Documente Academic
Documente Profesional
Documente Cultură
The building comprises two floors with six classrooms on each. The ground floor is
complete and work on the first floor is on-going. A physical inspection was carried out on
all structural elements (columns, beams, suspended slab/cantilever, stairs and
blockwork cladding). Information on elements like the column pad foundations which
have since been complete, were obtained from the Contractor. Generally, the design and
construction are sound and workmanship has been good.
Suspended slab, cantilever & stairs: These have been properly built and exhibit no
signs of defect. The slab is 150mm thick and is reinforced with 10mm diameter high yield
steel bars at 150mm centres, each way. There is no sagging or deflection and the
elements were constructed to proper lines and levels.
GENERAL OBSERVATIONS:
The site is well organised and the contractor is doing a good job. The defective cracks
are mainly due to lack of finishing skills on the part of the workforce.
RECOMMENDATIONS:
1. Contractor to be sending out samples of concrete and blockwork to materials
laboratories (at DTS, GTTI or CSE) for strength testing.
2. Import skilled labour from Senegal to complete the plasterwork although this is
not crucial unless the client is really concerned with having a near perfect finish.
SIGNED..............................................................................
Bevan Mendy (Civil/Structural Engineer)