Sunteți pe pagina 1din 80

VIETNAM-SINGAPORE INDUSTRIAL PARK

Binh Duong Province Viet Nam


----- o0o -----

INTERIM PAYMENT CERTIFICATE No.10

PROJECT:

MAIN
TENDER
PACKAGE
FOR
PROPOSED
CONSTRUCTION AND COMPLETION OF TBC-BALL
BEVERAGE CAN FACTORY AT STREET NO.18,
VIETNAM SINGAPORE INDUSTRIAL PARK II-A,
TAN UYEN DISTRICT, BINH DUONG PROVINCE,
VIETNAM

EMPLOYER:

TBC BALL BEVERAGE CAN VIETNAM LIMITED


FOSCO II, BLOCK E, SUITE E21, 40 BA HUYEN THANH QUAN
STR., DISTRICT 3, HCMC, VIETNAM

CONSULTANT:

ATELIER MANAGEMENT AND DESIGN CONSULTANCY


(VIETNAM) CO., LTD
17 TRAN NHAT DUAT STR., TAN DINH WARD, DISTRICT 1,
HCMC, VIETNAM

CONTRACTOR:

UY NAM INVESTMENT CONSTRUCTION JSC


COTECCONS TOWER, FLOORS 5-6, 236/6 DIEN BIEN PHU STR.,
BINH THANH DISTRICT, HCMC, VIETNAM

June 2012

Our ref: AMD/QS/011/TBC_MP/2012-10


26th

June 2012

TBC BALL BEVERAGE CAN VIETNAM LIMITED


FOSCO II, Block E, Suite E21, 40 Ba Huyen Thanh Quan Street,
Ward 6, District 3, HCMC, Vietnam.
Attention: Wuttichai Srivilai
Dear Sirs,
MAIN TENDER PACKAGE FOR PROPOSED CONSTRUCTION AND COMPLETION OF TBCBALL BEVERAGE CAN FACTORY

Valuation for Interim Payment Certificate No.10


1)

We are pleased to enclose herewith our valuation for the above, the amount due to the
Contractor under this certificate is:

VND

17,293,957,586

(Including 10% VAT)

(In words: Vietnam Dongs, Seventeen Billion, Two Hundred Ninety Three Million,
Nine Hundred Fifty Seven Thousand, Five Hundred Eighty Six Only.)

2)

Upon TBC approval and endorsement of this Interim Payment Certificate, the Contractor
shall be issued with the same Certificate for their subsequent submission of Invoice prior to
any payment being made to them.

3)

Please make payment directly to Uy Nam Investment Construction JSC on presentation


of this original certificate of payment.

Thank you
Yours faithfully,

Anthony Chang
Deputy General Director

C/C to:
- TBC Ball Beverage Can Vietnam Limited
- Uy Nam Investment Construction JSC

Contract Title

: Main Tender Package for Proposed Construction and Completion of


TBC - Ball Beverage Can Factory

To

: TBC Ball Beverage Can Vietnam Limited

INTERIM PAYMENT CERTIFICATE NO. 10


Date of Certificate

26th Jun 2012

Date of Valuation

20th Jun 2012

Date of Commencement

06th Jun 2011

Date of Completion

15th Jan 2012

Original Contract Sum (Including 10% VAT)

VND

281,600,000,000

Approved Variations (Including 10% VAT)

VND

3,025,844,940

Revised Contract Sum (Including 10% VAT)

VND

284,625,844,941

5% Limit of Retention Sum (Including 10% VAT)

VND

14,231,292,247

WORK PROGRESS COMPLETED


1. Value of Work Done

VND

281,600,000,000

2. Materials on site

100%

(Including 10% VAT)

VND

NIL

3. Variation Works

VND
(a)

3,025,844,940
=============
284,625,844,941

4. Less Retention Sum (5% x a)


5. Less Recovery of 1st Advance Payment

(b)

(14,231,292,247)

(c)

(74,263,764,586)

6. Less Recovery of 2nd Advance Payment

(d)

(7,662,166,590)

7. Less Previous Payment (including 10% VAT)

(e)

(171,174,663,932)
=============

TOTAL AMOUNT PAYABLE (Including VAT)

VND

17,293,957,586

We hereby certify that Interim Payment (Including 10% VAT)

VND

17,293,957,586

Total of Work Done (Included 10% VAT)

(In words: Vietnam Dongs, Seventeen Billion, Two Hundred Ninety Three Million, Nine
Hundred Fifty Seven Thousand, Five Hundred Eighty Six Only.)

Is due from the Employer


:

TBC Ball Beverage Can Vietnam Limited


Fosco II, Block E, Suite E21, 40 Ba Huyen Thanh Quan Str.,
District 3, HCMC, Vietnam.

To the Contractor

Uy Nam Investment Construction JSC


Coteccons Tower, Floors 5-6, 236/6 Dien Bien Phu Str., Ward
17, Binh Thanh District, HCMC, Vietnam.

Atelier Management and Design


Consultancy (Vietnam) Co., Ltd.

TBC Ball Beverage Can Vietnam Limited

TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH
DUONG PROVINCE, VIETNAM

SUMMARY OF WORK DONE No.10


1st Advance Payment (Excluding Provisional
Sum & VAT)
2nd Advance Payment (Excluding VAT)
Total of Advance Payment

Limit of
Retention

VND 74,263,764,586

VND 14,231,292,247

VND 7,662,166,590
CURRENCY: VND

VND 81,925,931,176

Date of valuation : 22 Jun, 2012

Progress payment No. 10

Advance payment

ITEM

DESCRIPTION

Period: 18 Apr , 2012 ~ 30 Jun, 2012


VALUE OF WORK DONE (Ending 22 Jun, 2012)
CONTRACT
AMOUNT (VND)

UNICONS' CLAIM
% Work
Done to
Date

Value of Work Done to


Date

ATELIER & UNICONS AGREED


VALUE OF WORK DONE
% Work
Done to
Date

8,989,982,800

100%

8,989,982,800

100%

8,989,982,800

BILL 2

GENERAL CONDITIONS & PRELIMINARIES


WORKS
FACTORY BUILDING

76,097,584,189

100%

76,097,584,189

100%

76,097,584,189

BILL 3

OFFICE BUILDING

11,374,426,599

100%

11,374,426,599

100%

11,374,426,599

BILL 4

UTILITY WORKS

14,095,854,515

100%

14,095,854,515

100%

14,095,854,515

BILL 5

EXTERNAL WORKS

30,903,126,514

100%

30,903,126,514

100%

30,903,126,514

BILL 6

MEP SERVICES

75,060,750,855

100%

75,060,750,855

100%

75,060,750,855

BILL 7

MISCELLANEOUS ITEMS

7,844,562,160

100%

7,844,562,160

100%

7,844,562,160

43,817,815,469

100%

43,817,815,469

100%

43,817,815,469

39,947,245,850

100%

39,947,245,850

100%

39,947,245,850

3,870,569,619

100%

3,870,569,619

100%

3,870,569,619

268,184,103,100

100%

268,184,103,100

100%

268,184,103,100

100%

256,000,000,000

100%

281,600,000,000

BILL 1

PROVISIONAL SUM
Mechanical Ventilation system
Spot Cooling System

REMARK

Value of Work Done to


Date

Material onsite
SUB TOTAL
*

Commercial Discount
TOTAL (EXCLUDED VAT)
10% VAT Tax
CONTRACT AMOUNT ( INCLUDED 10%
VAT ):

*
BILL 8
Add

(12,184,103,100)
256,000,000,000

(12,184,103,100)
100%

256,000,000,000

100%

281,600,000,000

25,600,000,000
281,600,000,000

(12,184,103,100)

25,600,000,000

25,600,000,000

VARIATION WORKS (included 10% VAT)

3,025,844,940

Variation works (included 10% VAT)

27,144,346,960

100%

27,144,346,960

100%

27,144,346,960

(24,118,502,019)

100%

(24,118,502,019)

100%

(24,118,502,019)

284,625,844,941

100%

Adjustment of the Provisional sum (included


10% VAT) -EI-14 +32

Less

TOTAL
REVISED
CONTRACT
SUM
AMOUNT (INCLUDED VARIATION WORKS
AND 10%VAT )
Retention Sum (5% x value of work done)

Less

Summary of Previous Payments

Less

Recovery of 1st Advance Payment

Less

Recovery of 2nd Advance Payment

Less

3,025,844,940

284,625,844,941

3,025,844,940

100%

284,625,844,941

(14,231,292,247)

(14,231,292,247)

(253,100,595,108)

(253,100,595,108)

(74,263,764,586)

(74,263,764,586)

(7,662,166,590)

(7,662,166,590)

Previous Payments No.1

(2,017,814,554)

(2,017,814,554)

Less

Previous Payments No.2

(5,396,300,965)

(5,396,300,965)

Less

Previous Payments No.3

(17,417,919,442)

(17,417,919,442)

Less

Previous Payments No.4

(14,401,543,052)

(14,401,543,052)

Less

Previous Payments No.5

(22,744,286,265)

(22,744,286,265)

Less

Previous Payments No.6

(25,905,765,070)

(25,905,765,070)

Less

Previous Payments No.7

(23,024,010,871)

(23,024,010,871)

Less

Previous Payments No.8

(24,579,228,455)

(24,579,228,455)

Less

Previous Payments No.9

(35,687,795,259)

(35,687,795,259)

TOTAL PAYMENT (Included VAT)

17,293,957,586

17,293,957,586

Submitted by:

Checked by:

Aprroved by:

Unicons Construction Investment JSC

Atelier Management & Design Consultancy (Vietnam) Co., Ltd

TBC-Ball Beverage Can Vietnam Ltd

Mr. Ngo Thanh Phong

Mr. Anthony Chang

Mr. Wuttichai Srivilai

Deputy General Director

Deputy General Director

Purchasing Manager

Summary-Pages 4/80

TBC - Ball Beverage Can Vietnam Limited


TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE,
VIETNAM
SUMMARY OF BILL1-GENERAL CONDITIONS & PRELIMINARIES WORKS
CURRENCY: VND
VALUE OF WORK DONE (Ending 20 June, 2012)
Item

Amount
Contract value

Description

Remarks

% Work
Done to
Date

Bill1/1

Generally

N/A

Bill1/2

Definitions and interpretation

N/A

Bill1/3

Description of the Works

N/A

Bill1/3

Phased completion

Bill1/3

Defects Notification period

Including

Bill1/4

Site and access

Including

Bill1/5

Law governing contract

N/A

Bill1/5

Necessary permit

Including

Bill1/5

Soil investigation and ground water

Excluding

10

Bill1/5 - Bill1/6

Surrounding structures and building

Excluding

11

Bill1/6

Interferance from squatters

Excluding

12

Bill1/7

Conditions of the contract

13

Bill1/7

Taxes

14

Bill1/8 Bill1/10

Insurances

15

Bill1/10

Engineer's verbal instructions

Including

16

Bill1/10

Reinforcement schedules

Including

17

Bill1/11

Contract bills

Including

18

Bill1/12

Provisioonal quantities

Excluding

19

Bill1/12

Adjustment of provisional sums

N/A

20

Bill1/12

Daywork

Including

21

Bill1/12

Drawings

Including

22

Bill1/13

Shop
drawings
drawings

Including

23

Bill1/13

Specification

Including

24

Bill1/14

Tests

25

Bill1/14

Setting out and checking the works

26

Bill1/15

As built survey drawings of intended


floor areas

Including

27

Bill1/15

Interim Payments

Including

28

Bill1/16

Payment of preliminaries

29

Bill1/16

Variation meetings

Including

30

Bill1/16

Including

31

Bill1/17

Excluding

32

Bill1/17

Draft final statement


Valuation of variations on omissions of
work,
materials or goods
Plant and equipment

Including

33

Bill1/17

Scaffolding and staging

Including

34

Bill1/18

Locating and checking the works

Including

35

Bill1/18

Labour on-costs

36

Bill1/19

Site management costs

37

Bill1/20

Working odd hours

Including

38

Bill1/20

Payment for overtime

Excluding

39

Bill1/20

Attendance

Excluding

40

Bill1/20

Loading in excess of design load

Including

41

Bill1/20

Transfer of plant, labour and materials

Excluding

% Work
Done to Date

Value of Work
Done to Date

100%

655,424,000

100%

655,424,000

100%

179,900,000

100%

179,900,000

100,000,000

100%

100,000,000

100%

100,000,000

456,000,000

100%

456,000,000

100%

456,000,000

100%

30,000,000

100%

30,000,000

550,000,000

100%

550,000,000

100%

550,000,000

1,254,000,000

100%

1,254,000,000

100%

1,254,000,000

Including

179,900,000

coordination

Value of Work
Done to Date

ATELIER & UNICONS AGREED


VALUE OF WORK DONE

N/A

655,424,000
-

and

UNICONS' CLAIM

30,000,000

Bill1 - Page 5/80

TBC - Ball Beverage Can Vietnam Limited


VALUE OF WORK DONE (Ending 20 June, 2012)
Item

Amount
Contract value

Description

Remarks

% Work
Done to
Date

42

Bill1/21

Access for insection and supervision

Including

43

Bill1/21

Pre completion inspection

Including

44

Bill1/21

Pollution and site hygiene

45

Bill1/22

Vector control

46

Bill1/23

47

193,800,000

48

Bill1/26

Public and private services

49

Bill1/27

50

Bill1/27

51

Bill1/28

Water used for the works


Temporary source of lighting and
elcectricity
for the works
Water and electricity from long-term
installation system and bills from the
public utilities authorities (Pua)

52

Bill1/28

Temporary hoarding and site security

53

Bill1/29

Advertising

54

Bill1/29

Project signboard

100%

193,800,000

421,953,000

100%

421,953,000

100%

421,953,000

366,125,000

100%

366,125,000

100%

366,125,000

Including

119,352,000

100%

119,352,000

100%

119,352,000

1,359,093,200

100%

1,359,093,200

100%

1,359,093,200

705,800,000

100%

705,800,000

100%

705,800,000

100%

261,800,000

100%

261,800,000

20,000,000

100%

20,000,000

100%

20,000,000

349,913,000

100%

349,913,000

100%

349,913,000

334,150,000

100%

334,150,000

100%

334,150,000

260,670,000

100%

260,670,000

100%

260,670,000

100%

679,833,000

100%

679,833,000

100%

228,000,000

100%

228,000,000

100%

152,000,000

100%

152,000,000

100%

262,169,600

100%

262,169,600

100%

50,000,000

100%

50,000,000

261,800,000
-

Including

Bill1/30 Bill1/31
Bill1/31 Bill1/32

61

Bill1/32

Site meeting

62

Bill1/32 Bill1/34

Programme chart report

63

Bill1/35

Fire protection during construction

64

Bill1/36

Removal or rubbish

65

Bill1/36

Record drawings

66

Bill1/36 Bill1/37

67

Bill1/37

68

Bill1/37 Bill1/38

As-built
drawings
and
as-built
documents
Operating
and
maintenance
instructions
Product/Workmanship indemnities and
warranties

69

Bill1/38

Protecting the works

70

Bill1/38

Safeguarding the works

71

Bill1/39

Branch office contractors

Including

72

Bill1/39

Progress photographs

Including

73

Bill1/39

Performance security

74

Bill1/40

Clearing and cleaning

Including

75

Bill1/40

Stamping charges

Including

76

Bill1/40

Washing bay

Bill1/40

Taking-over certificate

Bill1/29

56

Bill1/29

57
58
59
60

77

Bill1/30
Bill1/30

for
the
the
the
or

Total Amount -carried to Summary (Excluded VAT)

Value of Work
Done to Date

Including

Temporary building and facilities


the contractor
Temporary building and facilities
the direct contractor
Temporary office and facilities for
employer
Temporary office and facilities for
engineer
Temporary office and facilities for
engineer (Cont'd)
Temporary office for display
approved sample and prototyes

55

% Work
Done to Date

193,800,000

for

Value of Work
Done to Date

ATELIER & UNICONS AGREED


VALUE OF WORK DONE

100%

Safety, health and welfare of work


people
Damage, maintenance and use of
Bill1/24 - Bill/25
roads

UNICONS' CLAIM

679,833,000
-

Including

Including

Including

Including

Including

228,000,000
-

Including

Including

Including

Including

Including

152,000,000

262,169,600

50,000,000
8,989,982,800

Including
8,989,982,800

8,989,982,800

Bill1 - Page 6/80

TBC - Ball Beverage Can Vietnam Limited


TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE,
VIETNAM
BILL 2: FACTORY BUILDING
CURRENCY: VND
VALUE OF WORK DONE (Ending 20 June, 2012)
AMOUNT

ATELIER & UNICONS


AGREED VALUE OF WORK

UNICONS' CLAIM
NO

DESCRIPTION

UNIT

QTY
Contract value

EARTH WORK
The Contractor is referred to the
specification and existing site survey
condition related to this section of the
works and he is to include for comply
with all the requirements contained
therein
Excavation quantites are net volume on
the shape of structures in drawing before
excavating and no allowance is made for
subsequent variation to volume. Extra
excavation volume from Contractor's
excavation method statement shall be
Bacfilling quantity around filecap, tie
beam and other excavation due to
Contractor's excavation method
statement shall be allowed in the unit
rate
Disposal excavation materials quantity
are volumes before excavating and no
allowance is made for subsequent
variation to volume. The contracttor shall
include it in his unit rate loose factor and
surplus volume caused by his excavation

% Work
Done to
Date

4,008,290,316

% Work
Done to
Date

Value of Work
Done to Date
4,008,290,316

REMARK

Value of Work
Done to Date
4,008,290,316

Note

Note

Note

Note

Excavation for footing and ground beam

m3

2,247.63

239,372,808

100%

239,372,808

100%

239,372,808

Backfilling with selective material for


footing and ground beam

m3

1,837.53

353,173,130

100%

353,173,130

100%

353,173,130

Remove surplus excavated material off


site as directed

m3

410.10

17,511,386

100%

17,511,386

100%

17,511,386

m2

28,033.60

398,077,120

100%

398,077,120

100%

398,077,120

m3

4,896.12

2,171,918,832

100%

2,171,918,832

100%

2,171,918,832

0.25mm thk. PVC Damp proofing sheet


laying under slab
Ground slab type G2 - 200mm thk. base
coarse Agg. 0x4 compcated ratio k=0.98
to ground floor at production and
warehouse area

Ground slab type G1 - 200mm thk. base


coarse Agg. 0x4 compcated ratio k=0.98
to ground floor at coil storage area

m3

710.60

315,222,160

100%

315,222,160

100%

315,222,160

Back filling well compacted sub-grade,


K=0.98 to ground floor

m2

28,033.60

513,014,880

100%

513,014,880

100%

513,014,880

II

III

ANTI - TERMITE TREATMENT


The Tenderer is referred to existing site
survey condition related to this section of
the works and he is to include for comply
with all the requirements contained
therein
Engage a specification applicator to
supply and apply approved anti-termite
treatment to related structural areas in
contract as Engineer's approval

513,014,880

513,014,880

513,014,880

Note

m2

28,033.60

CONCRETE WORK

513,014,880

100%

16,767,811,851

Concrete Construction shall conform to


the Specification including all allowance
for grade, admixtures, vapor retarder,
curing materials, curing method when
necessary and Engineer's approval

Note

Ready mixed concrete for reinforced


concrete, max. slump and material to
comply with specification

Note

Welded wire mesh including


reinforcement bar for support

Note

513,014,880

100%

16,767,811,851

513,014,880

16,767,811,851

Lean concrete grade M100

Lean concrete for footing

m3

68.97

79,690,213

100%

79,690,213

100%

79,690,213

Lean concrete for ground beam

m3

40.29

46,555,095

100%

46,555,095

100%

46,555,095

2
a

Vibrated reinforced concrete grade


B25 (M350)
Ground slab type G2 - 270mm thk.
Ground floor slab at production and
warehouse area (except machine
foundation area)

Compacted,
K=0.95

m3

6,040.66

8,587,396,570

100%

8,587,396,570

100%

8,587,396,570

m3

959.31

1,363,755,096

100%

1,363,755,096

100%

1,363,755,096

Ground slab type G1 - 270mm thk.


Ground floor slab at coil storage area

Vibrated reinforced concrete grade


B20 (M250)

Footing and column stump

m3

220.27

286,566,988

100%

286,566,988

100%

286,566,988

Ground beam

m3

80.58

103,488,894

100%

103,488,894

100%

103,488,894

Bill2 - Page 7/80

TBC - Ball Beverage Can Vietnam Limited


c
d

Column, beam and 1st slab to utility area


at Axis (F-G)
Lintel, around door, window and bracing
on top of wall

m3

89.95

118,535,616

100%

118,535,616

100%

118,535,616

m3

22.31

33,099,994

100%

33,099,994

100%

33,099,994

Formwork

Lean concrete for footing

m2

143.98

16,845,660

100%

16,845,660

100%

16,845,660

Lean concrete for ground beam

m2

201.45

23,569,650

100%

23,569,650

100%

23,569,650

Ground floor slab at production and


warehouse area

m2

155.40

18,181,940

100%

18,181,940

100%

18,181,940

Ground floor slab at coil storage area

m2

64.94

7,597,395

100%

7,597,395

100%

7,597,395

Footing

m2

512.90

60,009,300

100%

60,009,300

100%

60,009,300

Ground beam

m2

805.80

94,278,600

100%

94,278,600

100%

94,278,600

m2

965.74

119,268,643

100%

119,268,643

100%

119,268,643

m2

248.24

58,087,224

100%

58,087,224

100%

58,087,224

m2

25,232.18

3,146,452,846

100%

3,146,452,846

100%

3,146,452,846

m2

25,232.18

1,521,500,454

100%

1,521,500,454

100%

1,521,500,454

g
h

Column, beam and 1st slab to utility area


at Axis (F-G)
Lintel, around door, window and bracing
on top of wall

Reinforcement bar

For ground floor slab at production,


warehouse area and coil storage area
(except machine foundation area)

a1
a2

A9 - 1 layer welded wire mesh steel on


bottom
A6 - 1 layer welded wire mesh steel on
top

Footing

kg

19,194.97

406,933,446

100%

406,933,446

100%

406,933,446

Ground beam

kg

18,270.86

387,342,316

100%

387,342,316

100%

387,342,316

kg

10,938.21

231,890,113

100%

231,890,113

100%

231,890,113

kg

2,677.63

56,765,798

100%

56,765,798

100%

e
f
IV

Column, beam and 1st slab to utility area


at Axis (F-G)
Lintel, around door, window and bracing
on top of wall
BRICK WORK

994,677,862

The Tenderer is referred to existing site


survey condition related to this section of
the works and he is to include for comply
with all the requirements contained
therein

Note

Work including construction of


reinforcement concrete stiffener, all
necessary joints, damp proof course and
anchoring to concrete structure as
Specification and Drawing

Note

Block brick and clay brick with size,


strength of mortar like as specified in
Specification and Drawing

Note

994,677,862

200mm thk. brick wall

m2

3,330.99

955,659,883

100%

955,659,883

100%

100mm thk. brick wall

m2

261.69

39,017,979

100%

39,017,979

100%

FINISHING WORK

2,725,327,448

Screeding and floor coating works


includes the minimum requirement of
thickness and comply with all the
requirements as Specification and
Drawing
Painting works including preration of
surfaces, supply and apply primer, coats
and all necessary accessaries as specified
in Specification and Drawing

56,765,798
994,677,862

2,725,327,448

955,659,883
39,017,979
2,725,327,448

Note

Note

Painting work includes the minimum


requirement of coating numbers as
stated in Specification and the thicknees
of coating shall be conform to the
Painting Manufacturer's recommendation

Note

Supply and install ceramic tile, granite


stone to floor and wall including wastage,
preparing surface for installation as
required and all necessaries and any sub
material to finish as specified in
Specification and Drawing

Note

Gypsum board ceiling includes frame,


trim, access panel, caulking material and
fixing accessories decorative moulding as
specified in Specification and Drawing

Note

Floor finishing
Cement and mortar screeding

Cement and mortar screeding to under


tiling
Floor coating to warehouse and
process can line area (except
machine foundation area)
5kg/m2 Grey hardener floor
Ashford formula floor coating

coating

m2

519.38

26,124,814

100%

26,124,814

100%

26,124,814

m2

24,600.94

1,163,624,273

100%

1,163,624,273

100%

1,163,624,273

Tilling and stone to floor

Bill2 - Page 8/80

TBC - Ball Beverage Can Vietnam Limited


Dong Tam
155,900,680 Classic 001,
002, 003

600mmx600mm granite tile - Floor type


N1, S1 to ground FL and 1st FL

m2

449.80

155,900,680

100%

155,900,680

100%

300x300mm non-slip ceramic tile to toilet


floor

m2

69.58

22,662,206

100%

22,662,206

100%

22,662,206

Counter for lavabo for toilet including


steel frame with rust preventive paint
finish, granite stone counter top and
other necessary accessories as specified
in Drawing (except wash basin and
mirror)

m2

2.28

5,141,628

100%

5,141,628

100%

5,141,628

ii

Wall finishing

m2

946.53

63,512,029

100%

63,512,029

100%

63,512,029

Classic001,
007,008,009

External plastering
1

15mm thk. cement and sand mortar


plaster to external wall
Internal plastering

15mm thk. cement and sand mortar


plaster to internal wall

m2

6,571.90

367,368,986

100%

367,368,986

100%

367,368,986

15mm thk. cement and sand mortar


plaster to lintel, around door, window
and bracing on top of wall

m2

248.24

20,802,177

100%

20,802,177

100%

20,802,177

m2

946.53

60,861,750

100%

60,861,750

100%

60,861,750

External painting

External emulsion paint works c/w 2 coat


putty, 1 primer coat & 2 coats of covering
paint to external wall

Internal emulsion paint works c/w 2 coat


putty, 1 primer coat & 2 coats of covering
paint to internal wall

m2

6,445.18

294,544,543

100%

294,544,543

100%

294,544,543

Internal emulsion paint c/w 2 coat putty,


1 primer coat & 2 coats of covering paint
lintel, around door, window and bracing
on top of wall

m2

248.24

11,344,385

100%

11,344,385

100%

11,344,385

Internal painting

Tiling and stone to wall


Classic001,0
02,003,004,
005,006

300x300mm ceramic tile to toilet wall

m2

126.72

51,727,104

100%

51,727,104

100%

51,727,104

100mmH ceramic tile to skirting

m2

17.22

8,694,378

100%

8,694,378

100%

8,694,378

1000mmH thk. Granite partition in toilet

m2

3.00

5,196,300

100%

5,196,300

100%

5,196,300

Compacted
laminate
12mm thck

m2

76.14

131,882,094

100%

131,882,094

100%

131,882,094

Compacted
laminate
12mm thck

Partition
10

Toilet partition C/w door to toilet by


compact grade formica

iii

Ceiling

9mm thk gypsum board ceiling with


exposed tee frame

m2

2,522.88

322,928,640

100%

322,928,640

100%

322,928,640

9mm thk anti-moisture gypsum board


ceiling with emulsion paint finishing to
toilet area

m2

69.58

13,011,460

100%

13,011,460

100%

13,011,460

VI

DOOR,
WINDOW,
LOUVRE
AND
GLASS WALL
Supply, delivery and install door and
window C/w door and window framed
leave, panic device and/or
ironmongeries, building in to brickwall,
filling frame with cement mortar or
equivalent caulking and accessories as
specified in Specification and Drawing
The work is included supply, fabrication,
installation and finishing including all
bolt, rivet, weld connection, grouting and
other necessary accessories as specified
in Specification and Drawing

727,633,000

727,633,000

727,633,000

Note

Note

Door system

D1 (6000Wx5000H) - Roller shutter door


included motor, 1mm thk. zincalume alu.
Panel

set

2.00

89,040,000

100%

89,040,000

100%

89,040,000

Taiwan,
steel sheet
1mm

D2 (6000Wx6000H) - Roller shutter door


included motor, 1mm thk. zincalume alu.
Panel

set

1.00

51,242,600

100%

51,242,600

100%

51,242,600

Taiwan,
steel sheet
1mm

D3 (4000Wx5000H) - Roller shutter door


included motor, 1mm thk. zincalume alu.
Panel

set

1.00

30,182,400

100%

30,182,400

100%

30,182,400

Taiwan,
steel sheet
1mm

D3a (3500Wx5000H) - Roller shutter


door
included
motor,
1mm
thk.
zincalume alu. Panel

set

1.00

27,017,100

100%

27,017,100

100%

27,017,100

Taiwan,
steel sheet
1mm

D4 (4000Wx4000H) - Roller shutter door


included motor, 1mm thk. zincalume alu.
Panel

set

6.00

153,766,200

100%

153,766,200

100%

153,766,200

Taiwan,
steel sheet
1mm

Bill2 - Page 9/80

TBC - Ball Beverage Can Vietnam Limited

D5 (3000Wx5000H) - Roller shutter door


included motor, 1mm thk. zincalume alu.
Panel

set

3.00

71,555,400

100%

71,555,400

100%

71,555,400

Taiwan,
steel sheet
1mm

D7 (3000Wx3200H) - Steel door with


2mm thk. tole at both side

set

8.00

146,723,200

100%

146,723,200

100%

146,723,200

Oil paint
finish

D8 (2000Wx3000H) - Steel door with


2mm thk. tole at both side

set

3.00

38,352,600

100%

38,352,600

100%

38,352,600

Oil paint
finish

D9 (1000Wx3000H) - Steel door with


2mm thk. tole at both side

set

1.00

7,174,400

100%

7,174,400

100%

7,174,400

Oil paint
finish

D14 (900Wx2500H) - Seri 1000 Alu.


