Price List

Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:

O - Labour Rates
JADUAL KADAR HARGA UPAH BURUH 2002

0.00

O001 O001A O001B O002 O003 O004 O005 O006 O007 O008 O009 O010 O011 O012 O013 O014 O015 O016 O017 O018 O019 O020 O021

Labourer (Unskilled) Semi-skilled labour Skilled labour Drainlayer Concrete Leveller and Screeder Mason Bricklayer Carpenter and Joiner Steel Barbender and Fixer Pneumatic Tool Operator Fitter Welder Plumber Painter Roofer Glazier Ironworker Pavior/Plasterer Tile Fixer Watchman Labour (Skilled) Pipelayer Fence Fixer

Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day

45.00 70.00 100.00 60.00 65.00 65.00 65.00 65.00 65.00 65.00 70.00 70.00 65.00 60.00 65.00 65.00 70.00 65.00 70.00 50.00 65.00 60.00 60.00

05/07/2005 26/04/2011 26/04/2011 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005 05/07/2005

O022 O023 O024 O025 O026 O027 O028

Labour to erect formwork Labour to cut, bend & fix steel bar Labour to cast concrete Labour to lay bricks; 115 mm thick Labour to install lintol 100m x 100mm Labour to lay damp proof course, 230mm wide Labour to lay cement & sand acreed to floor; 25mm thick, steel trowel Labour to plaster wall; cement & sand; 28mm thick; 3 coats; external
1

m2 tonne m3 m2 m m m2 m2

22.00 550.00 35.00 8.50 9.00 0.30 5.50 12.50

26/04/2011 26/04/2011 26/04/2011 26/04/2011 26/04/2011 26/04/2011 26/04/2011

O029

26/04/2011

CHEW FU KEONG

Page :

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O030

O - Labour Rates

(Continued)

O031 O032 O033

Labour to plaster wall; cement & sand; 28mm thick; 3 coats; internall Labour to lay tiles; homogeneous Labour to fix corner beading Labour to install timber door frame for single leaf door including sub-frame Labour to install timber door frame for double leaf door including sub-frame Labour to install timber door; single leaf Labour to install timber door; double leaves

m2 m2 m no no no no

8.50 16.00 2.30 36.00 39.00 50.00 70.00

26/04/2011

26/04/2011 26/04/2011 26/04/2011

O034

26/04/2011

O035 O036

26/04/2011 26/04/2011

Skilled And General Workers


O037 O038 O039 O040 O041 O042 O043 O044 O045 O046 O047 O048 O049 O050 O051 O052 O053 O054 O055 O056 O057 O058 O059 O060 O061

Concretor Concretor 'Kepala' Steel bar bender & fixer Bar bedber 'Kepala' Formwork carpenter Formwork carpenter 'Kepala' Bricklayer Bricklayer 'Kepala' Blocklayer Blocklayer 'Kepala' Roofer Roofer 'Kepala' Joinery carpenter Joinery carpenter 'Kepala' Structural steel worker Structural steel worker 'Kepala' Welder Welder 'Kepala' Plumber Plumber 'Kepala' Plasterer Plasterer 'Kepala' Tiler Tiler 'Kepala' Painter

day day day day day day day day day day day day day day day day day day day day day day day day day

50.00 62.00 53.00 66.00 54.00 68.00 52.00 65.00 57.00 71.00 55.00 71.00 57.00 82.00 65.00 94.00 71.00 101.00 61.00 83.00 57.00 75.00 61.00 85.00 55.00

18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008 18/12/2008

CHEW FU KEONG

Page :

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O062 O063 O064

O - Labour Rates

(Continued)

Painter 'Kepala' General worker (Male) General worker (Female)

