Sunteți pe pagina 1din 11

Cost of Document: Rs. 220/- (including S.

Tax)

Document for Empanelment of Consultants For Preparation of Detailed Project Report for installation of Solar Power Projects (Off-grid) of various capacities in the State of Uttarakhand.

September, 2010

Uttarakhand Renewable Energy Development Agency (UREDA) Energy Park Campus, Industrial Area, Patel Nagar, Dehradun Tel: 0135-2521553, 2521387, Fax: 0135-2521386 E-mail: uredahq@gmail.com, Web: www.ureda.nic.in

UTTARAKHAND RENEWABLE ENERGY DEVELOPMENT AGENCY. OFFICE: Energy Park Campus, Industrial Area, Patel Nagar, Dehradun Tel: 0135-2521387, 2521553 Fax 0135-2521386, E-mail: uredahq@gmail.com Notice for Empanelment of Consultants.
For providing technical help to various applicants who want to establish off-grid solar power projects in their premises/organization, UREDA invites proposals on the prescribed format for empanelment of consultants to provide consultancy services to the concerned user organization for preparation of Detailed Project Report (DPR) of various capacity solar power projects (from 1 KW to 100 KW) to avail financial incentives from MNRE under JNNSM. The prescribed format can be obtained on any working day from 31st August, 2010 to 14th September, 2010 from the office of undersigned by paying the cost of Document i.e. Rs. 220/- in form of bank draft in favour of Director UREDA payable at Dehradun. The document can also be downloaded from the Website www.ua.nic.in under tender section and cost of the document can be submitted with the proposal. The last date for submission is 15th September, 2010 up to 3:00 PM. The undersigned reserves all the rights to reject any or all the tenders without assigning any reason. DIRECTOR, UREDA

PARTICULARS OF OFFER 1. 2. Offer No. Particulars of the work : : UREDA/JNNSM/DPR/2010 Empanelment of Consultants for Preparation of Detailed Project Report for installation of Solar Power Projects (Off-grid) of various capacities in the State of Uttarakhand. One year Rs. 220/- (inclusive of trade tax) 15th September, 2010 up to 03:00PM Rs. 25,000/Two Months 15th September, 2010 at 03:30 PM Energy Park Campus, Industrial Area, Patel Nagar, Dehradun

3. 4. 5. 6. 7. 8. 9.

Period of empanelment Cost of document Last date/ time of submission Earnest money/Security Amount Validity of offer for acceptance Date and Time of opening of Offer Place of opening of offer

: : : : : : :

(Signature of Tenderer) Seal

Note:1Document issued by UREDA or downloaded from the website of UREDA will only be considered valid. Firms are requested to give full particulars and their legal and financial status.

2-

BACKGROUND The Government of India has recently launched the Jawaharlal Nehru National Solar Mission to promote ecologically sustainable growth while addressing Indias energy security challenge. It will also constitute a major contribution by India to the global effort to meet the challenges of climate change.

The immediate aim of the Mission is to focus on setting up an enabling environment for solar technology penetration in the country both at a centralized and decentralized level. The first phase (upto March 2013) will, inter alia, focus on promoting off-grid systems including hybrid systems to meet/supplement power, heating and cooling energy requirements. These systems still require interventions to bring down costs but the key challenge is to provide an enabling framework and support for entrepreneurs to develop markets.

In order to create a sustained interest within the investor community, Ministry of New & Renewable Energy (MNRE), Govt of India has decided to support viable business models. Accordingly, MNRE/GOI vide its letter no. 5/23/2009-P&C dated 8.7.10 issued the administrative approval for implementation of programme on OffGrid and Decentralized Solar Applications available on website of the Ministry i.e. www.mnre.gov.in.

Objective:To promote off-grid application of solar photovoltaic power projects for meeting
the targets set in the Jawaharlal Nehru National Solar Mission for Phase-I. To create awareness and demonstrate effective and innovative use of solar systems for individual/community/institutional/ industrial applications. To encourage innovation in addressing market needs and promoting

sustainable business models. To create a paradigm shift needed for commoditization of off-grid decentralized solar applications.