Frame door with 5mm thk. clear glass
panel on top and alu. lambri on buttom

set

1.00

3,409,500

100%

3,409,500

100%

3,409,500

Tungshin
aluminium

D15 (900Wx2500H) - Seri 1000 Alu.


Frame door with 5mm thk. opaque glass
panel on top and alu. lambri on buttom

set

2.00

6,819,000

100%

6,819,000

100%

6,819,000

Tungshin
aluminium

D19 (2000Wx2500H) - Seri 1000 Alu.


Frame door with 5mm thk. clear glass
panel on top and alu. lambri on buttom

set

2.00

14,411,200

100%

14,411,200

100%

14,411,200

Tungshin
aluminium

set

3.00

54,350,700

100%

54,350,700

100%

54,350,700

Tungshin
aluminium

VK4 (2000Wx2200H) - Seri 1000 Glass


partition, alu. Frame with 8mm thk. clear
glass panel

set

1.00

4,461,100

100%

4,461,100

100%

4,461,100

VK5 (3500Wx2200H) - Seri 1000 Glass


partition, alu. Frame with 8mm thk. clear
glass panel

set

1.00

7,696,200

100%

7,696,200

100%

7,696,200

VK6 (4300Wx2200H) - Seri 1000 Glass


partition, alu. Frame with 8mm thk. clear
glass panel

set

1.00

9,421,600

100%

9,421,600

100%

9,421,600

VK7 (5500Wx2200H) - Seri 1000 Glass


partition, alu. Frame with 8mm thk. clear
glass panel

set

1.00

12,009,800

100%

12,009,800

100%

12,009,800

VII

Window system
S1 (3000Wx3200H) - Sliding window,
Seri 1000 alu. Frame with 8mm thk. clear
glass panel
Glass partition

STEEL STRUCTURE

47,079,670,899

The works include supply, fabrication,


installation and testing all steel structure
of column, beam, rafter, purlin, girth,
bracing with all connections, plates, weld,
bolts, nuts, washes, finish painting and
other necessary accessoties as Drawing
and Specification

Note

Preparation and submission of all test


records and reports for steel structure.

Note

47,079,670,899

47,079,670,899

Steel structure for column, beam, plate


and other shape steel (steel sructure for
main frame using hot roll steel)

kg

575,811.61

15,777,238,221

100%

15,777,238,221

100%

15,777,238,221

Purlin for roofing

kg

320,471.79

8,428,408,109

100%

8,428,408,109

100%

8,428,408,109

Purlin for walling

kg

43,761.43

1,150,925,700

100%

1,150,925,700

100%

1,150,925,700

Paint finishing to steel structure and


purlin, 1 layer of anti-rust paint (0.5mm 0.8mm thk.), 1 layer of base coat
(0.6mm thk.) and 2 layers of finishing
coat (1mm thk./2coats)

m2

45,115.52

4,331,090,242

100%

4,331,090,242

100%

4,331,090,242

Anchor bolt for steel structure

item

1.00

154,885,500

100%

154,885,500

100%

154,885,500

Connection bolt

item

1.00

154,885,500

100%

154,885,500

100%

154,885,500

Turnbuckle and bracing system and all


necessary for purlin

item

1.00

610,869,300

100%

610,869,300

100%

610,869,300

Roofing sheet by Lysaght Kliplok APT


0.65mm thk. in zincalume G550

m2

30,653.37

9,671,136,815

100%

9,671,136,815

100%

9,671,136,815

Walling sheet by Lysaght Spandek, APT


0.65mm thk. in zincalume G550

m2

5,705.67

1,640,378,688

100%

1,640,378,688

100%

1,640,378,688

10

Skylight sheet to wall


translucent siding sheet

m2

331.20

136,321,920

100%

136,321,920

100%

136,321,920

11

Flashing

1,558.00

256,291,000

100%

256,291,000

100%

256,291,000

31,208.51

4,506,509,205

100%

4,506,509,205

100%

4,506,509,205

426.00

202,520,400

100%

202,520,400

100%

202,520,400

1.00

58,210,300

100%

58,210,300

100%

58,210,300

12

13

by

ampelite

50mm thk. Fibreglass insulation sheet to


roof with density 24kg/m3, including
Astro-foil layer on top and wire mesh on
bottom
Steel gutter APT 0.65mm thk. in
zincalume G550

14

Mortar non-shrink by Sika Grout

15

700mmWidth Powder coating alu. Louver


with anti-insect netting under gutter

m2

m
item
m2

298.20

Fy=24.5
KN/cm2
Fy=24.5
KN/cm2
Fy=24.5
KN/cm2
Jotun Epoxy
painting,
200micron
thck

Omited

Testing of steel structure

Bill2 - Page 10/80

TBC - Ball Beverage Can Vietnam Limited

16

The Contractor shall submit with his


tender the name of independent testing
company together with business license
and certificate of their instrumentation
and approved operators to carry out the
test for Engineer approval

Note

Rate for test is included all testing


equipment and all other necessary
accessories as Specification and Drawing,
preparation and submission of all test
records and reports to the Engineer upon
completion of the tests.

Note

Supply testing of steel structure as


specified in Specification and Drawing

item

VIII STEEL CANOPY AT AXIS 18

1,385,440,000

The work is included supply, fabrication,


installation and finishing including all
bolt, rivet, weld connection, grouting and
other necessary accessories as specified
in Specification and Drawing
1
IX

(140000Lx8000W) steel canopy with


steel frame and roofing sheet by
0.65mmTCT in zincalume G550

1,385,440,000

100%

712,482,900

Note

Rite-Hite Mechenical Dock Leveler with


capacity equal to 9 tons including rubber
pads, dock lok with manual operation,
dock light and control system

no

OTHER METAL WORK

1,120.00

DOCK LEVELER

18.0mLx17.4mW Ramp and RC wall at


dock leveler, including wall emusion paint
finishing, rubber pads, steel trowel
finished with rough surface on ramp and
all necessary accessaries as specified in
Specification and Drawing

XI

m2

The work is included supply, fabrication,


installation and finishing including all
bolt, rivet, weld connection, grouting and
other necessary accessories as specified
in Specification and Drawing

Note

3.00

712,482,900

Small trench 300mmWidth x


200mmDepth including frame and
accessories for trench at dock leveler
Steel staircase including steel handrail
and oil paint finishing

100%

712,482,900

100%

427,012,853

item

1,385,440,000

712,482,900

1,385,440,000
712,482,900

100%

427,012,853

712,482,900

427,012,853

1.00

365,603,000

100%

365,603,000

100%

365,603,000

17.00

7,813,200

100%

7,813,200

100%

7,813,200

10.12

53,596,653

100%

53,596,653

100%

53,596,653

96,255,000

SANITARY WARE

Water closet sitting c/w all accessories


finishing

set

17.00

41,415,400

100%

41,415,400

100%

41,415,400

Urinal with water tap (press) c/w all


accessories finishing

set

5.00

4,190,500

100%

4,190,500

100%

4,190,500

Wash hand basin c/w water tap and all


accessories finishing

set

12.00

9,306,000

100%

9,306,000

100%

9,306,000

Stainlesss steel paper holder

set

17.00

3,894,700

100%

3,894,700

100%

3,894,700

Water bib tap and washing hose for


Water closet

set

17.00

5,888,800

100%

5,888,800

100%

5,888,800

Mirror c/w accessories finishing


3450mmWx900mmH

set

1.00

3,469,800

100%

3,469,800

100%

3,469,800

3900mmWx900mmH

set

1.00

3,922,400

100%

3,922,400

100%

3,922,400

item

1.00

24,167,400

100%

24,167,400

100%

7
XII

Accessories & sub-material


OTHER ITEM

659,967,181

18.0mLx17.4mW Ramp and RC wall at


dock leveler, including wall emusion paint
finishing, rubber pads, steel trowel
finished with rough surface on ramp and
all necessary accessaries as specified in
Specification and Drawing

D150mm PVC rain water down pipe


including bracket and all accessories

Filter basket D150mm

Joint @6mx6m to groundfloor

TOTAL
CARRIED
(Exclude. VAT)

item

m
nos

TO

SUMMARY

659,967,181

24,167,400
659,967,181

1.00

365,603,000

100%

365,603,000

100%

365,603,000

450.00

140,805,000

100%

140,805,000

100%

140,805,000

36.00

14,079,600

100%

14,079,600

100%

14,079,600

8,302.36

139,479,581

100%

139,479,581

100%

139,479,581

76,097,584,189

76,097,584,189

76,097,584,189

Bill2 - Page 11/80

TBC - Ball Beverage Can Vietnam Limited

TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE, VIETNAM

BILL 3: OFFICE BUILDING


CURRENCY: VND
VALUE OF WORK DONE (Ending 20 June, 2012)
AMOUNT
NO

DESCRIPTION

UNIT

QTY

UNICONS' CLAIM

UNIT RATE
Contract value

EARTH WORK
The Contractor is referred to the
specification and existing site survey
condition related to this section of the
works and he is to include for comply
with all the requirements contained
therein
Excavation quantites are net volume on
the shape of structures in drawing
before excavating and no allowance is
made for subsequent variation to
volume. Extra excavation volume from
Contractor's excavation method
statement shall be allowed in the unit
rates
Bacfilling quantity around filecap, tie
beam and other excavation due to
Contractor's excavation method
statement shall be allowed in the unit
rate
Disposal excavation materials quantity

1
2
3
4

are volumes before excavating and no


allowance is made for subsequent
variation to volume. The contracttor
shall include it in his unit rate loose
factor and surplus volume caused by his
Excavation for footing and ground beam
Backfilling with selective material for
footing and ground beam
Remove surplus excavated material off
site as directed
0.25mm thk. PVC Damp proofing sheet
laying under slab

% Work
Done to
Date

423,959,862

Value of Work
Done to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
% Work
Done to
Date

423,959,862

423,959,862

Note

Note

Note

Note

m3

1,102.31

106,500

117,396,228

100%

117,396,228

100%

117,396,228

m3

896.51

192,200

172,309,739

100%

172,309,739

100%

172,309,739

m3

205.80

42,700

8,787,630

100%

8,787,630

100%

8,787,630

m2

1,632.40

14,200

23,180,080

100%

23,180,080

100%

23,180,080

100mm thk. Base coarse Agg. 0x4


compcated ratio k=0.98 to ground floor

m3

163.24

443,600

72,413,264

100%

72,413,264

100%

72,413,264

Back filling well compacted sub-grade,


K=0.98 to ground floor

m2

1,632.40

18,300

29,872,920

100%

29,872,920

100%

29,872,920

II

ANTI - TERMITE TREATMENT


The Tenderer is referred to existing site
survey condition related to this section
of the works and he is to include for
comply with all the requirements
contained therein

III

Engage a specification applicator to


supply and apply approved anti-termite
treatment to related structural areas in
contract as Engineer's approval

1,632.40

18,300

Note

100mm thk. lean concrete to ground


beam
Vibrated reinforced concrete grade
B20 (M250)

Footing

Column

29,872,920

100%

4,607,487,098

Ready mixed concrete for reinforced


concrete, max. slump and material to
comply with specification
Lean concrete grade M100

m2

Note

100mm thk. lean concrete to footing

29,872,920

29,872,920

29,872,920

100%

4,607,487,098

29,872,920

4,607,487,098

m3

29.32

1,155,500

33,881,571

100%

33,881,571

100%

33,881,571

m3

32.47

1,155,500

37,518,623

100%

37,518,623

100%

37,518,623

m3

72.02

1,301,000

93,700,243

100%

93,700,243

100%

93,700,243
-

b1

Column stump & column to ground FL

m3

55.47

1,317,800

73,096,883

100%

73,096,883

100%

73,096,883

b2

Column to 1st FL

m3

29.03

1,317,800

38,249,639

100%

38,249,639

100%

38,249,639

92,451,620

Compacted,
K=0.95

Note

Concrete Construction shall conform to


the Specification including all allowance
for grade, admixtures, vapor retarder,
curing materials, curing method when
necessary and Engineer's approval

29,872,920

CONCRETE WORK

REMARK

Value of Work
Done to Date

Beam

c1

Ground beam

m3

71.99

1,284,300

92,451,620

100%

92,451,620

100%

c2

1st floor beam

m3

72.33

1,312,200

94,906,387

100%

94,906,387

100%

94,906,387

c3

Roof floor beam

m3

125.89

1,312,200

165,192,858

100%

165,192,858

100%

165,192,858

Slab

Bill3 - Page 12/80

TBC - Ball Beverage Can Vietnam Limited


VALUE OF WORK DONE (Ending 20 June, 2012)
AMOUNT
NO

DESCRIPTION

UNIT

QTY

UNICONS' CLAIM

UNIT RATE
Contract value

% Work
Done to
Date

Value of Work
Done to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
% Work
Done to
Date

d1

80mm thk. Ground floor slab

m3

130.59

1,284,300

167,719,306

100%

167,719,306

100%

167,719,306

d2

1st floor slab

m3

193.27

1,312,200

253,608,369

100%

253,608,369

100%

253,608,369

d3

Roof floor slab

m3

197.57

1,312,200

259,248,730

100%

259,248,730

100%

259,248,730

Staircase

e1

Staircase S-01 at axis F/1b

m3

2.10

1,483,400

3,116,623

100%

3,116,623

100%

3,116,623

e2

Staircase S-01' at axis A2/1b

m3

2.10

1,483,400

3,116,623

100%

3,116,623

100%

3,116,623

e3

Staircase S-02 at axis D1/1b

m3

4.23

1,483,400

6,277,705

100%

6,277,705

100%

6,277,705

Lintel, around door and window

m3

6.92

1,483,400

10,271,062

100%

10,271,062

100%

10,271,062

Formwork

Lean concrete for footing

m2

61.36

117,000

7,179,120

100%

7,179,120

100%

7,179,120

Lean concrete for ground beam

m2

162.35

117,000

18,994,716

100%

18,994,716

100%

18,994,716

Footing

m2

143.35

117,000

16,771,950

100%

16,771,950

100%

16,771,950

Column

d1

Column stump & column to ground FL

m2

681.87

123,500

84,210,945

100%

84,210,945

100%

84,210,945

d2

Column to 1st FL

m2

333.21

123,500

41,151,435

100%

41,151,435

100%

41,151,435

719.86

117,000

84,223,620

100%

84,223,620

100%

84,223,620

Beam

e1

Ground beam

m2

e2

1st floor beam

m2

723.26

149,500

108,127,609

100%

108,127,609

100%

108,127,609

e3

Roof floor beam

m2

1,229.77

149,500

183,850,615

100%

183,850,615

100%

183,850,615

Slab

f1

Ground floor slab

m2

24.28

117,000

2,840,947

100%

2,840,947

100%

2,840,947

f2

1st floor slab

m2

1,648.80

149,500

246,495,959

100%

246,495,959

100%

246,495,959

f3

Roof floor slab

m2

1,682.82

149,500

251,581,949

100%

251,581,949

100%

251,581,949

Staircase

g1

Staircase S-01 at axis F/1b

m2

21.80

234,000

5,100,732

100%

5,100,732

100%

5,100,732

g2

Staircase S-01' at axis A2/1b

m2

21.80

234,000

5,100,732

100%

5,100,732

100%

5,100,732

45.56

g3

Staircase S-02 at axis D1/1b

m2

234,000

10,660,817

100%

10,660,817

100%

10,660,817

Lintel, around door and window

m2

138.48

234,000

32,404,320

100%

32,404,320

100%

32,404,320

Reinforcement bar

Footing

kg

4,609.63

21,200

97,724,253

100%

97,724,253

100%

97,724,253

Column

b1

Column stump & column to ground FL

kg

7,271.90

21,200

154,164,262

100%

154,164,262

100%

154,164,262

b2

Column to 1st FL

kg

6,052.91

21,200

128,321,667

100%

128,321,667

100%

128,321,667

Beam

c1

Ground beam

kg

9,287.53

21,200

196,895,547

100%

196,895,547

100%

196,895,547

c2

1st floor beam

kg

19,163.76

21,200

406,271,660

100%

406,271,660

100%

406,271,660

c3

Roof floor beam

kg

23,797.39

21,200

504,504,579

100%

504,504,579

100%

504,504,579

Slab

d1

to ground floor slab D6@200

kg

3,688.70

21,200

78,200,413

100%

78,200,413

100%

78,200,413

d2

1st floor slab

kg

12,872.34

21,200

272,893,558

100%

272,893,558

100%

272,893,558

d3

Roof floor slab

kg

13,250.22

21,200

280,904,616

100%

280,904,616

100%

280,904,616

8,884,389

100%

8,884,389

100%

8,884,389

Staircase

e1

Staircase S-01 at axis F/1b

kg

419.07

21,200

e2

Staircase S-01' at axis A2/1b

kg

419.07

21,200

8,884,389

100%

8,884,389

100%

8,884,389

e3

Staircase S-02 at axis D1/1b

kg

998.65

21,200

21,171,401

100%

21,171,401

100%

21,171,401

Lintel, around door and window

kg

830.88

21,200

17,614,656

100%

17,614,656

100%

f
IV

REMARK

Value of Work
Done to Date

BRICK WORK

681,535,249

681,535,249

17,614,656
681,535,249

Bill3 - Page 13/80

TBC - Ball Beverage Can Vietnam Limited


VALUE OF WORK DONE (Ending 20 June, 2012)
AMOUNT
NO

DESCRIPTION

UNIT

QTY

UNICONS' CLAIM

UNIT RATE
Contract value

The Tenderer is referred to existing site


survey condition related to this section
of the works and he is to include for
comply with all the requirements
contained therein

Note

Work including construction of


reinforcement concrete stiffener, all
necessary joints, damp proof course and
anchoring to concrete structure as
Specification and Drawing

Note

Block brick and clay brick with size,


strength of mortar like as specified in
Specification and Drawing

Note

% Work
Done to
Date

Value of Work
Done to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
% Work
Done to
Date

200mm thk. brick wall

m2

1,350.56

286,900

387,476,812

100%

387,476,812

100%

387,476,812

100mm thk. brick wall

m2

1,929.91

149,100

287,749,134

100%

287,749,134

100%

287,749,134

m3

0.73

2,065,000

1,500,429

100%

1,500,429

100%

1,500,429

m3

0.73

2,065,000

1,500,429

100%

1,500,429

100%

1,500,429

m3

1.60

2,065,000

3,308,446

100%

3,308,446

100%

3,308,446

3
4
5

1
VI

Solid brick steps on Staircase S-01 at


axis F/1b
Solid brick steps on Staircase S-01' at
axis A2/1b
Solid brick steps on Staircase S-02 at
axis D1/1b
WATER PROOFING AND MOISTURE
PROTECTION WORK
Work including all concrete surface
preparing, grouting, sealing, laping,
wastage, penetration treatment and
bonding agent as Manufacture's
recommendation

Note

Works described here includes the


minimum requirement of coating
numbers, testing before finish and it is
to include for comply with all the
requirements as Specification and
Drawing

Note

Waterproofing to floor of toilet at 1st FL

m2

61.73

132,400

FINISHING WORK

8,173,052

8,173,052

100%

3,661,800,635

Screeding and hardener works includes


the minimum requirement of thickness
and comply with all the requirements as
Specification and Drawing

Note

Painting works including preration of


surfaces, supply and apply primer, coats
and all necessary accessaries as
specified in Specification and Drawing

Note

Painting work includes the minimum


requirement of coating numbers as
stated in Specification and the thicknees
of coating shall be conform to the
Painting Manufacturer's
recommendation
Supply and install ceramic tile, granite
stone to floor and wall including
wastage, preparing surface for
installation as required and all
necessaries and any sub material to
finish as specified in Specification and
Drawing
Gypsum board ceiling includes frame,
trim, access panel, caulking material
and fixing accessories decorative
moulding as specified in Specification
and Drawing
i

8,173,052

8,173,052

REMARK

Value of Work
Done to Date

8,173,052

100%

3,661,800,635

8,173,052
3,661,800,635

Note

Note

Note

Floor finishing

1,441,332,401

Cement and mortar screeding


1
2

Cement and mortar screeding to under


tiling and on RC roof slab
Cement and mortar screeding to
staicase steps

m2

4,724.58

50,300

237,646,475

100%

237,646,475

100%

237,646,475

m2

58.82

95,000

5,587,463

100%

5,587,463

100%

5,587,463

m2

2,993.74

346,600

1,037,628,898

100%

1,037,628,898

100%

1,037,628,898

m2

158.95

325,700

51,768,712

100%

51,768,712

100%

51,768,712

m2

58.82

1,206,900

70,984,306

100%

70,984,306

100%

70,984,306

m2

16.73

2,255,100

37,716,548

100%

37,716,548

100%

37,716,548

Tilling and stone to floor


3
4
5

600mmx600mm granite tile - Floor type


N1, S1 to ground FL and 1st FL
300mmx300mm non-slip ceramic tile Floor type NW, SW to toilet floor from
ground FL to 1st FL
Granite stone to staircase steps for
staircase S-01, S-02, S-03
Counter for lavabo at ground FL and 1st
FL for toilet, including steel frame with
rust preventive paint finish, granite
stone counter top and other necessary
accessories as specified in Drawing
(except wash basin and mirror)

Classic001,
007,008,009

Bill3 - Page 14/80

TBC - Ball Beverage Can Vietnam Limited


VALUE OF WORK DONE (Ending 20 June, 2012)
AMOUNT
NO

DESCRIPTION

UNIT

QTY

UNICONS' CLAIM

UNIT RATE
Contract value

ii

% Work
Done to
Date

Value of Work
Done to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
% Work
Done to
Date

REMARK

Value of Work
Done to Date

1,676,275,420

Wall finishing
External plastering

15mm thk. cement and sand mortar


plaster to external wall

m2

801.80

67,100

53,801,048

100%

53,801,048

100%

53,801,048

15mm thk. cement and sand mortar


plaster to external beam, column

m2

209.15

72,600

15,183,927

100%

15,183,927

100%

15,183,927

Internal plastering

15mm thk. cement and sand mortar


plaster to internal wall

m2

7,020.70

55,900

392,457,018

100%

392,457,018

100%

392,457,018

15mm thk. cement and sand mortar


plaster to internal beam, column

m2

2,758.97

72,600

200,301,033

100%

200,301,033

100%

200,301,033

15mm thk. cement and sand mortar


plaster to ceiling (except ceiling to
staircase)

m2

212.42

83,800

17,801,131

100%

17,801,131

100%

17,801,131

15mm thk. cement and sand mortar


plaster to ceiling of staircase

m2

89.16

83,800

7,471,193

100%

7,471,193

100%

7,471,193

15mm thk. cement and sand mortar


plaster to lintel, around door and
window

m2

138.48

83,800

11,604,624

100%

11,604,624

100%

11,604,624

External painting

External emulsion paint works c/w 2


coat putty, 1 primer coat & 2 coats of
covering paint to external wall

m2

691.80

64,300

44,482,997

100%

44,482,997

100%

44,482,997

External emulsion paint works c/w 2


coat putty, 1 primer coat & 2 coats of
covering paint to beam, column

m2

209.15

64,300

13,448,024

100%

13,448,024

100%

13,448,024

m2

6,496.52

45,700

296,891,055

100%

296,891,055

100%

296,891,055

m2

805.94

45,700

36,831,230

100%

36,831,230

100%

36,831,230

m2

212.42

45,700

9,707,777

100%

9,707,777

100%

9,707,777

Internal painting

10

11

12

Internal emulsion paint works c/w 2 coat


putty, 1 primer coat & 2 coats of
covering paint to internal wall
Internal emulsion paint works c/w 2 coat
putty, 1 primer coat & 2 coats of
covering paint to column
Internal emulsion paint works c/w 2 coat
putty, 1 primer coat & 2 coats of
covering paint to ceiling (except ceiling
to staircase)

13

Internal emulsion paint works c/w 2 coat


putty, 1 primer coat & 2 coats of
covering paint to ceiling of Staircase

m2

89.16

45,700

4,074,386

100%

4,074,386

100%

4,074,386

14

Internal emulsion paint works c/w 2 coat


putty, 1 primer coat & 2 coats of
covering paint to lintel, around door and
window

m2

138.48

45,700

6,328,536

100%

6,328,536

100%

6,328,536

Tiling and stone to wall

15

300x300mm ceramic tile to toilet wall

m2

524.18

408,200

213,968,643

100%

213,968,643

100%

213,968,643

16

100mmH ceramic tile to skirting from


1st FL to terrace FL

m2

134.65

504,900

67,983,109

100%

67,983,109

100%

67,983,109

17

1000mmH thk. Granite partition in toilet


at ground FL and 1st FL

m2

6.50

1,732,100

11,258,650

100%

11,258,650

100%

11,258,650

18

Toilet partition C/w door to toilet by


compact grade formica

m2

157.43

1,732,100

272,681,039

100%

272,681,039

100%

272,681,039

Classic001,002,
003,004,005,00
6

Partition

iii

Ceiling

9mm thk anti-moisture concealed


gypsum board ceiling with emulsion
paint finishing (Type T-1) to toilet area

VII

9mm thk anti-moisture concealed


gypsum board ceiling with emulsion
paint finishing to 5 rooms between office
and warehouse (at Axis 1b)
9mm thk anti-moisture concealed
gypsum board ceiling with emulsion
paint finishing to other rooms (except
general store room, it will be paint
finishing ceiling)
DOOR, WINDOW, LOUVRE AND
GLASS WALL

544,192,814

m2

158.95

187,000

29,722,902

100%

29,722,902

100%

29,722,902

m2

47.25

187,000

8,835,750

100%

8,835,750

100%

8,835,750

m2

2,703.93

187,000

505,634,162

100%

505,634,162

100%

505,634,162

1,420,154,785

Bill3 - Page 15/80

TBC - Ball Beverage Can Vietnam Limited


VALUE OF WORK DONE (Ending 20 June, 2012)
AMOUNT
NO

DESCRIPTION

UNIT

QTY

Contract value
Supply, delivery and install door and
window C/w door and window framed
leave, panic device and/or
ironmongeries, building in to brickwall,
filling frame with cement mortar or
equivalent caulking and accessories as
specified in Specification and Drawing

Note

The work is included supply, fabrication,


installation and finishing including all
bolt, rivet, weld connection, grouting
and other necessary accessories as
specified in Specification and Drawing

Note

ATELIER & UNICONS


AGREED VALUE OF WORK

UNICONS' CLAIM

UNIT RATE

% Work
Done to
Date

% Work
Done to
Date

Value of Work
Done to Date

Door system

D6 (4000Wx3500H) - Roller shutter door


included motor, 1mm thk. zincalume
alu. Panel

set

2.00

23,393,700

46,787,400

100%

46,787,400

100%

46,787,400

D10 (3000Wx3500H) - Floor hinge door


with 12mm thk. clear glass panel

set

1.00

22,573,500

22,573,500

100%

22,573,500

100%

22,573,500

D11 (2400Wx3000H) - Floor hinge door


with 12mm thk. clear glass panel

set

1.00

18,148,200

18,148,200

100%

18,148,200

100%

18,148,200

D12 (1400Wx2500H) - Seri 1000 Alu.


Frame door with 5mm thk. Clear glass
panel on top and alu. lambri on buttom

set

11.00

5,174,000

56,914,000

100%

56,914,000

100%

56,914,000

D13 (1400Wx2500H) - Seri 1000 Alu.


Frame door with 5mm thk. opaque glass
panel on top and alu. lambri on buttom

set

2.00

5,174,000

10,348,000

100%

10,348,000

100%

10,348,000

D14 (900Wx2500H) - Seri 1000 Alu.


Frame door with 5mm thk. clear glass
panel on top and alu. lambri on buttom

set

26.00

3,409,500

88,647,000

100%

88,647,000

100%

88,647,000

D15 (900Wx2500H) - Seri 1000 Alu.