day day day

70.00 40.00 35.00

18/12/2008 18/12/2008 18/12/2008

Piling
OO01 OO01A O065 O066 OO02 O067 O068 OO03

Sheet pile Handle, pitch and drive

FSP 3A, 12m lenght FSP 3A, 9m lenght


Extracting

pcs pcs

80.00 70.00

16/12/2008 05/11/2008

FSP 3A, 12m lenght FSP 3A, 9m lenght


600mm diameter pretensioned spun concrete pile Allow for the provision of all necessary injection piling equipment, plant, tools and ancillary equipment (for the execution of all piling work in this contract) and for their transportation to site handling, assembling, erecting, dismantling and removal on completion of the work for any idle standing time Allow for moving and handling piling equiment, plant, tools, and ancillary equipment about the site as often and whenever necessary for the execution of the whole piling operation (as covered under this contract) including any excavation and filling required for moving the plant, tools and ancillary equipment from differing places and levels of the site, erection of any staging required and dismantling and removal on completion. Handle, transport and pitch 600mm Diameter spun pile; 12.00m long Drive only by injection method 600mm Diameter spun pile; 12.00m long (In No. 766) 12.70mm (overall) Butt weld connection 1884mm girth between edges of mild steel extension head and base cap plates including coated heavily with bituminous compound. Cut off 600mm diameter pre-tensionedspun concrete pile to be required level and roughen the inner surface to detail. Allow for Pile Dynamic Analysis (PDA) test and submission of analysis. 500mm diameter prestressed spun concrete pile

pcs pcs

70.00 60.00

05/11/2008 05/11/2008

O069

Item

42,250.00

04/03/2009

O070

Item

9,833.33

04/03/2009

O071

No M No

44.00 45.67 58.00

04/03/2009

O072

04/03/2009

O073

04/03/2009

O074

No

59.25

04/03/2009

O075

No

1,700.00

04/03/2009

OO04

CHEW FU KEONG

Page :

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O076

O - Labour Rates

(Continued)

O077

O078

O079 O080 O081 O082

Allow for mobilisation of labour, plants and hydraulic hammer piling equipment to site, moving around and demobilisation from site Handle, sling and pitch initial and extension vertical piles not exceeding 12m long Handle, sling and pitch initial and extension raked 1:4 piles not exceeding 12m long Drive vertical pile to the required depth Drive raked 1:4 piles to the required depth Fillet weld vertical extension pile joints Cut off piles to the required level and roughen inner surface of pile Provide labours, plants, temporary staging, kentledge, testing equipment and load 500mm diameter test pile to 1200KN Subsequent load test
350mm diameter prestressed spun concrete pile Allow for mobilisation of labour, plants and hydraulic hammer piling equipment to site, moving around and demobilisation from site Handle, transport and pitch initial and extension pile not exceeding 12m long Drive initial and extension pile to the required depth Fillet weld pile joint

Item

18,000.00

16/12/2008

no no m m no no no

64.00 80.00 45.00 60.00 97.50 120.00 15,000.00

16/12/2008

16/12/2008

16/12/2008 16/12/2008 16/12/2008 16/12/2008

O083

10/12/2008

O084 OO05

no

10,000.00

10/12/2008

O085

Item

14,666.67

23/12/2008

O086

no m no no

33.20 13.93 36.00 39.00

23/12/2008

O087

23/12/2008

O088 O089

23/12/2008 23/12/2008

O090 O091

Cut off pile head, strip concrete and exposed reinforcement to a length of 600mm including bending and binding exposed reinforced rods to the reinforcement in the pile cap Supply and fix 'concrete plug' Provide all equipments, hydraulic jack, deflection gauge, kentledge and other related items for initial load testing to a vertical load of 130 ton or 1300KN Subsequent load test
300mm diameter prestressed spun concrete pile Allow for mobilisation of labour, plants and jacked -in piling equipment to site, moving around and demobilisation from site Handle, transport, pitch and drive initial and extension pile to the required depth Fillet weld pile joint

no no

70.00 13,333.33

23/12/2008 23/12/2008

O092 OO06

no

6,933.33

23/12/2008

O093

Item

40,000.00

23/12/2008

O094

m no no

40.00 27.67 37.50

23/12/2008

O095 O096

23/12/2008 23/12/2008

O097

Cut off and remove surplus length and strip off pile head, bend back reinforcement for connection Initial pile test to 1100KN

no

14,500.00

23/12/2008

CHEW FU KEONG

Page :

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O098 O099 OO07 O100

O - Labour Rates

(Continued)

