12. Work Permit Plan with Registration of Salalah Free Zone Office
14. Counter Measure Plan against EID holiday, RAMADAM period &
MONSON season, etc.
1. TPMS application
PROJECT
MANAGER
M.SULEMAN
SR.ENG
SIHABUDIN
M&E( H.O.)
ELE. PLUMBING
FOREMAN FOREMAN
C.HAND C.HAND
SHASHI SOMAN
JOSEJONE KANJI
SKILLED/ SITE
ELE.
PLUMBERS UNSKILLED FOREMAN
WORKERS
WORKERS SHANKAR
TINSMITHS INSULATOR
WELDERS FITTERS
Construction Execution Plan
(Salalah Methanol Project)
Detailed Construction Schedule with S-Curve
03
Construction Execution Plan
(Salalah Methanol Project)
Construction Execution Plan
(Salalah Methanol Project)
Construction Execution Plan
(Salalah Methanol Project)
3. Work Shop
Work shop will be setup beside the lay down area
Construction Execution Plan
(Salalah Methanol Project)
Manpower Mobilization Plan
05
1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Sr.Engineer ( M & E ) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Electrical Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Plumbing Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Planning Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Project Engineer 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
7 QA/QC Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
8 Quantity Surveyor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
9 HSE Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
10 Electrical Supervisor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
11 Plumbing Supervisor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
12 Civil Supervisor 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
13 Draughtsman 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
14 Lab Technician 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
15 Surveyor 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 1 1 1 1 1 1 1 1
16 Foreman 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
17 Charge Hand 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
18 Carpenter 8 8 8 10 18 18 20 20 25 25 25 30 35 35 40 25 25 25 25 25 25 25 25 25 25 25 25 20 20
19 Steel Fixer 5 7 7 12 12 15 15 18 18 20 20 20 25 35 35 25 18 18 18 18 18 18 18 18 18 14 10 10 10
20 Mason 3 5 8 8 20 20 20 20 25 25 25 25 30 30 30 30 25 25 25 25 25 25 25 25 25 20 20 20 15
21 Helpers 25 25 40 40 50 50 50 50 50 50 60 60 60 60 60 60 70 70 70 70 70 70 70 70 70 70 60 50 45
22 Scaffolder 4 6 6 6 7 7 7 10 10 10 10 10 10 12 12 12 12 12 12 10 10 10 10 10 10 9 9 9 9
23 Electricians 3 3 3 3 3 3 5 5 5 5 5 7 7 7 7 7 7 8 8 7 7 7 6 6 6 4 4 4 4
24 finishing Carpenter 5 8 8 8 10 10 10 10 12 12 12 12 12 12 14 12 11 11 11 11 11 11 11 11 11 11 11 8 8
25 PRO 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
26 Drivers 5 8 8 10 10 10 15 15 15 18 18 18 18 18 18 18 18 18 18 18 18 15 15 15 15 15 10 10 10
27 Mechanics 3 3 3 5 5 5 5 7 7 7 7 7 7 8 8 8 8 8 8 8 8 8 8 5 5 5 5 4 4
TOTAL 82 94 113 125 162 165 174 182 194 199 209 216 231 244 251 224 221 222 222 219 219 214 213 210 210 198 179 160 150
Manpower Histogram
100
150
200
250
300
50
0
Sep
82
Oct
94
Nov
113
Dec
125
Jan
162
Feb
165
Mar
174
Apr
182
May
194
Jun
199
Jul
209
Aug
216
Sep
231
Oct
244
Nov
251
Dec
224
Jan
221
Feb
222
Mar
222
Apr
219
May
219
Jun
MANPOWER HISTOGRAM
214
Jul
213
Aug
210
Sep
210
Oct
(Salalah Methanol Project)
198
Nov
Construction Execution Plan
179
Dec
160
Jan
150
Construction Execution Plan
(Salalah Methanol Project)
Construction Plant & Equipment Mobilization Plan
We, National Construction & Trading LLC hereby confirm to comply strictly
with GS E&C’s Safety and Security regulations and HSE Management system
to execute the work successfully. In order to do so ;
1. We will submit a HSE Management System Plan to GS E&C for the approval
within 1 month after the Contract
2. We will dispose Workers with PPE and Safety Training Courses & Job
orientation
3. We will execute Morning Exercise, Tool Box meeting, Safety Slogan every
morning
4. We will make Safety Petrol at a appropriated interval
5. We will put a signboard to show the Safety keeping status
6. We will inspect the Rigging Tools periodically for the Safety purpose to prevent
any Accident
7. We will keep our Camp clean always
8. We will execute Emergency Shunting Training
9. We will make periodic training for the fire and safe driving
10. We will give awards to the ones deserve for the Safety, at the same time, give
warnings for the ones who violate the Rules
Construction Execution Plan
(Salalah Methanol Project)
10
Utility (Water, Power) Sourcing Plan
The Contractor shall maintain and update a material planning and tracking
sheet and submit it to GS E & C on a monthly basis along with the progress
reports.
The MTS format shall be agreed with GS E & C. The MTS shall provide a direct status of
material procurement with respect to planned and actual dates of execution of activities.
The Contractor shall carryout expediting on all purchase orders placed for the Contract. The
expediting shall either be from the Contractor Home Office at Muscat or at source of manufacturing.
The expediting from home-office shall be through telephonic / facsimile messages. The expediting
status of items shall be reported in the Monthly Progress Reports to the GS E & C.
