Documente Academic
Documente Profesional
Documente Cultură
Steam turbines are one of the major drivers of power generators in todays power plants. There are several types of turbines and a number of mechanical arrangements to obtain maximum efficiency and output. The auxiliaries however are very similar, performing equally important tasks in their systems.
Lube-oil System
1. Pumps
The lubricating oil system has three separate pumps which supply the bearings and hydraulic system with oil. Lube oil Jacking pump this is used when the turbine is being rotated by the turning gear. Emergency Lube oil Pump this cuts in if the turbine trips through loss of power. Lube oil Booster Pump this pump is used at start-up and ensures an adequate flow at slow speeds. It cuts out when the turbine reaches operation speed Main lube oil pump this pump draws the oil from a lube oil tank and supplies the turbine bearings and governor. This is normally a centrifugal pump driven by the turbine or generator shaft.
2. L.O. Filters
Some systems have duplex filters on the suction and discharge pipework of the pumps, but at a minimum a set on the discharge. These remove any debris picked up by the oil before the oil is fed to the bearings.
3. L.O. Coolers
The oil lubricates the bearings absorbing the heat from friction. This heat is dissipated by the coolers. These are usually tube coolers, water being the medium used to cool the oil.
4. L.O. Centrifuge
The centrifuge is usually positioned above the lube oil tank and runs continually whilst the turbine is operating, only coming off line for cleaning. It draws the lube oil from the lube oil tank removing any water and particles by centrifugal force before discharging the clean oil back to the tank.
5. Turbine Governor
As the loads on the generator vary requiring more or less steam to the turbine, the governor responds by controlling the speed of the turbine. The governor is hydraulically operated by lube oil supplied by the main pump.
7. Air Ejector
The air ejectors are used to create the initial vacuum in the condenser and maintain a vacuum of 28-29"Hg for optimum steam evaporation. The ejectors draw the air out of the condenser by passing high pressure steam through a vortex piping arrangement thus causing the vacuum.
8. Condensate Pump
This pump draws the water from the bottom of the condenser or hotwell and pumps it up to the deaerator.
9. Tray Deaerator
This is a pressure vessel with a horizontal and vertical section somewhat like a comic strip submarine shape. It effectively removes the air and oxygen from the feed water (condensate) which would otherwise damage the inside of the boiler tubes by corrosion. There are several types of deaerators; we will look at the tray type which is a vessel having a horizontal section with a vertical dome. The bottom horizontal section is used to collect and store the deaerated water; the vertical section has perforated trays set at intervals along its upper length. The condensate enters at the top of the vertical section cascading down through the trays, meeting steam injected from the sides and gathers at the bottom section where it is heated by steam coils or sprays. The air is vented from the very top of the deaerater vertical domed section.
*************************************************************************************************** ***************************************************************************************************
producing nearly 400 tons per hour of steam for power generation and utility purposes, firing coal and biomass with superheated steam at a pressure of 140 bar and temperature of 540C. A basic understanding of a boiler is required to understand what went wrong.
Furnace
The furnace of a modern boiler is made of welded tubes called membrane panels. The carbon steel tubes of diameter 60.3 mm welded at a pitch of 75 mm forms the boiler furnace with a height of 40 meters, width of 12 meters, and depth of 8 meters. The heat transfer area was around 1700 square meters. The heat in the furnace transfers to the water in these tubes to produce steam. The furnace is at temperatures in the range of 800C to 1000 C. The water flowing through the tubes keeps the tube metal temperatures well below the deformation temperatures. If there is no water flow in these tubes, the tubes will overheat and fail. This is true for any vessel that boils water. Even in your house, if you heat a pot or a pan without water it will twist out of shape.
Circulation
How does water circulate in these tubes? Water flows into these tubes from the boiler drum located at the top of the furnace through large pipes called "down comers." Steam starts forming in these tubes as it absorbs the heat from the furnace. The steam water mixture is at a lower density than the water in the down comers. Consider this like a U tube having the down comer filled with denser fluid (water) and the water wall tubes with lighter fluid (a water and steam mix). Both legs connect to the top drum. This density difference between the two legs causes circulation in these tubes.
Blowdown
The steam and water mixture from the water walls enter the drum, the steam separates, and the water recirculates back. The chemicals in the water do not evaporate and remain in the water. Continuous circulation of the water increases the concentration of the chemical content. Continuous removal of a part of the water from the bottom of the drum by a process called "blowdown" controls the concentration level.
Drains
The water wall membrane panels connect to headers at the top and bottom. The down comers connect to the bottom headers distributing the water evenly to the tubes. The top headers connect to the drum through riser tubes that carry the water steam mixture to the drum. The bottom headers have drain pipes with valves. These manual operation valves are only for use during the initial operation for flushing and cleaning the headers or for filling or removing the water from the boiler.
The Incident
The incident occurred during the final stages of commissioning. The unit was operating at near full load at the maximum operating pressure. Because of higher than allowable concentration of chemicals in the drum, the commissioning engineer decided to use the water wall drains for blowdown for a short time. Since these were manual valves operating under high pressure differential, the quick open-close operation was not quick enough. How long the valve was in open condition is unknown. This opening of the drains at the bottom headers had the effect of breaking the U tube effect and killing or reducing the flow of water through the tubes. This resulted in higher than acceptable metal temperatures in the water wall tubes. A few tubes failed, and the failure led to a unit outage. In the ensuing inspection, the extent of the damage was visible. The entire water wall on the front and sides of the furnace for almost the entire height was distorted into a wavy pattern.
Repair
Since the plant was in an electrically islanded facility, the power and steam was necessary to keep the plant production levels. The boiler was back in operation after replacement of the burst tubes- at a lower load and pressure with the waterwall distortion. Because this was a CFBC boiler, the sand and ash circulating in the furnace required quick replacement of these wavy tubes before any failures due to erosion took place. The boiler operated with this condition for almost six months until the replacement tubes were available at site. It took thirty days to replace the walls and another fifteen days to put the unit back into service.
Conclusion
One should know the design basics and do some critical thinking before attempting to do something that is not normally done. ***************************************************************************************************
We never know the worth of water 'til the well is dry. Thomas Fuller
Population pressures, climate changes and deforestation are driving mans most wanted resource to scarcity. Let us explore one more way to augment this resource. When you burn fossil fuels or hydrocarbon fuels, the exothermic combustion reaction of Hydrogen in the fuel and Oxygen in the air produces water. This water goes out as vapour along with the flue gas. In coal firing, moisture in the coal augments the water quantity. The quantity of water produced is much more than the steam cycle make-up quantity in fossil fuel power plants. If one can economically capture this water and use it for steam cycle make up and other utility applications in the power plant, it can greatly reduce the pressure on regional water balances. This will be a boon for low rainfall regions and desert economies.
Additional cooling water, parasitic power, and capital investment are the main economic considerations. Removal of acidic constituents in flue gas like SO2 and NOx condensing at the 120 C range necessitates a two stage recovery. The first stage acidic condensate is sent to waste treatment. The heat exchangers are to be from acidic corrosion resistant materials.
Use a desiccant to absorb the water. Another method is to use a desiccant to absorb the water. Flue gas passes through a liquid spray in an absorber tower. The desiccant absorbs the water. Flashing releases the water and regenerates the desiccant. Cooling the vapors produces water. Cost of the desiccant, additional cooling water, parasitic power, and capital investment are the main economic considerations.
Use nano technology. This is the most promising method for flue gas water capture. Nano membrane tubes that allow permeation of only H2O molecules is the key. This is almost like a solid state system. This does not put undue pressure on auxiliary systems and can directly deliver water that is pure without any further processing. The nano membrane tubes are still in the development stage. Like the reverse osmosis membrane technology that is very popular today, higher production volumes will bring down the cost and make water recovery a reality.
As technology develops, water recovery from flue gas will be an integral part of the thermal power plant cycle, making it more environmentally friendly. *************************************************************************************************** ***************************************************************************************************
Input parameters
The basic input parameters to the recovery boiler are: Black liquor quality which includes concentration (% dry solids), temperature, Higher Heating Value, composition, % organic to inorganic ratio, and other physical properties The feed water temperature and feed water chemical quality The combustion air temperature which plays a major role in bed stabilization
Black liquor
The important properties include liquor composition, total dissolved solids, ultimate chemical composition, specific gravity and density, viscosity, specific heat, thermal conductivity, boiling point, surface tension, calorific value, latent heat of vaporization and solubility characteristics. Other properties that are mostly qualitative in nature, and not genera,l and very often used for comparison purposes are precipitation point, swelling volume ratio, foam index, etc. Black liquor is distinctly alkaline (pH varies from 10.5 to 13.5), but not caustic owing to the fact that a large part of the alkali is present in form of neutral compounds. The lignin has intense black colour shading to reddish brown on dilution and retains a dark straw to yellow colour even when diluted to 0.04% with water. It is foamy at low concentrations. Black liquor from the sulfate process is generally foamier than that from the soda process. The foaming increases with an increase in resin content of wood used for pulping. The amount of total solids in black liquor depends on the quantity of alkali charged to the digester and the yield of pulp. Under average conditions, black liquor going to evaporators will contain 14-18% solids for wood and bamboo. In general, the inorganic compounds in black liquor tend to decrease specific heat and thermal conductivity, increase density, specific gravity, viscosity, boiling point elevation, and have practically no effect on surface tension. The organic constituents of black liquor tend to decrease specific heat, thermal conductivity, and surface tension, and increase density and viscosity values. The data also shows that there are considerable differences among values for the different liquors attributed to the diversity of organic constituents in black liquors caused by the variation in pulping species, pulping conditions, and pulp yields. The black liquor obtained from agricultural residues, wheat straw, rice straw, and bagasse, etc. are characteristically different.
Black liquor generally contains 50%-70% organics and 30%-50% inorganics. It also contains minor amounts of impurities such as lime, iron-oxides, sodium chloride, and alumina. High silica content is a major obstacle in any recovery process. The concentration of silica is particularly high in rice and wheat straw black liquors. The presence of silica leads to problems related to scaling, clarification, and precipitation. The non-wood fiber black liquors have a high percentage of silica: 4 - 6% (even more) in case of straw and 1.% in case of bagassee. Silica enters both as intrinsic and external silica with raw material and cooking liquors. The magnitude of silica for different liquors is: rice straw 3 - 16%, wheat straw 3 - 6%, bamboo 2 - 5%, bagasse 1 - 3%, and eucalyptus 0.1 - 0.8%. *************************************************************************************************** ***************************************************************************************************
Pre-commissioning cleaning
During manufacturing of seamless steel tubes, a quantity of mill scales are bound to be formed, and some of these can remain inside. During fabrication and erection of the pressure parts, some amount of oil and grease can also get into the tube surface apart from the weld slag and other materials. Taking all of these into consideration, the precommissioning cleaning has three major steps. Alkali boil out - which is for removing the oil and grease from the internal surface. Acid cleaning - for removing the mill scales in the internal surface. Both acid cleaning and alkali boil-out are done for all water-touched surfaces. Steam blowing - In the case of super heaters, reheaters, and steam pipes, they are cleaned by steam blowing.
Alkali boil-out
This operation in boilers is taken up after hydraulic testing of the boiler is completed and the oil burners are commissioned. Alkaline flushing is carried out before the boiler is taken for alkali boil out. It is a practice to mechanically remove the oil and grease wherever possible. The drum internals are installed before start of alkali boil out. Normally sodium carbonate and sodium phosphate in equal quantity along with a detergent to about 0.05 to 0.1% by volume are used for alkali boil out.
10
After the boil out solution is added, the drum level is checked though a gauge glass and confirmed before firing the boiler. The boiler is brought to 20 kg/cm square in about 8 hours time keeping in mind the rate of pressure raise and temperature raise allowed for cold startup. The drum level is maintained at normal level during this operation. After about four hours at pressure, the fire is shut down and the boiler is allowed to cool. This ensures the sludge settle down and the boiler blow down is carried out using the bottom drain. Care should be taken to maintain the drum water level with in the visible range of gauge glass. This operation is done for four times to a total of about 16 hours. Solution samples are taken at regular intervals, and if the original concentration drops to half or below, chemicals are added to bring back the concentration. The boiler is then drained after the drum metal temperature is below 90 degree C. The boiler is then rinsed with clear rinse water and flushed.
Acid cleaning
Many methods are used by different boiler makers to clean the mill scale and rust inside the tube surface. It is very important that this operation is carried out by an experienced and reliable agency. The methods used are circulating acid method and soaking method. In the case of the circulating method, external acid cleaning pumps are used to keep the acid in circulation. However in the case of soaking method the acid is kept stationary for a specified time. Many combinations of acids are used for this purpose. The most popular acid is 5% hydrochloric acid with inhibitors that are used to inhibit the action of acid on the cleaned surface of the tube. The super heater tubes should be plugged and water filled and maintained under positive pressure so that the acid vapors do not enter the tube surface. The boiler is drained under nitrogen at a positive pressure; this is needed to protect the internal virgin surface. The sludge resulting from mill scales and rust will have to be flushed from the bottom headers. The boiler then goes though a passivation operation to ensure a protective layer formation inside the tube surface.
Steam blowing
Steam blowing is used to clean the super heater coils and the steam pipes like main steam and reheater pipes. There are two methods used for steam blowing: continuous blowing and intermittent blowing. In both cases, the idea is to create a disturbance on the surface of the tube or pipe well above that is possible during the peak load operation of the boiler. It is seen that at a pressure of around 40 kg/cm squared, the internal surface of the super heater and steam pipes are subjected to such a disturbance that any loosely adhering material is dislodged when the steam is allowed to blow out to the atmosphere. The completion of steam blowing is declared if the target plate of turbine blade material kept at the predefined point is free from any indentation or is within allowed limits. To complete the steam blowing in super heater, reheater, steam pipes, etc, steam blowing is done in more than one stage.
Post-operational cleaning
During operation boilers accumulate deposits inside the tube surface depending upon the quality of water chemistry maintained. Once the boilers have operated for about five years then it is a good practice to take tube samples from the high heat flux region and evaluate them for internal deposit. The samples are taken from all the four walls of the boiler furnace walls and tested for the amount of deposit and the chemistry of deposit. If the deposit quantity is above 40 mg/cm squared, then the tube is termed dirty and acid cleaning is recommended. The type of acid to be used for cleaning will depend upon the chemistry and adherence of the deposits to the tube surface. If the deposit contains copper from the pre-boiler system, then this has to be first removed. The other ingredients of the deposit are removed subsequently. Hence the post operational cleaning can have a few stages of acid cleaning. To decide this, tube samples taken are subjected to a cleaning test in the lab using the actual acid, temperature, time and stages planned at the site. Based on the results of the cleaning in the lab and result there achieved, the final recommendation is given to the boiler owner. *************************************************************************************************** ***************************************************************************************************
11
History
The principle of electromagnetic induction is the basis of the generation of electricity. Discovered in 1830 by Michael Faraday, this later led to the development of the dynamo by Pixie. This started the generation of electricity by converting mechanical energy from steam turbines and hydro turbines. Be it the generation of a few watts of electricity or millions of watts (mega watts) of electricity, the basic principle remains the same.
