Alistair.Cockburn.

us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

Search Blog Articles Talks Books Poems

Sign in Recent Home

Sign up Shop Courses


Crystal

Agile development Education Emotion

Articles

Being

Blog Ethics

Books

Burn charts Games

Categories humans

Children

Complaints

Cooperative Game Images living

Course list

Environment

Facilitation

Humans in software

Humor

Incorrectly Transferred Muffins Metaphysics Methodology

Increments and iterations Misc

Interviews Notes Site

Journal of object-oriented programming Object Magazine OO design

Management Poems Travel

Me Process

Methods

Motivation maps Scrum SE2K

Patterns

People Talks

Project management Use cases

Quotes

Requirements

Software engineering

Swimming category

Type theory

Just-in-time methodology construction

1/1/2000 | ARTICLES: < previous | next > RATING: | 1Avg 4.0 on 2 2 3

copyright Alistair Cockburn


Short URL for Page:

Abstract
Projects and teams differ, so one methodology wont fit all of them. People vary and tend to inconsistency, but they are good at communicating, looking around, and often take initiative to do whatever is needed. Is it possible to build methodologies that are habitable and effective, and accommodate these two statements? In this paper, I show one can dynamically construct a flexible methodology that draws upon the native strengths of people, giving consideration to their native weaknesses. The mechanisms involved help with communication of both technical issues and project dependency tracking. Team morale and cooperation receive first-order attention. Work products are developed just to the point that intelligent colleagues can find their way forward. Each projects process is tailored over the course of the project to suit that project and team need.

http://a.cockburn.us/1971

Top Recommendations
Incremental rearchitecture

Balancing lightness with sufficiency

Costs and benefits of pair programming

Characterizing people as non-linear, first-order components in software development

Image18.gif

Keywords*
Agile in tables

just-in-time methodology, dynamic methodology, flexible process, lightweight methods, software engineering practices, human factors.
Tags

Synopsis of the argument


This paper builds on A methodology per project [Cockburn99a] and Characterizing people as first-order, non-linear components of software development [Cockburn99b] to discuss creating a lightweight, people-centric methodology tuned just for a particular project team, and to do so during the course of the project. The heart of the argument is this:

Agile development

Articles

Methodology

Other

Every project and team is different, but any one organization exhibits common traits, strengths and weaknesses. Through interviews, those can be identified, and used to seed the methodology. Principles of methodology construction also seed the methodology: People factors can easily dominate process matters on a project [Cockburn99b], [Weinberg]. Light methodologies based on interpersonal communication are strong ones [Cockburn99a]. The optimal lightness varies by project, depending on criteria such as staff size and proximity, and the systems damage potential [Cockburn99a]. The power of a light methodology centers around using informal, face-to-face

What Links Here

1 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

communication channels (rather than written documents) to bind the large amount of information flowing within the project. The team draws on the ability of people to look around, ask, and discuss while tracking project dependencies, requirements and design issues. This makes the methodology lighter and more economic, but also more habitable pleasant to live in. Experienced team leads frequently use these sorts of mechanisms to run a project to successful completion. Based on the above, it is even possible to construct a family of methodologies that adapt to the local teams size and culture. Such a family is outlined at the end of the paper.

Methodology per project and peoples characteristics


The first paper that this one builds upon is A methodology per project [Cockburn99a]. It ends with the summary: A methodology contains ten basic elements: roles, skills, activities, techniques, tools, teams, deliverables, standards, quality measures and project values. The main result of the paper is that there are necessarily multiple methodologies. Different methodologies are needed depending on the project size (number of people being coordinated) the criticality of the systems being created, and the priorities of the project. For any point in the size/criticality space, the designers of the methodology select a scope of concerns to address (which project roles, activities, deliverables, and standards to cover) and optimize some quality of the project, working from their personal experiences, including their wishes, fears and base philosophy. Comparison of methodologies should include these dimensions, and their relationship to the needs of the project or organization. Four principles in methodology design were elaborated, which can be summarized in short form as: Use larger methodologies for larger teams; Use denser methodologies for more critical projects Weight is costly Interactive, face-to-face communication is most effective The second of the two papers that this one builds upon is Characterizing people as first-order, non-linear components of software development [Cockburn99b]. It ends with the summary: The fundamental characteristics of people have a first-order effect on software development, not a lower-order effect. Consequently, understanding this first-order effect should become a first-order research agenda item, and not neglected as a second-order item. I suggest that this field of study become a primary area in the field software engineering for the next 20-50 years. I presented several characteristics of people that have recognizable effects on methodology design. The first is that we are sensitive to communication timing and modalities. The prediction is that physical proximity and ease of communication has dominant effect. The second is that people tend to inconsistency. The prediction is that methodologies requiring disciplined consistency are fragile in practice. The third is that people vary, not just daily, but from group to group. Methodologies dont currently, but do need to deal with this cultural variation.

