PROJECT MANAGEMENT
COMPANY BACKGROUND
Vision Mission Corporate Information Corporate Structure Organization Structure Logo company Shareholders Financial Source
Credit Facilities From Main Supplier List of Previous Project List of Current Projects
INTRODUCTION
Establish and incorporated on the 28th February 1997. Provide services in the field of building construction and civil works, particularly on roads, drainage and many more. ENVIRO is symbolize of environment and conscious the type of green building. BUILDERS is symbolize to the person which is build a building with commitment
VISION
MISSION
We promote an environment of competitiveness amongst our employee for their sense of leadership and team working. We are committed to provide high standard services and products that are fit for purpose.
To practice the implementation of precise outcome of physical and financial scheduled to be prominent among other constructions.
Focused on hiring and retaining employees with high experiences, skills and competencies to maintain a dynamic corporate culture.
ORGANISATION STRUCTURE
Managing Director Ar. Azizan Hijazi Bin Tan Sri Lukman
Manager Nur Hasrieza Binti Tan Sri Hassim Manager Herrye Bin Tan Sri Jonney Manager Manager Muhammad Faiz Bin Dato Osman
Site Engineer Document Controller Patricia Christ HR Assistant Ghaffar Bin Ghazali
Site Engineer Munirah Hayati Binti Ali Site Supervisor Helmy Bin Saad Assistant Quantity Surveying Quantity Serveying Munirah Binti Mahadi
LOGO COMPANY
GREEN COLOUR Our Company is committed to integrating environmental initiatives seamlessly into our project activities. We plan Design the best creation of construction works. We execute To give the best effort in completing the project was given in accordance with the criteria were determined You celebrate Our client will be satisfied with the results we have given either in quality or quantity. They celebrate it, we grateful with it.
CORPORATE INFORMATION
ENVIRO BUILDERS SDN BHD (678910-K) Provision of Building Construction (B04) and Civil
CORPORATE STRUCTURE
Managing Director
Ar. Azizan Hijazi Bin Tan Sri Lukman
Director of Contract
Sr. Norszazlina Binti Dato' Ali Abas
Director of Project
Ir. Herrye Bin Tan Sri Jonney
Director of Administration
Nur Hasrieza Binti Tan Sri Hassim
Director of Financal
Muhammad Faiz Bin Dato' Osman
SHAREHOLDERS
40% Managing Director
100% Shareholders
FINANCIAL SOURCES
Financial Institution (RM 8,000, 000.00) Maybank (RM 5,000,000.00) CIMB (RM 3,000,000.00)
Shareholders (RM 5,000, 000.00) Managing Director (RM 2,000, 000.00) Director of Project (RM 750, 000.00) Director of Contract (RM 750, 000.00) Director of Administration (RM 750, 000.00) Director of Finance (RM 750, 000.00)
Name of Supplier
Hailek Concrete Sdn Bhd Hsin Ngie Hardware Sdn Bhd
Type of Material
Ready Mixed Concrete Concrete
Payback Period
60 days 60 days
03. 04.
Concrete Plywood
1,500.000.00 150.000.00
60 days 60 days
05.
Sanitary Fittings
150.000.00
60 days
06.
Steel Bars
200,000.00
60 days
Sdn Bhd,
Name of Supplier
Kian Chiong Hardware Sdn Bhd
Type of Material
Mild Steel Bar
Payback Period
60 days
08. 09.
NSC Production Sdn Bhd. Lot Bricks CMS Sdn. Bhd Cement 150,000.00 60 days 150,000.00 60 days
10.
Paints Sand
200,000.00
60 days
11.
Stone
12. Ceramica Indah Sdn Bhd Tiles
200,000.00
60 days
150,000.00
60 days
1.
2011
1,230,000.00
2.
Cadangan Projek Pembinaan, Penaiktarafan dan Pembaikpulihan Sekolah-Sekolah dan Asrama di Negeri Sarawak Bagi Sk Sepiring Cadangan Perpustakaan Desa di Taman Harmoni, Sri Aman
2010
4,486,967.60
3.
2009
136,740.00.00
4.
Cadangan Membina dan Menyiapkan Sebuah Masjid, Jalan Ajibah Abol, 93400
2004
1,440,000.00
Kuching, Sarawak.
Sarawak
5.
Kerja-kerja Membina Dan Menyiapkan Rumah Rehat / Wakaf Jalan Ban Hock, P O Box 547 93700 Kuching Sarawak.
2003
791,322.92
6.
Kerja-kerja Membaikpulih Bangunan JKR 5535( 20 Bay) JKR Sarawak, Ibu Pejabat, Wisma Seberkas, Jln Tun Haji Abang Openg, 93582, Kuching Sarawak, Malaysia
2002
189,500.00
No.