When the copper conductor moves, the conductor cuts the magnetic field. This produces an emf (electromotive force) or voltage, which sends an electric current through the copper conductor. Mechanical energy moves the coil converting it to electrical energy.
All generators use this basic principle. Only the primary energy source and prime mover is different. The prime mover can be a steam turbine, a gas turbine, a wind turbine, or a hydro turbine. One very important factor about electric generators is their synchronised operation.
12
All the power plant generators connect to the national or the regional transmission grid. The domestic, public, or industrial users get the electricity from this grid. This means all these generators should produce electric power that has the same characteristics.
Three characteristics
The three important characteristics are Frequency: The power what we get is an alternating current with 50 Hz, which very simply means the voltage and the directional flow of the electric current changes 50 times a second. In the US, Japan, and some other countries the frequency is 60 Hz. Even though this is something we cannot see or feel this is a very important in the design of and operation of electric generators and appliances. Voltage: this is the main electromotive force that drives the electric current. Large generators produce electricity at 20,000 volts, smaller generators output at 400 volts or 6000 volts. These voltages are "stepped up or down" as required for transmission and distribution to the user. Transmission of electricity over large distances takes place at very high voltages in the order of 150,000 to 400,000 volts or more. A domestic user needs electricity at 230 volts (120 volts in US). Even though the different types of generators produce voltages at certain standard levels, at the connection point to grid they all have to have the same equivalent voltage. Phase: Large electric power generators produce 3-phase electric power. Very simply put this means there are three different circuits each generating power at the same voltage and frequency. The only difference is the highs and lows in each circuit takes place at different times in each of the 50 Hz cycle. The advantage is the electric current through each conductor is one third of that of a single phase making it very cost effective in transmission and application. In addition, it is easier to produce a magnetic field required to run an electric motor. Household appliances work only on a single phase, but almost all of industrial application at higher loads use three phase.
While connecting a generator to the grid it is very important that these three characteristics match with that of the grid to which it is connected. If not properly done this can disastrously damage the generator. The process of connection is known as synchronisation. *************************************************************************************************** ***************************************************************************************************
13
D1 = Tube ID before rolling when the tube OD just touches the drum hole. This is achieved after light rolling and is called touch rolling; not much torque will be required for this. Once the tube OD touches the drum hole ID, the expander torque will increase indicating the tube has touched the drum hole ID. D2 = Tube ID after rolling T1 = Tube wall thickness before rolling. Note: Even at touch roll point the thickness of the tube is the same as that before starting touch expansion.
Attending to the bank tube failure mainly depends on the type of failure and the intensity of the failure. In case of expanded joint leakage resulting in puncture of the tube, generally it is the practice to plug both ends of the bank tube in top and bottom drum. This is mainly due to the reason many a times it will not be possible to reach this tube location without removing large number of tubes. Plugging tubes should not be adopted if locally there are many tubes to be plugged. This can cause problem in other tubes nearby. Plugging is adapted to other type of failures when approach is not there without removing many bank tubes. No spool piece welding is to be done on bank tubes as this can cause failure in the expanded joint. When the failure reason is established as low expansion carried out, then re-expansion has to be done in all the tubes. It is always better to restrict the thinning of the tube thickness to a maximum of 15 to 18%. Above this you will see that the tube material start flaking and lead to brittle failures. Seal welding of bank tubes is permitted after expansion. All precautions are to be taken during welding not to deviate from the welding procedure as any welding on drum has to be done with the utmost care. It is required to lightly re-roll the seal welded tubes and do not flare the tube end.
14
For enlargement/ovality in the holes, the normal tolerance limit for acceptance is (d+0.032 ) + 0 / 0.015 ; where d is the outside diameter of the bank tube If due to steam or water erosion the hole size is more than the limit, then weld build up has to be carried out to get the required size with suitable preheating and post heating. After getting the required hole size, the insertion and subsequent expansion of the bank tubes have to be carried out in proper sequence If seal welding is carried out with suitable electrode and with required preheating. Do not weld the bank tube directly to the drum without achieving required expansion on the bank tubes, and no strength weld is allowed in this area.
Related Reading
Boiler tube failures are inevitable. There are twenty-two primary reasons for tube failures in a boiler. It is true that being forewarned is being forearmed. Knowledge and good operating and maintenance practice reduce tube failures. As carbon emission is a major concern today, more super critical pressure units are bound to be preferred due to the increase in plant cycle efficiency. This will make once through type boilers take over from drum type boilers . *************************************************************************************************** ***************************************************************************************************
15
Before taking up wall blower optimization, the following will have to be ensured. All wall blowers are set to the right steam pressure recommended by the designer Check the alignment of the wall blower with respect to the furnace walls Ensure at least 50 degree centigrade of super heat in the steam being used. This is to prevent damage of the furnace walls due to wet team impingement. All wall blowers are operational It will be of great help if the boiler furnace walls are photographed just after a planned shutdown. Before shutting down the boiler, do not wall blow the furnace for one full sequence. This will ensure deposit collection on the walls between the adopted frequency. While shutting down the boiler ensure minimal thermal shock, by slowly lowering the load. This will ensure deposits stay on the walls. Take the photograph from a convenient man hole. But take all safety precautions as anytime the deposit can fall down due to cooling or thermal gradient.
There are many methods used for optimization of wall blower operation, like the manual method, heat flux measurement method, and the automated method. The manual method is discussed as this will bring out the philosophy involved in optimizing wall blower operation.
The change in SH spray without change in other parameters indicates that the furnace deposits are increasing. If the superheater spray increases above a particular level (to be determined for each boiler) operate wall blowers. These are two basic things to adhere to while optimising wall blowers.
The procedure for wall blower operation can be evolved after the study and data analysis for the most effective way of wall blowing.
16
The use of heat flux meter by embedding thermopiles at appropriate location in the furnace walls to understand whether the tube in the region is clean or with deposition the operation of the wall blower requirement can be decided. In the case of fully automated intelligent wall blower system, the need to wall blow each blower is understood from the effective heat flux falling on the tubes. Designers use different methods to establish this. *************************************************************************************************** ***************************************************************************************************
17
The presence of trace elements in coal combustion has also received increased attention throughout the world during the last few years, with elements such as mercury of particular concern. One way to reduce trace element emissions is cleaning the coal prior to combustion. The use of cleaner coals those with lower ash and sulfur content can have the added advantage of substantially reducing operating costs. Again, however, some effects may be detrimental (ash deposition may be exacerbated, and the effects on corrosion and precipitator performance are uncertain), which makes testing vital. It has been found from field data that even if the blended coal closely resembles the design coal for the boiler, the blend need not perform the same way. This is mainly due to the transformation of inorganic particles during combustion and the way in which the organics are dispersed in coal. A limitation to blending coals is the compatibility of the coals themselves, and problems are more likely when blending petrographically different coals or coals with different ash chemistry. Non-additive properties make blend evaluation for power generation inherently complex. More work is required on understanding how the inorganic components of coals in the blend interact and how it affects ash behavior including its emissivity, reflectivity, and thermal conductivity. Blending decisions should be based on the knowledge of the specific behavior of a given pair of coals, rather than an assumption of linear variation of properties with blend traction. The ever more stringent constraints placed on coalfired power stations worldwide and the continuing development of new technologies means that the issue of fuel quality improvement will remain a primary factor. *************************************************************************************************** ***************************************************************************************************
18
surface in boiler is kept around 150 degrees centigrade, ranging from 120 to 155. It is very important that the metal temperature of the tubes is always kept above the condensation temperature. It may be noted that the metal temperature of the tubes is governed by the medium temperature of the fluid inside the tubes. This makes it necessary to preheat water to at least 150 degrees centigrade before it enters the economizer surface. In the case of an air pre-heater, two methods are used to increase the metal temperature. One is an air bypass for air pre-heater, and the second is using a steam coil air pre-heater to increase the air temperature entering the air pre-heater. The amount of SO3 produced in boiler flue gas increases with an increase of excess air, gas temperature, residence time available, the amount of catalysts like vanadium pentoxide, nickel, ferric oxide, etc., and the sulphur level in fuel. The flue gas dew point temperature increases steeply from 90 degree centigrade to 135 degrees centigrade with sulphur percentage increasing up to 1%. A further increase in sulphur percentage in fuel gradually increases the dew point temperature from 135 degree centigrade to 165 degrees centigrade at 3.5% sulphur in fuel.
Going in for low sulphur fuel sometimes become economically unviable for the process for which the steam generators are used. Today many low excess air designs are available in the market. These burners adopt many ways to reduced excess air requirement without affecting the unburnts in the flue gas after combustion. Fuel oil additives like simple magnesium oxides are used to contain cold end corrosion due to sulphur. The magnesium oxide is injected in to the furnace or mixed with fuel which combines with sulphur oxides to form magnesium sulphate. In fluidized bed combustors, lime addition is a simple method used to reduce sulphur corrosion. The post-combustion technologies adopted are: Designing with higher exit gas temperature Air bypass across air pre-heater Ammonia injection Flue gas desulphurization (FGD)
Designing boilers with higher exit gas temperature reduces the boiler efficiency. As a rule of thumb approximately every 20 degree centigrade increase of flue gas temperature at boiler outlet reduces the efficiency by 1%. Hence this is not a preferred method in the present days. Air pre-heater bypass is for mainly for startup purposes until the metal temperature can be maintained above condensation temperature even when the cold air enters. Some designers use steam coil air pre-heater for full operation of the boiler. Ammonia injection was a method adopted by a few designers in certain process plant boilers burning high sulphur oil due to the availability of ammonia. Ammonia is injected in the economizer region where the temperature of flue gas is below the ammonia dissociation temperature and sufficient time is available for the chemical reaction. Ammonia combines with sulphur trioxide to form ammonium sulphate. The rate of ammonia injection will depend upon the SO3 concentration. The problem with this method is it produces a high volume of loose deposits of
19
ammonium sulphate, which increases the pressure drop in the flue gas path. Removal of these deposits is done by water washing of the air pre-heater online. Flue gas desulphurization is a very common method adopted in the present day. Here the flue gas with acid vapors is scrubbed to remove it as a byproduct. Most of the FGD processes use alkali to scrub the flue gas. Many designers of FGD adopt the limestone gypsum process. This process has gained acceptance due to the saleable gypsum byproduct. Sea water availability makes it possible to use it as an absorbent of sulphur oxides in acid form. There is another process called the Wellman-Lord Process, which is a regenerative process that uses aqueous sodium sulphite solution for scrubbing flue gas. The saleable byproduct, depending on the plants design, could be elemental sulphur, sulphuric acid, or liquid SO2. There are many working plants using this technology in Japan, USA, and Germany. The Sodium Bicarbonate Injection Process is a direct injection method adapted to de-sulphur the flue gas. Here the sodium bicarbonate is injected in the duct after the air pre-heater and before the dust removal system like an electrostatic precipitator or bag filters. *************************************************************************************************** ***************************************************************************************************
The petrographic composition affects the ignition process, combustion, and the efficiency of combustion. Maceral types and reactivity need not have simple relations, all inertinites are not inert and not all vitrinites are reactive. The reflectance values of the maceral groups and the association of the different macerals, determined as micro lithotypes also need to be taken into account. Mineral matter also affect the type of char formed, and the situation gets further complicated by different char characterization. Pulverised fuel combustion is used widely in power plants for the generation of electricity. Selection and testing of coals is an important factor for the efficient operation of boilers, and many different tests are carried out for this purpose. Coal petrography has gained importance in order to understand how combustion behaves from the fuel side. Changes occurring during pyrolysis determine the morphology of the char and the char types present affect the overall combustion efficiency. The type of char formed can depend on the macerals present, the rank of the coal, the particle size, and the temperature of char formation. The main influence on char formation is associated with the organic part of the coal. The presence of certain types of minerals can affect the type of char formed. Reactivity can also be influenced by mineral matter. Vital properties such as flame stability and burnout efficiency can be affected by the presence or absence of certain minerals. Even though it is evident that mineral matter adversely affects complete combustion, the total removal of mineral matter is impractical and is also undesirable as regards the requirements of modern burners. These inorganic compounds can be classified into four groups according to their origin: Inorganic matter from original plants Inorganic - organic complex minerals formed due to inorganic and organic interaction during the first stage of coalification process. Minerals introduced by water or wind into the coal deposits as they were forming. Minerals deposited, during the second phase of coalification process after consolidation of the coal, by ground water solutions in cracks, fissures, or cavities by alteration of primary minerals.
Many variables affect complete combustion including temperature, oxygen level, residence time, and char morphology (mainly structure, porosity, density, and optical texture). Some workers clearly state that vitrinite chars are more reactive than inertinite chars. Vitrinite char has been estimated to burn two to four times as fast as inertinite char. Some semifusinite has been found to ignite before vitrinite and burn faster. The rank of a coal can be expressed by the reflectance of the vitrinite, which is related to C H and C/O ratios and volatile matter. The use of rank appears to be the most accurate means of predicting combustion behaviour. *************************************************************************************************** ***************************************************************************************************
Combustion Tuning in High Ash Pulverized Coal Fired Boilers having Direct Tangential Firing System
Combustion tuning in boilers will lead to optimizing the performance more so in high ash coal fired boilers. In high ash coal fired boilers having direct tangential firing systems, proper combustion will ensure minimum water wall deposits and thus an optimal furnace outlet temperature.
21
devolatilisation stage. The first stage is fast, taking times in the order of 0.1 sec. only. The second stage is slow, requiring times in the order of 1 sec. to 2.5 sec. and therefore, thus has a major effect on the size of the combustion chamber. In practical combustion situations, such as in a large pulverized coal combustor, different particles can undergo concurrently different processes such as pyrolysing, oxidising reactions under different temperature regimes.
Tangential firing
In a tangential firing system the coal is pulverized in coal mills and is carried by primary air to the furnace through coal pipes. The mills are usually a constant airflow mill and have a specific output in mass of coal ground depending on coal properties like hardness, moisture, and fineness which affect the mill output. In direct tangential firing systems, the pulverized coal from the coal mills is directly taken to the furnace. Coal properties such as FC/VM (Fixed Carbon / Volatile Matter), particle size, oxygen, calorific value of the coal, reactivity, and ash content seem to be the most important variables for pulverised coal combustion in tangentially fired boilers, and they are highly inter-related. The total quantity of coal to be pulverized for a specified size of boiler at a designed efficiency will depend on the calorific value of coal. As the ash content in coal goes up, the calorific value per unit mass of coal comes down. This increases the mass of coal to be prepared, which in turn increases the number of mills or elevations needed in a tangential firing system. The secondary air required for combustion is sent into the furnace through a windbox housing the coal nozzles, oil guns, and the secondary air nozzles. Behind the coal nozzles there are fuel-air dampers which are used for keeping the flame front away from the coal nozzles by at least one meter from the tip. This is required to prevent the coal nozzle tips from getting burnt due to radiation from coal flame. The flame front is predominantly affected by the volatile matter in coal and the fuel air damper is modulated for controlling the flame front. As the fuel air dampers are opened, more secondary air goes through this damper and physically pushes the flame front away. However, when the flame front is already away from the nozzle tip, the fuel air damper needs to be closed fully.
