Documente Academic
Documente Profesional
Documente Cultură
SECTION-I ..........................................................................1
Contract Management........................................................1
Procurement .....................................................................1
Contract Management........................................................2
Procedures of open competitive bidding and Alternative
methods of procurements...........................................6
SECTION-II ......................................................................15
Procurement of Works......................................................15
Pre-Qualification of Bidders..............................................15
A. General............................................................................................................21
1. Scope of Application...........................................................................21
2. Source of Funds.................................................................................21
A. Requirements.............................................................25
1.Brief Description of the Scope........................................25
2.Major Contract Components...........................................25
3.Estimated Quantities of Major Components....................25
4.Methods Required.........................................................25
5.Contract Implementation Period....................................25
B. Supplementary Information........................................25
1.Project Country.............................................................25
2.Contract Site.................................................................25
C. Facilities to be Provided by the Employer....................25
PEC Bidding Documents for Procurement of Works............30
Bid Evaluation and Award of Contract...............................43
The Role of the Employer & the Contractor........................52
Risk Allocation & Management in Construction Contracts. .56
Guide Book Cost and Contracts
ii Table of Contents
Construction Claims Management.....................................62
Price Adjustment in Construction Contract........................81
SECTION-III.......................................................................88
Procurement of Goods......................................................88
Introduction.....................................................................88
The Bidding Documents for Procurement of Goods generally
used, are based on documents prepared by the World
Bank 1997, 2001 and 2004, revised upto 2010...........88
INCOTERMS....................................................................107
International Commercial Terms.....................................107
Incoterms 2010............................................................111
Main features of the Incoterms 2010 rules....................111
Two new Incoterms rules DAT and DAP have replaced the
Incoterms 2000 rules DAF, DES, DEQ and DDU.........111
Documentary Credits in International Business Transactions
..............................................................................113
International Trade.........................................................113
In an international trade transaction involving goods or
services, the buyer and the seller negotiate details
about the method and timing of both payments and
delivery. ................................................................113
Dispute Settlement Provisions in Goods Contracts..........124
Essential elements of good contract management...........124
The right contract with right specifications and terms. ...124
www.pakistanconstitution-law.org..................................134
SECTION-IV.....................................................................135
Procurement of Consulting Services................................135
Introduction:..................................................................135
1.1 143
Guide Book Cost and Contracts
SECTION-I iii
152
Estimating Cost and Budget for Consulting Services.......163
Introduction.......................................................................................................163
Price Adjustment in Consultancy Contract......................................................170
Introduction.......................................................................................................170
In order to adjust the remuneration for foreign and/or local inflation, a price
adjustment provision should be included in the Contract...................170
PEC: 170
SECTION-V......................................................................173
Engineering Cost Management........................................173
Project Management.......................................................173
173
Note: For further information refer following websites;...181
Budget for Construction Projects....................................182
Bills of Quantities and Schedule of Rates ........................189
Bills of Quantities (BoQ) .................................................189
A quantified and completed list of works describing the full
requirements in the drawings and specifications. The
rates are quoted by the contractors........................189
Importance of BoQs........................................................189
Avoid unnecessary effort from multiple contractors to
prepare the tender.................................................189
Provide a standard basis for the tender purpose.............189
Provide Quality control...................................................189
Assist the tender evaluation ..........................................189
Provide rates for valuation of variations.........................189
Provide the basis for the payment purpose.....................189
Provide basis for financial reporting/cash flow................189
Schedule of Rates (SoR)..................................................189
Guide Book Cost and Contracts
iv Table of Contents
A schedule listing the works with the rates to provide a list
of rates for the valuation purposes in conformance to
the standard specifications.....................................189
Importance of Schedule of Rates ....................................189
Cost Estimation..............................................................189
Precision........................................................................189
Uniformity......................................................................189
Transparency.................................................................189
Quick.............................................................................189
Differences between BoQ & SoR......................................189
BoQ 189
Quantities form part of the Contract...............................189
Buildup the tender/contract sum.....................................189
Provide a list of rates for the valuation of a set purposed
work.......................................................................189
Take longer preparation time for all consultants.............189
SoR 189
The Quantities do not form part of the contract. .....189
Provide a list of rates for the valuation of works or
component of a work..............................................189
Buildup the Engineers Estimate/tender sum...................189
Usually based on standard specifications and drawings not
fully detailed. ........................................................189
The time required is usually shorter................................189
Specifications:................................................................190
Specifications are written descriptions of materials and
construction processes in relation to performance,
characteristics, installation and quality of work
requirements..........................................................190
Guide Book Cost and Contracts
SECTION-I v
Drawings:.......................................................................191
Drawings are the graphic means of showing work to be
done, as they depict shape, dimension, location,
measurement of material and relationship between
building components..............................................191
Rates of Materials, Labour & Rental charges of
Plant/Equipment;....................................................191
Rates collection; directly from markets, manufacturers,
suppliers, vendors and form different sources in a
district or city.........................................................191
Rate determination; by applying transportation charges to
Ex-factory/Ex-source rates......................................191
Identification of materials and their sources in a particular
district or city.........................................................191
Labour rates are different in different areas, mostly
obtained from Revenue Department.......................191
Plant/Equipments rental charges are almost same at all
places....................................................................191
The rates are derived at district head quarter /city level..191
Processing of Collected Rates;........................................191
At least from three Sources, Verification of these Rates and
then Comparison for their suitability of use is carried
out. .............................................................191
Quantities of different materials in a unit quantity of work
item, worked out based on specifications, experiences,
proven facts and references...................................192
Wastage of material in a unit quantity of work is considered
as 2% to 7% depending upon construction activity and
execution technique...............................................192
Labour inputs are different from place to place depending
upon socio-economical conditions...........................192
The efficiencies of equipments or machines remain all most
unchanged at all places..........................................192
Guide Book Cost and Contracts
vi Table of Contents
SECTION-VI.....................................................................195
FIDIC Conditions of Contracts..........................................195
Guide Book Cost and Contracts
SECTION-I 1
SECTION-I
Contract Management
Procurement
In order to describe how procurement should be planned and implemented by the Employer,
it is appropriate to establish at the outset why this topic is worthy of attention. This inquiry
can be fruitfully addressed by approaching it from following three linked perspectives:
(a) The constituents of proficient public procurement and its distinguishing characteristics;
(b) Its importance; and
(c) Priority of its achievement and maintenance.
Proficient procurement
The principal distinctive characteristics of proficient public procurement are:
Economy;
Efficiency;
Fairness;
Reliability;
Transparency; and
Accountability and Ethical Standards.
Economy:
Procurement is a purchasing activity whose purpose is to give the purchaser best value for
money. For complex purchases, value may imply more than just price, for example, since
quality issues also need to be addressed. Moreover, lowest initial price may not equate to low-
est cost over the operating life of the item procured. But the basic point is the same: the ulti-
mate purpose of sound procurement is to obtain maximum value for money.
Efficiency:
The best public procurement is simple and swift, producing positive results without protracted
delays. In addition, efficiency implies practicality, especially in terms of compatibility with
the administrative resources and professional capabilities of the purchasing entity and its pro-
curement personnel.
Fairness:
Good procurement is impartial, consistent, and therefore reliable. It offers all interested con-
tractors, suppliers and consultants a level playing field on which to compete and thereby, di-
rectly expands the purchasers options and opportunities.
Transparency:
Good procurement establishes and then maintains rules and procedures that are accessible
and unambiguous. It is not only fair, but should be seen to be fair.
Accountability and Ethical Standards:
Good procurement holds its practitioners responsible for enforcing and obeying the rules. It
makes them subject to challenge and to sanction, if appropriate, for neglecting or bending
those rules. Accountability is at once a key inducement to individual and institutional probity,
a key deterrent to collusion and corruption, and a key prerequisite for procurement credibility.
A sound procurement system is one that combines all the above elements. This directly and
concretely benefits the Employers, the Purchasing entities, responsive Contractors and
Suppliers, and the donor agencies providing the project finance.
Guide Book Cost and Contracts
2 SECTION-I
The Employer should establish fundamental rules for the use of its funds and for supervising
the execution of projects. Four considerations guide these rules:
(a) Ensuring economy and efficiency in project implementation including the procurement of
goods, works and services;
(b) Giving eligible bidders from member countries a fair opportunity to compete in
procurement;
(c) Encouraging the development of domestic industries and consulting services; and
(d) Providing for transparency in the procurement process.
PROCUREMENT LIFE CYCLE PHASE
Procurement Life Cycle commences from the procurement planning phase to post
contract review phase.
Throughout this period consideration is being given to the requirements of how the
contract will be managed based on consideration of the value, complexity, strategic im-
portance, risk, the general market maturity and the selected supplier capability.
Contract Management
Contract management is the process that enables both parties to a contract to meet their obli-
gations in order to deliver the objectives required from the contract. It also involves building a
good working relationship between the parties. It continues throughout the life of a contract
and involves managing proactively to anticipate future needs as well as reacting to situations
that arise. Contract Management is:
Process enabling both parties to meet obligation
Involves building good working relationship
Enables & assists in anticipating future needs
Implemented through the Contract Management Plan
Importance of contract management
The importance of contract management is to ensure that services / works are provided:
To the required standard;
Guide Book Cost and Contracts
SECTION-I 3
Within the agreed timeframe; and
Achieving value for money.
The key point is that the foundations for contract management are laid in the stages before
contract is awarded, including the procurement process. The terms of the contract should
include an agreed level of service, pricing mechanisms, incentives, contract timetable, means
to measure performance, communication routes, escalation procedures, change control
procedures, agreed exit strategy and agreed break options, and all the other formal
mechanisms that enable a contract to function. These formal contract aspects form the
framework around which a good relationship can grow. If the contract was poorly
constructed, it will be much more difficult to make the relationship a success.
CONTRACT MANAGEMENT PHASE
In planning for contract management it is often broken down into three broad areas:
Service delivery management;
Relationship management; and
Contract administration.
All the three areas must be managed for successful completion of contract.
Service Delivery Management
Service delivery management is concerned with ensuring the service is being fully delivered:
As agreed;
To the required level of performance; and
Quality.
The contract should define the service levels and terms under which a service is provided.
Service level management is about assessing and managing the performance of the service
provider to ensure value for money. Considering service quality against cost leads to an
assessment of the value for money that a contract is providing. Thus Managing service
delivery means ensuring that what has been agreed is delivered, to appropriate quality
standards.
Relationship Management
As well as the contractual and commercial aspects, the relationship between the parties is vi-
tal to making a success of the arrangement. Relationships should be managed in a profession-
al manner and be based on cooperation and mutual understanding taking into account the
need for probity and ethical behaviour. Maintaining a good relationship does not mean that
the terms of the contract are not enforced where this is warranted. It is about enforcing the
terms of the contract in a professional manner based on evidence of contractual performance.
This requires the establishment and maintenance of an appropriate record trail. What is nec-
essary in the circumstances will vary but the importance of the maintenance of accurate, con-
temporaneous records to successful contract management cannot be underemphasized. The
approach to relationship development will vary depending on the contract, but it is important
that the specific responsibilities are not neglected, even though there may not be a nominated
individual assigned to the role of relationship manager.
Relationship management is focused on keeping the relationship between the two parties:
Open and constructive;
Resolving or easing tensions; and
Guide Book Cost and Contracts
4 SECTION-I
Identifying problems early.
In long term contracts, where interdependency between the parties is inevitable, it is in the in-
terests for the success full contracts to make the relationship work. The three key factors for
success are trust, communication, and recognition of mutual aims. A structured approach to
managing relationships should be adopted, comprising of informal, day to day discussions
and interactions and formal meetings at pre-determined intervals with nominated personnel
from both the parties.
Contract Administration
Contract administration covers the formal governance of the contract. These may include:
Contract maintenance;
Change control;
Cost monitoring;
Ordering procedures;
Payment procedures; and
Management reporting.
The importance of contract administration to the success of the contract, and to the
relationship between the parties, should not be underestimated. Clear administrative
procedures ensure that all parties to the contract understand who does what, when, and how.
The contract documentation itself must continue to accurately reflect the arrangement, and
changes to it (required by changes to services or procedures) carefully controlled.
These procedures are normally documented in the contract management plan.
The Contract Management plan
The written contract is a record of each partys obligations. The contract management plan
might include:
o A summary by date of milestones and deliverables,
o Key individuals and their responsibilities e.g. the contract manager, gover-
nance board.
o A schedule of risks that have been identified and are being monitored and
managed.
o Reporting.
o Meeting schedules and any standard agenda items.
o Processes around how the contractual obligations are to be achieved.
o Procedures for the management of any specific activities in the contract.
o Contract variations. Details of the approval process and approval authorities.
o Details of any ordering procedures.
o Payment procedures
Construction projects are becoming more and more complex due to new standards, advanced
technologies, and owner-desired additions and changes. While the successful completion of
projects has been thought to depend mainly on cooperation between the contractor, consul-
tant, and owner, problems and disputes have always erupted due to conflicting opinions as to
the various aspects of design and construction. However these may be averted with the appli-
cation of greater sense of responsibility, lies on parties to contract for successful completion
of works.
Guide Book Cost and Contracts
SECTION-I 5
Contract Management solution is a must in your organization if;
You want compliance with contract prices as well as terms and conditions,
You want structured contract metadata to enable such things as risk analysis and plan-
ning; better supplier performance measurement and management; better opportunity dis-
covery for strategic sourcing, and compliance measurement and management,
You want more discipline, greater efficiency, and more speed in your process for contract
authoring,
You want all contracts with suppliers to consistently reflect enterprise financial and legal
standard terms, language, and priorities,
You want to be able to give more people access to contract data and documents without
sacrificing security,
You want to make it easier for people to comply by making it easy for them to search for
contracts and to extract the information they need from within contracts, and
You want audit trails and version controls around contract authoring and negotiation.
Successful Contract Management
A Successful contract management is defined as when:
The arrangements for service delivery continue to be satisfactory to employer /
client / customer and contractor / supplier / provider,
Expected business benefits and value for money are being realised,
The contractor / supplier / provider is co-operative and responsive,
The employer / client / customer knows its obligations under the contract,
Disputes are minimum,
There are no surprises for either party.
Guide Book Cost and Contracts
6 SECTION-I
Procedures of open competitive bidding and Alternative methods of
procurements
Procurement Planning Guidelines
General Considerations for implementation of work
Scope of work
Financing
Eligibility
Joint Ventures
Misprocurement
Fraud and Corruption
Procurement Plan
Type and Size of Contracts
Type of Bidding
Notification and Advertising
Prequalification of Bidders
Bidding Documents
General
Validity of Bids and Bid Security
Language
Clarity of Bidding Documents
Standards
Use of Brand Names
Pricing
Price Adjustment
Transportation and Insurance
Currency Provisions
Currency of Bid
Currency Conversion for Bid Comparison
Currency of Payment
Terms and Methods of Payment
Alternative Bids
Conditions of Contract
Performance Security
Liquidated Damages and Bonus Clauses
Force Majeure
Applicable Law and Settlement of Disputes
Guide Book Cost and Contracts
SECTION-I 7
Bid Opening, Evaluation, and Award of Contract
' Time for Preparation of Bids
' Bid Opening Procedures
' Clarifications or Alterations of Bids
' Confidentiality
' Examination of Bids
' Evaluation and Comparison of Bids
' Domestic Preferences
' Extension of Validity of Bids
' Post-qualification of Bidders
' Award of Contract
' Publication of the Award of Contract
' Rejection of All Bids
Invitation for Bids (Important Public Procurement Rules are summarised below)
PPR-12 Methods of advertisement
(1) Procurements for Govt. Departments; over hundred thousand rupees and up to the
limit of two million rupees shall be advertised on the PPRAs website in the manner
and format specified by regulation by the PPRA from time to time. These procurement
opportunities may also be advertised in print media, if deemed necessary by the
procuring agency. Procurements for Autonomous Bodies; this limit is for more than
five hundred thousand rupees.
(2) All procurement opportunities for Govt. Departments; over two million rupees
should be advertised on the PPRAs website as well as in other print media or newspa-
pers having wide circulation. The advertisement in the newspapers shall principally
appear in at least two national dailies, one in English and the other in Urdu.
PPRA require minimum information:
1. Name of procuring agency.
2. Tender number (for identification)
3. Procurement Title (indicating type and quantity).
4. Contact person (for seeking bidding documents).
5. Last date for obtaining bidding documents and its price (if any).
6. Closing time and date as well as place for receiving bids.
7. Time and Place of public opening of bids (Bids must be opened on the closing date).
8. Amount of bid security (%age of bid price or lump sum).
9. Time period for performance of contract.
PPR-13 Response time
The response time shall not be less than fifteen working days for national competitive
bidding and thirty working days for international competitive bidding from the date of
publication of advertisement or notice.
(PEC - preparation and submission of bids may take 42 to 154 days depending on the size of
the Works, Civil and E&M)
Guide Book Cost and Contracts
8 SECTION-I
PPR-15 Pre-qualification
A procuring agency, prior to the floating of tenders, invitation to proposals or offers in
procurement proceedings, may engage in pre-qualification of bidders.
PPR-20 Principal method of procurement
The procuring agencies shall use open competitive bidding as the principal method of
procurement for the procurement of goods, services and works.
PPR-21 Open competitive bidding
The procuring agencies shall engage in open competitive bidding if the cost of the object to be
procured is more than one hundred thousand rupees in case of Govt. Departments and five
hundred thousand rupees in case of Autonomous bodies, except provisions given under
PPR-42, Alternative methods of procurements.
PPR-25 Bid security
The procuring agency may require the bidders to furnish a bid security not exceeding five
per cent of the bid price.
(PEC - a lump sum figure ranging from 1% to 3% of the likely cost of the Works or a
percentage ranging from 1 % to 3 % of the Bid Price for Civil and E&M works)
PPR-26 Bid validity
A procuring agency, keeping in view the nature of the procurement, shall subject the bid to a
bid validity period. However under exceptional circumstances, if an extension is considered
necessary, all those who have submitted their bids shall be asked to extend their respective
bid validity period. Such extension shall be for not more than the period equal to the period of
the original bid validity.
The Bidders who agree to the procuring agencys request for extension of bid validity period
shall not be permitted to change the substance of their bids; and if do not agree to the exten-
sion shall be allowed to withdraw their bids without forfeiture of their bid bonds or securities
(PEC - the period of bid validity may range from 56 to 182 days depending upon the
size and nature of the Works, Civil and E&M)
Bids Opening
PPR-28 Opening of bids
The bids shall be opened at least thirty minutes after the deadline for submission of bids on
the same day.
PPR-31 Clarification of bids
No bidder shall be allowed to alter or modify his bid after the bids have been opened. Howev-
er the procuring agency may seek and accept clarifications to the bid that do not change the
substance of the bid. The clarification and the response shall be in writing.
PPR-33 Rejection of bids
The procuring agency may reject all bids or proposals at any time prior to the acceptance of a
bid or proposal. The procuring agency shall communicate, the grounds for its rejection of bids
or proposals, but not required to justify those grounds.
PPR-34 Re-bidding
The procuring agency before invitation for re-bidding may revise specifications, evaluation
criteria or any other condition for bidders as it may deem necessary.
Guide Book Cost and Contracts
SECTION-I 9
[As per PPRA, if all the bids prices substantially exceed the cost estimated/market value, the
procuring agency is allowed to cancel all the bids prior to acceptance as provided under
Rule-33 and invoke Rule 34 for re-bidding.]
PPR-35 Announcement of evaluation reports
Procuring agencies shall announce the results of bid evaluation in the form of a report giving
justification for acceptance or rejection of bids at least ten days prior to the award of
procurement contract.
PROCEDURES OF OPEN COMPETITIVE BIDDING
PPR-36 Procedures of open competitive bidding
The following procedures shall be permissible for open competitive bidding:
1. Single stage one envelope procedure
2. Single stage two envelope procedure
3. Two stage
4. Two stage two envelope procedure
1. Single stage one envelope procedure
Each bid shall comprise one single envelope.
The envelope shall contain, financial proposal and technical proposal.
All bids received shall be opened and evaluated in the manner prescribed in the bid-
ding document.
The bid found to be the lowest evaluated responsive bid shall be accepted.