2 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

The fourth is that people like to be good citizens, are good at looking around and taking initiative. These combine to form that common success factor, a few good people stepped in at key moments. Being good at communicating and looking around counter inconsistency, leading to the prediction that methodologies can make good use of low-precision artifacts whose gaps are covered by personal communication. Project histories also support this prediction, subject to the normalization of an adequately skilled staff, including management. In the title of Characterizing people as non-linear, first-order components in software development , I refer to people as components. That is how people are treated in the process / methodology design literature. The mistake in this approach is that people are highly variable and non-linear, with unique success and failure modes. Those factors are first-order, not negligible factors. Failure of process and methodology designers to account for them contributes to the sorts of unplanned project trajectories we so often see. Connecting these two sets of results, we get: That every project deserves its own, tailored process and methodology That lightweight and face-to-face are desirable attributes That people communicate best face-to-face That daily variability, inconsistency and laziness are the weaknesses to allow for (high-discipline processes are fragile) That a process should build upon good citizenship, the ability of people to look around, talk to each other, and take initiative, as the native strengths of people

Source of the material


This paper is based on interviews, research and on-project work conducted from 1991 to 2000. Much of the interview work is quoted or summarized in [Cockburn98], [Cockburn99a], [Cockburn99b]. Corroboration of the ideas has come from interviews with organizations reporting similar success with similar sorts of programs. The IBM Object Technology Practice in the UK has run pre-project methodology tuning workshops since 1998. Siemens in Munich described using a process-tuning activity at the start of projects. A military subcontractor in Florida described how his ISO-9000 certified group set up a specific, light process for each job using process checklists. The post-project debriefing technique is described also in Kerths work, where it is called a post-partum review [Kerth]. Altering the projects team structure and practices at the end of each increment was first described to me in the project called Ingrid in 1992 [Cockburn98]. It was invented out of necessity on that project. Since then I have augmented that practice with a mid-increment methodology check. I explicitly used the technique in project Winifred [Cockburn98], and at the Central Bank of Norway [Cockburn99a]. End-ofincrement methodology tuning was used explicitly by another consultant on project Insman in Germany [Cockburn99a]. All three projects delivered successfully and claimed good results from the technique. Variable methodologies have been used for years, as described in the IBM OTP and Siemens cases above, and in [MartinOdell] and [Graham97]. As far as I know, Crystal is the first that is tuned dynamically over the course of the project.

3 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

The practice of replacing written documents with face-to-face conversation is very old. It was advocated in the 1960s by Weinberg [Weinberg] and in the 1980s and 1990s by DeMarco [DeMarco99], [DeMarco97]. It has been an underground success tactic for many people, and recently has resurfaced independently, in eXtreme Programming [Beck99], the Crystal light methodology family [Cockburn01a], and Adaptive Software Development [Highsmith99].

Dynamic Methodologies
Once we understand that every project deserves its own methodology, it is clear that any initial suggestion is just a best first guess. To improve that initial suggestion within the life of the project requires that the project uses incremental development, generally nominated to be between one week and four months in length. The methodology is tailored: Let us look at those five periods.

Before the project


To derive the best first guess at the projects specific methodology, interview people from previous projects in the organization. The interviewees are quite likely to describe both the strengths and weaknesses of the organization. Here are two examples from different organization. Successful projects had good, close communication between the developers and the user groups (or management). Unsuccessful ones had poor communication This quote implies that getting good communication patterns and goodwill in communications should be a project management priority right from the start. Our user interface team all have Ph.D.s in psychology and sit together three floors above the programmers. We have some difficulty due both to the different education or world-view of the people, and the communication distance. This second quote implies that there will need to be extra mechanisms in the process to increase contact and reviews between those two groups of people. The interviewer should not have too many preconceptions about what answers to expect. Interviewees mention things that seem to have nothing to do with process, but turn out to be significant anyway. Examples include the second quote above, and any mention of peoples personalities, room lighting, and group social activities. Suitable questions are: What was the history of the project? What did you like / not like about the way the project executed? What would you like to keep the same / change on your next project? Which things are more important? All suggestions need to be recorded. Collate the interviews and look for common properties. These show the strengths and weaknesses of the organization. My interviewees often put people issues at the top of the list, as the two previous examples show. I also commonly find reference to the use (or dislike) of CASE tools, reviews, requirements flux, frequency of iterations, testing, and coding standards.