Scope of Work: For providing technical help to various applicants who want to establish off-grid solar power projects in their premises/organization, UREDA invites proposals for empanelment of consultants to provide consultancy services to the concerned user organization for preparation of Detailed Project Report (DPR) of various capacity solar power projects (from 1 KW to 100 KW). UREDA will empanel various consultants who wish to provide their services on the lowest quoted prices which are received under this offer. The consultant will

prepare the DPR for installation of power plants in accordance with technical specification as specified in the guidelines of MNRE under JNNSM. A list of indicative information required in the DPR is mentioned at Annexure-A. Empanelled firms will approach various user organizations who want to install off-grid solar power project in their organization/premises for preparation of Detailed Project Report to avail the incentives available from MNRE, Govt. of India under JNNSM. UREDA, in no way, will be responsible for not getting any consultancy order from user organization to any empanelled consultant.

Submission of Offer:The consultant firm should submitted their proposal/offer in two separate sealed envelops i.e. Part-I TECHNICAL Particulars along with Earnest Money/Security Amount and Part-II FINANCIAL Offer. The technical particulars shall be opened on above mentioned date and time. The financial offer of only technically short listed proposals shall be opened. The date of opening the financial offer shall be announced on the day of opening of technical particulars. Earnest Money/Security Amount:The consultant firm has to submit Earnest Money/Security Amount of Rs. 25,000/- in the shape of FDR/CDR from any Nationalized Bank pledged to Director UREDA or Demand Draft in favour of Director, UREDA payable at Dehradun along with its offer. The earnest money/security amount of un-successful offers shall be refunded within 15 days. The Earnest Money/Security Amount will be refunded after the completion of duration of empanelment. In case any consultant firm do not complete the assignment

within the stipulated time frame or the quality of the work is not satisfactory, UREDA reserves the right to forfeit the security deposit and cancel the assignment/ empanelment. Duration of Empanelment:The consultant firms will be empanelled initially for one year which can be extended further for maximum one year depending on the performance of the consultant firm.

Payments:Empanelled firms will get orders from UREDA or directly from user agencies on the rates approved by UREDA and will get payments as under:(i) 70% payment will be released after preparation and submission of draft DPR. (ii) Balance 30% payment will be released after submission of final DPR (after duly incorporation of comments received on Draft DPR) in 3 Hard Copies and one CD.

ANNEXURE-A

Indicative Information for DPR FORMAT FOR SUBMISSION OF PROPOSAL TO MNRE FOR FINANCIAL SUPPORT FOR INSTALLATION OF SOLAR POWER PROJECT UNDER OFF GRID & DECENTRALIZED SOLAR APPLICATIONS PROGRAMME UNDER JAWAHARLAL NEHRU NATIONAL SOLAR MISSION.
1. Name of applicant with complete postal address, telephone, fax number and email address for correspondence purpose Name of the contact person with telephone and e-mail address Type of organization (individual/noncommercial/commercial establishment /institutions/industries/Central & State Govt. Departments and their organizations, local bodies) PAN/TAN No. Sale Tax No. Type of Business Total sanctioned/connected grid load (From UPCL) Capacity of the proposed solar power project Details of system proposed to be installed at beneficiary's premises i) Place/location of proposed plant ii) Capacity of SPV panels proposed to be installed (kWp) iii) Battery storage capacity (KW-hr @ C10) iv) Other major components/sub systems proposed to be installed v) Total shadow free area earmarked for installation of the system (sq.m.) Total tentative cost of the project and means of finance i) Total project cost ii) User Share iii) Debt (if any) iv) MNRE support sought as per the scheme provisions If loan is being availed, submit consent letter and detail of the FI. Name and address of proposed supplier identified for turnkey installation of the system

2. 3.

3. 4. 5.

6.

7. 8.

9.

Security Deposit details Amount D.D. No./Date Bank Project Report should include:- total project cost, generation detail, location and site plan, plant layout diagram, technology to be used, technical specifications of SPV modules, sub-systems, major components; expected outcome from proposed installation in terms of fuel savings with detailed calculations and valid test reports and other safety parameters of the systems as per MNRE guidelines. The DPR should incorporate all the provisions as specified in the guidelines of MNRE.

10.