Subsequent load test PDA test


350 x 350mm R.C Pile

no no

7,166.67 1,450.00

23/12/2008 23/12/2008

O101

O102 O103

Allow for the provision of necessary hydraulic hammer piling equipment, plant and tools and for their transportation to the site, handling, assembling and removal after the completion of operation Allow for moving and handling piling equipment about the site Allow for submission of records of all piles Allow for the provision of necessary testing equipment, plant and tools and for their transportation to the site, handling, assembling and removal after completion including all idling and standing time Handle, transport, pitch and drive initial and extension pile to the required depth Fillet weld pile joint Cut off pile head to required level, strip off concrete to expose reinforcement, bend the pile reinforcement excess length to dispose to Contractor's own dump site Initial pile test to twice working load of 1500KN Subsequent load test PDA test including preparation of pile head, submission of test report 300 x 300mm R.C Pile Mobilisation & Demobilisation of hydraulic hammer piling frame and equipment Moving and handling piling equipment, plant and tools about the site As built survey Submission of piling record Handle, transport and pitch only, 12m long initial/extension pile Drive only initial/extension pile Filler weld pile joint Cut off pile head and cart away surplus length from site Preliminary load test 2 x 1000KN PDA test
250 250mm R.C Pile

Item

15,000.00

19/02/2009

Item Item Item

3,000.00 3,700.00 4,750.00

19/02/2009

19/02/2009 19/02/2009

O104

m no no

16.50 34.00 35.80

19/02/2009

O105 O106

19/02/2009 19/02/2009

O107 O108 O109

no no no

29,030.00 18,720.00 960.00

19/02/2009 19/02/2009 19/02/2009

OO08 O110

Item Item Item Item no m no no no no

13,666.67 4,000.00 4,000.00 1,500.00 43.00 14.50 30.00 35.00 14,166.67 1,333.33

16/12/2008

O111

16/12/2008

O112 O113 O114

16/12/2008 16/12/2008 16/12/2008

O115 O116 O117

16/12/2008 16/12/2008 16/12/2008

O118 O119 OO09

16/12/2008 16/12/2008

CHEW FU KEONG

Page :

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O120

O - Labour Rates

(Continued)

O121

O122 O123

Allow for moving and handling jacked-in piling equipment, plants, tools at the site as often and whenever necessary for the operation of the whole piling operation including for moving the plants, tools and ancillary equipment from different levels of the site and all necessary staging, platform and any idling standing time. Handle, transport, pitch and drive initial and extension pile to the required depth Fillet weld pile joint Cut off and remove surplus length and strip off pile head, bend back reinforcement for connection Initial load test to 660KN Subsequent load test PDA test
200 x 200mm R.C pile

no

42,500.00

23/12/2008

m no no

29.50 22.75 29.50

23/12/2008

23/12/2008 23/12/2008

O124 O125 O126 OO10 O127

no no no

10,350.00 8,750.00 1,187.50

23/12/2008 23/12/2008 23/12/2008

O128 O129 O130

Handle, transport and pitch, 6m long initial/extension pile Drive initial/extension pile to the required depth Fillet weld pile joint Cut off pile head and cart away surplus length from site 150 x 150mm R.C pile Allow for the provision of necessary hydraulic hammer piling equipment, plant and tools and for their transportation to the site, handling, assembling and removal after the completion of operation Allow for moving and handling piling equipment about the site Allow for submission of records of all piles Allow for the provision of necessary testing equipment, plant and tools and for their transportation to the site, handling, assembling and removal after completion including all idling and standing time Handle, transport, pitch and drive initial and extension pile to the required depth Fillet weld pile joint Cut off pile head to required level, strip off concrete to expose reinforcement, bend the pile reinforcement, excess length to dispose to Contractor own dump site Subsequent load test to twice working load of 400KN

no m no no

9.00 4.50 8.00

16/12/2008

16/12/2008 16/12/2008

OO11 O131

Item

4,500.00

19/02/2009

O132

Item Item Item

1,000.00 2,000.00 10,000.00

02/01/2009

O133 O134

02/01/2009 02/01/2009

O135

m no no

4.38 8.83 16.83

19/02/2009

O136 O137

19/02/2009 19/02/2009

O138

no

5,250.00

19/02/2009

CHEW FU KEONG

Page :

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O139

O - Labour Rates

(Continued)

