665.00 1449.70 1094.70

MT cum cum cum

2216.50 299.25 782.84 394.09 3692.68 28.50 298.85 327.35 138.00 248.00 386.00 4406.03 440.61 4846.64 678.53 5525.17 Per 1Cum 4406.03

b)

0.10 1.39

285.00 Day 215.00 Day

c)

Machinery Consrete Mixer (cap 0.40/0.28 cum) Generator 33KVa

0.40 0.40

345.00 Hour 620.00 Hour

d) e&f)

Total a+b+c Formwork @ 10% Over head charges & contractor's profit @ 14% Excluding VAT
Rate per cum = a+b+c+d+e+f
(ii)

Height 5m to 10m Basic Cost of Labour, Material & Machinery (a+b+c) of Item VI (i) Case I excluding of Formwork

2
d)

3
Add on cost of material, labour and machinery (a+b+c) for Formwork Add on cost of material, Labour and machinery excluding formwork to cater for extra lift

6
519.91 79.31 5005.25 700.74 5705.99

e&f)

Over head charges & contractor's profit @ 14% Excluding VAT


Rate per cum = a+b+c+d+e+f

RBR-SBST-5

M30 grade Reinforced cement concrete in Substructure(Pier cap,Pier hammer head block&Abutment bed block upto 10mts height) complete as per drawing and MORT&H technical specifications 1500,1700&2200
RCC Grade M30 (Design Mix) Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4 (G) Case I excluding of Formwork Height 5m to 10m

RBR-FNDN-4

a)

Unit = 1 Cum Taking out put = 1cum Material Cement Coarse Sand 20mm HBG metal 10mm HBG metal Labour Mason Mazdoor Machinery Consrete Mixer (cap 0.40/0.28 cum) Generator 33KVa

0.407 0.45 0.54 0.36

5500.00 665.00 1449.70 1094.70

MT cum cum cum

2238.50 299.25 782.84 394.09 3714.68 28.50 298.85 327.35 138.00 248.00 386.00 4428.03 509.22 70.85 5008.10 701.13 5709.23 Per 1Cum

b)

0.10 1.39

285.00 Day 215.00 Day

c)

0.40 0.40

345.00 Hour 620.00 Hour

d)

Total a+b+c Add on cost of material, labour and machinery (a+b+c) for Formwork Add on cost of material, Labour and machinery excluding formwork to cater for extra lift

11.50% 1.60%

e&f)

Over head charges & contractor's profit @ 14% Excluding VAT


Rate per cum = a+b+c+d+e+f

RBR-SBST-5

Reinforced cement concrete M30 grade(upto 5mts) for Bearing Pedastals complete as per drawing and MORT&H technical specifications 1500,1700&2200
RCC Grade M30 (Design Mix) Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4 (G) Case I excluding of Formwork ie., (a+b+c) of 7th item

4428.03

d)

Add on cost of material, labour and machinery (a+b+c) for Formwork

10.00%

442.80 4870.83 681.92 5552.75

e&f)

Over head charges & contractor's profit @ 14% Excluding VAT


Rate per cum = a+b+c+d+e+f

10

RBR-SPST-1

Providing and laying reinforced cement concrete M25 in superstructure( Slab & T Beams) as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5 MORD / Sections 1500, 1600 & 1700 MORTH(Height 5 to 10mts) R.C.C M 25 Grade (Design Mix)

a)

Unit = 1 Cum Taking out put = 15cum Material Cement Coarse Sand 20mm HBG metal 10mm HBG metal Labour Mason Mazdoor

0.60 0.45 0.54 0.36

5500.00 665.00 1449.70 1094.70

MT cum cum cum

3300.00 299.25 782.84 394.09 4776.18 28.50 298.85

b)

0.10 1.39

285.00 Day 215.00 Day

2
c)

3
Machinery Consrete Mixer (cap 0.40/0.28 cum) Generator 33KVa

6
327.35

0.40 0.40

345.00 Hour 620.00 Hour

138.00 248.00 386.00 5489.53 1646.86 7136.39 999.09 8135.48 Per 1Cum

d)

Total a+b+c Formwork @ 30%(Height between 5 to 10mts) Over head charges & contractor's profit @ 14% Excluding VAT

11

RBR-FNDN-7

Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 MORD & 1100, 1600 MORTH for Bars below 36 mm dia including over laps and wastage, where they are not welded.

Unit = 1 MT Taking out put = 1MT a) Material HYSD bars including 5% wastage and overlaps Binding wire
Labour for cutting, bending, shifting to site, tying and placing in position

1.05 6.00

43000.00 MT 55.00 MT

45150.00 330.00 45480.00

b)

Blacksmith Mazdoor (Unskilled)

2.00 6.40

260.00 Day 215.00 Day

c&d)

Over head charges & contractor's profit @ 14% Excluding VAT

520.00 1376.00 1896.00 47376.00 6632.64

54008.64
Per 1MT 12 RBR-SBST-6
Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 MORD / Sections 1600 & 2200 MORTH for Bars below 36 mm dia including over laps and wastage, where they are not welded.

Unit = 1 MT Taking out put = 1MT a) Material HYSD bars including 5% wastage and overlaps Binding wire
Labour for cutting, bending, shifting to site, tying and placing in position

1.05 6.00

43000.00 MT 55.00 MT

45150.00 330.00 45480.00

b)

Blacksmith Mazdoor (Unskilled)

2.00 6.84

260.00 Day 215.00 Day

c&d)

Over head charges & contractor's profit @ 14% Excluding VAT

520.00 1470.60 1990.60 47470.60 6645.88

54116.48
Per 1MT 13 RBR-SPST-2
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifications Clauses 1002, 1010 and 1202 MORD / 1600 MORTH, for Bars below 36 mm dia including over laps and wastage, where they are not welded.