Note: This procedure is ordinarily the main open competitive bidding procedure used for
most of the procurement.
Example:
Bidder Responsive Bid
Corrected Bid
Price
Lowest Responsive
Bidder
Name Pre-Qualification Status Rs in million Award
A Qualified Responsive 1000 A
B Qualified Responsive 1100 -
C Not Qualified Not invited - -
D Qualified Non Responsive 900 -
E Not Qualified Not invited - -
F Qualified Responsive 1200 -
2. Single stage two envelope procedure
The bid shall comprise a single package containing two separate envelopes. Each en-
velope shall contain separately the financial proposal and the technical proposal;
Guide Book Cost and Contracts
10 SECTION-I
The envelopes shall be marked as FINANCIAL PROPOSAL and TECHNICAL
PROPOSAL;
Initially, only the envelope marked TECHNICAL PROPOSAL shall be opened;
The envelope marked as FINANCIAL PROPOSAL shall be retained with the
procuring agency without being opened;
The procuring agency shall evaluate the technical proposal without reference to the
price and reject any proposal which does not conform to the specified requirements;
During the technical evaluation no amendments in the technical proposal shall be per-
mitted;
After the evaluation and approval of the technical proposal the procuring agency,
shall at a time, date and venue within the bid validity period, publicly open the finan-
cial proposals of the technically accepted bids only;
For the opening of financial proposals of bids all the bidders who have participated
will be invited.
The financial proposal of bids found technically non-responsive shall be returned un-
opened to the respective bidders;
The bid found to be the lowest evaluated bid shall be accepted.
Example:
Bidder Technical Proposal Financial Proposal
Lowest Responsive
Bidder
Status Status Rs in million Award
A Qualified Responsive 1000 A
B Qualified Responsive 1100 -
C Not Qualified Not opened - -
D Qualified Non Responsive 900 -
E Not Qualified Not opened - -
F Qualified Responsive 1200 -
Note:
This procedure may be termed as the modified form of Post-Qualification.
Single stage two envelope bidding procedure shall be used where the bids are to
be evaluated on technical and financial grounds and price is taken into account
after technical evaluation.
In this Bidding method, the Employer is well aware of the work in hand, its de-
sign and speciations.
3. Two stage procedure
First stage
The bidders shall first submit, according to the required specifications, a technical
proposal without price;
Guide Book Cost and Contracts
SECTION-I 11
The technical proposal shall be evaluated in accordance with the specified evaluation
criteria and may be discussed with the bidders regarding any deficiencies and unsatis-
factory technical features;
After such discussions, all the bidders shall be permitted to revise their respective
technical proposals to meet the requirements of the procuring agency;
The procuring agency may revise, delete, modify or add any aspect of the technical re-
quirements or evaluation criteria, or it may add new requirements;
Those bidders not willing to conform their respective bids to the procuring agencys
technical requirements may be allowed to withdraw from the bidding without forfei-
ture of their bid security;
Note: Such revisions, deletions, modifications or additions are communicated to all the
bidders equally at the time of invitation to submit final bids, and that sufficient time is
allowed to the bidders to prepare their revised bids.
Second stage
The bidders, whose technical proposals or bids have not been rejected and who are
willing to conform their bids to the revised technical requirements of the procuring
agency, shall be invited to submit a revised technical proposal along with the financial
proposal;
The revised technical proposal and the financial proposal shall be opened at a time,
date and venue announced and communicated to the bidders in advance;
The revised technical proposal and the financial proposal shall be evaluated in the
manner prescribed above.
The bid found to be the lowest evaluated shall be accepted.
Note: For the submission of the revised technical proposal and financial proposal the
procuring agency shall allow sufficient time to the bidders to incorporate the agreed
upon changes in the technical proposal and prepare their financial proposals
accordingly.
Two stage bidding procedure shall be adopted in large and complex contracts where
technically unequal proposals are likely to be encountered or where the procuring
agency is aware of its options in the market but, for a given set of performance re-
quirements, there are two or more equally acceptable technical solutions available to
the procuring agency.
4. Two stage - two envelope procedure
First stage
The bid shall comprise a single package containing two separate envelopes. Each en-
velope shall contain separately the financial proposal and the technical proposal;
The envelopes shall be marked as FINANCIAL PROPOSAL and TECHNICAL
PROPOSAL;
Initially, only the envelope marked TECHNICAL PROPOSAL shall be opened;
The envelope marked as FINANCIAL PROPOSAL shall be retained in the custody
of the procuring agency without being opened;
Guide Book Cost and Contracts
12 SECTION-I
The technical proposal shall be discussed with the bidders with reference to the
procuring agencys technical requirements;
Those bidders willing to meet the requirements of the procuring agency shall be al-
lowed to revise their technical proposals following these discussions;
Bidders not willing to conform their technical proposal to the revised requirements of
the procuring agency shall be allowed to withdraw their respective bids without forfei-
ture of their bid security;
Second stage
After agreement between the procuring agency and the bidders on the technical re-
quirements, bidders who are willing to conform to the revised technical specifications
and whose bids have not already been rejected shall submit a revised technical pro-
posal and supplementary financial proposal, according to the technical requirement;
The revised technical proposal along with the original financial proposal and supple-
mentary financial proposal shall be opened at a date, time and venue announced in ad-
vance by the procuring agency;
The procuring agency shall evaluate the whole proposal in accordance with the evalu-
ation criteria and the bid found to be the lowest evaluated bid shall be accepted.
Note: For the submission of the revised technical proposal and supplementary price
proposal a procuring agency shall allow sufficient time to the bidders to incorporate
the agreed upon changes in the technical proposal and to prepare the required
supplementary financial proposal.
Two stage two envelope bidding method shall be used for procurement where alterna-
tive technical proposals are possible, such as certain type of machinery or equipment
or manufacturing plant.
Acceptance of bids and award of contracts
PPR-38 Acceptance of bids
The bidder with the lowest evaluated responsive bid shall be awarded the contract, within the
original or extended period of bid validity.
[Public Procurement Rules, 2004 don't put any limit on number of tenders/ bids received in
response to tender notices provided that the procurement opportunity has been advertised in
the prescribed manner. The single bid may be considered if it meets the evaluation criteria
expressed in tender notice and is not in conflict with any other rules, regulations or policy of
the Federal Government.]
PPR-39 Performance guarantee
The procuring agency shall require the successful bidder to furnish a performance guarantee
which shall not exceed ten per cent of the contract amount.
(PEC - an amount equal to 10 percent of the Contract Price is commonly specified for
bank guarantees)
PPR-40 Limitation on negotiations
Guide Book Cost and Contracts
SECTION-I 13
There shall be no negotiations with the bidder having submitted the lowest evaluated bid or
with any other bidder.
PPR-41 Confidentiality
The procuring agency shall keep all information regarding the bid evaluation confidential
until the time of the announcement of the evaluation report.
ALTERNATIVE METHODS OF PROCUREMENTS
PPR - 42
a) Petty purchases
The object of the procurement is below the financial limit of Rs 25,000 (twenty five
thousand rupees). Such procurement shall be exempt from the requirements of bidding
or quotation of prices:
b) Request for quotations
(i) The cost of object of procurement is below the prescribed limit of Rs 100,000
(Rupees one hundred thousand) for Govt. Departments and Rs 500,000 (Ru-
pees five hundred thousand) for Autonomous bodies;
(ii) The object of the procurement has standard specifications;
(iii) Minimum of three quotations have been obtained; and
(iv) The object of the procurement is purchased from the supplier offering the low-
est price:
c) Direct contracting
(i) The procurement concerns the acquisition of spare parts or supplementary ser-
vices from original manufacturer or supplier:
(ii) only one manufacturer or supplier exists for the required procurement:
(iii) Where a change of supplier would oblige to acquire material having different
technical specifications or characteristics and would result in incompatibility
or disproportionate technical difficulties in operation and maintenance:
(iv) The contract(s) do not exceed three years in duration;
(v) Repeat orders not exceeding fifteen per cent of the original procurement;
(vi) In case of an emergency:
(vii) When the price of goods, services or works is fixed by the government or any
other authority, agency or body duly authorized by the Government, on its be-
half, and
(viii) For purchase of motor vehicle from local original manufacturers or their au-
thorized agents at manufacturers price.
d) Negotiated tendering
(i) For the supplies involved are manufactured purely for the purpose of support-
ing a specific piece of research or an experiment, a study or a particular devel-
opment;
Guide Book Cost and Contracts
14 SECTION-I
(ii) For technical or artistic reasons, or for reasons connected with protection of
exclusive rights or intellectual property, the supplies may be manufactured or
delivered only by a particular supplier;
(iii) For reasons of extreme urgency brought about by events unforeseeable by the
procuring agency, the time limits laid down for open and limited bidding
methods cannot be met. The circumstances invoked to justify extreme urgency
must not be attributable to the procuring agency:
Note: For complete set of PPRA Rules, refer S.R.O. 432(I)/2004, dated 09-06-2004,
Amended upto vide Cabinet Division No. 5/37/2005-M-III/Admin (PPRA), dated
23-09-2008.
Guide Book Cost and Contracts
SECTION-I 15
SECTION-II
Procurement of Works
Pre-Qualification of Bidders
Introduction:
The successful execution of contracts for large civil engineering works, supply and
installation, turnkey, and design & and build projects requires that contracts be awarded only
to firms, or combinations of firms, that are suitably experienced in the type of work and
construction technology involved, that are financially and managerially sound, and that can
provide all the equipment required in a timely manner. The assessment by an implementing
agency of the suitability of firms to carry out a particular contract prior to being invited to
submit a bid is a process called pre-qualification.
WB, ADB and most multilateral financing institutions require pre-qualification of
firms for the construction of large or complex Works contracts.
PPR-15: A procuring agency, may engage in pre-qualification of bidders in case of
services, civil works, turnkey projects and in case of procurement of expensive and
technically complex equipment.
PEC Works bye-laws-4(4): A license granted by the Council shall entitle a licensee to
perform an engineering work for the Client or Employer. However, the Client or Em-
ployer may prescribe his own requirements over and above the requirements for li-
cense prescribed by the Council.
WAPDA
For works worth more than Rs 250 million, pre-qualification of bidders is mandatory.
For works of Special nature valuing less than Rs 250 million, pre-qualification of bid-
ders may be carried out.
Pre-qualification of bidders to be decided by the authority next above the authority
competent to accept the Bid, upto Members/Managing Directors.
Advantage of Pre-qualification:
O Early elimination of non-conforming bidders.
O Selection of homogenous bidders.
O Encouraging genuine competitors to avoid unrealistic competitors.
O Reduce bid evaluation efforts.
O Allows adjustment/modifications in the bidding documents from the trend of appli-
cants.
O Facilitates Joint Venture formulation of pre-qualified bidders.
O Reduce problems of low priced bids.
O Help the non-qualified bidders from bidding efforts.
O Enables the Employer to access bidders eligibility for domestic bidder price prefer-
ence where this is applicable.
O Where a project is divided into separate contracts, applicants may be pre-qualified
through a single pre-qualification exercise.
Disadvantage of Pre-qualification:
o Loss of time and efforts before bidding
Guide Book Cost and Contracts
16 SECTION-II
o For normal projects, duplicity against PEC licensing (possibility of price-rigging is
easier among a limited number of identified bidders)
o Employer is required to review all prequalification applications, whereas post-qualifi-
cation requires review of the qualifications of, the bidder who have quoted the lowest
price, however if it fails then the qualifications of 2
nd
lowest proposer is evaluated and
so on.
o Time gap between pre-qualification and bidding may nullify effect and/or loss of left
over bidders
Areas for Pre-Qualification:
Section 4(4) & 7(3) of PEC W/bye-laws and PPRs-15(2) envisage following areas for Pre-
qualification:
Financial Soundness
Plant, Equipment and Personnel Capabilities
Previous experience (how a new contractor can work?)
Business Management Capabilities
Specific Expertise
Current PEC License
Any other area required relevant to work
The Pre-qualification Process
The pre-qualification process includes four main phases:
i. Advertising
ii. Preparation and Issuing of the Pre-qualification Document
iii. Application Preparation and Submission
iv. Application Evaluation, and Pre-qualification of Applicants
Pre-qualification of Bidders
(Based on PEC Standard Procedure for Pre-Qualification of Constructors)
E Invitation for Pre-qualification
E Pre-qualification Documents :
Invitation for Pre-qualification
Instructions to Applicants
Evaluation Criteria
Letter of Application to be filled in Applicants
Various forms according to the work
E Evaluation of the bidders
E Communication of the evaluation result on pass/fail basis
Preparing Invitation:
1. Name of the Executing Agency and Name of Project
2. Name of Executing Agency and General Project descriptions with location, nature and
complexity of works
Guide Book Cost and Contracts
SECTION-II 17
3. Expected date of issue of Invitation to Bid
4. Specify PEC construction license category
5. Address of Employer and Applicant
6. Amount of non refundable fee towards documents and Cost of mailing
7. Minimum essential requirements: may be number of projects completed, referred to
Instructions to Application documents.
8. Delivery address, Last date of delivery, and project /Contact number
9. Name of Employer
Instructions to Applicants:
All blank spaces to be filled in and instructions within parenthesis to be deleted.
Original plus No of copies of submission
Time period for Application submission
Name of the Project
Location, Time and Date for clarification, if provided
Qualification Criteria
Sr. No. Category Weightage/Marks
1. Financial Soundness 30
2. Experience Record 35
3. Personnel Capabilities 15
4. Equipment Capabilities 20
Total: 100
Prequalification status shall be decided on Pass/Fail basis.
The applicant must score at least 50% score in each category.
Qualification Sub-Criteria
1. Financial Position:
Sr. Nr. Description Maximum Marks
1.1 Available Bank Credit Line 5
1.2 Working Capital during last 3 years 5
1.3 Registration with Income Tax Department 5
1.4
Litigation History where decision went against the
Firm
5
1.5 Blacklisting from any Agency 5
1.6 Valid License for other related items of Work 5
Sub-total: 30
2. General Experience:
Sr. Nr. Description Maximum Points
2.1
Projects of similar nature and complexity
completed during latest 10 years
15
2.2 Projects of similar nature and complexity in hand 10
2.3 Experience of Works related to project but not 5
Guide Book Cost and Contracts
18 SECTION-II
basic part (general experience)
2.4
Status of enlistment with Government
Organizations and other agencies
5
Sub-total: 35
3. Personnel Capabilities:
Sr. Nr. Description Maximum Points
3.1 Graduate Engineers Registered with PEC
a)Number of Engineers
b)Experience of Engineers in number of years
6
3
3.2 Number of Diploma Engineers in Employment of
the Firm
a)Number of Engineers
b)Experience of Engineers in number of years.
4
2
Sub-total: 15
4. Equipment Capabilities (List relevant equipment and Assign Marks):
Sr. Nr. Equipment Type and Characteristics Maximum Marks
4.1 [e.g. Concrete Static mixer 0.4 cum capacity 2
4.2 Dumper 10 Ton Capacity 2
4.3 Mobile Crane 10 Ton etc.] 3
4.4
Sub-total: 20
Letter of Application:
E Employer to fill-in for their part
E Some of the instructions and spaces attributable to Applicant shall be retained
E Applicant must sign the Application in order to avoid disqualification
Forms;
Forms are annexed for obtaining information of applicants as General Experience Record,
Joint Venture Summary, Particular Experience Record, Details of Contracts of Similar Nature
and Complexity, Current Contract Commitments/ Works in Progress, Personnel Capabilities,
Candidate Summary, Equipment Capabilities, Financial Capability and Litigation History.
Evaluation Criteria:
Applicants meeting the minimum requirements mentioned above besides other factors shall
be considered for pre-qualification. No compromise shall be made on minimum requirements
of 50% score in each category.
Evaluation Result (Passing/Maximum):
Bidder
Financial Experience Personnel
Tool &
Plant
Total
Marks
PEC
Category
Status
15/30 17.5/35 7.5/15 10/20 50/100 A/B Q/CQ/NQ
Guide Book Cost and Contracts
SECTION-II 19
A 18 23 14 13 68 A Q
B 0 2 4 18 24 B NQ
C 0 3 0 13 16 B NQ
D 30 24 15 19 88 A Q
E 12 27 12 16 67 B CQ
F 12 25 5 17 59 B CQ
Q=Qualified, CQ=Conditional Qualified, NQ=Not Qualified
PEC Evaluation Criteria for Qualification; An example merely as guideline is given in
detail in PEC Procedure for pre-qualification of constructors.
PEC Pre-qualification documents based on Engineering Works bye-Laws:
E Pre-qualification is an assessment made by the Employer, of the appropriate level of
experience and capacity of firms before inviting a constructor to bid.
E Bidder/Constructor means any person, partnership, corporate body or other legal
entity registered or licensed as such by the PEC (works/bye-laws 2(f)).
E Sub-contractor means the constructor who has been sublet work by the prime con-
tractor (w/bye-laws 2(n)).
E Construction Contract means the contract under which the contractor promises to
complete the project undertaken by him through prime contract, sub-contract or in any
other form of contract regardless of the appellation thereof, and the other party prom-
ises to duly effect the payment for such project executed by the said contractor
(w/bye-laws 2(e)).
E Construction of an engineering work shall also mean to include surveys, sub-soil
and other investigations, erection, installation, testing and commissioning and execu-
tion of any other activities required to achieve the desired final shape of an engineer-
ing work, and shall also include extension remodeling, rebuilding and repair works
(w/bye-laws 2(d)).
E Registration of Constructors by some organization is not a substitute of Pre-qualifica-
tion.
E Organization blacklisting constructors shall inform PEC reasons for such action
(w/bye-laws 8(11)).
E Consulting engineer shall monitor constructors license status and inform PEC
(w/bye-laws 8(12)).
Priority of Documents:
E Provisions stated in the Pre-qualification Documents.
E In absence relevant provision in PEC Act, bye-laws, procedure.
E Pre-qualification Documents can not be prepared in contradiction to statute laws &
relevant PEC Procedure and bye-laws.
E Priority of PEC Documents:
Act
Relevant Bye-laws
Procedure (Guidelines)
Guide Book Cost and Contracts
20 SECTION-II
E PPRA Rules are assimilated in June 11, 2007 PEC documents.
PEC Licensed Contractors:
E Engineering works to be assigned only to PEC licensed constructors
E 20% of work of other discipline can be executed by a licensee, in a particular field or
disciplined, in which he is entitled (w/bye-laws 4(3)).
E Foreign contractors license in two stages
E Foreign contractors shall work with maximum 70% share of work in J/V with Pak-
istani contractors with minimum 30% share of work (w/bye-laws 7(2)).
E No separate license of J/V required (w/bye-laws 4(10))
E J/V can work for value more than their individual entitlement (w/bye-laws 4(10)).
E Can a licensed non-pre-qualified constructor bid in J/V with a pre-qualified bidder?
Yes; provided non-pre-qualified constructor subsequently found within pass
limit.
Foreign constructors Enlistment Certificate can be treated as domestic con-
structors license.
Pre-qualification must be as J/V (w/bye-laws 4(10))
License to foreign constructor is issued for project to project basis; therefore,
license is possible only for winning bid (w/bye-laws 7(2)).
Two or more firms of common individual can not bid separately but in J/V
(w/bye-laws 7(4)).
PEC license not required for only supply contracts, since, it is not engineering
works (Act.2(k))
PEC licensed in appropriate category
Note :
PEC Standard Procedure for Pre-Qualification of Constructors contains instructions to
users to use the document and to evaluate the pre-qualification application. In the
Invitation for Pre-qualification of Constructors, Instruction to Applicants and Letter of
Application, the User may make changes in the text only under some special
circumstances.
Pre-qualification Documents :
(Based on WB/ADB Standard Forms)
The Employer is responsible for the preparation and issuance of the Prequalification Docu-
ment (PQD).
The Employer shall prepare the PQD using the published version of the WB/ADB Standard
Documents without suppressing or adding text in Section I, Instructions to Applicants (ITA),
which does not allow modifications for works which are funded by the Bank.