Frame door with 5mm thk. opaque glass
panel on top and alu. lambri on buttom

set

6.00

3,409,500

20,457,000

100%

20,457,000

100%

20,457,000

S2 (3000Wx1700H) - Sliding window,


Seri 1000 Alu. Frame with 8mm thk.
clear glass panel

set

6.00

9,718,900

58,313,400

100%

58,313,400

100%

58,313,400

S3 (5000Wx2500H) - Sliding window,


Seri 1000 Alu. Frame with 8mm thk.
clear glass panel

set

1.00

23,551,300

23,551,300

100%

23,551,300

100%

23,551,300

S4 (5000Wx2500H) - Sliding window,


Seri 1000 Alu. Frame with 8mm thk.
clear glass panel

set

32.00

23,551,300

753,641,600

100%

753,641,600

100%

753,641,600

S5 (3000Wx2500H) - Sliding window,


Seri 1000 Alu. Frame with 8mm thk.
clear glass panel

set

4.00

14,197,800

56,791,200

100%

56,791,200

100%

56,791,200

S6 (4200Wx2500H) - Sliding window,


Seri 1000 Alu. Frame with 8mm thk.
clear glass panel

set

5.00

19,809,900

99,049,500

100%

99,049,500

100%

99,049,500

S7 (600Wx600H) - Swing window, Seri


1000 alu. Frame with 5mm thk. opaque
glass panel

set

4.00

547,100

2,188,400

100%

2,188,400

100%

2,188,400

set

9.00

6,651,400

59,862,600

100%

59,862,600

100%

59,862,600

VIII

2
3
IX

Taiwan, steel
sheet 1mm

Window system

Glass partition
VK2 (3000Wx2200H) - Glass partition,
Seri 1000 alu. Frame with 8mm thk.
clear glass panel
Glass wall for faade
Glass wall (11000Wx7650H) - Glass
wall, Seri 1000 alu. Frame with 12mm
thk. Tempered glass panel (except D1
(3000Wx3500H) - Floor hinge door)

m2

73.65

1,396,900

1000mmH Steel handrail to Staircase S01 at axis F/1b


1000mmH Steel handrail to Staircase S01' at axis A2/1b
1000mmH Steel handrail to Staircase S02 at axis D1/1b
GLASS CANOPY AS DETAIL 06

102,881,685

100%

102,881,685

100%

102,881,685

5,386,920

100%

5,386,920

100%

5,386,920

5,386,920

100%

5,386,920

13,300,058

100%

24,073,898

METAL WORK
The work is included supply, fabrication,
installation and finishing including all
bolt, rivet, weld connection, grouting
and other necessary accessories as
specified in Specification and Drawing

REMARK

Value of Work
Done to Date

Note

7.70

699,600

7.70

699,600

5,386,920

100%

19.01

699,600

13,300,058

100%

300,440,800

300,440,800

13,300,058

Steel handrail,
oil paint finish
Steel handrail,
oil paint finish
Steel handrail,
oil paint finish

300,440,800

Bill3 - Page 16/80

TBC - Ball Beverage Can Vietnam Limited


VALUE OF WORK DONE (Ending 20 June, 2012)
AMOUNT
NO

DESCRIPTION

UNIT

QTY

UNICONS' CLAIM

UNIT RATE
Contract value

The work is included supply, fabrication,


installation and finishing including all
bolt, rivet, weld connection, grouting
and other necessary accessories as
specified in Specification and Drawing

Note

(11000Lx4000W) - 12mm thk. glass


tempered canopy with steel truss at axis
(C3-D1)(1)

m2

44.00

6,828,200

300,440,800

% Work
Done to
Date

100%

300,440,800

% Work
Done to
Date

100%

300,440,800

SANITARY WARE

Water closet sitting c/w all accessories


finishing

set

31.00

2,436,200

75,522,200

100%

75,522,200

100%

75,522,200

Urinal with water tap (press) c/w all


accessories finishing

set

15.00

838,100

12,571,500

100%

12,571,500

100%

12,571,500

Wash hand basin c/w water tap and all


accessories finishing

set

33.00

775,500

25,591,500

100%

25,591,500

100%

25,591,500

Stainlesss steel paper holder

set

31.00

229,100

7,102,100

100%

7,102,100

100%

7,102,100

Water bib tap and washing hose for


Water closet

set

31.00

346,400

10,738,400

100%

10,738,400

100%

10,738,400

Shower c/w water tap & all accessories


finishing

set

8.00

502,900

4,023,200

100%

4,023,200

100%

4,023,200

Mirror c/w accessories finishing


4100mmWx900mmH

set

1.00

4,123,600

4,123,600

100%

4,123,600

100%

4,123,600

5660mmWx900mmH

set

1.00

5,692,500

5,692,500

100%

5,692,500

100%

5,692,500

2300mmWx900mmH

set

1.00

2,313,200

2,313,200

100%

2,313,200

100%

2,313,200

3100mmWx900mmH

set

1.00

3,117,800

3,117,800

100%

3,117,800

100%

3,117,800

1500mmWx900mmH

set

1.00

1,508,600

1,508,600

100%

1,508,600

100%

1,508,600

4300mmWx900mmH

set

1.00

4,324,700

4,324,700

100%

4,324,700

100%

4,324,700

1600mmWx900mmH

set

1.00

1,609,200

1,609,200

100%

1,609,200

100%

1,609,200

2500mmWx900mmH

set

1.00

2,514,400

2,514,400

100%

2,514,400

100%

2,514,400

1700mmWx900mmH

set

1.00

1,709,800

1,709,800

100%

1,709,800

100%

1,709,800

item

1.00

54,465,600

54,465,600

100%

54,465,600

100%

54,465,600

Accessories & sub-material

TOTAL
CARRIED
(Exclude. VAT)

TO

SUMMARY

11,374,426,599

216,928,300

11,374,426,599

REMARK

Value of Work
Done to Date

216,928,300

Value of Work
Done to Date

ATELIER & UNICONS


AGREED VALUE OF WORK

216,928,300

11,374,426,599

Bill3 - Page 17/80

TBC - Ball Beverage Can Vietnam Limited


TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE,
VIETNAM
SUMMARY OF BILL 4 - UTILITY WORKS
ADDENDUM NO.5
CURRENCY: VND
VALUE OF WORK DONE (Ending 20 June, 2012)

NO

AMOUNT
Contract value

ITEM

4A-MACHINE
TRENCH

FOUNDATION

AND

WET

CAN

UNICONS' CLAIM
% Work
Done to
Date

Value of Work
Done to Date

REMARK

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Value of Work
Work
Done to Date
Done to
Date

6,811,138,149

100%

6,811,138,149

100%

6,811,138,149

4B - WASTE WATER TREATMENT TANK 1

214,351,434

100%

214,351,434

100%

214,351,434

4C - WASTE WATER TREATMENT TANK 2

744,843,382

100%

744,843,382

100%

744,843,382

4D - FOUNDATION FOR OIL & IC TANK

4E - D.I SYSTEM AND SOLUBLE AREA

4F - CANTEEN

Not including

262,040,761

100%

262,040,761

100%

262,040,761

1,772,033,564

100%

1,772,033,564

100%

1,772,033,564

4G - GUARDHOUSE AT MAIN ENTRANCE

218,153,412

100%

218,153,412

100%

218,153,412

4H - INTERNAL GUARDHOUSE NEAR ROAD 19

162,896,203

100%

162,896,203

100%

162,896,203

4I - LPG STORAGE

1,081,293,126

100%

1,081,293,126

100%

1,081,293,126

10

4J - TRUCK SCALE

117,302,366

100%

117,302,366

100%

117,302,366

11

4K - FLAG POLE

34,943,378

100%

34,943,378

100%

34,943,378

12

4L - WASTE WATER TREATMENT TANK 3

116,475,612

100%

116,475,612

100%

116,475,612

13

4M - ADDITION ITEMS FOR FACTORY

128,202,396

100%

128,202,396

100%

128,202,396

14

4N - COMPRESSOR AND VACUUM FOUNDATION

453,806,615

100%

453,806,615

100%

453,806,615

15

4O - SCRAP SYSTEM TRENCH

64,366,623

100%

64,366,623

100%

64,366,623

16

4P - BALER ROOM

762,601,256

100%

762,601,256

100%

762,601,256

17

4Q - CHILER AND COOLING TOWER

978,214,815

100%

978,214,815

100%

978,214,815

18

BILL 4R: EUTRALIZATION TANK OF DI SYSTEM

173,191,421

100%

173,191,421

100%

173,191,421

TOTAL CARRIED TO SUMMARY (Exclude.


VAT)

14,095,854,515

14,095,854,515

14,095,854,515

Sum of Bill4 - Page 18/80

TBC - Ball Beverage Can Vietnam Limited

TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE, VIETNAM

SUMMARY OF BILL 5 - EXTERNAL WORKS


CURRENCY: VND
VALUE OF WORK DONE (Ending 20 June, 2012)
NO

ITEM

AMOUNT
Contract value

UNICONS' CLAIM
% Work Done to
Date

5A - INTERNAL ROAD

5B - DRAINAGE AND SEWERAGE SYSTEM

5C - TURFING

REMARK

ATELIER & UNICONS AGREED VALUE


OF WORK DONE

Value of Work Done % Work Done to


to Date
Date

Value of Work
Done to Date

15,676,021,584

100%

15,676,021,584

100%

15,676,021,584

9,438,539,731

100%

9,438,539,731

100%

9,438,539,731

620,838,941

100%

620,838,941

100%

620,838,941

5D - UNDERGROUND FIRE WATER TANK

1,958,958,299

100%

1,958,958,299

100%

1,958,958,299

5E - FENCE AND GATE

2,879,187,056

100%

2,879,187,056

100%

2,879,187,056

ITEM 5F: DRAINAGE SYSTEM CONECTING RAIN WATER DOWN


PIPE TO DRAIN OF INSPECTION MANHOLE

329,580,903

100%

329,580,903

100%

329,580,903

TOTAL CARRIED TO SUMMARY(Exclude. VAT)

30,903,126,514

30,903,126,514

30,903,126,514

Sum of Bill5 - Page 19/80

TBC - Ball Beverage Can Vietnam Limited

TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE, VIETNAM

BILL 7: ANY MISCELLANEOUS ITEMS TO BRING THE CONTRACT TO COMPLETION


CURRENCY: VND
VALUE OF WORK DONE (Ending 29 Oct, 2011)
AMOUNT
NO

DESCRIPTION

UNIT

TENDER QTY

UNC QTY

DIFFENCE

UNICONS' CLAIM

UNIT RATE
Contract value

General

Note

Any other works not yet mentioned but are


necessary for the completion of the entire works
(please specify):

Note

BUILDING WORKS

% Work
Done to
Date

Value of Work
Done to Date

ATELIER & UNICONS AGREED


VALUE OF WORK DONE
% Work
Done to
Date

REMARK

Value of Work Done


to Date

BILL 2 - FACTORY BUILDING

6,227,595,119

6,227,595,119

6,227,595,119

II

BILL 3 - OFFICE BUILDING

1,086,987,514

1,086,987,514

1,086,987,514

III

BILL 4A - MACHINE FOUNDATION AND WET


CAN TRENCH

928,801,839

928,801,839

928,801,839

ITEM 4C: WASTE WATER TREATMENT TANK 1

1,520,154

1,520,154

1,520,154

ITEM 4C: WASTE WATER TREATMENT TANK 2

3,578,898

3,578,898

3,578,898

.
V
.
V
.
VI

ITEM 4D - FOUNDATION FOR OIL & IC TANK

Not including

.
VII

ITEM 4E - D.I SYSTEM AND SOLUBLE AREA

.
VIII

ITEM 4F: CANTEEN

119,762,527

119,762,527

119,762,527

VIII

ITEM 4G: GUARDHOUSE AT MAIN ENTRANCE

(47,260,754)

(47,260,754)

(47,260,754)

IX

ITEM 4H: INTERNAL GUARDHOUSE NEAR


ROAD 19

(20,105,934)

(20,105,934)

(20,105,934)

ITEM 4I: LPG STORAGE

(79,478,744)

(79,478,744)

(79,478,744)

XI

ITEM 4J: STRUCK SCALE

156,834,033

156,834,033

156,834,033

6,034,500

6,034,500

6,034,500

.
XI

ITEM 4K: PLAG POLE

.
V

ITEM 4L: WASTE WATER TREATMENT TANK 3

(1,152,834)

(1,152,834)

(1,152,834)

BILL 4M: ADDITION ITEMS FOR FACTORY

(4,609,668)

(4,609,668)

(4,609,668)

BILL 4N: COMPRESSOR AND VACUUM FOUNDATION

BILL 4O: SCRAP SYSTEM TRENCH

BILL 4P: BALER ROOM

BILL 4Q: CHILER AND COOLING TOWER

BILL 4R: EUTRALIZATION TANK OF DI SYSTEM

616,468

616,468

616,468

.
XII

ITEM 5A - INTERNAL ROAD

XIII

ITEM 5B - DRAINAGE SYSTEM AND


SEWERAGE SYSTEM

XIV

ITEM 5C - TURFING

1,169,154,282

1,169,154,282

1,169,154,282

(1,623,861,156)

(1,623,861,156)

(1,623,861,156)

11,305,084

11,305,084

11,305,084

XV

ITEM 5D - UNDERGROUND FIRE WATER TANK


AND BUMP ROOM

XVI

ITEM 5E - FENCE AND GATE

XVI

ITEM 5F: DRAINAGE SYSTEM CONECTING


RAIN WATER DOWN PIPE TO DRAIN OF
INSPECTION MANHOLE

23,897,360
(173,693,435)

23,897,360
(173,693,435)

23,897,360
(173,693,435)

58,636,905

58,636,905

58,636,905

7,844,562,160

7,844,562,160

7,844,562,160

Addendum No.1

TOTAL CARRIED TO SUMMARY (Exclude. VAT)

Bill7 - Page 20/80

TBC - Ball Beverage Can Vietnam Limited

TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE, VIETNAM

SUMMARY OF BILL 8 - VARIATION WORKS


CURRENCY: VND
VALUE OF WORK DONE (Ending 20 June, 2012)
NO

ITEM

AMOUNT
approved value
(incl. VAT)

UNICONS' CLAIM
% Work Done to
Date

REMARK

ATELIER & UNICONS AGREED VALUE


OF WORK DONE

Value of Work Done % Work Done to


to Date
Date

Value of Work
Done to Date

EI-02 - Change shape of foundation of Fatory, office, fence &


guard house

237,819,252

100%

237,819,252

100%

237,819,252

EI-04 - Change dimension of beam of Factory and Office

194,421,563

100%

194,421,563

100%

194,421,563

EI-06 - Change top rebar of factory ground slap from weld


mesh d6 to weld mesh d10

2,546,499,652

100%

2,546,499,652

100%

2,546,499,652

EI-08 - Upgrade thickness of steel frame of wall cladding

731,446,818

100%

731,446,818

100%

731,446,818

EI-10,19 - Updated DIW tank

28,500,945

100%

28,500,945

100%

28,500,945

EI-11, 25 - Remove and addition foundations and ground


beams gird line F(15-18), F'(15-18), F-G(5-2)

92,050,531

100%

92,050,531

100%

92,050,531

EI-12 - updated uncoiler and upper press foundation

42,926,945

100%

42,926,945

100%

42,926,945

EI-15a - change roof sheet material

(480,642,184)

100%

(480,642,184)

100%

(480,642,184)

EI-15b - change wall sheet material

359,526,608

100%

359,526,608

100%

359,526,608

10

EI-16a - Adding Curb at corner of wall and slab of Factory

406,636,326

100%

406,636,326

100%

406,636,326

11

EI-16b - Increase the size of roof gutter of Factory

591,924,531

100%

591,924,531

100%

591,924,531

12

EI-17a - change alu. Frame of alu door and window

2,801,283,287

100%

2,801,283,287

100%

2,801,283,287

13

EI-17b - change thickness of roller door

751,113,993

100%

751,113,993

100%

751,113,993

14

EI-18 - change counter in WC

81,716,868

100%

81,716,868

100%

81,716,868

15

EI-20 - update WWTP, WTP

1,168,011,582

100%

1,168,011,582

100%

1,168,011,582

16

EI-21 - Omit the galvanized steel maintenance ladder inside all


Infrastructure Drainage & Sewerage Manholes

17

EI-22 - updated truck scale

(18,186,300)

100%

(18,186,300)

100%

(18,186,300)

74,458,704

100%

74,458,704

100%

74,458,704

Sum of Bill 8 - Page 21/80

TBC - Ball Beverage Can Vietnam Limited

18

19

EI-23 - Omit the drainage system inside the factory, including


all the pumps, piping, valves, pressure gauges, flexible joints
and electrical control (to be done by others). Additional drain
pipe and sump pit at cooling tower.
EI-24 - Revised height brick wall and wall cladding at Baler
room and Oil tank. Metal louver with frame at GL G/5-10

20

EI-26 - Revised invert level for manhole M1 to M7

21

EI-27- Updated bus duct layout & MSB1, 2 & 3


+ Change location of MSB 1, 2 & 3 so Busducts will be saved
+ Increase loading so circuit breakers in MSBs ang DBs will be
changed
+ Update the capacitor bank in MSB1, 2 & 3 from 750kVAr to
1000kVAr)

22

(690,631,767)

100%

(690,631,767)

100%

(690,631,767)

(56,577,193)

100%

(56,577,193)

100%

(56,577,193)

(17,325,271)

100%

(17,325,271)

100%

(17,325,271)

1,274,755,477

100%

1,274,755,477

100%

1,274,755,477

EI-28 - Extend the 10ton slab area up to GL 12+4.0m/D-F

101,683,826

100%

101,683,826

100%

101,683,826

23

EI-29 - Update WC05, Double ceiling, deduct 1st Utility, add


cover of roller door, painting downpipe

865,714,193

100%

865,714,193

100%

865,714,193

24

EI-30 - Update Earth bonding system

1,546,449,309

100%

1,546,449,309

100%

1,546,449,309

609,444,961

100%

609,444,961

100%

609,444,961

49,418,422

100%

49,418,422

100%

49,418,422

1,698,618,121

100%

1,698,618,121

100%

1,698,618,121

372,044,994

100%

372,044,994

100%

372,044,994

25

26

EI-32A - 1. To purchase and install the mechanical ventilation


system
as
per
approval
quotatation
no
TBCBALL/UNIC/PRO/M&E/01 dated 20/08/2011 -Rev No.5
2. This instruction will also supplement for EI No.14 dated 27
July 2011
3. The Contratcor will designer & buider and responsible for
this Mechanical Ventilation system
EI-33 - Add more Air-conditioner at transformer, Isolator &
Electric room

27

EI-34 - Change sika hardenner to Ashford formula

28

EI-35 - Updated plinth, gutter & top slab of WWTP, WTP & DI
plant

29

EI-36 - Updated office roof beam

29,733,665

100%

29,733,665

100%

29,733,665

30

EI-37 - Updated detail for additional system of water supply


and drainage for MC Shop & Lab Room

92,478,142

100%

92,478,142

100%

92,478,142

31

EI-38 - Additional stone layer axis GL 2-14/A-F

1,568,652,819

100%

1,568,652,819

100%

1,568,652,819

32

EI-39 - Updated M&E system in MC shop

393,967,995

100%

393,967,995

100%

393,967,995

33

EI-40 - Updated LPG storage

(347,098,545)

100%

(347,098,545)

100%

(347,098,545)

34

EI-41 - Updated opening at GL 14

111,062,484

100%

111,062,484

100%

111,062,484

35

EI-42 - Updated Walkway, Flag Pole

291,998,513

100%

291,998,513

100%

291,998,513

36

EI-43 - Updated Trench at ODM Room

340,292,157

100%

340,292,157

100%

340,292,157

Sum of Bill 8 - Page 22/80

TBC - Ball Beverage Can Vietnam Limited

37

EI-44, 49, 55, 64 - updated cooling tower

(654,177,145)

100%

(654,177,145)

100%

(654,177,145)

38

EI-45a - Bin center (C&S)

702,510,730

100%

702,510,730

100%

702,510,730

39

EI-45b - Bin center (M&E)

55,861,773

100%

55,861,773

100%

55,861,773

40

EI-46a - Guardhouse 2 (C&S)

194,323,104

100%

194,323,104

100%

194,323,104

41

EI-46b - Guardhouse 2 (M&E)

90,466,087

100%

90,466,087

100%

90,466,087

42

EI-47 - Epoxy coating for machine trench and D.I slab

1,958,231,053

100%

1,958,231,053

100%

1,958,231,053

43

EI-48 - Updated Louver at GL G

263,245,648

100%

263,245,648

100%

263,245,648

44

EI-50 - Updated Canopy 8m & 18m at GL 18

252,423,515

100%

252,423,515

100%

252,423,515

45

EI-51 - Updated body maker area

289,100,146

100%

289,100,146

100%

289,100,146

46

EI-52 - Omission of Windows S6 at Office at GL A/1-2 & GL G/12

(227,555,369)

100%

(227,555,369)

100%

(227,555,369)

47

EI-53 - updated baler room

917,367,633

100%

917,367,633

100%

917,367,633

48

EI-54 - updated beam smoke detector system

1,116,726,781

100%

1,116,726,781

100%

1,116,726,781

49

EI-56 - updated 03 rooms inside MC shop

143,233,475

100%

143,233,475

100%

143,233,475

50

EI-57 - Updated location of PDP - 1003

133,440,626

100%

133,440,626

100%

133,440,626

51

EI-58 - Updated ramp & Slope for Dock Leveler Bay

110,910,368

100%

110,910,368

100%

110,910,368

52

EI-59 - Updated Lighting & Socket for Baler room

134,329,578

100%

134,329,578

100%

134,329,578

53

EI-60 - omit loading office

(135,710,187)

100%

(135,710,187)

100%

(135,710,187)

54

EI-61 - update road axis G

906,825,255

100%

906,825,255

100%

906,825,255

55

EI-62 - updated Door and Windows of Warehouse Office at GL


18/A

147,605,232

100%

147,605,232

100%

147,605,232

56

EI-63 - omit West road

(1,992,837,200)

100%

57

EI-65a - Kitchen modification work for C&S

186,350,203

100%

186,350,203

100%

186,350,203

58

EI-65b - Kitchen modification work for M&E

84,037,522

100%

84,037,522

100%

84,037,522

59

EI-65c - Painting inside the factory & warehouse

1,083,435,548

100%

1,083,435,548

100%

1,083,435,548

60

EI-65d - VQ74-Changing size of HDPE Pipe

262,454,962

100%

262,454,962

100%

262,454,962

(1,992,837,200)

100%

(1,992,837,200)

Sum of Bill 8 - Page 23/80

TBC - Ball Beverage Can Vietnam Limited

61

EI-65e - VQ76-Install uPVC pipe from D.I unit to wahser

39,862,771

100%

39,862,771

100%

39,862,771

62

EI-65f - VQ78-Air compressor pipe for MC shop, Ink room, lab


room

30,233,401

100%

30,233,401

100%

30,233,401

63

EI-65g - VQ87-Additional street lighting

76,529,131

100%

76,529,131

100%

76,529,131

64

EI-65h - VQ82-Install LPG pipe, valve follow client require

132,592,581

100%

132,592,581

100%

132,592,581

65

EI-65i - VQ83-Water supply bypass pipe

53,441,794

100%

53,441,794

100%

53,441,794

66

EI-65j - VQ84-Earthing system for truck scale

47,812,582

100%

47,812,582

100%

47,812,582

67

EI-65k - VQ85-Additional lighting in MC shop

24,427,712

100%

24,427,712

100%

24,427,712

68

EI-65l - VQ77-Modify cooling tower pipe

196,347,769

100%

196,347,769

100%

196,347,769

69

EI-65m - VQ88-Additional 03 ceiling fans in guardhouse

18,217,464

100%

18,217,464

100%

18,217,464

70

EI-65n - VQ89-Additional control panel in D.I area

33,894,257

100%

33,894,257

100%

33,894,257

71

EI-65o - VQ91-Lighting for body maker, decorator chiller

49,986,125

100%

49,986,125

100%

49,986,125

72

EI-65p - VQ79-Install Power supply panel and cable for


Decorator chiller

41,214,762

100%

41,214,762

100%

41,214,762

73

EI-65q - Update curb, manhole West road (2 sides)

354,275,074

100%

354,275,074

100%

354,275,074

74

EI-65r - Connection road at main gate

400,453,911

100%

400,453,911

100%

400,453,911

75

EI-65s - Updated open drain

238,514,530

100%

238,514,530

100%

238,514,530

76

EI-65t - Backfilling temporary offices as Client require (scope of


TVT)

120,522,600

100%

120,522,600

100%

120,522,600

77

EI-65u - LPG cylinder storage

195,742,811

100%

195,742,811

100%

195,742,811

78

EI-65v - Additional steel doors at General storage room and


ODM room

49,674,177

100%

49,674,177

100%

49,674,177

79

EI-65x - Logo outside office wall

290,400,000

100%

290,400,000

100%

290,400,000

80

EI-65y - VQ99-Cacbon filter and louver

35,302,960

100%

35,302,960

100%

35,302,960

81

EI-65z - Additional Client requirements (17.03.2012) for (C&S


WWT control room, Warehouse office (item 7), SUS 304 cover
for FF tank (item 19), Cover of office staircase)

282,011,413

100%

282,011,413

100%

282,011,413

82

EI-65w - VQ86-Additional lighting in control rm of WWT

44,867,895

100%

44,867,895

100%

44,867,895

83

EI-65aa - Different between Tender and FC Dwg: Electrical


system

(1,276,808,103)

100%

84

EI-65bb - Different between Tender and FC Dwg: LPG system

113,928,406

100%

(1,276,808,103)
113,928,406

100%
100%

(1,276,808,103)
113,928,406

Sum of Bill 8 - Page 24/80

TBC - Ball Beverage Can Vietnam Limited

85

EI-65cc - Different between Tender and FC Dwg: Plumbing


system

86

EI-65dd - Motorbike parking

87

EI-65ee - Bitumen on west road

88

179,141,493

100%

179,141,493

100%

179,141,493

1,161,331,001

100%

1,161,331,001

100%

1,161,331,001

300,602,739

100%

300,602,739

100%

300,602,739

EI-66 - Reimburse soil transportation cost

(651,440,000)

100%

(651,440,000)

100%

(651,440,000)

89

EI-67 - Omit CCTV System

(305,525,058)

100%

(305,525,058)

100%

(305,525,058)

90

Change from PVC conduit to GI conduit

1,000,000,000

100%

1,000,000,000

100%

1,000,000,000

TOTAL CARRIED TO SUMMARY(Include. VAT)

27,144,346,960

27,144,346,960

27,144,346,960

Sum of Bill 8 - Page 25/80

MAIN TENDER PACKAGE FOR PROPOSED CONSTRUCTION AND COMPLETION OF TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SIN
TAN UYEN DISTRICT, BINH DUONG PROVINCE, VIETNAMPROJECT

VARIATION WORKS
Different between Tender and FC Drawing -Changing from PVC conduit to GI conduit

VALUE OF WORK DONE (E


AMOUNT
NO

DESCRIPTION

UNIT

QTY

UNIT RATE

UNICONS' CLAIM

LABOR
Contract value

% Work
Done to
Date

A. LPG pipe
G.I Pipe D32

7,946

153,563

PVC conduit D32

(7,946)

22,828

17,063
incl.