Combustion air
The total air quantity for combustion in a boiler will depend upon the million kilocalories being fired to generate steam at a specified parameter. This total air is divided into primary air and secondary air in the ratio of 30 % and 70%. As the ash percentage goes up in coal, the amount of mill air flow goes up, as the number of mills to be in operation goes up. This results in an upset between primary and secondary air ratio. Tuning combustion in high ash pulverized coal fired boilers having direct tangential firing systems should address all the above said factors.
22
Now keep the mill air flow at the flow value noted when furnace fluctuation started plus about 1 t/hr, make sure no furnace pressure fluctuation is seen o Repeat this for all the mills one by one This ensures minimum primary air flow being used for transporting the high ash coal powder to the furnace Check the flame front if it is one meter away from the coal nozzle tip then close all fuel air dampers. If volatile matter in coal is 20% or less this condition gets satisfied Keep the windbox pressure of 80 to 100 mm of water column Watch the furnace for the flame conditions like brightness and flickering
The steps carried out will help to achieve combustion at optimal level. Optimum combustion in the boiler will ensure performance of the boiler within a desired limit. *************************************************************************************************** ***************************************************************************************************
These are some of the very different scenarios in power generation investment. How to compare and calculate the economics of each type of power generation? How to arrive at a cost to charge the consumer? The Levelized Cost of Energy (LCOE) is the method that is commonly used. The method can also compare different technologies competing for a utility bid. Utilities use this to calculate the electricity cost to be charged to the consumer. In the electricity bidding market this LCOE is a very important factor.
23
Since most of the costs or expenses and the sales revenue occur in a future time, one has to account for the time value of money and the risks. This is done by calculating the Present Value of these cash flows. A discount rate is used to calculate the Present Value. The discount rate varies within organizations and industries. This takes into account the risk factors, economic fundamentals, the investment mix, and the debt structuring. The present value of the future returns less the investment in the beginning gives the Net Present Value (NPV). The $/Kwhr rate used to calculate sales revenue to achieve a zero NPV is the Levelized Cost of Energy.
Calculation of LCOE
To calculate LCOE one would require The capacity of the plant expressed in megawatts or kilowatts. The capacity can remain the same throughout the lifetime or can be reduced due to operational wear and tear. The yearly plant load factor . This accounts for the availability and utilization of the plant, the maintenance outages, and load reductions due to demand or machine defects. This two will give the units of electricity generated during the life time of the plant. This together with unit cost of electricity will give the Sales revenue. The costs can be of five major types: Investment costs. This includes the yearly interest charges, the paybacks, and other financial charges. The initial investment or the overnight charges is considered as occurring at the end of the construction phase of the project and is used to calculate the Net Present Value. Taxes. Depending on regulations and policies. Also to be included are subsidies or incentives for renewable power. Fuel cost. To calculate this one would require the heat rate or efficiency of the plant (kilojoules per kilo watt hour) , the cost of fuel ($/kg or $/Kg) and escalations to the cost of the fuel. Operation and maintenance costs. This is taken as a fixed number for each unit of electricity generated. Depreciation and major replacement costs. To calculate the Net Present Value one will require the discount rate expressed as percentage. It could be in the range of 10 to 18 %, which is matter of national and organizational policies. Using an Excel spreadsheet will be the easiest way to do this calculation. The cost can be calculated for each year. The sales revenue for each year is calculated based on the units generated and an assumed value of unit electricity cost. The difference of the sales revenue and the costs give the yearly cash flow. The present value for this series of cash flow is calculated by the NPV function in Excel. The present value less the initial investment gives the Net Present Value. The assumed value of electricity cost is adjusted or iterated to get a zero NPV. The Goal seek function in an Excel spreadsheet also can be used for this. The unit electricity cost to achieve zero NPV is the Levelized Cost of Energy.
*************************************************************************************************** ***************************************************************************************************
24
For a given coal, the elimination or reduction of the residual matter and emissions are not possible. These are chemically fixed. What can change is only the method of capture and its disposal. What the proponents of Clean Coal Technology are doing is only this. In earlier days, dispersion of the ash and gaseous emissions to the atmosphere was through the chimney. The after effects were disastrous, affecting a large population base. Acid rain, ground level ozone, respiratory diseases, and reduced visibility all were a result of this. Strict environmental regulations helped in developing technology to capture these emissions. Today electrostatic precipitators collect almost all of the ash particles. Flue gas Desulphurization Units and Selective Catalytic Reduction units capture most of the emissions. The captured ash and residues will turn out to be environmental issues as these coal fired power plants age. The collected ash or the sulphate from the desulphurization units over the years make massive piles that will lead to environmental issues. A 600 MW Coal fired power plant produces almost a million tons of ash in three years. It affects agriculture, groundwater, and the health of the people living nearby. It may take many years to notice the effects. This does not make the coal clean.
25
NOx and CO
The process of combustion itself generates some undesirable gaseous emissions like NOx and CO. These, though not necessarily a part of the basic reaction, are present in everyday combustion. Advances in combustion technology and operation philosophy have seen considerable reduction of these emissions. This is really eliminating an unwanted emission and a success of clean coal technology.
CO2 emissions
CO2 still emits into the atmosphere. Commercial scale capturing of CO 2 ( Carbon Sequestering Systems ) and sending it to underground reservoirs is yet to be viable. CO2 emission will continue to be the main burden of coal, unless large scale forestry takes place to absorb the emissions.
Residue Utilization
Utilizing the captured residue, substituting for other natural resources, is an environmentally better disposal method. Technologies like: Mixing fly ash in cement, Using fly ash for road laying Using fly ash to make bricks Using sulphate from flue gas desulphurization for making gypsum boards Even though this is only a smaller percentage of the residue or emissions captured, this is a constructive clean coal method. Nature has taken millions of years to sequester the carbon into coal. In a few milliseconds, man has found the means to release it back to the atmosphere. The Pandoras box has been opened, and we can only wait for Hope. A real clean coal with no emissions or environmental effects is impossible, but a cleaner coal is a must.
*************************************************************************************************** ***************************************************************************************************
26
pressure part erosion. Fly ash erosion is experienced in the economizer, primary SH, and inlet section of steam reheater tubes. When non-uniform flue gas flow distribution occurs in these areas, the rate of erosion increases multifold. Factors influencing fly ash erosion in coal fired boilers are The velocity of flue gas The temperature of flue gas The mineral content in coal The change in direction of flue gas The arrangement of pressure parts and The operation above the maximum conditions design rating or with excess airflow above design rate.
Of these factors, the velocity of flue gas, the temperature of flue gas (ash), and mineral matter in coal are the main influencing factors.
*************************************************************************************************** ***************************************************************************************************
Predicting Combustibles in Pulverized Coal Fired Boilers - Fly Ash and Bottom Ash
Predicting the percentage of combustibles in fly ash in a tangential fired boiler using proximate analysis of coal gives boiler designers an edge during the proposal and contract stages. Here is how to predict fly ash and bottom ash combustibles in order to compute carbon loss in a boiler. In boilers with pulverized firing systems, about 80% of the ash in coal being fired is carried as fly ash. The other about 20% get collected as bottom ash. During the combustion of coal, some portion of the hydrocarbon, mainly char, leaves the furnace as unburned particles. The amount of such unburned particles leaving the furnace depends on many factors like the coal property, the type of burning system, the resident time available in the furnace, the ash percentage in coal, the calorific value of coal, the fuel ratio, the operating conditions, etc. The existence of unburned carbon in ash decreases not only the combustion efficiency, but also the grade of fly ash for commercial sale.
27
Carbon loss is influenced by the following: (1) coal preparation and grinding, such as changes in ash and maceral content ; mean, standard deviation, and higher moments of the particle size distribution; moisture remaining in the pulverized coal, (2) properties of the pulverized coal and its char like heating value, char yield on pyrolysis, char structure, char reactivity, ash content and composition, and characteristics, and (3) adjustments of the burners and furnace such as air preheat, excess air, mixing, residence time, and furnace temperature. Hottel and Stewert (1940) were the first to consider the interaction between furnace design and coal properties in the determination of carbon conversion, analyzing the effects of grind, reactivity, temperature, excess air, and residence time on unburned carbon loss. With the estimated values of percentage combustibles in fly ash as well as bottom ash, the carbon loss can be calculated by using the formula given in BS_EN_12952, ASTM, PTC 4 and any other International Standards. Boiler designers during the design stage have only proximate analysis, ultimate analysis and ash composition of coal. Carbon loss calculation involves calculating the carbon loss in fly ash and bottom ash. This article provides a tool for the designers and others to predict the percentage of combustibles in fly ash and bottom ash in a tangential fired boiler using proximate analysis of coal and the residence time in the boiler furnace. Based on combustibles in flyash and bottom ash, it is possible to compute the carbon loss in a boiler.
[{(FC/VM)+(HVV/8080)*100+Log(A)}/Res^2] The equation governing the curve fitted on a fourth order polynomial is Y = -3E-06 X4 + 0.0004 X3 - 0.0161 X2 + 0.2969 X - 0.9438 with a R square value of 0.8824.
As this predictive equation is only made for a pulverized coal tangentially fired boiler, this has to be verified for pulverized coal wall firing, down shot firing, opposed firing, etc. However, more than 50% of the pulverized coal fired boilers in the world are equipped with tangential firing system.
28
The single most independent variable affecting the bottom ash combustibles is the plus 50 mesh size of pulverized coal. A plot of percentage bottom ash combustible plotted against percentage plus 50 particle sizes has a fourth order polynomial curve with an R2 value of 0.9412. The equation governing this fit is
*************************************************************************************************** ***************************************************************************************************
29
30
After consolidation of the data and understanding the data, the next step is to do a set of field tests. These field tests include. Visual inspection for o Erosion, corrosion o Swelling, scaling o Deposits, misalignments o Supports, pipe hangers etc Dimensional checks o Thickness o Outside diameter Non-destructive examination Penetrant testing including fluorescent type Magnetic particle inspection (Wet fluorescent & Dry) Ultrasonic tests In-situ hardness checks Eddy current testing Tube sampling water walls for internal deposit analysis Superheater and reheater sample if needed Special examinations for o WW H2 embrittlement o Superheater/Reheater for oxide scales, o Metallographic examination of thick wall component o Fibroscopic inspection of headers and other regions needed o Spot chemical check when needed
Once when the field tests are completed, a few laboratory examinations and tests are carried out. The tube samples taken from the water walls, superheater, and reheater are subjected to microscopic examination (Light Microscopy & Scanning Electron Microscopy) to understand the microstructure of the tube material. The water wall tubes are subjected to internal deposit analysis. Both the quantity of the deposit and the chemical composition are carried out to evaluate the need to carry out post operational acid cleaning. Based on this, the solvent for post operational acid cleaning is decided. Other mechanical and metallurgical tests are also carried out for the tube samples collected. If any external deposits are collected from locations in the boiler, they are also analysed to understand the cause of the deposition. The presence of both external and internal corrosion is also evaluated based on the deposit analysis and the tube sample study. If the failure data gives a clue for any hydrogen embrittlement in the water wall tubes, a detailed field test and analysis is carried out to decide the area requiring replacement. The samples taken from the thick walled components are analysed for spheroidisation and cavitation level. Based on the level the repair and replacement strategy is arrived at.
*************************************************************************************************** ***************************************************************************************************
31
Operating parameters
First check the excess air being given to the boiler for combustion. If it is lower than recommended by the designers, then increase it. It may even help if the excess air is increased slightly above the design recommendation. Check the primary air through the mill. If they are much higher than required, this reduces the secondary air available for combustion, since the excess air in the boiler is maintained. Once the primary air is ensured to be the minimum required, then check the secondary air distribution between the burners or elevation accordingly. Check if the number of mills in operation can be increased, if yes then cut in new mill and reduce the load on the operating mills. During this suitably take care of secondary air distribution. If for any reason a high reactive fuel like oil or gas is fired in combination with coal then it will be good to remove this fuel. High reactive fuel will reduce oxygen availability for coal molecules resulting in a localized reducing atmosphere. This increases the potential for coal ash to slag. Check the soot blower operation, both the wall blowers in the furnace and the long retract. Increase the frequency of wall blowers as this can cool the flame more and reduce the slagging potential. Check the pulverized coal fineness ensure 75% through 200 mesh sieve and only less than 1% is left over 50 mesh sieve. If with all the above the heavy deposition / slagging does not reduce then this may even warrant a load reduction on the boiler.
Elaborate studies both in the field and laboratories by collecting large volume data on all required area has not yielded a single or multiple set of rules to predict coal slagging in boiler furnaces.
32
*************************************************************************************************** **************************************************************************************************
33
Water contains dissolved salts, which upon evaporation of water forms scales on the heat transfer surfaces. Scales have much lower heat transfer capacity than steel: the heat transfer coefficient of the scales is 1 kcal/m/C/hr against 15 kcal/m/C/hr for steel . This leads to overheating and failure of the boiler tubes. Scale also reduces flow area, which increases pressure drop in boiler tubes and piping. Low pH or dissolved oxygen in the water attacks the steel. This causes pitting or lowering the thickness of the steel tubes, leading to rupture of the boiler tubes. Contaminants like chlorides, a problem in seawater cooled power plants, also behave in a similar way. Flow assisted corrosion occurs in the carbon steel pipes due to the continuous removal of the protective oxide layer at high flows. Impurities carried over in the steam, causing deposits on turbine blades leading to reduced turbine efficiency, high vibrations, and blade failure. These contaminants can also cause erosion of turbine blades. Silica at higher operating pressures volatilizes and carries over to the turbine blades.
The first step is to get the make-up water to the steam cycle as pure as possible. The correct operation of the DeMineralisation (DM) plants ensures this. The second step is to form a magnetite layer on the inside surface of the tubes which protects the metal surface from any further corrosion attacks. The third step is to maintain this magnetite layer throughout the life of the plant. If the water quality goes down, this protective layer will be destroyed and corrosion starts damaging the tubes. In a 500 MW power thermal plant around 1300 Tons of water is circulating per hour continuously in the water steam cycle through the boiler, turbine, condenser and heaters. As the water circulates, there is an increase in contaminant level and a change in water quality. This is due to many reasons like: contact with almost 25000 m area of wetted steel in the tubes, piping and heat exchangers the residue of chemicals added entrapped oxygen and other gases especially in the vacuum area returning condensate from traps, glands, vents and drains impurities in the DM water make-up
Major parameters that require monitoring for water treatment are: 1. 2. 3. 4. The dissolved solids. The pH of the boiler feed water. Dissolved Oxygen in the feed water entering the boiler. Silica in boiler water.
