Documente Academic
Documente Profesional
Documente Cultură
Project Classifications
Replacement
Expansion
Safety/Environmental Projects
associated with a project. Evaluate the risk of the project. Evaluate the cash flows by applying one or more of the capital budgeting techniques.
Example
Year Project S Project L 0 -1000 -1000 1 600 400 2 300 400 3 300 500 4 200 400
Assumptions
Equally Risky They have same cost They have same life
Payback Period
Expected number of years required to recover the original investment
Decision Rules: PP = payback period MDPP = maximum desired payback period Independent Projects: PP MDPP - Accept PP > MDPP - Reject Mutually Exclusive Projects: Select the project with the fastest payback, assuming PP MDPP.
Payback Period
How long will it take for the project to generate enough cash to pay for itself? (500) 150 150 150 150 150 150 150 150
Payback Period
How long will it take for the project to generate enough cash to pay for itself? (500) 150 150 150 150 150 150 150 150
Payback Period
Is a 3.33 year payback period good? Is it acceptable? Firms that use this method will compare the payback calculation to some standard set by the firm. If our senior management had set a cut-off of 5 years for projects like ours, what would be our decision?
This project is clearly unprofitable, but we would accept it based on a 4-year payback criterion!
Improves over regular payback period method by taking into account the time value of money. Still ignores all cash flows received after the payback period
Drawbacks
Discounted
Year
0 1
Discounted Payback
(500) 0 250 1 250 2 250 3 250 250 4 5
Discounted
Year
0 1
Cash Flow
-500 250
CF (14%)
-500.00 219.30 280.70
1 year
Discounted Payback
(500) 0 250 1 250 2 250 3 250 250 4 5
Year 0 1 2
Discounted Payback
(500) 0 Year 0 1 2 250 1 Cash Flow -500 250 250 250 2 250 3 250 250 4 5
1 year
2 years
Discounted Payback
(500) 250 250 250 250 250 4 5
0
Year 0 1 2 3
Discounted CF (14%) -500.00 219.30 1 year 280.70 192.38 2 years 88.32 168.75
Discounted Payback
(500) 0 Year 0 1 2 3 250 1 250 2 250 3 250 250 4 5
Discounted CF (14%) -500.00 219.30 1 year 280.70 192.38 2 years 88.32 168.75 .52 years
Discounted Payback
(500) 0 250 1 250 2 250 250 250 3 4 5 Discounted
Year
0 1 2 3
Problem
Expected Net Cash Flow Year 0 1 2 3 Project L (100) 10 60 80 Project S (100) 70 50 20
Payback
Project L
0 CFt -100 Cumulative -100 PaybackL = 2 + 1 10 -90 30/80 2
2.4
3 80 50
60 100 -30 0
= 2.375 years
Payback
Project S
0 CFt -100 1
1.6 2
3 20 40
70 100 50 -30 0 20
Discounted Payback
Project L
0 CFt PVCFt -100 -100 10% 1 10 9.09 -90.91 2 60 49.59 -41.32 3 80 60.11 18.79
Discounted Payback
Project S
0 CFt PVCFt -100 -100 10% 1 70 63.64 -36.36 2 50 41.32 4.96 3 20 15.02 19.98
NPV
t 1
1 k
CFt
CF0 .
Notice that NPV of the project depends on the projects cost of capital There is a cost of capital for which the NPV is zero (and negative if cost is higher)
NPV= PV inflows Cost = Net gain in wealth. For independent projects, accept project if NPV > 0. For mutually exclusive projects, choose the one with the highest NPV are selected. This adds the most value to the firm.
Problem
Expected Net Cash Flow Year 0 1 2 3 Project L (100) 10 60 80 Project S (100) 70 50 20
Problem
Suppose we are considering a capital investment that costs Rs. 276,400 and provides annual net cash flows of Rs. 83,000 for four years and $116,000 at the end of the fifth year. The firms required rate of return is 15%.
2 3 NPV = 18,235.71
NPV =
IRR:
S
t=1
t=1 n
CFt (1 + k) t
- IO
CFt t (1 + IRR)
= IO
IRR (Continued)
1. Guess a rate. n 2. Calculate:
CFt t ( 1 IRR ) t 1
3. If the calculation = CF0 you guessed right If the calculation > CF0 try a higher rate If the calculation < CF0 try a lower rate L+ PVBL - I PVBL - PVBU * (U L)
Accurate IRR =
At i= 10% PV = 1818.2+2479.3+3005.2+3415.1 = 10717.8 At i= 15% PV= 1739.1+2268.4+2630.1+2858.8 = 9496.4 Using interpolationIRR = 10 + 10717.8- 10000 x (15-10) = 12.94% 10717.8 9496.4
Calculating IRR
IRR = 17.63%
Decision Rule:
If IRR is greater than the cost of capital (also called the hurdle rate) accept the project. IRR is independent of cost of capital(k)
Mutually Exclusive Projects Accept the project with the highest IRR, assuming IRR > k.
Problem
Expected Net Cash Flow Year 0 1 2 3 Project L (100) 10 60 80 Project S (100) 70 50 20
Project L
0 1 10 2 60 3 80
IRR = ?
Enter CFs in CFLO, then press IRR: IRR = 18.13% L IRRL = 18.13%.
Project S
IRR = ?
1 70
2 50
3 20
Enter CFs in CFLO, then press IRR: IRRL = 23.56% IRRS = 23.56%.
Problem
Expected Net Cash Flow Year 0 1 2 3 Project L (100) 10 60 80 Project S (100) 70 50 20
30
S
20 10 0 0 -10 5 10 15 20 23.6
20
S L
NPV L 50 33 19 7 (4)
NPV S 40 29 20 12 5
IRR S = 23.6%
NPV and IRR will always result in the same accept/reject decision
P Rs(10000) Q Rs(50000)
20000
75000
P Rs(10000) Q Rs(50000)
20000
75000
100
50
7857
16964
Both are acceptable, but Q contributes more to the wealth IRR unsuitable for ranking projects of different scales
Drawbacks of IRR
+ +) 2. If there are multiple sign changes in the cash flow stream, we could get multiple IRRs. + + - + +)
(500) 0
200 1
100 2
(200) 3
400 4
300 5
Multiple IRRs
0 -800
k = 10%
1 5,000
2 -5,000
Multiple IRRs
NPV Profile
IRR2 = 400% 450 0 100 IRR1 = 25% 400 k
NPV
-800
Multiple IRRs
0 -800
k = 10%
1 5,000
2 -5,000
Logic of Multiple IRRs At very low discount rates, the PV of CF2 is large & negative, so NPV < 0. At very high discount rates, the PV of both CF1 and CF2 are low, so CF0 dominates and again NPV < 0. In between, the discount rate hits CF2 harder than CF1, so NPV > 0. Result: 2 IRRs.
A B
A company is considering the purchase of a delivery van and is evaluating the following two choices: (a) The company can buy a used van for Rs 20,000, after 4 years sell the same for Rs 2,500 and replace it with another used van which is expected to cost Rs 30,000 and last 6 years with no terminating value. (b) The company can buy a new van for Rs 40,000. the projected life of the van is 10 years and has an expected salvage value of Rs 5,000 at the end of ten years. The services provided by the vans under both choices are the same. Assuming the cost of capital 10 percent, which choice is preferable?