Documente Academic
Documente Profesional
Documente Cultură
05 10/01/2011, Gi
GUIDELINES FOR INSTALLATION OF SELF-SUPPORTING OPTICAL AERIAL CABLES (OPGW, OPPC, MASS) WITH STEEL TUBE(S)
www.AFLglobal.com
1.
This guide provides general recommendations for the selection of methods, equipment and tools for the stringing of optical aerial cables with:
2.
References
IEC/TR 61328: IEEE Std 524: Live working Guidelines for the installation of transmission line conductors and earthwires - Stringing equipment and accessory items IEEE guide to the installation of overhead transmission line conductors
3.
Safety
All safety practices of the government, the power utility and the installation contractor must be followed. These safety procedures will take precedence over any information contained in this document. For the safety requirements towards inductive and capacitive influence it is necessary that the cable is properly grounded during installation. For detailed information refer to above mentioned standards.
4.
Reels must be transported and stored in an upright position and safely secured against movements during transportation. Loading and unloading must be done using suitable cranes or forklifts. The reels must not be tipped out or thrown. When using wooden reels it must be checked if the bolt nuts have to be retightened after transportation .
www.AFLglobal.com
5.
Stringing Method
To prevent damages, the cable must be installed using the tension method. That means the cable is tensioned during stringing to keep it clear of the ground and obstacles. Cable lengths must be installed separately, that means it is not allowed to connect several delivery lengths to be strung in one step.
6.
Bending radius
The minimum permissible bending radius under load is 15 times the cable diameter. The unloaded cable is permitted to be bent with a minimum radius of 10 times the cable diameter. See technical data sheet for specific values.
7.
Sheaves
The sheaves must be in good condition. Diameter of sheaves (bottom of groove): Initial and terminal points of the line (deflection angle 120) At tension towers At suspension towers
800 mm
600 mm 450 mm
In any case the minimum bending radius of the cable must not be exceeded. Generally it is recommended that the sheave diameters should be as big as possible to limit the load for the cable. For cables with ACS wires in the outer layer it is absolutely necessary to have metallic sheaves with neoprene coated grooves or sheaves with grooves made of plastic (e.g. PA) at initial and terminal points and at angle points of the line. In case of only AA or Al wires in the outer layer the sheaves can be coated or blank. (Note the earthing requirements). In any case it must be ensured that the sheave grooves do not damage the cable's armour. Grooves have to be adapted to cable diameter and must not be smaller than 0.55 times the cable diameter. Groove profile and radius should be wide enough to allow passage of swivels and wire mesh grips. If an old conductor is used as pulling rope the size of rope joints must also be taken into consideration. For that reason the sides of the grooves should open in an angle between 15 and 20. The sheaves must be in good working order and properly lubricated. Sheaves should preferably be provided with high quality roller or ball bearings to minimise the rolling and frictional resistance.
www.AFLglobal.com
8.
Cable Pay-Off
Cable pay-off can be a reel stand or a movable reel carrier. In any case it must be equipped with a suitable brake to prevent the reel from carry on turning when the stringing stops. This would cause the cable layers slackening on the drum. The pay-off should be positioned not less than 5m behind the tensioner. It is strictly prohibited to do tension stringing directly from the reel without using a tensioner!
9.
Tensioner (brake)
The bullwheel sheave diameter has to be more than 70 times the cable diameter or 1200 mm whatever is smaller. The wheels must be in such condition that they do not have any burrs or cavities which may damage the cable. The running-grooves must be adapted in size to the cable diameter. At best they are coated with neoprene or similar material. The tensioner must be able to assure constant tension and allow a steady slow down at different stringing speed without the effect of cable run after. Tensioning should be readily controllable and capable of maintaining constant and even operation. There should be a minimum of 6 turns to anchor the cable. To prevent from birdcaging the correct orientation for entry and exit of the cable must be respected. For right hand lay (Z), the cable must enter the brake on the left and exit on the right (see figure 4). For left hand lay (S), the cable must enter on the right and exit on the left.
Figure 4:
www.AFLglobal.com
10. Puller
The puller should preferably a bullwheel puller with integrated or separate reel winder. The speed must be infinitely variable and allow a smoothly pull of the cable without jerking or bouncing. The puller must be equipped with a tension control system and an adjustable tension dependant switch off. The stringing tension has to be recorded during the whole installation. Before stringing, the puller has to be checked according to accuracy of tension measurement.
The pulling rope should be attached to the cable by a swivel link with the help of a of wire mesh grip (see figure 6). The installation equipment i.e. the puller and tensioner should be placed in line with the two first towers (within app. 10). The sheaves at the running-in point and at the exit point of the line should be arranged in such a way that bird-caging of the cable is prevented. If there are signs of bird-caging the stringing has to be interrupted and the stringing arrangement must be corrected. At the start of stringing the puller should be slowly speeded up with about 5m/min and in case of properly run the speed can be increased to maximum speed of 60m/min. The actual installation speed is of course dependent upon the line configuration. During stringing special attention must be paid to the swivel and wire mesh grip running through the sheaves and lattice towers. Special attention must be paid during insertion of the cable into the lattice tower for joint box installation, to prevent damage or bird-caging.
www.AFLglobal.com
For cable jointing a certain excess length of tubes and fibres is necessary which will be placed in the joint box. For this purpose a cable surplus of approximately 5 m is required. Sagging procedure is the same as for ordinary conductor ropes.
Important notes:
Anti-torque devices: As cables with only one armouring layer tend to rotate, the use of suitable anti-torque devices (pendulum weights) is mandatory. They should be directly placed onto the cable. In case of a central steel tube cable it can be installed without anti-torque device if the line configuration allows for a limitation of the stringing tension to a maximum of 10% of the rated tensile strength. This does not apply for cables with steel-aluminium tube! Come Along Clamps: If for sagging or installation of the accessories come along clamps shall be used, please note that common self-gripping clamps are strictly prohibited for any cable listed in chapter 1. Self gripping clamps which are properly adapted to the cable diameter or suitable preformed fittings shall be used as come along clamps for stranded steel tube and central steel-aluminium tube designs. Only suitable preformed fittings are allowed as come along clamps for central steel tube cables.
www.AFLglobal.com
www.AFLglobal.com