PDA test including preparation of pile head, submission of test report


Concretor

no

958.33

19/02/2009

O140 O141 OO12

Concretor Lean Concrete


Lean concrete, 50mm thick including necessary trimming base of excavation To underside of pile cap, footing, ground beam, apron slab, ground floor slab, trench beam, trench slab, pit slab and the like Reinforced concrete including vibrating and trowelling to a smooth and uniform level in Pile cap, footing, column stump, ground beam, trench beam and lift pit Column

m3 m3

16.00 16.00

13/02/2009 26/02/2009 03/12/2008

O142

m2

1.50

17/02/2009

OO13

O143

m3 m3 m3 m3 m3 m3 m3 m3

19.00 20.00 21.00 20.00 19.00 19.00 19.00 20.00

03/12/2008

O144 O145 O146 O147 O148

03/12/2008 03/12/2008 03/12/2008 03/12/2008 03/12/2008

Stiffener and lintol Roof beam 150mm thick ground floor slab and apron slab 150mm thick suspended floor slab and suspended floor beam 150mm thick roof slab 200mm thick wall

O149 O150

03/12/2008 03/12/2008

Bar Bender
O151 O152 OO14

Bar-Bender Fabric BRC


Rods, 12mm, 16mm, 20mm, 25mm, 32mm and 40mm diameter In foundation

tonne m2

330.00 1.35

13/02/2009 24/10/2008

O153 O154 O155 O156 OO15 O157 OO16 O158

kg kg kg kg

0.33 0.33 0.33 0.33

03/12/2008 03/12/2008 03/12/2008 03/12/2008

In column In beam In wall


Strirrups and Links

6mm, 10mm and 12mm diameter


BRC Fabric

kg

0.33

03/12/2008

In ground floor slab, apron slab, trench slab, suspended floor slab and roof slab
Formwork

m2

1.30

03/12/2008

O158A

Formwork
Page :

m2
7
of

13.00

13/02/2009

CHEW FU KEONG

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
OO17

O - Labour Rates
Timber formwork fabrication, fixing and striking not exceeding 3.50m high To sides of pile cap, footing, column stump, ground beam, trench beam and lift pit To sides of column and stiffener

(Continued)

O159

m2 m2 m2 m2 m2

13.00 13.00 13.00 13.00 13.00

03/12/2008

O160 O161

03/12/2008 03/12/2008

O162 O163

To sides and soffits of suspended floor beam and roof beam To sides and soffits of suspended floor slab To sloping soffit of staircase

03/12/2008 03/12/2008

Precast prestressed hollow core slab, plank and precast beam Installation & Grouting Works
OO18

O164

O165

O166 O167 O168 O169 O170 O171 O172 O173 O174 O175 OO19

Installation (Labour Only NOT inclusive cranage) Hollow core slabs & planks in thickness 300mm & below Hollow core slabs & planks in thickness 300mm & above Hollow core slabs & planks in thickness 325mm

m2 m2 m2 m2 no no no no no no no no

3.43 5.00 3.80 4.60 103.13 178.00 152.50 200.00 108.80 132.00 100.00 132.00

26/02/2009

26/02/2009

26/02/2009 26/02/2009 26/02/2009 26/02/2009 26/02/2009 26/02/2009 26/02/2009 17/02/2009 31/12/2008 26/02/2009

Hollow core slabs & planks in thickness 360mm Precast beams, L < 10m Precast beams, 10m < L < 15m Precast column, 1 tier in one length Precast column, 2 tiers in one length Precast staircase flight Precast landing slab Precast wall, 2400 x 1800 x 150mm thick Precast wall, 2250 x 1800 x 150mm thick
Grouting Works to Precast System (Labour & Materials) Grouting to beam dowels connection

O176 O177

no no no

52.56 104.99 102.74

26/02/2009 26/02/2009

O178

OO20

O179 O180 O181 O182

Grouting to beam & column gap including formwork Grouting to BSF connection gap including formwork Grouting to HCS/Plank shearkey joint (E.mix) to AV5 - 265 EV4-325 EV4-460 Plank 110

26/02/2009

m m m m

9.13 14.30 19.60 5.90

26/02/2009 26/02/2009 26/02/2009 17/02/2009

CHEW FU KEONG

Page :

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O183 OO21

O - Labour Rates

(Continued)

WV6 - 205
Grouting to column base, 50mm in gap in between; column to pile cap & column to column 500 x 500mm