34
35
PH control is by the addition of chemicals like Tri-Sodium Phosphate in the boiler water or the caustic treatment. This helps in maintaining the pH levels in the range of 9.0, slightly alkaline. The chemical reactions result in the formation of salts, which increases the dissolved solids level. In subcritical unit, blow down removes this. This is not possible in supercritical units. So an all volatile treatment (AVT) is used. This method uses amines whose reaction products are volatile, leaving behind no solids. This passes along with steam and removal takes place in the de-aerator or polishing systems. AVT is also the new method in subcritical drum type units. Super critical units also use the oxygenated treatment (OT) system, which involves injecting a known quantity of oxygen in the feed water. This helps in maintaining the magnetite or hematite layer, which provides the barrier to prevent any further corrosion in the piping and tubes. During start-ups and at lower loads where the water chemistry regimes are fluctuating, boiler water control is by the AVT method.
. Dissolved oxygen removal is in the deaerator where at saturation temperatures oxygen stripping is easier. Addition of hydrazine at the deaertaor outlet also removes the dissolved oxygen if any in the feed water. Supercritical units also use deaerators. But some plants using only OT operate without a deaerator.
Silica control can is by blow down in a subcritical unit. In Supercritical units the only way is to ensure very low Silica in incoming DM water and good removal in the condensate polishing unit.
As the thermal plant operating pressures increase and become supercritical, water chemistry management also becomes critical. Along with adopting the correct water treatment method, a high quality DM plant and precision analytical instruments for monitoring online water chemistry is a must to eliminate outages of the plant.
36
Specific causes
One feed pump trips Mal-operation of feed control auto Mal-operation of feed pump scoop Mal-operation of feed control / regulating valve Sudden reduction in load Sudden tripping of one or more mills Tube failure in water wall with large opening Mal-operation of emergency drain valve Mal-operation of low point drain
Plant response
Low drum level alarm Very low drum level trip
The effect of very low drum level operation is very severe that it can cause the water wall tubes to get overheated; it can cause snaking of water wall tubes leading to lot of projection in and out of furnace. It can cause instant short term fish mouth tube failures in water wall. This kind of failure has led to furnace explosion under certain specific conditions and based on the location of the failure. If the failure of the tube is in such a location in furnace that the
37
steam coming out of the tube mixes with the coal particles to form producer gas, then an explosive mixture forms and the boiler furnace explodes. The overheating is seen to happen in many water wall tubes rather than a single tube as experienced in many cases. Rectification of the furnace wall becomes more difficult and time consuming as it requires extensive checking both by an NDT (non-destructive testing) method as well as a sampling method. Leaving tubes that have snaked may not lead to any adverse effect in performance of the boiler except in certain specific locations, like near the burner where fuel impingement can occur and cause fuel ash erosion. The reason for such major failure of water wall tubes when the drum level goes to lower than the very low limit is due to the fact that the steam in the drum gets entrained in the down comers of the circulation system, and this upsets the whole natural circulation in the boiler. When the circulation in furnace tubes is upset, the cooling of tubes does not take place effectively, which leads to failure of tubes due to short term overheating.
38
Boiler
Boiler design depends on the type of fuel being fired; gas fired boilers have the smallest furnace and the coal fired the biggest. The coal fired boiler furnace size further changes with respect to the amount and type of inorganics (ash) the coal contains. When we compare two boilers firing with the same percentage ash coal- one slagging type and the other non-slagging- the one with the slagging nature will have to be designed with a larger furnace size. Except for the economics of coal fired boiler for steam generation, in all other aspects it has a lesser preference with the users. Coal fired boilers have many more auxiliaries, are cumbersome to operate, the uncertainties in fuel
39
characteristics are high, higher pollutants have to be addressed, etc. There are many types of design available for all fuels, and more so for coal firing with combinations of auxiliaries. The amount of auxiliary power consumption is the highest for coal fired boilers.
Other systems
All other systems like the compressed air system, lighting system, firefighting system, turbine, generator and electric power gridding system can have the same features for any type of boiler used with any fuel as they all are independent of boiler type and fuel.
Related Reading
Boiler classification can be based on many factors like usage, fuel fired, fuel firing system, type of arrangement etc. Commonly known types are pulverized coal fired boilers, fluidized bed boilers, super critical boilers, oil and gas fired boilers. All cater to industrial and power generation. Hydrocarbon fuels are the major source of energy for power and process steam generation, and coal takes a major share in this. Boiler furnace design will depend more on fuel characteristics, and further heat transfer surface sizing will depend on furnace outlet temperature. Furnace sizing is a very important for a successful boiler design. The variation in boiler furnace size can upset the performance drastically. Oil and gas fired units have more uniform sizes, but the coal fired units have large variation. Optimization of combustion in high ash Indian coal fired boilers is of special interest due to the organic and inorganic mix up and the large amount of variation in the organics.
*************************************************************************************************** ***************************************************************************************************
40
Look at the number of mills operating Note the load, air flow, and outlet temperature on each mill Check the oxygen level at Eco / APH outlet Check the furnace pressure, scanner performance- watch for a few minutes for any fluctuations Look at the coal proximate analysis within 8 hours- if not available then at the max 24 hrs Check the PC fineness reading of each running mill if available Keep a note of those mills which have plus 50 more than 2% and minus 200 below 65%
*************************************************************************************************** ***************************************************************************************************
41
Detailed measurements of furnace flame temperature profile in the field were carried out while varying the air distribution pattern. The results of the study shows that the proper understanding of the fuels combustion characteristics could help in tuning the combustion regime whereby the flat furnace gas temperature profile could be changed to match closely the normal profile experienced with reactive coals. The temperature in the burner zone could be increased by about 50 Degree C and the furnace outlet temperature could be reduced by about 90 Degree C.
42
The newly introduced clean coal operation technologies are aiming at reducing the amounts of these pollutants escaping into the atmosphere. They are targeted mostly toward the reduction of carbon dioxide since global warming is the most severe environmental impact. The first clean coal energy plant, actually a pilot plant using US FutureGen technology and operated by a Swedish firm called Vattenfall, started operating in 2008 in Spremberg, Germany. The facility uses the technique of carbon capture and storage to clean coal. More specifically, carbon dioxide is captured and then compressed into a liquid state and stored. This way the CO2 does not escape into the atmosphere. The technique is described in more detail below, along with other clean coal technologies that are currently under development.
43
More specifically, the idea is based on capturing carbon dioxide from fossil fuels, including coal and natural gas (methane). As soon as the CO2 is separated from the rest of the fuel, it has to be safely stored. Storage or sequestration take place in deep geological formations or deep in the ocean. Although leaks are a major problem in both cases, geological formation storage is considered to be safer since storage in the oceans runs a greater risk of acidification.
44
Removal of SO2 and NOx pollutants: The burning of coal results in the emission of sulphur dioxide and nitrogen oxides. Several methods are used to remove these pollutants, for instance : Sulphur dioxide - Flue gas desulphurization (FGD) systems use limestone and water, a mixture that reacts with the SO2 of the flue gas to form gypsum, a very popular material used in the construction industry. Nitrogen oxides - The specially designed low NOx burners prevent the formation of the gas by reducing the amount of oxygen available in the hottest part of the coal combustion chamber.
Conclusion
There is a great deal of concern regarding the future of these technologies. Greenpeace suggests that no coal-fired power plant is ever truly clean. All that clean coal techniques manage is to circulate the pollutants and finally release them back into the environment. Apart from that, the economic viability of these technologies is in question. Research on clean coal technologies is taking place "for over 10 years and $5.2 billion have already been spent in the US alone" (Greenpeace). It is expected that it will take hundreds of millions of dollars and many more years before they are commercially available. Despite the concerns, clean coal technology is now shifting toward a newly modified coal gasification technique that may provide what is called "zero emissions" or actually low emissions of carbon dioxide and other pollutants. Although the US DOE planned to have commercial designs for power plants using the technology by 2012, the project was postponed *************************************************************************************************** ***************************************************************************************************
45
Reliability. One of the greatest advantages of coal fired plants is reliability. Coals ability to supply power during peak power demand either as base power or as off-peak power is greatly valued as a power plant fuel. It is with this fact that advanced pulverized coal fired power plants are designed to support the grid system in avoiding blackouts. Affordability. Energy produced from coal fired plants is cheaper and more affordable than other energy sources. Since coal is abundant, it is definitely cheap to produce power using this fuel. Moreover, it is not expensive to extract and mine from coal deposits. Consequently, its price remains low compared to other fuel and energy sources. Abundance. There are approximately over 300 years of economic coal deposits still accessible. With this great amount of coal available for use, coal fired plants can be continuously fueled in many years to come. Known technologies. The production and use of coal as a fuel are well understood, and the technology required in producing it is constantly advancing. Moreover, coal-mining techniques are continuously enhanced to ensure that there is a constant supply of coal for the production of power and energy. Safety. Generally, coal fired plants are considered safer than nuclear power plants. A coal power plant's failure is certainly not likely to cause catastrophic events such as a nuclear meltdown would. Additionally, the welfare and productivity of coal industry employees has greatly improved over the years. In fact, injuries, time lost, and fatalities have decreased significantly in the past years.
46
47
Based on the fuel given, for design calculate the fuel quantity, air and flue gas flow required. Now determine the size and shape of furnace which will require knowledge of burner size, other combustion systems, emission requirements, ash handling, furnace outlet temperature limitation, etc. Design superheaters, reheaters, ecomomisers, and air heaters so that the second pass can be finalized. Care must be taken to size the heat transfer areas such that any requirement due to fouling and the erosive nature of fuel is addressed. Design the desuperheating requirement, location and number of equipment for cleaning of pressure parts. Boiler enclosures, supports, piping, expansion guides, and movements are all to be designed and checked. The code to which the boiler is designed is very important and has to be adhered.
It is to be remembered that among coal fired boilers themselves, the furnace sizes will vary considerably depending on the age of the coal, ash characteristics, the reactivity, etc.
48
49
50
Flushing the tubes to ensure any blockages are removed Keeping the water quality at the recommended level Making sure drum internally are set and maintained properly Ensuring the right material transition point, higher grade material in the lower temperature portion of the tube for some length can take care of operational variation. Ensuring the right quality material selection during design stage.
Related Reading
Understanding Tube Failures in High Pressure Boilers - Boiler tube failures are inevitable. There are twenty-two primary reasons for tube failures in a boiler. It is true that being forewarned is being forearmed. Knowledge and good operating and maintenance practice reduce tube failures. Mechanisms of Steam Soot Blower Erosion - There are many mechanisms that can cause steam soot blower erosion of boiler tubes at various heat transfer sections. Knowing the way these mechanisms contribute to erosion will help to prevent loss of availability of boiler. Causes of High Temperature Corrosion in Boilers - High temperature corrosion occur in boilers occurs mainly in two areas- waterwalls and superheaters. The inorganic impurities in fuel like vanadium, sodium, sulphur, etc., are responsible. Read on to learn more about how this happens. *************************************************************************************************** ***************************************************************************************************
Introduction
Urgent need of alternative sources of energy is being greatly felt in every part of the globe. Due to dependence on coal based thermal power plants and fission type nuclear power plants, which uses uranium and plutonium, our environment is being badly affected by emissions of carbon and the problems of radioactivity and radioactive waste. Hydro power plants also have some limitations. Research and development in the field of solar, wind and biogas, and electricity storage devices, is also pursued vigorously in every part of the world. Every scientist and engineer engaged in this field wants some lead on which they may start research so that our requirement of energy may be fulfilled. The emphasis is on clean, green energy and cheap sources. There is talk about carbon emission, global warming, and environment protection, etc. Some scientists, without any support from governments and big institutions, have presented the idea of cold fusionLENR (low energy nuclear reaction) or CANR (chemically assisted nuclear reaction). If their claims are verified, then it may be answer to every problem addressed above.
51
Nuclear fusion is an answer with which we may find limitless energy, but its practical use seems a distant possibility. In nuclear fusion hydrogen nuclei are fused into helium to get huge amounts of energy. Hydrogen nuclei are positively charged so repel each other as per Coulombs law. For a nuclear fusion process to take place, temperature and pressures like the Sun are needed. Experiments in using nuclear fusion for the generation of power have failed due to the requirement of recreating sun-like high temperatures and pressures in lab conditions. Production of radioactivity and the need to deal with radioactive waste makes this process unsuitable for the production of cheap, green, and clean energy.
There is news about cold fusion, which is also termed as low energy nuclear reactions or chemically-assisted nuclear reactions. It is claimed that cold fusion may produce 27 times more energy than gasoline and that this process produces no radioactivity and radioactive waste. The cost of energy produced is also claimed to be extremely low compared with fossil fuel, i.e. 1 cent/kwh. The cold fusion reactors seem to be like electrolysis cells. Every home may be equipped with small cold fusion generator, i.e. up to 12KW, making our conventional energy sources and transmission infrastructure obsolete. It is claimed that hydrogen is fused into helium at room temperature in an electrolysis chemical process. Palladium electrodes or nickel electrodes are being used for excitation in this process. Production of tritium, neutron, helium, copper and huge amounts of energy is being claimed, but such claims still need to be verified by the mainstream scientific community.
52
Scientists who claimed that they have seen the cold fusion process in operation have always failed to replicate this process again, causing the research to be discredited. The big question is how cold fusion is triggered. No scientific explanation of room temperature fusion is to be found in our nuclear physics textbooks, so we fail to understand its theory, whether it is nuclear physics or chemistry. Some say it is a nuclear reactor and others term it merely a chemical electrolysis cell.
Conclusion
53
However we must look at such experiments with an open mind. Any promising experiment must be examined with great care because such research may lead to us clean and green energy alternative sources. We need miracles in the field of alternative energy for our bright future so scientists and engineers must examine every lead, including cold fusion, low energy nuclear reactions, chemically assisted nuclear reactions, condensed matter nuclear science, plasma electrolysis and nuclear transmutations, with extreme care and an open mind prepared to revolutionize the world. There is currently no alternative to known alternative energy sources to secure our future. We must develop the tradition of listening and welcoming every lead in order to create our miracle. The efforts of cold fusion scientists must be appreciated because they are trying to change our future positively. Such efforts will lead to us some viable alternative solution, we must hope. *************************************************************************************************** ***************************************************************************************************
54
Boiler downward expansion should be noted as the pressure is raised to 40 kg/cm The firing rate must be slowly increased, keeping in mind the drum temperature differential Keep the drum level slightly above the normal level as when the blowing is started the water level will raise and go beyond sight then as the blow proceeds it will drop below lowest sight level if water level maintained is at or below normal. In the first stage of blowing the first blow is done at much lower pressure to check the temporary pipe supports and anchors. The temporary valve provided is opened to blow through the superheater, the main steam pipe and the temporary pipe. The first few blows, generally three blows, are done without any target plate till the color of steam is clear. Then the preliminary target or impact plates made of stainless steel material 40 to 50 mm wide, 25 mm thick and of length to suit the pipe diameter is placed to capture the indentation of the particles going along with the steam. The target plate must be placed just after the mainstream line in the temporary pipe but not too far and the velocity at this place must be around 245 m/s. 2 While blowing the fire is killed and the pressure is dropped to around 15 kg/cm ; this ensures a good temperature differential for any adhering material to dislodge. The boiler is started after closing the steam blowing valve and the process is continued. The final target plate of turbine blade is placed once the preliminary target plate is in acceptable form, and the blowing is continued till the indentations are acceptable to the turbine manufacturer. After the mainstream line is completed the other stages are done in the similar way to achieve a clear target plate of acceptable quality.