Construction Execution Plan
(Salalah Methanol Project)
Raw Material (Including Finishing) Supply & Sourcing Plan (Contd…)
The reporting shall also include details of any slippage. The Contractors Inspection, Expediting &
Vendor Data Control Procedure shall be implemented to provide effective control on expediting and
reporting.
The materials shall be inspected upon receipt. The material control documentation at the Contractor’s
Central Stores shall include:
1. Preparation of Stores Receipt Voucher (SRV)
2. Preparation of Site Issue Voucher (SIV)
3. Accounting Documentation.
The materials shall be transported to Site suitably. The material handling instructions shall be complied
with to avoid damage during loading and unloading. The material for construction shall be issued from
the Site Stores. The Store Keeper shall be responsible for management of materials as per Site Stores
procedure.
On completion of project, the surplus materials, if any, shall be returned to the Central Stores vide STN
(Stores Transfer Note) as per Contractors applicable procedure.
Construction Execution Plan
(Salalah Methanol Project)
12 Work Permit plan with registration of Salalah Free Zone Office
Construction Execution Plan
(Salalah Methanol Project)
To be issued later.
Construction Execution Plan
(Salalah Methanol Project)
14
Counter Measure Plan against EID holidays, RAMADAN period & Monsoon season, etc.
17
Labor Control Plan (1/2)
1. Transportation
A bus will be arranged to carry workers from / to site.
17
Labor Control Plan (2/2)
3. We will reward workers for good ideas and for safe workers at the end of the
month to keep workers encouraged.
21
Scaffolding Plan
Scaffolds are used in construction area as temporary work laces to provide support for workmen,
plant and materials used in buildings, construction, maintenance, repair and demolition work, etc.
SCAFFOLDING HAZARD
The accidents to workers that are due to fails from a height or to scaffold collapses show clearly
the importance of properly constructed and maintained ladders and scaffolds. Apar from
collapses the principal hazards are;
Unsecured ladders slipping
Use of unsuitable or faulty materials
Inadequately supported scaffold boards
Inadequate or irregular platform widths
Omission of guard rails or toe beads
Failure to secure scaffold to the building or to brace it adequately
Overloading the platforms and scaffold, etc.
1.1.1.1.1.1.1.1.3
Construction Execution Plan
(Salalah Methanol Project)
Sole plates at least 9”X1 1/2”(230mmX 40mm) cross section are required to spread the load on
earth, made up ground, asphalted surface etc. Sole plates shall extend under at least two
standards and joints shall be positioned so that they fall within one half to one third of the distance
between any two adjacent standards. At the end standard the sole plate shall project a similar
distanced.
Small timber pads may be used on solid bearing, such as concrete where there is no risk of the
standard and base plate sinking or becoming displaced. Any other make shift arrangement e.g.
barrels, boxes, loose bricks of concrete blocks shall not be used as a substitute for sole plate for
construction of scaffold.
Where materials are to be stacked on a working platform or working place above the height of the
toe boards, suitable barriers shall be positioned so as to prevent the fall of such material from the
platform or place.
Access to a working platform is best achieved by providing a separate ladder tower or cantilevered
access platform so as not to obstruct the platform and to minimize the possibility of persons falling
through the gap in the guardrail or decking.
Construction Execution Plan
(Salalah Methanol Project)
Scaffolding shall be erected, altered and dismantled by experienced workmen working under
the direction of a competent supervisor.
Scaffolding materials and other objects shall not be dropped, thrown tipped or shot from
heights.
All scaffolding shall be inspected after completion of erection and then at least every seven
days and after weather likely to have affected stability.
Workers shall not work on scaffolds during storms or high winds.
ERECTION
The procedure for erection should be such that an unstable condition is not reached at any
time. This recommendation is as important in low scaffolds as in taller ones. The ties for the
scaffold are to be erected and should reach each tie position.
No portion of the scaffold should be utilized unless that portion is fully decked, braced and
tied. Warning notices shall be fixed to draw attention to those arts of a scaffold, which are
incomplete and should not be used.
Construction Execution Plan
(Salalah Methanol Project)
DISMANTLING
During dismantling, no component, which endangers the stability of the remaining structure,
shall be removed.
If dismantling has reached the stage at which a critical member has to be removed, e.g. a tie
or a brace, the stability of the structure shall be assured by fixing a similar of otherwise
adequate member in place lower down before the member to be taken out is removed.
Because of the changes, which are made in a scaffold structure during its working life, it is not
safe to assume that dismantling can be carried out in the reverse order to the erection. The
scaffold, especially its tying and bracing, should be inspected prior to dismantling.
If the scaffold is defective, it should be made good before dismantling commences.
The procedure of dismantling shall be orderly and planned and should proceed generally from
the top in horizontal sections.
Scaffolds shall not be dismantled in vertical sections from one end towards the other,
especially in cases where a hoist tower, which apparently gives support to the scaffold, is to
be left standing, unless special consideration is given to ties and bracing.
Construction Execution Plan
(Salalah Methanol Project)
Steel Erection Plan will be submitted after receiving the detail drawings
and after discussion with the Subcontractor.
Construction Execution Plan
(Salalah Methanol Project)
23
Early Activity Execution Plan
1. Temporary Facility
- Temporary Facilities wiil be completed by 15.11.2007
3. Other Substation
- Other Substations will be completed by 11.09.2008