5.00

31/12/2008

O184 O185 O186 O187 OO22 O188 O189 O190 OO23

no no no no

97.90 100.10 68.33 82.50

26/02/2009 17/02/2009 26/02/2009 17/02/2009

450 x 600mm 300 x 700mm 300 x 300mm


Grouting to column corrugated connection

4 dowels (300 x 300) 6 dowels 8 dowels (500 x 500)


Grouting to column corrugated connection at beam top rebar 2 tiers

no no no

138.60 156.25 278.30

17/02/2009 26/02/2009 26/02/2009

O191 O192 O193 O194 OO24 O195 O196 O197 O198 O199 O200

no no no no

55.00 121.00 121.00 69.75

17/02/2009 17/02/2009 17/02/2009 26/02/2009

Grouting to staircase flight Grouting to landing slab Grouting to wall


Associated Works On Site

Concrete G30 to topping, 75mm thick Concrete G40 to beam infill & beam top Concrete G40 to beam-column junction Rebar to beam top, span & support Rebar to topping, EB/PB RD6 mesh to topping, 4.44kg/m2, measure nett, allow lap in rate Formwork to underside of hcs at perimeter beam end Formwork to edge of topping

m3 m3 m3 kg kg m2 m m

310.00 340.00 340.00 3.25 3.25 13.00 18.00 18.00

17/02/2009 31/12/2008 31/12/2008 17/02/2009 17/02/2009 17/02/2009

O201

31/12/2008

O202

31/12/2008

Bricklayer
O203 O204 OO25 O205 OO26 O206 OO27

Bricklayer Hoisting brick


Lay cement and sand brick

pcs pcs

0.15 0.02

24/10/2008 15/11/2008

110mm thick wall


Lay clay brick

m2

8.05

03/12/2008

115mm thick wall


Lay hollow concrete block

m2

8.05

03/12/2008

CHEW FU KEONG

Page :

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O207

O - Labour Rates

(Continued)

200mm thick wall

m2

8.50

13/01/2009

Plasterer
O208 O209 OO28

External Internal
Plaster including mortar mixer, wheel barrow and trowelling tools and erection of working platform to a working height of not more than 3.0m high 19mm thick with wood float or sponge finish in two (2) coats Brickwall and concrete surface; externally 19mm thick with steel trowelled finish in two (2) coats Brickwall and concrete surface; internally

m2 m2

7.53 6.99

13/02/2009 13/02/2009

OO29

O210 OO30

m2

8.00

04/12/2008

O211

m2

7.00

04/12/2008

Door
O212 O213 O214 OO31 O215 O216 OO32 O217 O218 OO33 O219 O220 OO34 O221 O222 OO35 O223 O224 OO36 O225 O226

Lintol Small Lintol Big Lintol Arch


Timber/Metal Frame

no no no

5.00 15.00 100.00

27/11/2008 27/11/2008 27/11/2008

Door Frame, SL Door Frame, DL


Timber window frame fixing

no no

10.00 15.00

24/10/2008 24/10/2008

Overall size 300mm x 300mm high Overall size 1200mm x 1200mm high
Timber door frame fixing

no no

10.00 13.00

04/12/2008 04/12/2008

Overall size 900mm x 2100mm high Overall size 1800mm x 2100mm high
Metal door frame fixing

no no

13.00 19.00

04/12/2008 04/12/2008

Overall size 900mm x 2100mm high Overall size 1800mm x 2100mm high
Timber Leaf Including Ironmongery

no no

13.00 19.00

04/12/2008 04/12/2008

Door Leaf including ironmongery, SL Door Leaf including ironmongery, DL


Fire Leaf Including Ironmongery

no no

15.00 30.00

24/10/2008 24/10/2008

Door Leaf including ironmongery, SL Door Leaf including ironmongery, DL

no no

40.00 80.00

24/10/2008 24/10/2008

CHEW FU KEONG

Page :

10

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
OO37 O227 O228 OO38 O229 OO39

O - Labour Rates
Partition Leaf Including Ironmongery

(Continued)