Unit = 1 MT Taking out put = 1MT a) Material HYSD bars including 5% wastage and overlaps Binding wire
Labour for cutting, bending, shifting to site, tying and placing in position

1.05 8.00

43000.00 MT 55.00 MT

45150.00 440.00 45590.00

b)

Blacksmith Mazdoor (Unskilled)

3.00 8.44

260.00 Day 215.00 Day

780.00 1814.60 2594.60 48184.60

2
c&d)

3
Over head charges & contractor's profit @ 14% Excluding VAT

6
6745.84

54930.44
Per 1MT 14 RBR-SPST-7 (ii) Construction of precast RCC railing of M30 Grade, aggregate size not
exceeding 12 mm, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications, in sections 1500, 1600, 1700 & 2703 MORTH.

Unit = 1 Rmt Taking out put = 2X24mts span=48mts. a) Material i) Cement concrete M30 Grade Refer relevant item of concrete in Item 14.1(C)
by using batching plant, excluding formwork i.e. per cum basic cost (a+b+c) of 7th item
No. of vertical posts = (12 + 2)2 = 28 Nos., External area of vertical post 0.25x0.275 = 0.069sqm, Concrete in Vertical posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD / 202).

4.092

4428.03 cum

18119.50

Add @10% (5%for formwork & 5% for handling and fixing of precast panels in position

1811.95 19931.45 41679.68 61611.13 8625.56 70236.69

ii) HYSD bar reinforcement Rate as per item No 14.2 (Excluding OH & CP)

0.865

48184.60 MT

b&c) Over head charges & contractor's profit @ 14% Excluding VAT
Rate for 48 m (a+b+c) Rate per metre (a+b+c)/48

1463.27
Per 1Rmt

15

RBR-SPST-5

Providing and laying cement concrete wearing course M 30 grade including reinforcement complete as per drawing and technical specifications Clauses 800 and 1206.3 MORD and 2702 MORTH

a)

Unit = 1 Cum Taking out put = 1cum Material Cement Coarse Sand 20mm HBG metal 10mm HBG metal Labour
Mason (1st Class) Mazdoor (Unskilled) Mazdoor (Unskilled) for cleaning deck slab concrete surface

0.407 0.45 0.54 0.36

5500.00 665.00 1449.70 1094.70

MT cum cum cum

2238.50 299.25 782.84 394.09 3714.68 28.50 298.85 32.25 327.35 138.00 248.00 386.00 4428.03 132.84 4560.87 638.52

b)

0.10 1.39 0.15

285.00 Day 215.00 Day 215.00 Day

c)

Machinery Consrete Mixer (cap 0.40/0.28 cum) Generator 33KVa Total a+b+c Formwork @ 3% of cost of concrete Over head charges & contractor's profit @ 14% Excluding VAT
Rate per cum = a+b+c+d+e+f

0.40 0.40

345.00 Hour 620.00 Hour

d) e&f)

5199.39
Per 1Cum

16

Reinforced cement concrete M30 approach slab including reinforcement and formwork complete as per drawing and Technical specification 1500, 1600, 1700 & 2704 MORTH

a)

Unit = 1 Cum Taking out put = 15cum Material Cement Coarse Sand 20mm HBG metal 10mm HBG metal

6.10 6.75 8.10 5.40

5500.00 665.00 1449.70 1094.70

MT cum cum cum

33550.00 4488.75 11742.57 5911.38 55692.70

2
b) Labour Mason Mazdoor

4
1.50 20.86

5
285.00 Day 215.00 Day

6
427.50 4484.90 4912.40 2070.00 3720.00 5790.00 66395.10 1327.91 2746.522 70469.53 9865.73 80335.26

c)

Machinery Consrete Mixer (cap 0.40/0.28 cum) Generator 33KVa

6.00 6.00

345.00 Hour 620.00 Hour

d) e) f&g)

Total a+b+c Formwork @ 2%


HYSD bar reinforcement Rate as per item No 12 (Excluding OH&CP)

0.05

54930.44

Over head charges & contractor's profit @ 14% Excluding VAT


Rate per 15cum = a+b+c+d+e+f Rate per metre (a+b+c+d+e+f+g)/15

5355.68
Per 1Cum

17

RBR-SBST-9

Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7 MORD / 2706 & 2200 MORTH.

Unit = Nos Taking out put = 30Nos a) Material


AC pipe 100 mm dia including wastage @ 5 per cent. Average length of weep hole is taken as one metre for the purpose of estimating

31.50 30.00
10.00%

138.10 Rmt

4350.15 435.02 4350.15

MS clamps Collar for AC pipe (average taking 10% of above pipe rate) Cement mortar 1:3 (For rate refer to item 11.5 I)

b)

Labour Mason Mazdoor (Unskilled)

0.50 0.28

285.00 Day 215.00 Day

c&d)

Over head charges & contractor's profit @ 14% Excluding VAT


Cost for 30 Nos = (a+b+c+d) Rate per No = (a+b+c+d)/30

142.50 60.20 202.70 4552.85 637.40 5190.25

173.01
Per 1No

18

RBR-SBST-11 Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8 MORD / 710.14 of IRC, 78 & 2200 MORTH

Unit = 1 Cum Taking output =10cum a) Labour Mazdoor for filling,watering&ramming Mazdoor (Skilled) Material Filter media of stone aggregate confirming to clause 2504.2.2 of MORT&H specifications Cost of materials Filter media as per specification(50% soling stone of 150mm dia and 50% 40mm HBG metal) Machinery Water tanker 6Kl capacity Basic rate (a+b+c) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 10 cum of granular backfill = a+b+c+d+e Rate per cum = (a+b+c+d+e)/10

7.32 1.00

215.00 Day 215.00 Day

1573.80 215.00 1788.80

b)

12.00

638.45 Cum

7661.40

c)

0.06

345.00 Hour

d&e)

20.70 9470.90 1325.93 10796.83

1079.68
Per 1Cum

1
19

3
conforming to IRC:83 (Part-II) Section IX(fully moulded type Neoprene Rubber Bearings of 500x400x96 mm. in 7 layers of 10 mm. each) complete, including all accessories as per drawings and technical specification Clause 1207.1 MORD

RBR-SBST-12 Supplying, fitting and fixing in position true to line and level electrometric bearing