At the start of the project

4 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

At this point, construct a draft methodology for the project, particularly the teams, standards, work products and milestones. Skip over technique descriptions, as those are too bulky to write and read on the project. Settle these questions: How long are the iterations and increments? What reviews are done? Where do people sit? What work products need to be produced? What standards are mandatory, what are recommended (for tools, drawings, tests, and code)? What does time reporting look like? What can be done to keep communication and morale up? Review the draft with the team and management, making changes as needed, until consensus is achieved. The entire process takes between two and five days, and results in a draft that is tuned to the organization and the individuals, and is ready to use on the project.

During the first increment


Approximately in the middle of the first increment, run the same sort of interview with the team members, individually or in a group meeting, depending on the size and locations of the people on the team. The dominant question to address is, Are we going to make it, working the way we are working? Typically, lack of communication, fluctuating requirements, and questions about standards are the issues that show up in the middle of the first increment. Change only those parts that are easy to change, or catastrophic if not changed. Save any fine tuning for later increments. This activity takes one to three hours.

After the first increment


Hold a team workshop after each increment, and ask: What did we learn? What can we do better? The answers are likely to cross every boundary of the project, from management intervention, to timecards, to group communication, to seating, to project reviews and standards, and team composition. As with the initial methodology suggestion, review the results with the development team, and managers. This activity might take four to twelve hours. Some teams do this during regular working hours, some go off-site, to combine this with team building, relaxation and setting up the next increment.

During subsequent increments


Subsequent mid-increment checks can be omitted if the project is using increments three weeks or less. The dominant questions in the mid-increment check is, Is this working? Do we need to do something better in this increment?

5 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

Sometimes the team tries a new idea on the second or third increment, an idea that simply does not work well. The team cannot afford to stay with such an idea, and needs an opportunity to roll back to the previous mode of working, or try out a new idea. Project Winifred [Cockburn98] went through three different team structures during their third increment. The team had decided that the team structure used in increments one and two was inadequate. The first two new suggestions tried in increment three, however, did not work well. The third new structure tried did work, and the team used that structure for the rest of the project. Expect mid-increment changes to coding and review standards, team structures and informal communication structures. This activity may take two to six hours, depending on the magnitude of the changes. The result of twice-per-increment methodology reviews is that the team is able to take into account their most recent experiences. They produce, during the execution of the project, a methodology specifically tailored to their situation.

Building on Peoples strengths


People issues can overshadow process issues [Cockburn99b]. Although the twiceper-increment methodology tuning sessions should settle them, we should hope not to start from scratch on every project. This section is for a discussion of using the strengths and weaknesses of people in forming some basic advice for the pre-project suggestion. Lighter is faster, using people as communicators Light methodologies are plausibly better than heavy methodologies (with certain caveats and costs [Cockburn99a]), and they are particularly suited when time-tomarket is important. The question arises, though: If fewer work products are produced and they are produced in a more casual fashion, what binds together the information that gets generated on the project? The answer comes from two of the strengths of people, that they generally are interested in being good citizens, and communicate best in an informal, face-to-face setting [Cockburn99a]. Using these two strengths means that the methodology will rely on some amount of oral tradition and ongoing communication to bind and refine the information being generated within the project. Since spoken communication is more expressive and less expensive than written communication [Cockburn99a], the oral component can be quite large, often much larger than expected. An example is in the eXtreme Programming methodology [Beck99], where not even the requirements are written down in detail, but live in ongoing conversations between usage experts who are full participants on the development team. So far there are good results being reported on XPs heavy reliance on this oral tradition [C3Project]. The amount of oral tradition that can be tolerated depends on the projects characteristics (team size, location, project criticality, turnover, etc.) and the team itself. The exact amount to be used is one of the items that gets altered in the methodology tuning sessions. Managing intra-project dependencies Intra-project dependencies benefit by being moved to a largely oral binding, just as requirements and design notes do. Often, the designated process requires someone to create a detailed task plan identifying the dependencies between requirements, architecture and function work products, and then try to keep the task-dependency sheet up to date. That last

