FABRICATION AND INSTALLATION OF PIPE SUPPORT

Document No. Project Name Contract No. Client

: : : :

EPIC CONTRACTOR
Rev Date Description Prepared by Reviewed by APPROVED BY

YANBU II POWER & WATER PROJECT


Contract PO No.: Doc No. : Rev No. :
FABRICATION AND INSTALLATION OF PIPE SUPPORT

Date of Issue:27/03/2012 Page 2 of 5

REVISION HISTORY

EPIC CONTRACTOR
Reviewed by Approved by Validity Period

SPDC

Rev

Date

Prepared by

Date

Reviewed by

Approved by

TABLE OF CONTENTS
1.0 2.0 3.0 4.0 5.0 SCOPE REFERENCE DOCUMENTS DEFINITION OF TERMS RESPONSIBILITIES PROCEDURE

YANBU II POWER & WATER PROJECT


Contract PO No.: Doc No. : Rev No. :
1.0 SCOPE This procedure describes the fabrication and installation of pipe support for piping systems constructed by HANWHA on YANBU II POWER & WATER PROJECT. 2.0 REFERENCE DOCUMENTS 1) Structural Steel 2) Station and manifold Piping and Tie-ins 3) Pipeline Construction 4) Welding 5) Concrete and cement finish work 6) Contractor safety 7) Pipe Support FABRICATION AND INSTALLATION OF PIPE SUPPORT

Date of Issue: 27/03/2012 Page 4 of 5

3.0 DEFINITION OF TERMS 1) Standard Construction Specifications 2) Design and Engineering Practices 3) Quality Assurance / Quality Control

4.0 RESPONSIBILITIES 1) The construction manager is responsible for the implementation of this procedure. 2) The QA/QC manager is responsible for the review of this procedure and ensures that all quality control aspects of equipment handling, storage, fabrication and installation of pipe supports are in accordance to the quality control procedure.

5.0 PROCEDURE

1) 2) 3) 4) 5) 6) 7) 8) 9)

GENERAL Material to be fabricated and installed will be withdrawn from the receiving area in accordance with material control procedure. Material storage and protection requirements shall be in accordance with the manufacturers recommendation. Stainless steel materials shall not be stored in contact with other materials, strict segregation of stainless steel materials and carbon steel material is required during all stages of storage. Nylon sling shall be used for handling stainless steel materials. The pipe supports shall be fabricated and installed according to pipe support design drawings All fabrication and installation of pipe support shall be carried out in an approved manner by well skilled workers. All tools and equipment shall be in good working condition. Piping shall be properly anchored and guided before pressure testing. Field-weld supports shall be set correctly in place and adjusted to the final position before welding. All grouting work shall be performed in accordance with the relevant procedure.

YANBU II POWER & WATER PROJECT


Contract PO No.: Doc No. : Rev No. :
10) 11) 12) 13) 14) 15) 16) FABRICATION AND INSTALLATION OF PIPE SUPPORT

Date of Issue: 27/03/2012 Page 5 of 5

17) 18) 19) 20) 21) 22)

Daily welding record for fabricated and installed (welded) supports shall be kept. All welding shall be carried out in accordance with approved welding procedure specification. Welding shall be carried out by a qualified pipe welder. Spring supports shall be installed with the spring locks in place. Locking plates or pins shall not be removed until hydrostatic test and insulation of the piping system has been completed. All dummy support end plates shall be welded on site. The location, level and dimensions of concrete supports or bases for piping, machinery and associated equipment shall be in accordance with Approved for construction drawings Where any supports or bases are required to be cast on the top of existing concrete floor slabs or foundations, the existing concrete must be broken out sufficiently to fully expose the original steel reinforcement so as to obtain a proper bond with the additional concrete and steel reinforcement. All support or bases must be tied to the structural concrete with vertical and horizontal reinforcement. During installation of plant and equipments, the pockets of the foundation bolts shall be filled with an approved high strength non-shrink grout (standard cements/sand grout). The form work material shall have no surface defects. The formwork shall be rigidly constructed, true to the shape, alignment and dimensions shown on the Approved working drawings The quantity, sizes, form, positions and spacing of all steel reinforcement bars shall be in accordance with the Approved drawings. All cutting and trimming of bars and wires shall be done cold with the use of manual or power operated cutters.