1,355,815,752
(181,394,172)

TOTAL (Not included V.A.T)

1,174,421,580

TOTAL CARRIED TO SUMMARY OF THIS V.O (Include. VAT)

1,291,863,738

DISCOUNT (Include VAT)


TOTAL CARRIED TO SUMMARY OF THIS V.O (Include Discount + VAT)

(291,863,738)
1,000,000,000

100%
100%

MPLETION OF TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A,

CURRENCY: VND
VALUE OF WORK DONE (Ending 29 Oct, 2011)
UNICONS' CLAIM
Value of Work
Done to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
% Work
Value of Work
Done to
Done to Date
Date

1,355,815,752.04

100%

1,355,815,752

(181,394,171.98)

100%

(181,394,172)

1,174,421,580

1,174,421,580

1,291,863,738

1,291,863,738

(291,863,738)
1,000,000,000

(291,863,738)
1,000,000,000

REMARK

PROJECT

: MAIN TENDER PACKAGE FOR PROPOSED CONSTRUCTION AND COMPLETION OF TBC-BALL BEVERAGE CAN FACTORY AT STREET
NO.18, VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE, VIETNAM

BILL 6

: M.E.P SERVICES

SUMMARY - REVISION 2 - 03 JUNE 2011


VALUE OF WORK DONE (Ending 20 June, 2012)
AMOUNT
UNICONS' CLAIM
NO

DESCRIPTION
Contract value

6A

ELECTRICAL SERVICES

% Work
Done to
Date

Value of Work
Done to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
% Work
Done to
Date

Value of Work
Done to Date

48,891,763,929

100%

48,891,763,929

100%

48,891,763,929

445,500,000

100%

445,500,000

100%

445,500,000

6A.1

Sub-Total for Designing & supervising of High


Voltage System

6A.2

Sub-Total for High Voltage System

2,827,256,788

100%

2,827,256,788

100%

2,827,256,788

6A.3

Sub-Total for Transformers

7,574,078,650

100%

7,574,078,650

100%

7,574,078,650

6A.4

Sub-Total for Incoming High Voltage Cables

2,658,391,835

100%

2,658,391,835

100%

2,658,391,835

6A.5

Sub-Total for Underground HV Cable Pipe Ducts

418,392,100

100%

418,392,100

100%

418,392,100

6A.6

Sub-Total for LV Switchboards

4,577,708,002

100%

4,577,708,002

100%

4,577,708,002

6A.7

Sub-Total for Distribution Boards

2,272,997,674

100%

2,272,997,674

100%

2,272,997,674

6A.8

Sub-Total for Distribution Submains Cables

9,572,462,512

100%

9,572,462,512

100%

9,572,462,512

6A.9

Sub-Total for Final Subcircuit Wiring

461,371,628

100%

461,371,628

100%

461,371,628

6A.10

Sub-Total for Light Fitting and Small Power


Installation

8,991,057,775

100%

8,991,057,775

100%

8,991,057,775

6A.11

Sub-Total for Lightning Protection System

1,597,098,952

100%

1,597,098,952

100%

1,597,098,952

6A.12

Sub-Total for Main Earthing System

212,196,190

100%

212,196,190

100%

212,196,190

6A.13

Sub-Total for Street Lightings and Landscape


Lighting

1,216,028,850

100%

1,216,028,850

100%

1,216,028,850

6A.14

Sub-Total for CCTV System

6A.15

Sub-Total for Fire Alarm System

6A.16
6A.17

614,550,053

100%

614,550,053

100%

614,550,053

1,381,548,071

100%

1,381,548,071

100%

1,381,548,071

Sub-Total for Telephone/Data system

354,601,934

100%

354,601,934

100%

354,601,934

Sub-Total for PA system

297,600,564

100%

297,600,564

100%

297,600,564

6A.18

Sub-Total for Testing and Commissioning

210,100,000

100%

210,100,000

100%

210,100,000

6A.19

Sub-Total for Licensing

6A.20

Sub-Total for Maintenance and Warranty

198,000,000

100%

198,000,000

100%

198,000,000

6A.21

Sub-Total for Fire Stopping

46,200,000

100%

46,200,000

100%

46,200,000

6A.22

Sub-Total for Others works

2,964,622,349

100%

2,964,622,349

100%

2,964,622,349

MECHANICAL SERVICES

26,168,986,926

100%

26,168,986,926

100%

26,168,986,926

1,028,903,540
6,972,355,289

100%
100%

1,028,903,540
6,972,355,289

100%
100%

1,028,903,540
6,972,355,289

6B

Included

6B.1
6B.2

Sub-Total for Mechanical Ventilation System


Sub-Total for Air-conditioning

6B.3

Sub-Total for Automatic Sprinkler System

10,582,355,055

100%

10,582,355,055

100%

10,582,355,055

6B.4

Sub-Total for Hosereel System

1,050,837,129

100%

1,050,837,129

100%

1,050,837,129

6B.5

Sub-Total for External Fire Hydrant

2,026,254,513

100%

2,026,254,513

100%

2,026,254,513

6B.6

Sub-Total for Portable Fire Extinguishers

136,077,063

100%

136,077,063

100%

136,077,063

6B.7

Sub-Total for Cold Water System

1,894,490,054

100%

1,894,490,054

100%

1,894,490,054

6B.8

Sub-Total for Sanitary Drainage System

371,887,056

100%

371,887,056

100%

371,887,056

6B.9

Sub-Total for Testing and Commissioning

237,000,000

100%

237,000,000

100%

237,000,000

6B.10

Sub-Total for Maintenance and Warranty

240,000,000

100%

240,000,000

100%

240,000,000

6B.11

Sub-Total for Fire Stopping

60,000,000

100%

60,000,000

100%

60,000,000

6B.12

Sub-Total for Others works

1,568,827,228

100%

1,568,827,228

100%

1,568,827,228

75,060,750,855

100%

75,060,750,855

100%

75,060,750,855

Total Lump Sum Tender Price Carried To Final Summary

REM
ARK

PROJECT

MAIN
TENDER
PACKAGE
FOR
PROPOSED
CONSTRUCTION AND COMPLETION OF TBC-BALL
BEVERAGE CAN FACTORY AT STREET NO.18,
VIETNAM SINGAPORE INDUSTRIAL PARK II-A,
TAN UYEN DISTRICT, BINH DUONG PROVINCE,

BILL 6

M.E.P SERVICES

BILL 6.1

BREAKDOWN OF LUMP SUM PRICES - Revision2 - Dated: 03 June 2011

The itemised Breakdown of the Lump Sum Tender Price as listed below shall form only as an indication of the breakdown value for this contract
works. The tenderer shall price the contract works in accordance with the Tender Drawings and Documents. No claim for extra or otherwise
shall be considered for any trade/items/works as specified and shown in the Tender Drawings and Specifications but not described hereunder.

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

6A
6A.1

6A.2

ELECTRICAL SERVICES
Designing
& supervising of High
Voltage System
Designing, supervising fee for 22kV
Transmission lines & Power substation
c/w liaise and plan submission to the
local Power Company including all
necessary cost for the connection of
new HV cables to their existing HV
network
High Voltage System

panel

Value of Work Done


to Date

48,891,763,929

48,891,763,929

445,500,000

445,500,000

445,500,000

445,500,000

100%

445,500,000

100%

2,827,256,788

445,500,000

2,827,256,788

932,916,265

100%

932,916,265

100%

932,916,265

543,750,733

100%

543,750,733

100%

543,750,733

100%

1,106,997,698

100%

1,106,997,698

ii)

630A
bus-coupler
including circuit breaker

iii)

630A
transformer
panels
including circuit breaker

1,106,997,698

One lot 22KV cables from


consumers' HV switchroom to
Transformers complete with
iv)
termination to the HV switch
board and transformers and
also provides cable supports

218,418,893

XLPE/SEhh/PVC/DSTA/PVC22kV-3C-300mm2

Value of Work Done


to Date

%
Work
Done
to
Date

48,891,763,929

2,827,256,788

Supply, delivery and installation of


22KV switchboard c/w protection
relays, floor frames, cable boxes and
all accessories, etc.
630A incoming panels including
i)
circuit breakers

218,418,893

218,418,893

178,877,178

100%

178,877,178

100%

178,877,178

Termination Kit 3C-300mm2


Accessories

33,180,000
6,361,715

100%
100%

33,180,000
6,361,715
-

100%
100%

33,180,000
6,361,715
-

Supply
&
installation
HV
v) metering panel including CT &
PT, metering nad all accessories

25,173,200

PT 24KV (dry type)


CT 24KV (dry type)
Measuring Meter c/w box
Accessories
6A.3

%
Work
Done
to
Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

Transformers

9,990,000
9,990,000
4,460,000
733,200

25,173,200
100%
100%
100%
100%

7,574,078,650

9,990,000
9,990,000
4,460,000
733,200
-

25,173,200
100%
100%
100%
100%

7,574,078,650

7,574,078,650

Supply, delivery and installation of


a) oil silicon type transformers with
fittings, cables boxes and etc
i) Transformer 1
ii) Transformer 2

9,990,000
9,990,000
4,460,000
733,200
-

1,541,550,000
1,541,550,000

100%
100%

Page 29 of 80

1,541,550,000
1,541,550,000

100%
100%

1,541,550,000
1,541,550,000

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

3
iii) Transformer
ELECTRICAL
SERVICES
Supply, delivery
and installation of
LV
Bus
duct/cables
from
Transformers to MSB complete
with termination to the MSB &
b)
transformers,
ladder/tray/
trunking/underground
pipe
enscated in concrete and provides
cable supports
i) Transformer 1 to MSB 1
Feeder 4000A 3P5W Copper c/w
intergral earth IP54
Elbow
Flange
End
Flex link
Short link bar (TX)
Horz. Hanger
Acc
ii) Transformer 2 to MSB 2
Feeder 4000A 3P5W Copper c/w
intergral earth IP54

1,541,550,000

%
Work
Done
to
Date
100%

Value of Work Done


to Date
1,541,550,000

%
Work
Done
to
Date
100%

Value of Work Done


to Date
1,541,550,000

2,949,428,650

2,949,428,650

2,949,428,650

1,009,395,590

1,009,395,590

1,009,395,590

866,339,320

100%

866,339,320

100%

866,339,320

38,028,800

100%

38,028,800

100%

38,028,800

33,124,260

100%

33,124,260

100%

33,124,260

20,384,800

100%

20,384,800

100%

20,384,800

39,147,000

100%

39,147,000

100%

39,147,000

1,976,410
10,395,000

100%
100%

1,976,410
10,395,000
-

100%
100%

1,976,410
10,395,000
-

1,009,395,590

1,009,395,590

1,009,395,590

866,339,320

100%

866,339,320

100%

866,339,320

Elbow

38,028,800

100%

38,028,800

100%

38,028,800

Flange End

33,124,260

100%

33,124,260

100%

33,124,260

Flex link

20,384,800

100%

20,384,800

100%

20,384,800

Short link bar (TX)

39,147,000

100%

39,147,000

100%

39,147,000

Horz. Hanger
Acc

1,976,410
10,395,000

100%
100%

1,976,410
10,395,000
-

100%
100%

1,976,410
10,395,000
-

iii) Transformer 3 to MSB 3


Feeder 4000A 3P5W Copper c/w
intergral earth IP54

6A.4

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

930,637,470

930,637,470

930,637,470

787,581,200

100%

787,581,200

100%

787,581,200

Elbow

38,028,800

100%

38,028,800

100%

38,028,800

Flange End

33,124,260

100%

33,124,260

100%

33,124,260

Flex link

20,384,800

100%

20,384,800

100%

20,384,800

Short link bar (TX)

39,147,000

100%

39,147,000

100%

39,147,000

Horz. Hanger
Acc

1,976,410
10,395,000

100%
100%

1,976,410
10,395,000
-

100%
100%

1,976,410
10,395,000
-

Incoming High Voltage Cables

2,658,391,835

2,658,391,835

2,658,391,835

Supply, delivery and installation of


Reclosed, DS, eletrical pole 22KV
Cables run in underground cable pipe
ducts complete with termination to HV
switchboard, cable support, excavation
of drawpits including backfilling and
making good of the land in the area of
work, accessories and etc. for.
Supply, delivery and installation of
a) Reclosed, DS 63A - 24kV for Switch
On/Off & Lines Protection
Reclosure 24kV-630A with control
Au. Power and FCO for recloser
DS 630A-24kV-25kA/1s with
LA 18KV

1,066,392,000

1,066,392,000

1,066,392,000

994,124,000
2,260,000
32,352,000

100%
100%
100%

994,124,000
2,260,000
32,352,000

100%
100%
100%

994,124,000
2,260,000
32,352,000

37,656,000

100%

37,656,000

100%

37,656,000

Page 30 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

Supply, delivery
and installation of
ELECTRICAL
SERVICES
1 set of incoming HV 22KV Cable
from authority HV network of
b)
12(14)m
height pole
to HV
Switchroom c/w terminal kit and
also provides cable supports
Concrete pole 14m + 02 anchor
Cross Arm. Galv. Steel.
24KV Pin insulator + tige
Horizontal insulator polymer 24KV
Earthing system under 4Ohm
High-Voltage Overhead cable.

%
Work
Done
to
Date

1,591,999,835

Value of Work Done


to Date

%
Work
Done
to
Date

1,591,999,835

1,591,999,835

100%
100%
100%
100%
100%
100%

13,290,000
15,216,000
8,209,200
10,645,800
37,520,000
110,300,000

100%
100%
100%
100%
100%
100%

13,290,000
15,216,000
8,209,200
10,645,800
37,520,000
110,300,000

1,341,578,835

100%

1,341,578,835

100%

1,341,578,835

22kV termination 3Cx240mm2

44,240,000

100%

44,240,000

100%

44,240,000

Acc

11,000,000

100%

11,000,000
-

100%

11,000,000
-

cable
3Cx300mm2

To liaise and plan submission to the


local Power Company including all
c) necessary cost for the connection
of new HV cables to their existing
HV network
Underground Electrical Cable Pipe
Ducts
Supplying
and
installation
of
underground HD uPVC cable ducts and
draw
pits
for
Electrical
cables
reticulation network including all the
excavation, reinstatement remain of
excess earth and debris, if necessary
and making good of the land in the
area of work.
Heavy Duty uPVC pipes encased
i)
in concrete or in trench

HD uPVC conduit D168mm (4


line)
Exavation & fillback (sand,
brick.)
Concrete encasement
Electric maker
Accessories.
ii) Draw pits

Included
418,392,100

418,392,100

418,392,100

350,024,900

350,024,900

350,024,900

123,084,200

100%

123,084,200

100%

123,084,200

74,505,200

100%

74,505,200

100%

74,505,200

113,107,500
6,178,000
33,150,000

100%
100%
100%

113,107,500
6,178,000
33,150,000

100%
100%
100%

113,107,500
6,178,000
33,150,000

68,367,200

68,367,200

68,367,200

Mainhole type A &B

45,915,200

100%

45,915,200

100%

45,915,200

Manhole cover heavy duty


40Tons

22,452,000

100%

22,452,000

100%

22,452,000

6A.6

Value of Work Done


to Date

13,290,000
15,216,000
8,209,200
10,645,800
37,520,000
110,300,000

underground
Cu/PVC/XLPE/DSTA
(2line)

6A.5

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

LV Switchboards
Supplying and installation of LV Main
Switchboards,
Emergency
Main
Switchboards and Sub-Switchboards
complete
with
circuit
breakers,
metering, (meter Supply, delivery and
installation of by power company)
protection devices, terminal blocks,
cable boxes, and etc at LT consumer
switch room.
a) MSB 1

4,577,708,002

4,577,708,002

4,577,708,002

1,458,434,374

100%

Page 31 of 80

1,458,434,374

100%

1,458,434,374

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

%
Work
Done
to
Date

Value of Work Done


to Date

1,579,992,338

100%

1,579,992,338

100%

1,579,992,338

c) MSB 3

1,539,281,290

100%

1,539,281,290

100%

1,539,281,290

Distribution boards
Supplying
and
installation
of
Distribution boards complete with
busbars, MCCBs/MCBs/RCCBs/Tap off
Unit,
time
switches,cables,
from
LVMSB or EMSB to these DBs including
cable tray or trunking and other
accessories, and etc.
a) DB-ACMV
b) DB-LCT
c) DB-CH 1
d) DB-CH 2
e) DB-EFP
f) DB-FAF1
g) DB-FAF2
h) DB-EAF1
i) DB-EAF2
j) DB-WS
k) DB-OFFICE
l) DB-FAF&EAF
m
DB-GH
)
n) DB-SWP
o) DB-1-1
p) DB-1-2
q) DB-1-3
r) DB-2-1
s) DB-2-2
t) DB-EL
u) DB-L-1
v) DB-L-2

2,272,997,674

2,272,997,674

2,272,997,674

81,625,037
340,257,919
51,833,551
51,833,551
170,883,691
192,575,885
192,575,885
161,309,830
161,309,830
44,037,961
29,319,500
210,410,620

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

81,625,037
340,257,919
51,833,551
51,833,551
170,883,691
192,575,885
192,575,885
161,309,830
161,309,830
44,037,961
29,319,500
210,410,620

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

81,625,037
340,257,919
51,833,551
51,833,551
170,883,691
192,575,885
192,575,885
161,309,830
161,309,830
44,037,961
29,319,500
210,410,620

15,208,375

100%

15,208,375

100%

15,208,375

18,779,704
6,261,837
15,982,814
6,261,837
12,948,259
13,385,623
30,208,002
19,368,489
19,368,489

100%
100%
100%
100%
100%
100%
100%
100%
100%

18,779,704
6,261,837
15,982,814
6,261,837
12,948,259
13,385,623
30,208,002
19,368,489
19,368,489

100%
100%
100%
100%
100%
100%
100%
100%
100%

18,779,704
6,261,837
15,982,814
6,261,837
12,948,259
13,385,623
30,208,002
19,368,489
19,368,489

w) DB-L-3

19,368,489

100%

19,368,489

100%

19,368,489

DB-L-4
DB-L-5
DB-L-6

16,239,571
14,693,545
15,732,422

100%
100%
100%

16,239,571
14,693,545
15,732,422

100%
100%
100%

16,239,571
14,693,545
15,732,422

DB-ODU 01

82,869,297

100%

82,869,297

100%

82,869,297

DB-ODU 02

72,695,595

100%

72,695,595

100%

72,695,595

DB-AHU 01

19,752,746

100%

19,752,746

100%

19,752,746

DB-AHU 02

19,752,746

100%

19,752,746

100%

19,752,746

DB-AC-CANTEEN

51,812,635

100%

51,812,635

100%

51,812,635

114,333,940

100%

114,333,940

100%

114,333,940

x)
y)
z)
aa
)
ab
)
ac
)
ad
)
ae
)
af
)
ag
)
ah
)
6A.8

Value of Work Done


to Date

%
Work
Done
to
Date

ELECTRICAL
SERVICES
MSB 2
b)

Bus bar for busduct 4000A


6A.7

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

DB-AC 1
DB-LPG

100%

100%

DB-DOCK

100%

100%

Distribution Submains Cables

9,572,462,512

Page 32 of 80

9,572,462,512

9,572,462,512

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

DESCRIPTION
Contract value

%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

Supplying
andSERVICES
installation of Submain
ELECTRICAL
cables
complete
with
ladder/tray/trunking/underground pipe
enscated in concrete completed with
termination, cable support, excavation
and
backfilling,
manholes
and
accessories, etc.

a) From MSB 1~3 to :

i)

DB-ACMV

683,394,678

683,394,678

683,394,678

592,310,871

100%

592,310,871

100%

592,310,871

Cu/PVC 1C-185mm2

72,864,553

100%

72,864,553

100%

72,864,553

Accessories

18,219,254

100%

18,219,254
229,975,253

100%

18,219,254
229,975,253

199,101,095

100%

199,101,095

100%

199,101,095

24,744,143

100%

24,744,143

100%

24,744,143

6,130,015

100%

6,130,015
117,741,608

100%

6,130,015
117,741,608

101,408,863

100%

101,408,863

100%

101,408,863

13,189,114

100%

13,189,114

100%

13,189,114

3,143,631

100%

3,143,631
64,672,986

100%

3,143,631
64,672,986

Cu/XLPE/PVC 1C-185mm2

ii) DB-LCT

Cu/XLPE/PVC 1C-240mm2
Cu/PVC 1C-120mm2
Accessories
iii) DB-CH 1

Cu/XLPE/PVC 1C-70mm2
Cu/PVC 1C-35mm2
Accessories
iv) DB-CH 2

229,975,253

117,741,608

64,672,986
55,682,685

100%

55,682,685

100%

55,682,685

Cu/PVC 1C-35mm2

7,263,570

100%

7,263,570

100%

7,263,570

Accessories

1,726,732

100%

1,726,732
915,748,969

100%

1,726,732
915,748,969

796,988,784

100%

796,988,784

100%

796,988,784

Cu/PVC 1C-185mm2

94,350,255

100%

94,350,255

100%

94,350,255

Accessories

24,409,930

100%

24,409,930
224,029,446

100%

24,409,930
224,029,446

195,170,843

100%

195,170,843

100%

195,170,843

22,886,943

100%

22,886,943

100%

22,886,943

5,971,660

100%

5,971,660
286,079,841

100%

5,971,660
286,079,841

249,028,114

100%

249,028,114

100%

249,028,114

29,426,070

100%

29,426,070

100%

29,426,070

7,625,658

100%

7,625,658
151,480,731

100%

7,625,658
151,480,731

131,863,888

100%

131,863,888

100%

131,863,888

15,579,646

100%

15,579,646

100%

15,579,646

4,037,197

100%

4,037,197
-

100%

4,037,197
-

Cu/XLPE/PVC 1C-70mm2

v) DB-EFP

Cu/FR/PVC 1C-185mm2

vii) DB-FAF1

Cu/FR/PVC 1C-185mm2
Cu/PVC 1C-185mm2
Accessories
vi) DB-FAF2

Cu/FR/PVC 1C-185mm2
Cu/PVC 1C-185mm2
Accessories
vii) DB-EAF1

Cu/FR/PVC 1C-240mm2
Cu/PVC 1C-120mm2
Accessories

915,748,969

224,029,446

286,079,841

151,480,731

Page 33 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
viii)DB-EAF2

%
Work
Done
to
Date

191,387,336

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

191,387,336

Value of Work Done


to Date

191,387,336

166,430,150

100%

166,430,150

100%

166,430,150

19,856,411

100%

19,856,411

100%

19,856,411

5,100,775

100%

5,100,775
268,424,273

100%

5,100,775
268,424,273

230,395,682

100%

230,395,682

100%

230,395,682

30,869,396

100%

30,869,396

100%

30,869,396

Accessories

7,159,194

100%

100%

ix) DB-OFFICE

230,539,860

7,159,194
230,539,860

7,159,194
230,539,860

195,883,273

100%

195,883,273

100%

195,883,273

28,507,224

100%

28,507,224

100%

28,507,224

6,149,363

100%

6,149,363
169,087,281

100%

6,149,363
169,087,281

143,647,733

100%

143,647,733

100%

143,647,733

20,929,355

100%

20,929,355

100%

20,929,355

4,510,193

100%

4,510,193
192,167,278

100%

4,510,193
192,167,278

167,261,596

100%

167,261,596

100%

167,261,596

19,757,497

100%

19,757,497

100%

19,757,497

5,148,184

100%

5,148,184
52,096,994

100%

5,148,184
52,096,994

41,148,468

100%

41,148,468

100%

41,148,468

Cu/PVC 1C-16mm2

9,547,881

100%

9,547,881

100%

9,547,881

Accessories

1,400,644

100%

1,400,644
519,815,456

100%

1,400,644
519,815,456

450,597,216

100%

450,597,216

100%

450,597,216

Cu/PVC 1C-240mm2

55,363,578

100%

55,363,578

100%

55,363,578

Accessories

13,854,662

100%

13,854,662
526,853,107

100%

13,854,662
526,853,107

450,597,216

100%

450,597,216

100%

450,597,216

Cu/PVC 1C-200mm2

62,213,074

100%

62,213,074

100%

62,213,074

Accessories

14,042,817

100%

14,042,817
420,095,996

100%

14,042,817
420,095,996

363,700,006

100%

363,700,006

100%

363,700,006

Cu/PVC 1C-300mm2

45,198,562

100%

45,198,562

100%

45,198,562

Accessories

11,197,427

100%

11,197,427
585,578,853

100%

11,197,427
585,578,853

Cu/FR/PVC 1C-240mm2
Cu/PVC 1C-120mm2
Accessories
ix) DB-WS

Cu/XLPE/PVC 1C-185mm2
Cu/PVC 1C-95mm2

Cu/XLPE/PVC 1C-120mm2
Cu/PVC 1C-70mm2
Accessories
ix) DB-FAF&EAF

Cu/XLPE/PVC 1C-120mm2
Cu/PVC 1C-70mm2
Accessories
ix) DB-GH

Cu/XLPE/PVC 1C-35mm2
Cu/PVC 1C-16mm2
Accessories
x) DB-SWP

Cu/XLPE/PVC 1C-16mm2

xi) DB-01 (#1001)

Cu/XLPE/PVC 1C-240mm2

xii) DB-02 (#1002)

Cu/XLPE/PVC 1C-240mm2

xiii)DB-03 (#1003)

Cu/XLPE/PVC 1C-300mm2

xiv)DB-04 (#1004)

268,424,273

169,087,281

192,167,278

52,096,994

519,815,456

526,853,107

420,095,996

585,578,853

Page 34 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
Cu/XLPE/PVC
1C-240mm2

%
Work
Done
to
Date

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

Value of Work Done


to Date

507,307,125

100%

507,307,125

100%

507,307,125

Cu/PVC 1C-240mm2

62,664,270

100%

62,664,270

100%

62,664,270

Accessories

15,607,457

100%

15,607,457
333,060,235

100%

15,607,457
333,060,235

287,248,020

100%

287,248,020

100%

287,248,020

36,931,430

100%

36,931,430

100%

36,931,430

8,880,785

100%

8,880,785
428,035,321

100%

8,880,785
428,035,321

370,463,648

100%

370,463,648

100%

370,463,648

Cu/PVC 1C-120mm2

46,161,488

100%

46,161,488

100%

46,161,488

Accessories

11,410,186

100%

11,410,186
816,380,871

100%

11,410,186
816,380,871

707,272,166

100%

707,272,166

100%

707,272,166

Cu/PVC 1C-185mm2

87,344,048

100%

87,344,048

100%

87,344,048

Accessories

21,764,656

100%

21,764,656
217,036,708

100%

21,764,656
217,036,708

186,871,241

100%

186,871,241

100%

186,871,241

24,378,536

100%

24,378,536

100%

24,378,536

5,786,930

100%

5,786,930
302,241,441

100%

5,786,930
302,241,441

260,200,463

100%

260,200,463

100%

260,200,463

33,982,202

100%

33,982,202

100%

33,982,202

8,058,777

100%

8,058,777
265,375,098

100%

8,058,777
265,375,098

228,503,315

100%

228,503,315

100%

228,503,315

29,795,989

100%

29,795,989

100%

29,795,989

7,075,795

100%

7,075,795
198,234,011

100%

7,075,795
198,234,011

170,786,122

100%

170,786,122

100%

170,786,122

22,162,306

100%

22,162,306

100%

22,162,306

5,285,584

100%

5,285,584
92,403,178

100%

5,285,584
92,403,178

79,950,345

100%

79,950,345

100%

79,950,345

Cu/PVC 1C-50mm2

9,986,487

100%

9,986,487

100%

9,986,487

Accessories

2,466,346

100%

2,466,346
94,977,195

100%

2,466,346
94,977,195

xv) DB-05 (#1005)

Cu/XLPE/PVC 1C-240mm2
Cu/PVC 1C-120mm2
Accessories
xvi)DB-06 (#1006)

Cu/XLPE/PVC 1C-240mm2

xvii)DB-07 (#1007)

Cu/XLPE/PVC 1C-185mm2

xviii)
DB-08 (#1008)

Cu/XLPE/PVC 1C-185mm2
Cu/PVC 1C-95mm2
Accessories
xix)DB-CDM

Cu/XLPE/PVC 1C-185mm2
Cu/PVC 1C-95mm2
Accessories
xx) DB-WTP

Cu/XLPE/PVC 1C-185mm2
Cu/PVC 1C-95mm2
Accessories
xxi)DB-SPB

Cu/XLPE/PVC 1C-185mm2
Cu/PVC 1C-95mm2
Accessories
xxii)DB-VAP 1

Cu/XLPE/PVC 1C-95mm2

xxiii)
DB-VAP 2

333,060,235

428,035,321

816,380,871

217,036,708

302,241,441

265,375,098

198,234,011

92,403,178

94,977,195

Cu/XLPE/PVC 1C-95mm2

82,205,997

100%

82,205,997

100%

82,205,997

Cu/PVC 1C-50mm2

10,236,149

100%

10,236,149

100%

10,236,149

Page 35 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
Accessories

100%

2,535,048
298,014,616

258,308,096

100%

258,308,096

100%

258,308,096

31,761,472

100%

31,761,472

100%

31,761,472

7,945,048

100%

7,945,048
311,605,483

100%

7,945,048
311,605,483

270,135,389

100%

270,135,389

100%

270,135,389

33,162,713

100%

33,162,713

100%

33,162,713

8,307,380

100%

8,307,380
385,928,409

100%

8,307,380
385,928,409

334,095,337

100%

334,095,337

100%

334,095,337

Cu/PVC 1C-120mm2

41,545,339

100%

41,545,339

100%

41,545,339

Accessories

10,287,734

100%

10,287,734
-

100%

10,287,734
-

Cu/PVC 1C-185mm2
Accessories
xxv)DB-ACR 2

Cu/XLPE/PVC 1C-185mm2
Cu/PVC 1C-185mm2
Accessories
xxvi)
DB-WR 1

Cu/XLPE/PVC 1C-240mm2

Final Subcircuit Wiring

298,014,616

311,605,483

385,928,409

461,371,628

461,371,628

461,371,628

Supply, deliver and install final


Subcircuit wiring for contruction
including
wiring,
a) areas
trunking/conduits,
conduit
accessories and etc to DBs
i)