6 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

proves to be extremely difficult, since the work products are continually changing state. With even just four people, this is a difficult task; it ranges from cumbersome to impossible for larger projects. Based on the ideas we have established so far, the alternative strategy is to rely on two strengths of people: being good at discussing, and being good at looking around. Let the team leads track and resolve their dependencies pairwise. On a weekly, semi-weekly or daily basis, the project coordinator will collect their dependency needs in a list, and get the team leads together to discuss it. The purpose of the discussion is to discover dependency needs that are not being met (and irreconcilable differences). Note that while he project coordinator summarizes the state of the dependencies for risk management reporting purposes, it is the team leads individual communication that binds the dependency information on the project. People are variable and inconsistent If a common weakness of people is that they are variable and inconsistent, then the methodology must deal with the issue. Two approaches have been defined up to now, each potentially effective: Create mechanisms that hold strict behavioral standards in place Design the methodology to be tolerant of individual variations Two methodologies that exemplify the first strategy are eXtreme Programming [Beck99] and the Personal Software Process / Team Software Process [Humphreys97] [Humphreys00]. The first strategy can produce an effective methodology if the mechanisms being held in place are effective. Strict adherence to ineffective practices leads to an ineffective methodology. This is less trivial a statement than it may seem at first, since there is no consensus in the industry as to which practices are effective or ineffective, under what various circumstances. The project leaders might enforce strict adherence to practices they considered effective, and be surprised at the negative result they encounter (see, for example, project Reel in [Cockburn99b]). For the first strategy to work, it is important that the high-discipline practices be considered tolerable to the team. Otherwise they will avoid or fall away from the practices, losing both the discipline and the benefits. This is what causes high-discipline methodologies to be fragile. Although there is not a lot of data to examine, at least one testimonial exists that XP and TSP use tolerable mechanisms [XP3], [Webb]. Two methodologies that exemplify the second strategy are Adaptive Software Development [Highsmith99] and the Crystal methodology family [Cockburn01a] [Cockburn01b]. In the second strategy, the methodology is designed to be tolerant of individual variations and less reliant on people being consistent. In such a methodology, the team members form consensus on the minimum compliance characteristics needed in the work products and practices. Standardization is encouraged, but not enforced. What allows the second approach to work is that the developers generally take pride in their work, so that they have personal interest in seeing that their work is acceptable. It is not yet possible to say that one approach is better than the other, but we can make two predictions. Strict adherence to strict and effective practices should be more productive but harder to attain. Laissez-faire or tolerant practices should be easier to get adopted, but possibly less productive.

7 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

Methodology Families
At this point, we have established the principle of binding ongoing project information with a varying amount of oral versus written communication. We have the technique of just-in-time methodology construction. We also have a chart to identify the sort of project being undertaken (Figure 1).

*Figure 1.Projects, organized as People x Criticality x Priority. A C3 project is one with up to 3 people, whose potential for damage is loss of comfort; an E30 project is one with up to 30 people, whose potential for damage is loss of essential moneys (from [Cockburn99a]). The grid shown in Figure 1 comes from [Cockburn99a]. The point of the grid is to highlight that a three-person, loss-of-comfort project should properly use a different methodology than a three-person, loss-of-life project, or a 30-person, loss-of-comfort project. The loss-of-life project should use more methodology elements to ensure correctness, and the 30-person project will need more methodology elements to coordinate the large numberof people involved. The third dimension to the chart illustrates that a project working against time-to-market pressures should be set up differently from one working against traceability pressures. The chart can be used to nominate the amount of oral communication and other methodological elements for the project. We now have the building blocks to describe families of methodologies that are dynamic and sensitive to the characteristics of people. One such is Crystal. Crystal is being developed in [Cockburn01a] and [Cockburn01b], so I include only the points here that are relevant to the discussion at hand. All Crystal methodologies are founded on a common value, strong on communication, light on work products. Methodological elements can be reduced to the extent that running software is delivered more frequently and interpersonal communication channels are richer. These are choices that can be made and altered on any project. System criticality is generally not at all open for negotiation. Staff size and location should be open for negotiation, but often are not. Both constrain the methodology. More communication mechanisms must be introduced as more people or more geographically dispersed people are employed. Other mechanisms must be introduced as system criticality increases. The Crystal family partitions projects into life-critical and non-life critical. It would also differentiate between loss of comfort and loss of essential money types projects, but project interviews to date do not show a significant difference in working styles across