Precautions
During steam blowing The thick wall components like the drum, headers and piping are subjected to much higher thermal stresses than the normal operation of the boiler, so it is prudent to keep the number of blows to the minimum required for effective cleaning. As a rule of thumb it is good to keep the number of blows less than 50 a day. The temporary pipe is designed for a much lower pressure than the boiler system and hence the operators should take extra care not to exceed the pressure beyond what is required for blowing. Care must be taken in the forced circulation boiler. If the drum level is very low and the pump losses its suction then the boiler must be tripped and the blow must be terminated It is not possible to avoid carryover of solids to the superheater during steam blowing, hence boiler water should not be treated with non- volatile chemicals The temporary supports provided should be watched and every day before starting the boiler they must be inspected fully to avoid any catastrophe.
55
Many of the factors like percentage ash, chemical composition, the number of hours of operation, etc. cannot be tailored to contain the wear of the burner components. The designers adopt mainly weld overlay or cladding or metal spraying to improve life of the coal burner. The method chosen will depend on the ash percentage and composition of coal being used in the boiler, the cost, and the life enhancement period.
Related Reading
Fly Ash Erosion in Boilers Firing High Ash Coals Coal is one of the main fuels for power production. Coal quality deterioration over the years has created challenges for boiler designers the world over to compact and minimize erosion in pressure parts. Fly ash erosion is a major factor for pressure parts damage in high ash coal fired boilers.
56
Coal Formation Theories - Coal may be defined as a compact stratified mass of plant debris which has been modified chemically and physically by natural agencies, interspersed with smaller amounts of inorganic matter. In situ and Drift are the two major theories of coal formation. Considerations for Coal Blending in Power Stations Coal blending in power stations is mainly adopted to reduce the cost of generation and increase the availability of coal. The low-grade coals can be mixed with better grade coal without deterioration in thermal performance of the boiler, thus reducing the cost of generation. *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
Economizer
The feed water from the high pressure heaters enters the economizer and picks up heat from the flue gases after the low temperature superheater. Many types of economizer are designed for picking up heat from the flue gas. These can be classified as an inline or staggered arrangement based on the type of tube arrangement. The staggered arrangement is compact and occupies less volume for the same amount of heat transfer when compared to the inline arrangement. Economizers are also designed with plain tube and fined tubes. The fins can be longitudinal or spiral. All these types are suitable for clean fuels like gas, oil, and low ash coals. For high ash coals, only the plain tube inline arrangement is used. This is mainly to reduce ash erosion and thus reduce erosion failures. These economizers pick up about 50 to 55 degrees centigrade in a large capacity boiler, which will reduce the flue gas temperature by about 150 to 170 degree centigrade. The boiler designers always keep the economizer water outlet temperature to about 25 to 35 degrees below the drum saturation temperature. This is done to mainly avoid steaming in the economizer. A steaming economizer generally is less reliable. As a rule of thumb, for every one degree pick up of economizer water temperature, there will be a drop of about 3 to 3.5 degrees.
57
combination of tubular and regenerative air pre-heater, then they have a choice of tri-sector regenerative air heater. Normally the ambient air is heated to about 300 to 350 degree centigrade. This results in a flue gas temperature drop of around 230 to 250 degree centigrade. So for each degree pick up in air temperature, roughly 0.8 degree drop in flue gas temperature is achieved. Steam coil air pre-heaters are another type. These are used only during start up of the boiler to prevent low temperature corrosion. This air heater does not contribute to improving the efficiency of boilers, but are provided to improve availability. It is seen that during start up the chances of low temperature corrosion is high, and hence the need to provide the steam coil air heaters is evident. Both economizer and air pre-heaters are called heat recovery systems in a boiler. Were it not for these heat recovery systems, present day boilers would be operating at much lower efficiency levels. *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
These lead to twenty-two primary causes that can cause a tube failure in a high pressure boiler: Short term overheating failure
58
Long term overheating failure (called also as creep failures) Dissimilar metal weld failure Fatigue caused by vibration Thermal fatigue due to temperature fluctuation Corrosion fatigue failures Caustic corrosion inside the tube Hydrogen damage in water wall internal surface Tube internal pitting Fly ash erosion Falling slag erosion Soot blower erosion Coal particle erosion Low temperature flue gas corrosion Fire side waterwall corrosion Coal ash corrosion Oil ash corrosion Damage during maintenance cleaning Chemical excursion damage Material defect and weld defects
59
The plant responds to these conditions by a large reduction in furnace pressure and leads to unstable furnace flame conditions. Depending on the indication and the reason for the cause of the problem the boiler operator will have to respond. Switch to induced draft fan control from auto mode to manual mode if the control system is the reason leading to low furnace pressure and take corrective action. Ask the controls engineer to rectify the fault before again turning on to the auto mode. Check the induced draft fan vane control system for proper functioning by changing the set point and finding the response. Rectify if required. Check the air flow condition and ensure the correct air flow to the boiler as per the load condition If one of the forced draft fan has tripped then after establishing the reason for trip and correcting the same, restart the forced draft fan.
The local operator in the field invariably has to check the induced draft fan vane control if this was the reason causing the low furnace pressure. If one of the forced draft fan has tripped, then he has to make ready the fan for restart after ascertaining the reason for the trip.
60
Related Concepts
There are many causes that can contribute to flame failure in boilers and require operator action. Operating the boiler with unstable flame is always dangerous and can lead to boiler explosion. Tripping the boiler is the option for all boiler designers and operators. High furnace pressure in boilers is a direct indication of a disturbance in combustion performance. The rate of change in the furnace pressure can vary from a simple sudden surge due to fuel variations to a huge furnace explosion. All forced draft fan trips in a boiler will cause a boiler trip. Putting the boiler back in operation and giving steam at the required parameter to the consumer is very important. Boiler operators should know how to handle both forced draft fan trips in a running boiler as delay in this can cause a very high loss to the plant.
61
62
The steam coil air pre-heaters are used in the majority of boilers to keep the cold end temperature higher during cold start-ups. The recuperative and regenerative air pre-heaters are for heating the combustion air to the boiler. Designers select these air pre-heaters depending upon the economics, the heat to be recovered from the flue gas leaving the economizer in the boiler, the capacity of the plant, etc. In all the three designs, plugging is seen to be a threat. The steam coil air pre-heaters can get plugged across the fins by anything that is carried along with the air being heated, depending on the location. As these air pre-heaters are used only at low loads and start-ups, if they get plugged there is a large amount of pressure drop across the length and the forced draft power consumption goes higher. The designers are now using a by-pass duct to house the steam coil air pre-heater. This saves the power consumed by the forced draft fan during higher loads. Placing this in the by-pass duct also enables any required on line maintenance to be done. In the case of tubular air pre-heaters, the plugging gets initiated during cold start-up due to reasons like unburned oil deposit on the cold end side, no flow region because of duct connections, tube leakage in the economizer area, infective soot blowing, wet steam during air pre-heater soot blower, frequent start-ups, etc. It is normally seen that the plugging gets initiated from the cold end side except in the case of a no flow region due to a duct connection. In the case of the regenerative air pre-heaters, the plugging is caused due to large number of start-ups, poor oil gun performance, ineffective soot blowing, ash particles settling, water washing of air pre-heaters with inadequate
63
drying, low frequency of operation of air pre-heater soot blowers, high amount of air pre-heater leakage with prolonged low load operation, etc. In both recuperative and regenerative air pre-heaters, the plugging rate goes up when ammonia is used for containing sulphur oxide emissions. Selective catalectic reduction and NO x control with higher than 10 ppm of ammonia slip have also been reported to have caused a higher rate of air pre-heater plugging. In the case of both recuperative and regenerative air pre-heaters, getting plugged affect the boiler performance adversely. The higher the plugging, the lesser the heat transfer surface available, and hence the flue gas temperature leaving the air pre-heater increases. This reduces the boiler operating efficiency and increases fuel consumption Increases the velocity of flue gases thus leading to higher erosion rate of the heat transfer surface Increases the downtime of the boiler for maintenance of air pre-heaters Increases the auxiliary power consumption of the boiler In the case of regenerative air pre-heaters, preferential plugging can cause vibration and combustion oscillations
Related Reading
Air Pre-heater Fires in Large Capacity Boilers - The damage due to air pre-heater fire is very severe depending upon the intensity of the fire. In many cases it has made the regenerative air pre-heater elements a molten mass. The boiler availability loss will be high if a fire takes place in the air heater Cold End Corrosion in Boiler and Its Prevention - In steam generating units using fuels with sulphur has a potential hazard of sulphur corrosion at the cold end of the boiler. The severity depends on many factors like percentage of sulphur in fuel, excess air, moisture in flue gas etc. Many options are available to contain cold end corrosion Both Regenerative Air Pre-Heater Motors Trip - Tips to Handle - In regenerative type air heater in boiler when the electrical motor trips always the air motor start on auto. Failure of this will lead to a major breakdown of air preheater and loss of availability of boiler. *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
64
can kill. People fail to realize that even our domestic supply of 120 Volts is a potential hazard that can be deadly if certain conditions are met. The hazards of electricity are of three kinds: electrocution, electric arc flash, and electric arc blast. Apart from these an electric shock can also kill or injure people working at heights through falls. Electric current passing through the heart can cause fibrillation of the heart resulting in a cardiac arrest. The electric arc generated by switch gears while loading and unloading equipment can cause deep tissue burns, and the pressure from an arc blast can make a household wall fall due to the impact. In view of all these hazards the NFPA 70E has stated regulations to reduce the risk of injury to workers due to shock and arc flash hazards
65
66
resistance of the subject. The curve plotted is a series of straight lines which give the current passing through the body. The range of current is summarized from very slight possibility of fatality to possibly and probably fatal.
67
68
AC current is more dangerous to the heart than DC current. The incidence of ventricular fibrillation is ten times more frequent after AC than DC shock.
69
4. 5. 6.
7. 8.
9.
Dissolved Oxygen has to be maintained below 0.007 ppm for pressure range 61-165 kg/cm2 and 0.005 ppm for a pressure range 166-205 kg/cm2. Iron is to be maintained below 0.010 ppm for pressure range 61-165kg/cm2 and 0.005 ppm for pressure range 166-205 kg/cm2. Copper needs to be below 0.010 ppm for pressure 61-100 kg/cm2, 0.005 ppm for pressure 101-165 kg/cm2 and 0.005/0.003 for pressure 166-205 kg/cm2. The copper level should match with the corresponding values has to be maintained in superheated steam. Total silica should be maintained below 0.020 ppm for pressure range 61-165 kg/cm2 and below 0.010 ppm for 166-205 kg/cm2. Specific electrical conductivity at 25oC measured after Cation exchanger in the H+ form after CO2 removal in Micromhos/cm to be less than 0.50 for pressure 61-100 kg/cm2 and below 0.30 for 101-205 kg/cm2. However, the specific electrical conductivity at 250 C in the special case of AVT, can be 0.2 (Max) and sodium 0.003 ppm (Max.). Hydrazine residual to be maintained below 0.01-0.02 ppm for all pressure range and the total organic carbon in ppm to be below 0.20.
All the measurements are to be made at the high-pressure heater outlet or economizer inlet. The pH levels required in feed water can be obtained by dosing ammonia or any proven method. It should be noted that the level of ammonia in the condensate and feed water should not exceed 0.5 ppm (as NH3) for a copper alloy pre-boiler system and 1.0 ppm (as NH3) for a Cu free pre-boiler system. Oxygen is generally measured before de-aerator and maintained below 20 ppb to minimize pre-boiler corrosion.
The phosphate and pH are given based on Co-ordinate phosphate treatment so as to prevent the presence of free hydroxide in the boiler water. Normally each power station has their own practice; the values given are only a guideline as understood from various practices. In the case of all volatile treatment for pressure range 166-205 all the values are to be more stringent. Not maintaining these chemical regimes of feed water and boiler water can lead to carry over of salts to superheaters and even to turbine blades causing plant availability loss.
70
71
Carbon Monoxide - CO
CO is a poisonous gas and is harmful to life. Carbon monoxide is formed due to the incomplete combustion fuels such as coal. Modern coal fired boilers have excess air levels that are 15 to 20 % greater than stoichiometric requirements. Furnace aerodynamics ensure the proper mixing of fuel and air so under normal conditions, the CO formed is negligible or almost nil. High levels of CO, 2000 -3000 ppm or higher are possible if the combustion is not good. This is mainly due to operator fault or improper maintenance of pulverizers, burners, and air registers Apart from the poisonous nature of the CO, CO formation is an indication of inefficient heat release from the coal. This in turn requires more coal to produce the same amount of power, increasing CO 2 emissions and associated problems. Almost all power plants have continuous monitoring of CO. This is an emission that can be eliminated.
72
Even though NOX formation is an inherent combustion related activity, this can be avoided by proper flame patterns and air fuel mixing. Due to the very complex flow patterns during combustion, there may be certain parts of the flame that are higher than the 1500 C. The low NOX burning systems are designed to streamline the flame to eliminate these hot spots. The air distribution systems and the aerodynamic design of the burner components are the two main items that are considered in low NOX burners. The NOx itself contributes to acid rain, smog formation, visibility, and eye irritation. National Air Quality Standards of the US restrict NOx emissions to 100 g/m3 on an annual arithmetic mean. The Indian cap is 80 g/m3. "Selective Catalytic Reduction" is the method to eliminate NOX. NOX is absorbed by urea liquid in the presence of a catalyst to form ammonia which disintegrates to form nitrogen and water vapor *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
Specific causes
One of the primary air fans operating trips Starting more mills without properly loading the primary air fans and stabilizing Closing of primary air fan inlet damper by mistake or malfunction Closing of air pre-heater outlet damper due to any reason Closing of primary air fan discharge damper due to any reason
Plant response
73
Mills trip by control system as per the designed logic There will be a rapid drum level fall needing regulation Boiler pressure and temperature will fall due to fuel input reduction if turbine and generators do not respond to the required level. Boiler furnace pressure becomes unsteady Combustion disturbance are noticed When oil support is not available flame failure can result With flame failure the boiler will trip
74
75
Tesla's turbine goes by several names: boundary layer turbine, Prandtl Layer turbine, bladeless turbine, and cohesion-type turbine. These names help reveal the most unique aspect of the Tesla turbine, which is its lack of blades. Most turbines use a system of blades, which spin from the force of a fluid flowing over the blades. The Tesla turbine design relies instead on the boundary layer effect and adhesion to spin flat plates. This has a number of benefits, which will be explained further later on in the article.