Door Leaf including ironmongery, SL Door Leaf including ironmongery, DL


PVC Leaf

no no

10.00 20.00

24/10/2008 24/10/2008

Door Leaf, SL
Timber hollow core door fixing with hinges and normal/standard lockset Standard hollow core flush door faced both sides with plywood; overall size 900mm x 2100mm high x 40mm thick Standard double leaf hollow core flush door faced both sides with plywood; overall size 1800mm x 2100mm high x 40mm thick Timber solid core door fixing with hinges and normal/standard lockset Standard solid core flush door faced both sides with plywood; overall size 900mm x 2100mm high x 42mm thick Standard double leaf solid core flush door faced both sides with plywood; overall size 1800mm x 2100mm high x 42mm thick Timber fire door fixing with hinges and normal/standard lockset Standard one (1) hour fire-rated door; overall size 1070mm x 2100mm high x 50mm thick Standard double leaf one (1) hour fire-rated door; overall size 1800mm x 2100mm high x 50mm thick Ironmongery fixing

no

7.00

27/11/2008

O230

no

17.00

04/12/2008

O231

pair

28.00

04/12/2008

OO40

O232

no

30.00

04/12/2008

O233

pair

54.00

04/12/2008

OO41

O234

no pair

42.00 74.00

04/12/2008

O235

04/12/2008

OO42 O236 O237

Door closer Lockset

no no

9.00 5.00

04/12/2008 18/02/2009

Pavior
OO43 O238 O239 OO44 O240

Mason

Rendering, 25mm thick Rendering, 50mm thick


To floor

m2 m2

5.38 5.92

13/02/2009 13/02/2009

O241

25mm thick cement and sand render with steel trowelled finish to a smooth and level surface 20mm thick cement and sand base screed with steel trowelled finish to a smooth and level surface to receive finishing
Tiling

m2 m2

5.40 5.40

04/12/2008

04/12/2008

CHEW FU KEONG

Page :

11

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
OO45

O - Labour Rates
Wall tile including preparation and laying of cement and sand backing screed To wall

(Continued)

OO46 O242 O243 O244 OO47

200mm x 200mm ceramic tile 450mm x 450mm granite slab 450mm x 450mm marble slab
Floor tile including preparation and laying of cement and sand backing screed To floor

m2 m2 m2

17.00 54.00 43.00

04/12/2008 04/12/2008 04/12/2008

OO48 O245 O246 O247 O248 OO49 O249 O250 O251 O252 O253 O254 O255 O256 O257

300mm x 300mm ceramic tile 300mm x 300mm homogeneous tile 600mm x 600mm granite slab 600mm x 600mm marble slab
Wall & Floor Finishes

m2 m2 m2 m2

17.00 17.50 48.00 43.00

04/12/2008 04/12/2008 04/12/2008 04/12/2008

Power float Wall tile Floor tile Skirting Wall tile menara TM Melaka Floor tile Menara TM Melaka Floor tile skirting Menara TM Melaka Carpet tile Carpet roll

m2 m2 m2 m m2 m2 m m2 m2

3.60 17.22 17.76 5.25 34.43 34.43 2.40 9.70 14.00

24/10/2008 06/01/2009 06/01/2009 06/01/2009 24/10/2008 24/10/2008 24/10/2008 26/11/2008 26/11/2008

Roofer
OO50

OO51 O258 OO52 O259 OO53 O260 OO54 O261 O262 OO55

Structural steelwork fabrication, erection and fixing including cranage Heavy section

Universal beam and universal column


Hollow section

kg

0.90

04/12/2008

Square, rectangular and circular hollow sections


Attached connection

kg

1.00

04/12/2008

Cleats, stiffeners and plates and the like


Roof truss

kg

0.90

04/12/2008

Up to 10.0m span Above 10.0m span


Roofer

kg kg

0.90 0.90

04/12/2008 04/12/2008

CHEW FU KEONG

Page :

12

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O263 O264 O265 O266 O267 O268

O - Labour Rates

(Continued)

Lay aluminium foil Lay chicken wire netting Fix fascia board Fix valley gutter Lay concrete roof tile Lay concrete roof tile to pitch not exceeding 30 degree Lay metal deck to pitch not exceeding 30 degree Lay 50mm thick fibre wool insulation & wire mesh netting to slope Lay sisalation to slope

m2 m2 m m pc m2 m2 m2 m2

2.38 1.81 6.29 5.58 0.50 6.00 5.00 1.50 1.00

29/10/2008 26/04/2008 26/04/2008 18/02/2009 24/10/2008 03/12/2008

O269 O270

03/12/2008 03/12/2008

O271

03/12/2008

Ceiling Installer
O272 O273 OO56

Ceiling board and frame Skim coat


Ceiling framing & finishing fixing non-suspended ceiling 1200mm x 600mm x 3.2mm thick ceiling board