Unit = cubic centimeter


Considering an electrometric bearing of size 500 x 400 x 96 mm for this analysis,

Overall volume = 19200 cu.cm Volume of 6 Nos 488x388x4 mm size reinforcing steel plates = 4545cu.cm. Hence volume of elastomer = 14655 cu. cm.

a)

Taking out put = 14655cu.cm Labour Mazdoor (Unskilled) Mazdoor (Skilled) Material
Electrometric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the process of vulcanisation, complete with all components as per drawing and technical specification

1.06 0.50

215.00 Day 215.00 Day

227.90 107.50 335.40 9600.00

b)

19200.00

0.50 CC

c&d)

Over head charges & contractor's profit @ 44%(30+14) Excluding VAT


Cost for 14655 cu.cm. of elastomeric bearing = a+b+c+d Rate per cu.cm of elastomeric bearing = (a+b+c+d)/14655
Note : For such type of manufactured item, the overhead cost is taken as 30 per cent instead of 20 per cent

4371.58 13971.58

0.95
Per 1cu.cm

20

RBR-SPST-11 Drainage spouts complete as per drawing and technical specifications


Clause 1209 MORD & 2705 MORTH

Unit = Nos Taking out put = 1No a) i) ii) iii) iv) b) Material Corrosion Resistant structural steel grating including 5% wastages GI pipe of 65mm dia GI Bolts 10mm dia Galvanised MS flat clamp Labour For fabrication Skilled Blacksmith,welder etc., Mazdoor (Unskilled)
For fixing in position Mason (1st Class) Mazdoor (Unskilled) Add @ 5 per cent of cost of material and labour (a+b) for electrodes, gas cutting, sealant, anti-corrosive bituminous paint, mild steel grating etc.

4.00 6.00 6.00 2.00

42500.00 575.00 19.00 170.00

MT Mts Nos Nos

170.00 3450.00 114.00 340.00

0.02 0.04 0.01 0.21


5.00%

260.00 Day 215.00 Day 285.00 Day 215.00 Day

5.20 8.60 2.85 45.15 4135.80 206.79 4342.59 607.96

c&d)

Over head charges & contractor's profit @ 14% Excluding VAT

4950.55
Per 1No 21 RBR-SPST-26 Providing and applying 2 coats of water based cement paint to unplastered
concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 sqm as per Tech Specification 800 MORTH.

a)

Unit = 1 Sqm Taking out put = 10Sqm Labour Painter Mazdoor (skilled)

0.25 0.26

300.00 Day 215.00 Day

75.00 55.90 130.90

b)

c&d)

Material Water based paint (Chromium Rubberised)of approved quality for cement concrete surface Total (a+b) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 10 sqm (a+b+c+d) Rate per sqm (a+b+c+d)/10

5.00

500.00 Lts

2500.00 2630.90 368.33 2999.23

299.92

6
Per 1Sqm

22

RBR-FNDN-38 Pile Load Test on single Vertical Pile in accordance with IS:2911(Part-IV)
and as per Tech Specification 1113 MORTH

a) b)

Unit = 1 MT Taking out put = 1MT Initial and routine load test Lateral load test
Note : Although, this item is incidental to work and is not required to be included in BOQ of contract, the same is required to be added in the estimate to assess cost of work.

1.00 1.00

1000.00 MT 1000.00 MT

1000.00 1000.00

Total a+b Over head charges & contractor's profit @ 14% Excluding VAT Rate per 1 MT

2000.00 280.00

2280.00
Per 1MT

23 RBR-FNDN-10 Providing and constructing one span service road to reach island
location from one pier location to another pier location as per Tech. Specification 1203 MORTH.

Assuming span length 30 mts, width of service road is 10mts and depth of water 3mtr Unit = 1 Mtr Taking out put = 30Mts a) i) ii) b) Material Earth(3*450=1350) Sand Bags(3*300=900)(Rate as per SSR New Item 2 page38) Labour Mazdoor for filling sand bags,stiching and placing(3*6.24=18.72) 1350.00 900.00 27.00 Cum 17.00 Nos 36450.00 15300.00 51750.00 18.72 215.00 Day 4024.80 4024.80

c)

Machinery Front end Loader 1 cum capacity Tipper 5.5 cum capacity

27.00 28.00

1320.00 Hour 345.00 Hour

35640.00 9660.00 45300.00 101074.80 14150.47 115225.27

d&e)

Over head charges & contractor's profit @ 14% Excluding VAT


Cost for 30 m = (a+b+c+d+e) Rate per m = (a+b+c+d+e)/30

3840.85
Per 1Rmt

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

LEADE STATEMENT (Bridge work)


Name of the work:-Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta
Sl.N o. Meterial Name of the Quarry 3 Venkatapuram Venkatapuram Venkatapuram Venkatapuram Venkatapuram Venkatapuram Bahuda River Bahuda River Rate approved by GOAP Rate approved by GOAP Rate approved by GOAP Distance (km) Unit Initial Cost 6 500.00 844 688 560 260 57.5 285 210 5500 43000 42500 Blasting Charges Machine Conveyan crushing ce charges 7 8 9 70.00 324.70 70.00 70.00 70.00 70.00 211.00 172.00 140.00 324.70 324.70 324.70 324.70 324.70 380.00 380.00 Deduct stocking charges 11 Net Amount 12 894.70 1449.70 1254.70 1094.70 654.70 382.20 665.00 590.00 5500.00 43000.00 42500.00

1 2 1. 40MM HBG metal SS5 2. 20MM HBG Chips SS5 3 4 5 6 7 8 9 12MM HBG Chips SS5 10MM HBG Chips SS5 75MM HBG Chips SS5 Soling stone 150mm dia Sand for Motor Sand for Filling Cement

4 5 33.00 1 Cum 33.00 1 Cum 33.00 1 Cum 33.00 1 Cum 33.00 1 Cum 33.00 1 Cum 40.00 1 Cum 40.00 1 Cum 1 MT 1 MT 1 MT

10 HYSD Steel Bars 11 Structural steel

1 2 3 4

Certified that the above leads are correct and nearest to the best of my knowledge Certified that the materials are available in sufficient quantities. Certified that the required metal and stone required blasting. The estimate is prepared based on SSR 2008-2009.