The turbine consists of a number of flat discs with ventilation holes around the center, each mounted on the same shaft. Spacers placed between the discs keep them properly separated. For maximal efficiency, the spacing must be as small as possible- only 0.4 mm for a steam-propelled turbine. The discs must be very smooth, and increased smoothness is always better for proper boundary layer development. The discs are housed in a chamber, which is designed with nozzles to feed gas into the chamber. The nozzles feed in gases at supersonic speed, which is achieved by combustion outside of the chamber.
76
Calculations show that the turbine efficiency for Tesla turbines is above 60 percent, and up to 95 percent. Tesla himself believed that steam-powered Tesla turbines could achieve turbine efficiencies up to 95 percent. These calculations use the shear stress induced by the boundary layer effects of the flowing fluid. This requires calculation of some characteristics of the motive fluid, like the Reynolds number. To prevent drag on the ends of the discs, which reduces efficiency, the spinning plates must be as thin as possible. This requirement contributed to material problems that prevented the Tesla turbine from gaining acceptance.
77
Specific causes
Tripping of induced draft fan Mal-operation of regulating vanes of the fans Unstable flame o Low wind box pressure o Improper burner operation o Sudden starting of mills with fuel in the mill o Sudden fuel input in to the furnace o Loss of ignition energy Gradual buildup of fouling in air pre-heaters Tripping of air pre-heater Furnace water seal broken High excess air levels Large amount of air ingress in the second pass of boiler
The causes given are all applicable for balanced draft furnace, but in the case of forced draft furnace some of the causes are not applicable.
Plant response
Furnace pressure high alarm appears for corrective action by operator Furnace trip activates if pressure goes above trip limit Boiler furnace pressure surge Can lead to explosion
78
If induced draft fan tripped, reduce load and stabilize boiler parameters Stabilize combustion if combustion is unstable Restart air pre-heater if tripped Check furnace seal and establish if broken Check induced draft fan for any mal-operation
It is a good practice for the local operator to get clearance from the control room before making any change (unless it is a standard procedure to take corrective action by the local operator). As furnace pressure increase is one of the indications for boiler explosion boiler operating engineers and all concerned must view increase in furnace pressure very critical and take corrective action and ensure safety.
79
80
81
Input-Output Method
The simple method is to measure quantity of fuel input and the steam energy output. This method is the input output method.
Efficiency %= Output / Input X100 =[Steam Flow kg/s x Steam Enthalpy kj/kg] - [Water Flow kg/sWater Enthalpy kj/kg] / [Coal Flow kg/s x HHV of Coal kj/kg] 100
In case of reheat units the reheater inlet and outlet enthalpy also has to be considered. Enthalpy of steam and water is available in steam tables if we know the pressure and temperature. Pressure and temperatures are available online in all the boilers. Steam Flow and water Flow also is normally available online. However the accuracies are to be verified before using them. One can determine the higher heating value by taking a sample of coal as it enters the boiler and analyzing it in the laboratory. These are normally done on a daily basis in most power plants. Fuel flow is more complicated. Gravimetric feeders used in modern power plants can give the coal flows to a certain degree of accuracy. Otherwise this will have to be computed from volumetric flows and bulk density of the fuels. This method, although it looks simple on paper, is not the industry preferred method because Flow measurements are not accurate nor steady Good quality flow instruments are costly. Flow measurements always involve a co-efficient, which can very much alter the results. Trouble shooting problems for determining the reasons for a lower efficiency is difficult.
However, this method finds use for quick calculation if the flow measurements are reliable and steady.
82
Losses Method
Another method and a more practical approach is to measure the losses and then calculate the efficiency.
Quick Facts
The most important factor that affects the Boiler efficiency is the Gas temperature leaving the boiler. In a coal fired boiler of a 500 MW power plant if the temperature increases by ten degree centigrade the efficiency reduces by about 0.5 %. Another main factor is the unburnt coal in the in the ash. One % increase in unburnts is around 0.5 % reduced efficiency. These two are controllable by the proper maintenance and operational adjustments. The operator has to find out reasons why these two parameters are high and take necessary corrective action. *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
83
These causes lead to flame failure individually or in a few a combination. This will depend upon when the flame quality becomes unacceptable.
It has to be remembered that delay in lighting up the boiler will decay the boiler pressure and temperature. Depending upon the duty of the boiler the time taken to come back on line will vary.
84
85
86
87
88
Plant Response
Sharp rise in air temp at APH outlet will be noticed Increase in flue gas temperature at air pre-heater outlet
Adopting some of the good operating practices of boiler can prevent air pre-heater fire totally during the life of the boiler.
89
Reduce number of startups of boiler to a bare minimum. Avoid operating boiler in low loads requiring oil support for a prolonged duration. It is a good practice to check oil viscosity characteristics on a periodic basis and whenever there is a change in supplier. Clean oil gun tips and lap the internals to satisfy the design requirements. Never restart the oil burners without purging during startup. Boiler startup operation must be avoided when air pre-heater soot blowers are not available. Always make it a practice to soot blow all the air pre-heaters, the non working air pre-heaters also must be soot blown by keeping the isolation damper marginally open to allow the soot to be blown out. During startups, low load operation, and shutting down, make it a practice to watch the trend of air and gas temperature leaving the air pre-heaters. Operate air pre-heater soot blowers regularly. Any fire detecting device provided by supplier has to be kept active and tested as and when possible.
To repair the air pre-heater damaged due to fire takes large amount of time and needs spares for replacements. Some of the spares of large air heaters will not be available off-the-shelf which can further delay the process of repair. The boiler availability loss will be high if a fire takes place in an air heater. Responding quickly to suspected air preheater fire immediately and taking corrective action can save a lot of money, downtime, and generation loss.
Carryover from the drum can be of two types: mechanical carryover and vaporous carryover. Mechanical carryover take place in a boiler mainly due to drum internals; drum level, foaming, and spray water. If the alignment of drum internals are not maintained as per requirement then the separation efficiency comes down and carryover occurs. Faulty screen driers also contribute to carryover. It is necessary to adhere to the dos and donts given by the designer
90
during operation and maintenance of the boiler to avoid carryover. Maintaining a very high drum level reduces the separation efficiency and a high level of carryover results. High alkalinity, oil in water and high TDS (Total Dissolved Solids) in boiler water will result in foaming in drum which leads to carryover. The chart attached gives a total picture of carryover. Carryover can be minimized by adhering to good operating and maintenance practices. Maintain drum water level within +/- 50 mm Maintain silica below the recommended value for the operating pressure Check and maintain the drum internals periodically and whenever carry over is noticed Feed water conductivity at 25 deg C to be maintained between 0.2 and 0.3 S/cm Boiler water solids to be maintained during operation within limits Measure steam purity and maintain within the specified limits Ensure feed water conductivity meter online to help monitoring the same
The end result of carryover will lead to deposition in superheater tubes which will result in long term overheating of superheater tubes. Carryover will also lead to deposits in the low pressure stage blades of turbine which reduces blade efficiency and increase heat rate of the machine. *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
Possible mechanisms
All blowers are set to be set at the right steam pressure recommended by the designer if this is not done then it leads to poor cleaning or higher rate of tube erosion due to high steam pressure. This is true for all soot blowers in the boiler starting from furnace to air pre-heater. The alignment of the blower with respect to the furnace walls, superheater tubes, reheater tubes, economizer tubes and air pre-heater tubes or elements is very critical and not maintaining this leads to erosion of the tubes and subsequent metal wastage. The thinning of the tubes finally leads to pinhole failures and many secondary figures due to this depending upon the orientation of the leak. It is required to ensure at least 50 degree centigrade of super heat in the steam being used for blowing. If the super heat in the steam is lower than required then during blowing wet steam impinge the tubes at high velocity and the impact force damaging the heat transfer tubes. This can be identified by the typical spit like metal wastage on the tubes surrounding the blowers area of effectiveness.
91
The duration of operation of blowers is another main reason for erosion of the heat transfer tubes. Even if you maintain the correct pressure and temperature the erosion will take place at a slow phase if duration is more than required. In coal fired boiler if alignment is not correct then the ash deposits being cleaned can get entrained and cause erosion of tubes. However in oil fired boilers it is not a mechanism that can happen due to the fact that the ash in oil is not significant at all. The higher frequency of operation of the soot blowers than needed also leads to tube erosion. Optimizing the soot blower operation is important as operating those blowers where deposits are not there or very low will lead to metal wastage over a period of time. Failure to drain the condensate in the soot blower steam pipes is also contributing mechanism of tube erosion. The condensate gets entrained in the steam while the blower operates and has a much higher damaging effect than the lower degree of superheat in steam.
What happens when the water is at a higher pressure, say, at 100 bar? Then the boiling takes place at 311 deg C and the latent heat of vaporisation is 1318 kJ/kg.
92
If the water pressure is 200 bar then the boiling takes place at 366 deg C and the latent heat of vaporisation is 584 kJ/kg. As the pressure increases the boiling temperature increases and the latent heat of vaporisation decreases. A further increase in pressure and temperature leads us to a point at which the latent heat of vaporisation is zero, or there is no boiling. Water directly becomes steam. This is the Critical Pressure and the Critical Temperature. For steam this occurs at 374 deg C and 220.6 bar. Conventional steam power plants operate at a steam pressures in the range of 170 bar. These are Subcritical power plants. The new generation of power plants operate at pressures higher than the critical pressure. These are Supercritical power plants. The operating pressures are in the range of 230 to 265 bar. The efficiency of the Rankine cycle depends on the pressure at which it operates. Higher pressure and temperature increase the efficiency of the thermal cycle and power plant. This is the reason for operating at higher steam pressures.
93
by using the relationship: the vortex shedding frequency is equal to the product of the Strouhal number and gas velocity divided by the tube outer diameter. There are many standard graphs available to calculate the velocity of sound in air at the temp at which the medium is flowing over the tube bundle. The maximum temperature of the medium is used to calculate this velocity. The sonic velocity can also be approximately computed from where T is the maximum temperature of the medium in degree R. Knowing the sonic velocity and the vortex shedding frequency will enable the calculation of the standing wave length by using the formula: wave length in ft is equal to sonic velocity in feet per second divided by the Strouhal frequency in Hz. Knowing the wave length, it is the practice to see that no cavity width is available 22 feet for /2 greater or equal to 22 feet and 11 feet for /2 less than 22 feet. It is to be ensured that no adjacent cavity is of the same width and will not be less than 2 feet. The anti-vibration baffles are fixed based on these computations to avoid flow induced vibration. The mechanical fixing of these baffles can be done in many ways depending upon the designers requirement. In coal fired boilers with higher ash content, it may be even worthwhile to wait for some time to see if these vibrations die down after a few months of operation and starts and stops.
Strouhal Number
94
Energy can neither be created nor destroyed First Law of Thermodynamics.... Mayer.
Renewables
Hydro turbines, the oldest and the most commonly used renewable energy source, have the highest efficient of all power conversion process. The potential head of water is available right next to the turbine, so there are no energy conversion losses, only the mechanical and copper losses in the turbine and generator and the tail end loss. The efficiency is in the range of 85 to 90 %. Wind turbines have an overall conversion efficiency of 30 % to 45 %. These two renewable sources, though efficient, are dependent on availability of the energy source. Solar thermal systems can achieve efficiency up to 20 %. The moving path of the sun and the weather conditions drastically alter the incident solar radiation. The efficiency on an annual basis, around 12 %, is considerably less than on a daily basis. Geo thermal systems, on the other hand, also use the Rankine cycle with steam temperatures at saturation point. Since there is no other conversion loss, this plant can achieve efficiencies in the range of 35 %.
95
Nuclear
The efficiency of nuclear plants is little different. On the steam turbine side they use the Rankine thermodynamic cycle with steam temperatures at saturated conditions. This gives a lower thermal cycle efficiency than the high temperature coal fired power plants. Thermal cycle efficiencies are in the range of 38 %. Since the energy release rate in nuclear fission is extremely high, the energy transferred to steam is a very small percentage - only around 0.7 %. This makes the overall plant efficiency only around 0.27 %. But one does not consider the fuel efficiency in nuclear power plants; fuel avaliabity and radiation losses take center stage
Diesel Engines
Diesel engines, large capacity industrial engines, deliver efficiencies in the range of 35 42 %. The power industry is trying to increase this conversion efficiency of power plants to maximise electricity generation and reduce environmental impact *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
Desuperheating system
96
Three major systems are adopted the world over: the injection type, the flue gas flow diverting type, and the burner tilt. The last two are adopted for reheater steam temperature control. The first one is adopted for superheater temperature control. It also used in reheaters during emergencies when there is a need to quench the temperature even after reaching the maximum of control on the normal system adopted. The material selection for the superheater before the injection will be greatly influenced by the quantity of injection.
Related Reading
How Long Term Overheating Tube Failures Happen in Boilers - Long term overheating tube failures are due to operating metal temperature of the boiler tubes going above the allowable limit. These types of failure are seen in steam cooled tubes like superheaters and reheaters and in water cooled tubes of waterwalls. Classification of Steam Boilers - Boiler classification can be based on many factors like usage, fuel fired, fuel firing system, type of arrangement etc. Commonly known types are pulverized coal fired boilers, fluidized bed boilers, super critical boilers, oil and gas fired boilers. All cater to industrial and power generation.
97
In the case of both FD fans tripping, the boiler will go for trip as the air supply to the fuel is cut off in full or excluding the primary air depending upon the system design. The PA fan also trip as soon as all the FD fans trip. Depending upon whether the boiler is for a process unit or power station, the action on the steam consumer end will vary.
98
Start FD fan Maintain purge conditions Complete purge Introduce furnace probe Light up boiler Open start-up vent valve or bring to service LP / HP bypass depending upon the consumer Quickly start PA fan / milling system and give steam to the consumer maintaining the required steam parameters Maintain steam parameters and load the boiler as consumption of steam increases Control the water level in drum Maintain furnace conditions Load to maximum load as required once all parameters stabilize
All the said actions are broad and for general understanding only. It is required to train and educate the operators for each design of the units. There are lot of changes taking place on the controls side and equipment design side. This brings in a need to understand the specifics of the system that is being handled.
Related Reading
Classification of Steam Boilers - Boiler classification can be based on many factors like usage, fuel fired, fuel firing system, type of arrangement etc. Commonly known types are pulverized coal fired boilers, fluidized bed boilers, super critical boilers, oil and gas fired boilers. All cater to industrial and power generation.
99
What is Lignite?
Wood and other vegetable matter decayed and transformed under pressure millions of years ago to form coal. Lignite has a Lower Rank in the coalification process, meaning this more recent than bituminous and anthracite coals.Called Brown Coal, vast reserves of lignite are available in limited areas of the world. Australia, US and China have the major reserve of Lignite. Germany leads the pack with the largest number of power plants burning Lignite. In US, most of the reserves are located in the North Dakota province. In India, the Lignite reserves are in Neyveli in the south and in Rajasthan.Low calorific value and resulting low cost is what makes it attractive. Because of the lower energy density, transportation is not attractive. Lignite power plants are located near to the mines.Around 17 % of the worlds coal reserves are lignite. As the worlds oil and gas reserves decline, other sources become attractive. That is why there is a sustained interest in the use of Lignite.