Project Name
Proposed 10 units of 3 storey shophouses
Completion
Client
on Lots 924 & 927 Block 68 Mukah Land District (Phase 3), Mukah
2012
1,532,000.00
TENDER
BUILD UP RATE
QUOTATION
TENDERING
CADANGAN MEMBINA DAN MENYIAPKAN SEBUAH DEWAN SERBAGUNA UNTUK KEGUNAAN MASYARAKAT KOTA SAMARAHAN, SARAWAK
TENDER SUMMARY
TENDER PRICE
RM 3,715 705.66
DURATION
50 Weeks/300 Days
TENDER SUMMARY
BUILD UP RATE
BUILD UP RATE
Concreting Works Reinforcement Bar Works Mild/High Form works Insurance Plastering works
Brick works
Roof Finishes
PRICE COMPARISONS
PRICE TENDERING
SEND FAX/EMAIL
TENDER PRICING
PRICE EVALUATION
ACCEPTANCE OF PRICE
Feedback from the supplier
Make a deal with the supplier that the company is accept the price that is given
PROJECT PLANNING
METHOD STATEMENT
MATERIAL SCHEDULE
INSURANCE
S-CURVE
CPM
SITE LAYOUT
MACHINERIES SCHEDULE
INSURANCE
1 2 3 PERFORMANCE BOND CONTRACTOR ALL RISK
PERFORMANCE BOND
RM 185,785.28
= RM 185,785.66
=RM 10,003.02
=RM120,761.50
=RM8,984.96
SITE LAYOUT
CADANGAN MEMBINA DAN MANYIAPKAN SEBUAH DEWAN SERBAGUNA UNTUK KEGUNAAN MASYARAKAT KOTA SAMARAHAN, SARAWAK.
WORK PROGRAMME
FINANCIAL S-CURVE
CPM
PHYSICAL S-CURVE
FINANCIAL S-CURVE
EB-CADANGAN MEMBINA DAN MENYIAPKAN SEBUAH DEWAN SERBAGUNA UNTUK KEGUNAAN MASYARAKAT KOTA SAMARAHAN,SARAWAK_REV.2 RM4,000,000.00
RM3,500,000.00 RM3,000,000.00 RM2,500,000.00 Cost RM2,000,000.00 RM1,500,000.00 RM1,000,000.00 RM500,000.00 RM0.00
Months
PHYSICAL S-CURVE
EB-CADANGAN MEMBINA DAN MENYIAPKAN SEBUAH DEWAN SERBAGUNA UNTUK KEGUNAAN MASYARAKAT KOTA 20,000.00h SAMARAHAN,SARAWAK_REV.2
18,000.00h 16,000.00h 14,000.00h 12,000.00h Work 10,000.00h 8,000.00h 6,000.00h 4,000.00h 2,000.00h 0.00h
Months
WEEKLY SCHEDULE
LABOUR
METHOD STATEMENT
SUMMARY
NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 PRELIMINERIES PILING WORKS WORK BELOW LOWEST FLOOR FINISHES FRAME UPPER FLOORS ROOF EXTERNAL WALLS INTERNAL WALL AND PARTITIONS STAIRCASE DOORS WINDOW FLOOR FINISHES WALL FINISHES CEILING FINISHES SANITARY FITTINGS GAMES COURT GRAND TOTAL ELEMENT TOTAL DAYS 33 days 88 days 17 days 7 days 7 days 54 days 11 days 10 days 19 days 7 days 8 days 8 days 11 days 9 days 4 days 7 days 300 DAYS
Method Statement
RESOURCES ALLOCATION
No. 01. Name of Supplier Hailek Concrete Sdn Bhd Type of Material Ready Mixed Concrete Address No. 188, Jln Chong Jin Chong,93250 Kuching, Sarawak 157H, Jalan Satok, 93400 Concrete Kuching, P.O Box 756, 93716 Kuching, Sarawak Lot 957, Block 224,
Concrete
Tel & Fax No. Tel : 082-6 87 910 Fax : 082-687 911 Tel : 082-256329/ 082-415106 Fax : 082-426632 Tel : 082-683000 Fax : 082-683866
02.
03.
Sdn. Bhd
RESOURCES ALLOCATION
No. Name of Supplier Type of Material Address RH Plaza, 1st Floor, Lot 5400, 04. Sarawak Plywood (M) Sdn Bhd
Plywood
Tel & Fax No. Tel : 082-451 789 Fax : 082-461 300
Tel : 082-348557
Syarikat Perniagaan
06.