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR, Srikakulam

Data sheet for Road cum Bridge Protection works


S.NoSpecification/ Quantity 1
1

Description
3

Qty 4

Rate 5

Per

Amount 6

Excavation of structures:
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and RBR-FNDN-1 other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH

Ordinary soil

(I)

Upto 3 m. depth
Unit = cum Taking outpuot = 10 cum Labour Mazdoor unskilled Seinorage charges Dewatering charges @ 10% Cost of Shoring and shuttering @3% Basic rate per Cum Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10

(a)

3.64 10.00

215.00 day 22.00 cum

(b)

782.60 220.00 1002.60 100.26 1102.86 33.09 1135.95 159.03 1294.98

129.50

(II)

3 Mts to 6Mts depth


Unit = cum Taking outpuot = 10 cum Labour Mazdoor unskilled Seinorage charges Dewatering charges @ 15% Cost of Shoring and shuttering @10% Basic rate per Cum Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10

(a)

4.68 10.00

215.00 day 22.00 cum

(b)

1006.20 220.00 1226.20 183.93 1410.13 141.01 1551.14 217.16 1768.30

176.83

(III)

Above 6mts depth


Unit = cum Taking outpuot = 10 cum Labour Mazdoor unskilled Seinorage charges Dewatering charges @ 20% Cost of Shoring and shuttering @10% Basic rate per Cum Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 10 cum = a+b+c

(a)

6.24 10.00

215.00 day 22.00 cum

(b)

1341.60 220.00 1561.60 312.32 1873.92 187.39 2061.31 288.58 2349.90

Rate per cum = (a+b+c)/10

234.99

Filling in foundation trenches as per drawing and

RBR-FNDN-2 technical specification Clause 305.3.9 MORD & 304


I

MORTH Sand filling

a)

Unit=Cum Taking out put=1 cum Material Sand Labour Mazdoor (Unskilled)

1.000

590.00 cum

590.00 590.00 66.65 66.65 656.65 91.93 748.58 Per 1Cum

b)

0.31

215.00 Day

(b)

Total a+b Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 1 cum = a+b+c

3 RBR-FNDN4(ii)

Providing M10 concrete for plain/reinforced concrete in open foundations using 40 mm nominal size Graded hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH.

a)

Unit=Cum Taking out put=1 cum Material Cement Coarse Sand 40mm HBG metal 20mm HBG metal 10mm HBG metal Labour Mason Mazdoor (Unskilled) Machinery Consrete Mixer (cap 0.40/0.28 cum) Total a+b+c

0.22 0.45 0.57 0.28 0.05

5500.00 665.00 894.70 1447.53 1092.53

MT cum cum cum cum

1210.00 299.25 509.98 405.31 54.63 2479.16 28.50 507.40 535.90 138.00 138.00 3153.06 126.12 3279.18 459.09 3738.27 Per 1Cum

b)

0.10 2.36

285.00 Day 215.00 Day

c)

0.40

345.00 Hour

d)

Formwork @ 4% on cost of material, labour and machinery (a+b+c)

Total a+b+c+d Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 1 cum = a+b+c

Providing M15 Grade concrete for plain concrete in open foundations complete as per drawings and MORD RBR-SBST-5 technical specifications Clause 802,803,1202&1203 for sub structure items like Toe walls Unit=Cum Taking out put=1 cum Material Cement Coarse Sand 40mm HBG metal

a)

0.275 0.480 0.480

5500.00 MT 665.00 cum 894.70 cum

1512.50 319.20 429.46

20mm HBG metal 10mm HBG metal b) Labour Mason Mazdoor (Unskilled) Machinery Consrete Mixer (cap 0.40/0.28 cum)

0.240 0.08

1447.53 cum 1092.53 cum

347.41 87.40 2695.96 28.50 298.85 327.35 138.00 138.00 3161.31 316.13 3477.45 486.84 3964.29 Per 1Cum

0.10 1.39

285.00 Day 215.00 Day

c)

0.40

345.00 Hour

( a+b+c) 10% towards Form work(a+b+c) Total( a+b+c) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 1 cum = a+b+c

Construction of embankment with approved materials(Quarry Rubbish) from barrow pits with a lift upto 1.50mts ,transporting to site,spreading,grading to RBR-EECD-4 the required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000mts as per Technical Specification Clause 301.5 Unit=Cum Taking out put=1 cum Labour Mazdoor (Unskilled) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum per hour

a) b)

1.04 1.67 4.50 0.50 0.50 2.00 1.25

215.00 Day 2009.50 Hour 696.40 Hour 1175.63 Hour 2600.00 Hour 345.00 Hour 844.40 Hour

223.60 223.60 3355.87 3133.80 587.81 1300.00 690.00 1055.50

Tipper 5.5 cum with 10 t capacity Dozer D-50 for spreading @ 200 cum per hour(1881 X 50 /80= 1175.63) Motor grader for grading @ 200 cum per hour Water tanker 6 kl capacity Three wheel 80-100 kN Static Roller @ 80 cum per hour or Vibratory Roller 80 - 100 kN @ 100 cum per hour

10122.98 c) Material Water Cost of quarry rubbish including conveyance 12.000 100.000 0.00 kl 114.00 cum 0.00 11400.00 11400.00 21746.58 3044.52 247.91 Per 1Cum

Total( a+b+c) Over head charges & contractor's profit @ 14% Excluding VAT Rate per 1Cum (a+b+c)/100

Providing and laying filter material underneath pitching in slopes complete as per drawing and technical RBR-PTWK-7 specifications Clause 1302 MORD / 2504 MORTH(Gravel Backing for Revetments as per APSS)

a) b)

