Documente Academic
Documente Profesional
Documente Cultură
Customer
Ship
Selling Entity
Ship
Warehouse
Factory
Ship
Produce to forecast
Supplier
Ship
Produce to forecast Produce to order with lead time
Lean Enterprise
SUPPLIER FACTORY WAREHOUSE
SELLING ENTITY
Distributor
CUSTOMER
RATE-BASED PLANNING
Procurement
Reduced material costs due to elimination of short-term fluctuations Reduces impact of long lead time items
Manufacturing
Plant efficiencies Reduces lost output due to last minute schedule changes
Logistics
Cost of expedited transportation/deployment
Issues to be Addressed
How to level schedules in the face of variation in product demand How to balance demand variation with production, supply, and transportation resources. How to communicate production requirements to all key suppliers and transportation providers so that all parties operate assets efficiently.
Dealer Network #2 Green 15.63 Yellow 5.99 Red 9.85 Distributor #3 Green Yellow Red
Standard Deviation
Standard Deviation (): a measure of the magnitude of variation around an average value. Xi = individual measurements of a population of measurements (e.g., weekly demand data). X = average value for a population of measurements. standard = deviation
n
X 5 4 6 3 4 22
22 X = 5 = 4.4
i =1
i - X) (X n
standard = deviation =
(5-4.4)2 + (4-4.4)2 + (6-4.4)2 + (3-4.4)2 + (4-4.4)2 5 0.36 + 0.16 + 2.56 + 1.96 + 0.16 5
1.04
= 1.02
3.11 6.31
5.98 28.42
11.96 56.85
17.95 85.27
NOTE: Average Green Model = Dist. #1 + Dealer Network #2 + Dist. #3 = 20.52 + 15.63 + 15.84 = 51.99 STD Deviation Green Model * Complete the above table for the red model. = (Std Dev #1)2 + (Std Dev #2)2 + (Std Dev #3)2 = (1.94) 2 + (1.62) 2 + (1.82) 2 = 3.11
Demand Variation
We will use this information to: Construct planning bills of materials. Support demand funneling strategies. Support safety stock strategies.
Example Implications
The range of variation in demand for each of 100 individual items might be 50%, while the range of variation for the aggregate demand might be 5%. The former would determine inventory requirements in a make to stock environment. The later would determine inventory requirements in a configure to order environment. Variation of demand common components, as a percentage of the average demand, much smaller than the variation for individual end items. The demand for an item at one warehouse location has a standard deviation of 3. At a second warehouse the same item has a standard deviation 5of 4. If the 3 4 demand for the two warehouse were combined the standard deviation would be . Thus in the first case the safety stock required for three standard deviation protection would be 3*3+3*4= 21. In the second case the required safety stock is reduced to 3*5=15. The demand for end items varies 100%. Thus in a make to inventory environment a high level of safety stock is required. The aggregate demand may vary only 10%, indicative of the amount of flex capacity needed in a make to order environment.
2 2
CTO
End Items
Modules
Planning Level
Components Components
PRODUCT TYPES
PRODUCT TYPE Build-to-Stock (BTS) Build-to-Order (BTO) DEFINITION Built prior to demand with a standard bill of material. EXAMPLE Diet Coke
Built to demand Executive Jet requirements with standard Bill of Material. Built to demand with standard modules or components. Higher product variation than BTO. Built from drawings. Unique end products. Desk-top Computer
Configure-to-Order (CTO)
MPS
New Orders
vs.
CTO Specials
ETO
Wk3
Wk1
Wk2
Wk3
Wk4
CTO
Specials Ds
Demand
At-Once Order < lead-time
BTO ETO
BTS
BTO/ CTO
ETO/ BTO
CTO
Infinite Flexibility
Market
Product Response Profile
| 0 | 1 | 2 | 3 | 4 . . . . wks
Plant
| | | | | 0 1 2 3 4 . . . . wks | 0 | 1 | 2 | 3 | 4
Supplier
| 0 | 1 | 2 | 3 | 4
?
| 5
RAMP UP....
Time
Delivery Wheel
Demand Wheel
7 Day 3 Day
1 Day
Vol Lemon Lime
Reeve, 2002
I-B Wings
Conventional
Specific Tail Number I-C
S M R
Schedule
Materials Release
Metal Bond
M R P
M R P
M R P
M R P
I-C I-C I-D
M R P
I-E
I-E I-F I-E I-F
MR
I-E I-F I-E I-F
I-D
Parts committed to 48-Wk tail numbers I-D Missing! months before use Schedule I-E
S
M R P
I-G
M R P
Parts HPM
I-F ASEA
Salt Treat
Ocean
Stretch Form
Composites
M R P
48-Week Cycle
I-H
Takt
Nose Middle
LEAN
Tail
Final Assembly
Schedule
Wings
Press Area
HPM ASEA
Thru - Kanban
Salt Treat
Stretch Form