Value of Work Done


to Date

2,535,048
298,014,616

Cu/XLPE/PVC 1C-185mm2

6A.9

Value of Work Done


to Date

%
Work
Done
to
Date

100%

xxiv)
DB-ACR 1

2,535,048

%
Work
Done
to
Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

DB-1-1

2,461,711

2,461,711

2,461,711

Cu/PVC 1C-8mm2

1,860,599

100%

1,860,599

100%

1,860,599

Cu/PVC 1C-8mm2

471,701

100%

471,701

100%

471,701

Accessories

129,411

100%

129,411
25,339,891

100%

129,411
25,339,891

ii) DB-1-2

25,339,891

Cu/PVC 1C-25mm2

20,613,728

100%

20,613,728

100%

20,613,728

Cu/PVC 1C-16mm2

3,403,205

100%

3,403,205

100%

3,403,205

Accessories

1,322,958

100%

1,322,958
18,725,598

100%

1,322,958
18,725,598

iii) DB-1-3

18,725,598

Cu/PVC 1C-8mm2

14,203,446

100%

14,203,446

100%

14,203,446

Cu/PVC 1C-8mm2

3,537,759

100%

3,537,759

100%

3,537,759

984,393

100%

984,393
17,992,837

100%

984,393
17,992,837

Accessories
iv) DB-2-1

17,992,837

Cu/PVC 1C-25mm2

14,642,855

100%

14,642,855

100%

14,642,855

Cu/PVC 1C-16mm2

2,410,604

100%

2,410,604

100%

2,410,604

939,379

100%

939,379
30,862,651

100%

939,379
30,862,651

Accessories
v) DB-2-2

30,862,651

Cu/PVC 1C-25mm2

25,091,882

100%

25,091,882

100%

25,091,882

Cu/PVC 1C-16mm2

4,159,473

100%

4,159,473

100%

4,159,473

Accessories

1,611,295

100%

1,611,295
-

100%

1,611,295
-

Page 36 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

ELECTRICAL
vii) DB-EL SERVICES

%
Work
Done
to
Date

5,903,567

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

5,903,567

Value of Work Done


to Date

5,903,567

4,885,614

100%

4,885,614

100%

4,885,614

Cu/PVC 1C-16mm2

709,001

100%

709,001

100%

709,001

Accessories

308,951

100%

308,951
10,423,458

100%

308,951
10,423,458

Cu/XLPE/PVC 1C-25mm2

vi) DB-L-1

10,423,458

Cu/PVC 1C-35mm2

8,792,743

100%

8,792,743

100%

8,792,743

Cu/PVC 1C-16mm2

1,087,135

100%

1,087,135

100%

1,087,135

543,581

100%

543,581
11,430,676

100%

543,581
11,430,676

Accessories
vii) DB-L-2

11,430,676

Cu/PVC 1C-35mm2

9,652,902

100%

9,652,902

100%

9,652,902

Cu/PVC 1C-16mm2

1,181,669

100%

1,181,669

100%

1,181,669

596,105

100%

596,105
12,337,063

100%

596,105
12,337,063

Accessories
viii)DB-L-3

12,337,063

Cu/PVC 1C-35mm2

10,417,489

100%

10,417,489

100%

10,417,489

Cu/PVC 1C-16mm2

1,276,202

100%

1,276,202

100%

1,276,202

643,373

100%

643,373
13,344,280

100%

643,373
13,344,280

Accessories
ix) DB-L-4

13,344,280

Cu/PVC 1C-35mm2

11,277,648

100%

11,277,648

100%

11,277,648

Cu/PVC 1C-16mm2

1,370,735

100%

1,370,735

100%

1,370,735

695,897

100%

695,897
15,206,932

100%

695,897
15,206,932

Accessories
ix) DB-L-5

15,206,932

Cu/PVC 1C-35mm2

12,806,821

100%

12,806,821

100%

12,806,821

Cu/PVC 1C-16mm2

1,607,069

100%

1,607,069

100%

1,607,069

793,041

100%

793,041
16,214,149

100%

793,041
16,214,149

Accessories
ix) DB-L-6

16,214,149

Cu/PVC 1C-35mm2

13,666,980

100%

13,666,980

100%

13,666,980

Cu/PVC 1C-16mm2

1,701,603

100%

1,701,603

100%

1,701,603

Accessories

845,566

100%

100%

ix) DB-ODU 01

12,857,898

845,566
12,857,898

845,566
12,857,898

10,468,044

100%

10,468,044

100%

10,468,044

1,720,319

100%

1,720,319

100%

1,720,319

Accessories

669,535

100%

100%

x) DB-ODU 02

14,459,370

669,535
14,459,370

669,535
14,459,370

11,794,979

100%

11,794,979

100%

11,794,979

Cu/XLPE/PVC 1C-50mm2
Cu/PVC 1C-35mm2

Cu/XLPE/PVC 1C-50mm2

1,911,466

100%

1,911,466

100%

1,911,466

Accessories

752,925

100%

100%

xi) DB-AHU 01

38,130,229

752,925
38,130,229

752,925
38,130,229

Cu/PVC 1C-35mm2

Page 37 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
Cu/XLPE/PVC
1C-35mm2

%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

32,311,899

100%

32,311,899

100%

32,311,899

Cu/PVC 1C-16mm2

3,828,606

100%

3,828,606

100%

3,828,606

Accessories

1,989,723

100%

100%

xii) DB-AHU 02

72,328,666

1,989,723
72,328,666

1,989,723
72,328,666

61,322,583

100%

61,322,583

100%

61,322,583

Cu/PVC 1C-16mm2

7,231,811

100%

7,231,811

100%

7,231,811

Accessories

3,774,272

100%

3,774,272
62,890,619

100%

3,774,272
62,890,619

Cu/XLPE/PVC 1C-35mm2

xiii)DB-AC-CANTEEN

62,890,619
51,854,320

100%

51,854,320

100%

51,854,320

Cu/PVC 1C-16mm2

7,751,745

100%

7,751,745

100%

7,751,745

Accessories

3,284,554

100%

3,284,554
80,462,033

100%

3,284,554
80,462,033

66,538,128

100%

66,538,128

100%

66,538,128

Cu/PVC 1C-70mm2

9,742,975

100%

9,742,975

100%

9,742,975

Accessories

4,180,930

100%

4,180,930
-

100%

4,180,930
-

Cu/XLPE/PVC 1C-25mm2

xiv)DB-AC 1

80,462,033

Cu/XLPE/PVC 1C-120mm2

6A.10

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

Light
Fitting
Installation

and

Small

Power

8,991,057,775

8,991,057,775

Supply, delivery and installation of


light fittings complete with light
switches,
control
accessories,
a) battery - powered kits, cabling
from DBs to accessories, where
applicable which are fed from the
following areas:
i)

Factory areas

8,991,057,775

7,221,666,378

7,221,666,378

7,221,666,378

Highbay lighting fitting MH 250W IP65

1,026,677,850

100%

1,026,677,850

100%

1,026,677,850

Fluorescent highbay lighting


fitting Philips 2x54W, C/W
ELECTRONIC ballast & lamp

3,160,532,100

100%

3,160,532,100

100%

3,160,532,100

4,584,660

100%

4,584,660

100%

4,584,660

47,055,040

100%

47,055,040

100%

47,055,040

Switch 1 gang 1 way

609,441

100%

609,441

100%

609,441

Switch 2 gang 1 way

588,765

100%

588,765

100%

588,765

Switch 3 gang 1 way

296,886

100%

296,886

100%

296,886

1x8W Fluo. Exit light, single side.


2x6W Surface halogen emergency light.

Switch 1 gang 2 way

100%

100%

Switch 2 gang 2 way

100%

100%

Cu/PVC - 2.5mm2/1C

577,438,753

100%

577,438,753

100%

577,438,753

379,099,686

100%

379,099,686

100%

379,099,686

PVC Conduit D20

167,720,346

100%

167,720,346

100%

167,720,346

PVC Conduit D32

46,979,629

100%

46,979,629

100%

46,979,629

Fitting for PVC Conduit

45,136,898

100%

45,136,898

100%

45,136,898

Cu/PVC - 4.0mm2/1C

Page 38 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
Trunking
100x50 Powder
Coating Paint

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM
%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

707,761,560

100%

707,761,560

100%

707,761,560

114,020,672

100%

114,020,672

100%

114,020,672

3,626,586

100%

3,626,586

100%

3,626,586

71,472,000

100%

71,472,000

100%

71,472,000

Purling clamp

278,250,000

100%

278,250,000

100%

278,250,000

Steel rod D10

512,160,000

100%

512,160,000

100%

512,160,000

Hanger support

46,260,230

100%

46,260,230

100%

46,260,230

Accessories

31,395,276

100%

100%

ii) Office areas

725,929,867

31,395,276
725,929,867

31,395,276
725,929,867

Tee Trunking 100x50


Elbow Trunking 100x50
Trunking hanger

Ground Floor
2x36W Fluo. Batten, c/w
electronic ballast & lamp
3x36W Recessed fluo. modular,
c/w ellectronic ballast louvre &
lamps
3x18W Recessed fluo. modular,

16,314,800

100%

16,314,800

100%

16,314,800

106,710,400

100%

106,710,400

100%

106,710,400

c/w ellectronic ballast louvre &


lamps
25W Decorative ceiling mounted
light, c/w lamp D300
Recessed downlight c/w 18W
compact fluorescent lamp

93,340,530

100%

93,340,530

100%

93,340,530

5,097,600

100%

5,097,600

100%

5,097,600

24,330,445

100%

24,330,445

100%

24,330,445

1x8W Fluo. Exit light, single side.

15,282,200

100%

15,282,200

100%

15,282,200

2x6W Surface halogen


emergency light.

16,175,170

100%

16,175,170

100%

16,175,170

Switch 1 gang 1 way

696,504

100%

696,504

100%

696,504

Switch 2 gang 1 way

1,648,542

100%

1,648,542

100%

1,648,542

Switch 3 gang 1 way

1,781,316

100%

1,781,316

100%

1,781,316

Switch 1 gang 2 way

329,499

100%

329,499

100%

329,499

Cu/PVC - 2.5mm2/1C

76,144,408

100%

76,144,408

100%

76,144,408

PVC Conduit D20

37,716,952

100%

37,716,952

100%

37,716,952

First Floor
2x36W Fluo. Batten, c/w
electronic ballast & lamp

18,762,020

100%

18,762,020

100%

18,762,020

261,189

100%

261,189

100%

261,189

18,420,162

100%

18,420,162

100%

18,420,162

217,030,420

100%

217,030,420

100%

217,030,420

PVC Conduit D20

26,401,866

100%

26,401,866

100%

26,401,866

Fitting for PVC Conduit

12,521,379

100%

12,521,379

100%

12,521,379

Hanger support

30,673,546

100%

30,673,546

100%

30,673,546

6,290,919

100%

6,290,919
-

100%

6,290,919
-

Switch 1 gang 1 way


Cu/PVC - 2.5mm2/1C
Cable tray 300x100

Accessories

Page 39 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL
iii) CanteenSERVICES
areas

2x36W Fluo. Batten, c/w


electronic ballast & lamp
3x36W Recessed fluo. modular,
c/w ellectronic ballast louvre &
lamps
25W Decorative ceiling mounted
light, c/w lamp D300

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM
%
Work
Done
to
Date

90,108,868

Value of Work Done


to Date

%
Work
Done
to
Date

90,108,868

Value of Work Done


to Date

90,108,868

2,855,090

100%

2,855,090

100%

2,855,090

53,174,400

100%

53,174,400

100%

53,174,400

509,760

100%

509,760

100%

509,760

Switch 1 gang 1 way

348,252

100%

348,252

100%

348,252

Switch 2 gang 1 way

235,506

100%

235,506

100%

235,506

Switch 3 gang 1 way

296,886

100%

296,886

100%

296,886

Cu/PVC 1C-2.5mm2

16,354,035

100%

16,354,035

100%

16,354,035

PVC Conduit D20

6,336,448

100%

6,336,448

100%

6,336,448

Fitting for PVC Conduit

3,721,379

100%

3,721,379

100%

3,721,379

Accessories

6,277,112

100%

6,277,112
211,073,448

100%

6,277,112
211,073,448

iv) Utility, Technical and Others Areas

211,073,448

Air Comp., Pump Room


2x36W Fluo. Batten, c/w
electronic ballast & lamp

27,735,160

100%

27,735,160

100%

27,735,160

Switch 1 gang 1 way

435,315

100%

435,315

100%

435,315

Switch 2 gang 1 way

117,753

100%

117,753

100%

117,753

Switch 3 gang 1 way

148,443

100%

148,443

100%

148,443

Cu/PVC 1C-2.5mm2

83,822,840

100%

83,822,840

100%

83,822,840

100%

Switchroom
2x36W Fluo. Batten, c/w
electronic ballast & lamp

8,157,400

100%

8,157,400

100%

8,157,400

Switch 1 gang 1 way

87,063

100%

87,063

100%

87,063

Cu/PVC 1C-2.5mm2

4,677,389

100%

4,677,389

100%

4,677,389

ODM, Toilet
2x36W Fluo. Batten, c/w
electronic ballast & lamp

15,091,190

100%

15,091,190

100%

15,091,190

Switch 1 gang 1 way

87,063

100%

87,063

100%

87,063

Switch 2 gang 1 way

117,753

100%

117,753

100%

117,753

Switch 3 gang 1 way

148,443

100%

148,443

100%

148,443

Page 40 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL SERVICES

Cu/PVC 1C-2.5mm2

8,648,121

%
Work
Done
to
Date
100%

8,648,121

100%

Value of Work Done


to Date

8,648,121
-

22,840,720

100%

22,840,720

100%

22,840,720

7,391,250

100%

7,391,250

100%

7,391,250

Switch 2 gang 1 way

117,753

100%

117,753

100%

117,753

Cu/PVC 1C-2.5mm2

21,872,680

100%

21,872,680

100%

21,872,680

9,577,112

100%

9,577,112

100%

9,577,112

2x36W Fluo. Explosion proof


lighting fitting

Conduit, support and Accessories


Supply, delivery and installation of
small
power
socket
outlets,
b) isolators, connector units, cabling
from DBs to accessories, where
applicable which are fed from the
i)

Value of Work Done


to Date

%
Work
Done
to
Date

Main Store, WTP, Fuel Storage


2x36W Fluo. Batten, c/w
electronic ballast & lamp

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

Factory areas

603,195,457

603,195,457

603,195,457

Industrial type Socket Outlet 5P


32A

38,113,500

100%

38,113,500

100%

38,113,500

Industrial type Socket Outlet 3P


16A

28,182,260

100%

28,182,260

100%

28,182,260

348,333,825

100%

348,333,825

100%

348,333,825

G.I Pipe D20

29,717,771

100%

29,717,771

100%

29,717,771

G.I Pipe D32

57,400,286

100%

57,400,286

100%

57,400,286

Fitting for G.I Conduit

41,114,090

100%

41,114,090

100%

41,114,090

PVC conduit D20

15,101,868

100%

15,101,868

100%

15,101,868

PVC conduit D32

20,663,784

100%

20,663,784

100%

20,663,784

9,379,437

100%

9,379,437

100%

9,379,437

Accessories

15,188,636

100%

100%

ii) Office areas

118,456,997

15,188,636
118,456,997

15,188,636
118,456,997

Cu/PVC 4mm2

Fitting for PVC Conduit

Ground Floor

Double Socket Outlet 3P 16A

7,924,728

100%

7,924,728

100%

7,924,728

Socket Outlet 3P 16A W/P

1,709,550

100%

1,709,550

100%

1,709,550

Cu/PVC 4.0mm2

36,949,163

100%

36,949,163

100%

36,949,163

PVC conduit D20

32,059,409

100%

32,059,409

100%

32,059,409

5,887,391

100%

5,887,391
-

100%

5,887,391
-

2,547,234

100%

2,547,234

100%

2,547,234

Accessories

First Floor
Double Socket Outlet 3P 16A

Page 41 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL SERVICES

Value of Work Done


to Date

100%

15,908,528

100%

15,908,528

PVC conduit D20

11,693,764

100%

11,693,764

100%

11,693,764

3,777,230

100%

3,777,230
8,844,647

100%

3,777,230
8,844,647

8,844,647

Double Socket Outlet 3P 16A

1,132,104

100%

1,132,104

100%

1,132,104

Cu/PVC 1C-4mm2

4,504,403

100%

4,504,403

100%

4,504,403

PVC conduit D20

2,278,104

100%

2,278,104

100%

2,278,104

930,036

100%

930,036
11,782,114

100%

930,036
11,782,114

Accessories
iv) Utility, Technical and Others Areas

11,782,114

Double Socket Outlet 3P 16A

1,273,617

100%

1,273,617

100%

1,273,617

Cu/PVC 1C-4mm2

7,231,149

100%

7,231,149

100%

7,231,149

PVC conduit D20

2,278,104

100%

2,278,104

100%

2,278,104

999,244

100%

999,244
-

100%

999,244
-

Accessories
Lightning Protection System

1,597,098,952

1,597,098,952

Supply, delivery and installation of


Lightning Protection System
Lightning conductor cpt-2

1,597,098,952

93,850,250

100%

93,850,250

100%

93,850,250

Alu tape 25x3mm

528,391,949

100%

528,391,949

100%

528,391,949

Aluminium tape saddle

307,175,319

100%

307,175,319

100%

307,175,319

Support for Clamp

201,837,960

100%

201,837,960

100%

201,837,960

43,703,215

100%

43,703,215

100%

43,703,215

262,330,500

100%

262,330,500

100%

262,330,500

Mounting stand for cpt-2

21,792,500

100%

21,792,500

100%

21,792,500

Stranded copper insulated


conductor PVC 70mm2

53,486,257

100%

53,486,257

100%

53,486,257

Cadwel welding

8,187,000

100%

8,187,000

100%

8,187,000

Grounding test box

4,320,375

100%

4,320,375

100%

4,320,375

Bi-Metal Connector

7,592,500

100%

7,592,500

100%

7,592,500

14mm dia, 2.4m length copper clad steel ground


29,021,550
rod

100%

29,021,550

100%

29,021,550

PVC conduit D32

2,817,789

100%

2,817,789

100%

2,817,789

16,950,000

100%

16,950,000

100%

16,950,000

4,230,720

100%

4,230,720

100%

4,230,720

11,411,069

100%

11,411,069
-

100%

11,411,069
-

Clamp fix down conductor copper cable


Earth Pit

Testing and Commissioning


Excavating & Backfilling
Accessories
6A.12

Value of Work Done


to Date

%
Work
Done
to
Date

15,908,528

iii) Canteen areas

a)

%
Work
Done
to
Date

Cp Cu/PVC 4.0mm2

Accessories

6A.11

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

Main Earthing System


Supply,
delivery
and
installation
ofation of Earthing System inclusive
earth continuity conductors, copper
tapes, earth rods, earth pits, etc. and
testing of the system

212,196,190

212,196,190

Page 42 of 80

212,196,190

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
MV & LV System
a)

%
Work
Done
to
Date

147,725,865

Value of Work Done


to Date

%
Work
Done
to
Date

147,725,865

Value of Work Done


to Date

147,725,865

Stranded copper insulated


conductor PVC 300mm2

76,062,496

100%

76,062,496

100%

76,062,496

Bare copper cable 1Cx100mm2

37,052,750

100%

37,052,750

100%

37,052,750

Earth Cu Busbar 50x6mm

1,597,100

100%

1,597,100

100%

1,597,100

Cadwel welding

2,729,000

100%

2,729,000

100%

2,729,000

Grounding test box

864,075

100%

864,075

100%

864,075

14mm dia, 2.4m length copper clad steel ground


9,673,850
rod

100%

9,673,850

100%

9,673,850

11,615,500

100%

11,615,500

100%

11,615,500

Excavating & Backfilling

2,983,500

100%

2,983,500

100%

2,983,500

Accessories

5,147,594

100%

5,147,594

100%

5,147,594

PVC conduit D114

b) ELV System

Stranded copper insulated


conductor PVC 300mm2

64,470,325

64,470,325

64,470,325

32,367,020

100%

32,367,020

100%

32,367,020

Bare copper cable 1Cx100mm2

9,263,188

100%

9,263,188

100%

9,263,188

Earth Cu Busbar 50x6mm

1,597,100

100%

1,597,100

100%

1,597,100

Cadwel welding

2,183,200

100%

2,183,200

100%

2,183,200

864,075

100%

864,075

100%

864,075

14mm dia, 2.4m length copper clad steel ground


7,739,080
rod

100%

7,739,080

100%

7,739,080

PVC conduit D114

5,226,975

100%

5,226,975

100%

5,226,975

Excavating & Backfilling

2,983,500

100%

2,983,500

100%

2,983,500

Accessories

2,246,188

100%

2,246,188
-

100%

2,246,188
-

Grounding test box

6A.13

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

Street and Landscape Lighting


Supply, delivery and installation of
Street and Landscape Lighting c/w
Street Light, Pole, foundation, wiring,
conduit,
underground
pipe
duct,
accessories, excavation & making good
of the land in the area of work etc for
the following areas:
Street Lighting 250W HPS c/w
lighitng post 8m high incl arm

1,216,028,850

1,216,028,850

1,216,028,850

411,859,500

100%

411,859,500

100%

411,859,500

Flood light 250W HPS

52,919,200

100%

52,919,200

100%

52,919,200

Earth electrode

38,353,497

100%

38,353,497

100%

38,353,497

Cu/XLPE/PVC 2C-4mm2

31,462,323

100%

31,462,323

100%

31,462,323

Cu/PVC 4mm2

15,221,800

100%

15,221,800

100%

15,221,800

282,853,080

100%

282,853,080

100%

282,853,080

Cu/XLPE/PVC 2C-10mm2

Page 43 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL SERVICES

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM
%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

126,214,027

100%

126,214,027

100%

126,214,027

6,584,186

100%

6,584,186

100%

6,584,186

PVC Conduit D20

573,298

100%

573,298

100%

573,298

PVC Conduit D60

80,970,014

100%

80,970,014

100%

80,970,014

GI Conduit D40

Cu/PVC 10mm2

Bare Copper cable 25mm2

13,637,229

100%

13,637,229

100%

13,637,229

Fuse 5A

2,197,455

100%

2,197,455

100%

2,197,455

Terminal block 2P

2,950,350

100%

2,950,350

100%

2,950,350

Excavation and Backfilling

89,044,000

100%

89,044,000

100%

89,044,000

Lighting Post foundation

44,222,100

100%

44,222,100

100%

44,222,100

Accessories

16,966,791

100%

16,966,791

100%

16,966,791

6A.14

CCTV System

614,550,053

614,550,053

Supply, delivery and installation of


Camera, All of Main equipment,
UPS
complete
with
chargers,
batteries,
controls,
a) invertors,
filters, cable, cable trays, trunking,
conduit, uPVC pipes, supports and
etc inside the guardhouse

614,550,053

Wall mounted fix type camera

94,482,000

100%

94,482,000

100%

94,482,000

Keyboard digital

33,933,900

100%

33,933,900

100%

33,933,900

LCD 20'' Monitor

35,328,000

100%

35,328,000

100%

35,328,000

345,630,900

100%

345,630,900

100%

345,630,900

3,804,000

100%

3,804,000

100%

3,804,000

UPS 3000VA

26,296,000

100%

26,296,000

100%

26,296,000

RG 6U signal cable

31,197,711

100%

31,197,711

100%

31,197,711

2x1C 1.5mm2 Cu/PVC

18,926,477

100%

18,926,477

100%

18,926,477

Conduit PVC 20

15,844,121

100%

15,844,121

100%

15,844,121

Fitting for PVC Conduit

5,674,740

100%

5,674,740

100%

5,674,740

Accessories

3,432,204

100%

3,432,204
-

100%

3,432,204
-

Divar Recorder 8 Channel 2TB


Switch 4 port

6A.15

Value of Work Done


to Date

Fire Alarm System


Supply, delivery and installation of
Main Fire Alarm Panel complete
with remote fire pumps/tanks
a)
status mimic section and alarm
functions and 24V battery charger
and batteries
Fire Alarm Control Panel 4 loop
MIMIC panel
24 VDC battery

1,381,548,071

1,381,548,071

1,381,548,071

83,746,025

83,746,025

83,746,025

59,510,246

100%

59,510,246

100%

59,510,246

23,125,743

100%

23,125,743

100%

23,125,743

1,110,036

100%

1,110,036

100%

1,110,036

Page 44 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

Supply, delivery
and installation of
ELECTRICAL
SERVICES
b) Manual Call Points, alarm bells,
smoke/heat detectors

%
Work
Done
to
Date

169,434,615

Value of Work Done


to Date

%
Work
Done
to
Date

169,434,615

Value of Work Done


to Date

169,434,615

Photoelectric Conventional
Smoke Detector

28,860,928

100%

28,860,928

100%

28,860,928

Photoelectric Addressable
Smoke Detector

9,065,292

100%

9,065,292

100%

9,065,292

Conventional Heat Detector

5,920,190

100%

5,920,190

100%

5,920,190

Manual control point

47,176,517

100%

47,176,517

100%

47,176,517

Alarm bell

23,742,430

100%

23,742,430

100%

23,742,430

Conventional zone module

11,007,854

100%

11,007,854

100%

11,007,854

Monitor module

21,214,016

100%

21,214,016

100%

21,214,016

Control module

22,447,389

100%

22,447,389
-

100%

22,447,389
-

Supply, delivery and installation of


Wiring from manual call points,
c) alarm bells, smoke/heat detectors,
fire pump control panels to Main
Fire Alarm Panel

1,128,367,431

1,128,367,431

1,128,367,431

FR Signal cable 1P x 1,5 mm2

261,283,175

100%

261,283,175

100%

261,283,175

FR Signal cable 1P x 2,5 mm2

137,644,504

100%

137,644,504

100%

137,644,504

FR Signal cable from FACP to


MIMIC 8C x 1,5 mm2

112,090,594

100%

112,090,594

100%

112,090,594

25 PVC Conduit (For office)

20,028,693

100%

20,028,693

100%

20,028,693

25 GI Conduit (For work shop)

462,733,772

100%

462,733,772

100%

462,733,772

PVC Juntion Box 50 x 50mm

1,996,898

100%

1,996,898

100%

1,996,898

GI Juntion Box 50 x 50mm

3,230,276

100%

3,230,276

100%

3,230,276

GI Juntion Box 150 x 150mm

2,422,707

100%

2,422,707

100%

2,422,707

Pipe Claim D25

63,329,571

100%

63,329,571

100%

63,329,571

GI Sleeve Pipe D25

41,067,183

100%

41,067,183

100%

41,067,183

932,113

100%

932,113

100%

932,113

21,607,944

100%

21,607,944

100%

21,607,944

PVC Sleeve Pipe D25


Accessories.
Supply, delivery and installation of
Guard
House
control
console
d)
panels/cabinets to house all M&E
services equipment

6A.16

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

Telephone/Data system
To liaise and plan submission to the
local service provider including all
necessary cost for the connection
a)
of new telephone and data system
to their existing telephone and data
system

354,601,934

11,550,000

354,601,934

100%

Page 45 of 80

11,550,000

354,601,934

100%

11,550,000

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
Supply, delivery
and installation of
1 set of incoming telephone and
data cable from authority
b)
telephone & data network to MDF
c/w underground piping, terminal
kit and also provides cable supports

Telephone incoming cable 20pair


outdoor type

%
Work
Done
to
Date

91,453,161

Value of Work Done


to Date

%
Work
Done
to
Date

91,453,161

Value of Work Done


to Date

91,453,161

6,756,400

100%

6,756,400

100%

6,756,400

11,615,500

100%

11,615,500

100%

11,615,500

6,600,000

100%

6,600,000

100%

6,600,000

Main Hole

42,606,000

100%

42,606,000

100%

42,606,000

Concreate for encasement

Conduit uPVC 114


Fitting for PVC Conduit

11,310,750

100%

11,310,750

100%

11,310,750

Excavating & Backfilling

4,339,200

100%

4,339,200

100%

4,339,200

Sand backfill

4,520,160

100%

4,520,160

100%

4,520,160

Waning tape

2,380,500

100%

2,380,500

100%

2,380,500

Brick for marking to warning


300x300x15

443,445

100%

443,445

100%

443,445

Accessories

881,206

100%

881,206
-

100%

881,206
-

Supply, delivery and installation of


Equipment, UPS, Telephone/Data
c) Outlet, Cable trays, trunking,
conduits, wiring as appropriate for
the following areas:
i)

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

251,598,774

251,598,774

Office erea

251,598,774

Telecom service

100%

Internet service

100%

Main distribution frame


80P+Lightning surge arrestor

21,458,000

100%

21,458,000

100%

21,458,000

Patch panel UTP cable +


Lightning surge arrestor

23,716,500

100%

23,716,500

100%

23,716,500

Sub switch with 24 port

100%

100%

Sub switch with 48 port

100%

100%

IDF 30P

1,829,550

100%

1,829,550

100%

1,829,550

IDF 50P

2,106,250

100%

2,106,250

100%

2,106,250

Server rack patch

1,356,000

100%

1,356,000

100%

1,356,000

Ups 5KVA
Ups 6KVA

100%

100%

90%
90%

30-pair multi-core cables

1,310,533

100%

1,310,533

100%

1,310,533

50-pair multi-core cables

2,457,250

100%

2,457,250

100%

2,457,250

Tel cable UTP-2P (2x2x0.5)

22,703,666

100%

22,703,666

100%

22,703,666

Data cable CAT5e UTP

32,937,581

100%

32,937,581

100%

32,937,581

6,352,017

100%

6,352,017

100%

6,352,017

Data socket

12,221,727

100%

12,221,727

100%

12,221,727

Conduit PVC 25

41,302,325

100%

41,302,325

100%

41,302,325

8,721,426

100%

8,721,426

100%

8,721,426

Telephone socket

Fitting for PVC Conduit

Page 46 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
Accessories

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM
%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

3,915,456

100%

3,915,456
-

100%

3,915,456
-

Telephone socket

388,899

100%

388,899

100%

388,899

Data socket

748,269

100%

748,269

100%

748,269

ii) Factory, Canteen, Utility, and Others Areas

Tel cable UTP-2P (2x2x0.5)

4,268,010

100%

4,268,010

100%

4,268,010

Data cable CAT5e UTP

19,811,873

100%

19,811,873

100%

19,811,873

Conduit PVC 25

24,718,816

100%

24,718,816

100%

24,718,816

Fitting for PVC Conduit

6,597,403

100%

6,597,403

100%

6,597,403

Excavating & Backfilling

7,593,600

100%

7,593,600

100%

7,593,600

Sand backfill

2,787,120

100%

2,787,120

100%

2,787,120

Waning tape

452,500

100%

452,500

100%

452,500

1,844,002

100%

1,844,002

100%

1,844,002

Accessories

6A.17

PA System

297,600,564

297,600,564

297,600,564

Supply, delivery and installation of


Speaker, PA Central Controller, All
of Main equipment , UPS complete
with chargers, invertors, batteries,
a)
controls, filters, cable, cable trays,
trunking, conduit, uPVC pipes,
supports and etc inside the
guardhouse