Unit=Cum Taking out put=1 cum Labour Mazdoor (Unskilled) Material Gravel

1.10 1.160

215.00 Day 121.50 cum

Total( a+b) Over head charges & contractor's profit @ 14% Excluding VAT

236.50 236.50 140.94 140.94 377.44 52.84

Cost for 1 cum = a+b+c

430.28 Per 1Cum

Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical RBR-PTWK-5 specifications Clause 1302 MORD / 2504 MORTH(Stone boulder)

a)

b)

Unit=Cum Taking out put=1 cum Labour Mason(Ist class) Mazdoor (Unskilled) Material Stone Boulder(25Kg minumum) Stone spalls of minimum 25mm size

0.35 0.79 1.000 0.200

285.00 Day 215.00 Day 173.50 cum 101.00 cum

Total( a+b) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 1 cum = a+b+c

99.75 169.85 269.60 173.50 20.20 193.70 463.30 64.86 528.16 Per 1Cum

a)

b)

Cement Mortor 1:3) Unit=Cum Labour Mazdoor (Unskilled) Bisti Material Cement Sand (a+b)

0.90 0.08 0.330 0.150

215.00 Day 260.00 Day 5500.00 cum 665.00 cum

193.50 20.80 1815.00 99.75 2129.05

8 RBR-SBST-4

Stone masonry in cement mortar for substructure complete as per drawing & technical specification Clauses 702, 704, 1202 & 1204 MORD and 1400 & 2200 MORTH

a)

b)

Unit=Cum Labour Mason(Ist class) Mazdoor (Unskilled) Material Stone for CR masnory 1st sort
Through and bond stone (7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)As per SSR Item SS 28 Page 157

2.50 2.32
0.94 7.00

285.00 Day 215.00 Day 281.50 cum 25.00 Nos

712.50 498.80 1211.30 264.61 175.00

CM(1:3) (a+b)

0.28

2129.05 cum

596.13 1035.74 2247.04 Per 1Cum

Providing and laying flooring laid over cement concrete bedding with M 10 grade complete as per drawing and RBR-PTWK-8 technical specification Clause 1303 MORD(With CR Masnory)

a)

b)

Unit=Cum Taking out put=1 cum Labour Mason(Ist class) Mazdoor (Unskilled) Material Coursed Rubble masnory in CM(1:3)

0.50 1.50 0.330

285.00 Day 215.00 Day 2247.04 cum

142.50 322.50 465.00 741.52

PCC M10 concrete bedding(without d,e&f items)

0.150

3279.18 cum

Total( a+b) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 1 cum = a+b+c

491.88 1233.40 1698.40 237.78 1936.18 Per 1Cum

10

Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels, RBR-CCPV-5 rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 MORD.

a)

Unit=Cum Taking out put=75 cum Material Cement@350Kgs per cum of concrete Coarse sand@0.45 Cum per Cum of concrete Crushed stone aggregate 20mm size@0.60 Cum per cum of concrete Crushed stone aggregate 12mm size@0.30 Cum per cum of concrete Recron 3S synthetic fibres Polythene sheet 125 micron Mild steel dowel bars of 25mm dia of grade S240,20 Nos each having length 500mm at bridge slab and construction joint including 5% wastage(4X20X0.50)+5% = 42m@2.80 Kg per m= 117.6 Kgs Bitumen primer@200ml per joint for 23 joints Bitumen sealant@800ml per joint for 23 joints Jute rope 12mm dia including 5% wastage Debonding strips 3.75mX10mmX5mm cut out from rubber filler board or similar material including 5% wastage Polythene sheathing,covering 2/3rd dowel bars(20X23) and tight fit including 5% wastage Plasticizer 0.5 percent by wt.of cement Curing compound@ 0.33 litre per sqm Joint filler board 20mm thick Labour
Mason (1st class) Mason (2nd class) Mazdoor (Unskilled) Mazdoor (Skilled) Surveyor Mazdoor (Semi-Skilled) Blacksmith for cutting of dowel bars including removal of burrs, fabrications & fixing of dowel bars.

26.250 33.750 44.550 22.950 65.625 412.5 117.6

5500.00 MT 665.00 cum 1447.53 cum 1092.53 cum 240.00 cum 15.00 Sqm 41.00 kg

144375.00 22443.75 64487.24 25073.45 15750.00 6187.50 4821.60

0.005 19 90 90

29701.60 26.00 5.00 9.00

MT lt Rmt Rmt

148.51 494.00 450.00 810.00

483 122 131.25 3

0.50 No 57.00 lt 57.00 lt 732.00 Sqm

241.50 6954.00 7481.25 2196.00 301913.80 1425.00 1300.00 32250.00 1290.00 520.00 1290.00 260.00

b)

5.00 5.00 150.00 6.00 2.00 6.00 1.00

285.00 260.00 215.00 215.00 260.00 215.00 260.00

Day Day Day Day Day Day Day

38335.00 c) Machinery
Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh batcher and suitable capacity calibrated water tank Needle vibrator

36.00

345.00 Hour

12420.00

Screed vibrator Plate vibrator


Concrete joint cutting machine for initial & final cuts

Water tanker 6kl capacity


Air Compressor (1 hour initial + 1 hour final)

9.00 9.00 9.00 4.00 5.00 2.00

120.40 287.30 201.70 345.00 345.00 370.00

Hour Hour Hour Hour Hour Hour

1083.60 2585.70 1815.30 1380.00 1725.00 740.00 21749.60 361998.40 10859.95 4971.44 696.00 5667.44 Per 1Cum

( a+b+c) 3% towards Form work(a+b+c) Cost of 1cum =( a+b+c)/75 Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 1 cum = a+b+c

11 RBR-EECD-3

Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain (not exceeding 0.6 m depth) and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 MORD / 305 MORTH

a) b)

c)

Unit=Cum Taking out put=100 cum Labour Mazdoor (Unskilled) Machinery Hydraulic excavator 0.9 cum capacity@60 cum per hour Dozer D-50 for spreading @ 200 cum per hour Motor grader for grading @ 200 cum per hour Water tanker 6 kl capacity Three wheel 80-100 kN Static Roller Material Water seinarage charges