Characteristics of Lignite
Lignite has some special characteristics.These characteristics vary from mine to mine. The most important is that the calorific value is low. The calorific value ranges from 8000 kJ/kg to 15000 kJ/kg. Compare this to bituminous coal that has calorific value of 12000 to 20000 kJ/kg. Lignite has high moisture content in the range of 45 % to 55 %. The Volatile matter content is also high. On an ash and moisture, free basis the Volatile Matter percentage in the range of 45% to 55 %. High amounts of Sulphur especially in the form of Ferrous Sulphide FeS 2, reduce the ash fusion temperature to low levels like 900 C. This gives the coal high potential for slagging. The lignite is softer than bituminous coal, with a HGI in the range of One Hundred making it easier to pulverize.
These characteristics make Lignite burning different from burning bituminous coals. Germany with large number of Power plants burning Lignite is the forerunner in the technology for Lignite fired boilers.
Environmental Issues
Mining of Lignite also raises many environmental issues. Because of the lower Calorific value, the quantity of Coal required is high. This has a higher CO2 emission than plants firing bituminous coal. The overburden to coal ratio is higher than other types of coal. This results in destruction of agricultural land and displacement of people. Lignite mining involves the removal of enormous quantities of water. Depending on the quality of the water, it could be a boon for agriculture or an environmental issue.
Even with all the drawbacks, availability of large reserves of lignite makes it feasible to use this energy source effectively. Large capacity Lignite fired boilers in the 800 MW to 1100 MW range supercritical parameters are in service today
100
The Chimney
The stack in coal fired power plants can be tall in the range of 200 to 300 M. The height depends on the size of unit, local regulations, population densities, wind and other atmospheric conditions. A Kazakhstan stack at 420 M tall is reportedly the tallest in the world. The stack has an outer RCC shell and a steel inner lining for the flue gas path. The outer shell also sometimes called the windshield provides the strength. The inner lining protects the concrete layer from corrosive flue gases. Connection of multiple units to a single shell will have multiple inner flue gas liners.
A complicated system of jacks and radial screws makes this possible in the slip form method. Radial steel yokes, which have an inverted U at both ends, support the slip form shutters all around the shell. Walers strengthen and keep the shutters in place. The working deck and scaffolding is supported from the walers and yokes. The yokes are supported on hydraulic jacks, which move on jack rods embedded in the concrete. As the concrete pouring progresses the jacks lifts up the yokes, together with the decks and slip form. Screwed on pieces extend the jack rod as the work progresses. The entire system of decks and shutters appear as if floating on top of the stack. Radial screws adjust the diameter and the width of the pouring. Sufficient gap between the top of the yoke and the slip form allows installation of reinforcement steel. A laser alignment system allows the operator to control verticality and avoid twisting. Follow this link to a video on this method of construction. http://www.youtube.com/user/mmcg968#p/a/u/1/lxGvgQRX-o8
101
Construction of other vertical structures like silos and core structures in high-rise buildings also use this method.
Steam Power Plant Condenser Cooling 4: Hybrid Wet and Dry Cooling
The air cooled condenser is a low water use option used for steam power plant water cooling, but at a cost and performance penalty. Adding a small evaporative cooling component to make it hybrid wet and dry cooling, can eliminate most of the performance penalty with only slightly more water use.
Introduction
The air cooled condenser (also called a dry cooling tower) is seeing increased use for steam power plant condenser cooling because of increasing concern about the extent of power plant water usage for condenser cooling. Use of an air cooled condenser drastically reduces the rate of power plant water usage, but at the expense of increased capital cost, increased operating cost and a reduction in power production efficiency, especially in hot weather. An air cooled condenser with an added evaporative cooling component has come to be called a hybrid wet and dry cooling system. This combination provides the possibility of eliminating most of the efficiency penalty with only a small increase in power plant water usage.
102
Plume abatement, wet and dry systems are essentially a wet cooling tower that uses a small amount of dry cooling to dry out the cooling tower when the plume is most likely to be visible during cold, high-humidity days. This type of hybrid power plant water cooling system will reduce water consumption to some extent from the amount used by a strictly wet cooling tower, but the primary objective is plume abatement. The diagram at the left shows a system with a small air cooled condenser at the top of a wet cooling tower. The air cooled condenser would only be used during cold, high-humidity periods.
103
There are several configurations possible for a hybrid wet and dry cooling system that is intended for water conservation. There could be a single tower or separate wet and dry towers, using series or parallel airflow and series or parallel cooling water flow. The diagram at the left shows a hybrid cooling system with an
104
evaporative cooling tower and an air cooled condenser as separate structures. The air cooled condenser would handle all of the cooling load except for the hottest periods, when part of the cooling load would be handled by the wet cooling tower. Another option using a single tower with supplementary wet cooling available to be used as needed for hot weather is shown at the right. Some of the low capital cost alternatives include spraying water into the air cooled condenser or deluging the air cooled surface with water for short periods. Hybrid wet and dry cooling systems can reduce steam power plant water usage to 5% to 80% of that needed for a wet cooling tower, and still achieve substantial hot weather efficiency and capacity improvements over a steam power plant with a completely dry cooling system.
105
All these add to the cost of investment and operating the system. This also have an effect on the plant heat rate. This is what makes plant operators delay investment. However, penalties due to CO2 emissions may make this viable. This system can capture around 85% of the CO2 generated. To overcome the issue of cost, other processes and materials are under development. Some, which are promising and are in and advanced stage, are using special membrane filters and hyperbranched aluminosilica (HAS).
106
the combustion chamber contain CO2, Nitrogen and some unused Oxygen from the air. In a coal fired unit, typical values of flue gas will be CO2 12%, O2 around 3%, and the balance Nitrogen at 85%. (A typical natural gas fired gas turbine will have CO2 4%, O2 15% and N2 81%). Now the first task of the CCSS is to separate this 12% of CO2 from the flue gas so that it can go for storage. A 1000 MW coal fired unit produces 2500 tons of gas per hour. This is almost 300 tons per hour of CO2 separation. The task is enormous. There are two ways to capture the CO2.
107
Introduction
The condensing unit is a crucial part of a steam power plant water circulation system . The condenser must have cooling in order to convert low pressure steam leaving the turbine to liquid condensate that can be pumped into the boiler. The typical options for this cooling are cooling water that is discharged back to the source body of water at an elevated temperature (once through cooling), a wet cooling tower that provides evaporative cooling, an air cooled condenser (dry cooling), a hybrid wet/dry cooling system (primarily air cooled with evaporative cooling use as needed), or a cooling pond.
The part that the condensing unit plays in a Rankine cycle steam power plant is shown in the diagram at the left. High pressure steam from the boiler passes through the turbine, thus causing it to rotate and generate electricity. The low pressure steam leaving the turbine must be converted to liquid condensate that can be pumped into the boiler to keep the cycle going. The diagram shows the simplest type of cooling system, once through cooling, whereby cooling water is withdrawn, typically from a surface water body, with heated water from the condenser discharged back to the surface water body. This type of condenser cooling withdraws water from the source water body at a
108
very great rate. It returns almost all of that water to the source water body, but at an elevated temperature. This type of steam power plant water cooling system is used in most U.S. plants built before 1970. (Bistline, 2008)
from the source water body is the wet cooling tower. The diagram at the right shows the general flow patterns. The heated water leaving the condenser passes through a cooling tower and is cooled by evaporative cooling. This type of cooling system withdraws much less water from the source water body, but it consumes much more water than the once through system, due to evaporation into the atmosphere. This type of steam power plant water cooling system is used in many U.S. plants built since 1970. (Bistline, 2008)
109
Dry cooling, utilizing an air cooled condenser, is illustrated in the diagram at the left. The air cooled condenser, often referred to as 'dry cooling,' eliminates the need for steam power plant water use for cooling. There has been increasing interest in dry cooling/air cooled condenser use, because of increased concern about and regulation of water use for electric power production. The dry cooling option, however, comes at an increased initial cost, increased operating cost and increased heat rate (decreased efficiency), leading to increased cost for production of electricity. Recently hybrid wet/dry systems are being developed and put into use, with less cost and less efficiency penalty than strictly dry cooling.
110
The water consumption is about the same as for a wet cooling tower, because the cooling in the pond is primarily due to evaporation. Based on information from a Department of Energy Report, cooling ponds are used by about 15 % of U.S. electric steam power plant generating capacity as the primary method of cooling for their condensing unit. (DOE/NETL, 2008)
111
Introduction
Steam power plant water use has been coming under increasing scrutiny because of the large quantities of water involved and the many competing uses for water. The cooling options for the condensing unit (once through cooling, wet cooling tower, air cooled condenser, hybrid wet/dry cooling, and cooling pond) were introduced in the article: Steam Power Plant Cooling - Part 1: Introduction to Alternatives. Here the condenser/cooling options will be compared in terms of water withdrawal, water consumption, economics, and percentage of U.S. generating capacity using each option.
112
Three of the major options for steam power plant water cooling and the condenser are summarized in the diagrams in this section. There is a diagram for i) once through cooling, ii) wet cooling tower, and iii) air cooled condenser. When a cooling pond is used, it would simply replace the cooling tower shown in the second diagram. The fifth alternative, hybrid wet/dry cooling, would have an air cooled condenser and some features of a wet cooling tower system.
113
A comparison of typical water withdrawal rates and water consumption rates is given in the table at the left, for once-through cooling, cooling tower, and cooling pond systems, with fossil fueled and nuclear fueled steam power plants, based on information from a 2002 report of the Electric Power Research Institute (EPRI, 2002). (Click on the table to view a larger version.) Note that the water withdrawal rate for once through cooling is two orders of magnitude larger than that for pond or cooling tower systems. The withdrawal rate for pond and cooling tower systems is simply replacement for the water evaporation into the atmosphere. There are only small differences in the rate of water consumption for the three systems. Some sources show the rate of water consumption for once through cooling being much lower than in this table. EPRI (2002) estimates this rate as being only slightly lower than for a cooling tower or pond, based on increased evaporation from the source water body due to the heated water being discharged to it. No figures are shown for an air cooled condenser, because the power plant water use for an air cooled condenser is much less than for the three options shown in the table.
114
of four types of condenser/cooling systems, is shown in the table at the right. The information in the table came from a 2008 report of the Department of Energy, National Energy Technology Laboratory report (DOE/NETL, 2008). Most of the steam power plants built in the U.S. before 1970 use once through cooling. Due to increasing concern about and regulation of water use for electric power production, most of them built after 1970 use cooling towers. These two types of condenser cooling systems account for about 84 % of steam power plants. Most of the rest use cooling ponds. Dry cooling has emerged as another option because of the water withdrawal and consumption rates for the other options, even with wet cooling towers. About 1 % of steam power plants use an air-cooled condenser (dry cooling system).
Economic Comparison
115
There is a reason that once through cooling was used in almost all steam power plants built before 1970. It is the simplest system and has the least initial cost and least operating cost. Both the wet cooling tower system and the air cooled condenser (dry cooling) system have higher capital cost, higher power requirement (and thus higher operating cost), leading to approximately 1.9 % higher cost of electricity due to use of a wet cooling tower and approximately 4.9 % higher cost of electricity for air cooled condenser use, as shown in the table at the left. The information in the table came from a presentation at a California State Water Resources Control Board Workshop in 2005. (Maulbetsch, 2005). *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
Steam Power Plant Condenser Cooling Part 3: The Air Cooled Condenser
An air cooled condenser is an option for condensing steam if water availability is limited. The air cooled condenser, also known as a dry cooling tower, is seeing increased use as a steam power plant condenser. Steam power plant water usage is a concern due to increased water needs by other sectors.
Introduction
An air cooled condenser provides a means of condensing steam without using cooling water, when a lack of water prevents use of a traditional water cooled condenser in a steam power plant. There is increasing interest in use of the air cooled condenser, also called a dry cooling tower, for steam power plant water condensing due to competition from other sectors for use of scarce water resources. The general configuration and options for an air cooled condenser, how it is used for steam power plant water condensing, and an experimental method of improving its performance are discussed in this article.
116
in the picture at the left. The typical flow pattern of steam, air and condensate is shown in the diagram at the right. The low pressure steam exhausted from the turbine goes into the air cooled condenser in the large tube shown at the top of the A-frame in the picture. The steam flows down through finned tubes that make up the A-frame and is cooled and condensed by air being blown past the finned tubes by a fan or fans at the bottom. A natural draft air cooled condenser requires the familiar hyberbolic tower. The hyperbolic tower must be so large that this option is only used for quite small power plants. A mechanical draft air cooled condenser is used in over 90% of the world power plants with dry cooling.
117
The majority of the steam power plants in use today use once through cooling or a wet cooling tower for condenser cooling. Both of these systems require large amounts of water in comparison with a dry cooling tower (air cooled condenser) system, as discussed in the article, Steam Power Plant Condenser
Cooling - Part 2: Comparison of Alternatives. Flow diagrams are shown in this section for comparison with the air cooled condenser diagram in the previous section. There is increasing pressure to use the dry cooling tower / air cooled condenser option in new power plants because of the concern about and regulation of steam power plant water usage. A plant with an air cooled condenser uses only about 5% as much water as one with once through cooling or a wet cooling tower.
118
119
After treatment, the gas then passes through the CO2 extraction plant where the CO2 is separated and stored, ready for transport to a long term storage area. Following this process the zero CO2 syngas is piped to the gas turbines in the turbine hall.
120
121
Related Reading
Water Quality in High Pressure Boilers - The process for water treatment is decided dependent on the source of water of the power plant and its quality. The levels of water quality to be maintained depend upon the drum operating pressure.
122
Superheater Temperature Control in Boilers - Steam temperature control is carried out in all boilers to get a constant temperature within a range. Methods like desuperheating by water injection, flue gas flow diverting, burner tilting are few systems adopted. Main steam and reheat outlet temperature are controlled by these methods in boiler. How Long Term Overheating Tube Failures Happen in Boilers - Long term overheating tube failures are due to operating metal temperature of the boiler tubes going above the allowable limit. These types of failure are seen in steam cooled tubes like superheaters and reheaters and in water cooled tubes of waterwalls. Water injection in superheater and reheater of boiler is a common method adopted by boiler designers. Within designed limit spraying in superheater will not be harmful if the water quality is maintained and the nozzles of the desuperheater are not eroded. In large capacity boilers, the superheater and reheater temperature at the boiler outlet is controlled by many methods. Water spraying in both superheater and reheater is a very commonly adopted method. In using a spray water system, there are many points to be addressed as otherwise serious failures can result. The superheaters and reheater are sized in such a way that the full steam temperatures are achieved from 60 % boiler load. This means the steam temperature will be much higher than the rated steam temperature. Hence, to control this increase, water spraying is adopted. These desuperheaters are designed in such a way that the water is split into fine particles and allowed to mix with the steam, ensuring no water particles remain as it enters the superheater.
