Sunteți pe pagina 1din 57

Project Management: A Managerial Approach 4/e

By Jack R. Meredith and Samuel J. Mantel, Jr.


Published by John Wiley & Sons, Inc.
Presentation prepared by RTBM WebGroup

Project Management
A Managerial Approach

Chapter 9

Resource Allocation

Critical Path Method Crashing a Project


CPM includes a way of relating the project schedule to the level of physical resources allocated to the project This allows the project manager to trade time for cost, or vice versa In CPM, two activity times and two costs are specified, if appropriate for each activity
Chapter 9-1

Critical Path Method Crashing a Project


The first time/cost combination is called normal, and the second set is referred to as crash Normal times are normal in the same sense as the m time estimate of the three times used in PERT Crash times result from an attempt to expedite the activity by the application of additional resources
Chapter 9-2

Critical Path Method Crashing a Project


Careful planning is critical when attempting to expedite (crash) a project Expediting tends to create problems; and the solution to one problem often creates several more problems that require solutions Some organizations have more than one level of crashing
Chapter 9-3

Fast-Tracking
Another way to expedite a project is known as fast-tracking
It refers to overlapping the design and build phases of a project Because design is usually completed before construction starts, overlapping the two activities will result in shortening the project duration
Chapter 9-4

The Resource Allocation Problem


A shortcoming of most scheduling procedures is that they do not address the issues of resource utilization and availability Scheduling procedures tend to focus on time rather than physical resources Time itself is always a critical resource in project management, one that is unique because it can neither be inventoried nor renewed
Chapter 9-5

The Resource Allocation Problem


Schedules should be evaluated not merely in terms of meeting project milestones, but also in terms of the timing and use of scarce resources A fundamental measure of the project managers success in project management is the skill with which the trade-offs among performance, time, and cost are managed
Chapter 9-6

The Resource Allocation Problem


The extreme points of the relationship between time use and resource use are these:
Time Limited: The project must be finished by a certain time, using as few resources as possible. But it is time, not resource usage, that is critical Resource Limited:The project must be finished as soon as possible, but without exceeding some specific level of resource usage or some general resource constraint
Chapter 9-7

The Resource Allocation Problem


If all three variables - time, cost, specifications - are fixed, the system is overdetermined In this case, the project manager has lost all flexibility to perform the trade-offs that are so necessary to the successful completion of projects A system-constrained task requires a fixed amount of time and known quantities of resources
Chapter 9-8

Resource Loading
Resource loading describes the amounts of individual resources an existing schedule requires during specific time periods The loads (requirements) of each resource type are listed as a function of time period Resource loading gives a general understanding of the demands a project or set of projects will make on a firms resources

Chapter 9-9

Resource Loading
An excellent guide for early, rough project planning Because the project action plan is the source of information on activity precedences, durations, and resources requirements, it is the primary input for both the project schedule and its budget The action plan links the schedule directly to specific demands for resources
Chapter 9-10

Resource Loading
The PERT/CPM network technique can be modified to generate time-phased resource requirements The project manager must be aware of the ebbs and flows of usage for each input resource throughout the life of the project It is the project managers responsibility to ensure that the required resources, in the required amounts, are available when and where they are needed
Chapter 9-11

Resource Leveling
Resource leveling aims to minimize the periodby-period variations in resource loading by

shifting tasks within their slack allowances

The purpose is to create a smoother distribution of resource usage Several advantages include:
Less hands-on management is required May be able to use a just-in-time inventory policy

Chapter 9-12

Resource Leveling
When resources are leveled, the associated costs also tend to be leveled The project manager must be aware of the cash flows associated with the project and of the means of shifting them in ways that are useful to the parent firm Resource leveling is a procedure that can be used for almost all projects, whether or not resources are constrained
Chapter 9-13

Constrained Resource Scheduling


There are two fundamental approaches to constrained allocation problems: Heuristic Methods Optimization Models Heuristic approaches employ rules of thumb that have been found to work reasonably well in similar situations Optimization approaches seek the best solutions but are far more limited in their ability to handle complex situations and large problems
Chapter 9-14

Heuristic Methods
Heuristic approaches to constrained resource scheduling problems are in wide, general use for a number of reasons:
1. They are the only feasible methods of attacking the large, nonlinear, complex problems that tend to occur in the real world of project management 2. While the schedules that heuristics generate may not be optimal, they are usually quite good- certainly good enough for most purposes

Chapter 9-15

Heuristic Methods
Most heuristic solution methods start with the PERT/CPM schedule and analyze resource usage period by period, resource by resource In a period when the available supply of a resource is exceeded, the heuristic examines the tasks in that period and allocates the scarce resource to them sequentially, according to some priority rule Technological necessities always take precedence
Chapter 9-16

Heuristic Methods
Common priority rules:
As soon as possible As late as possible Shortest task first Most resources first Minimum slack first Most critical followers Most successors Arbitrary
Chapter 9-17