The Employer and the Applicant should keep in mind that all information and data specific to
an individual prequalification process must be provided by the Employer in the following
sections:
Section I, Instructions to Applicants (ITA)
Section II. Prequalification Data Sheet (PDS)/ Applicants Data Sheet (ADS)
Guide Book Cost and Contracts
SECTION-II 21
Section III. Qualification Criteria
Section IV. Application Forms
Section V. Eligible Countries
Section VI. Scope of Works
Section VII. Evaluation of Applications
The Applicant is responsible for the preparation and submission of its application.
During this stage, the Employer shall promptly respond to requests for clarifications from
Applicants and amend, as needed, the PQD.
The Employer shall appoint experienced staff to conduct the evaluation of applications.
Section I. Instructions to Applicants
The Instructions to Applicants (ITA) specify the procedures that regulate the prequali-
fication process.
The ITA contains standard provisions that have been designed to remain unchanged,
their wording should not be modified.
The ITA refers those clauses that need to be complemented to suit the conditions of a
particular pre-qualification process to the Prequalification Data Sheet (PDS); the PDS
provides such additional information.
Sample:
A. General
1. Scope of
Application
1.1 In connection with the Invitation for Prequalification indicated in Section-
II, Prequalification Data Sheet (PDS), the Employer, as defined in the
PDS, issues this Prequalification Document (PQD) to applicants
interested in bidding for the works described in Section-VI, Scope of
Works. The name and identification of contract corresponding to this
prequalification, are provided in the PDS.
2. Source of
Funds
2.1 The Employer will arrange the finance towards the cost of the project
named in the PDS. The Employer intends to apply a portion of the funds
to eligible payments under the contract resulting from the bidding for
which this prequalification is conducted.
Sample:
Section II. Prequalification Data Sheet (PDS)
A. General
ITA 1.1 The Employer is: : [ insert full name, including name of Project Officer, and
address]
ITA 1.1 The list of contracts is: [insert number, names and identification numbers]
ITA 2.1 The name of the Project is: [insert name of Project]
ITA 4.1 (i) The parties in a JV [insert shall or shall not] be jointly
and severally liable
(ii) Maximum number of partners in the JV shall be: [insert a
number or insert not limited]
B. Contents of the Prequalification Document
Guide Book Cost and Contracts
22 SECTION-II
ITA 7.1 For clarification purposes, the Employer's address is:
[insert information _or state same as in 1.1 above]
Attention: [insert name of Project Officer]
Address: [insert full contact/address]
Note: The above provision may be amended as per specific requirements. A couple of
sample Forms are given at the end.
2. Historical Contract Non-Performance
2.1 History of Non-Performing Contracts
2.2 Failure to Sign Contract
2.3 Pending Litigation
3. Financial Situation
3.1 Financial Performance
3.2 Average Annual Construction Turnover
4. Experience
4.1 General Construction Experience
4.2 Specific Construction Experience
Section IV. Application Forms
The Employer shall include in the PQD all application forms that Applicants must complete
and submit together with their applications. These forms are as specified in Section IV of the
prequalification document:
a. Application Submission Form
b. Applicant Information Form
c. Applicant's Party Information Form
d. Historical Contract Non-Performance
e. Financial Situation
f. Average Annual Construction Turnover
g. General Construction Experience
h. Similar Construction Experience
i. Construction Experience in Key Activities
Example: Financial Soundness of the Bidders;
Audited balance sheet for last 5 years to demonstrate:
Sr.# Financial Information
Actual: previous five years (US $ million)
5 4 3 2 1
1. Total assets 18.5 19.0 20.0 23.0 25.0
2. Current assets 12.0 13.0 14.5 14.0 15.0
3. Total liabilities 9.0 10.5 10.0 11.0 11.5
4. Current liabilities 7.0 6.5 7.0 7.5 7.8
Guide Book Cost and Contracts
24 SECTION-II
5. Profits before taxes 1.4 1.3 1.3 1.4 1.8
6. Profits after taxes 1.0 0.9 0.9 1.0 1.3
7. Net worth (1) - (3) 9.5 8.5 10.0 12.0 13.5
8. Current ratio (2)/(4) 1.7 2.0 2.1 1.9 1.9
9. Return on equity % (5)/(7 of
prior year)
13.7 15.3 14.0 15.0
1. Current soundness of applicants and long term profitability;
Curent ratio = Curent assets / Curent liabilities
Average over last 5 years = (1.7+2.0+2.1+1.9+1.9)/5 = 1.9
If <1.5, then risk of potential financial problem exists for last 5 years.
Return on Equity = Profits before taxes / Net worth of prior year %
Average over last 5 years = (13.7+15.3+14.0+15.0)/4 = 14.5
If <10, then it is not consistent with net worth record for specified period.
2. Capacity to cash flow;
Contract Description: Building Construction
Estimated Cost (Including contingencies): US$ 528 million
Duration: 2 years
Cash flow = 528/24 = US$ 22 million per month
For four months = 22x4 = US$ 88 million
WB & ADB requires cash flow for about four months
3. Average annual construction turn over
Turn over = 528/2 = $ 264 million per year
Average annual turnover = 264x1.5* = US$ 396 million
*Factor = 2 if contract price is less than US$ 200 million
Section V. Eligible Countries
This Section states the country eligibility policy of the Employers Country, and provides lists
of ineligible countries.
Section VI. Scope of Work/Contract
WB Based;
The Scope of Works should provide sufficient information for an Applicant to decide whether
or not to compete for that type of works, and whether it will need to use subcontractors for
specific parts of the Works, and/or form a Joint Venture. It should provide information on the
three following aspects:
1. Description of the Works
Describe the Works in sufficient detail to identify location, nature, and complexity. Estimat-
ed quantities of major components of the works should be indicated in the bill of quantities.
2. Construction Period
Guide Book Cost and Contracts
SECTION-II 25
State expected construction period and time in weeks or months; if alternative time schedules
are permitted, give the range of acceptable construction periods. Additional construction time
may be permitted for a combination of contracts if prequalification is for multiple contracts.
The evaluation shall then take into account the benefits foregone for the longer times of
completion.
3. Site and Other Data
Provide general information on the climate, hydrology, topography, geology, access to site,
transportation and communications facilities, medical facilities, project layout, facilities,
services provided by the Employer, and other relevant data.
ADB Based;
The Scope of Contract should be complete, precise and clear in order to avoid unnecessary re-
quests for clarification from Applicants that may cause delays in the prequalification process.
Depending on the nature of clarifications, the Employer may need to amend the Prequalifica-
tion Document and eventually extend the deadline for submission of Applications.
A. Requirements
1. Brief Description of the Scope
2. Major Contract Components
3. Estimated Quantities of Major Components
4. Methods Required
5. Contract Implementation Period
B. Supplementary Information
1. Project Country
2. Contract Site
C. Facilities to be Provided by the Employer
Guide Book Cost and Contracts
26 SECTION-II
Sample:
Application Submission Form
Date: ____________
IFP No.: ___________
Title: _________________________
To:
General Manager (C&M) Water, WAPDA,
530, WAPDA House, Lahore
We, the undersigned, apply to be prequalified for the referenced Bid and declare that:
(a) we have examined and have no reservations to the Prequalification Documents, including
Addendum(s) issued in accordance with Instructions to Applicants (ITA) Clause 8;
(b) we, including any subcontractors or suppliers for any part of the contract resulting from this
prequalification process, have nationalities from eligible countries, in accordance with ITA
Sub-Clause 4.3;
(c) we, including any subcontractors or suppliers for any part of the contract resulting from this
prequalification, do not have any conflict of interest, in accordance with ITA Sub-Clause 4.4;
(d) we, including any subcontractors or suppliers for any part of the contract resulting from this
prequalification, have not been declared ineligible by the Employer's country laws, official regulations,
or under execution of a Bid Securing Declaration in the Employer's Country or having submitted Bid
Security did not sign the contract after receipt of Letter of Acceptance as a successful Bidder, in
accordance with ITA Sub-Clauses 4.6 and 4.8;
(e) we are not a Government owned entity and if we are, we meet the requirements of ITA Sub-
Clause 4.7;
(f) we, in accordance with ITA Sub-Clause 24.1, plan to subcontract the following key activities
and/or parts of the works:
______________________________
______________________________
(g) we declare that the following commissions, gratuities, or fees have been paid or are to be paid
with respect to the prequalification process, the corresponding bidding process or execution of
the Contract:
Name of Recipient Address Reason Amount
________________
________________
________________
________________
________________
________________
________________
________________
________________
________________
________________
________________
(h) We understand that you may cancel the prequalification process at any time and that you are
neither bound to accept any application that you may receive nor to invite the prequalified
applicants to bid for the contract subject of this prequalification, without incurring any liability to
the Applicants, in accordance with ITA Clause 26.
Signed _____________________________
Name _______________________________ in the Capacity of ____________________________
Guide Book Cost and Contracts
Preliminary Examination:
Completeness of documentation
Eligibility
Joint. Venture requirements
Qualification Assessment
History of Non-Performing Contracts
Pending Litigation
Financial Performance
Average Construction Turnover
General Construction Experience
Similar Construction ?/?Experience
Experience
Prepare report and notification and
seek Employers approval/Banks no
objection as necessary
NO
SECTION-II 27
Duly authorized to sign the application for and on behalf of:
Applicants Name _________________________________________________________________
Address _________________________________________________________________________
Dated on ________ day of ______________, __________
Sample:
Form ELI -1.1
Applicant Information Form
Date: _______________
IFP No.: _______________
Page _____of _____ pages
Applicant's/ Joint Venture applicant legal name:
In case of Joint Venture (JV), legal name of each partner:
Applicant's Actual or Intended country of constitution:
Applicant's actual or Intended year of constitution:
Applicant's legal address in country of constitution:
Applicant's authorized representative information
Name:
Address:
Telephone/Fax numbers:
E-mail address:
Attached are copies of original documents of
E Articles of Incorporation or Documents of Constitution, and documents of registration of the legal
entity named above, in accordance with ITA 4.3.
E In case of JV, letter of intent to form JV or JV agreement, in accordance with ITA 4.1.
E In case of Government owned entity, documents establishing legal and financial autonomy and
compliance with commercial law, in accordance with ITA 4.7.
Section VII. Evaluation of Applications Yes / No basis
Guide Book Cost and Contracts
Preliminary Examination:
Completeness of documentation
Eligibility
Joint. Venture requirements
Qualification Assessment
History of Non-Performing Contracts
Pending Litigation
Financial Performance
Average Construction Turnover
General Construction Experience
Similar Construction ?/?Experience
Experience
Prepare report and notification and
seek Employers approval/Banks no
objection as necessary
NO
28 SECTION-II
The following flow chart indicates the successive steps of the evaluation process as a Guide
during the evaluation, concurrently with Section-III. This Section is the part of users guide
only.
Prequalification Evaluation Flow Chart
Post-qualification :
World Bank
Guide Book Cost and Contracts
NO
Submission of Applications
Preliminary Examination:
Completeness of documentation
Eligibility
Joint. Venture requirements
Request clarification and/or
substantiation of information from
Applicant
Does Applicant
substantially
comply with
preliminary
examination ?
Reject the Application.
Prepare reasons for rejection
Qualification Assessment
History of Non-Performing Contracts
Pending Litigation
Financial Performance
Average Construction Turnover
General Construction Experience
Similar Construction ?/?Experience
Experience
Are
the Applicants
deficiencies
material?
NO YES
YES
NO
YES
Are the
Applicants
deficiencies material?
Request clarification and/or
substantiation of Information from
Applicant
Does
the Applicant meet
all
the qualification
criteria ?
Does clarification and/or
substantiation of information
substantially meet the
qualification criteria
Qualify the Applicant
Prepare report and notification and
seek Employers approval/Banks no
objection as necessary
Conditionally
qualify the
Applicant
NO
YES
YES
NO
SECTION-II 29
An assessment made by the Employer after the evaluation of bids and immediately
prior to award of contract, to ensure that the lowest-evaluated, responsive, eligible
Bidder is qualified to perform the contract in accordance with previously specified
prequalification requirements.
The Standard Bidding Documents prepared for use for the procurement of works for
smaller contractsvalued at generally less than US$10 million, may be used under
post-qualification of the bidders.
Does not prefer Post-qualification for large and complex works.
PPRA
Does not prefer Post-qualification.
ADB
Does have Post-qualification Bidding Documents, as SBD for Procurement of Works
without Following Prequalification.
The Post-qualification process may be used for contracts of simple nature to be pro-
cured through National Competitive Bidding valuing generally less than US$
01 million.
The prequalification shall be used for National Competitive Bidding for the contracts
for sophisticated works like fabrication of technically complex plant and equipment.
PEC
PEC Bidding Documents may be used for Post-qualification.
Note: The Single Stage-Two Envelop bidding procedure may be termed as the refined form of
Post-Qualification, therefore being a well recognized transparent bidding procedure,
Single Stage-Two Envelop should be used instead of Post-qualification.
Complete sets of Prequalification Documents are available on the following web sites:
www.pec.org.pk
www.picc.org.pk
www.worldbank.org/procure
www.adb.org/Procurement
www.ppra.org.pk
Guide Book Cost and Contracts
SECTION-I 30
PEC Bidding Documents for Procurement of Works
(Works worth more than Rs 25 million)
Bidding and Contracting Requirements
o Bidding documents are the fundamental documents and the basis for the execution of
contracts.
o Well prepared bidding documents are essential for the success of projects. Ambigu-
ous, incomplete or inconsistent bidding documents not only cause confusions and mis-
understandings, errors and are the source of delay and construction errors, resulting in
costly disputes or litigation.
o It is thus vital to establish uniform procedures and standards for preparing bidding
documents to minimize confusions, errors, delays and disputes.
Basis of the Documents
FIDIC GCC PART-I: 1987 (4
th
Edition) reprinted in 1988 and 1992 with further
amendments
Pakistan Standard Conditions of Contract (Civil), 1st Edition reprinted in July 1993
Standard Bidding Documents finalized by WAPDA in 1987 for use on medium sized
contracts
National Highway Authority Contract No.1, Indus Highway Project (N-55)
Asian Development Bank-Sample Bidding Documents
World Bank Standard Bidding Documents-Procurement of Works May 2005 (based
on FIDIC 99 Second Edition)
Public Procurement Rules, 2004
Nature of the Documents
For Civil Works (may also include related works)
Finalized by PEC Act & bye-laws Committee
Reviewed by stakeholders employers, consultants, constructors, Govt. organizations
Approved and Notified by P&D GoP and ECNEC in 2002 and 2004 respectively
Revised on June 11, 2007 and Notified by ECNEC on Feb 12, 2008
Law of the land for all private/public sector projects over Rs. 25 million
Under P&D 2004 Notification non use of the document will attract suspension of
PSDP funds
Revised on March 2006 & June 2007
Relevant PPRA rules included
Integrity Pact added under PMs directive
Combined COPA I & II as PCC
Reduced large work value from Rs. 50 million to Rs. 25 million
Changed the word Tender to Bid
Harmonized the Documents with PPRA
Insurance bonds at the option of Contractor
Payment period increased to 28 days
Guide Book Cost and Contracts
SECTION-II 31
Delayed payment compensation revised as KIBOR+2% for local and LIBOR+1% for
foreign currencies.
Purpose of the Documents
Increasing uniformity and productivity
Equitability among the contracting parties
Ensuring quality construction
Minimizing malpractices in award and execution
Timely completion of the projects
Avoidance of cost overruns
Growth of construction and consultancy sectors
Compliance of international standards and WTO provisions
Structure of the Documents
Instructions to Users of the Documents
Invitation for Bids
Instructions to Bidders
Bidding Data
General Conditions of Contract, Part I (GCC)
Particular Conditions of Contract, Part II - (PCC)
Specifications - Special Provisions
Specifications - Technical Provisions
Form of Bid & Appendices to Bid
Sample Bill of Quantities
Form of Bid Security
Form of Agreement
Form of Performance Security/Bond & Mobilization Advance Guarantee/Bond
Drawings
Salient Instructions
Read the Instructions as check list
Part I of GCC to remain unchanged
Amendments in Part II, PCC are guided or as per requirement.
Any amendment in Part II, PCC shall not alter the spirit of the documents
All the spaces to be filled in and instructions within parenthesis to be deleted appro-
priately
Instructions to Bidders and Bidding Data may not form part of the contract
Invitation for Bids
Normally remains part of the Bidding Documents
Calls for PEC license and pre-qualification / enlisting requirement (IB-3)
Blank spaces for the following to be filled by Employer:
Name of employer, funding detail, name of project and brief project
descriptions
Guide Book Cost and Contracts
32 SECTION-II
Employers mailing address
Cost of Bidding Documents
Bid Security amount; delivery address; hours and date; time for bid opening
on same date
Instructions to Bidders (IB)
No change required in Instructions to Bidders
Notes on Bidding Data will be deleted
Instructions in parenthesis only will be deleted
In case of conflict , the information in Bidding Data will supersede those of the In-
structions to Bidders
Documents comprising the bid are listed in IB-7
IB, GCC, PCC, Forms and all other items in IB-7 to be prepared/reviewed by
the employer
Bidding Data (BD)
Instructions to fill Bidding Data are as under:
1.1 Name and address of the Employer:
[Name of the Employer and his representative complete with address tele, fax, etc.]
1.1 Name of the Project & Summary of the Works:
[Insert brief summary, including relationship to other contracts under the Project. If
the Works are to be tendered in separate contracts, describe all the contracts.]
2.1 Name of the Borrower/Source of Financing/ Funding Agency:
[Insert name of Borrower and statement of relationship with the Employer, if different
from the Borrower]
2.1 Amount and type of financing:
[Loan/credit in various currencies towards the cost of the project]
8.1 Time limit for clarification:
[Minimum number of days to seek clarification by the prospective bidder may be
inserted as 28 days.]
10.1 Bid language:
[The same language in which the Bidding Documents are written. English, should be
used in National/ International Competitive Bidding.]
11.1(b) Prequalification Information to be updated:
[Indicate what items of information submitted with application for prequalification is
to be updated. It may include: Evidence of access to financial resources, works
awarded during the interim period, availability of essential critical equipment etc.]
11.1(c) Furnish Technical Proposal:
[The bidder to submit a technical proposal in sufficient detail to demonstrate the
adequacy of the bid in meeting requirements for timely completion of the Works.]
13.1 Currencies of Bid and Payment:
Guide Book Cost and Contracts
SECTION-II 33
[Bidders to quote entirely in Pak. rupees but specify the percentages of foreign
currency they require]
14.1 Period of Bid validity:
[Insert number of days after the deadline for Bid submission. Normally the validity
period should not exceed 182 days.]
15.1 Amount of Bid Security:
[This amount should be the same as also quoted in the Invitation for Bids. A fixed sum
is advisable with 1 to 3 % of engineers estimate]
17.1 Venue, time, and date of the Pre-Bid meeting:
[Insert address of venue, or indicate that the meeting will not take place. The meeting
should take place not later than four weeks before the deadline for Bid submission. It
should take place concurrently with the Site visit, if any (see Sub-Clause IB-6).]
18.4 Number of copies of the Bid to be completed and returned:
[Usually one original and two copies]
19.2(a) Employer's address for the purpose of Bid submission:
[Should match the receiving address provided in the Invitation for Bids.]
19.2(b) Name and Number of the Contract:
[Insert and number of Contract.]
20.1(a) Deadline for submission of bids:
[The time and date should be the same as that given in the Invitation for Bids]
23.1 Venue, time, and date of Bid opening:
[Date should be the same as that given for the deadline in Invitation for Bids but
time for opening of bids shall be at least thirty minutes after the time for the deadline
for submission of bids].
32.1 Standard form and amount of Performance Security acceptable to the
Employer:
[Select the kind of Performance Security (bank guarantee and / or insurance bond),
and indicate the amount.
An amount equal to 10 percent of the Contract Price is commonly specified for bank
guarantees, which %age should match with that stipulated in Appendix-A to Bid.
WAPDA requires bank guarantee]
Bid and Appendices
1. Form of Bid - only Bid Reference to be provided by Employer
2. All other blank spaces shall be filled by the Bidder
3. Bidder must sign and stamp Form of Bid appropriately
Appendix A: Special Stipulations
1. Engineers Authority to issue Variation GC 2.1
Guide Book Cost and Contracts
34 SECTION-II
[up to 2 % of the Contract Price]
2. Amount of Performance Security GC 10.1
[10 % of the Contract Price]
The cost of complying with requirements of this Sub-Clause shall be borne by the
Contractor (PEC).