Related Reading
Water Quality in High Pressure Boilers - The process for water treatment is decided dependent on the source of water of the power plant and its quality. The levels of water quality to be maintained depend upon the drum operating pressure.
123
Superheater Temperature Control in Boilers - Steam temperature control is carried out in all boilers to get a constant temperature within a range. Methods like desuperheating by water injection, flue gas flow diverting, burner tilting are few systems adopted. Main steam and reheat outlet temperature are controlled by these methods in boiler. How Long Term Overheating Tube Failures Happen in Boilers - Long term overheating tube failures are due to operating metal temperature of the boiler tubes going above the allowable limit. These types of failure are seen in steam cooled tubes like superheaters and reheaters and in water cooled tubes of waterwalls.
124
o Look at the expansion guides at the drum floor for any abnormality o Look at the corner connections of the buckstays / furnace rap Watch and listen for any abnormal noise or steam leak noise at each location If steam leak detection system is provided in the boiler then take extra care to listen in areas where the frequency indicated is higher but lower than alarm level. Open the first peep hole from top available and watch for flame licking or high deposit on the tubes. Also look for any black particles on the ash deposited on the peep hole frame inside portion. o Note: Opening peep hole while boiler is under operation must be done carefully. Be on the door side of the peep hole and slowly open to see any positive pressure inside the furnace. Wait for a second or two to be sure of absence of furnace puffing. Never put you head and eyes too close to the peep hole. Always hold the door handle as you can close the door if you suspect any furnace pressurization. Each floor as you are coming down go round the furnace and note each corner connections, the valves for any leaks, any abnormal sound, any vibration, the flame condition and fluctuations, the deposition on walls and panels, the carbon particles on the peephole inside, note also if any bridging of the opening with slag note also if it is flowing or solid, look for any expansion restraint in each area. It will be a good practice to carry few small bags and a scope to collect the carbon particles seen and any deposit noticed. Care must be taken not to hurt you as these will be at a much higher temperature. When you are in the burner floor look at the various damper positions and correlate with the control room data and flame condition. Look for any oil leak in the start-up oil burners. Look for any ash leak from any area as you are coming down and note this location. After reaching the bottommost peephole (Normally at the bottom hoper level), open this and watch the deposit fall to the bottom hopper. Note the size, frequency, have an idea about the quantum, the brightness as it falls, is there any brightening and dimming in this location inside the furnace. All this will aid you to evaluate the flame and combustion behavior of the boiler. Further below look at the seal turf water level, any ash accumulation and overflow. Coming to the ground level look at the bottom ash for large clinkers, unburnt carbon, and watch the quantity too. o Note: This is possible only if it is a continuous evacuation system, however in water impounded hopper watch for these during evacuation
Related Reading
Classification of Steam Boilers - Boiler classification can be based on many factors like usage, fuel fired, fuel firing system, type of arrangement etc. Commonly known types are pulverized coal fired boilers, fluidized bed boilers, super critical boilers, oil and gas fired boilers. All cater to industrial and power generation. Coal Formation Theories - Coal may be defined as a compact stratified mass of plant debris which has been modified chemically and physically by natural agencies, interspersed with smaller amounts of inorganic matter. In situ and Drift are the two major theories of coal formation. Coal Analysis for Boiler Designers - Hydrocarbon fuels are the major source of energy for power and process steam generation, and coal takes a major share in this. Boiler furnace design will depend more on fuel characteristics, and further heat transfer surface sizing will depend on furnace outlet temperature.
125
Why Pulverizing ?
The basic requirement of coal combustion is that all the carbon particles in coal should get sufficient air to burn and release the heat. Coal normally is available to power plants in large lumps ranging from 2 mm to 50 mm size. Coal is commercially available in different sizes known as Run of Mine, stoker, slack, etc. depending on their size. In the olden days, coal burning was done on grates without any change in size or pulverizing. Because of the large size of coal, some of the carbon particles do not come in contact with the air. These unburned carbon particles go out with ash. This is a loss and could be in the range of 5 % or greater in the older grate-fired combustion. Modern boilers powder the coal to a very fine dust so that while burning, it is almost like a fluid stream. The size of the coal particles is in the range of 75 microns. This means every particle comes into contact with the air. The loss due to unburned carbon is only in the range of 0.5 % or less making the boilers very efficient. The pulverizer does the powdering or the pulverizing. Pulverizers come in different models and are a very important auxiliary of a power plant.
Grindability
There is one important characteristic of coal that decides the type, size, and power required for pulverizing. This is the grindability of coal and is denoted by the Hardgrove Grindability Index (or HGI). Grindability in general is a function of the grade of coal. Sub-bituminous coal from the Indian sub-continent has an index near fifty. A higher number indicates the coal is soft and easy to grind. Anthracitic coals, higher grade coals, have higher hardness and consequentially a lower Grindability Index in the range of forty or less.
126
Lignite, the lower grade of coal, on other hand is very soft and easy to pulverize and can have an index of a hundred and greater.
The Grindability Index decides what type of pulveriser to use and the power requirement for pulverizing. *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
Considerable investments in plant and technology together with social and political will are essential for this changeover.
127
This Carbon sequestration is a costly process, and we have to wait and see how much society will be willing to pay extra for it.
128
overheating failure near the transition point or at the transition point will need a very detailed review by the designers. The failed sample of the tube will have to be metallurgically evaluated for the reason of failure and the temperature to which the tube had been subjected. Related Reading How Long Term Overheating Tube Failures Happen in Boilers - Long term overheating tube failures are due to operating metal temperature of the boiler tubes going above the allowable limit. These types of failure are seen in steam cooled tubes like superheaters and reheaters and in water cooled tubes of waterwalls. Superheater Temperature Control in Boilers - Steam temperature control is carried out in all boilers to get a constant temperature within a range. Methods like desuperheating by water injection, flue gas flow diverting, and burner tilting are few systems adopted. Main steam and reheat outlet temperature are controlled by these methods in boiler. *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
129
A coal sampled at the mines having a moisture of 20%, after storage for a few weeks, when entering the boiler can have moisture of only 8%. If the Coal sampled at the mines has an HHV of 18800 kJ/kg the same coal at the boiler will have a higher HHV. This is because the percentage of combustibles in one kg is more. Based on a simple proportion calculation, multiplying by a factor [100-8]/ [100-20] the HHV will be 21620 kJ/kg. In real life, Coal analysis takes place in the laboratory. The coal is spread out and air-dried to remove most of the surface moisture. The Coal Analysis and Calorific Value is determined and reported as on Air Dried Basis (ADB). This ADB analysis is corrected to the actual conditions in the field to the extent of the difference in the moisture content. Since there is a lag between the sampling and the lab analysis, some moisture can evaporate. To avoid this error, coal is sampled in two parts. The first part kept in a sealed container and is used to determine only the Total Moisture (TMactual). The second part is used to find the ADB analysis. Moisture is also determined in the ADB analysis. (Madb)
The ADB analysis is corrected to the field conditions by using the Moisture content in the first sample. The HHV, the proximate analysis and the Ultimate analysis are all corrected by using the same factor. The correction factor is based on simple proportion accounting for the moisture difference.
VMactual = VMadb x [100 TMactual] / [100- Madb] Ashactual = Ashadb x [100 TMactual] / [100- Madb]
Often when comparing different coals it is a practice to take zero percentage Moisture as the reference (Moisture Free basis). All analysis values and HHV is corrected to this zero moisture. *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
130
human consumption and agriculture. Power plant requirements are only secondary. This necessitates the need for thermal power plants that require less water. Cooling Towers help by reusing the cooling water, making power plants economical and more environmentally friendly. Environmental regulations in most countries require that fresh water sources like lakes or rivers cannot be used anymore for an open cycle system. This makes using cooling towers the only option. Open cycle systems can only use seawater. Cooling towers can be of two types. First is the natural draft-cooling tower with a large hyperbolic tower, which pulls in air due to the stack effect. Even though the capital costs are high, operating costs are less.This is because there is no fan to create the air flow. However, most commonly used is the Mechanical or forced cooling tower. A fan forces or sucks air through the cooling tower where the water falls through a packed heat transfer media. Operating costs are high for operating this, but they are simple and quick for construction. o The fans can be induced fan or forced draught fan. o The airflow can be parallel or cross flow to the water flow.
Cooling towers work on the principle of psychometric properties of air. A part of the cooling water evaporates taking in Latent Heat from the water reducing its temeprature. A properly sized Cooling tower can cool the incoming water to temperatures up to 3 C more than the ambient wet bulb temperature. The relative humidity of the ambient air is an important deciding factor. This makes it very important that the location and direction of the towers is such as to prevent re-entrainment of the plume exiting the tower and interference from the adjacent towers. Wet air if it reenters the tower reduces the cooling capacity of the towers.
Biocides and chemical controls are required to eliminate bacterial growth and eliminate scales that are harmful and at the same time a performance reduction factor.
131
132
emission criteria do not include the formation of secondary particle by the sources, but in the future, these may also be part of the pollution *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
NFPA (National Fire Protection Association) and others have analyzed the causes of explosion and find that operator error (can be more clearly put as operator anxiety to save unit from trip) has contributed to about 47%,
133
insufficient purge about 39%, control failure 11%, and equipment failure 3%. The only way to avoid an explosion is to avoid the accumulation of fuel in the boiler *************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
Fuel Flexibility
The most important advantage of the CFB is the flexibility of firing a wide range of coal from 9500 to 25000 kJ/kg. CFBs can also burn a limitless number of other types of solid fuels, separately or mixed with coal. The limitations if any are only in the feeding and other mechanical equipment. The output capacity and steam parameters depend on the heating value of the fuel. CFB boiler can use different types of solid fuels that include low quality coal, lignites, coal blends, bagasse in sugar plants, bark in pulp and paper mills, coal washery rejects in mines, petcoke and other bio mass products. Most of these fuels are seasonal, production or availability dependent. Mixing with coal or using coal when other fuels are not available gives an uninterrupted steam and energy supply.
NOx Reduction
The combustion temperature in the furnace in a CFB boiler is considerably less than PC boilers resulting in lower NOx emissions. There is no additional requirement of separate NOx capturing devices which reduces capital investment.
Maintenance
Eliminating the pulverizer and pulverized coal piping reduces maintenance, related outages and equipment redundancy. A part of this saving is offset by higher maintenance due to erosion in pressure parts and furnace area, and maintenance of the refractory.
134
Auxiliary Power
Eliminating the pulveriser reduces power but is offset by increased power for higher quantity of primary air. Auxiliary power reduction by eliminating the FGD is a definite gain.
Limitations
Unit capacities with CFB technology are limited to 200 MW range. Higher capacities are in development. Higher steam pressures and temperatures increase the power plant cycle efficiency. CFB technology has yet to achieve the same level of parameters in the new large power plants.
*************************************************************************************************** *************************************************************************************************** *************************************************************************************************** ***************************************************************************************************
135
In CFB boiler limestone addition in the furnace reduces the Sulphur Dioxide during combustion itself. This requires only a simple limestone storage and handling unit. In PC boilers around 15 % of ash collects at the bottom of the furnace and the balance in the electrostatic precipitators. In CFB boilers the collection at the bottom is almost 50 % lessening the load on the Electroststic Precipitators. The water and steam circuit, the natural circulation of water and heat transfer surfaces are all the same in both the systems.
The diagrams below indicate the overall difference between the CFB boiler and the PC boiler systems.
136
Why water?
Why do we use water as the media for a hydrostatic test ? Water is the most easily available liquid. There are no environmental or toxic issues. There is another important reason. It is the compressibility or rather the incompressibility of water. Water is almost incompressible. For carrying out the hydrostatic test in large power plant boiler we require around 600 cubic metre of water. Since water is almost incompressible, to increase the pressure form atmospheric to 250 bar we require only an additional amount of one cubic meter of water. This is faster and requires much less effort. In case of the failure of any part the pressure also is reduced immediately preventing further damage.
Test Requirements
137
Ensure that all work is completed and documented. Connect a high pressure positive displacement pump (Hydrostatic pump) to the boiler. Fix a calibrated and accurate pressure gauge to the boiler. All valves and opening in the boiler are closed. Fill the boiler with water using a high capacity filling pump. During filing ensure removal of entrapped air by opening vents at the highest point in the boiler. Entrapped air will drastically increase the time taken to reach the test pressure. Running the hydrostatic test pump increases the boiler pressure gradually till the test pressure. Normally the test pressure is is 1.5 times the maximum allowable operating pressure. Close the pump discharge valves to lock the system pressure. The pressure in the boiler should maintain without dropping for at least 30 minutes. Bring down the pressure to the normal operating pressure and visually inspect for any signs leakages or wetting of the surfaces. Depending on the size and capacity of the boiler this may take a few hours. After the inspection reduce the pressure gradually to atmospheric and drain the boiler. Test is witnessed by inspection agencies or regulatory authorities, who then approves and certifies the test. Mandatory Hydrostatic tests done annually by regulatory authorities are a check on material degradation and ensure the continuous safety of the boiler. Hydrostatic tests are not only for boilers. Use the same methods to test any pressure vessel or piping that stores or transports pressurised media. This is a simple but very important test which all mechanical and process engineers should know about.
Efficiency
Energy conversion takes place in two stages.
138
The first part of the conversion is efficiency of the boiler and combustion. For this example we take 88 % on an HHV basis that is the normal range for a well-optimized power plant. Second part is the steam cycle efficiency. Modern Rankine cycle, adopted in coal fired power plants, have efficiencies that vary from 32 % to 42 %. This depends mainly on the steam parameters. Higher steam perssure and temperatures in the range of 600 C and 230 bar have efficiencies around 42 %. We assume a value of 38 % for our case. The overall conversion efficiency then is (38% x 88%) 33.44 %.
Heat Rate
Heat rate is the heat input required to produce one unit of electricity. (1 kw hr) One Kw is 3600 kJ/hr. If the energy conversion is 100 % efficient then to produce one unit of electricity we require 3600 kJ. After considering the conversion efficiency in a power plant we require an heat input of (3600 / 33.44% ) 10765 kJ/ kw hr.
Coal Quantity
Since coal has a heat value of 20,000 kJ/kg, for producing one kw.hr we require (10765 / 20000) 0.538 kg of coal. This translates to (0.538 x 100 x 1,000) 53800 kg/hr (53.8 T/hr) of coal for an output of 100 MW.
Coal Cost
Basic cost of coal depends on the market conditions. Transportation costs, regional influences and government taxes are also part of the cost. Coal traders web sites give base prices in the international market. We take a coal price of around 65 $ / Ton. The cost of coal consumed by 100 MW power plant is (53.8 x 65) 3497 $ /hr A 100 MW unit produces 100,000 units of electricity. So the cost of coal per unit of electricity is (3497/100,000) 3.5 cents per unit.
139