TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD

PCC - 1 Issue No.: 4


Issue Date: 04 March2010

PARTCULAR CONDTONS OF PARTCULAR CONDTONS OF PARTCULAR CONDTONS OF PARTCULAR CONDTONS OF


CONTRACT CONTRACT CONTRACT CONTRACT




















1. The General Conditions of Contract shall be
amended in accordance with the provisions of
these Particular Conditions of Contract.

2. These Particular Conditions of Contract shall be
read and construed with the General Conditions of
Contract.

3. If there is any conflict or inconsistency between
the provisions of the General Conditions of
Contract and these Particular Conditions of
Contract, these Particular Conditions of Contract
shall prevail.
TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD





PCC - 2 Issue No.: 4
Issue Date: 04 March2010


Particular Conditions


1.


General Provisions
1.1
Definitions


Materials

1.1.15 Insert and shall include Free Issue Materials. at the end of the
paragraph.

Free Issue Item 1.1.20 Add the new definition:

Free Issue Materials means any material supplied by the Employer
free of charge to the Contractor to be incorporated into the Works.


3.

Employers Representatives
3.1
Authorised
Person

Insert (The authorised person may appoint his representatives for the Works
and shall notify to the Contractor), after end of sentence.


4.

The Contractor
4.1
General
Obligations

Insert (excluding Free Issue Materials), after . . . all supervision, labour,
Materials


4.2
Contractors
Representative
Insert and to act after . . . to receive instructions



4.4
Performance
Security
Add new paragraph:

This Bond shall be valid and shall be irrevocable and shall remain in force and
effect until six (6) months after the end of period for notifying defects as stated
in the Appendix

4.5
Safety
Procedures
Add new Sub-Clause 4.5:

The Contractor shall comply with all applicable safety regulations, Employers
instruction on safety matters and take care for the safety of all persons entitled
to be on the Site.

The Contractor shall provide any temporary works (including roadways,
footways, guards and fences) which may be necessary because of the
execution of the Works, for the use and protection of the public and of owners
and occupiers of adjacent land.


TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD





PCC - 3 Issue No.: 4
Issue Date: 04 March2010


4.6
Quality
Assurance
Add new Sub-Clause 4.6:

The Contractor shall establish a specific project Quality Plan and Inspection
and Test Plan to demonstrate compliance with requirement of the Contract.
The Employer shall be entitled to audit any aspect of the system of the
Contractors and his subcontractors Quality Plan and/or Inspection and Test
Plan.


4.7
Environmental
Protection
Add new Sub-Clause 4.7:

The Contractor shall take all reasonable steps to protect the environment (both
on and off the Site) and to limit damage and nuisance to people and property
resulting from pollution, noise and other results of his operations.


6.

Employers Liabilities


6.1
Employers
Liabilities

Delete item (e), (h) and (i).


7. Time of Completion

7.3
Extension of
Time
Add or any Force Majeure event. After the word Employers Liabilities
before the end of the sentence in Para 1, Line 3.



10.


Variation and Claims

10.2
Valuation of
Variations

Add The record shall be verified by the Employer and agreed by both Parties.
at the end of the sub-clause 10.2 e:


10.4
Right to Claim
Add except for the cost incurred from rectifying any loss or damage to
Contractors Equipment at the end of the 1
st
sentence.



11


Contract Price and Payment
11.2
Monthly
Statements
Replace sub-heading Monthly Statement with Statements and invoices

Replace monthly intervals with at the interval specified in the Appendix
in first para.

Replace each month with at the intervals specified in the Appendix in the
last para.


11.3
Interim Payment

Replace 28 . . . with 56 in the first para.


TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD TENAGA NASONAL BERHAD





PCC - 4 Issue No.: 4
Issue Date: 04 March2010


11.4
Payment of First
Half of Retention
Replace 14 with 28 and add and with submission of statement
and invoice. at the end of the sentence.


11.5
Payment of
Second Half of
Retention

Replace 14 days with 28 days with submission of statement and
invoice . . .


11.6
Final Payment
Replace 28 with 56 in the second para.



12


Default
12.3
Insolvency
Replace sub-heading with Insolvency and Bankruptcy

Insert or bankrupt after . . . is declared insolvent in the first sentence and or
bankruptcy after . . . Contractors insolvency in the second sentence.


12.4
Payment
upon
Termination

Replace 28 with 42 in the last para.



13

13.2


14


Risk and Responsibility

Replace 28 with 42 in the last para.


Insurance
14.1
Extent of
Cover

Add until taking over, relevant after the word maintain in Para 1, Line 1




Delete and the Contractors Equipment and insert and after ..Works,
Materials, in sub-para (a) of Para 1





Delete Para 1 sub para (c)


14.2
Arrangements

Delete held jointly by the parties and from Para 2, Line 2


14.4
Other Insurances

Add new Sub-Clause 14.4:

The Contractor shall effect and maintain all other relevant insurances in so
far as necessary to comply with any relevant impositions of Laws.