0.52 1.67 0.50 0.50 2.00 1.25 12.000

215.00 Day 2009.50 Hour 1175.63 2600.00 345.00 844.40 Hour Hour Hour Hour

111.80 111.80 3355.87 587.81 1300.00 690.00 1055.50 6989.18 0.00 2000.00 2000.00 9100.98 1274.14 103.75 Per 1Cum

0.00 kl

Total( a+b+c) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 1 cum =( a+b+c)/100

12 RBR-SBBS2B(iii)

a) Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN static roller / Vibratory Roller 80-100 kN capacity to achieve the desired density, complete as per Technical Specification Clause 402 MORD

a)

b)

Unit=Cum Taking out put=300 cum Labour Mazdoor (Skilled) Mazdoor (Unskilled) Machinery Motor grader for grading @ 200 cum per hour

2.40 8.00 6.00

215.00 Day 215.00 Day 2600.00 Hour

516.00 1720.00 2236.00 15600.00

Vibratory Roller 80-100 kN

Water tanker 6 kl capacity


Tractor with Rotavator 25 cum per hour

6.00 5.00 12.00 255.000 129.000

1886.90 Hour 345.00 Hour 345.00 Hour 121.50 cum 590.00 cum

c)

Material 9.5 mm to 4.75 mm @ 66 per cent(Gravel) Sand 2.36 mm below @ 34 per cent

Total( a+b+c) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 1 cum =( a+b+c)/300

11321.40 1725.00 4140.00 32786.40 30982.50 76110.00 107092.50 142114.90 19896.09 540.04 Per 1Cum

13 RBR-PTWK-1

Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table 1300.1, no fragment weighing less than 25 / 40 kg laid dry complete as per drawing and technical specifications Clause 1301 MORD / 2503 MORTH

a)

Unit=Cum Taking out put=1 cum Labour


Mason (1st class)

Mazdoor (Unskilled) b) Material


Stone boulder (25 kg / 40 Kg minimum) Stone spalls

0.35 0.79

285.00 Day 215.00 Day

99.75 169.85 269.60 219.50 20.20 239.70 509.30 71.30 580.60 Per 1Cum

1.00 0.20

219.50 cum 101.00 cum

Total( a+b) Over head charges & contractor's profit @ 14% Excluding VAT
Cost for 1 cum =( a+b+c)/100

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

LEAD STATEMENT(Protection works)


Name of the work:-Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta Est.Cost:- Rs.435.56 lakhs
S.No Description of item Name of the quarry Lead in Kms Total 3 6 Mamidipalli 5.00 Bahuda River 40.00 Bahuda River 40.00 Mamidipalli 5.00 Venkatapuram 33.00 Venkatapuram 33.00 Venkatapuram 33.00 Mamidipalli 5.00 Venkatapuram 33.00 Mamidipalli 5.00 Mamidipalli 5.00 Mamidipalli 5.00 Mamidipalli 5.00 Rate approved by GOAP Initial Cost Conveyance Blasting charges Machine Deduct Total crushing stacking charges 10 0.00 0.00 0.00 0.00 0.00 208.83 137.83 0.00 0.00 0.00 0.00 0.00 0.00 11 12 121.50 590.00 665.00 173.50 894.70 1447.53 1092.53 114.00 382.20 219.50 173.50 101.00 281.50 5500.00

1 1 2 3 4 5 6 7 8 9 10 11 12 13 14

2 Gravel Sand for filling Sand for Mortar Rough stone OTG for revetment--300mm 40mm HBG metal-SS5 20mm HBG metal-SS5 10mm HBG metal-SS5 Quarry rubbish Soling stone 150mm size Jeddy stone for aprons 450 to 600mm size Rough stone 300mm dia for SS Revetment Stone spalls of OTG 25mm CR stone Ist sort Cement(including 1% storage charges)

7 58.00 210.00 285.00 110.00 500.00 844.00 560.00 50.50 57.50 156.00 110.00 37.50 218.00 5500.00

8 63.50 380.00 380.00 63.50 324.70 324.70 324.70 63.50 324.70 63.50 63.50 63.50 63.50

9 0.00 0.00 0.00 0.00 70.00 70.00 70.00 0.00 0.00 0.00 0.00 0.00 0.00

Certified that the above leads are correct to the best of my knowledge

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

QUARRY CHART
Name of the work:-Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta

VIZAG
2Km 171/0 HBG Quarry Venkatapuram

Mahendratanaya River

Thalla Guranti 15/0 14/0

Bathupuram Proposed Bridge site Mamidipalli Gravel Quarry 1Km 202/0 198/0 0/0 BRC Puram 3/7

228/0 Bahuda River Sand Ichapuram

Sand 228 -202 14 40

Gravel 202 -198 1 5

HBG 202 -171 2 33

Asst.Exe.Engineer PIU,Sompeta

Dy.Exe.Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

DESIGN CALCULATIONS FOR TOE WALL


A)Design data:-:Angle of internal friction ' Q ' = Unit Wieght of Soil ' r ' = Coefficient of Active Earth pressure ' K a ' = Unit Weight of concrete ' p ' = Height of wall ' h ' = Width of wall at Top ' b1 ' = Design:Let the width of the wall at bottom be ' b2 ' 30 18KN/cum 1/3 16KN/cum 2.50m 0.45m
0

B R W
2

Active Earth pressure Pa

= 1/2Ka r h = 18.73KN/m

It acts horizontally at a height of h/3 from the base(Since there is no inclined surcharge and the face of the wall is vertical) The Wt.of the wall acting down wards through the centroid of the wall section ' W ' = 9.00 +20b2 Let ' R ' be the resultant of the above forces acting through the intersection of the above forces with components RH and RV For no tension to develop,the resultant should pass through the middle third of the base, taking limiting case, R should act at 2b2/3 from heel ' B ' From the condition of equilibrium of forces, RH = Pa RV = W and Sum of moments of ' W ' and ' Pa ' about " B " should be equal to the moment of resultant ' R ' about ' B' RV X 2b2/3 = W 1Xb1/2 + W 2[b1+(b2-b1)/3] + PaXh/3
2 6.67 b2 +