Heuristic Methods
Most priority rules are simple adaptations of the heuristics used for the traditional job shop scheduling problem of production/operations management Most heuristics use a combination of rules: a primary rule, and a secondary rule to break ties As the scheduling heuristic operates, one of two events will result:
The routine runs out of activities before it runs out of resources The routine runs out of resources before all activities have been scheduled

Chapter 9-18

Optimizing Methods
The methods to find an optimal solution to the constrained resource scheduling problem fall into two categories:
Mathematical programming Enumeration

Mathematical programming can be thought of as liner programming (LP) for the most part
Chapter 9-19

Optimizing Methods
Linear programming is usually not feasible for reasonably large projects where there may be a dozen resources and thousands of activities In the late 1960s and early 1970s, limited enumeration techniques were applied to the constrained resource problem Tree search, and branch and bound methods were devised to handle up to five resources and 200 activities
Chapter 9-20

Multiproject Scheduling and Resource Allocation


The most common approach to scheduling and allocating resources to multiple projects is to treat the several projects as if they were each elements of a single large project Another way of attacking the problem is to consider all projects as completely independent To describe such a system properly, standards are needed by which to measure scheduling effectiveness
Chapter 9-21

Multiproject Scheduling and Resource Allocation


Three important parameters affected by project scheduling are:
Schedule slippage

Resource utilization
In-process inventory

The organization (or the project manager) must select the criterion most appropriate for its situation
Chapter 9-22

Multiproject Scheduling and Resource Allocation


Schedule slippage, often considered the most important of the criteria, is the time past a projects due date or delivery date when the project is completed Resource utilization is of particular concern to industrial firms because of the high cost of making resources available The amount of in-process inventory concerns the amount of work waiting to be processed because there is a shortage of some resource
Chapter 9-23

Multiproject Scheduling and Resource Allocation


All criteria cannot be optimized at the same time
As usual, the project manager will have to make trade-offs among the criteria A firm must decide which criterion to evaluate its various scheduling and resource allocation options
Chapter 9-24

Mathematical Programming
Mathematical programming can be used to obtain solutions to certain types of multiproject scheduling problems These procedures determine when an activity should be scheduled, given resource constraints Mathematical programming, however, is rarely used in project management to handle the multiproject problem (mostly, heuristics are used)
Chapter 9-25

Mathematical Programming
The three most common objectives of mathematical programming are:
1. Minimum total throughput time (time in the shop) for all projects 2. Minimum total completion time for all projects 3. Minimum total lateness or lateness penalty for all projects

These objectives are most appropriate for job shop type solutions to resource constraints

Chapter 9-26

Heuristic Techniques
There are scores of different heuristic-based procedures in existence They represent rather simple extensions of well-known approaches to job-shop scheduling:
Resource Scheduling Method Minimum late finish time Greatest resource demand Greatest resource utilization Most possible jobs
Chapter 9-27

Summary
The critical path method (CPM) is a network constructed in the same manner as PERT but considers the possibility of adding resources to tasks to shorten their duration The resource allocation problem is concerned with determining the best trade-offs between available resources, including time, throughout the duration of the project

Chapter 9-28

Summary
Resource loading is the process of calculating the total load from project tasks on each resource for each time period of the projects duration Resource leveling is concerned with evening out the demand for various resources required in a project by shifting tasks within their slack allowances

Chapter 9-29

Summary
There are two basic approaches to addressing the constrained resources allocation problem:
Heuristic methods Optimizing methods

For multiproject scheduling, three important measures of effectiveness are schedule slippage, resource utilization, and level of inprocess inventory

Chapter 9-30

Summary
When a new project is added to a multiproject system, the amount of slippage is directly related to the average resource load Mathematical programming models for multiproject scheduling aim to either minimize total throughput time for all projects, minimize the completion time for all projects, or minimize total lateness for all projects

Chapter 9-31

Resource Allocation

Questions?

Chapter 9-32

Resource Allocation

Picture Files

Resource Allocation

Figure 9-1

Resource Allocation

Figure 9-2

Resource Allocation

Figure 9-3

Resource Allocation

Figure 9-4

Resource Allocation

Figure 9-5

Resource Allocation

Figure 9-6

Resource Allocation

Figure 9-7

Resource Allocation

Figure 9-8

Resource Allocation

Figure 9-9a

Resource Allocation

Figure 9-9b

Resource Allocation

Figure 9-10

Resource Allocation

Figure 9-11

Resource Allocation

Figure 9-12

Resource Allocation

Figure 9-13

Resource Allocation

Figure 9-14

Resource Allocation

Figure 9-15

Resource Allocation

Figure 9-16

Resource Allocation

Table Files

Resource Allocation

Resource Allocation

Resource Allocation

Copyright 2000 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in Section 117 of the 1976 United States Copyright Act without the express written permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein.

S-ar putea să vă placă și