Voice alarm controller c/w 240W


Amplifier - LBB1990/00

29,787,249

100%

29,787,249

100%

29,787,249

Voice alarm router - LBB1992/00

16,731,874

100%

16,731,874

100%

16,731,874

6,465,079

100%

6,465,079

100%

6,465,079

Plena weekly timer - PLN-6TMW

21,663,955

100%

21,663,955

100%

21,663,955

Call station - LBB1956/00

10,719,026

100%

10,719,026

100%

10,719,026

7,717,412

100%

7,717,412

100%

7,717,412

10,287,436

100%

10,287,436

100%

10,287,436

Plena DVD/MP3/Tuner - PLNDVDT

Call station keypad LBB1957/00


Plena power amplifier 360/240W,
EVAC Compliant - LBB1935/20
Ceiling LSP 6W - LHM0606/10

6,765,703

100%

6,765,703

100%

6,765,703

Economy horn LSP 15W LBC3470/00

13,173,200

100%

13,173,200

100%

13,173,200

Vietrack 19'' cabinet 36U

14,066,000

100%

14,066,000

100%

14,066,000

Cu/PVC 2.5mm2

50,933,059

100%

50,933,059

100%

50,933,059

Conduit PVC 20

52,803,733

100%

52,803,733

100%

52,803,733

Conduit GI 50

30,276,964

100%

30,276,964

100%

30,276,964

Fitting for PVC Conduit

21,442,201

100%

21,442,201

100%

21,442,201

4,767,673

100%

4,767,673

100%

4,767,673

Accessories

6A.18

Value of Work Done


to Date

Testing and commissioning


a) Electrical System

210,100,000
82,500,000

210,100,000
100%

Page 47 of 80

82,500,000

210,100,000
100%

82,500,000

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

6A.19

6A.21

Value of Work Done


to Date

35,200,000

100%

35,200,000

100%

35,200,000

c) CCTV System

13,200,000

100%

13,200,000

100%

13,200,000

d) Fire Alarm System

33,000,000

100%

33,000,000

100%

33,000,000

e) Telephone/Data system

23,100,000

100%

23,100,000

100%

23,100,000

f) PA system

23,100,000

100%

23,100,000

100%

23,100,000

Licensing

Maintenance and Warranty


Comprehensive
Maintenance/Servicing
during
Contractual Maintenance Period
Fire Stopping
One lot of fire stops and fire proofing
materials

6A.22

Value of Work Done


to Date

%
Work
Done
to
Date

ELECTRICAL
AttendanceSERVICES
for Power Utilities
b) Company testing including all test
fees

Included

Licensing fees for the electrical


installation from date of 'TURN-ON' to
end of Defects Liability Period
6A.20

%
Work
Done
to
Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

Any Other Works

100%
198,000,000
198,000,000

198,000,000
100%

46,200,000
46,200,000

198,000,000

198,000,000
100%

46,200,000
100%

2,964,622,349

46,200,000

198,000,000
46,200,000

100%

2,964,622,349

46,200,000
2,964,622,349

Any other works not mentioned above


but are necessary for the completion
of the entire works (please specify):

a) Electrical System

T in

DB-CA

6,627,092

100%

6,627,092

100%

6,627,092

DB-LPG

6,159,779

100%

6,159,779

100%

6,159,779

23,457,100

100%

23,457,100

100%

23,457,100

DB-DOCK
Cp ngun DB-CA

Cu/XLPE/PVC 1C-6mm2
Cu/PVC 1C-6mm2

15,252,663

100%

15,252,663

100%

15,252,663

3,310,171

100%

3,310,171

100%

3,310,171

Cp ngun DB-DOCK

Cu/XLPE/PVC 1C-6mm2
Cu/PVC 1C-6mm2

15,445,734

100%

15,445,734

100%

15,445,734

3,352,072

100%

3,352,072

100%

3,352,072

Cp ngun DB-LPG

Cu/XLPE/PVC 1C-10mm2
Cu/PVC 1C-10mm2
Supplying
and
installation
of
ladder/tray/
trunking/underground
pipe enscated in concrete for Submain
cables

17,673,703

100%

17,673,703

100%

17,673,703

8,026,173

100%

8,026,173

100%

8,026,173
-

1,881,370,466

Page 48 of 80

1,881,370,466

1,881,370,466

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

Cable tray
800x100 Powder
ELECTRICAL
SERVICES

%
Work
Done
to
Date

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

Value of Work Done


to Date

377,862,016

100%

377,862,016

100%

377,862,016

Cable tray 300x100 Powder


Coating Paint

720,372,553

100%

720,372,553

100%

720,372,553

Cable tray 100x100 Powder


Coating Paint

36,561,380

100%

36,561,380

100%

36,561,380

1,982,752

100%

1,982,752

100%

1,982,752

Tee cable tray


800x100/300x100mm

42,883,040

100%

42,883,040

100%

42,883,040

Horizontal elbow cable tray


800x100mm/300x100mm

15,096,640

100%

15,096,640

100%

15,096,640

Horizontal elbow Trunking


300x100mm

4,186,178

100%

4,186,178

100%

4,186,178

Down elbow cable tray


800x100mm

4,883,808

100%

4,883,808

100%

4,883,808

Tee cable tray 3000x100

6,112,255

100%

6,112,255

100%

6,112,255

958,218

100%

958,218

100%

958,218

16,192,982

100%

16,192,982

100%

16,192,982

837,236

100%

837,236

100%

837,236

29,937,082

100%

29,937,082

100%

29,937,082

326,148

100%

326,148

100%

326,148

Purling clamp

156,854,560

100%

156,854,560

100%

156,854,560

Hanger rod D10

272,283,811

100%

272,283,811

100%

272,283,811

Steel C 75x75

87,325,820

100%

87,325,820

100%

87,325,820

Steel C 50x50

30,023,360

100%

30,023,360

100%

30,023,360

Hanger Support

43,377,052

100%

43,377,052

100%

43,377,052

Accessories

33,313,576

100%

33,313,576

100%

33,313,576

Coating Paint

Tee cable tray 800x100

Tee cable tray


300x100/100x100mm
Horizontal elbow cable tray
300x100mm/100x100mm
Horizontal elbow Trunking
300x100mm
Down elbow cable
tray300x100mm
Down elbow cable tray
100x100mm

Supply,
deliver
trunking/conduits,
accessories and
Subcircuit wiring

and
etc

install
conduit
for final

983,947,396

983,947,396

983,947,396

Cable tray 450x100

134,234,738

100%

134,234,738

100%

134,234,738

Cable tray 300x100

184,637,820

100%

184,637,820

100%

184,637,820

Cable tray 200x100

49,842,320

100%

49,842,320

100%

49,842,320

Cable tray 100x100

48,906,380

100%

48,906,380

100%

48,906,380

G.I Pipe D25

61,689,758

100%

61,689,758

100%

61,689,758

G.I conduit D40

33,335,448

100%

33,335,448

100%

33,335,448

Purling clamp

63,971,000

100%

63,971,000

100%

63,971,000

279,360,000

100%

279,360,000

100%

279,360,000

Hanger rod D10

Page 49 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL
Steel C SERVICES
75x75

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM
%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

REMARK

Value of Work Done


to Date

54,563,413

100%

54,563,413

100%

54,563,413

Steel C 50x50

22,885,453

100%

22,885,453

100%

22,885,453

Hanger Support

35,719,079

100%

35,719,079

100%

35,719,079

Accessories

14,801,986

100%

14,801,986

100%

14,801,986
-

6B

MECHANICAL SERVICES

6B.1

Mechanical
Ventilation
(Provisional Sum)

System

Supply, delivery and installation of


mechanical
ventilation
fans,
silencers, attenuators, c/w antia)
vibration
mounts,
flexible
connectors and accessories as
specified for the following areas:
i)

ii)

26,168,986,926

26,168,986,926

26,168,986,926

1,028,903,540

1,028,903,540

1,028,903,540

103,587,540

103,587,540

103,587,540

Factory
areas

FAF 31000l/s @ 400Pa

100%

EAF 31000l/s @ 400Pa

100%

FAF 20000l/s @ 400Pa

100%

EAF 18000l/s @ 400Pa

100%

Penetration for airduct through


metal clading wall

100%

Hangers, supports, spring


isolators & accessories

100%

Office
areas

41,264,370

41,264,370

41,264,370

165l/s @ 50Pa

18,339,720

100%

18,339,720

100%

18,339,720

220l/s @ 50Pa

4,584,930

100%

4,584,930

100%

4,584,930

275l/s @ 50Pa

9,169,860

100%

9,169,860

100%

9,169,860

140l/s @ 50Pa

4,584,930

100%

4,584,930

100%

4,584,930

4,584,930

100%

4,584,930

100%

303l/s @ 50Pa
iii) Canteen areas

34,184,640

34,184,640

4,584,930
34,184,640

140l/s @ 50Pa

4,584,930

100%

4,584,930

100%

4,584,930

220l/s @ 50Pa

4,584,930

100%

4,584,930

100%

4,584,930

25,014,780

100%

25,014,780

100%

25,014,780

2500l/s @ 300Pa ( Kitchen )


Utility, Technical and Others
iv)
Areas

28,138,530

28,138,530

28,138,530

450l/s @ 50Pa

18,339,720

100%

18,339,720

100%

18,339,720

440l/s @ 50Pa

4,584,930

100%

4,584,930

100%

4,584,930

370l/s @ 50Pa

4,584,930

100%

4,584,930

100%

4,584,930

628,950

100%

628,950

100%

628,950

Thermostat
Mechanical ventilation ductwork
complete with grilles accessories,
b) dampers, access panels, fire rating,
insulating and balancing dampers
as specified for the following areas:

50,316,000

Page 50 of 80

50,316,000

50,316,000

Verify ID
Contract

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

areas
i) Factory SERVICES
ELECTRICAL

%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

Air duct 1,2mmT w/ int. insulation

100%

Air duct 1,2mmT

100%

FAG 500x1000 c/w OBD

100%

FAG 600x1500 c/w OBD

100%

FAG 800x1500 c/w OBD

100%

EAG 700x1300 c/w OBD

100%

EAG 700x1800 c/w OBD

100%

Flexible connector for fan

100%

Hanger, supporters, silicone, adhesive, clamps, bolts & nuts,


100%
.etc.
ii) Office, Canteen, Utility,
Kitchen hood
Electrical, control for mechanical
ventilation
fans
c/w
panels,
c)
starters,
cables,
trunking,
termination, for:
i) Factory areas

6B.2

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

50,316,000
50,316,000

100%

875,000,000

50,316,000
50,316,000

100%

875,000,000
100%

50,316,000
50,316,000
875,000,000

ii) Office areas

375,000,000

100%

375,000,000

100%

375,000,000

iii) Canteen areas

250,000,000

100%

250,000,000

100%

250,000,000

iv) Utility, Technical and Others Areas

250,000,000

100%

250,000,000

100%

250,000,000

Air-conditioning system
a) Airconditioning Equipment

i)

Supply, delivery and installation


of Chiller and AHU including
stainless steel brackets, valves
and accessories

6,972,355,289

6,972,355,289

6,972,355,289

3,625,811,910

3,625,811,910

3,625,811,910

Air cooled liquid chilled, Cap. :


37,5RT
AHU, Cap. 37,5 RT
Valves & accessories :

100%

100%
100%

Gate valve, DN 100

100%

Gate valve, DN 25

100%

Butterfly valve, DN 65

100%

Strainer, DN 65

100%

Flow switch

100%

Thermometer, straight type

100%

Thermometer, immersion type

100%

Pressure gauge c/w cock valve

100%

Flexible connector, DN 65

100%

Motorised valve, DN 65

100%

Test point

100%

Temperature Controller

100%

Page 51 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value
Accessories : flanges, bolts &
ELECTRICAL
SERVICES
nuts, gaskets,
submaterials.etc.
Concrete foundation for Chiller
Concrete foundation for AHUs
Supply, delivery and installation
of air cooled VRV including
ii)
stainless steel brackets, valves
and accessories
Outdoor unit :
Cap.
113kW
Cap.
117kW
Cap. 133kW
Indoor unit
Concealed ceiling, duct type,
7.3kW
9.3kW
14.5kW
16.5kW
Wall mounted, cooling cap. :
2.3kW
3.7kW
4.7kW
5.8kW
7.3kW
Remote
Refnet
Concrete foundation for O.U
Hanger for I.U
Sub-material : exp. bolts, bolts
& nuts, paints .etc.
Supply, delivery and installation
of air cooled split units including
iii)
stainless steel brackets, valves
and accessories
Concealed ceiling, duct type,

%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

100%

100%
100%

2,703,299,340

2,703,299,340

2,703,299,340

441,651,000

100%

441,651,000

100%

441,651,000

453,096,000

100%

453,096,000

100%

453,096,000

1,084,072,080
17,475,360
41,268,360
235,609,500
59,705,100
10,821,720
57,427,650
11,782,050
24,067,680
25,072,740
29,729,700
123,580,800
25,158,000
7,887,600

100%

1,084,072,080

100%

1,084,072,080
-

100%
100%
100%
100%

100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%

17,475,360
41,268,360
235,609,500
59,705,100
10,821,720
57,427,650
11,782,050
24,067,680
25,072,740
29,729,700
123,580,800
25,158,000
7,887,600

100%
100%
100%
100%
100%
100%
100%
100%
100%

17,475,360
41,268,360
235,609,500
59,705,100
10,821,720
57,427,650
11,782,050
24,067,680
25,072,740
29,729,700
123,580,800
25,158,000
7,887,600

54,894,000

100%

54,894,000

100%

54,894,000

922,512,570

922,512,570

922,512,570

17,4 kW

165,215,610

100%

165,215,610

100%

165,215,610

24,3 kW

404,045,460

100%

404,045,460

100%

404,045,460

Floor standing type


24,2 kW
Wire remote controller
Support for O.U
Hanger for I.U
Foudation frame for I.U
Sub-material : exp. bolts, bolts
& nuts, paints .etc.
b) Pipework and Ductwork

i)

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

Supply, delivery and installation


of insulated Air ductworks
complete
with
all
fittings,
accessories & etc
Air duct c/w insulation for AHUs
Air duct c/w ext.insulation for
Air duct c/w int.insulation for
Flexible pipe DN250 c/w
Flexible pipe DN300 c/w
Flexible pipe DN350 c/w

306,600,000

100%

306,600,000

100%

306,600,000

816,480
16,352,700
8,852,760
3,018,960

100%
100%
100%
100%

816,480
16,352,700
8,852,760
3,018,960

100%
100%
100%
100%

816,480
16,352,700
8,852,760
3,018,960

17,610,600

100%

17,610,600

100%

17,610,600

1,153,191,239

1,153,191,239

1,153,191,239

494,076,629

494,076,629

494,076,629

212,151,713
124,281,696
3,250,800
34,148,100
3,540,600

100%
100%
100%
100%
100%

Page 52 of 80

212,151,713
124,281,696
3,250,800
34,148,100
3,540,600

100%
100%
100%
100%
100%

212,151,713
124,281,696
3,250,800
34,148,100
3,540,600

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

FlexibleSERVICES
connector for I.Us
ELECTRICAL
Sub-material : adhesive,
aluminium tape, hangers &
Supply, delivery and installation
of
insulated
refrigerant
pipeworks complete with all
ii)
fittings, control valves, valves,
strainers, Y-Brand, painting,
labelling and accessories,
Copper Pipe D6.4 c/w Insulation
rubber tube
Copper Pipe D9.5 c/w Insulation
Copper Pipe D12.7 c/w
Copper Pipe D15.9 c/w
Copper Pipe D19.1 c/w
Copper Pipe D22.2 c/w
Copper Pipe D28.6 c/w
Copper Pipe D34.9 c/w
Copper Pipe D41.3 c/w
Copper fitting
Sub-material : adhesive,
aluminium tape, hangers &
supports, bolts & nuts, etc.
Supply, delivery and installation
of condensate drain pipeworks
complete with all fittings and
iii)
accessories,
insulating
and
insulation of floor wastes/traps
and horizontal waste pipe

%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

13,698,720

100%

13,698,720

100%

13,698,720

103,005,000

100%

103,005,000

100%

103,005,000

516,279,960

516,279,960

516,279,960

4,365,900

100%

4,365,900

100%

4,365,900

30,098,250
31,857,000
43,218,000
47,158,650
53,870,250
42,520,800
31,576,860
102,369,750
78,928,500

100%
100%
100%
100%
100%
100%
100%
100%
100%

30,098,250
31,857,000
43,218,000
47,158,650
53,870,250
42,520,800
31,576,860
102,369,750
78,928,500

100%
100%
100%
100%
100%
100%
100%
100%
100%

30,098,250
31,857,000
43,218,000
47,158,650
53,870,250
42,520,800
31,576,860
102,369,750
78,928,500

50,316,000

100%

50,316,000

100%

50,316,000

142,834,650

142,834,650

142,834,650

PVC drain pipe D21 c/w


Insulation rubber tube 13mmT

491,400

100%

491,400

100%

491,400

PVC drain pipe D27 c/w


Insulation rubber tube 13mmT

10,278,450

100%

10,278,450

100%

10,278,450

7,271,250

100%

7,271,250

100%

7,271,250

3,864,000

100%

3,864,000

100%

3,864,000

16,101,750
93,051,000
1,713,600

100%
100%
100%

16,101,750
93,051,000
1,713,600

100%
100%
100%

16,101,750
93,051,000
1,713,600

10,063,200

100%

10,063,200

100%

10,063,200

PVC drain pipe D34 c/w


Insulation rubber tube 13mmT
PVC drain pipe D42 c/w
Insulation rubber tube 13mmT
Stainlesssteel trunking
PVC trunking 200x150
PVC fitting
Sub-material : hangers &
supports, bolts & nuts, etc.
Supply, delivery and installation
of cooling and water chiller
iv) pipeworks complete with all
fittings,
insulating
and
accessories

B.S pipe- DN65

100%

B.S pipe- DN25

100%

Steel Pipe fiting


Insualtion for pipe
Sub-material : hangers &

100%
100%
100%

c) Air distribution

i)

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

Supply, delivery and installation


of Deffuser, Griller, VCD, OBD,
VAV, balancing dampers, Fire
dampers, Non-return Damper,
complete with all fittings and
accessories

169,766,730

169,766,730

169,766,730

169,766,730

169,766,730

169,766,730

Page 53 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

SAG diffuser
4 way 600x600 c/w
ELECTRICAL
SERVICES
OBD
RAG 600x600 c/w Insect screen
& filter G4
SAG 800x500 c/w OBD
VCD DN450
Accessories
d) Electrical Controls
Supply, delivery and installation
of electrical and controls for
airconditioning
equipment
i)
complete with wired remote
controller,
trunking,
termination, control wiring and
Control cables & conduits

%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

84,970,620

100%

84,970,620

100%

84,970,620

43,018,920

100%

43,018,920

100%

43,018,920

20,073,690
21,703,500

100%
100%
100%

20,073,690
21,703,500

100%
100%
100%

20,073,690
21,703,500

89,218,500

89,218,500

89,218,500

89,218,500

89,218,500

89,218,500

89,218,500

100%

89,218,500

100%

89,218,500

Pumps system for Chiller & Cooling


e)
tower

1,934,366,910

1,934,366,910

1,934,366,910

Supply, delivery and installation


of Chiller water pumps

904,946,910

904,946,910

904,946,910

i)

Chilled water pump,


6,3l/s@10mH2O
Cooling water pump,
23l/s@66mH2O
Valves & accessories for pumps

100%
578,112,570
-

100%
100%

578,112,570

100%

578,112,570
-

Gate valve, DN 25

1,673,280

100%

1,673,280

100%

1,673,280

Gate valve, DN15

3,230,640

100%

3,230,640

100%

3,230,640

Butterfly valve, DN 125

8,914,500

100%

8,914,500

100%

8,914,500

Butterfly valve, DN 65
Check valve, DN 125

Check valve, DN 65
Strainer, DN 125

Strainer, DN 65
Pressure gauge c/w cock valve
Flexible connector, DN 125

6,541,920
-

Flexible connector, DN 65
Accessories : flanges, bolts &
nuts, gaskets, .etc.
Inertia base c/w spring isolator
Supply, delivery and installation
ii) of Pump control panel c/w
wiring and accessories
Control panels for CW pumps
Supply, delivery and installation
iii) of Pumps connection piping and
valves
f) Chiller water Storage tank
Supply, delivery and installation
of water Storage tank complete
i)
with Insulation, support frame,
valves and accessories
Automatic Sprinkler System

100%

100%

100%

100%

100%

100%

6,541,920

100%

6,541,920

100%

100%

29,736,000

100%

29,736,000

100%

29,736,000

276,738,000

100%

276,738,000

100%

276,738,000

1,029,420,000

Control panels for CHW pumps

6B.3

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

1,029,420,000
100%

1,029,420,000

100%

1,029,420,000

1,029,420,000

100%

1,029,420,000

100%

10,582,355,055

Page 54 of 80

10,582,355,055

10,582,355,055

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

DESCRIPTION
Contract value

%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

Supply, delivery
and installation of
ELECTRICAL
SERVICES
a)
Main Sprinkler Pumps

996,619,855

Electric fire pump Q= 310M3/h, H=


130M.

347,367,075

100%

347,367,075

100%

347,367,075

Diezel Pump 310M3/h, H= 130M.

649,252,780

100%

649,252,780

100%

649,252,780

b)

Supply, delivery and installation of


Jockey Pump & Hydro-pneumatic

996,619,855

102,333,445

996,619,855

102,333,445

102,333,445

Jockey Pump Q= 9M3/h, H= 135M.

72,927,910

100%

72,927,910

100%

72,927,910

Pressure vessel 500L.

29,405,535

100%

29,405,535

100%

29,405,535

Supply, delivery and installation of


Pump Control Panel c/w wiring and
c)
controls for monitoring and alarm
functions
Fire pump control panel.
Power Cable for fire pump
Control cable for fire pump 1Cx
Trunking 400x100mm.
Accessories
Supply, delivery and installation of
d)
Pumps connection piping and
Gate valve DN200.
Gate valve DN50.
Check Valve DN200.
Check Valve DN50.
Relief valve DN150.

688,102,441
302,577,000
320,892,000
29,403,454
27,941,259
7,288,728

688,102,441
100%
100%
100%
100%
100%

609,302,414

302,577,000
320,892,000
29,403,454
27,941,259
7,288,728

688,102,441
100%
100%
100%
100%
100%

609,302,414

302,577,000
320,892,000
29,403,454
27,941,259
7,288,728
609,302,414

77,018,369
3,534,684
24,380,649
1,190,469
54,437,487

100%
100%
100%
100%
100%

77,018,369
3,534,684
24,380,649
1,190,469
54,437,487

100%
100%
100%
100%
100%

77,018,369
3,534,684
24,380,649
1,190,469
54,437,487

Pipe DN250.

25,041,862

100%

25,041,862

100%

25,041,862

Pipe DN200.

44,805,801

100%

44,805,801

100%

44,805,801

Pipe DN150.

10,494,217

100%

10,494,217

100%

10,494,217

1,686,744

100%

1,686,744

100%

1,686,744

Pipe DN50.
Flange DN250.
Flange for valve DN200
Flange for valve DN150
Bolt for Flange
Buffer for flange DN250
Gasket for flange DN200
Gasket for flange DN150
Support in pump room
Painting pipe line in pump room
Foot Valve DN250.
Y filter DN250.
Flow metter DN200.
Flexible DN200.
Flexible DN50.
Electronic water level Switch
Pipe fittings
Tee DN250.
Tee DN200.
Elbow DN250.

100%

90%

15,028,432

100%

15,028,432

100%

15,028,432

2,072,449
6,516,133

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

2,072,449
6,516,133
3,212,530
493,012
4,000,753
2,800,527
19,763,720
24,404,593
10,433,964
19,043,584
2,736,515
15,122,846
130,118,525

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

2,072,449
6,516,133
3,212,530
493,012
4,000,753
2,800,527
19,763,720
24,404,593
10,433,964
19,043,584
2,736,515
15,122,846
130,118,525
-

3,212,530
493,012
4,000,753
2,800,527
19,763,720
24,404,593
10,433,964
19,043,584
2,736,515
15,122,846
130,118,525
-

Page 55 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

Elbow DN200.
ELECTRICAL
SERVICES
Elbow DN150.
Elbow Screwed end DN50.
Reduce DN250/200.
Reduce DN250/150.
Reduce DN250/50.
Reduce DN200/150.
Concrete of base fire pump
Accessories.
Ducument & Certificate
Supply, delivery and installation of
Sprinkler Control Valves c/w water
e) proving equipment, drain valves,
alarm switches, pressure gauges,
water gongs and all other
Butterfly valve with supervisory
switch DN150.
Butterfly valve with supervisory
OS & Y Valve DN150.
OS & Y Valve DN100.
Gate valve DN200.
Check Valve DN150.
Pressure reducing valve DN100.

7,260,000
59,704,548
44,000,000

%
Work
Done
to
Date
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

919,883,937

Value of Work Done


to Date

7,260,000
59,704,548
44,000,000

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

100%
100%
100%

919,883,937

Value of Work Done


to Date
7,260,000
59,704,548
44,000,000
919,883,937

74,549,700

100%

74,549,700

100%

74,549,700

9,425,824
70,948,709
35,193,824
44,010,496
7,595,454
158,459,647

100%
100%
100%
100%
100%
100%

9,425,824
70,948,709
35,193,824
44,010,496
7,595,454
158,459,647

100%
100%
100%
100%
100%
100%

9,425,824
70,948,709
35,193,824
44,010,496
7,595,454
158,459,647

359,895,106

100%

359,895,106

100%

359,895,106

Gate valve DN25.


Sight glass.
Union DN25.

11,996,504
41,585,655
356,003

100%
100%
100%

11,996,504
41,585,655
356,003

100%
100%
100%

11,996,504
41,585,655
356,003

Automatic air vent valve.

12,282,120

100%

12,282,120

100%

12,282,120

Presssure gauge + Cook valve.

8,010,078

100%

8,010,078

100%

8,010,078

Pressure Switch + Cook valve.

12,394,347

100%

12,394,347

100%

12,394,347

Flange for valve DN200

5,009,477

100%

5,009,477

100%

5,009,477

Flange for valve DN150

22,796,936

100%

22,796,936

100%

22,796,936

6,007,559
13,826,917
1,070,843
5,423,132
1,166,265
17,879,339

100%
100%
100%
100%
100%
100%

6,007,559
13,826,917
1,070,843
5,423,132
1,166,265
17,879,339

100%
100%
100%
100%
100%
100%

6,007,559
13,826,917
1,070,843
5,423,132
1,166,265
17,879,339

Alarm Valve DN150.

Flange for valve DN100


Bolt for flange.
Gasket for flange DN200
Gasket for flange DN150
Gasket for flange DN100
Accessories.
Supply, delivery and installation of
Main riser pipes (including fire
f)
rated
encasement
where
run
outside protected lobby)
Pipe DN150.

Pipe DN50.
Support for pipe line
Accessories.
Supply, delivery and installation of
g) Flow switches and wiring to main
fire alarm panel
Flow switch DN150.

48,271,403

48,271,403

48,271,403

41,976,869

100%

41,976,869

100%

41,976,869

2,530,115

100%

2,530,115

100%

2,530,115

2,926,000
838,419

100%
100%

2,926,000
838,419

100%
100%

2,926,000
838,419

33,025,833
28,998,293

33,025,833
100%

Page 56 of 80

28,998,293

33,025,833
100%

28,998,293

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

ELECTRICAL
Flow switchSERVICES
DN100.
Supply, delivery and installation of
h) Sprinkler heads c/w pipework and
accessories
i) Factory areas

Pipe DN150.

4,027,541

%
Work
Done
to
Date
100%

Value of Work Done


to Date

4,027,541

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date
100%

Value of Work Done


to Date

4,027,541

7,184,815,726

7,184,815,726

7,184,815,726

6,228,002,751

6,228,002,751

6,228,002,751

1,034,729,816

100%

1,034,729,816

100%

1,034,729,816

Pipe DN50.

228,216,396

100%

228,216,396

100%

228,216,396

Pipe DN40.

404,489,991

100%

404,489,991

100%

404,489,991

Pipe DN32.
Pipe DN25.

372,400,248
74,679,326

100%
100%

372,400,248
74,679,326

100%
100%

372,400,248
74,679,326

Tee DN150

531,716,610

100%

531,716,610

100%

531,716,610

Tee DN50
Tee DN40
Tee DN32

64,606,680
61,258,026
34,710,335

100%
100%
100%

64,606,680
61,258,026
34,710,335

100%
100%
100%

64,606,680
61,258,026
34,710,335

Elbow DN150.