If in compliance with requirements, the charges to be incurred, is made part of BoQ
under Bill Nr. 1: General Items;
The Contractor will arrange the Security, 10% of Contract Price from the bank, and in
this connection bank charges incurred by the Contractor will be paid to him through
BoQ item, generally known as prime cost/LS item.
Example: Engineers Estimate is Rs 1000 million with one year completion and
one year defect liability (maintenance) period.
Bank Charges;
Performance Security (PS) @ 10% of EE = Rs 100 million
a) Bank Alfalah will charge @ 3.22 % of PS per year
=> Rs 6.44 million for 2 years
b) H B L @ 1.72 % of PS per year
=> Rs 3.43 million for 2 years
c) A B L @ 1.43 % of PS per year
=> Rs 2.85 million for 2 years
d) N B P @ 2.03 % of PS per year
=> Rs 4.06 million for 2 years
It may be 2% to 3% for estimation purpose;
However normally charges are used.
3. Time for Furnishing Programme GC 14.1
[Within 42 days from the date of receipt of Letter of Acceptance]
4. Min. amount of third party insurance GC 23.2
[Rs 12.00 million]
Example: Insurance Coverages, Clause GC - 21, 23 & 24;
Section I;
Material Damage: Sum Insured (Contract Sum plus 15%)
Say Rs 1,000,000,000
Act of God including rain Rs 1,800,000
All other perils Rs 900,000
Equipment: Repair/replacement value
Section II;
Guide Book Cost and Contracts
N B P
SECTION-II 35
Third Party Liability: Limit of indemnity in respect of one or
series of accidents arising out of one event i.e. Rs 12,000,000 De-
ductible for one occurrence Rs 120,000
Bodily Injury:
Property damage:
Section III;
Workman Compensation: The Insured/Contractors liability
to employees (Workman) of the Contractor.
Compensation according to Workmen's Compensation Act,
1923 - Schedule I to IV.
The Costs of arranging such insurances shall be borne by the Contrac-
tor (PEC).
If these Costs/Premiums are made part of BoQ under Bill Nr. 1: Gener-
al Items;
The Costs of arranging such insurances/Premiums, incurred by the Contractor will be
paid to him through BoQ items, generally known as LS items.
Example: Engineers Estimate is Rs 1000 million with one year completion and
one year defect liability (maintenance) period.
i) Contractor All Risk Policy (CAR);
Premium @ 5 of value of work.
=> (5/1000 x 1000) = Rs 5.00 million
ii) Contractor Plant & Machinery (CPM);
Premium @12.5% on CAR Premium per year;
=> (12.5/100 x 5 x 2) = Rs 1.25 million for 2 years.
Total Premium for CAR & CPM = Rs 6.25 million for 2 years
iii) Third Party Liability (TPL);
Premium @10% on CAR Premium, per year;
=> (10/100 x 5 x 2) = Rs 1.00 million for 2 years
iv) Workman Compensation (WC);
Premium 5% on total salary component;
Total salary component for 2 years assumed = 18% of value of work
Salary component for 2 year = 18/100 x 1000 = Rs 180 million
WC Premium @ 5% on total salary component.
=> (5/100 x 180) = Rs 9.00 million
Note: These premiums based on are generally considered for estimation purpose.
The value of premium is on lower side for higher value of work.
5. Time for Commencement GC 41.1
[Within 14 days from the date of receipt of Engineers Notice to Commence]
6. Time for completion GC 43.1 & 48.2
Guide Book Cost and Contracts
N I C L
36 SECTION-II
[364 days]
7(a) Amount of Liquidated Damages GC 47.1
[Rs 27,397/- per day]
Example: Engineers Estimate is Rs 1000 million with one year completion and
one year defect liability (maintenance) period.
LD per day = % to 1% x V/P, where % to 1% depends on size and
period of work, V is value of work (Engineers Estimate) say Rs 1000
millions and P, completion period in days, e.g. (one year) 365 days.
Considering 1% of Engineers Estimate per day;
LD = 1/100 x 1000,000,000/365 = Rs 27,397/- per day up to the limit 10%
of the Contract Price.
As per WB and ADB, usually liquidated damages are set between 0.05
percent and 0.10 percent per day. If Sectional Completion and Damages
per Section have been provided, the latter should be specified.
As per PEC, it shall be a sum equal to 10 % of the likely cost of the Works
divided by one-fourth of the number of days specified as completion time.
Mere calculation based on percentage basis, which is common in
practice, should be avoided!
7(b). Amount of Bonus GC 47.3
[If applicable half of the LDs per day subject to a maximum of 5% of Contract price]
8. Defects Liability Period GC 49.1
[364 days]
9. Percentage of Retention Money GC 60.2
[10 % of the amount of Interim Payment Certificate.]
Example: Engineers Estimate is Rs 1000 million with one year completion and
one year defect liability (maintenance) period.
The amount of an IPC/Running Bill is Rs 83 million. (Rs.1000/12)
Retained Money = 10/100 x 83 = Rs 8.3 million per IPC
10. Limit of Retention Money GC 60.2
[5 % of Contract Price]
Example: Engineers Estimate is Rs 1000 million with one year completion and
one year defect liability (maintenance) period.
Limit of Retention = 5/100 x 1000 = Rs 50 million.
Deduction at the rate of 10% of IPCs up to Rs 50 million.
(50% is released upon issuance of TOC and the remaining 50% i.e. Rs 25
million after DLP)
11. Min. amounting Running Bills GC 60.2
[Rs 50 Million]
Guide Book Cost and Contracts
SECTION-II 37
Example: Engineers Estimate is Rs 1000 million with one year completion and
one year defect liability (maintenance) period.
The minimum amount of Interim Payment Certificate should be deter-
mined by the Employer depending upon the size and duration of the
Works.
Average amount of Running Bills = 1/1.5 x 1000/12 = Rs 55.33, say Rs 50
million
12. Time of Payment of Interim Payment Certificate GC 60.10
[28 days in case of local currency or 42 days in case of foreign currency].
In the event of the failure of the Employer to make payment within the
times stated, the Employer shall pay to the Contractor compensation at the
28 days rate of KIBOR+2% per annum for local currency and LIBOR+1%
for foreign currency, upon all sums unpaid from the date by which the
same should have been paid.
The provisions of this Sub-Clause are without prejudice to the Contractors
entitlement under Clause 69, Default of Employer.
13. Mobilization Advance PCC 60.12 Select one of the following
a) Mobilization Advance; 15 % of the Contract Price (Interest Free)
In two Equal Parts, Ist Part within 14 days after singing the agreement or date
of receipt of Engineers Notice to Commence, whichever is earlier, and Second
part within 42 days from the date of payment of the first part.
The Advance shall be recovered in equal installments; first installment at the
expiry of third month after the date of payment of first part of Advance and the
last installment two months before the date of completion of the Works.
(WAPDA allows: 10% to 15% of the Contract Price)
b) Mobilization/ Demobilization Cost; 15% of the Contract Price
80 % of the Mobilization Cost shall be paid for mobilization at Site and 20 % of
Mobilization Cost shall be paid for operation and maintenance of the constructed
facilities and for demobilization as per schedule of payment.
c) Materials Supplied by Employer;
The Employer shall supply to the Contractor materials, like cement, steel, bitumen
or any other material whichever deemed necessary to complete the project; and
the cost thereof shall be recovered from the Contractor through monthly
statements on the basis of actual consumption.
Appendix B: F/C. Requirements
Stamp Not Used if no foreign currency payment foreseen.
If F.C payment foreseen, blanks spaces in Appendix-B to be filled in by Bidder
(IB-13.1).
Exchange Rate TT&OD Selling Rates published or authorized by SBP 28 days prior
to Bid (IB-13.2).
Percentage and type of F.C without Provisional Sums.
Guide Book Cost and Contracts
38 SECTION-II
Equivalent Rupees on the Exchange Rate.
Data to be filled in accordingly.
Modify Sub-Clauses 72.2 & 72.3 of GCC in PCC accordingly if, exchange rate for
payment is different and payment of Provisional sums in F.C.
Appendix C: Price Adjustment
To be filled in by Employer.
Employer may add/delete/modify elements according to project need.
Federal Bureau of Statistics indices apply where, available.
Appendix-C should be read with Formula under Sub-Clause 70.1 PCC.
Weightages or coefficients to be prepared on rate analysis for project to project.
Price Adjustment apply for contract duration six months or more.
Contractor can submit weightages and source of indices if he differs with Appendix-
C; subject to approval by Engineer [70.1(c) PCC].
Appendix D: Bill of Quantities
Given bills are examples only.
Employer should prepare various bills leaving blank spaces for rates and totals.
Reasonable accuracy in quantity estimate required to avoid cost overruns, Price Ad-
justment accuracy etc.
Appendix E: Construction Schedule
Construction Schedule to be provided by the bidder in prescribed manner.
Completion by parts/section shall be distinctly identified by separate Schedule.
Sheets to be attached as necessary.
Sub-clauses 43.1 & 48 of GCC to be referred.
Clause 43.1: completion part or whole of the works within scheduled time (Clause-
48) or extended time (Clause-44).
Appendix F: Method of Work
Bidder to submit this information.
Organization chart of personnel for various activities.
Mobilization Plan/Facilities be provided.
Method of executing the work etc.
Appendix G: Major Equipment
To be filled in by Bidder in three categories;
- owned
- To be purchased
- To be arranged on Lease
Appendix H: Camp & Housing
Guide Book Cost and Contracts
SECTION-II 39
To be submitted by Bidder.
Sub-clause 34 (labour, staff, camp by Contractor at his own cost and responsibility)
GCC apply.
Site Preparation.
Provision of services.
Construction facilities.
Construction equipment assembly.
Security Services etc.
Appendix I: List of Sub-Contractors
To be submitted by the bidder.
Name of sub-contractors for each part of the work.
Profile of the sub-contractors to be submitted.
PEC license for the sub-contractors to be provided where applicable.
Appendix J: Estimated Progress Payments
To be submitted by the bidder
Quarterly estimates based on his
- Programme of works
- Rates in BoQs
- In Pakistani Rupees
Appendix K: Organization Chart
To be submitted by bidder for
- Supervisory staff
- Labour
Appendix L: Integrity Pact
To be signed and stamped by the bidder
Name of the bidder is to be filled
Mandatory under Prime Ministers directive and PPRA Rules
Punitive action against non-compliance stipulated under Sub-Clause 74.1 PCC
Forms
Bid Security IB-15
Form of Performance Security
Form of Contract Agreement
Mobilization Advance Guarantee
General Conditions of Contract (GCC)
FIDIC 1987, Fourth edition as GCC PART-I, no change is required in the GCC.
Particular Conditions of Contract (PCC)
Change in GCC Guided in Instructions to User of the Documents and space /in-
structions provided in PCC PART-II
Guide Book Cost and Contracts
40 SECTION-II
In the PCC following are the spaces/instructions:
1.1(a)(i) Name and address of Employer
1.1(a)(iv) Name and address of the Engineer
2.1(b) Employer may further vary Engineers duties and authorities
requiring employers approval.
5.2(k) any other document in priority of Contract Documents
14.1 Employer to select appropriate (Bar chart)
21.1 Employer may vary Insurance sub-clause 21.1(b)
53.4 Failure to Comply - This Sub-Clause is deleted in its entirety
60.12 Financial Assistance to Contractor Employer to select one of the
three alternatives and delete the other two
67.3 Arbitration place of arbitration to be provided
68.2 Notice to Employer and Engineer Names and addresses of
Employer and the Engineer to be provided
70.1(b) Price adjustment formula Actual formula to be prepared
73.2 Customs Duty & Taxes Employer may incorporate the provisions
Salient Amendments in June, 2007 Documents
Only one Particular Conditions of Contract instead of two (Part-I & II).
Bid preparation time 42 to 154 days.
No conditions of contract in special provisions.
Technical specifications Guide included environmental, safety and seismic conditions.
Bank Guarantee from schedule bank/ insurance companies in Pakistan.
J/V condition added in Invitation for Bids.
Post qualification for reasons even for Pre-qualified bidder (IB 29.2).
Announcement of bid evaluation report at least 10 days prior to issue of LoA.
No negotiations for award, clarification meetings only to clarify outstanding matters
in bid evaluation reports (IB-31.2).
Integrity Pact added with text at Appendix-L (IB-35).
Price Adjustment: Appendix-C and Formula changed.
Engineer's duties and authorities requiring approval of items added (2.1 PCC).
Provisions for replacement of the Engineer revised (2.8 PCC).
Mandatory requirement for insurance from NIC relaxed (25.5 PCC).
Time for payment harmonized with PPRA (60.10 PCC).
Complete formula for Price Adjustment built-in (70.1 PCC).
Debatable Issues
Invitation for Bids Part of the Bidding Documents.
Instructions to Bidders not part of the contract.
Foreign contractors and funding agencies intend to avoid PEC licensing and J/V re-
quirements.
Guide Book Cost and Contracts
SECTION-II 41
Document signed by participants to be part of the bid evaluation report.
Lowest evaluated responsive bidder to be awarded.
IB.30 does not permit the Employer from escaping award to the lowest.
Employer seeks negotiation but legally not tenable.
Bid and Performance Securities from Insurance Company.
Deletion of Sub Clause-53.4, Failure to Comply.
Price Adjustment for 6 months or more duration contract. Determination of co-effi-
cient often incorrect.
Employer reluctant to include delayed payment compensation provision.
Contractors want Insurance Guarantee at their option.
Specifications: Special Provisions
It can include information specific to the project, about:
Location of project
Site of works
Datum levels
Climate / Data
Utilities
Geology, Hydrology
Extent of work
Description of Works
Shop drawings
Right to change
Contractors responsibility
Quality of Materials
Use of Standards / Specifications
Quality Control (QC) and Quality Assurance (QA)
Contract close-up
Inspection / Tests
Contract Schedule
Layout of works / surveys
Access to site
Facilities by contractors
Facilities by employer
Environmental protection
Lump Sum price breakdown
Measurement / payment
Specifications: Technical Provisions
General items
Care and handling of water including dewatering
Earthwork
Sand and aggregates
Guide Book Cost and Contracts
42 SECTION-II
Cement
Concrete in general
Blinding concrete
Reinforced concrete
Reinforcement
Stone pitching
Canal lining
Bored cast-in-situ RC piles
Brickwork in general
Gate equipment
Miscellaneous works
Reinforced cement concrete railing
Drainage under concrete lining of canal
Note;
Complete form of PEC Bidding Documents is available on the following web sites:
www.ppra.org.pk,
www.pec.org.pk &
www.picc.org.pk
Guide Book Cost and Contracts
SECTION-II 43
Bid Evaluation and Award of Contract
Introduction
Evaluation and Award are most important but often controversial matters.
Bid is an offer or proposal of a specified price.
Bid Price refers to the amount of money needed to acquire something.
Type of bidding ICB, LCB, SSB (Single Source).
Tender and bid are used in the same meaning.
Procedures of biddings:
Single Stage-single envelope
Single Stage two envelopes
Two Stage single envelope
Two Stage two envelopes
Evaluation is the process to determine whether a bid meets specified criteria.
Generally according to provisions in the bid.
Agreement = Bid + Acceptance
A contract is the agreement enforceable by law.
Principles to conform Contract Act 1872.
Essentials of a valid contract: (a) competent to contract (b) free consent (c) lawful
considerations (d) lawful object.
Parameters
Limited to procurement of goods and works.
Process commences upon receipt of bids.
Process ends after Award.
Based on Single Stage Single Envelope method.
Based on the following PEC documents:
Standard Procedure for Evaluation
Instructions to Bidders for Civil Works Documents
Instructions to Bidders for E&M Works Documents
Instructions to Bidders for Smaller Works Documents
PPRA Rules 2004
Construction Engineering Works bye-laws
Planning Commission Guidelines
Priority of Documents for Evaluation
Provisions stated in the Bidding Documents.
In absence relevant provision in PEC Act, bye-laws, procedure.
Bidding Documents can not be prepared in contradiction to statute laws & relevant
PEC framework bidding documents and bye-laws.
Priority of PEC Documents:
Act
Guide Book Cost and Contracts
44 SECTION-II
Relevant Bye-laws
Procedure (Guidelines)
PPRA Rules are incorporated in June, 2007 PEC documents
General Principles
Evaluation shall be based on explicit provisions in the Bidding Documents.
In case deficient, ambiguous provisions; PEC documents and International Practices
to follow.
Three bids requirement is a convention and an inference from Rule # 42 of PPRA
Rules 2004.
Members of Committee for adjudication of evaluation must be engineers.
Instructions to Users of PEC documents are of legal value as rules.
Besides required knowledge, evaluators must have moral integrity, impartiality and
should work on good faith.
Non-transparent evaluation and awards results:
Lack of interest by bidders at large.
Foreign bidders hesitate to invest.
Less competition increased cost, more time for project completion.
Area of Dispute
Substantial responsiveness.
Arithmetic corrections.
Price Adjustments of acceptable deviations (Loadings).
Long list of unresolved issues.
Pre-award negotiations/clarifications.
Domestic Preference.
Conditional acceptance Award to lowest bidder.
Getting Ready for Evaluation
Evaluation team comprising relevant professionals.
Preferably team members should be from among those preparing Bidding Documents.
Necessary checklists, formats specific to the Bidding Documents are ready.
Bid opening materials received:
Copies of bids verified with originals.
Signed statements of the bid opening committee members.
Instructions to proceed with evaluation with schedule.
ISO-9001Process and Quality Plan for evaluation.
Bid Opening
The committee publicly announce and sign tabulated sheet for:
Name of bidder, single or a J/V of firms
Guide Book Cost and Contracts
SECTION-II 45
Quoted Price (read out)
Discounts, if any
Withdrawal of bids, if any
Late receipt of bids, if any
Submission of bid security & amount or otherwise
Alternative bids, if any
Minutes of the meeting prepared by the Committee
Read-Out Total Bid Prices and Discount
Sr.
Nr.
Bidder's
Name
Read-Out Tender Price
Discoun
t
Offered
Tender
Security
Provide
d
Yes/No
Discounted Tender Price
FCC *LCC FCC LCC
EURO USD PKR
EUR
O
USD PKR
1 Bidder A - 1,478,779 43,584,814 Nil Yes - - -
2 Bidder B 2,806,511 - 65,908,443 Nil Yes - - -
3 Bidder C - 2,431,072 68,760,570 Nil Yes - - -
* Includes Provisional Sum of PKR 15,000,000
Preliminary Examination
Pertains to Eligibility, Qualification, Bid Security and Completeness of Bid;
Eligibility of Bidders:
Have valid PEC License.
Pre-qualification/enlisted with Employer.
From eligible countries.
Qualification of Bidders:
Capacity to work & minimum years of work experience.
From eligible source country.
Average Annual turn over during last five years equal to or more than the Bid
price.
Adequate funding facility/line of credit.
If foreign bidder; represented local by agent having maintenance, repair and
spare parts facilities.
Written power of Attorney for the signatory.
Availability of critical construction equipment.
Joint Venture Agreement, in case the bidder is a J/V.
At least one of the J/V partners shall satisfy experience requirement.
Properly signed by the authorized person(s) and the authorization is bona-fide
and available.
Any other items, provided in the Bidding Documents due to its peculiarity.
Documents comprising the Bid are accompanied, duly signed and stamped.
Guide Book Cost and Contracts
46 SECTION-II
Accompanied Bid Securities:
Amount and validity period are adequate.
In the prescribed form.
From Scheduled Bank/ Insurance in Pakistan.
[WAPDA does not allow Bid Securities from any Insurance Company]
For the specified period.
Original Security.
In the name of J/V in case bidder is a J/V.
Segregation of Bid Security in special circumstances.
Clarification of Bids IB.23 & IB.25:
To assist in examination, evaluation and comparison.
Query to bidder is at the discretion of Employer.
Bid-Queries and their responses shall be in writing.
Not to change the substance of the bid.
