Documente Academic
Documente Profesional
Documente Cultură
Purpose / Remarks
To set max system current To set min system current System voltage at 20C Rectifiers set voltage Total battery charge current limit Temp. correction coefficient
Boost charge voltage Starting battery current value Stopage battery current value Support voltage for rectifier during batt. test. Test duration. Automatic battery test interval Min. battery test duration Start time for automatic batt. Test Months no automatic start is possibe Sets voltage for equalizing Duration of equalizing Interval b/n the starts of equalizing BLVD disconnection BLVD re-connection High Temp. alarm Low Temp. alarm LLVD disconnection LLVD re-connection Site Name
Boost charge voltage Starting battery current value Stopage battery current value Support voltage for rectifier during batt. test. Test duration. Automatic battery test interval Min. battery test duration Sets voltage for equalizing Duration of equalizing Interval b/n the starts of equalizing High Temp. alarm Low Temp. alarm LLVD disconnection LLVD re-connection Site Name
48 15 90 0.0 3:00 None 54.5 60.0 30.0 43.0 50.0 30.0 10.0 45.0 50.0
CONFIGURATION OF PSC BOARD contNB: Engineers should ensure that Utrip3-low and Utrip3-Ok are always configured correctly since the low voltage dis-connect relay is activated and will switch off the Battery to prevent deep dicharge of the battery or will switch off non-essential loads in the low priority section of the distribution busbar. It reconnect the loads into the system if the voltage rises above Utrip3-ok limit. It should also be noted that the "Auxiliary" settings on the PSC board are used to set parameters for special functions e.g. disconnecting of battery or load due to low system voltage.
Alarm Stop Mains Failure-Site on Batteries Service not Automatic-Often ON when the battery is charging In Operation
EXIT
ENTER
The code required by the PSC board to enable access to its configurable menus is: 1. Press the UP arrow twice 2. Down arrow once and 3. Exite twice
PSC 1000
COBOMO-CARD
HOW THE ALARMS ARE DEFINED ALARM INLET 0/8: Usage: External Alarm
Type: Breaking
1 2 3 4 5 6 1 2 3 4 5 6
Usage: External Alarm ID: 7 or Dependend on the available alarm inlet Type: Breaking Comment : A2 POWER ALARM (NUA)
Alarm cables
2. All transmission circuits should be connected at High Priority side (the breakers on the right side of the Partial load disconnect relay "K12") in the ASCOM DC power supply as shown in the cabinet below.
Low Priority Load High Priority Loads DC Power Supply Cable
3. Engineers and Technicians should ensure that Loads are not protected by breakers and fuses with rating less than the full load current 4. The rectifier allocation should be such that each cabinet will demand one rectifier. So for a site which has one 900 RBS, Two 1800 RBS and One transmission cabinet should have Five rectifiers, such that: 3 rectifiers for the RBS loads + 1 rectifier for transmission + 1 extra rectifier to charge the Batteries = 5 rectifiers
25A
6A
6A
6A
6A
25A
2 K1 t ia ar (P
System Shunt
ec nn co t)
d oa lL dis
KEY
Direction of Current flow through the Busbar Used for labelling
LOAD BALANCING, PRECISE PROTECTION AND CIRCUIT CONNECTION contNB: In the event of mains failure, the loads at the site will be supported by the battery bank connected to the ASCOM DC power plant. The function of the Partial load disconnection relay is to switch off the less essential loads when the battery voltage falls below Utrip3-low value. When AC power is not restored and the batteries continuous to discharge, the voltage will drop below
Utrip1-low. This in turn will activated the Low Voltage Disconnect relay (K11) which will switch off all loads connected to the
ASCOM-thus preventIing deep battery dicharge.
th
8.8.8.8
SET
OUT
DC Power Supply
HIGH ROOM TEMPERATURE ALARM contThe following should be taken note of:
a) AL: is High Limit Alarm and should be set at "30oC" b) SC: Is the measurement deviation. It modifiers the measured value either by increasing or decreasing it by a specific amount.It should be set at "0" since we want to display the actual room temperature without any increament or decreament. c) P: Is the proportion Area and should be set to "0". This setting will put the meter in ON/OFF mode and will prevent it from intermittent switching between ON and OFF. It will be OFF only when alarm limit is exceeded and ON when the room temperature is below the set limit. d) I: Is the calculus time and it is used to adjust the static difference. It has a range between 0 and 999. when its too high the static difference will be unstable. It should be set at "240". e) d: Is the differential time and should be set at "30". f) t: Control period which controls the output of the control relay. Should be set at "2". g) HY: Main control by drop in level and should be set at "1.0". h) At: Parameter setting itself. It has two state ON/OFF and should be set "OFF" since Engineers and technician will be required to do the settings. i) Loc: Is Electronic lock and should be set at "0"
HOME
10
Limitation Or Problems with the existing System The Major limitation of the existing cabinets are that: a) The batteries are driven into deep discharge when the mains and generator fails. The reasons are that, the fan unit on the door of the second BBS cabinet is connected directly across the batteries in that cabinet . As such it is not controlled by the BFU which could have switch of the supply to it when the voltage falls too low ( Below 24v DC) The fan hence continue to run until the voltage is very low to the extent that it can not drive it any more ( i.e. the batteries had been driven into deep discharge). In this battery state, the relay in the BFU fails to connect the batteries to be charged by the PSUs when mains or generator power is restored. In effect the site will continue to go down when ever mains and generator power fails until the condition is corrected by charging the batteries externally. b) The effects does not end there but continuous to shorten the life span of the batteries since a batteries life span is dependent on the complete chargedischarge it undergoes. Hence half discharge and charging would double the life span.
I.
Suggested solutions One solution is to assigned one PSU in the RBS cabinet to the fan in the second BBS cabinet- In that it will stop running when the mains and generator power fails
II.
Another proposed solution is to Bring one battery bank from the second BBS cabinet into the first BBS cabinet and do away with the third cabinet. The disadvantage of this solution will be that, it will permit only one transmission unit in that cabinet.
III. The third proposed solution will be to rely on Ericsson to supply only two cabinets, one RBS cabinet and an extended BBS cabinet capable of housing three battery banks and a number of Transmission indoor units.
11