23,172,012

100%

23,172,012

100%

23,172,012

13,566,273
206,931,783
32,257,013
212,753,395
38,041,512
11,716,331
37,096,664
9,434,728
56,262,458
636,113,061
609,356,792
309,308,735
284,301,077
255,429,310
11,468,398
16,975,595
15,142,862
2,680,621
48,970,331
30,381,867
73,963,921
56,295,397
145,741,022
140,087,951
33,126,238
110,619,978

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

13,566,273
206,931,783
32,257,013
212,753,395
38,041,512
11,716,331
37,096,664
9,434,728
56,262,458
636,113,061
609,356,792
309,308,735
284,301,077
255,429,310
11,468,398
16,975,595
15,142,862
2,680,621
48,970,331
30,381,867
73,963,921
56,295,397
145,741,022
140,087,951
33,126,238
110,619,978

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

13,566,273
206,931,783
32,257,013
212,753,395
38,041,512
11,716,331
37,096,664
9,434,728
56,262,458
636,113,061
609,356,792
309,308,735
284,301,077
255,429,310
11,468,398
16,975,595
15,142,862
2,680,621
48,970,331
30,381,867
73,963,921
56,295,397
145,741,022
140,087,951
33,126,238
110,619,978

Elbow Screwed end DN32


Reduce DN150/65.
Reduce DN150/50.
Reduce DN50/40.
Reduce DN50/25.
Reduce DN40/32.
Reduce DN40/25.
Reduce DN32/25.
Reduce DN25/15.
Wet sprinkler head 68oC - K=8.0
Wet sprinkler head 68oC - K=11.2
Rosette cover for Sprinkler head.
Painting pipe line.
Flange for pipe DN150
Sleeve coupling DN50
Sleeve coupling DN40
Sleeve coupling DN32
Sleeve coupling DN25
Bolt for flange.
Gasket for flange DN150
Support for pipe DN150
Support for pipe DN50
Support for pipe DN40
Support for pipe DN32
Support for pipe DN25
Accessories.

Page 57 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
ii) Office and
other Areas

%
Work
Done
to
Date

956,812,975

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

956,812,975

Value of Work Done


to Date

956,812,975

Pipe DN150.

10,494,217

100%

10,494,217

100%

10,494,217

Pipe DN100.

59,303,234

100%

59,303,234

100%

59,303,234

Pipe DN80.

21,103,064

100%

21,103,064

100%

21,103,064

Pipe DN65.

13,406,208

100%

13,406,208

100%

13,406,208

Pipe DN50.

12,650,576

100%

12,650,576

100%

12,650,576

Pipe DN40.

25,183,190

100%

25,183,190

100%

25,183,190

Pipe DN32.
Pipe DN25.

29,183,339
273,553,617

100%
100%

29,183,339
273,553,617

100%
100%

29,183,339
273,553,617

Tee DN150

5,187,479

100%

5,187,479

100%

5,187,479

10,997,964
8,111,793
4,952,263
1,516,193
14,055,780
8,099,078
2,506,329

100%
100%
100%
100%
100%
100%
100%

10,997,964
8,111,793
4,952,263
1,516,193
14,055,780
8,099,078
2,506,329

100%
100%
100%
100%
100%
100%
100%

10,997,964
8,111,793
4,952,263
1,516,193
14,055,780
8,099,078
2,506,329

Elbow DN150.

2,317,201

100%

2,317,201

100%

2,317,201

Elbow Screwed end DN50.


Elbow Screwed end DN25

267,003
1,846,768

100%
100%

267,003
1,846,768

100%
100%

267,003
1,846,768

Reduce DN150/80.

2,328,644

100%

2,328,644

100%

2,328,644

Reduce
Reduce
Reduce
Reduce
Reduce
Reduce
Reduce
Reduce

1,217,246
940,866
517,477
7,844,473
705,650
591,220
3,399,515
232,038

100%
100%
100%
100%
100%
100%
100%
100%

1,217,246
940,866
517,477
7,844,473
705,650
591,220
3,399,515
232,038

100%
100%
100%
100%
100%
100%
100%
100%

1,217,246
940,866
517,477
7,844,473
705,650
591,220
3,399,515
232,038

Tee
Tee
Tee
Tee
Tee
Tee
Tee

DN100
DN80
DN65
DN50
DN40
DN32
DN25

DN150/50.
DN100/80.
DN100/50.
DN100/40.
DN100/32.
DN80/65.
DN80/40.
DN80/32.

Page 58 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

Reduce DN65/50.
ELECTRICAL
SERVICES
Reduce DN65/40.
Reduce DN65/32.
Reduce DN50/40.
Reduce DN50/32.
Reduce DN50/25.
Reduce DN40/32.
Reduce DN40/25.
Reduce DN32/25.
Reduce DN25/15.
Wet sprinkler head 68oC - K=5.6
(Upright head)
Wet sprinkler head 68oC - K=5.6
(pendent head).

1,160,190
1,403,830
266,844
559,434
534,005
223,774
2,325,148
8,877,834
6,054,759
11,087,284

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

1,160,190
1,403,830
266,844
559,434
534,005
223,774
2,325,148
8,877,834
6,054,759
11,087,284

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

1,160,190
1,403,830
266,844
559,434
534,005
223,774
2,325,148
8,877,834
6,054,759
11,087,284

32,888,999

100%

32,888,999

100%

32,888,999

44,656,085

100%

44,656,085

100%

44,656,085

Rosette cover for Sprinkler head.

30,476,750

100%

30,476,750

100%

30,476,750

124,962,315

100%

124,962,315

100%

124,962,315

2,590,561

100%

2,590,561

100%

2,590,561

14,518,266
5,443,357
3,810,085
635,721
1,348,787
771,341
9,819,231
6,648,575
308,133
1,409,237
679,217
479,317
606,114
5,511,037
3,800,715
2,460,623
1,776,334
4,872,918
6,497,224
78,198,727
16,637,784

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

14,518,266
5,443,357
3,810,085
635,721
1,348,787
771,341
9,819,231
6,648,575
308,133
1,409,237
679,217
479,317
606,114
5,511,037
3,800,715
2,460,623
1,776,334
4,872,918
6,497,224
78,198,727
16,637,784

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

14,518,266
5,443,357
3,810,085
635,721
1,348,787
771,341
9,819,231
6,648,575
308,133
1,409,237
679,217
479,317
606,114
5,511,037
3,800,715
2,460,623
1,776,334
4,872,918
6,497,224
78,198,727
16,637,784

Painting pipe line.


Flange for pipe DN150
Flange for pipe DN100
Flange for pipe DN80
Flange for pipe DN65
Sleeve coupling DN50
Sleeve coupling DN40
Sleeve coupling DN32
Sleeve coupling DN25
Bolt for flange.
Gasket for flange DN150
Gasket for flange DN100
Gasket for flange DN80
Gasket for flange DN65
Support for pipe DN150
Support for pipe DN100
Support for pipe DN80
Support for pipe DN65
Support for pipe DN50
Support for pipe DN40
Support for pipe DN32
Support for pipe DN25
Accessories.
6B.4

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

Hosereel System
Supply, delivery and installation of
a)
Hosereel Pumps
Supply, delivery and installation of
Pump control panel c/w wiring and
b)
controls for monitoring and alarm
functions
Supply, delivery and installation of
c) Pumps connection piping and
valves
Supply, delivery and installation of
Fire department connection c/w
cabinet and piping to hosereel
d)
system
(including
fire
rated
encasement
where
protected
lobby)

Pipe DN100.

1,050,837,129

1,050,837,129

1,050,837,129

433,365,042

294,471,230

433,365,042

100%

Page 59 of 80

294,471,230

433,365,042

100%

294,471,230

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

%
Work
Done
to
Date

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

Value of Work Done


to Date

ELECTRICAL SERVICES
Pipe DN65.

18,379,479

100%

18,379,479

100%

18,379,479

Pipe DN50.

28,674,640

100%

28,674,640

100%

28,674,640

Tee DN100

10,997,964

100%

10,997,964

100%

10,997,964

Tee DN150
Elbow Screwed end DN50.

336,932
2,937,029

100%
100%

336,932
2,937,029

100%
100%

336,932
2,937,029

Reduce DN100/65.

1,034,953

100%

1,034,953

100%

1,034,953

Reduce DN100/50.
Reduce DN65/50.

3,622,335
464,076

100%
100%

3,622,335
464,076

100%
100%

3,622,335
464,076

28,789,758

100%

28,789,758

100%

28,789,758

5,223,503

100%

5,223,503

100%

5,223,503

1,440,966
1,125,755
657,129
27,365,150
2,811,196
5,032,947
-

100%
100%
100%
100%
100%
100%
100%

1,440,966
1,125,755
657,129
27,365,150
2,811,196
5,032,947
-

100%
100%
100%
100%
100%
100%
100%

1,440,966
1,125,755
657,129
27,365,150
2,811,196
5,032,947
-

Painting pipe line.


Flange for pipe DN65
Sleeve coupling DN50
Bolt for flange.
Gasket for flange DN65
Support for pipe DN100
Support for pipe DN65
Support for pipe DN50
Accessories.
Supply, delivery and installation of
Pipework including drain and air
e)
relief
valves,
earthing
and
accessories
Automatic air vent valve.
Supply, delivery and installation of
f)
Indoor Hose cabinets
Fire box indoor (450x650x230).

4,605,795

4,605,795
100%

260,573,643

4,605,795

4,605,795
100%

260,573,643

4,605,795
260,573,643

68,652,922

100%

68,652,922

100%

68,652,922

63,879,603

100%

63,879,603

100%

63,879,603

107,131,417

100%

107,131,417

100%

107,131,417

11,178,931

100%

11,178,931

100%

11,178,931

Connection type B.

2,640,497

100%

2,640,497

100%

2,640,497

Thread two DN50.


Accessories.

2,237,736
4,852,537

100%
100%

2,237,736
4,852,537

100%
100%

2,237,736
4,852,537

Fire hose reel DN50 (25


metric/roll).
Angle valve DN50.
Nozzled DN50.

g)

4,605,795

Supply, delivery and installation of


Outdoor Hose cabinets

352,292,650

352,292,650

352,292,650

Fire box indoor (700x550x330).

40,327,590

100%

40,327,590

100%

40,327,590

Fire hose reel DN65 (25


metric/roll).

49,905,940

100%

49,905,940

100%

49,905,940

9,654,531

100%

9,654,531

100%

9,654,531

Nozzled DN65.

Page 60 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

6B.5

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

ELECTRICAL
ConnectionSERVICES
type A.

2,176,410

100%

2,176,410

100%

2,176,410

Thread two DN65.

2,746,312

100%

2,746,312

100%

2,746,312

Foam System include (Foam


cabinet, Foam tank, Protioner, Fire
hose, Foam Nozzle)

215,600,000

100%

215,600,000

100%

215,600,000

3% FoamAFFF fighting substances.


Accessories.

24,849,901
7,031,966

100%
100%

24,849,901
7,031,966
-

100%
100%

24,849,901
7,031,966
-

External Fire Hydrant


Supply, delivery and installation of
a)
Underground fire hydrant pipework

2,026,254,513

2,026,254,513

2,026,254,513

1,908,808,798

1,908,808,798

1,908,808,798

Pipe DN200.

1,176,152,282

100%

1,176,152,282

100%

1,176,152,282

Pipe DN100.

102,246,955

100%

102,246,955

100%

102,246,955

Tee DN200.

30,466,904

100%

30,466,904

100%

30,466,904

Elbow DN200.
Elbow DN100.
Reduce DN200/150.
Reduce DN200/100.

31,476,110
3,204,031
1,748,231
7,692,218

100%
100%
100%
100%

31,476,110
3,204,031
1,748,231
7,692,218

100%
100%
100%
100%

31,476,110
3,204,031
1,748,231
7,692,218

219,164,638

100%

219,164,638

100%

219,164,638

25,031,493
55,294,424
23,424,700
2,429,719
15,617,532
23,100,000
36,546,878
62,370,000
29,040,000
30,802,682
33,000,000

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

25,031,493
55,294,424
23,424,700
2,429,719
15,617,532
23,100,000
36,546,878
62,370,000
29,040,000
30,802,682
33,000,000

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

25,031,493
55,294,424
23,424,700
2,429,719
15,617,532
23,100,000
36,546,878
62,370,000
29,040,000
30,802,682
33,000,000

Flange DN200.
Flange DN100.
Bolt for flange.
Buffer for flange DN200
Buffer for flange DN100
Bitum
Back filling
Support for pipe line DN200 (in
Concrete for Underground pipe
Bearing pipe outside
Accessories.
Testing systems.
Supply, delivery and installation of
b) Pillar hydrants c/w sluice valves,
valve chambers, duck foot bends
Breeching inlet 4 way.
Out door hydrant DN100.
Concrete for fire hydrant
6B.6

%
Work
Done
to
Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

Portable Fire Extinguishers


Supply, delivery and installation of
Portable
fire
extinguisher dry
a)
powder ABC c/w mounting brackets
and steel cabinets

117,445,716

117,445,716

117,445,716

9,988,301

100%

9,988,301

100%

9,988,301

100,527,415

100%

100,527,415

100%

100,527,415

6,930,000

100%

6,930,000

100%

6,930,000

136,077,063

136,077,063

136,077,063

51,763,525

51,763,525

51,763,525

Page 61 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

ELECTRICAL SERVICES
Extinguisher powder ABC 8Kg.
Support for extinguisher.
Fire sigh board.
Supply, delivery and installation of
Portable fire extinguisher CO2 c/w
b)
mounting
brackets
and
steel
cabinets
Extinguisher carbon dioxide 5kg.
Support for extinguisher.
6B.7

Cold Water System


a) Supply, delivery and installation

%
Work
Done
to
Date

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

Value of Work Done


to Date

45,573,197

100%

45,573,197

100%

45,573,197

3,583,874
2,606,454

100%
100%

3,583,874
2,606,454

100%
100%

3,583,874
2,606,454

84,313,537

84,313,537

80,729,663

100%

3,583,874

100%

84,313,537

80,729,663

100%

3,583,874

100%

80,729,663
3,583,874

1,894,490,054

1,894,490,054

1,894,490,054

70,504,087

70,504,087

70,504,087

Water meter DN80

14,468,300

100%

14,468,300

100%

14,468,300

Gate valve D100

20,560,254

100%

20,560,254

100%

20,560,254

7,155,940
525,580

100%
100%

7,155,940
525,580

100%
100%

7,155,940
525,580

18,638,511

100%

18,638,511

100%

18,638,511

2,334,438
2,640,000
1,320,000
1,320,000
1,541,065

100%
100%
100%
100%
100%

2,334,438
2,640,000
1,320,000
1,320,000
1,541,065

100%
100%
100%
100%
100%

2,334,438
2,640,000
1,320,000
1,320,000
1,541,065

11,000,000

100%

11,000,000

100%

11,000,000

Flange DN100
Flange DN80/D90
PPR Pipe -DN100/D110
Elbow PPR-DN100
Valve manholes
Water meter Manhole
Excavating & Backfilling
Accessories
To liaise and plan submission to the
VSIP including all necessary cost
b)
for the connection of new water
supply system to their existing
Supply, delivery and installation of
cold water pipework complete with
c) excavation & making good of the
land in the area of work, supports,
valves, fittings and accessories for
From incoming to bulk meter
i)
c/w bulk meter chamber

1,684,095,095

1,684,095,095

1,684,095,095

98,926,737

98,926,737

98,926,737

Gate valve DN100

20,560,254

100%

20,560,254

100%

20,560,254

Float valve DN100

43,628,200

100%

43,628,200

100%

43,628,200

Horn Bell

1,295,910

100%

1,295,910

100%

1,295,910

Cable and PVC conduit

1,507,000

100%

1,507,000

100%

1,507,000

Check valve DN100

6,512,143

100%

6,512,143

100%

6,512,143

Flange DN100

2,602,160

100%

2,602,160

100%

2,602,160

PPR Pipe -DN100/D110

13,555,281

100%

13,555,281

100%

13,555,281

Elbow PPR-DN100
Tee PPR-DN100
Vent tap for Pool DN100

2,334,438
711,095
2,530,000

100%
100%
100%

2,334,438
711,095
2,530,000

100%
100%
100%

2,334,438
711,095
2,530,000

Sleeve STK DN100

1,078,958

100%

1,078,958

100%

1,078,958

352,000
2,259,299

100%
100%

352,000
2,259,299

100%
100%

352,000
2,259,299

Excavating & Backfilling


Accessories
From bulk water meter to
ii)
domestic water transfer tanks
Luppe Valve DN100

202,481,243

202,481,243

202,481,243

7,031,618

100%

7,031,618

100%

7,031,618

Gate valve DN100

41,120,508

100%

41,120,508

100%

41,120,508

Y-strainner DN100

10,530,080

100%

10,530,080

100%

10,530,080

Page 62 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

ELECTRICAL
FlexibleSERVICES
joint DN100
Check valve DN100
Float level switch

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM
%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

11,414,920

100%

11,414,920

100%

11,414,920

13,024,286

100%

13,024,286

100%

13,024,286

3,570,875

100%

3,570,875

100%

3,570,875

3,735,875

100%

3,735,875

100%

3,735,875

Pressure gauge (0~15bar) +


valve
Pressure switch(0~10bar) +
valve
Pressure tank +valve, V=500L

1,565,701

100%

1,565,701

100%

1,565,701

27,456,605

100%

27,456,605

100%

27,456,605

Water hammer arrest

49,198,600

100%

49,198,600

100%

49,198,600

5,529,590

100%

5,529,590

100%

5,529,590

13,555,281

100%

13,555,281

100%

13,555,281

2,334,438
1,422,190
5,093,165

100%
100%
100%

2,334,438
1,422,190
5,093,165

100%
100%
100%

2,334,438
1,422,190
5,093,165

Flange DN100
PPR Pipe -DN100/D110
Elbow PPR-DN100
Tee PPR-DN100
Tee PPR-DN100/32
Concrete for support water
pump
Accessories
From bulk meter to points of
iii)
usage in common areas

5,897,512

100%
100%

1,099,125,531

5,897,512

100%
100%

1,099,125,531

5,897,512
1,099,125,531

GI PIPE DN150

13,169,930

100%

13,169,930

100%

13,169,930

GI PIPE DN80

14,681,220

100%

14,681,220

100%

14,681,220

GI PIPE DN50

3,999,570

100%

3,999,570

100%

3,999,570

50,832,302

100%

50,832,302

100%

50,832,302

PPR Pipe -DN80/D90

169,469,190

100%

169,469,190

100%

169,469,190

PPR Pipe -DN50/D63

197,692,259

100%

197,692,259

100%

197,692,259

PPR Pipe -DN40/D50

28,784,250

100%

28,784,250

100%

28,784,250

PPR Pipe -DN32/D40

75,007,680

100%

75,007,680

100%

75,007,680

PPR Pipe -DN25/D32

80,574,556

100%

80,574,556

100%

80,574,556

PPR Pipe -DN20/D25

13,326,885

100%

13,326,885

100%

13,326,885

PPR Pipe -DN15/D20

3,032,288

100%

3,032,288

100%

3,032,288

104,395,104
16,757,049
54,572,331
53,871,532
4,266,374
1,352,089
1,167,219
2,173,952
1,198,454
171,486
242,259
35,288
527,032

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

104,395,104
16,757,049
54,572,331
53,871,532
4,266,374
1,352,089
1,167,219
2,173,952
1,198,454
171,486
242,259
35,288
527,032

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

104,395,104
16,757,049
54,572,331
53,871,532
4,266,374
1,352,089
1,167,219
2,173,952
1,198,454
171,486
242,259
35,288
527,032

2,083,696

100%

2,083,696

100%

2,083,696

172,073
500,438
51,067
139,837
738,595
923,793

100%
100%
100%
100%
100%
100%

172,073
500,438
51,067
139,837
738,595
923,793

100%
100%
100%
100%
100%
100%

172,073
500,438
51,067
139,837
738,595
923,793

PPR Pipe -DN100/D110

Coupling PPR-DN50/D63
Coupling PPR-DN40/D50
Coupling PPR-DN32/D40
Coupling PPR-DN25/D32
Coupling PPR-DN20/D25
Coupling PPR-DN15/D20
Elbow PPR - DN100/D110
Elbow PPR - DN80/D90
Elbow PPR - DN50/D63
Elbow PPR - DN40/D50
Elbow PPR - DN32/D40
Elbow PPR - DN25/D32
Elbow PPR - DN20/D25
Threaded 90 Elbow Female DN15
Reduce PPR - DN50/40
Reduce PPR - DN50/32
Reduce PPR - DN40/32
Reduce PPR - DN40/25
Tee PPR - DN100/D110
Tee Reduce PPR-DN100/80

Page 63 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

Tee Reduce
PPR-DN80/50
ELECTRICAL
SERVICES
Tee Reduce PPR-DN80/40
Tee PPR-DN50/D63
Tee PPR-DN40/D50
Tee Reduce PPR-DN32/20
Tee Reduce PPR-DN25/20

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM
%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

Value of Work Done


to Date

1,066,036
7,565,498
1,666,069
479,784
727,276
297,147

100%
100%
100%
100%
100%
100%

1,066,036
7,565,498
1,666,069
479,784
727,276
297,147

100%
100%
100%
100%
100%
100%

1,066,036
7,565,498
1,666,069
479,784
727,276
297,147

Gate valve - DN50

16,462,677

100%

16,462,677

100%

16,462,677

Gate valve - DN40

2,888,996

100%

2,888,996

100%

2,888,996

1,356,300
22,834,196
5,236,000
74,800,000
42,075,000
25,760,755

100%
100%
100%
100%
100%
100%

1,356,300
22,834,196
5,236,000
74,800,000
42,075,000
25,760,755

100%
100%
100%
100%
100%
100%

1,356,300
22,834,196
5,236,000
74,800,000
42,075,000
25,760,755

Flange DN50/D63
Garden Faucet
Concrete for Garden faucet
Excavating & Backfilling
Sand backfill
Accessories
From domestic water transfer
iv)
tanks to around external &
PPR Pipe -DN80/D90
Tee PPR - DN80/D90
Elbow PPR - DN80/D90
Gate valve - DN80
Flange DN80/D90
Hanger & Support
Accessories
From domestic water transfer
tanks to water sub-meters
v) and/or main branch-off points
on all floors including main
droppers and main dropper
From water sub-meters and/or
main branch-off points to
vi)
toilets, Valves provision for
pantry and other final points of

81,865,273

81,865,273

81,865,273

45,191,784

100%

45,191,784

100%

45,191,784

1,032,218
2,173,952

100%
100%

1,032,218
2,173,952

100%
100%

1,032,218
2,173,952

25,040,004

100%

25,040,004

100%

25,040,004

2,102,320
4,406,277
1,918,717

100%
100%
100%

2,102,320
4,406,277
1,918,717

100%
100%
100%

2,102,320
4,406,277
1,918,717

201,696,311

201,696,311

201,696,311

PPR Pipe -DN50/D63

5,857,548

100%

5,857,548

100%

5,857,548

PPR Pipe -DN40/D50

19,957,080

100%

19,957,080

100%

19,957,080

PPR Pipe -DN32/D40

12,126,242

100%

12,126,242

100%

12,126,242

PPR Pipe -DN25/D32

14,665,422

100%

14,665,422

100%

14,665,422

PPR Pipe -DN20/D25

18,894,561

100%

18,894,561

100%

18,894,561

PPR Pipe -DN15/D20

28,503,503

100%

28,503,503

100%

28,503,503

Coupling PPR-DN50/D63
Coupling PPR-DN40/D50
Coupling PPR-DN32/D40
Coupling PPR-DN25/D32
Coupling PPR-DN20/D25
Coupling PPR-DN15/D20
Elbow PPR - DN50/D63
Elbow PPR - DN40/D50
Elbow PPR - DN32/D40
Elbow PPR - DN25/D32
Elbow PPR - DN20/D25
Elbow PPR - DN15/D20
Tee PPR-DN40/D50
Tee PPR-DN32/D40
Tee PPR-DN25/D32
Tee PPR-DN20/25
Threaded 90 Elbow Female DN15

3,367,584
11,852,547
8,930,018
9,738,315
6,055,498
12,490,729
299,614
1,200,399
387,614
70,576
527,032
2,464,431
239,892
431,038
1,554,721
2,881,439

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

3,367,584
11,852,547
8,930,018
9,738,315
6,055,498
12,490,729
299,614
1,200,399
387,614
70,576
527,032
2,464,431
239,892
431,038
1,554,721
2,881,439

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

3,367,584
11,852,547
8,930,018
9,738,315
6,055,498
12,490,729
299,614
1,200,399
387,614
70,576
527,032
2,464,431
239,892
431,038
1,554,721
2,881,439

8,396,070

100%

8,396,070

100%

8,396,070

Page 64 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

DESCRIPTION
Contract value

%
Work
Done
to
Date

Value of Work Done


to Date

%
Work
Done
to
Date

ELECTRICAL
SERVICES
Gate valve
- DN40

2,888,996

100%

2,888,996

100%

2,888,996

Gate valve - DN25

9,983,974

100%

9,983,974

100%

9,983,974

2,055,020

100%

2,055,020

100%

2,055,020

11,149,192
4,727,257

100%
100%

11,149,192
4,727,257

100%
100%

11,149,192
4,727,257

Gate valve - DN20


Hanger & Support
Accessories
Supply, delivery and installation of
the following pumpsets complete
d) with RSJ base, vibration isolation,
power and control wiring, control
panels, and accessories:
Cold water booster pumps and
i)
hyropneumatic tanks
Water Pump Q=65m3/h,
Control Panle for Pump
Pressure tank +valve, V=500L
Acessories : inertia base, spring
isolators. .etc.

