PROJECT
INFRASTRUCTURE
DEVELOPMENT
The HBJ pipeline carries most of the
India’s liquid natural gas.
Hazira in Gujarat, north of Mumbai
would have been the end terminal of
the HBJ pipeline.
But in 1997, Enron international
announced plans to link Dabhol
because of its existing power
generation facilities.
Moreover, Enron said they will add
about 1500 miles to the HBJ pipeline,
whose development costs $300 - $900
million.
FEASIBILITY STUDY
(Generation of
Need for a large power plant in Maharashtra
ideas)
(Initial
India invites Enron Corp. to explore possibilities
screening)
Feasibility analysis
(Enron ready to add 1500 miles pipeline )
Market analysis Technical analysis
(shareholders available)
Financial analysis
- Enron international
50%
- MSEB
30%
- Bechtel
10%
10% - GE
TIMELINE OF THE PROJECT
(G.O.M, Enron, Bechtel, GE (PPA signed- power purchase
sign MOU) agreement)
1992 1993
(renegotiation; construction
of phase 1 resumes)
(MSEB begins to
default)
2000
(phase 1 becomes operational) 1996
1999
DETAILS OF THE POWER PLANT
PHASE 1 PHASE 2
Capacity – 740 MW Capacity-
1,275 MW
Cost – $ 1.078 billion Cost- $ 3.5
billion
Fuel – Naphtha Fuel- LNG
Operations began- 1999 Construction
suspended