Requirements for clarifications may also include confirmation and to provide
supporting documents.
Substantial Responsiveness (IB.24 & IB.26):
A substantially responsive bid is one which (i) meets the eligibility criteria;
(ii) has been properly signed; (iii) is accompanied by the required Bid Security; and (iv)
conforms to all the terms, conditions and specifications of the Bidding Documents, with-
out material deviation or reservation.
The details and implications of any deviations which are not explicit
should be clarified by the Engineer/Employer with respective bidders without change in the
substance or price of the bids. Bids with minor deviations may be considered substantially
responsive if their further consideration assigns a monetary cost or adjustment to the bid
for the purpose of bid comparison only.
Bids, not be considered responsive, if:
Not accompanied with bid security.
The bidder/JV Partner participated in more than one bid.
Bid received after deadline for submission.
Bid submitted through fax, telex, telegram or e-mail.
Prices quoted are not firm, in case of firm price contract.
Bidder/JV refuses to accept arithmetic corrections.
Bid is materially different.
Any other conditions of rejection stated in a particular Bidding Documents.
Arithmetic Corrections IB.27:
Check for the discount calculations.
The amount in words will govern instead of amount in figure.
Unit rates govern to correct line total.
Guide Book Cost and Contracts
SECTION-II 47
Exception to the general rule, if the Employer is of the opinion that gross mis-
placement of the decimal point in the unit rate.
Correction thus made is binding upon bidder; non-acceptance will entail for-
feiture of Bid Security.
Material deviation or reservation:
Which affects in any substantial way the scope, quality, or performance of the works?
Which limits in any substantial way, inconsistent with the Bidding Documents, Em-
ployers rights or bidders obligations?
Whose rectification/adoption will affect competitive position of bidders?
Minor informality, non-conformity or irregularity will not constitute reasons for rejec-
tion, which can be waived-off.
Detailed evaluation to be carried out only for the substantially responsive bids.
Detailed Evaluation of Bids
Correction for Prices:
Read-out total bid prices excluding provisional sums and discounts.
Corrected total bid price (discount + arithmetic corrections).
Corrected price converted to single currency.
Evaluated Bid Price after Price Adjustment.
Corrected Total Bid Prices Converted to Single Currency
Sr.
Nr.
Bidders
Name
Corrected Total Tender Price
Corrected Total Tender Price
Excluding Provisional Sums
Eq.PKR
FCC
LCC
PKR
EURO USD
(1) (2) (3) (4) 5={(3)x**}+{(4)-15,000,000*}
1 Bidder A - 1,468,814 43,557,284 146,062,403
2 Bidder B 2,806,511 - 65,908,452 387,689,172
3 Bidder C 2,431,072 68,760,570 248,246,330
*Provisional Sum of PKR 15,000,000 ** Exchange Rate; US$=Pak. Rs 80/-, Euro=Pak. Rs 120/-
Bank is State Bank of Pakistan
Computations & rates to be part of Bid Evaluation Report:
Exchange Rate used on the date of Bid Date for evaluation
Price Adjustments for Technical Compliance
Price Adjustments for Commercial Compliance
Domestic Preference, if applicable
Price adjustments (Loading):
For evaluation purpose only
Only against stated provisions
Completeness included in other items
Missing items competitors average price
Technical compliance highest price of bidders
Guide Book Cost and Contracts
48 SECTION-II
Payment terms highest Bank Rate/annum
Completion Schedule 0.05% of total bid price per day
Commercial Compliance cost of doing the deficiencies
Other deviations Prima Facie situation
Domestic Preference IB.27(E&M):
For Civil Works no preference
Preference for use of indigenous products as per SRO 827, dated: 03-12-2001
All Bidders; domestic, J/V, foreign entitled to Price Preference for minimum
total of 20% value addition
Preference 15%, 20% & 25% are allowed
Preference is calculated on a prescribed formula by reducing corresponding
ex-factory bid price
ADDITIONS, ADJUSTMENTS AND PRICED DEVIATIONS
Bidder Corrected/
Discounted
Bid Price
Additions Adjustments Priced
Deviations
Total Price
(b) + (c) + (d) + (e)
(a) (b) (c) (d) (e) (f)
Each insertion in columns c, d, or e should be explained in adequate detail, accompanied by
calculations.
Summary of Evaluation Procedure
Minor Material deviations
Deviations from the bidding requirements which do not appear at first sight so serious as
to provide immediate grounds for bid rejection maybe considered further in the evaluation
process. The following are examples of such deviations:
i. An amount of advance payment and other payment terms (including retention money,
guarantees, the details of price adjustment provision) differing from the prescribed
conditions;
ii. Non-compliance with local regulations relating to labour, imports taxes, duties, no-
tarization, etc.;
iii. Changes in specified methods of construction or execution (temporary works, shift work
by labour, etc.);
iv. Subcontractors slightly meeting pre-specified requirements;
v. Omission (deliberate or unintentional) of minor works or items included in the scope of
work;
vi. Non-acceptance of full liabilities (e.g. risks to third parties, nearby structures, etc.);
vii. Modification of, or a limit to the amount specified for liquidated damages; and
Guide Book Cost and Contracts
SECTION-II 49
viii. Proposed changes in standards or codes relating to materials, workmanship or design.
After clarification from Bidder, the implication of a deviation may be such as to justify
rejection of the bid as non-responsive. A bid is likely not to be considered if;
i. It is submitted by a Bidder who has participated in more than one Bid.
ii. It is received after the time and date fixed for its receipt.
iii. It is submitted through fax, telex, telegram or e-mail.
iv. It is not accompanied with Bid Security.
v. It is unsigned
vi. Its validity is less than specified.
vii. It is submitted for incomplete Scope of Work.
viii. It indicates completion date later than specified.
ix. It indicates that prices quoted are not firm during currency of the contract except
those prices where escalation/adjustments are permitted in the Conditions of
Contracts.
x. It indicates that material to be supplied does not meet the eligibility require-
ments.
xi. It indicates that Bid Prices do not include the amount of taxes & duties.
xii. If Bidder refuses to accept the arithmetic corrections.
xiii. It is materially and substantially different from the Conditions/Specifications of
Bidding Documents.
xiv. It provides Sub-contracting, contrary to conditions specified in the Bidding Doc-
uments.
xv. It fails to comply Mile-Stones/critical dates specified in Bidding Documents.
xvi. The bidder is not valid license holder of the PEC
Major Material deviations
i. Stipulating price adjustment when fixed price bids were called for.
ii. Failing to respond to specifications.
iii. Failing to comply with Mile-stones/critical dates provided in Bidding Documents.
iv. Subcontracting contrary to the Conditions of Contract specified in Bidding Docu-
ments.
v. Refusing to bear important responsibilities and liabilities allocated in the Bidding
Documents, such as performance guarantees and insurance coverage.
vi. Taking exception to critical provisions such as applicable law, taxes and duties
and dispute resolution procedures.
vii. Those deviations that are specified in the IB requiring rejection of the bid (such as,
in the case of works, participating in the submission of other bids other than as a subcon-
tractor).
Example: Conformance to Bidder Requirements (Commercial)
Sr.
Nr.
Clause
Nr. of IB
Description Specified Requirement Bidder A Bidder B Bidder C
Guide Book Cost and Contracts
50 SECTION-II
1 2.1 Prequalification of
Bidders
Whether the Bidder is pre-
qualified
C C C
2 2.1 Eligibility of
Bidders
Registered with PEC C1 C1 NC1
3 2.1 Eligibility of Plant
and Services
(a) Covering Letter C C C
4 9.1 Documents
comprising the Bid
(b) Form of Bid /Letter of
Offer (duly filled-in,
signed and stamped)
C2 C C
C: Conformance NC: Non Conformance S: Submitted NS: Not Submitted NA: Not Applicable
Example of notes
Bidder A
C1:As required under the provisions of Sub-Clause 2.1 of Instructions to Bidders (IB), PEC
license valid for the year 2005 has been provided for Siemens Pakistan only, whereas,
Bidder has not provided Enlistment Certificate for Siemens AG, Germany.
C2:Bid Schedule A Price Schedule is initialed by a person for whom no Power of Attorney
is available with the Bid. In response to post bid query, Bidder provided Power of
Attorney of required person.
C3:Bid Schedule E Specific Plant Data is not initialed as per Sub-Clause 9.1 of IB.
C4:The amount of Bid Security shown is incorrect. This matter has further been discussed in
the Report.
Evaluation Process
Process to be confidential until Announcement of evaluation result.
Announcement to be made at least 10 days prior to award.
Announcement text has been simplified under IB.24.
Any effort to influence Employer in processing bid or in award may result
in rejection of such bid.
Aggrieved bidder may lodge written complaint within 15 days of Announce-
ment.
Mere lodging complaint should not suspend procurement process.
Employers Evaluation or Grievance Redressal Committee will dispose off
the grievances.
Bid Evaluation will not contain too many unresolved matters requiring reso-
lution prior to award.
Award of Contract
Employers Right to Accept or Reject - PPR-38
Prior to contract award: Accept or reject any bid, annual bidding process and
reject all bids at any time.
No liability of Employer for affected bidders.
Grounds for rejection (without justification) will be communicated to request-
ing bidder(s).
Rejection of all bids shall be notified to all bidders promptly.
IB 29.1 when read in conjunction with PPR-38; lowest evaluated responsive
bidder can not be avoided.
Guide Book Cost and Contracts
SECTION-II 51
Employer shall not award to a bidder black listed by PEC (IB.24).
Employers right to post qualification;
Even the bidders were pre-qualified, for a reason or prima facie evidence.
If pre-qualified, post qualification is for only lowest evaluated responsive bid-
der.
Minimum post qualification review items are; (a) completed at least one such
project and value of the project is equal or higher than the Bid Price in last five
years.
No negotiations but clarifications on outstanding items in Bid Evaluation Report
(IB 31.2).
Conditional Acceptance of bid is not tenable under Section 7 of Contract Act 1872.
Letter of Acceptance to be issued prior to expiration of Bid validity period.
Upon receipt of Performance Security, the Employer will notify others and return their
bid securities.
Failure to furnish Performance Security within 28 days of LOA may annul the award
of contract and forfeit the bid security.
Section 7 of Contract Act 1872
Acceptance must be absolute. In order to convert a proposal into a promise, the
acceptance must:
(1) be absolute and unqualified;
(2) be expressed in some usual and reasonable manner, unless the proposal prescribes the
manner in which it is to be accepted. If the proposal prescribes a manner in which it is
to be accepted, and the acceptance is not made in such manner, the proposer may,
within a reasonable time after the acceptance is communicated to him, insist that his
proposal shall be accepted in the prescribed manner, and not otherwise; but if he fails
to do so, he accepts the acceptance.
Evaluation Report
The Bid Evaluation Summary Checklist shall consist:
* Explanation of any inconsistencies between prices and modifications to prices read
out at bid opening and recorded.
* Details about eliminating of any bids during preliminary examination. Attached
selected pages showing objectionable features.
* Explanation of any substantial corrections for computational errors that may affect the
ranking of bidders.
* The additions, adjustments, and priced deviations shall require detailed explanations
where they may affect the ranking of bidders.
* Eligibility for domestic preference if any must be verified and its details shall be
attached.
* Explanation of any cross-discount not read out and recorded at bid opening. In
addition, copies of any evaluation reports for the other related contracts awarded to the
same bidder may be attached.
* Detailed reasons for refusing to award a contract to a party other than the lowest
evaluated bidder.
Guide Book Cost and Contracts
52 SECTION-II
* If an alternative bid is accepted, provide a detailed explanation of the reasons for its
acceptance, addressing issues of timeliness, performance, and cost implications.
* An attachment explaining adjustments to the price. Also explanation of any changes
to scope of bid and contract conditions.
* Provide evidence of alternative insurance.
* Attach copies of any correspondence from bidders that raise objections to the bidding
and evaluation process, together with detailed responses.
* Attach copies of any letters to bidders requesting clarifications. Provide copies of
responses.
It should be noted that evaluation and the resulting report need not necessarily be lengthy.
Procurement of goods without domestic preference can usually be quickly and easily
evaluated. In general, the complexity of evaluation lies with larger works and with the supply
and installation of industrial plants and equipments.
The report should include a number of attachments to explain details of bid evaluation or to
show specific controversial wording or numbers in a bid. Cross-referencing should be used
extensively, as well as references to pertinent clauses in the bidding documents.
Note:
The evaluation forms and guide providing step-by-step procedures for the evaluation of
bids are available on the following web sites;
www.pec.org.pk
www.picc.org.pk
www.worldbank.org/procure
www.adb.org/procurement
The Role of the Employer & the Contractor
The role of the Employer and the Contract are almost same in the FIDIC 1987 and 1999,
except the provisions of the Employers Personnel and the Employers Claims provided in
FIDIC 1999, beside some other minor differences in relation to the above mention subject. In
FIDIC 1987 the Employer can not invoke his right to claim in a manner given in FIDIC 1999.
Nonetheless under FIDIC 1987, the Employer may deduct money from the Contractors due
payments, only against proven and determined fault of the Contractor and that often occurs
on termination of contracts by the Employer.
The role of the Employer and the Contractor discussed below, are based on FIDIC 1999.
The Role of the Employer
Guide Book Cost and Contracts
SECTION-II 53
The FIDIC standard form for the Contract Agreement includes the statement
that the Employer covenants to pay the Contractor the Contract Price in consideration of
the execution of the Works and the remedying of defects therein. However, this does not
mean that the Employer is only required to appoint an Engineer to administer the project
and then sign the payment certificates.
Even though the Engineer is classed as Employers Personnel there are some
tasks which are allocated to the Employer.
The Employer could delegate the paperwork to the Engineer, but the actual
tasks require the Employer to be involved.
It is important that the Employer designates a staff member, separate from the
Engineer to represent him whenever the Contract requires notice to, or action by the Em-
ployer.
Right of Access to the Site
The Employer shall give the Contractor right of access to, and possession of all
parts of the Site within the time stated in the Appendix to Tender.
The Employer may withhold such site/right of possession until the Perfor-
mance Security has been received.
If no such time is stated in the Appendix to Tender, the Employer shall give
the Contractor right of access to, and possession of the Site within such times as may be
required to enable the Contractor to proceed in accordance with the programme submit-
ted.
If the Contractor suffers any delay as a result of a failure by the Employer to
give any such right or possession within such time, the Contractor shall give notice to the
Engineer and shall be entitled to:
Extension of time for any delay if completion is or will be delayed, and
Payment of any such Cost plus reasonable overhead, which shall be included
in the Contract Price.
After receiving this notice the Engineer shall proceed in accordance
with the clause on determinations to determine these matters. However, if the Em-
ployers failure was caused by an error or delay by the Contractor including an error in, or
delay in the submission of any of the Contractors Documents, the Contractor shall not be
entitled of time and Cost.
The possession does not necessarily mean exclusive possession, but
shared possession needs clarification in the Particular Conditions.
When the Contractor takes possession of the Site, he is responsible for
safety, security and insurance. If the Contractor does not have full control of the Site and
the activities on the Site, or the site will be shared, then the extent of the Contractors re-
sponsibilities must be clearly stated.
If the Employer fails to give right of access to and possession of the
Site within the stated period then the Contractor will be entitled to an extension of time
plus its associated costs with reasonable overhead.
Permits, Licenses or Approvals
The Employer shall provide reasonable assistance to the Contractor at
the request of the Contractor:
By obtaining copies of the Laws of the Country which are relevant to
the Contract:
Guide Book Cost and Contracts
54 SECTION-II
For the Contractors applications for any permits, licenses or approvals
required by the Laws of the Country
Employers personnel
The Employer shall be responsible for ensuring that the Employers
Personnel and the Employers other Contractors on the Site:
Cooperate with the Contractors efforts, and
Take actions similar to those which the Contractor is required to take in rela-
tion to the clauses relevant for Safety Procedures and Protection of the Environ-
ment.
Employer s Personnel includes:
The Engineer and his assistants.
All staff, labour and employees of the Employer and the Engineer.
Any other person who the Employer or the Engineer has decided to designate
as Employers Personnel.
When two or more Contractors are working on the same Site the possibilities of delays
and costs from failures of cooperation can lead to serious problems.
The FIDIC Clauses may be adequate when one Contractor is carrying out a
high percentage of the total work on the Site.
If the work is more evenly divided between two or more Contractors, the pro-
visions of the Contract need to be reviewed.
Employers Claims
If the Employer considers himself entitled to any payment the Employ-
er or the Engineer shall give notice and particulars to the Contractor.
The notice shall be given as soon as practicable after the Employer be-
came aware of the event or circumstances giving rise to the claim.
The particulars shall specify the Clause or other basis of the claim, and
shall include substantiation of the amount and/or extension to which the Employer con-
siders himself to be entitled for the claim.
The Engineer shall then proceed in accordance with the Determina-
tion clause to agree or determine:
The amount that the employer shall be paid by the Contractor.
This amount can be deducted from the Contract Price and Pay-
ment Certificates.
If the Employer deducts money from the Contractor which he
(the Employer) is not entitled to do, will enable the Contractor to claim for all conse-
quences of the deductions.
This could involve a substantial claim by the Contractor. In
such case, the Employer would be advised to reserve his rights but not to deduct any
money until the final resolution of this matter.
The Role of the Contractor
In accordance with the FIDIC form, the Contractor will
execute and complete the Works and remedy any defects therein, in conformity with the
provisions of the Contract.
Guide Book Cost and Contracts
SECTION-II 55
In order to achieve this, the Contractor accepts a large
number of secondary obligations.
The Contractor shall design (to the extent specified in
the Contract), execute and complete the Works in accordance with the Contract and with
the Engineers instructions and shall remedy any defects in the Works.
The Contractor shall provide the Plant and Contractors
Documents specified in the Contract, and all Contractors personnel, Goods, consum-
ables and other things and services required to carry out the Works.
The Contractor shall be responsible for the:
Adequacy,
Stability, and
Safety of all site operations and methods of construction.
The Contractor shall whenever required by the Engineer, submit details
of the arrangements and methods which the Contractor proposes to use.
No significant alteration to these arrangements and methods shall be
made without having been notified to the Engineer.
The FIDIC Conditions of Contract for Construction are intended to be
used for projects with the design provided by the Employer.
The phrase execute and complete is important in the Contract. The
requirement to execute and complete can also give an obligation to complete any item of
work which is necessary for total completion of the Works, but may not have been shown
in detail on the Drawings.
This is an obligation to carry out and complete the Works and the ques-
tion of whether payment is included in the Accepted Amount is a separate issue.
Performance Security
The Contractor shall obtain a Performance Security for proper
performance, in the amount and currency stated in the Appendix to Tender.
The Contractor shall deliver the Performance Security to the
Employer within 28 days after receiving the letter of Acceptance, and shall send a copy to
the Engineer.
The Contractor shall ensure that the Performance Security is
valid and enforceable until the Contractor has executed and completed the Works and
remedied any defects.
If the Performance Security has an expiry date and the Contrac-
tor has not become entitled to receive the Performance Certificate by the date 28 days pri-
or the expiry date, the Contractor shall extend the validity of the Performance Security un-
til the completion of the Works and any defects have been remedied.
Contractors Representative
The Contractors Representative is the Contractors equivalent to the Engineer.
Some Tender Documents specify:
The required qualifications.
The required experience and
That the Contractors Representative must be named in the tender.
The Contractors Representative must:
Guide Book Cost and Contracts
56 SECTION-II
Have received the consent (approval) of the Engineer.
Not be removed or replaced without the prior consent of the Engineer.
Have the authority to act on the Contractors behalf under the Contract.
Be on site whenever work is in progress.
Be fluent in the language for communication stated in the Contract.
Subcontractors
The Contractor shall be responsible for the acts or defaults of any Subcontractor and
his employees.
Cooperation
The Contractor shall allow the following to carry out work on or near the site:
The Employers Personnel.
Any other contractors employed by the Employer.
The personnel of any legally constituted public authorities (government bod-
ies) that carry out work not included in the Contract.
However, the Contractor may make a claim for Unforeseeable Cost
and get paid as a Variation.
Any delays would qualify for an extension of time.