178,715,647

178,715,647

178,715,647

178,715,647
100,045,220
28,845,652
27,824,775

100%
100%
100%

100,045,220
28,845,652
27,824,775

100%
100%
100%

100,045,220
28,845,652
27,824,775

22,000,000

100%

22,000,000

100%

22,000,000

6B.8

Value of Work Done


to Date

Sanitary Drainage System

371,887,056

371,887,056

371,887,056

Supply, delivery and installation of


sanitary
drainage
system,
inspection chambers, grease trap,
a)
screen chamber, hatch boxes, floor
traps, gully traps, scupper rain,
piping and accessories

50,000,000

100%

50,000,000

100%

50,000,000

To liaise and plan submission to the


VSIP including all necessary cost
b) for the connection of new sanitary
system to their existing sanitary
system

5,000,000

100%

5,000,000

100%

5,000,000

Supply, delivery and installation of


sanitary
drainage
system
(aboveground), comprising soil,
c)
waste and vent pipes, floor drains,
floor
traps
and
accessories
connecting to inspection chambers
i) Area of toilet - WC101
Water closet sitting c/w all
accessories finishing

381,582,456

381,582,456

381,582,456

97,701,821

97,701,821

97,701,821

41,415,400

100%

41,415,400

100%

41,415,400

Urinal with water tap (press)


c/w all accessories finishing

4,190,500

100%

4,190,500

100%

4,190,500

Wash hand basin c/w water tap


and all accessories finishing

9,306,000

100%

9,306,000

100%

9,306,000

Stainlesss steel paper holder

3,894,700

100%

3,894,700

100%

3,894,700

Water bib tap and washing hose


for Water closet

5,888,800

100%

5,888,800

100%

5,888,800

uPVC Pipe D150

4,280,105

100%

4,280,105

100%

4,280,105

uPVC Pipe D100

12,574,693

100%

12,574,693

100%

12,574,693

uPVC Pipe D80

560,189

100%

560,189

100%

560,189

uPVC Pipe D50

889,643

100%

889,643

100%

889,643

Page 65 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

ELECTRICAL
SERVICES
uPVC Pipe
D40
uPVC Pipe D32

%
Work
Done
to
Date

472,351

100%

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

472,351

100%

Value of Work Done


to Date

472,351

952,583

100%

952,583

100%

952,583

9,460,325
2,065,223
1,751,309
76,161,256

100%
100%
100%
100%

9,460,325
2,065,223
1,751,309
76,161,256

100%
100%
100%

9,460,325
2,065,223
1,751,309
76,161,256

uPVC Pipe D150

29,485,165

100%

29,485,165

100%

29,485,165

uPVC Pipe D100

12,155,536

100%

12,155,536

100%

12,155,536

uPVC Pipe D80

2,912,982

100%

2,912,982

100%

2,912,982

uPVC Pipe D40

472,351

100%

472,351

100%

472,351

Fitting for uPVC Pipe


Hanger & Support
Accessories
ii) Area of toilet - WC102

uPVC Pipe D32

842,670

100%

842,670

100%

842,670

21,994,043
4,490,535
3,807,974
8,302,048

100%
100%
100%

21,994,043
4,490,535
3,807,974
8,302,048

100%
100%
100%

21,994,043
4,490,535
3,807,974
8,302,048

3,912,127

100%

3,912,127

100%

3,912,127

uPVC Pipe D50

635,459

100%

635,459

100%

635,459

uPVC Pipe D32

366,378

100%

366,378

100%

366,378

2,356,246
500,893
530,946
84,544,965

100%
100%
100%

2,356,246
500,893
530,946
84,544,965

100%
100%
100%

2,356,246
500,893
530,946
84,544,965

uPVC Pipe D150

43,514,397

100%

43,514,397

100%

43,514,397

uPVC Pipe D100

6,846,222

100%

6,846,222

100%

6,846,222

uPVC Pipe D40

330,646

100%

330,646

100%

330,646

uPVC Pipe D32

512,929

100%

512,929

100%

512,929

24,552,411
4,755,606
4,032,754
51,476,964

100%
100%
100%

24,552,411
4,755,606
4,032,754
51,476,964

100%
100%
100%

24,552,411
4,755,606
4,032,754
51,476,964

uPVC Pipe D150

18,071,553

100%

18,071,553

100%

18,071,553

uPVC Pipe D100

8,522,847

100%

8,522,847

100%

8,522,847

uPVC Pipe D80

2,352,793

100%

2,352,793

100%

2,352,793

uPVC Pipe D50

317,730

100%

317,730

100%

317,730

Fitting for uPVC Pipe


Hanger & Support
Accessories
iii) Area of toilet - WC103
uPVC Pipe D100

Fitting for uPVC Pipe


Hanger & Support
Accessories
iv) Area of toilet - WC104

Fitting for uPVC Pipe


Hanger & Support
Accessories
v) Area of toilet - WC105

uPVC Pipe D32

1,795,253

100%

1,795,253

100%

1,795,253

14,893,354
2,988,872
2,534,563
29,503,783

100%
100%
100%

14,893,354
2,988,872
2,534,563
29,503,783

100%
100%
100%

14,893,354
2,988,872
2,534,563
29,503,783

uPVC Pipe D150

3,804,537

100%

3,804,537

100%

3,804,537

uPVC Pipe D100

9,920,036

100%

9,920,036

100%

9,920,036

uPVC Pipe D80

2,352,793

100%

2,352,793

100%

2,352,793

uPVC Pipe D40

897,467

100%

897,467

100%

897,467

622,843

100%

622,843

100%

622,843

8,438,085

100%

8,438,085

100%

8,438,085

Fitting for uPVC Pipe


Hanger & Support
Accessories
vi) Area of toilet - WC106

uPVC Pipe D32


Fitting for uPVC Pipe

Page 66 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

DESCRIPTION
Contract value

Hanger SERVICES
& Support
ELECTRICAL
Accessories
vii) Area of toilet - WC201

100%
100%

1,876,636
1,591,387
16,603,240

uPVC Pipe D150

4,042,321

100%

4,042,321

100%

4,042,321

uPVC Pipe D100

1,956,063

100%

1,956,063

100%

1,956,063

uPVC Pipe D80

1,120,378

100%

1,120,378

100%

1,120,378

uPVC Pipe D50

1,461,556

100%

1,461,556

100%

1,461,556

uPVC Pipe D40

283,411

100%

283,411

100%

283,411

uPVC Pipe D32

769,394

100%

769,394

100%

769,394

uPVC Pipe D25

241,131

100%

241,131

100%

241,131

4,734,704
1,079,157
915,126
17,288,378

100%
100%
100%

4,734,704
1,079,157
915,126
17,288,378

100%
100%
100%

4,734,704
1,079,157
915,126
17,288,378

uPVC Pipe D150

2,377,836

100%

2,377,836

100%

2,377,836

uPVC Pipe D100

1,956,063

100%

1,956,063

100%

1,956,063

uPVC Pipe D80

2,128,717

100%

2,128,717

100%

2,128,717

uPVC Pipe D50

2,351,198

100%

2,351,198

100%

2,351,198

uPVC Pipe D40

330,646

100%

330,646

100%

330,646

uPVC Pipe D32

696,118

100%

696,118

100%

696,118

uPVC Pipe D25

241,131

100%

241,131

100%

241,131

Fitting for uPVC Pipe


Hanger & Support
Accessories

4,834,180
1,151,693
1,220,795

100%
100%
100%

4,834,180
1,151,693
1,220,795
-

100%
100%
100%

4,834,180
1,151,693
1,220,795
-

Testing and Commissioning

237,000,000

c) Automatic Sprinkler System

237,000,000

237,000,000

45,000,000

100%

45,000,000

100%

45,000,000

115,000,000

100%

115,000,000

100%

115,000,000

40,000,000

100%

40,000,000

100%

40,000,000

d) Hosereel System

100%

e) External Fire Hydrant

100%

f) Portable Fire Extinguishers

100%

g) Cold Water System

21,000,000

100%

21,000,000

100%

21,000,000

h) Sanitary Drainage System

16,000,000

100%

16,000,000

100%

16,000,000

Maintenance and Warranty


Comprehensive
Maintenance/Servicing
during
Contractual Maintenance Period
Fire Stopping
One lot of fire stops and fire proofing
materials

6B.12

Value of Work Done


to Date

1,876,636
1,591,387
16,603,240

b) Air-conditioning

6B.11

Value of Work Done


to Date

%
Work
Done
to
Date

100%
100%

a) Mechanical Ventilation System

6B.10

%
Work
Done
to
Date

1,876,636
1,591,387
16,603,240

Fitting for uPVC Pipe


Hanger & Support
Accessories
viii)Area of toilet - WC202

6B.9

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE

UNICONS' CLAIM

Any Other Works


Any other works not mentioned above
but are necessary for the completion
of the entire works (please specify):

240,000,000
240,000,000

240,000,000
100%

60,000,000
60,000,000

240,000,000

240,000,000
100%

60,000,000
100%

1,568,827,228
-

Page 67 of 80

60,000,000
1,568,827,228
-

240,000,000
60,000,000

100%

60,000,000
1,568,827,228
-

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

Sanitary system
: Suppy, delivery
ELECTRICAL
SERVICES
& installation of HDPE pipe, waste
a) drainage pumps referred to
drawing AMD/TBCBall/1102/SAN/2003 - Rev.A dated
Drainage Pump
Drainage Pump Q=35m3/h,
H=20m

%
Work
Done
to
Date

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date

Value of Work Done


to Date

967,111,828

967,111,828

967,111,828

633,415,149

633,415,149

633,415,149

158,131,820

100%

158,131,820

100%

158,131,820

Control Panle for Pump


Drainage Pump Q=10m3/h,
H=20m

25,504,468

100%

25,504,468

100%

25,504,468

97,326,680

100%

97,326,680

100%

97,326,680

Control Panle for Pump


Luppe Valve DN100
Luppe Valve DN80
Gate valve DN100
Gate valve DN80
Flexible joint DN100

95,126,680
14,063,236
35,717,088
20,560,254
50,080,008
5,707,460

100%
100%
100%
100%
100%
100%

95,126,680
14,063,236
35,717,088
20,560,254
50,080,008
5,707,460

100%
100%
100%
100%
100%
100%

95,126,680
14,063,236
35,717,088
20,560,254
50,080,008
5,707,460

Flexible joint DN80

20,068,650

100%

20,068,650

100%

20,068,650

Check valve DN100


Check valve DN80
Float level switch
Flange DN100
Flange DN80

13,024,286
34,641,640
17,854,375
2,602,160
8,409,280

100%
100%
100%
100%
100%

13,024,286
34,641,640
17,854,375
2,602,160
8,409,280

100%
100%
100%
100%
100%

13,024,286
34,641,640
17,854,375
2,602,160
8,409,280

HDPE Pipe -DN100

1,704,081

100%

1,704,081

100%

1,704,081

HDPE Pipe -DN80

3,980,456

100%

3,980,456

100%

3,980,456

876,773

100%

876,773

100%

876,773

2,189,066

100%

2,189,066

100%

2,189,066

766,216

100%

766,216

100%

766,216

1,772,503

100%

1,772,503

100%

1,772,503

128,700
413,600
7,920,000
14,845,668
333,696,679

100%
100%
100%
100%
100%

128,700
413,600
7,920,000
14,845,668
333,696,679

100%
100%
100%
100%

128,700
413,600
7,920,000
14,845,668
333,696,679

HDPE Pipe DN150

219,052,409

100%

219,052,409

100%

219,052,409

HDPE Pipe DN100

13,824,356

100%

13,824,356

100%

13,824,356

HDPE Pipe DN80

11,415,381

100%

11,415,381

100%

11,415,381

Elbow 45deg HDPE DN150

767,283

100%

767,283

100%

767,283

Elbow 45deg HDPE DN100

1,543,121

100%

1,543,121

100%

1,543,121

535,105

100%

535,105

100%

535,105

Y HDPE DN80

3,138,234

100%

3,138,234

100%

3,138,234

End Cap uPVC DN150

2,086,815

100%

2,086,815

100%

2,086,815

End Cap uPVC DN100

5,192,981

100%

5,192,981

100%

5,192,981

438,098

100%

438,098

100%

438,098

65,642,500
2,239,380

100%
100%

65,642,500
2,239,380

100%
100%

65,642,500
2,239,380

Elbow 45deg HDPE-DN100


Elbow 45deg HDPE-DN80
Tee HDPE-DN100
Tee HDPE-DN80
Testing socket D100
Testing socket D80
Support for Drainage pump
Accessories
Drainage Inside factory

Elbow 45deg HDPE DN80

End Cap uPVC DN80


Support for HDPE pipe
Sleeve STK

Page 68 of 80

REMARK

VALUE OF WORK DONE (Ending 20 June, 2012)


AMOUNT
NO

UNICONS' CLAIM

DESCRIPTION
Contract value

Accessories
ELECTRICAL
SERVICES
LPG piping sytem : Suppy, delivery
& installation of HDPE pipe, waste
b)
drainage pumps referred to
drawing AMD/TBCSteel Pipe DN100 grade B,
schedule 40

7,821,016

%
Work
Done
to
Date
100%

601,715,400

Value of Work Done


to Date
7,821,016

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
%
Work
Done
to
Date
100%

601,715,400

Value of Work Done


to Date
7,821,016
601,715,400

319,896,500

100%

319,896,500

100%

319,896,500

Steel Pipe DN40 grade B, schedule


40

29,452,500

100%

29,452,500

100%

29,452,500

Globe valve DN100


Globe valve DN50
Regulator valve DN50
Steel fitting
T&C

36,367,100
65,409,300
35,915,000
97,350,000
17,325,000

100%
100%
100%
100%
100%

36,367,100
65,409,300
35,915,000
97,350,000
17,325,000

100%
100%
100%
100%
100%

36,367,100
65,409,300
35,915,000
97,350,000
17,325,000

Page 69 of 80

REMARK

PROJECT

: MAIN TENDER PACKAGE FOR PROPOSED CONSTRUCTION AND COMPLETION OF TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM
SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE, VIETNAM

Bill 7

: ADJUSTMENT OF PROVISONAL SUM (EI-14, 32)

SUMMARY - REVISION 5 - 20 AUG 2011


VALUE OF WORK DONE (Ending 20 June, 2012)
AMOUNT
NO

DESCRIPTION
Contract value

I
A

% Work
Done to
Date

Value of Work Done


to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
% Work
Value of Work Done
Done to
to Date
Date

ADDITION THE NEW PROVISIONAL AMOUNT FOLLOW EI(14,32)


12,688,200,800

100.0%

12,688,200,800

100.0%

12,688,200,800

A.1

Supply fan in Warehouse

1,423,889,733

100.0%

1,423,889,733

100.0%

1,423,889,733

A.2

Supply fan in Factory

7,777,561,226

100.0%

7,777,561,226

100.0%

7,777,561,226

A.3

Exhaust fan in Factory

3,486,749,840

100.0%

3,486,749,840

100.0%

3,486,749,840

6,426,583,653

100.0%

6,426,583,653

100.0%

6,426,583,653

MECHANICAL SERVICES

ELECTRICAL ADDITION

B.1

Supply fan in Factory & Warehouse

3,487,149,132

100.0%

3,487,149,132

100.0%

3,487,149,132

B.2

Exhaust fan in Factory

1,436,152,493

100.0%

1,436,152,493

100.0%

1,436,152,493

B.3

Main cable from MSB to MCC of fan

1,503,282,028

100.0%

1,503,282,028

100.0%

ELECTRICAL DEDUCTION

C.1

Distribution boards

C.2

Distribution Submains Cable

D
D.1
E

(1,940,246,685)

STEEL STRUCTURE AND WATERPROOFING FOR FANS


Stell structure and waterproofing gfor fans
DISCOUNT

TOTAL AMOUNT (INCLUDED VAT)

PROVISIONAL

AMOUNT

(1,940,246,685) 100.0%

1,503,282,028
(1,940,246,685)

(918,182,050)

(918,182,050)

100.0%

(918,182,050)

(1,022,064,635)

(1,022,064,635)

100.0%

(1,022,064,635)

5,217,366,774

(500,000,000)

Sub Total Lump Sum (Incl. VAT)


DEDUCT THE ORIGIN
(INCLUDED VAT)

100.0%

100.0%

5,217,366,774

Sub Total Lump Sum (Excl. VAT)

II

UNICONS' CLAIM

5,217,366,774

100.0%

5,217,366,774
100.0%

5,217,366,774
5,217,366,774

(500,000,000) 100.0%

(500,000,000)

21,891,904,542

100.0%

21,891,904,542

100.0%

21,891,904,542

24,081,094,996

100.0%

24,081,094,996

100.0%

24,081,094,996

(48,199,597,016)

100.0%

(48,199,597,016)

100.0%

(48,199,597,016)

(24,118,502,019)

100.0%

(24,118,502,019)

100.0%

(24,118,502,019)

REMAR
K

Substation 2, Transformer room & Consumer switchroom(Street Lighting)

0.2

0.21

0.22

0.23

0.24

.25

PROJECT :

MAIN TENDER PACKAGE FOR PROPOSED CONSTRUCTION AND COMPLETION OF TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM
SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE, VIETNAM

Bill 7

ADJUSTMENT OF PROVISONAL SUM (EI-14, 32)

SUMMARY - REVISION 5 - 20 AUG 2011


The itemised Breakdown of the Lump Sum Tender Price as listed below shall form only as an indication of the breakdown value for this contract works. The tenderer shall price the
contract works in accordance with the Tender Drawings and Documents. No claim for extra or otherwise shall be considered for any trade/items/works as specified and shown in the
Tender Drawings and Specifications but not described hereunder.
VALUE OF WORK DONE (Ending 20 June, 2012)
UNIT RATE
Description

No.

Unit

AMOUNT

Quantity

Material rate

Labour / overheads
/
Profits

A. Mechanical
A.1 Supply fan in Warehouse
Fan
I
Hooded Roof Ventilator

Contract value

12,688,200,800
1,423,889,733
1,241,172,000
set

114,912,000

6,124,000

1,089,324,000

UNICONS' CLAIM
%
Work
Done
to
Date
100%

100%

Value of Work
Done to Date
12,688,200,800
1,423,889,733
1,089,324,000

ATELIER & UNICONS


AGREED VALUE OF
WORK DONE
%
Work
Value of Work
Done
Done to Date
to
Date
100%
12,688,200,800
100% 1,423,889,733
100%

1,089,324,000

Maker: New York Blower

Original: Philippin
Model: NYPSBC54Q

Working point: 38,002 CFM @ Free blow


Speed of fan: 996 rpm (Belt driven
type)
Motor: 5Hp
Power: 400v / 3p / 50Hz
Hood made of Actec in Vietnam
Stainless steel wire-mesh for fresh air
intake
Steel support for fan to be hot-dip
galvanized

set
set

9
9

5,582,000
8,644,000

630,000
2,016,000

55,908,000
95,940,000

100%
100%

55,908,000
95,940,000

100%
100%

55,908,000
95,940,000

II

Actec Other's cost


(Other Temp. facilities, office,
Transportation, Site Management etc.)

lot

53,273,212

53,273,212

100%

53,273,212

100%

53,273,212

III

Unicons's fee

lot

129,444,521

129,444,521

100%

129,444,521

100%

129,444,521

6,124,000

7,777,561,226
4,245,600,000
3,739,440,000

A.2 Supply fan in Factory


Fan
I
Hooded Roof Ventilator
Maker: New York Blower
Original: Philippin
Model: NYPSBC54S
Working point: 36,996 CFM @ 1/2" SP
Speed of fan: 996 rpm (Belt driven
type)
Motor: 10Hp
Power: 400v / 3p / 50Hz
Hood made by Actec in Vietnam
Stainless steel wire-mesh for fresh air
intake
Steel support for fan to be hot-dip
galvanized
II

Duct works
Transistion between fan & duct
Spiral air duct 1400mm thickness 1.2mm
c/w angle bar flange
Elbow 90 degree made of galvanised
steel sheet 1.2mm c/w flange
Plenum box c/w air grilles (Square type Air velocity at face size 5m/s)
Supports for vertical air ducts
Supports for horizontal air ducts

set

30

118,524,000

7,777,561,226
100%

3,739,440,000
-

7,777,561,226
100%

3,739,440,000
-

set

30

5,582,000

630,000

186,360,000

100%

186,360,000

100%

186,360,000

set

30

8,644,000

2,016,000

319,800,000

100%

319,800,000

100%

319,800,000

set

30

3,927,000

683,000

2,601,264,000
138,300,000

100%

2,601,264,000
138,300,000

100%

2,601,264,000
138,300,000

333

2,361,000

389,000

915,750,000

100%

915,750,000

100%

915,750,000

pc.

48

8,236,000

972,000

441,984,000

100%

441,984,000

100%

441,984,000

set

30

24,701,000

5,082,000

893,490,000

100%

893,490,000

100%

893,490,000

set
set

30
24

3,520,000
3,245,000

554,000
485,000

122,220,000
89,520,000

100%
100%

122,220,000
89,520,000

100%
100%

122,220,000
89,520,000

III

Actec Other's cost


(Other Temp. facilities, office,
Transportation, Site Management etc.)

lot

223,646,206

223,646,206

100%

223,646,206

100%

223,646,206

IV

Unicons's fee

lot

707,051,021

707,051,021

100%

100%

5,032,000

3,486,749,840
3,069,510,000
2,749,710,000

100%

707,051,021
3,486,749,840
2,749,710,000
-

707,051,021
3,486,749,840
2,749,710,000
-

A.3 Exhaust fan in Factory


Fan
I
Upblast Roof Ventilators
Maker: New York Blower
Original: Philippin
Model: NYJBC54P
Working point: 35,856 CFM free blow
Speed of fan: 665 rpm (Belt driven
type)
Motor: 3Hp
Power: 400v / 3p / 50Hz

set

30

86,625,000

Page 74 of 80

100%

VALUE OF WORK DONE (Ending 20 June, 2012)


UNIT RATE
Description

No.

Unit

Quantity

Material rate

Wind Band made by Actec Vietnam


Steel support for fan to be hot-dip
galvanized
II

III

Actec Other's cost


(Other Temp. facilities, office,
Transportation, Site Management etc.)
Unicons's fee

B. Electrical addition
B.1 Supply fan in Factory & Warehouse
Control panel
I
Control panel (DB-SAF-P-W)
II

III

IV

set

30

lot

lot

100,262,582

319,800,000
100,262,582

%
Work
Done
to
Date

100%

319,800,000

100%

100,262,582

100%

100,262,582

316,977,258

316,977,258

100%

2,530,000

423,044,140

100%

17,186
10,303
69

108,524
13,423
52,407

9,600
4,153
9,600

2,030,075,627
181,085,528
4,278,458

100%
100%
100%

m
m
m
m
set
set
set
set
set
set
m
m
set

45
45
152
1,030
3
6
1
3
2
18
444
69
69

1,193,895
890,967
466,543
374,206
1,674,473
1,330,366
1,330,366
981,850
1,080,923
571,854
153,563
85,839
108,790

156,008
116,424
67,949
50,592
62,100
46,575
39,330
46,575
39,330
31,050
17,063
17,250
11,500

60,745,644
45,332,595
81,242,814
437,541,580
5,209,720
8,261,649
1,369,696
3,085,276
2,240,506
10,852,263
75,757,500
7,113,161
8,300,010

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

Isolator
Isolator 3P 32A-WHT35

set

69

1,108,485

57,500

80,452,965

100%

Accessories

lot

17,710,000

3,450,000

21,160,000

100%

Cable
Cable Cu/MT/XLPE/LSZH 3C x 4.0mm2
Cable Cu/PVC 1CX4.0mm( E)
Flexible cable Cu/PVC/PVC 3C x 4.0 mm2

m
m
m

Cable tray without cover & conduit


Cable tray 400x100
Cable tray 300x100
Cable tray 200x100
Cable tray 150x100
Tee cable tray 400x100/200x100mm
Tee cable tray 300x100/150x100mm
Tee cable tray 300x100
Tee cable tray 200x100/1500x100mm
Horizontal elbow Trunking 300x100mm
Horizontal elbow Trunking 150x100mm
GI conduit D32 - E31
GI flexible D32
Cable gland BG34 Inox

1,436,152,493
162,288,492

1,265,000

163,553,492

100%

108,524
13,423
52,407

9,600
4,153
9,600

606,329,465
90,217,608
1,860,199

100%
100%
100%

84
760
1
6
12
180
30
30

1,575,605
374,206
1,818,416
1,969,616
571,854
145,554
85,839
108,790

195,593
50,592
72,450
72,450
31,050
17,063
17,250
11,500

148,780,590
322,846,214
1,890,866
12,252,395
7,234,842
29,270,893
3,092,679
3,608,700

100%
100%
100%
100%
100%
100%
100%
100%

set

30

1,108,485

57,500

34,979,550

100%

lot

10,235,000
1,503,282,028

100%

m
m

872
109

1,139,087
629,222

32,898
28,800

1,021,971,269
68,585,150

100%
100%

m
m

428
107

872,007
250,675

29,637
12,000

100%
100%

set
set
set
set
set

(1)
(1)
(1)
(1)
(1)

192,575,885
192,575,885
161,309,830
161,309,830
210,410,620

Incl.
Incl.
Incl.
Incl.
Incl.

lot
lot
lot
lot

(1)
(1)
(1)
(1)

224,029,446
286,079,841
151,480,731
191,387,336

Incl.
Incl.
Incl.
Incl.

385,903,427
26,822,182
(1,940,246,685)
(918,182,050)
(192,575,885)
(192,575,885)
(161,309,830)
(161,309,830)
(210,410,620)
(1,022,064,635)
(224,029,446)
(286,079,841)
(151,480,731)
(191,387,336)

Cable
Cable Cu/MT/XLPE/LSZH 3C x 4.0mm2
Cable Cu/PVC 1CX4.0mm( E)
Flexible cable Cu/PVC/PVC 3C x 4.0 mm2

m
m
m

5,133
5,133
30

Cable tray
Cable tray 600x100
Cable tray 150x100
Vert. elbow cable tray 600x100mm
Tee cable tray 600x100/150x100mm
Horizontal elbow Trunking 150x100mm
GI conduit D32 - E31
GI flexible D32
Cable gland BG34 Inox

m
m
set
set
set
m
m
set

Isolator
Isolator3P
3P32A-WHT35
32A-WHT35

Accessories
V
B.3 Main cable from MSB to MCC of fan
From MSB to DB-SAF-P-W
I
Cable Cu/MT/XLPE/LSZH 1C-240mm2
Cable Cu/PVC 1C-240mm2
From MSB to DB-EAF-P
II
Cable Cu/MT/XLPE/LSZH 1C-185mm2
Cu/PVC 1C-95mm2
C. Eletrical deduction
C.1 Distribution boards

Isolator

8,280,000

1,955,000

C.2 Distribution Submains Cable


From MSB 3 to DB-FAF1
From MSB 3 to DB-FAF2
From MSB 3 to DB-EAF1
From MSB 3 to DB-EAF2

319,800,000

420,514,140

DB-FAF1
DB-FAF2
DB-EAF1
DB-EAF2
DB-FAF&EAF

Value of Work
Done to Date

ATELIER & UNICONS


AGREED VALUE OF
WORK DONE
%
Work
Value of Work
Done
Done to Date
to
Date
-

100%

6,426,583,653
3,487,149,132

IV

2,016,000

Contract value

UNICONS' CLAIM

set

III

Labour / overheads
/
Profits

8,644,000

set

B.2 Exhaust fan in Factory


Control panel
I
Control panel
II

AMOUNT

Page 75 of 80

100%
100%
100%
100%
100%
100%
100%
100%
100%

316,977,258
6,426,583,653
3,487,149,132
423,044,140
2,030,075,627
181,085,528
4,278,458
60,745,644
45,332,595
81,242,814
437,541,580
5,209,720
8,261,649
1,369,696
3,085,276
2,240,506
10,852,263
75,757,500
7,113,161
8,300,010
80,452,965
21,160,000
1,436,152,493
163,553,492
606,329,465
90,217,608
1,860,199
148,780,590
322,846,214
1,890,866
12,252,395
7,234,842
29,270,893
3,092,679
3,608,700
34,979,550
10,235,000
1,503,282,028
1,021,971,269
68,585,150
385,903,427
26,822,182
(1,940,246,685)
(918,182,050)
(192,575,885)
(192,575,885)
(161,309,830)
(161,309,830)
(210,410,620)
(1,022,064,635)
(224,029,446)
(286,079,841)
(151,480,731)
(191,387,336)

100%
100%

100%

100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%

100%

100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%

100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

316,977,258
6,426,583,653
3,487,149,132
423,044,140
2,030,075,627
181,085,528
4,278,458
60,745,644
45,332,595
81,242,814
437,541,580
5,209,720
8,261,649
1,369,696
3,085,276
2,240,506
10,852,263
75,757,500
7,113,161
8,300,010
80,452,965
21,160,000
1,436,152,493
163,553,492
606,329,465
90,217,608
1,860,199
148,780,590
322,846,214
1,890,866
12,252,395
7,234,842
29,270,893
3,092,679
3,608,700
34,979,550
10,235,000
1,503,282,028
1,021,971,269
68,585,150
385,903,427
26,822,182
(1,940,246,685)
(918,182,050)
(192,575,885)
(192,575,885)
(161,309,830)
(161,309,830)
(210,410,620)
(1,022,064,635)
(224,029,446)
(286,079,841)
(151,480,731)
(191,387,336)

VALUE OF WORK DONE (Ending 20 June, 2012)


UNIT RATE
No.

Description

From MSB 3 to DB-FAF&EAF

Unit

Quantity

Material rate

Labour / overheads
/
Profits

lot

(1)

169,087,281

Incl.

kg
kg
m2
nos
nos

35,329
3,757
1,556
5,024
69

27,400
35,400
96,000
27,000
55,526,099

Incl.
Incl.
Incl.
Incl.
Incl.

D. Steel structure and waterproofing for fans


Built up steel
Hot rolled steel
Paint finishing
Bolts
Penetration flashings system for fans

Page 76 of 80

AMOUNT

%
Work
Done
to
Date
(169,087,281) 100%
5,217,366,774
968,003,649 100%
132,991,924 100%
149,422,372 100%
135,648,000 100%
3,831,300,829 100%

Contract value

ATELIER & UNICONS


AGREED VALUE OF
WORK DONE
%
Work
Value of Work
Value of Work
Done
Done to Date
Done to Date
to
Date
(169,087,281) 100%
(169,087,281)
5,217,366,774
100%
5,217,366,774
968,003,649
100%
968,003,649
132,991,924
100%
132,991,924
149,422,372
100%
149,422,372
135,648,000
100%
135,648,000
3,831,300,829
100%
3,831,300,829

UNICONS' CLAIM

D COMPLETION OF TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18, VIETNAM


INH DUONG PROVINCE, VIETNAM

m only as an indication of the breakdown value for this contract works. The tenderer shall price the
m for extra or otherwise shall be considered for any trade/items/works as specified and shown in the

REM
ARK

Page 77 of 80

REM
ARK

Page 78 of 80

REM
ARK

Page 79 of 80

MAIN TENDER PACKAGE FOR PROPOSED CONSTRUCTION AND COMPLETION OF TBC-BALL BEVERAGE CAN FACTORY AT STREET NO.18,
VIETNAM SINGAPORE INDUSTRIAL PARK II-A, TAN UYEN DISTRICT, BINH DUONG PROVINCE, VIETNAMPROJECT

VARIATION WORKS
EI-57: Changing location of PDP#1003

CURRENCY: VND
Value of Work Done to Date
AMOUNT
NO

DESCRIPTION

UNICONS' CLAIM

UNIT
Contract value

% Work
Done to
Date

Value of Work
Done to Date

ATELIER & UNICONS


AGREED VALUE OF WORK
DONE
% Work
Value of Work
Done to
Done to Date
Date

PDP# 1003
1 Cable
Cu/XLPE/PVC - 240mm2/1C

91,907,086

100%

91,907,086.00

100%

91,907,086

Cu/PVC - 200mm2/1C(E)

12,238,632

100%

12,238,632.00

100%

12,238,632

Accessories

lot

5,424,522

100%

5,424,521.56

100%

5,424,522

11,739,420

100%

11,739,420.00

100%

11,739,420

2 Trunking
Cable tray 300x100

TOTAL (Not included V.A.T)

121,309,660

121,309,660

121,309,660

TOTAL CARRIED TO SUMMARY OF THIS V.O


(Include. VAT)

133,440,626

133,440,626

133,440,626

REMARK

S-ar putea să vă placă și