3.00b2

-16.959375

=0

Solving b2 = 1.39m However provide 1.50m width at the bottom

Hence Bottom width b2 = Check For Safety Against Sliding:-

1.50m

Wt.of the wall ' W ' =

39.00KN/m

Factor of safety against sliding is given by F =WTan Q/Pa 1.200429 > 1.50Hence Safe Check For Stresses:-

Taking moments about ' B ' 39.00a = Hence ' a ' = 0.93 0.18485577 36.459375

Hence eccentricity ' e ' = Maximum stress =

W/b2(1+6e/b2) = 45.2 < 120KN/M (Bearing Capacity)


2

Hence Safe

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

Cross section of Toe wall


Name of the work:-Construction of Bridge @ 0/0km on Road from Bathupuram to Chinnakosta Estimate Cost: Rs 435.56Lakhs

0.45Mts

2.50Mts 1.00Mts

M10 CC(1:3:6) GL GL

1.80Mts

M10 CC(1:3:6)

0.30Mts

1.65Mts 1.50Mts

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

EARTWORK CALCULATIONS

ABSTRACT QUANTITY OF EARTH WORK


NAME OF THE WORK : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road.

Sl.No. 1

Chainage 2

Area 3

Mean 4

Distance 5

Quantity 6

Remarks 7

1.Approach road Bathupuram side:


1 2 3 4 4 0 50 100 150 200 12.147 13.602 12.746 17.105 22.273 0.000 12.874 13.174 14.926 19.689 50.00 50.00 50.00 50.00 50.00 0.000 643.722 658.708 746.277 984.459 3033.165

2.Approach road Tallaguranti side:


1 2 3 0 50 100 36.343 31.958 30.665 0.000 34.150 31.311 50.00 50.00 50.00 0.000 1707.522 1565.563 3273.08Cum 6306.25Cum

TOTAL QUANTITY:

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

Approach Road sections to the Bridge Bathupuram side


NAME OF THE WORK : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road.
40.000 39.000

38.000
37.000

36.000
35.000 -7.000 -6.000 -5.000 -4.000 -3.000 -2.000 -1.000 0.000

1.000

2.000

3.000

4.000

5.000

6.000

7.000

8.000

F- Level G- Level Sl.No. 1 1 2 3 4 5 6 7

36.780 36.780 Chainage 2 -5.990 -3.750 -1.875 0.000 1.875 3.750 7.150

37.955 38.000 37.955 37.005 37.050 36.850 CROSS SECTION AT - 0/000 Formation L. Ground Level Difference Mean 3 4 5 6 36.780 37.900 37.955 38.000 37.955 37.900 36.200 36.780 36.850 37.005 37.050 36.850 36.250 36.200 0.000 1.050 0.950 0.950 1.105 1.650 0.000 0.000 0.525 1.000 0.950 1.028 1.378 0.825

37.900 36.850

37.900 36.250 Distance 7 0.000 2.240 1.875 1.875 1.875 1.875 3.400

36.200 36.200 Area 8 0.000 1.176 1.875 1.781 1.927 2.583 2.805 12.147

NAME OF THE WORK : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road.
40.000 39.000

38.000
37.000

36.000
35.000 -7.000 -6.000 -5.000 -4.000 -3.000 -2.000 -1.000 0.000

1.000

2.000

3.000

4.000

5.000

6.000

7.000

8.000

F- Level G- Level Sl.No. 1 1 2 3 4 5 6 7

36.780 36.780 Chainage 2 -5.690 -3.750 -1.875 0.000 1.875 3.750 6.850

37.750 36.850

37.805 37.850 37.805 36.835 36.880 35.940 CROSS SECTION AT - 0/50 Difference 5 0.000 0.900 0.970 0.970 1.865 1.910 0.000 Mean 6 0.000 0.450 0.935 0.970 1.418 1.888 0.955

37.750 35.840 Distance 7 0.000 1.940 1.875 1.875 1.875 1.875 3.100

36.200 36.200 Area 8 0.000 0.873 1.753 1.819 2.658 3.539 2.960 13.602

Formation L. Ground Level 3 4 36.780 37.750 37.805 37.850 37.805 37.750 36.200 36.780 36.850 36.835 36.880 35.940 35.840 36.200

NAME OF THE WORK : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road.
39.000 38.000

37.000 36.000
35.000 34.000 -7.000 -6.000 -5.000 -4.000 -3.000 -2.000 -1.000 0.000 1.000 2.000 3.000

4.000 5.000 6.000 7.000 8.000

F- Level G- Level Sl.No. 1 1 2 3 4 5 6 7

36.540 36.540 Chainage 2 -5.870 -3.750 -1.875 0.000 1.875 3.750 7.210

37.655 37.700 37.655 36.835 36.740 35.940 CROSS SECTION AT - 0/100 Formation L. Ground Level Difference Mean 3 4 5 6 36.540 37.600 37.655 37.700 37.655 37.600 35.870 36.540 36.850 36.835 36.740 35.940 35.840 35.870 0.000 0.750 0.820 0.960 1.715 1.760 0.000 0.000 0.375 0.785 0.890 1.338 1.738 0.880

37.600 36.850

37.600 35.840 Distance 7 0.000 2.120 1.875 1.875 1.875 1.875 3.460

35.870 35.870 Area 8 0.000 0.795 1.472 1.669 2.508 3.258 3.045 12.746

NAME OF THE WORK : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road.
39.000

38.000
37.000

36.000
35.000 34.000 -9.000 -8.000 -7.000 -6.000 -5.000 -4.000 -3.000 -2.000 -1.000 0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000

F- Level G- Level Sl.No. 1 1 2 3 4 5 6 7

35.450 35.450 Chainage 2 -7.750 -3.750 -1.875 0.000 1.875 3.750 6.830

37.505 37.550 37.505 35.980 36.120 35.940 CROSS SECTION AT - 0/150 Formation L. Ground Level Difference Mean 3 4 5 6 35.450 37.450 37.505 37.550 37.505 37.450 35.910 35.450 35.870 35.980 36.120 35.940 35.840 35.910 0.000 1.580 1.525 1.430 1.565 1.610 0.000 0.000 0.790 1.553 1.478 1.498 1.588 0.805