Setting out
The Contractor shall be responsible for the correct positioning of all
parts of the Works, and shall rectify (correct) any error in the positions, levels, dimensions
or alignment of the Works.
Risk Allocation & Management in Construction Contracts
Project risk is an uncertain event or condition that, if it occurs, has a positive or a negative
effect on at least one project objective. A risk may have one or more causes and, if it occurs,
there may be one or more impacts.
All contracts contain risks. The prime objective under a contract is to allocate risks between
parties to the contract. An ideally successful contract is one which got completed in stipulated
time and within the reasonable cost meeting the requisite specifications.
Sources of Construction Contract Risk
Construction Contracts will generally need to identify and assign risks in the following areas:
O Project Execution
Quality
Schedule
Guide Book Cost and Contracts
SECTION-II 57
Cost
O Financial Factors
Escalation
Foreign exchange
Cost of money
O Market Factors
Supply demand in local and global pricing as distinct from escalation
O Regulatory Factors
Change in legislation and regulation
Contract Risk Allocation is Critical
Allocate the risk factor to the party best able to manage the risk
Excessive contractor risk will result in un-economic levels of contingency and
risk costs
Excessive owner risk may make the project un-finance-able
Balance risk allocation to ensure alignment between the Owner and
Contractor on project objectives.
Reflect the reality of the regulatory environment and associated
impact on project scope and schedule.
Terminology
Hazard; a particular event which has the potential if it occurs of an adverse effect.
Risk; the probability of occurrence of a defined hazard and the magnitude of the con-
sequences.
Risk Assessment; the estimation and evaluation of the risk; the magnitude of the con-
sequences together with the probability of the consequences.
Risk Identification; an awareness of those risks which could adversely affect the out-
come of the project.
Risk Management; the identification, measurement and economic control of risks.
Risk Allocation
The main objective of any contract is to allocate risks between the contracting parties. Risks
of likely events and occurrences affecting the performance of contract are allocated between
the Contractor and the Employer through various provisions of the contract.
The understanding of contractual allocation of risks is fundamentally necessary to identify
claims arising from these risks.
The Contractual Risks
There are two types of contractual risks:
Those that have been expressly stated in the contract to be allocated to a particular
party; and
Those risks that are deemed to be included in the contract by the operation of the law
governing the contract.
PEC Form of Contract Document based on FIDIC, 4th Edition, Red Book (Conditions of
Contract for Civil Works) makes the Employer expressly responsible for the risks connected
with certain events and occurrences.
Guide Book Cost and Contracts
58 SECTION-II
Examples of Risks in Construction
Inclement weather;
Unforeseen ground conditions;
Industrial action;
Deficiencies in design;
Insolvency or non-performance by a sub- contractor;
Unavailability of materials;
Cost overruns in labour and materials; and
Occupational health and safety.
Dealing with Risk Allocation
Normally in construction industry people deal with risk by burying their head in the
sand.
If the risks are not ignored, they are dealt with simply by adding contingencies to es-
timated costs and time.
If the risks are actually allocated it is in a lopsided and inappropriate manner.
Rarely is there a structured and logical approach to risk identification, allocation and
management.
Controlling
It can be assumed i.e. risk taking;
It can be priced i.e. built into the tender price;
It can be laid off i.e. insured or passed on to another entity e.g. subcontractor;
It can be refused i.e. decline the job; or
It can be shared i.e. in alternative contractual arrangements such as alliance and
partnering.
But it should never be ignored!
Types of Risks in Construction
Acts Of God
Physical
Financial & Economic
Political & Environmental
Design
Construction Related
Acts Of God
- Flood
- Earthquake
- Landslide
- Fire
- Wind damage
Physical
- Damage to structure
- Damage to equipment
Guide Book Cost and Contracts
SECTION-II 59
- Labour injuries
- Fire
- Theft
Financial & Economic
- Inflation
- Availability of funds
- Exchange rate fluctuations
- Financial default
Political & Environmental
- Changes in laws and regulations
- Requirement for permits
- Law & order
- Pollution and safety rules
Design
- Incomplete design scope
- Defective design
- Errors & omissions
- Inadequate specifications
Construction Related
- Labour disputes
- Labour productivity
- Different site conditions
- Design changes
- Equipment failure
Risk Management
A systematic approach to control the level of risk to mitigate its effects, is known as Risk
management. It refers to the art of identifying, analyzing, responding to and controlling
project risk factors in a manner which best achieves the objectives of all participants.
Contractual risk transfer is a form of risk management which has been employed for many
years in the construction industry. It involves the allocation or distribution of the risks
inherent to a construction project between or among contracting parties. If done effectively,
risk transfer does not grossly or inequitably allocate all risk to one party, but instead places
risk upon parties according to their ability to control and insure against risk. Additionally,
effective risk management typically generates positive results on a project by improving
project performance, increasing cost effectiveness and creating a good working relationship
between contracting parties.
Risk Management System
1. The contract serves as the principal risk management vehicle, par-
ties must begin managing and minimizing risks long before the contract is signed. To
avoid inequities, all parties should come to the negotiating table with some idea of
their risk management goals. Unfortunately, most contractors pay insufficient atten-
tion to the risk management process (e.g., compare budget of estimating department
Guide Book Cost and Contracts
60 SECTION-II
versus investment allocated to training and maintaining cadre of risk management
professionals).
2. Contractual risk transfer in the construction industry is seen most
frequently in contract provisions regarding indemnity, consequential damages, differ-
ing site conditions and delay.
3. Risk management requires a systematic and practical method of
dealing with both the predictable and unpredictable risks inherent in the construction
industry. Contract administrators must acquaint themselves with the risks they are to
manage and develop specific risk minimization strategies. Risk management typical-
ly involves the following functions:
Risk Analysis
Estimating the potential impacts of risk to decide what risks to retain and what risks
to transfer to other parties which include:.
Risk Identification
Risk Estimation
Risk Evaluation
Risk Monitoring
The risk manager must evaluate risk factors or characteristics of a risk such as the
risk event, its probability of occurrence, and the amount of potential loss or gain. The
impact of possible risks can be controlled to the extent the risks are effectively
identified and managed.
Risk Response
I. Elimination, II. Transfer, III. Retention & IV. Reduction
Elimination
- Tendering a very high bid
- Placing conditions on the bid
- Pre-contract negotiations as to which party takes certain risks
- Not biding on the high risk portion of the contract
Transfer
- The activity responsible for the risk may be transferred, i.e. hire a subcontrac-
tor to work on a hazardous process
- The activity may be retained, but the financial risk transferred, i.e. methods
such as insurance.
Retention
- Handling risks by the company who is undertaking the project.
- Two retention methods, active and passive.
Active retention is a deliberate management strategy after a conscious evalua-
tion of the possible losses and costs of alternative ways of handling risks.
Passive retention occurs through negligence, ignorance or absence of decision.
Reduction
- Continuous effort.
Guide Book Cost and Contracts
SECTION-II 61
- Related with improvements of a companys physical, procedural, educational,
and training devices.
- Improving housekeeping, maintenance, first aid procedures and security.
- Education and training within every department.
Model of Risk Allocation
A party to a contract should bear a risk where:-
The risk is within the partys control;
The party can transfer the risk, e.g. through insurance, and it is most economically be-
neficial to deal with the risk in this fashion;
The preponderant economic benefit of controlling the risk lies with the party in ques-
tion;
To place the risk upon the party in question is in the interests of efficiency, including
planning, incentive and innovation; and
If the risk eventuates, the loss falls on that party in the first instance.
The Principal should not ask a Contractor to price an unquantifiable risk that is within
the control of the Principal e.g. ground conditions.
The Principal, may ask the Contractor to manage and control a neutral risk e.g. weath-
er.
The Contractor should carry the risk for the safety of its own workers.
Guide Book Cost and Contracts
62 SECTION-II
Construction Claims Management
The management of construction claims is the greatest challenge that is being faced in todays
competitive business environment. Construction projects are becoming increasingly
susceptible to a variety of factors that give rise to time extensions and cost recovery. Although
the construction business environment has moved toward partnering arrangements in recent
years, the number of contractual difficulties continues to rise. Thus the construction industry
needs to develop methodologies for construction claim management to better manage the
ongoing trend.
In order to understand the nature of claims before dealing with them, the clauses that trigger
claims in a contract are investigated, and to avert conflicts, it is necessary that, the contract
should prescribe:
The respective obligations of contracting parties in clear terms.
Specifies as to when, or the time period within which, the obligations undertaken in
the contract are to be performed.
The events and circumstances whose risk of occurrence is allocated to one party or the
other.
The mechanism to resolve the controversies/disputes connected with or arising from
the Contract.
A well-drafted contract states
The obligations (duties) of each party.
The timings of discharge of obligations (duties)
The consequences, if the party fails to do its duty at the prescribed time (breach).
The completion period of the entire contract.
The risk allocation of the specified unforeseen event or circumstances (causation)?
How and to what extent would the party resultantly suffering from such unpredictable
occurrence be compensated (claim/damages)?
How would the party proceed to get compensation?
Mobilization & Performance Schedule
In view of the contractual duties/obligations and the prescribed completion period the
contractor mobilizes his resources and prepares his performance schedule to meet the
completion deadline so fixed.
The Contractor shall commence the Works on Site within the period specified in Ap-
pendix-A to Bid from the date of receipt by him from the Engineer of a written Notice to
Commence (Sub Clause-41.1, CoC)
An Ideal Contract
If every thing goes well in accordance with what had been foreseen by the parties at the time
of signing the contract then the contractor usually succeeds in completing the contract in the
scheduled time.
The record of construction industry
Completion of any project on time is not so good.
Guide Book Cost and Contracts
SECTION-II 63
Usually public sector construction projects overrun their completion
schedule by more than 40 percent and some of them overrun their original time targets by
more than 80 percent.
Delay in the timely completion of construction projects is the major rea-
son for contractual disputes and claims.
There are other causes of claims also.
Events Intervening Performance
Some events and occurrences may intervene during the performance
which do not allow the contractor to complete his performance within the given comple-
tion period.
Contractors performance is impeded /hampered not necessarily due to
his own default.
Events Adversely Affect Performance
Events within the contractors control or beyond his control may adversely affect his
performance for which the contract may or may not compensate the contractor for loss of
time or/and extra costs incurred during the impeding occurrences.
Slow Progress
- A good Claims Manager develops the necessary insight to identify the
cause that leads to slow progress or disruption of an on-going construction activity and
then find out as to whether or not the said cause leads to a claim in his favour under the
provisions of the contract.
- Successful management of claims gives an edge to the contractor be-
cause through such claims he can make good the loss of time and money occasioned by
the claim events.
Compensatory Provisions
Provisions of the contract may allow compensation to the contractor if he himself has not
caused the impeding event and the other party (Employer) has undertaken the risk of such
happening upon him under the terms of the contract. The demand for such compensations in
terms of time and money is called Claim. Successful management of claims gives an edge
to the contractor because through such claims he can make good the loss of time and money
occasioned by the claim events
The duty/obligation undertaken by the contractor under the terms of the contract
Independent; the contractors performance exclusively, nothing to do
with the performance of other parties in the contract; or,
Dependant upon the performance; of Employer or the Engineer or any
other contractor /third person; or,
Dependant upon circumstances; and situations that were supposed to re-
main unchanged during the execution of the contract.
Primary Source of Claim and Contractual Scheme of Risk Allocation
Claims may not end up as disputes if the parties clearly understand the risk allocation
established by their contract or its governing law.
Claims Provisions under Changed Conditions Clauses in a Contract
The Differing Site/Physical Conditions Clause;
Guide Book Cost and Contracts
64 SECTION-II
The Changes Clause (Character/Scope of work);
The Suspension of Work Clause.
Cost & Time Claims for Compensable / Excusable Delays
Demand for compensations in terms of time and money is called Claim. Successful
management of claims gives an edge to the contractor because through such claims he can
make good the loss of time and money occasioned by the claim events. Understanding the
contractual allocation of risks is necessary to identify claims arising from risks.
PEC Form of Contract Document based on FIDIC, 4th Edition, Red Book makes the
Employer expressly responsible for the risks connected with certain events and occurrences.
Delayed Drawings / Engineers Instructions
Work Program submitted by the contractor is an indicator to the
Engineer as to when the drawings or instructions should reach the contractor without af-
fecting his performance adversely. (Sub Clause-14.1, CoC)
Failure or inability of the Engineer to issue any drawing or in-
struction, for which the Contractor has given prior notice, is a claim-able event. (Sub
Clause-6.4, CoC)
Obstructions or Adverse Conditions encountered during Performance of Contract
Ordinarily, the contractor is not expected to encounter any
physical obstruction or decelerating physical condition during the execution of the Works.
Adverse effect on the performance of the contract caused by
climatic condition on Site is not recognized as a physical condition that would entitle the
contractor to relief under this provision in so far as the cost compensation is concerned.
Time compensation is allowed. (Sub Clauses-12.2 & 44.1, CoC)
Halting Progress of Execution when Confronted with Antiques etc.
The contract requires the contractor to be watchful in case he
finds fossils, coins and antiques of geological or archeological interest on site during exe-
cution of the contract.
Upon discovery of these or such like articles on work site he
is required to halt further progress of work and inform the Engineer immediately. (Sub
Cluse-27.1, CoC)
Instructed Suspension of Contract Execution
The Engineer has authority under the contract to suspend the execution
of the Works or hold back the contractor from performing any part of the contract if he
thinks that the same is necessary.
The contractor is duty bound to comply with such an instructed suspen-
sion. During suspension the contractor is required to protect and secure the works already
executed (Sub Cluse-40.1, CoC).
Reasons for Suspension entailing no compensation
Guide Book Cost and Contracts
SECTION-II 65
The contractor is not compensated for suspension ordered for following reasons:
Due to some default of the contractor, or,
In view of foreseen climatic conditions on site, or,
It is necessary for proper execution of works or their safety, or,
When the instructed suspension is already provided for in the contract.
Opted Suspension of Contract Execution requiring compensation
Whenever payment of a certified amount is delayed by the Employer the contractor, among
other remedies such as interest and termination of contract, is also entitled to suspend
execution of whole of the contracted Works or any part of such works (Sub Cluse-40.2, 40.3,
69.1 & 69.4 CoC).
Possession of Site and its Access
Immediately upon the issuance of Notice to Commence, the
Employer is duty bound to make appropriate proportion of the work site available to the
contractor for work.
In addition the Employer is also duty bound to give proper
access to the work site so that the contractor can mobilize his construction resources and
commence work on the available site (Sub Cluse-42.1 & 42.2, CoC).
Prescribed Risks of the Employer
War:
Revolt:
Ionizing Radiation:
Pressure Waves:
Unrest:
Employers Occupation of Works:
Design Failure:
Forces of Nature/Act of God: (Sub Cluse-20.4, CoC).
Variations
The Engineer has vast powers to vary the contracted Works but usually he is deprived
of any power or limited power to vary the contract. (Sub Cluse-2.1, CoC).
Contractor is to comply with the instruction to vary the quantity, quality, form, char-
acter, kind, position and dimension of the Works. (Sub Cluse-51.1, CoC).
Additional Tests
The Contract always prescribes the tests that are to be performed before, during or af-
ter the execution of the Contract.
These prescribed tests being part of work to be carried out under the Contract they are
deemed to have been accounted for, both in terms of cost & time, by the Contractor in his
bid. (Sub Cluse-36.3, CoC).
If any test required by the Engineer is not intended by or provided for, or not so partic-
ularized in the contract then the cost of such test shall be borne by the Employer. (Sub
Cluse-36.5, CoC).
Guide Book Cost and Contracts
66 SECTION-II
Delay Claims
The term delay in construction activity is used to represent the time during which
some part of the construction project has been extended beyond what had been originally
planned.
This extended time may have been caused due to some unforeseen or unexpected cir-
cumstance.
Delaying incidents
An incident that affects the performance of a particular activity without affecting the
completion deadline is also called delay.
It is not necessary that delay in execution should necessarily disturb the planned com-
pletion deadline.
A delaying incident may originate from within the Contractors organization or from
any other factor interacting with the construction project.
Delaying incidents within the Contractors Organization
The delaying incidents originating within the Contractors organization are
those which have been caused by the Contractor or his representatives.
Mismanagement and absence of planned execution by the Contractor may be
responsible for the delay that results. Contractor is responsible to make good the time
lost due to such delays.
Delaying incidents outside the Contractors Organization
Delaying incidents outside the Contractors organization may be caused by:
Employer, or,
Designer, or,
Other prime contractors, or,
Subcontractors, or,
Suppliers, or,
Labour Unions, or,
Nature, or,
Other organizations and entities which participate in the construction process.
Events entitling for Extension of Time
the amount or nature of extra or additional work, or
exceptionally adverse climatic conditions, or
any delay, impediment or prevention by the Employer, or
any cause of delay referred to in the Conditions of Contract, or
other special circumstances which may occur, other than through a default of or
breach of contract by the Contractor or for which he is responsible,
EOT submission requirements
A description of the cause of the delay and the contractual provision which is
being relied upon for the extension;
The date when the delay commenced and the period for the delay;
Guide Book Cost and Contracts
SECTION-II 67
The date of notice of delay, specifying the reference and relevant documents;
A summary of records and particulars;
A narrative of the events and effect on progress;
A diagrammatic illustration showing the status of the programme progress and
current completion date prior to the commencement of the delay;
A diagrammatic illustration showing the effects of the delay on the progress
and the completion date;
A statement requesting an EOT for the period shown in the illustration.
Procedure for Claiming Extension of Time for Completion Sub Clause-44.2, CoC:
Provided that the Engineer is not bound to make any determination unless the Contractor has;
within 28 days after such event has first arisen notified the Engineer with a copy to the
Employer, and
within 28 days, or such other reasonable time as may be agreed by the Engineer, after
such notification submitted to the Engineer detailed particulars of any extension of time
to which he may consider himself entitled in order that such submission may be
investigated at the time.
Interim Extension of Time Sub Clause-44.3, CoC:
Where an event has a continuing effect such that it is not practicable for the Contractor to
submit detailed particulars within the period of 28 days referred to in Sub-Clause 44.2(b),
CoC, he shall nevertheless be entitled to an extension of time provided that he has submitted
to the Engineer interim particulars at intervals of not more than 28 days and final particulars
within 28 days of the end of the effects resulting from the event.
Valuation of Variation
BoQ Rates: "varied work" shall be valued at the rates and prices set out in the Con-
tract or as basis of valuation. (Sub Clause-52.1, CoC)
Rates derived from BoQ Rates: the rates and prices in the Contract shall be used as the
basis for valuation. (Sub Clause-52.1, CoC)
New Rates: the rate or price contained in the Contract is, by reason of varied work,
rendered inappropriate or inapplicable, then, a suitable rate or price shall be agreed.
(Sub Clause-52.2, CoC)
Variations Exceeding 15 per cent (Sub Clause-52.3, CoC)
If, on the issue of the Taking-Over Certificate for the whole of the Works, it is found that
as a result of:
(a) all varied work valued under Sub-Clauses 52.1 and 52.2, and
(b) all adjustments upon measurement of the estimated quantities set out in the Bill of
Quantities, excluding Provisional Sums, dayworks and adjustment of price made un-
der Clause 70.
but not from any other cause, there have been additions to or deductions from the Con-
tract Price which taken together are in excess of 15 per cent of the "Effective Contract
Price" then in such event (subject to any action already taken under this Clause-52),
there shall be added to or deducted from the Contract Price such further sums determined
by the Engineer having regard to the Contractor's Site and general overhead costs of the
Contract.
Daywork (Sub Clause-52.4, CoC)
Guide Book Cost and Contracts
68 SECTION-II
The Engineer may, if in his opinion it is necessary or desirable, issue an instruction that
any varied work shall be executed on a daywork basis.
Indicators of Claim
Performance difficulty is the first indicator of a likely claim; whenever some occurrence,
condition or event on site creates obvious performance difficulties such difficulty should
immediately be seen against the background of the happening of a likely claim event.
Causes impeding Progress
It is to be seen as to whether the causes impeding the progress of performance of the
contractor are the one:
Whose risk has been undertaken by the Employer or the Engineer/Architect under the
terms of the contract or it is caused by some one else;
Whose risk is attributable to one party or the other under the governing law of the con-
tract.