m2 m2

6.50 2.00

13/02/2009 24/10/2008

O274 O275

m2 m2

6.00 6.50

04/12/2008 04/12/2008

1200mm x 600mm x 4.5mm thick ceiling board

Sanitary
O276 O277 O278 O279 O280 O281 O282 O283 O284 O285

Squatting w.c complete set Closed coupled sitting w.c complete set Table top wash basin complete set Wall hung handicap wash basin complete set Sink Urinal Wall mounted pillar tap Hand bidet with flexible hose complete set Surface mounted stainless steel paper holder Stainless steel vertical liquid soap dispenser complete set Single robe hook with door stopper Stainless steel floor trap complete with insect cage, size 150mm x 150mm 40mm diameter stainless steel grab rail for OKU

no no no no no no no no no no no no no

52.50 52.50 42.50 45.00 40.00 50.00 15.00 20.00 15.00 25.00 15.00 10.00 35.00

02/01/2009 02/01/2009 02/01/2009 24/12/2008 02/01/2009 02/01/2009 24/12/2008 24/12/2008 24/12/2008 24/12/2008

O286 O287

24/12/2008 24/12/2008

O288

24/12/2008

CHEW FU KEONG

Page :

13

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O289

O - Labour Rates

(Continued)

On completion of the installation of sanitary fittings, test all fittings, make good any defects and leave in perfect working order to the entire satisfaction of the Architect
WATER TANK

Item

500.00

24/12/2008

OO57

O290

O291

Approved FRP water storage tank square type as described complete with cover and all necessary fixing accessories 3520 Gallons; Ditto; overall size 4000mm x 2000mm x 2000mm high approximately 20m above ground level 2200 Gallons; Ditto; overall size 5000mm x 2000mm x 1000mm high approximately 600mm above ground level

No

400.00

02/03/2009

No

340.00

02/03/2009

Scaffolder
O292

O293

O294

O295

O296

O297

O298

O299

O300

O301

Erect frame including cross braces, base plate and joint pin Dismantle frame, cross braces, base plate & joint pin including stacking up properly directed on site Fix 6.0m g.i pipe bracing including all accessories and coupler Dismantle 6.0m g.i pipe bracing & accessories and coupler including stacking up properly as directed on site Fix 3.0m g.i pipe bracing including all accessories and coupler Dismantle 3.0m g.i pipe bracing & accessories and coupler including stacking up properly as directed on site Fix wall tie including drilling hole for anchor bolt (bolt by Main Contractor) Dismantle wall tie including making good bolt hole Fix netting size 6'0"x17'0" including tying in position by wires Dismantle netting including rolling up properly and return to store as directed
Drainage

frame frame

6.00 3.00

27/11/2008

27/11/2008

no no

6.00 4.00

27/11/2008

27/11/2008

no no

3.00 2.00

27/11/2008

27/11/2008

no no pc pc

4.00 2.00 10.00 6.00

27/11/2008

27/11/2008

27/11/2008

27/11/2008

OO58 O302 O303 O304 O305

Surface Water

Concrete base & P.C half round drain 230mm thick brickwall & plastering R.C Strut Brickwall sump including R.C base

m m2 no no

18.00 23.50 10.00 150.00

27/11/2008 27/11/2008 27/11/2008 27/11/2008

CHEW FU KEONG

Page :

14

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H

Price List
Ref Code Item Description Unit Rate Mark Up % Supp Code

Name : PCK1

Last Updated

Trade Heading:
O306 O307 O308 OO59 O309 O310 OO60 O311

O - Labour Rates

(Continued)

600mm diameter pipe culvert 225mm SGW pipe Precast road kerb
Rain Water Down Pipe

m no no

75.00 5.00 5.00

27/11/2008 27/11/2008 27/11/2008

100mm diameter 150mm diameter


Gutter

m m

10.66 10.66

23/12/2008 23/12/2008

Galvanised iron

18.05

23/12/2008

Road furniture
O312

Install single beam highway guardrail

8.50

10/12/2008

CHEW FU KEONG

Page :

15

of

15

Date of Printing: 21/Jul/11 Global Estimating System (32 Bit) - H