8 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

that range of projects. The differences seem to be those that can be handled in the methodology tuning workshops. Crystal distinguishes between project sizes at a growth ratio of around 2 or 2.5 (Figure 2). Doubling the number of people on a project changes its communication characteristics significantly enough to call for additional coordination and communication mechanisms: the number of people that can practically be put within earshot of each other, within easy walking distance, and so on. Crystal is segmented into color-coded bands with common characteristics: Clear for the smallest and lightest, then Yellow, Orange, Red, Maroon, Blue, Violet and so on, for larger groups using larger methodologies.

*Figure 2.The Crystal methodologies are named by color. Each color brings its own rules and basic elements, each is as light as practical for that range of projects, and each gets tuned to the project at hand using the techniques described earlier in this paper. In the following, I illustrate the principles that have been discussed so far, by outlining first a fairly heavy member of the Crystal family, Crystal Orange (for projects up to 40 people), then contrasting that to the lightest member of the Crystal family, Crystal Clear (for projects up to 6 people), and finally, contrasting that to XP, which is lighter still (but more disciplined). Crystal Orange Crystal Orange is outlined in [Cockburn98], although without the Crystal name there. There, the following project characterization is made: ..for a medium-sized production project in an industrial setting. The characteristic of such are project are: 10 to 40 people total 1 to 2 years duration Time-to-market is important There is a need to communicate with present and future staff, and a need to keep time and costs down It is not a life-critical system It is a common sort of project, requiring trade-offs between complete, extensive deliverables and rapid change in requirements and design. I have kept the number of deliverables low, to reduce the cost of maintaining them, yet included enough to keep the teams communicating. I tailored job assignments and teams to allow the fluidity usually needed on this kind of project. Many other sorts of projects also need provisions for fluidity and can take advantage of this methodology.

9 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

Crystal Orange is a methodology suited for a D40 project: up to 40 people, sitting in one building, working on a system that might cause loss of discretionary moneys (a companys billing or payroll system would fall into this category). It calls out more team structures and more team coordination than is needed on a 20-person project. It is lacking in the subteaming structures that are needed on an 80-person project, and it is missing design- and code verification activities as would be used on life-critical systems. It might be extended to an E50 type of project depending on the team. Briefly, Crystal Orange calls for the following (all described in more detail in [Cockburn98], see the section on Methodology): The staff roles are Sponsor, Business expert, Usage expert, Technical facilitator, Business analyst/designer, Project Manager, Architect, Design Mentor, Designer/programmer, Lead designer/ programmer, Reuse Point, Writer, Tester, UI designer The people are arranged in teams responsible for system planning, project monitoring, architecture, technology, functions, infrastructure, and external test The policy standards are that software is delivered incrementally and regularly, every 2-4 months, progress is tracked by milestones consisting of software deliveries or major decisions, as opposed to written documents, there is automated regression testing of application function, there is direct user involvement, there are two user viewings per release, downstream activities start as soon as upstream is stable enough to review, methodology tuning workshops are held at the start and middle of each increment The policy standards are mandatory, but equivalent substitution is permitted, as would be the case if Scrum work scheduling [Schwaber], eXtreme Programming, or Adaptive Software Development [Highsmith99] policies were used Work products include a requirements document, release sequence, schedule, status reports, UI design document, a common object model, inter-team specs, user manual, source code, test cases, and migration code. Each work product is developed until it is understandable by colleagues, to a level of precision and stability that permits peer review Work product templates, coding style, user interface standards and details of regression testing are left as local standards, to be set and maintained by the team The techniques used by the individual roles are left entirely to the discretion of the individuals Crystal Clear For comparison, let us look at the lightest member of the family. Crystal Clear is for projects in the D6 category: for up to 6 people, sitting in one room or adjoining offices. With only 6 people, there is no need to coordinate multiple subteams, as was the case in Orange. Given that the people sit close together, there is less work needed to keep the participants aware of their part and status in the project. Clear might be usable on an E8 project. Crystal Clear calls only for the following (described in more detail in [Cockburn01a]): The roles needing separate people are Sponsor, Senior designer, Designer/ programmer, and User (part-time at least). The people on the project share the other roles: Project Coordinator, Business Expert, Requirements Gatherer