Management of Claims
Claim management is an important aspect of the overall contract management which is a
salient attribute of the Project Managing. Good project management is based on managing the
contract and the claims properly.
Important Steps in Claims Management
The Claim Index:
It is prepared as a checklist and contains clearly defined various occurrence or course of
events or causes that could possibly result in performance difficulty.
' The Occurrence Report:
' Preparation of Claims:
' Substantiation of Claims:
' Submission of Claims:
Types of Claims
There are mainly three types of claims that arise from any contract:
* Time Claim (Extension of time for completion of contract);
* Cost of Time Claim (Prolongation Costs), and
* Cost Claim (Compensation for extra expense incurred due to an
event whose risk is upon the Employer).
Excusable Delays
Excusable delays are compensated by mere grant of extension of time for completion
without any monetary compensation (additional costs).
Such delays are usually caused by events covered by the force majuere clause of the
contract.
Both the Employer and the Contractor suffer loss, the Employer in terms of late com-
pletion of project and the Contractor for the expense incurred during the delay period.
Instances of Excusable Delays - I
Acts of God or of the public enemy;
Acts of the Government;
Guide Book Cost and Contracts
SECTION-II 69
Acts of another contractor in performance of his contract with the Govern-
ment;
Fires;
Floods; and
Epidemics.
Instances of Excusable Delays - II
Quarantine restrictions;
Strikes;
Freight embargoes;
Unusually severe weather; and
Delays of subcontractors or suppliers at any tier arising from unforeseeable
causes beyond the control and without the fault or negligence of both the contrac-
tor and the subcontractors or suppliers
Compensable Delays
Compensable delays are compensated by grant of extension of time as well as additional cost
incurred due to such delays.
Procedure for Claiming Costs
Step I - Notice of Claims (Sub-Clause 53.1, CoC)
Notwithstanding any other provision of the Contract, if the Contractor intends to claim any
additional payment pursuant to any Clause of these Conditions or otherwise, he shall give
notice of his intention to the Engineer, with a copy to the Employer, within 28 days after the
event giving rise to the claim has first arisen.
Step II - Contemporary Records (Sub-Clause 53.2, CoC)
Upon the happening of the event referred to in Sub-Clause 53.1, CoC, the Contractor shall
keep such contemporary records as may reasonably be necessary to support any claim he may
subsequently wish to make. Without necessarily admitting the Employer's liability, the
Engineer shall, on receipt of a notice under Sub-Clause 53.1, CoC, inspect such contemporary
records and may instruct the Contractor to keep any further contemporary records as are
reasonable and may be material to the claim of which notice has been given. The Contractor
shall permit the Engineer to inspect all records kept pursuant to this Sub-Clause and shall
supply him with copies thereof as and when the Engineer so instructs.
Step III - Substantiation of Claims (Sub-Clause 53.3, CoC)
Within 28 days, or such other reasonable time as may be agreed by the Engineer, of giving
notice under Sub-Clause 53.1, CoC, the Contractor shall send to the Engineer an account
giving detailed particulars of the amount claimed and the grounds upon which the claim is
based. Where the event giving rise to the claim has a continuing effect, such account shall be
considered to be an interim account and the Contractor shall, at such intervals as the Engineer
may reasonably require, send further interim accounts giving the accumulated amount of the
claim and any further grounds upon which it is based. In cases where interim accounts are
sent to the Engineer, the Contractor shall send a final account within 28 days of the end of the
Guide Book Cost and Contracts
70 SECTION-II
effects resulting from the event. The Contractor shall, if required by the Engineer so to do,
copy to the Employer all accounts sent to the Engineer pursuant to this Sub-Clause.
Step IV - Failure to Comply (Sub-Clause 53.4, CoC)
If the Contractor fails to comply with any of the provisions of Sub-Clause 53.1, 53.2 & 53.3 in
respect of any claim which he seeks to make, his entitlement to payment in respect thereof
shall not exceed such amount as assessed by the Engineer or any arbitrator or arbitrators ap-
pointed pursuant to Sub-Clause 67.3.
Note: The Sub-Clause 53.4 has been deleted in its entirety under Particular Condition
of Contract (PCC) of PEC Bidding Documents.
Payment of Claims (Sub-Clause 60.1, 60.5, 60.6 & 60.8, CoC)
The Contractor shall be entitled to have included in any interim payment certified by the
Engineer pursuant to Clause 60 such amount in respect of any claim as the Engineer, after due
consultation with the Employer and the Contractor, may consider due to the Contractor
provided that the Contractor has supplied sufficient particulars to enable the Engineer to
determine the amount due. If such particulars are insufficient to substantiate the whole of the
claim, the Contractor shall be entitled to payment in respect of such part of the claim as such
particulars may substantiate to the satisfaction of the Engineer.
General Cost Claims
Prolongation
Acceleration
Disruption
Idling
Change in Cost (Escalation)
Subsequent Legislation
Prolongation Cost Claim
The prolongation costs are only paid for such extended periods which are granted on the basis
of delaying events whose risks have been assumed by the Employer expressly given in the
contract or for which the Employer is held liable to compensate under the governing law by
implication.
Acceleration Cost Claim
The contractor was slow as per Clause-14, Program, CoC, and
then he accelerate the pace of work under notice (Sub Clause-46.1, Rate of Progress). The
contractor gets no cost compensation.
The contractor accelerate the work pace at his own, he gets no
compensation other than reduced Liquidated Damages (LDs) for other section of work
(Sub Clause-47.2, Reduction of LDs) or the bonus (Sub Clause-47.3, Bonus for Early
Completion of Works)
As per requirement of the Employer if the contractor completes
the contract before the original or extended completion time then the contractor will be
compensated. (additional resources plus fixed cost i.e. overhead)
Guide Book Cost and Contracts
SECTION-II 71
Disruption Cost Claim
Sub Clause-6.3, Disruption of Progress and Sub Clause-6.4, Delay and Cost of
Delay of Drawings, allows cost and time compensation for disruption caused by non
availability of drawings or any instruction with out which the work could not be contin-
ued.
Sub Clause-12.2, Not Foreseeable Physical Obstructions or Conditions, if in
the opinion of the Engineer, the obstructions or conditions could not have been reasonably
foreseen by an experienced contractor, then after due consultation with the Employer and
the Contractor, determine the Delay and Cost of Delay.
Idling Cost Claim
There may be occasions where the contractor goes under:
1. Instructed suspension or,
2. Forced suspension or,
3. Self-suspension.
Owing to these three causes, the resources of the contractor deployed for execution of
contract go into an idling state. All additional costs connected with suspension are
compensated.
Change in Cost Claim (Escalation)
Owing to increase in the cost of construction inputs during execution of work w.r.t. the rates
and prices prevailed at the time of bidding, then pursuant to Sub Clause-70.1, Increase or
Decrease of Cost, the contractor is compensated for only the specified inputs as mentioned in
the Appendix-C to Bid.
Subsequent Legislation Cost Claim
Changes in existing or introduction of new State Statute, Ordinance, Law, Regulation or Bye-
Laws, would make the contractor entitle to the increased cost for the legislative items w.r.t.
the cost prevailed at the time of bidding, pursuant to Sub Clause-70.2, Subsequent Legislation
Principle of law
It is mentioned in Section-67 of Contract Act, 1872 that every promise must extend
reasonable facilities to the party obliged to perform so that his performance is completed
unhindered.
Consequence of prevention is compensation to the party provided under, Section-53 & 54 of
Contract Act, 1872, as under;
Liability of party preventing event on which the contract is to take effect (Section-53):
When a contract contains reciprocal promises, and one party to the contract prevents the other
from performing his promise, the contract becomes voidable at the option of the party so
prevented; and he is entitled to compensation from the other party for any loss which he may
sustain in consequence of the non-performance of the contract.
Illustration;
A and B contract that B shall execute certain work for A for a thousand rupees. B is
ready and willing to execute the work accordingly, but A prevents him from doing so.
The contract is voidable at the option of B; and, if he elects to rescind it, he is entitled
to recover from A compensation for any loss which he has incurred by its non-
performance.
Guide Book Cost and Contracts
72 SECTION-II
Effect of default as to that promise which should be first performed, in contract
consisting of reciprocal promises (Section-54):
When a contract consists of reciprocal promises, such that one of them cannot be performed,
or that its performance cannot be claimed till the other has been performed, and the promiser
of the promise last mentioned fails to perform it, such promiser cannot claim the performance
of the reciprocal promise, and must make compensation to the other party to the contract for
any loss which such other party may sustain by the non-performance of the contract.
Illustration;
(a) A hires B's ship to take in and convey from Karachi to the Mauritius a car got to be
provided by A, B receiving a certain freight for its conveyance. A does not provide
any cargo for the ship. A cannot claim the performance of B's promise, and must
make compensation to B for the loss which B sustains by the non-performance of
the contract.
(b) A contracts with B to execute certain builders' work for a fixed price, B. supplying
the scaffolding and timber necessary for the work, B refuses to furnish any scaf-
folding or timber, and the work cannot be executed. A need not execute the work,
and B is bound to make compensation to A for any loss Caused to him by the non-
performance of the contract.
(c) A contracts with B to deliver to him, at a specified price, certain merchandise or
board a ship which cannot arrive for a month, and B engages to pay for the mer-
chandise within a week from the date of the contract. B does not pay within a
week. A's promise to deliver need not be performed, and B must make compensa-
tion.
(d) A promises B to sell him one hundred bales of merchandise, to be delivered next
day, and B promises A to pay for them within a month. A does not deliver accord-
ing to his promise. B's promise to pay need not be performed, and A must make
compensation.
Guide Book Cost and Contracts
SECTION-II 73
Dispute Resolution in Construction Contracts
Grievances during Procurement Process
PPR-48, Redressal of grievances by the procuring agency;
o The procuring agency shall constitute a committee comprising of odd number of per-
sons, with proper powers and authorizations, to address the complaints of bidders that
may occur prior to the entry into force of the procurement contract.
o Any bidder feeling aggrieved by any act of the procuring agency after the submission
of his bid may lodge a written complaint concerning his grievances not later than fifteen
days after the announcement of the bid evaluation report.
o Any bidder not satisfied with the decision of the committee of the procuring agency
may lodge an appeal in the relevant court of jurisdiction.
INTRODUCTION TO CONSTRUCTION ARBITRATION
Typical Features of Construction Disputes (1)
* Technically complex, fact intensive, require technical experts as well
as lawyers.
* Often more than two parties, even in turnkey projects (involvement of
subcontractors, suppliers, lenders, consultants, other contractors etc).
* Often more than one relevant contract (subcontracts, supply contracts,
construction of other facilities on same project, off take contracts, operation and mainte-
nance etc).
* Parties of (some times many) different nationalities on the same job.
* Site may be in another administrative areas altogether.
Typical Features of Construction Disputes (2)
* Large sums in dispute, at least in absolute terms.
* Project usually of long duration, with disputes emerging throughout.
* English law often applies, or at least contracts often inspired by Eng-
lish law. PEC Bidding Documents consists of PEC bye laws.
* Use of standard form contracts (e.g. FIDIC contracts).
Issues that Causes Construction Disputes
* Alleged interference by or deficiencies of the Employer:
Lack of site possession
Late approvals or instructions
Changes in design/materials/specification
Non payment
* Alleged deficiencies of Contractor:
Contractors design omissions and deficiencies
Defective manufacture and construction
Delayed performance (various causes attributable to contractor)
Excessive cost, when contract price not fixed
Guide Book Cost and Contracts
74 SECTION-II
* Third party events:
Adverse site conditions
Adverse weather
Material escalation
Hostilities/strikes
Changes in law
Typical Construction Claims
Contractor usually claims one or more of the following:
Compensation for extra work performed
Compensation and/or schedule relief for acceleration, delay
and/or disruption
Payment and interest
Blocking draw of performance bond
Employer usually claims one or more of the following:
Damages (usually liquidated) for delay, or for poor perfor-
mance (plant not at specification)
Correction or compensation for defective work (under war-
ranties)
Draw on performance bond
Mechanism for Resolving Construction Disputes
PEC Binding Dispute Resolution Forms
Engineers Decision
Arbitration
Court Litigation
PEC Rules of Reconciliation and Arbitration Not
Notified
FIDIC and ICC have their own Dispute Board pro-
cedures
Dispute Resolution Process
The Engineers Decision (ED) pursuant to Sub Clause-67.1 marks the
opening of the dispute resolution mechanism provided in the contract. This Clause is the
stepping stone to eventual reference of dispute to arbitration. In case the Engineer gives a
decision acceptable to both the parties (Employer/Contractor) then the ED finally settles
the dispute at the initial stage.
No notice is required to be given when the Contractor intends to seek Engi-
neers Decision under Sub Clause-67.1
The matter in dispute/disagreement can be referred to the Engineer any
time. There is no express time limit for the same.
Guide Book Cost and Contracts
SECTION-II 75
Step-1 (Engineers Decision (ED))
The reference of dispute for ED is required in writing.
An oral request is not valid.
The reference has to clearly state that the decision is sought under Sub Clause-67.1,
CoC.
The Engineer upon receiving the request for ED, has 84 days to give his decision.
The time limit starts from the day the Engineer receives the reference.
The Engineer is required to notify his decision to both, the Contractor and the Em-
ployer.
The Decision given beyound 84 days is invalid.
The Notice of intention to commence arbitration on the matter in the dispute is to be
given within 70 days when:
Either the Engineer fails to give his Decision within 84 days.
Or the Engineer gives the Decision but any party (Employer/Contractor) is
dissatisfied with the ED.
The time limit starts from the day the parties in dispute receive the ED.
In case neither the Employer nor the Contractor serves upon the other party the re-
quired notice of intention to commence arbitration then upon the expiry of 70 days, the
ED becomes final and binding for both parties.
Step-2 (Amicable Settlement)
Pursuant to Sub Clause-67.2 the parties are encouraged to settle their dispute amicably
within 56 days.
The parties may shorten or extend this time period mutually.
If no mutual agreement, then they have to wait for 56 days even if no attempt is made
to settlement.
The time limit start from the date when one party receives the notice to commence
arbitration given by the party having dissatisfied with the ED.
Arbitration may commence any time after the expiry of 56 days, but not before unless
agreed by the parties.
Pursuant to Sub Clause-67.3, when the ED has not become final and binding under
Sub Clause-67.1, and amicable settlement has not been reached under Sub Clause-67.2,
the dispute shall be finally settled under the provisions of the Arbitration Act 1940.
Guide Book Cost and Contracts
76 SECTION-II
Pursuant to Sub Clause-67.4, the reference to arbitration is made without complying
with the requirements stated in Sub Clause-67.1 and Sub Clause-67.2.
Step-3 (Arbitration Act 1940)
Under an arbitration agreement, the reference shall be to a sole arbitrator.
If the reference is to an even number of arbitrators, the arbitrators shall appoint an
umpire not later than one month from the latest date of their respective appointments.
The arbitrators shall make their award within four months after entering on the refer-
ence.
The arbitrator(s) unanimously make their award.
The award is made rule of court.
If the arbitrators have not made an award or have delivered to any party to the arbitra-
tion agreement or to the umpire a notice in writing stating that they can not agree, or there
is a split award then the umpire shall forthwith enter on the reference in lieu of the arbitra-
tors.
The umpire shall make his award within two months of entering on the reference.
The award of the umpire shall be final and binding on the parties.
The award is then made rule of court.
Step-4 (The Court of Law)
If any of the party is not satisfied with the award given by the arbitrators/umpire, he
may file appeal in the court of law.
The case will then be decided in the court.
The decision of the court shall be final and binding.
The provisions of the Code of Civil Procedure, 1908, shall apply to all proceedings be-
fore the court, and to all appeals.
All the provisions of the Limitation Act, 1908 shall apply to arbitrations as they apply
to proceedings in the Court.
Note:
The Court may appoint one or several arbitrators.
The Court may modify or set aside the award of arbitrator(s) or umpire.
The Court may remove an arbitrator or umpire
Amicable settlement is open all the time.
Normally arbitration is initiated after completion of work.
Maximum time for the appointment of arbitrator(s) under Limitation Act,
1908 on reference to arbitration is one year.
If one party fails to appoint an arbitrator, either originally or by way of substi-
tution, for fifteen clear days after the service by the other party of a notice in writing
Guide Book Cost and Contracts
Given effect unless
Contractors Notice of
Dissatisfaction
14 days of receipt
Silver
Book
SECTION-II 77
to make the appointment, such other party having appointed his arbitrator before giv-
ing the notice, the party who has appointed an arbitrator may appoint that arbitrator to
act as sole arbitrator in the reference, and his award shall be binding on both parties as
if he had been appointed by consent.
FIDIC and its Dispute Resolution Provisions
In November 1992 FIDIC, introduced the procedure of Dispute Resolu-
tion in Clause 67 of its Red Book, 1987, through ED to Rules of Conciliation and Arbi-
tration of the International Chamber of Commerce (Arbitration Act 1940 used by PEC).
FIDIC introduced the concept of Dispute Board into its Orange Book
(Design & Build) contract in 1995.
In 1999, FIDIC revised its Forms of Contract:
FIDIC Dispute Resolution provision is set out in Clause 20 of the New Red
(Conditions of Contract for Construction for Building and Engineering
Works), Yellow (Conditions of Contract for Plant and Design-Build for Elec-
trical and Mechanical Plant and for Building and Engineering Works) and Sil-
ver (Conditions of Contract for EPC/Turnkey Projects) Books.
Approach used by FIDIC is the Dispute Adjudication Board (DAB) which is-
sues a decision.
The FIDIC DAB provisions apply whenever a FIDIC contract is used unless
parties delete the provision.
The FIDIC DAB decisions are immediately binding and parties are obliged to
comply with the decision pending other stages of the dispute resolution proce-
dure, e.g. revised by amicable settlement or arbitral award.
New Red (Construction Contract) and Yellow (Plant and Design-Build Con-
tract) Books provide the Engineer to act as adjudicator and DAB. Silver Book
(EPC Contract) and Gold Book (DBO) have no Engineer, so disputes here
handled by DAB.
FIDIC Clause 20 (Claims, Disputes and Arbitration) provides for a combi-
nation of a Dispute Adjudication Board (20.4), amicable settlement (20.5),
and ICC arbitration (20.6).
Dispute Adjudication Board
Rules set out in New Red and Yellow books
Rules apply to the resolution of a referred dispute only
They may offer decisions or advice & opinion in the matter
Formation:
One or three person in the Board
The members are Independent & Impartial
Each party nominates one member
Parties consult members and agree a chairman
List of potential members in tender
If no agreement;
FIDIC President will nominate
Guide Book Cost and Contracts
Given effect unless
Contractors Notice of
Dissatisfaction
14 days of receipt
Silver
Book
A Typical ICC Arbitration Procedure
78 SECTION-II
Due consultation with parties
Functions:
Become Familiar
Visit the site
Keep up to date
Encourage resolution of issues
When a dispute is referred:
Act Fairly & Impartially
Convene a hearing
Deliberate
Prepare a Decision
Avoid unnecessary delay or expense
Advantages of the DAB
Resolves disputes in 84 days
Lower costs than Arbitration or Litigation
Impartiality
Real time assessment
Improves standards
Provides clarity
Diffuses problems
Encourages competitiveness in tenders
FIDIC Procedure for Contractors Claims (1999)
Guide Book Cost and Contracts
28 day Notice of Claim to Engineer
42 day Fully
Detailed Claim
to Engineer
Final Claim 28 days after
end of effects
42 days after receipt of claim
Engineers Response
Sub Clause 20.1
Contractors
Claims
Sub Clause
3.5
Determinati
ons
28 day Notice of Claim to Employer
42 day Fully Detailed
Claim
to Employer
Final Claim 28 days after end of
effects
42 days after receipt of claim
Employers Response
Given effect unless
Contractors Notice of
Dissatisfaction
14 days of receipt
New Red/Yellow
Books
Silver
Book
Agreement/ Determination
given effect unless revised under Clause 20
Employer to Agree or
Determine
Employer to Agree or
Determine
A Typical ICC Arbitration Procedure
SECTION-II 79
International Arbitration
No institutions specialised in construction cases. Instead, the usual top international
arbitration institutions are recommended, such as:
International Chamber of Commerce (ICC)
London Court of International Arbitration (LCIA)
Singapore International Arbitration Centre (SIAC)
Hong Kong International Arbitration Centre (HKIAC)
China International Economic and Trade Arbitration Commission (CI-
ETAC)
Beijing Arbitration Commission (BAC)
International Centre for Settlement of Investment Disputes (ICSID)
(Note: In leading institutions arbitration rules are largely similar. For further details, visit:
Guide Book Cost and Contracts
A Typical ICC Arbitration Procedure
Application for
Interim Relief
Request for
Arbitration
Answer to
Request
and Filing of
Counter claims
Hearings
Post-Hearing
Submissions
Exchange of
Written
Submissions
Constitution of
Arbitral
Tribunal
Terms of
Reference
and Procedural
Timetable
Limited
Discovery
(Exchange of
Documents)
Final Award &
Costs
Typical duration: 15-24
months
Reference to Dispute Adjudication
Board (DAB)
(1 or 3 Member)
Sub Clause-20.5
Sub Clause-20.5
80 SECTION-II
www.iccwbo.org, www.lcia.org, www.siac.org.sg, www.hkiac.org, www.cietac.org,
www.bjac.org.cn/en & www.icsid.worldbank.org)
Guide Book Cost and Contracts
SECTION-II 81
Price Adjustment in Construction Contract
Increase or decrease in costs of goods and services is a common phenomena world over. In
order to cater rise or fall of costs, provisions of Price Adjustment in construction contracts are
practiced to have more realistic competitive bids and execution of contracts on equitable and
just basis.
