PRADEEPTHI ENVIRO ENGINEERS

OFFICE: Gollabattula Street, Yanam- 533464, Ph: 0891-2797377

WORKS: B-1, Block-B, Industrial Estate, Auto nagar, Visakhapatnam-530018 Cell No: 9246762309, Email: pees_india@yahoo.in

Ref: PEES/POR/014

Date: 05-04-2012

To M/S. SRI PYDIMAMBA WASTE OIL RECIVERY PLANT Peddapuram, E.G.Dt-AP Sir, Sub: - Effluent Treatment Plant (ETP) Reg.

We thank for your telephone call and further your visit regarding on Effluent Treatment Plant, for your waste oil processing plant at -Peddapuram. In this regard we are very much interested to undertake the work, for the same we here with submit our offer for your kind consideration.

SCOPE OF WORK Effluent Treatment Plant for 10 m3/day

The waste water is to be treated as per APPCB discharge standards. RESULT Sl.No. 1. 2. 3. 4. 5. pH TOTAL DISSOLVED SOLIDS SUSPENDED SOLIDS CHEMICAL OXYGEN DEMAND COD BIO-CHEMICAL OXYGEN DEMAND BOD (3 days incubation at 270C) 6. OIL & GREASE mg/l 20-30 02 PARAMETER UNIT -mg/l mg/l mg/l mg/l RAW 5.0-8.5 2000 - 2200 2500 - 2700 400-500 200-300 TREATED 7.0-7.5 < 1500 < 100 < 200 < 30

TREATMENT SCHEME: Primary Treatment Bar Screen Chamber Collection tank Oil and Grease Trap Flash Mixer Primary Clarifier

TERTIARY TREATMENT Sand Filter Carbon Filter

DESCRIPTION OF WORK & DIMENSIONS S.No 1. DESCRIPTION BAR SCREEN CHAMBER 01 Nos. PEES SCOPE PEES Complete supply, Errection & Commissioning PEES Errection & Commissioning PEES Errection & Commissioning COMPANY SCOPE ---

2.

OIL FAT AND FLOATING MATTER REMOVAL Syphon system arrangement Air line in equalization tank arrangement with grid

---

4.

PRIMARY CLARIFIER-LAMELLA MECHANISM SUPPLY- ONE NO Design details of Clarifier Size of lamella - 2.0 x 2.0mt Depth - 2.5 m Freeboard - 0.2 mt Clarifier details Fills of Trapezoidal 12 deg slant Bottom plate and inlet connections Outlet launder and outlet connections. Adaptor shaft, sludge arm and all wetted parts are of MS epoxy coated. Squeezing arms.

PEESComplete supply, errection and Commissioning

---

Scope of Work Submission of drawings for clarifier Assistance in civil construction work. Supply, erection and Commissioning of primary clarifier . 7.
SAND FILTER 1No. Size 0.6 dia X 1.2 m Height MS Structure ACTIVATED CARBON FILTER 1No. Size 0.6 dia X 1.2 m Height MS Structure Effluent treatment plant design, drawings.

8.

PEES Complete supply, errection and Commissioning PEESComplete supply, errection and Commissioning PEES SCOPE PEES SCOPE -----

9. 10. 11.

Civil work execution and Commissioning of ETP

PUMPS AND MOTORS No of pumps required 02 nos. 1 HP pumps - 02 nos Delivery - 6-8 m3/hr Make - Texmo /Kirloskar /Reputed any

PEESComplete supply, errection and Commissioning

---

12.

ELECTRICAL WORKS Suitable panel board Starters and MCP Separate energy meter Indicator lamp Cabling wire PLUMBING Pipeline units, Coupling, Bends and Suitable valve control Pipe line connection up to ETP end only CIVIL WORKS OPERATORS CHEMICALS,POWER ,WATER ETC. Training to operators

----

company scope

13.

PEESComplete supply, errection and Commissioning ------SVELC SCOPE

---

14. 15. 16. 17.

COMPANY SCOPE COMPANY SCOPE COMPANY SCOPE ---

COST ESTIMATION: S. No 01 02 03 Description of work Mechanical Equipment for ETP Transport,Errection and Commissioning Taxes Cost Rs. 3,50,000-00 Rs. 30,000-00 Extra

COMPANY SCOPE All Civil works Water, power to be supplied at free of cost Lodging & Boarding for two persons to be provided.

PAYMENT TERMS

30% advance along with the work order. 60% against proforma invoice. 10% at the time of errection

PERIOD OF JOB COMPLETION:

Job will be completed within two weeks from the date of release of work order along with advance payment (after completion of civil works).
MODE OF PAYMENT

Cash/DD payable at VISAKHAPATNAM. Assuring you of our best services at all times.

Thanking You Truly yours, For PRADEEPTHI ENVIRO ENGINEERS

(M. MURALI KRISHNA) Managing Partner