I.

New Projects
Power Transmission Interconnection lines
1. 400 kV interconnection line Albania (Tirana)-Kosovo (Prishtina) 2. 400 kV Interconnection Line FYR of Macedonia Albania Italy

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

IS UNDER IMPLEMENTATION THE PROJECT: 400 KV INTERCONNECTION LINE ELBASAN TIRANA 2 (ALBANIA)-PODGORICE (MONTENEGRO)
ELBASAN TIRANA 2 (ALBANIA) Financed by Italian Government; Duration of the project: 24 months The total length is approximately 47 km. Overall project value (Euro): 29 million Euro TIRANA 2 (ALBANIA)-PODGORICE (MONTENEGRO) Financed by KfW; Duration of the project: 24 months Overall project value (Euro): 42 million Euro The total length is approximately 156 km. For the first part of the line Tirana 2 to Vau Dejes, the towers will be for double circuit (78 km), to be used also for the 400 kV interconnection line Albania-Kosovo. Moreever, Albania would need to further increase its capacities of interconnection lines
MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

400 KV INTERCONNECTION LINE ALBANIA (TIRANA 2)-KOSOVO (PRISHTINA).


For this interconnection line CESI Italy carried out one feasibility study financed by World Bank. The study took under consideration: For Kosova Development of Electrical Demand Kosova 2000 2020 Development Peak System Load Kosova 2000 2020 Development of Electricity generation Kosova 2000 2020
For Albania

Development of Electrical Demand Albania 2000 2020 Development f Peak System Load Albania 2000 2020 Development of Electricity generation Albania 2000 2020

400 KV INTERCONNECTION LINE ALBANIA(TIRANA 2)-KOSOVO (PRISHTINA).


Origin of Founding:

New Projects:

KfW has expressed interest for financing the project KESH/OST None

Name of Client: Implementing consultancy agency: Type of the Project:

Infrastructure

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

400 KV INTERCONNECTION LINE ALBANIA (TIRANA 2)-KOSOVO (PRISHTINA).


Status of the Project: Significance of the project: Duration of the Project: Overall project value (Euro):

Proposed Bilateral

Risk analyze : DONE

24 months

Environmental Assessment:

39 Million EURO (Estimated)

DONE

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

The main components of the Project are:


400 kV bay in Kosovo B substation; 400 kV bay in Tirana 2 ; 400 kV single circuit / twin bundle Kosovo B(KS) Vau Dejes(AL) section; 400 kV double circuit / twin bundle (second circuit) Vau Dejes Tirana 2 section. The total line length is 239 km and the lengths of three sections are: 1. Section Kosovo B Albanian border 2. Section Albanian border Vau Dejes 3. Section Vau Dejes Tirana 2 85.5 km; 75.5 km; 78.0 km

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

The main benefits of the interconnection line


The new interconnection line: enhances the reliability of Kosovo and Albanian systems and improves to greater extend the reliability of the Regional interconnected system( neighboring countries) representing a necessary reinforcement of the regional networks; realize important cost saving in operation through joint and coordinating operations of both power systems; allow to realize an short-term and medium term generation dispatch optimization of the hydrologic and thermal resources of Albania and Kosovo; guarantee up to year 2020 the reliable operation of the interconnected Transmission Systems and ensure an adequate transfer capability to allow for the economic Exchange of electricity between Kosovo and Albania; mitigate some congestion problems on regional interconnected transmission system related with the Critical North South corridor through a decreasing the maximum power and annual energy transits;

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

New Project

400 KV OHTL AND SUBMARINE CABLE INTERCONNECTION AMONG FYR OF MACEDONIAALBANIA-ITALY

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

400 KV OHTL AND SUBMARINE CABLE INTERCONNECTION AMONG FYR OF MACEDONIAALBANIA-ITALY


Feasibility study : Environmental Assessment: Risk analyze : Origin of Founding: Name of Client: Italy/ MEPSO (FYROM) DONE DONE DONE None KESH/OST (Albania)/TERNA

Overall project value (Euro): First phase: 450 Million EURO (Estimated) Type of the Project: Infrastructure

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

400 KV OHTL AND SUBMARINE CABLE INTERCONNECTION AMONG FYR OF MACEDONIAALBANIA-ITALY Technical characteristic :
OVERHEAD TRANSMISSION LINE (MACEDONIA AND ALBANIA)
VOLTAGE 400 KV RATED CAPACITY 1,200 MVA (NTC LIMIT SET TO UP TO 1,200 MW) FORMATION WITH TWO SHIELD WIRES (OF WHICH AT LEAST ONE INCLUDES\FIBER-OPTIC)

Significance of the project

Trans-regional

HVDC LINK (ALBANIA ITALY)


HVDC CONVERTERS UP TO 1,000 MW 400 KV SUBMARINE CABLE

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

THE MAIN COMPONENTS OF THE PROJECT ARE:

400 kV overhead transmission line from 400/220/110 kV Bitola substation up to Elbasan substation, around 128 km. 400 kV transmission line Elbasan - Durres around 70 km. Construction of the new AC/DC substations in Durres and Foggia. Construction of new submarine cable from Durres substation to Foggia substation, approximately 330km.

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007

The main benefits of the interconnection line are:

The new 400 KV OHTL and Submarine cable interconnection among FYR OF MACEDONIA-ALBANIA-ITALY will have positive effect on the regional network performance. From an economic point of view, the benefits due to transmission interconnection Macedonia-Albania-Italy would exceed the total investment cost with a benefit-cost ratio of 3.0 over the study period. Also, some other benefits of this project are the increase of the revenue from the electricity transit, the increase of the system reliability, sharing reserve capacities, etc.

MINISTRY OF ECONOMY, TRADE AND ENERGY SEPTEMBER, 2007