Importance;
Bidders quote price on prevailing market rates.
Cost of basic construction materials fluctuate unpredictably in Pakistan.
Unlimited cost increase not foreseeable and cannot be built in competitive bidding
process.
Contractors can execute work only at reasonable costs.
Legally and logically contracts are not executable without an equitable mechanism ac-
ceptable to the parties.
Results of non-adjustments: Project delay, disputes, termination of contracts result-
ing more cost for the Employer.
Introduction;
Terms Escalation/De-Escalation, Rise/Fall and Increase / Decrease in cost.
Meaning Adjustment of Contract Price for increase or decrease of prices of ad-
justable materials / services.
It is compensation and not extra benefit to Contractor.
Adjusted on monthly IPCs/Running Bills during contract period.
Basic formula: Price Adjustment = Quantity x (current rate base rate).
FIDIC formula: . etc
Eo
En
d
Mo
Mn
c
Lo
Ln
b A pn + + + + =
If a price adjustment factor is applied to payments made in a currency other than the
currency of the source of the index for a particular indexed input, a correction factor
Zo/Zn will be applied to the respective component factor of pn for the formula of the
relevant currency. Zo is the number of units of currency of the country of the index,
equivalent to one unit of the currency of payment on the date of the base index, and
Zn is the corresponding number of such currency units on the date of the current in-
dex. However the correct procedure for price adjustment is to use an index relating to
the country of supply for a particular input and to make payment in the currency of
that country.
Provision in Contract Documents
Bidding Documents for Civil Works: Sub Clause - 70.1 (PEC & FIDIC -1987).
Bidding Documents for E&M Works: Sub Clause - 47.1 (PEC & FIDIC -1987).
Bidding Documents for Building and Engineering Works: Sub Clause - 13.8
(FIDIC -1999)
Bidding Documents for EPC Turnkey Projects: Sub Clause -13.8 (FIDIC
-1999)
Bidding Documents for Building and Engineering Works: Sub Clause - 13.8
(FIDIC-MDB 2005)
Guide Book Cost and Contracts
82 SECTION-II
Calculation of Price Adjustment using Formula;
Nonadjustable factor B = Adjustable factor
A + b + c + d + = 1
Engineers Estimate or Effective Contract Price = 1
Pn = A + B
Pn = A + {(Coef.)i x (Current/Base Price)i}
Pa = Pn x Po
Pa is Price adjusted amount.
Pn is Price Adjustment Factor.
Po is effective contract price/workdone amount.
A is constant, nonadjustable factor, representing the nonadjustable portion.
b, c, d, etc. are coefficients / weightings representing portion of each cost element.
Ln, Mn, En, etc. are the current cost indices of cost elements for month n
Lo, Mo, Eo, etc. are base cost indices corresponding to above cost elements.
Ln/Lo is known as Price Relative Factor or Cost Relative Factor.
The source of indices and the weightages/coefficients for use in the adjustment formula under
Sub Clause-70.1, CoC, shall be as follows:
Appendix C to Bid (PEC)
Cost
Element
Description Weightings Unit Base Rates Rs
Applicable
Index
A Fixed Portion 0.350 - - -
b Labour Day-hour FBS
c Cement Bag FBS
d Reinforcing Steel Ton FBS
e High Speed Diesel (HSD) Ltr. FBS
f Bricks 1000 No FBS
g Bitumen Kg FBS
h
Total 1.000
Notes on Appendix C (PEC)
Employers using this price adjustment provisions may add or delete any elements as
deemed appropriate to the project.
Indices are taken from FBS or Source of indices shall be those listed in Appendix-C as
approved by Engineer.
The base cost indices or prices shall be those applying 28 days prior to the latest day
for submission of bids.
Guide Book Cost and Contracts
. etc
Eo
En
d
Mo
Mn
c
Lo
Ln
b A pn + + + + =
SECTION-II 83
[The base cost indices or prices shall be for the month falling on the date 28 days
prior to the latest day for submission of bids. The unit of time shall be a calendar
month.]
Current indices or prices shall be those applying 28 days prior to the last day of the
billing period.
[The current cost indices or prices shall be for the month falling on the date
28 days prior to the latest day of the billing period or for the month/period of exe-
cution to which a particular monthly statement is related. The unit of time shall be
a calendar month.]
Any fluctuation in the indices or prices of materials other than those given above shall
not be subject to adjustment of the Contract Price.
Fixed portion shown here is for typical road project, Employer to determine the
weighting of Fixed Portion considering only those cost elements having cost impact of
five (5) percent or more on specific project.
Supporting Guidelines
If at any time, current indices are not available, provisional indices are determined by
the Engineer will be used subject to subsequent adjustments.
As the basis of Price adjustment, Contractor may submit the tabulation of Weightings
& Source of Indices different from AppendixC, subject to mutual agreement between
the parties.
Price adjustments admissible even for the sanctioned extended completion period.
If extension due to Contractor's fault, Price adjustments will be done using indices be-
fore or after the completion time, favorable to the Employer.
Determination of Weightings (Based on PEC Guidelines)
The Procuring agency at the time of preparation of bidding documents, works out the
Weightages/ Coefficients from the Rate Analysis of the related Engineers Estimate/ BoQ.
Each of the cost elements, having cost impact of five (05) percent or higher can be selected
for adjustment. Cost elements of HSD and Labour shall be included in the Price Adjustment
formula irrespective of their percentage determined for a particular project, if these are
applicable for that project.
In determining the weightages, the following procedure shall be adopted:
(a) Base Price alone of an element based on market rate shall be consid-
ered excluding cost of construction / installation, overheads and profit.
(b) Appropriate Rate Analysis of the Engineers Estimate shall be made to
determine costs of the basic elements.
(c) For elements having different characters, individual cost of such family
of the elements shall be determined and added to work out as a single element
cost. For example, in a particular project various types of steel such as sheet
steel, hydraulic structure steel and Grade-40 & Grade-60 steel are used. In
such a case, respective prices of all three types of steel are to be considered
and added up to come out with the single steel cost component. Similar case
may be for different types of cement used, etc.
(d) Each cost element determined as above, shall be divided by the total
amount of Engineers Estimate to determine various weightages.
(e) It is clarified that while computing Price Adjustment, base and current
prices of the representative elements have to be used in the same way as they
Guide Book Cost and Contracts
84 SECTION-II
are mentioned in the PEC bidding documents. For example Grade-40 half inch
dia Steel is the representative cost element for all types of steel; similarly un-
skilled labour is the representative cost element for all types of labour etc.
Weightage of fixed portion (Non-adjustable portion of the estimated cost of the
contract), A shall be determined as under:
(i) First the weightages of all the cost elements having value of 5 percent or more
(HSD and Labour to be included irrespective of their weightages) to be added
up to a level when the total is 65 percent or less. In that case the total is to be
subtracted from 100 percent to determine the weightage of the fixed
portion,A
(ii) In case total weightage of the cost elements including HSD and Labour
exceeds 65 percent, the element(s) having lowest weightage(s) other than HSD
and labour, shall be excluded in considering the adjustable costs elements.
(iii) Fixed portion shall never be less than 35 percent and the adjustable
portion shall never be more than 65 percent of the Engineers Estimate.
(iv) Sum of fixed portion, A and weightages a, b, c, d, .etc., of the ad-
justable portion shall always be one (01).
Example for determination of weightings
An Engineer's Estimate prepared during June, 2006 for the construction of a building
amounts to Rs 196,880,500. Thereafter in order to prepare Appendix-C of Bidding
Documents, particularly for the determination of weightages i.e. percentage of construction
inputs in the Engineer's Estimate worked out with the help of Rate Analysis in accordance
with above mention guidelines.
The South African Federation of Civil Engineering Contractors
The coefficients provided below are issued as a basic guideline only and are subject to
amendment, depending on the specific requirements and variations contained in differing
types of contracts.
No. Work Category Labour Plant Materials Fuel
Guide Book Cost and Contracts
SECTION-II 85
1 Bulk Earthworks 0.10 0.65 0.05 0.20
2 Earthworks (with culverts and drainage) 0.15 0.50 0.20 0.15
3
3.1
(a)
(b)
3.2
(a)
(b)
New Road Construction:
National Provincial Roads:
Including bitumen
Excluding bitumen
Urban Roads:
Including bitumen
Excluding bitumen
0.15
0.20
0.25
0.30
0.35
0.40
0.15
0.30
0.35
0.25
0.55
0.35
0.15
0.15
0.05
0.05
4
(a)
(b)
Township Roads and Services
Including bitumen
Excluding bitumen
0.20
0.21
0.25
0.27
0.45
0.42
0.10
0.10
5
(a)
(b)
Rehabilitation/Resurfacing Works
Including bitumen
Excluding bitumen
0.15
0.20
0.25
0.35
0.50
0.35
0.10
0.10
6
(a)
(b)
Routine Maintenance Works
Including bitumen
Excluding bitumen
0.45
0.48
0.30
0.37
0.15
0.05
0.10
0.10
7 Water and Sewer Reticulation 0.15 0.20 0.55 0.10
8 Concrete Works (reservoirs and other
general civil engineering works)
0.25
0.15
0.55
0.05
9 Concrete Works (major structures) 0.15 0.20 0.55 0.10
Note; Overhead and minor elements of construction input are included in above components.
Determination of Price Adjustment
Price Adjustment in term of 65 % Foreign and 35 % Local Component of the Contract
Price;
Foreign Portion (Rs) for IPC # 2, Amounting; Rs 26,862,316.00
Element Coefficient
Base
Indices
Current
Indices
Factor
(5/4)
Adj. Factor
(6x3)
(1) (2) (3) (4) (5) (6) (7)
a Fixed Portion 0.15 - - - 0.1500
b Labour - Exp. (E) 0.07 18.63 22.17 1.1900 0.0833
c Equipment 0.27 151.50 187.60 1.2383 0.3343
d Misc. 0.16 151.70 212.20 1.3988 0.2238
Sub Total 0.65 0.7914
Portion not Adj. (Local) 0.35 0.3500
Total 1.00 1.1414
IP
C Rs 26,862,316.00 30,661,934.52
Net Increase (Rs) 3,799,618.52
Local Portion (Rs) for IPC # 2 Amounting; Rs 26,862,316.00
Element Coefficient
Base
Indices
Current
Indices
Factor
(5/4)
Adj. Factor
(6x3)
(1) (2) (3) (4) (5) (6) (7)
a Fixed Portion 0.05 - - - 0.0500
Guide Book Cost and Contracts
86 SECTION-II
b Labour - Local (L) 0.06 2,500.00 6,000.00 2.4000 0.1440
c Fuel 0.07 134.26 422.36 3.1458 0.2202
d Cement 0.06 245.00 375.00 1.5306 0.0918
e Reinforcing Steel 0.06 18,600.00 61,500.00 3.3065 0.1984
f Misc. 0.05 106.74 192.08 1.7995 0.0900
Sub Total 0.35 0.7944
Portion not Adj. (Foreign) 0.65 0.6500
Total 1.00 1.4444
IP
C Rs 26,862,316.00 38,800,144.77
Net Increase (Rs) 11,937,828.77
Local + Foreign (Rs) 15,737,447.29
Change or adjustment of Weightings:
World Bank; Sub Clause-70.7
The weightings for each of the factors of cost given in the Appendix to Bid shall be
adjusted if, in the opinion of the Engineer, they have been rendered unreasonable, un-
balanced, or inapplicable as a result of varied or additional work already executed or
instructed under Clause 51 or for any other reason.
PEC; Sub Clause-70.1 (f)
The weightages for each of the factors of cost given in Appendix-C to Bid shall be ad-
justed if, in the opinion of the Engineer, they have been rendered unreasonable, unbal-
anced, or inapplicable as a result of varied or additional work executed or instructed
under Clause 51. Such adjustment(s) shall have to be agreed in the variation order.
Abrupt or sudden changes in price of materials and labours do not put any impact on
Weightings.
Note;
Non Adjustable Portion includes:
Minor Construction Inputs [less than 5% (PEC) / 3-5% (WB) of the
total estimated cost of work]
Contractors Overhead and profit.
If any of the specified material is not used for a certain period, then impact of increase
or decrease, relative cost indices should be a unit i.e. one (1).
If any of the specified material is stored at site by the Contractor, then for adjustment,
the current rate pertaining to that material would be taken for the month falling on the
date that material was purchased by the Contractor, and similarly a weighted average
rate shall be used for the material purchased once but used during different months.
Sample:
SOUTH SANGHAR DISPOSAL CHANNELS, CONTRACT NR. S15.AB8
Calculation of Mean Price
Guide Book Cost and Contracts
SECTION-II 87
Material Ordinary Portland Cement
Unit Metric Ton
Basic Price Rs.2600.00
Material Used Calculation of Mean Price
According to Quantity Invoice Delivery Delivered Schedule Unit Schedule Total
IPCs Nr. Date Quantity Price(Rs) Price(Rs)
(1) (2) (3) (4) (5) (6) (7)
IPC-3(June94) 2.040 235 09-05-94 3.000 2737.00 8211.00
IPC-4(July94) 2.270 301 07-07-94 5.000 3197.00 15985.00
IPC-5(Aug-Sep94) 2.350 6325 12-09-94 5.000 3197.00 15985.00
IPC-6(Oct94) 1.710 128 01-02-95 4.000 3151.00 12604.00
IPC-7(Nov94) 1.170 112 06-04-95 2.000 3151.00 6302.00
IPC-8(Dec94) 1.180 1436 08-05-95 3.000 3151.00 9453.00
IPC-9(Jan95) 1.580
IPC-10(Feb95) 3.030
IPC-11(Mar95) 1.850
IPC-12(Apr95) 2.190
IPC-13(May95) 0.130
IPC-14(Aug95) 0.060
IPC-15(Sep95) 1.800
IPC-16(Oct95) 0.380
IPC-17(Nov95) 0.000
TOTAL 21.740 22.000 68540.00
Mean = (7) /
(5) 3115.45
Example
Weighted Average Rate per Running Bill
IPC # Effective Period
Cement
Period Days
Rate/bag
per month
d x e
Ave. Rate
[(dxe)i/di]
a b c d e f g
1 05/11/2007 - 19/12/2007 Nov.,2007 25 215.00 5375.00
Dec.,2007 19 215.00 4085.00
Total 44 9460.00 215.00
2 20/12/2007 - 15/01/2008 Dec.,2007 13 215.00 2795.00
Jan.,2008 15 235.00 3525.00
Total 28 6320.00 225.71
Guide Book Cost and Contracts
SECTION-III 88
SECTION-III
Procurement of Goods
Introduction
The Bidding Documents for Procurement of Goods generally used, are based on
documents prepared by the World Bank 1997, 2001 and 2004, revised upto 2010.
These Bidding Documents for Procurement of Goods, assumes that no prequalifi-
cation has taken place before bidding.
Background for best practices
Purchasing process
Market/Procurement analysis
A. Planning of the purchase B. Chosing the right method for the
purchase
C. Drafting the Invitation to Bids D. Planning the award criteria
E. Sending procurement notice and / or
invitation to bids
F. Receipt of the bids
G. Qualification of the bidder. H. Evaluating the bids
I. Decision making J. Informing
K. Remedies L. Contract and/or order
M. Monitoring the contract N. Closing the contract
Formation of Bidding Documents for Procurement of Goods (WB Based)
Guide Book Cost and Contracts
SECTION-I1I 89
PART 1 Bidding Procedures
Section I. Instructions to Bidders (ITB)
Section II. Bidding Data Sheet (BDS)
Section III. Evaluation and Qualification Criteria
Section IV. Bidding Forms
Section V. Eligible Countries
PART 2 Supply Requirements
Section VI. Schedule of Requirements
PART 3 - Contract
Section VII. General Conditions of Contract (GCC)
Section VIII. Special Conditions of Contract (SCC)
Section IX. Contract Forms
Sample:
Invitation for Bids (IFB)
[ insert: name of Project ]
[ insert: IFB Title ]
[ insert: IFB Number ]
1. The [insert name of Purchaser] [has received/has arranged from its recourses] a
[loan/credit/found] toward the cost of [insert name of Project], and it intends to apply part
of the proceeds of this [loan/credit/found] to payments under the Contract for [insert
name/no. of Contract].
2. The [insert name of Implementing Agency] now invites sealed bids from eli-
gible and qualified bidders for [insert brief description of the Goods to be procured].
3. Interested eligible bidders may obtain further information from and inspect
the bidding documents during [insert office hours] at the office of [name of appropriate
purchasing unit] [mailing address of appropriate office for inquiry and issuance of bid-
ding documents and cable, telex, and/or facsimile numbers].
4. Qualifications requirements include: [insert a list of technical, financial, le-
gal and other requirements]. A margin of preference for certain goods manufactured do-
mestically [insert shall or shall not, as appropriate] be applied. Additional details are
provided in the Bidding Documents.
5. A complete set of Bidding Documents in [insert name of language] may be
purchased by interested bidders on the submission of a written Application to the above ad-
dress and upon payment of a non refundable fee [insert amount in local currency].
6. Bids must be delivered to the above address at or before [insert time and
date]. Late bids will be rejected. Bids will be opened in the presence of the bidders repre-
sentatives who choose to attend in.
All bids must be accompanied by a Bid Security of
[insert amount in local currency or minimum percentage of bid price].
7. The bidders are requested to give their best and final prices as no negotia-
tions are expected.
PART 1 BIDDING PROCEDURES
Section I. Instructions to Bidders (ITB)
This Section provides information to help Bidders prepare their bids.
Guide Book Cost and Contracts
90 SECTION-III
Information is also provided on the submission, opening, and evaluation of bids and
on the award of Contracts.
Section I contains provisions that are to be used without modification. However if it is
not Bank finance procurement, then certain clauses may be tailored/ changed to suit
the procuring agency.
Section I contains about 42 Clauses.
Sample
Section I. Instructions to Bidders (ITB)
A. General
1. Scope of Bid 1.1 The Procuring agency/Purchaser indicated in the Bidding
Data Sheet (BDS), issues these Bidding Documents for the
supply of Goods and Related Services incidental thereto as
specified in Section VI, Schedule of Requirements. The name
and identification number of this procurement are specified in
the BDS. The name, identification, and number of lots of are
provided in the BDS.
2. Source of
Funds
2.1 The Purchaser or Recipient specified in the BDS has applied
for or received financing (hereinafter called funds) from the
Government of Pakistan or the Financial Institution or has ar-
ranged from its own resources toward the cost of the project
named in the BDS. The Purchaser intends to apply a portion
of the funds to eligible payments under the contract for which
these Bidding Documents are issued.