10 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

There is only one team The same policy standards apply as for Orange, except that increments are two months or less Fewer work products are required: release sequence, schedule of user viewings and deliveries, annotated use cases, design sketches & notes as needed, screen drafts, a common object model, running code, migration code, test cases and user manual Work product templates, coding style, user interface standards and details of regression testing are still left as local standards, to be set and maintained by the team Individual techniques are again left to the discretion of the individuals and the team. Substitution is permitted from similar methodologies (e.g., Scrum and eXtreme Programming) eXtreme Programming eXtreme Programming can be substituted for Clear. As Clear, it calls for frequent deliveries, close communications, user on staff, automated regression test suites, attention to team morale, and a strong oral culture. XP started as a methodology for D6-D8 projects, and has been successfully been used on a D14 category project [C3Project]. But XP has one major difference from Clear. eXtreme Programming and Clear are opposite with regard to discipline and tolerance. XP sits at the end of the band with fewest written work products and strictest standards. It relies on strict adherence to design standards, programming standards, pair programming, aggressive code refactoring, and fully 100% running unit tests. In keeping with a low-tolerance, high-discipline methodology, it includes the role of coach and various group mechanisms to keep the practices in place. XP is designed to highlight productivity, using strict standards, while Clear is designed to tolerate variation across people, meeting a much smaller set of rules. Given that Clear is prioritized for tolerance, and XP is a high-discipline, low-tolerance methodology, it should be clear that XP practices can be substituted into Clear, but the Clear tolerances cannot be substituted into XP.

Summary
This paper builds on two previous results. Since people issues can easily dominate a projects results, a software development methodology should explicitly take the characteristics of people into account, particularly their variability, their goodwill, and their ability to communicate informally Different projects have different methodology needs From those, this paper makes three contributions. First, the technique of dynamic, or just-in-time methodology construction. The technique uses open-ended interviews of previous projects and the current project, twice per delivery increment, to establish and tune rules and conventions for the project participants, and to track the communication effectiveness and morale of the team. Running this methodology-tuning workshop twice per increment allows the project team to discard ineffective ways of working, trying new ones until a set is found that suits them. Second, the project can be preloaded with a light, effective, and habitable methodology that uses peoples natural ability to communicate informally,

11 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

face-to-face. It finds a balance incorporating the largest oral and smallest written component needed to hold in place the information generated on the project. The balance point differs depending on various project characteristics and on the team members. Third, it is possible to construct a spectrum of family methodologies with common principles that also can be tuned during the course of the project. Crystal, a color-coded family of methodologies, was outlined. The color bands differ primarily in the communication elements of the methodology, without changing the basic principles: replacing written deliverables with short, rich communication channels and delivery of running software. A projects personal methodology is seeded with a methodology from the projects color band and is then modified based on pre-project interviews. The result is tuned twice per increment over the course of the project, creating a project-personal methodology within the life of the project. References [Beck99] Beck, K., Extreme Programming Explained: Embrace Change, AddisonWesley, 1999. [C3Project] The C3 Team, Chrysler goes to Extremes, in Distributed Object Computing, October, 1998, pp. 24-28. [Cockburn98] Cockburn, A., Surviving Object-Oriented Projects, Addison-Wesley, 1998. [Cockburn99a] Cockburn, A., A methodology per project, submitted to IEEE Software. Online as Humans and Technology Technical Report, TR 99.04, http://members.aol.com/humansandt/papers/methyperproject/methyperproject.htm. [Cockburn99b] Cockburn, A., Characterizing People as Non-Linear, First-Order Components in Software Development, 4th International Multiconference on Systemics, Cybernetics, and Informatics, Orlando, FL, July, 2000. Online as Humans and Technology Technical Report, TR 99.05, at http://members.aol.com/humansandt /papers/nonlinear/nonlinear.htm. [Cockburn01a] Cockburn, A., Crystal/Clear: A Human-Powered Methodology for Small Teams, Addison-Wesley, 2001, in preparation. Online draft at http://members.aol.com /humansandt/crystal/clear. [Cockburn01b] Cockburn, A., Software Development as a Cooperative Game, Addison-Wesley, 2001, in preparation, online draft at http://members.aol.com /humansandt/crystal/game. [DeMarco97] DeMarco, T., The Deadline, Dorset House, 1997. [DeMarco99] DeMarco, T., Lister, T., Peopleware: Productive Projects and Teams, 2nd Ed., Dorset House, 1999. [Graham97] Graham, I., Henderson-Sellers, B., Younessi, H., The OPEN Process Specification, Addison-Wesley, 1997. [Highsmith99] Highsmith, J., Adaptive Software Development, Dorset House, 1999. [Humphreys97] Humphreys, W., Introduction to the Personal Software Process, Addison-Wesley, 1997. [Humphreys00] Humphreys, W., Introduction to the Team Software Process, AddisonWesley, 2000. [Kerth] Kerth, N., An approach to postmorta, postparta, and project reviews, online at