37.450 35.870

37.450 35.840 Distance 7 0.000 4.000 1.875 1.875 1.875 1.875 3.080

35.910 35.910 Area 8 0.000 3.160 2.911 2.770 2.808 2.977 2.479 17.105

NAME OF THE WORK : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road.
38.000

37.000
36.000 35.000

34.000
33.000 -9.000 -8.000 -7.000 -6.000 -5.000 -4.000 -3.000 -2.000 -1.000 0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000 8.000 9.000

F- Level G- Level Sl.No. 1 1 2 3 4 5 6 7

35.020 35.020 Chainage 2 -8.410 -3.750 -1.875 0.000 1.875 3.750 8.430

37.405 37.450 37.405 35.870 35.910 35.810 CROSS SECTION AT - 0/200 Formation L. Ground Level Difference Mean 3 4 5 6 35.020 37.350 37.405 37.450 37.405 37.350 35.010 35.020 35.450 35.870 35.910 35.810 35.120 35.010 0.000 1.900 1.535 1.540 1.595 2.230 0.000 0.000 0.950 1.718 1.538 1.568 1.913 1.115

37.350 35.450

37.350 35.120 Distance 7 0.000 4.660 1.875 1.875 1.875 1.875 4.680

35.010 35.010 Area 8 0.000 4.427 3.220 2.883 2.939 3.586 5.218 22.273

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

Approach Road sections to the Bridge Tallaguranti side


NAME OF THE WORK : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road.
39.000
38.000

37.000
36.000

35.000
34.000 -11.000 -9.500 -8.000 -6.500 -5.000 -3.500 -2.000 -0.500

1.000

2.500

4.000

5.500

7.000

8.500

10.000

F- Level G- Level Sl.No. 1 1 2 3 4 5 6 7

34.750 34.750 Chainage 2 -10.050 -3.750 -1.875 0.000 1.875 3.750 9.810

37.955 38.000 37.955 35.540 35.780 35.250 CROSS SECTION AT - 0/000 Formation L. Ground Level Difference Mean 3 4 5 6 34.750 37.900 37.955 38.000 37.955 37.900 34.870 34.750 35.210 35.540 35.780 35.250 34.980 34.870 0.000 2.690 2.415 2.220 2.705 2.920 0.000 0.000 1.345 2.553 2.318 2.463 2.813 1.460

37.900 35.210

37.900 34.980 Distance 7 0.000 6.300 1.875 1.875 1.875 1.875 6.060

34.870 34.870 Area 8 0.000 8.473 4.786 4.345 4.617 5.273 8.848 36.343

NAME OF THE WORK : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road.
39.000
38.000

37.000
36.000

35.000
34.000 -10.000 -8.500

-7.000

-5.500

-4.000

-2.500

-1.000

0.500

2.000

3.500

5.000

6.500

8.000

9.500

F- Level G- Level Sl.No. 1 1 2 3 4 5 6 7

34.890 34.890 Chainage 2 -9.470 -3.750 -1.875 0.000 1.875 3.750 9.490

37.750 35.120

37.805 37.850 37.805 35.590 35.680 35.610 CROSS SECTION AT - 0/50 Difference 5 0.000 2.630 2.215 2.170 2.195 2.530 0.000 Mean 6 0.000 1.315 2.423 2.193 2.183 2.363 1.265

37.750 35.220 Distance 7 0.000 5.720 1.875 1.875 1.875 1.875 5.740

34.880 34.880 Area 8 0.000 7.522 4.542 4.111 4.092 4.430 7.261 31.958

Formation L. Ground Level 3 4 34.890 37.750 37.805 37.850 37.805 37.750 34.880 34.890 35.120 35.590 35.680 35.610 35.220 34.880

NAME OF THE WORK : Construction of High level Bridge across the river Mahendratanaya on Bathupuram chinnakosta Road.
39.000

38.000 37.000 36.000


35.000 34.000 -10.000 -8.500

-7.000

-5.500

-4.000

-2.500

-1.000

0.500

2.000

3.500

5.000

6.500

8.000

9.500

F- Level G- Level Sl.No. 1 1 2 3 4 5 6 7

34.910 34.910 Chainage 2 -9.130 -3.750 -1.875 0.000 1.875 3.750 9.210

37.655 37.700 37.655 35.380 35.710 35.410 CROSS SECTION AT - 0/100 Formation L. Ground Level Difference Mean 3 4 5 6 34.910 37.600 37.655 37.700 37.655 37.600 34.870 34.910 35.120 35.380 35.710 35.410 35.020 34.870 0.000 2.480 2.275 1.990 2.245 2.580 0.000 0.000 1.240 2.378 2.133 2.118 2.413 1.290

37.600 35.120

37.600 35.020 Distance 7 0.000 5.380 1.875 1.875 1.875 1.875 5.460

34.870 34.870 Area 8 0.000 6.671 4.458 3.998 3.970 4.523 7.043 30.665

Assistant Executive Engineer PIU,Sompeta

Dy. Executive Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam

GENERAL ALIGNMENT OF THE PROPOSED HIGH LEVEL BRIDGE AT BATHUPURAM

Estimate cost:Rs 435.56Lakhs

Fly wing

Length of Bridge = Back to back of abutments 8vents of 16.50mts effective span without footpaths
Return wall

RCL:38.42

T beams with slab

Road level:36.98
Revetment
Expansion Joint

BDK:37.83
MFL:35.38

Abutment LBL:29.55

Pier of size 2.0mts dia

Pile Cap 9 piles of 1.2mts dia 4 piles of 1.0mts dia

Asst.Exe.Engineer PIU,Sompeta

Dy.Exe.Engineer PIU,Sompeta

Executive Engineer PIU,Srikakulam

Superintending Engineer PR,Srikakulam