Details of Various Equipments Required in SPV Power Project 1. PV MODULES :


1.1 The PV modules must conform to the latest edition of any of the following IEC/ equivalent BIS Standards for PV module design qualification and type approval: Crystalline Silicon Terrestrial PV Modules : IEC61215/IS14286 Thin Film Terrestrial PV Modules : IEC 61646 Concentrator PV Modules & Assemblies : IEC 62108 In addition, the modules must conform to IEC 61730 Part 1requirements for construction & Part 2-requirments for testing, for safety qualification. PV modules to be use din a highly corrosive atmosphere (coastal areas, etc.) must qualify Salt Mist Corrosion Testing as per IEC 61701)

1.2

1.3

2. BALANCE OF SYSTEM (BOS) ITEMS/COMPONENTS:


2.1 The BOS items/components of the SPV power plants/systems deployed under the Mission must conform to the latest edition of IEC/equivalent BIS Standards as specified below:BOS item/component Applicable IEC/equivalent BIS Standard Standard Description Efficiency Measurements Environmental Testing Design Qualification Environmental Testing General Requirements & Methods of Test Tubular Lead Acid/Valve Regulated Lead Acid General test and Standard Number IEC 61683 IEC 60068 (6, 21, 27,30,75,78) IEC 62093 IEC 60068 (6, 21, 27,30,75,78) IEC 61427 IS 1651/IS 133369 IS 15549 IEC 60189

Power Conditioners/ Inverters* Charge Controller/ MPT units* Storage Batteries

Cables

Measuring Methods PV insulated cables for working Voltages up to and including 1100 V-Do-, UV resistant for outdoor installation.

IS 694/IS 1554 IS/IEC 69947

* Must additionally conform to the relevant national/international Electricity Safety Standards.

BOS item/component Switch/Circuit Breakers/ Connectors Junction Boxes/ Enclosures SPV System Design Installation Practices

Applicable IEC/equivalent BIS Standard Standard Description General Requirements Connectors-safety General Requirements Standard Number IS/IEC 60947 part I, II, III EN 50521 IP 65 (for outdoor)/ IP 21 (for indoor) IEC 62208 IEC 62124 IEC 60364-7-712

PV Stand-alone System design verification Electrical installation of buildings requirements for SPV power supply systems

FORMAT FOR EMPANELMENT OF CONSULTANTS FOR PREPARATION OF DETAILED PROJECT REPORT FOR INSTALLATION OF SOLAR POWER PROJECTS (OFF-GRID) OF VARIOUS CAPACITIES IN THE STATE OF UTTARAKHAND.

Technical Particulars
1. Name of consultant/firm with complete postal address, telephone, fax number and e-mail address for correspondence purpose.

2. 3.

3.

4.

5. 6. 7. 8.

Name of the contact person with telephone and e-mail address Type of firm (Proprietor/ Partnership/ Pvt. Ltd./Ltd./Other) PAN/TAN No. Sale Tax No. Type of Business Working Experience regarding Preparation of DPR for Renewable Energy Projects (Provide Details) Manpower Available (Provide Full Details) (a) Senior Level (b) Field Level Balance sheet of Last 2 Years (Also Provide Annual Report) Methodology Adoption for Preparation of DPR (Attach separate Sheet). Is there office of organization in Uttarakhand Earnest Money/Security Amount details Amount D.D. No./Date Bank

I, . hereby certified that all the information mentioned above are true to the best of my knowledge. Signature Name Designation Seal
. . . .

Financial Offer
(Will be submitted in Separate Envelop) S.No. 1. Particulars of Work Amount in Figure Preparation of DPR for SPV projects up to 1 KW (with battery storage) Preparation of DPR for SPV projects up to 5 KW (with out battery storage) Preparation of DPR for SPV projects above 1 KW and up to 25 KW (with battery storage) Preparation of DPR for SPV projects above 1 KW and up to 25 KW (without battery storage) Preparation of DPR for SPV projects above 25 KW and up to 50 KW (with battery storage) Preparation of DPR for SPV projects above 25 KW and up to 50 KW (without battery storage) Preparation of DPR for SPV projects above 50 KW and up to 100 KW (with battery storage) Preparation of DPR for SPV projects above 50 KW and up to 100 KW (without battery storage) Amount in Words

2.

3. (a)

3. (b)

4. (a)

4. (b)

5. (a)

5. (b)

Note: The above rates are inclusive of all the taxes and duties.

Signature Name Designation Seal

. . . .