12 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

http://c2.com/doc/ppm.pdf. [MartinOdell] Martin, J., Odell, J., Object-oriented Methods, Pragmatic Considerations, Prentice Hall, 1996. [Schwaber] Schwaber, K., Scrum development process, online at http://www.jeffsutherland.org/oopsla/schwapub.pdf. [Webb] Webb, D., Humphrey, W., Using TSP on the TaskView Project, in CrossTalk, The Journal of Defense Software Engineering, Feb 1999, pp. 3-10, online at http://www.stsc.hill.af.mil/crosstalk/1999/feb/webb.asp [Weinberg] Weinberg, J., The Psychology of Computer Programming, Silver Edition, Dorset House, 1998. [XP] eXtreme Programming, as described on the web: http://extremeprogramming.com. Alistair, Ive just finished Software Creativity 2 by Robert Glass. One of the main conclusions at the end of the book is basically to recommend methodology per project. He describes, in words, something similar to your Project Classification Scale. The thing I found interesting is that he seems to have come to this conclusion independently of the agile community, based instead of studies into creativity. John

Well, the idea has been re-derived a number of times. Capers Jones in his Benchmarking book made a nice argument for needing 65,000 methodologies (back then, even). When I was doing my Dr. thesis, I found I couldnt use the methodologyper-project as a new result, since there was ample previous research concluding the same (including the PhD of Lars Mathiassen, who was acting as my coach.). Even Jacobson and RUP had the idea. Working out that different projects need different processes/ methodologies is the easy part. Recognizing that EVERY project needs a different methodology is a hard pill to swallow, but a number of people have seen fit to swallow it. Those are not yet the hard or even critical parts The ultimate question is, What To Do About It? HOW does one create a new methodology on every project without hosing the project budget? The thing the doctoral defense committee found most novel unusual surprising about my thesis was the idea of tailoring and tuning a methodology in stages /during/ a project via the reflection workshops. Seems no one had tried that before. (RUP had the basic idea, but people took too long to do it on each and every project. They were missing the incremental / iterative / periodic nature of the Crystal reflection workshops). Alistair

Discussion
Alistair,

Edit

Ive just finished Software Creativity 2 by Robert Glass. One of the main conclusions at the end of the book is basically to recommend methodology per project. He describes, in words, something similar to your Project Classification Scale. The thing I found interesting is that he seems to have come to this conclusion independently of the agile community, based instead of studies into creativity.

13 de 14

26/05/2012 17:31

Alistair.Cockburn.us | Just-in-time methodology construction

http://alistair.cockburn.us/Just-in-time+methodology+construction

John Posted by: Alistair on 6/19/2008 1:07:04 PM


Rss

Last modified by: Alistair on 2/14/2009 11:33:27 AM


| Full Rss or New Articles and Blogs another skybend creation

Visits: 12285

-by Alistair on 07/23/2008 at 11:06 AM Alistair Cockburn 1970-2012

A comment on the format, not the content (which Im still in the middle of reading): Theres something wrong with the Textile code source near the bottom of the Methodology per project and peoples characteristics section. One line reads, In the title of , I refer to people . The source contains the title, but something about the pairs of square brackets and the colon keeps the actual title from being displayed. Im not interested in digressing from my current task enough to spend the time learning your coding, but wanted to point this out. I took a small stab at fixing it, which didnt work, and without a preview change button, I dont want to take the risk of breaking the page further. -by Morris Keesan on 2/10/2009 at 1:01 PM

Many thanks some conversion tags ended up as [ [ : stuff instead of [ [ stuff. This was a leftover one of those. Thanks for commenting. Alistair -by Alistair on 2/12/2009 at 12:02 PM

Display Name Email (not displayed) Comment

NOTE: Comments containing html hyperlinks will not be saved. Verification

Remember Me

14 de 14

26/05/2012 17:31

S-ar putea să vă placă și