Perindustrian King
Hong Sdn Bhd,
Steel Bar
RESOURCES ALLOCATION
No. Name of Supplier Kian Chiong 07. Hardware Sdn Bhd NSC Production Sdn 08. Bhd. Lot Bricks Type of Material Address Lot 22A, No. 1B, Angching Mild Steel Bar Lorong, Kuching. Lot 1315, Jalan Muara Tuang, 93700, Kota Samarahan, Sarawak. 09. Kim Poh bricks Works, Bricks No. 871 Jln kuching-serian, Batu 24, 94200 Siburan Sarawak. Lot 5895, Pending Industrial 10. CMS Sdn. Bhd Cement Estate, Jalan Kilang Simen, P O Box 2000, Kuching 93740, Sarawak Tel : 082-332111 Fax : 082-334537 Tel : 082-868626 Tel & Fax No. Tel: 082-248394 Fax: 082- 429246 Tel: 082-628990 Fax:082-628899
RESOURCES ALLOCATION
No. Name of Supplier Jee Foh Multi Supply 11. Co No. 39 Gambir Road, 93000 Kuching Asabin Trading Sdn 12. Bhd, No. 871 Jln kuching-serian,
Paints
Type of Material
Paint
Tel : 082-573842
Fax: 082-573842
RESOURCES ALLOCATION
No. 14. Name of Supplier Han Cheng Enterprise Type of Material Sand Stone Address
No. 2503, Jalan Stapok Utama, Kuching 93250, Sarawak.
Tel & Fax No. Tel : 016-8882033 Fax : 082- 681709 Tel: 082-451567 Fax: 082-452135
4 1/2 Mile Kong Ping Road Off Penrissen Road Kuching, Sarawak 93250 Malaysia
CADANGAN MEMBINA DAN MENYIAPKAN SEBUAH DEWAN SERBAGUNA UNTUK KEGUNAAN MASYARAKAT KOTA SAMARAHAN, SARAWAK.
ERP
SAFETY SIGNBOARDS
PPE
HIRARC
Accident/ Incident
Fire Explosion
Layout Plan
SAFETY SIGNBOARDS
JOB ALLOCATI ON
WORK PERMITT
WORK ONGOING
PPE
TIME CONTROL
CPM WORK CARD
TIME CONTROL
CPM Arrange of the planning work more than properly WORK CARD/RECORD Record of the working days for each worker.
COST CONTROL
Material on site
o Supervise materials flow on site operations from delivery process to
Facilities on site
o Ensure facilities on site are maximally utilized
LABOUR CONTROL
Incentive given to the labour
o Allowance and sufficient overtime o Safety and welfare of labour
MATERIAL CONTROL
PURCHASE ORDER (P.O) PAYMENT SUMMARY PAYMENT
DELIVERY ORDER(D.O)
RECEIVE INVOICE
Ready to be used
Check condition
Transfer to site
QUALITY CONTROL
Material used according to specification
Inspection on material
Inspection of product
PROGRESS WORK
UPPER FLOOR SLAB Formwork is 100% completed. Rebar works is 100% completed. Concreting works is 100% completed.
UPPER FLOOR COLUMN Formwork is 100% completed. Rebar works is 100% completed. Concreting works is finish on time.
STAIRCASE Formwork is 100% completed. Rebar works is 100% completed. Concreting works is finish on time.
FINANCIAL S-CURVE
CADANGAN MEMBINA DAN MENYIAPKAN SEBUAH DEWAN SERBAGUNA UNTUK KEGUNAAN MASYARAKAT KOTA SAMARAHAN, SARAWAK. FINANCIAL S-CURVE
100%
90%
80% 70%
Percentages
60% 50% 40% 30% 20% 10% 0% May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14
Month
schedule ACTUAL
PHYSICAL S-CURVE
CADANGAN MEMBINA DAN MENYIAPKAN SEBUAH DEWAN SERBAGUNA UNTUK KEGUNAAN MASYARAKAT KOTA SAMARAHAN, SARAWAK. PHYSICAL S-CURVE
Percentages
60% 50%
40%
30% 20% 10% 0% May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14
Month
schedule ACTUAL
SubContractor Payment
Item
Certificates
Dated RM RM
7,530.97 2,452.99 1,074.18 7,220.79 6,963.79 8,181.63
RM
143,088.38 46,606.72 20,409.37 137,195.09 132,311.98 155,450.91
RM
143,088.38 189,695.10 210,104.47 347,299.56 479,611.54 635,062.45
1 2 3 4 5 6
Perakuan Bayaran Interim No. 1 Perakuan Bayaran Interim No. 2 Perakuan Bayaran Interim No. 3 Perakuan Bayaran Interim No. 4 Perakuan Bayaran Interim No. 5 Perakuan Bayaran Interim No. 6 TOTAL
RM668,486.79
RM33,424.34
RM635,062.45 RM2,004,861.49
1 2 3
25 days
CPM EOT
Conventional
BEAM
IBS
Conventional COLUMN
IBS
Conventional
SLAB
IBS
CONCLUSION
Enviro Builders confident to: 1) 2) Finish the project without degrading the quality of work. Deliver high quality of works in terms of planning, material used and workmanship. Provide the best facilities in the construction throughout our excellent design concept.
3)
Q & A SESSION