Documente Academic
Documente Profesional
Documente Cultură
Authored by
Satyesh A. S. Kakodkar
Presentation Outline
Introduction Literature Methodology & Case Study Results Conclusions
Introduction
History of roads
Roman roads
French roads
British roads
types of pavements
Total road length National Highways State Highways Major District Roads District Roads & Rural Roads
Cross-section of Road
Char aggregate
Providing drainage
Scope of Work
Proportioning of aggregates for WMM Job mix for BM and AC Execution of Ambeudok road work stretching from
Saibaba junction - Fomento Mine + 2 branches
Designing of speed breaker and its execution Provision of road signs and roadmarkings
project overview
Work executed in two parts 50-50% and 80-20% combinations (i.e. char-conventional %) were used Providing speed breakers with 100% char waste Conclusions were made based on the facts road stretch
Site
Overview
Literature
Disadvantages of traditional old roads
1.Highly Uneconomical method of construction 2. Excessively thick around 75 to 120cm 3.Requires large quantity of natural resources which is not feasible in present time
Granular sub-base
Used in low cost roads experiencing minimum traffic and rainfall
Base course
Bituminous macadam
3.1% for 80-100mm thick layer = 3.5% for 50-75mm thick layer
= Contd.
63 mm downsize aggregates
Bitumen content
Bitumen content =
4.0% for 80 - 100mm thick layer = 4.5% for 50 - 75mm thick layer
=
Contd.
4.5% for 35 - 40mm thick layer = 5.0% for 25 - 30mm thick layer
=
Contd.
Bituminous concrete
Surface course
Surface dressing To be sprayed on previously prepared base followed by a layer of compacted stone chips
Open - graded premix surfacing Consists of 20mm compacted thickness comprising of small aggregates laid on previously prepared base
Close - graded premix surfacing Consists of 20mm compacted thickness comprising of graded aggregates laid on previously prepared base Seal coat Imparts water proofing and is to be sprayed over AC Mastic asphalt Thickness = 25 50mm Bitumen = 14-17% by weight of total graded mixture
Classification of tests
Physical properties
Crushing - strength Abrasion - hardness Impact - toughness Soundness - durability Shape - grading Specific gravity - density Water absorption - affinity to water Bitumen adhesion - capacity to bind with bitumen
Chemical properties
Sulphates Chlorides Iron Calcium oxide Silicon oxide Aluminum oxide Magnesium dioxide Manganese oxide Insoluble residue in acid Insoluble residue in base
Tests Conducted
Test conducted are conformed by :
Scope of work
a. Pre-construction stage C. Post-construction stage
Survey of site Clearing site Excavation and widening Drainage provision Stacking of material Repairing work
b. During construction stage Laying of WMM Appling of tack coat Laying of BM and AC Provision of seal coat
Laying of speed breaker Extraction of core sample Signages Road markings Inspection and handling over site
D. Test conducted Analyses of core sample Bitumen extraction
RESULTS
of the tests conducted
b)
c)
Properties of aggregates
Physical Properties
Coarse aggregates ( Table 18 )
Fine aggregates Char
Chemical properties
Coarse aggregates Fine aggregates Char ( Table 19)
Proportioning of aggregates Proportioning of aggregates for WMM ( Table 5 and 6 ) Job mix for BM1 ( Table 9 ) Job mix for BM2 ( Table 9 ) Job mix for AC ( Table 11 )
5, 6
conclus ons
General conclusions 1. Properties (char waste) at par with natural aggregates corresponding to their size or still better
2. Char waste free from silt, deleterious material , free from chlorides & sulphates
3. These waste have uniform size passing through 12mm & retained on 600 micron constituting 93% retained above 4.75mm 4. Are strong, tough, durable & conforming to specification laid down in MoRTH
Specific conclusions
1.when stack for longer period & exposed to atmosphere turn brownies in colour
2.Around 50-60% of char waste is in range of 6-4.75mm , ensures locking of aggregates in WMM leading to better CBR value. avoiding usage of any filler material like lime and cement 3.Char waste by 50% of total volume of fine aggregate used in WMM did not pose any construction / locking problem during execution. 4.On vibro-compaction also there was no segregation of char waste when blended with natural aggregate.
5. Did not pose any problem when blended with bitumen in binding. However initial popping sound when temperature in hot mixed plant rises to 60 0c when blended with natural aggregate. 6.No popping sound was observed when use 100% as replacement to conventional aggregates in AC in the mixing plant.
7. Better result (Marshall stability, flow value, compaction) were observed between 110-1200C as compared incase of conventional aggregate maintained at 1600C. 8.At higher compaction and temperature while laying Char waste have shown development of cracks in the pavement and however there are discrepancy as time elapses.
9.AC when laid with low temperature(110-1200C ) and compaction did not show neither cracks nor segregation. These facts were also witnessed in analysis of moulds used for Marshall stability after extraction as courses.
10. No cracks were observed even when subjected to 1/3rd of total monsoon(4 months).
Recommendations
Since naturally occurring aggregates are scarce compared to the present and future demand, Char waste can be used as better substitute. Its an eco friendly.
Looking at the grading of the Char waste, it can be comfortably adopted for WMM, BM and AC.
Since Char is used handled at lower temperature compared to conventional
Thank you